ML11291A094: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter:UNITED STATES
{{#Wiki_filter:UNITED STATES  
                          NUCLEAR REGULATORY COMMISSION
NUCLEAR REGULATORY COMMISSION  
                                              REGION III
REGION III  
                                2443 WARRENVILLE ROAD, SUITE 210
2443 WARRENVILLE ROAD, SUITE 210  
                                        LISLE, IL 60532-4352
LISLE, IL 60532-4352  
                                          October 17, 2011
Mr. Larry Meyer
Site Vice President
October 17, 2011  
NextEra Energy Point Beach, LLC
6610 Nuclear Road
Mr. Larry Meyer  
Two Rivers, WI 54241
Site Vice President  
SUBJECT:       POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2; COMPONENT DESIGN
NextEra Energy Point Beach, LLC  
                BASES INSPECTION (CDBI) REPORT 05000266/2011009; 05000301/2011009
6610 Nuclear Road  
Dear Mr. Meyer:
Two Rivers, WI 54241  
On September 2, 2011, the U.S. Nuclear Regulatory Commission (NRC) completed a
SUBJECT:  
Component Design Bases Inspection (CDBI) at your Point Beach Nuclear Plant. The enclosed
POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2; COMPONENT DESIGN  
report documents the results of this inspection, which were discussed on September 2, 2011,
BASES INSPECTION (CDBI) REPORT 05000266/2011009; 05000301/2011009  
with Mr. T. Vehec and other members of your staff.
Dear Mr. Meyer:  
The inspection examined activities conducted under your license as they relate to safety and
On September 2, 2011, the U.S. Nuclear Regulatory Commission (NRC) completed a  
compliance with the Commissions rules and regulations and with the conditions of your license.
Component Design Bases Inspection (CDBI) at your Point Beach Nuclear Plant. The enclosed  
The inspectors reviewed selected procedures and records, observed activities, and interviewed
report documents the results of this inspection, which were discussed on September 2, 2011,  
personnel.
with Mr. T. Vehec and other members of your staff.  
Based on the results of this inspection, four NRC-identified findings of very low safety
The inspection examined activities conducted under your license as they relate to safety and  
significance were identified. Three of the findings involved violations of NRC requirements.
compliance with the Commissions rules and regulations and with the conditions of your license.
However, because of their very low safety significance, and because the issues were entered
The inspectors reviewed selected procedures and records, observed activities, and interviewed  
into your corrective action program, the NRC is treating the issues as Non-Cited Violations
personnel.  
(NCVs) in accordance with Section 2.3.2 of the NRC Enforcement Policy.
Based on the results of this inspection, four NRC-identified findings of very low safety  
If you contest the subject or severity of this NCV, you should provide a response within 30 days
significance were identified. Three of the findings involved violations of NRC requirements.
of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear
However, because of their very low safety significance, and because the issues were entered  
Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001, with a
into your corrective action program, the NRC is treating the issues as Non-Cited Violations  
copy to the Regional Administrator, U.S. Nuclear Regulatory Commission - Region III,
(NCVs) in accordance with Section 2.3.2 of the NRC Enforcement Policy.  
2443 Warrenville Road, Suite 210, Lisle, IL 60532-4352; the Director, Office of Enforcement,
If you contest the subject or severity of this NCV, you should provide a response within 30 days  
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the Resident Inspector
of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear  
Office at the Point Beach Nuclear Plant. In addition, if you disagree with the cross-cutting
Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001, with a  
aspect assigned to any finding in this report, you should provide a response within 30 days of
copy to the Regional Administrator, U.S. Nuclear Regulatory Commission - Region III,  
the date of this inspection report, with the basis for your disagreement, to the Regional
2443 Warrenville Road, Suite 210, Lisle, IL 60532-4352; the Director, Office of Enforcement,  
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the Resident Inspector  
Office at the Point Beach Nuclear Plant. In addition, if you disagree with the cross-cutting  
aspect assigned to any finding in this report, you should provide a response within 30 days of  
the date of this inspection report, with the basis for your disagreement, to the Regional  
Administrator, Region III, and the NRC Resident Inspector at the Point Beach Nuclear Plant.
Administrator, Region III, and the NRC Resident Inspector at the Point Beach Nuclear Plant.


L. Meyer                                     -2-
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its
enclosure, and your response (if any) will be available electronically for public inspection in the
L. Meyer  
NRC Public Document Room or from the Publicly Available Records System (PARS)
component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Website
at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
                                            Sincerely,
                                            /RA/
-2-  
                                            Ann Marie Stone, Chief
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its  
                                            Engineering Branch 2
enclosure, and your response (if any) will be available electronically for public inspection in the  
                                            Division of Reactor Safety
NRC Public Document Room or from the Publicly Available Records System (PARS)  
Docket Nos.   50-266; 50-301
component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Website  
License No.   DPR-24; DPR-27
at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).  
Enclosure:     Inspection Report 05000266/2011009; 05000301/2011009
Sincerely,  
                w/Attachment: Supplemental Information
cc w/encl:     Distribution via ListServ
/RA/  
Ann Marie Stone, Chief  
Engineering Branch 2  
Division of Reactor Safety  
Docket Nos.  
50-266; 50-301  
License No.  
DPR-24; DPR-27  
Enclosure:  
Inspection Report 05000266/2011009; 05000301/2011009  
  w/Attachment: Supplemental Information  
cc w/encl:  
Distribution via ListServ  


          U.S. NUCLEAR REGULATORY COMMISSION
                          REGION III
Enclosure
Docket No:         05000266; 05000301
U.S. NUCLEAR REGULATORY COMMISSION  
License No:         DPR-24; DPR-27
REGION III  
Report No:         05000266/2011009; 05000301/2011009
Docket No:  
Licensee:           NextEra Energy Point Beach, LLC
05000266; 05000301  
Facility:           Point Beach Nuclear Plant, Units 1 and 2
License No:  
Location:           Two Rivers, WI
DPR-24; DPR-27  
Dates:             August 1 through September 2, 2011
Report No:  
Inspectors:         Alan Dahbur, Senior Engineering Inspector, Lead
05000266/2011009; 05000301/2011009  
                    Caroline Tilton, Senior Engineering Inspector, Mechanical
Licensee:  
                    Mohammad Munir, Engineering Inspector, Electrical
NextEra Energy Point Beach, LLC  
                    Carl Moore, Operations Inspector
Facility:  
                    John Bozga, Civil Structural Inspector
Point Beach Nuclear Plant, Units 1 and 2  
                    Jerry Nicely, Electrical Contractor
Location:  
                    Bill Sherbin, Mechanical Contractor
Two Rivers, WI  
Trainee:           Cimberly Nickell, Nuclear Safety Professional
Dates:  
                    Development Program, NRR
August 1 through September 2, 2011  
Approved by:       Ann Marie Stone, Chief
Inspectors:  
                    Engineering Branch 2
Alan Dahbur, Senior Engineering Inspector, Lead  
                    Division of Reactor Safety
                                                                    Enclosure
Caroline Tilton, Senior Engineering Inspector, Mechanical  
Mohammad Munir, Engineering Inspector, Electrical  
Carl Moore, Operations Inspector  
John Bozga, Civil Structural Inspector  
Jerry Nicely, Electrical Contractor  
Bill Sherbin, Mechanical Contractor  
Trainee:  
Cimberly Nickell, Nuclear Safety Professional  
Development Program, NRR
Approved by:  
Ann Marie Stone, Chief  
Engineering Branch 2  
Division of Reactor Safety


                                      SUMMARY OF FINDINGS
IR 05000266/2011009, 05000301/2011009; 8/01/2011 - 9/02/2011; Point Beach Nuclear Plant,
1
Units 1 and 2; Component Design Bases Inspection (CDBI).
Enclosure
The inspection was a 3-week onsite baseline inspection that focused on the design of
SUMMARY OF FINDINGS  
components. The inspection was conducted by regional engineering inspectors and two
IR 05000266/2011009, 05000301/2011009; 8/01/2011 - 9/02/2011; Point Beach Nuclear Plant,  
consultants. Four Green findings were identified by the inspectors. Three of the findings were
Units 1 and 2; Component Design Bases Inspection (CDBI).  
considered Non-Cited Violations (NCVs) of NRC regulations. The significance of most findings
The inspection was a 3-week onsite baseline inspection that focused on the design of  
is indicated by their color (Green, White, Yellow, Red) using Inspection Manual Chapter (IMC)
components. The inspection was conducted by regional engineering inspectors and two  
0609, Significance Determination Process (SDP). Findings for which the SDP does not apply
consultants. Four Green findings were identified by the inspectors. Three of the findings were  
may be (Green) or be assigned a severity level after NRC management review. The NRCs
considered Non-Cited Violations (NCVs) of NRC regulations. The significance of most findings  
program for overseeing the safe operation of commercial nuclear power reactors is described in
is indicated by their color (Green, White, Yellow, Red) using Inspection Manual Chapter (IMC)  
NUREG-1649, Reactor Oversight Process, Revision 4, dated December 2006.
0609, Significance Determination Process (SDP). Findings for which the SDP does not apply  
A.     NRC-Identified and Self-Revealed Findings
may be (Green) or be assigned a severity level after NRC management review. The NRCs  
        Cornerstone: Initiating Events
program for overseeing the safe operation of commercial nuclear power reactors is described in  
    * Green. The inspectors identified a finding of very low safety significance involving the
NUREG-1649, Reactor Oversight Process, Revision 4, dated December 2006.  
        licensees failure to meet the requirements of the American Institute of Steel
A.  
        Construction (AISC) Specification. Specifically, the licensees design basis calculation
NRC-Identified and Self-Revealed Findings  
        failed to ensure the turbine building structural steel floor beams met the AISC
Cornerstone: Initiating Events  
        specification. This finding was entered into the licensees corrective action program. No
*  
        violation of NRC requirements was identified.
Green. The inspectors identified a finding of very low safety significance involving the  
        The performance deficiency was determined to be more than minor because the finding
licensees failure to meet the requirements of the American Institute of Steel  
        was associated with the Initiating Events Cornerstone attribute of design control and
Construction (AISC) Specification. Specifically, the licensees design basis calculation  
        adversely affected the cornerstone objective to limit the likelihood of those events that
failed to ensure the turbine building structural steel floor beams met the AISC  
        upset the plants stability and challenged critical safety functions during shutdown, as
specification. This finding was entered into the licensees corrective action program. No  
        well as power operations. The finding screened as very low safety significance (Green),
violation of NRC requirements was identified.  
        because the transient initiator would not contribute to both the likelihood of a reactor trip
The performance deficiency was determined to be more than minor because the finding  
        and the likelihood that mitigation equipment or functions will not be available. This
was associated with the Initiating Events Cornerstone attribute of design control and  
        finding had a cross-cutting aspect in human performance and work practice because the
adversely affected the cornerstone objective to limit the likelihood of those events that  
        licensee did not ensure effective supervisory and management oversight of work
upset the plants stability and challenged critical safety functions during shutdown, as  
        activities, including contractors, such that nuclear safety was supported. Specifically, the
well as power operations. The finding screened as very low safety significance (Green),  
        licensee failed to have adequate oversight of design calculation and documentation for
because the transient initiator would not contribute to both the likelihood of a reactor trip  
        establishing structural adequacy of the turbine building structural steel beams at EL. 44-
and the likelihood that mitigation equipment or functions will not be available. This  
        0. [H.2(c)] (Section 4OA5.1.b.(2))
finding had a cross-cutting aspect in human performance and work practice because the  
        Cornerstone: Mitigating Systems
licensee did not ensure effective supervisory and management oversight of work  
    * Green. The inspectors identified a finding of very low safety significance (Green) and
activities, including contractors, such that nuclear safety was supported. Specifically, the  
        associated Non-Cited Violation of 10 CFR Part 50, Appendix B, Criterion III, Design
licensee failed to have adequate oversight of design calculation and documentation for  
        Control, involving the licensees failure to correctly translate design basis assumptions
establishing structural adequacy of the turbine building structural steel beams at EL. 44-
        into procedures or instructions. Specifically, the licensee failed to monitor average
0. [H.2(c)] (Section 4OA5.1.b.(2))  
        outside air temperature which was one of the design input criteria for the temperature
Cornerstone: Mitigating Systems  
        heat-up calculation associated with rooms which housed safety-related equipment. This
*  
        finding was entered into the licensees corrective action program.
Green. The inspectors identified a finding of very low safety significance (Green) and  
                                              1                                            Enclosure
associated Non-Cited Violation of 10 CFR Part 50, Appendix B, Criterion III, Design  
Control, involving the licensees failure to correctly translate design basis assumptions  
into procedures or instructions. Specifically, the licensee failed to monitor average  
outside air temperature which was one of the design input criteria for the temperature  
heat-up calculation associated with rooms which housed safety-related equipment. This  
finding was entered into the licensees corrective action program.  


  The performance deficiency was associated with Mitigating System Cornerstone and
  determined to be more than minor because, if left uncorrected, it could lead to a more
2
  significant safety concern. The finding screened as very low safety significance (Green)
Enclosure
  because the finding was not a design or qualification deficiency, did not represent a loss
The performance deficiency was associated with Mitigating System Cornerstone and  
  of system safety function, and did not screen as potentially risk significant due to a
determined to be more than minor because, if left uncorrected, it could lead to a more  
  seismic, flooding, or severe weather initiating event. The finding had a cross-cutting
significant safety concern. The finding screened as very low safety significance (Green)  
  aspect in the area of human performance, resources because the licensee did not
because the finding was not a design or qualification deficiency, did not represent a loss  
  ensure adequate training and qualification of personnel. Specifically, the licensee failed
of system safety function, and did not screen as potentially risk significant due to a  
  to adequately train licensed operators to ensure adequate knowledge with respect to the
seismic, flooding, or severe weather initiating event. The finding had a cross-cutting  
  interface between functionality of a non-safety system component and the impact of a
aspect in the area of human performance, resources because the licensee did not  
  failure on the operability of safety-related equipment. [H.2(b)]. (Section 1R21.3.b.(1))
ensure adequate training and qualification of personnel. Specifically, the licensee failed  
* Green. The inspectors identified a finding of very low safety significance (Green) and
to adequately train licensed operators to ensure adequate knowledge with respect to the  
  associated Non-Cited Violation of 10 CFR Part 50, Appendix B, Criterion III, Design
interface between functionality of a non-safety system component and the impact of a  
  Control, for the failure to ensure a minimum AFW flow of 275 gpm as specified in the
failure on the operability of safety-related equipment. [H.2(b)]. (Section 1R21.3.b.(1))  
  accident analysis for the Loss of Normal Feedwater event. This finding was entered into
*  
  the licensees corrective action program.
Green. The inspectors identified a finding of very low safety significance (Green) and  
  The performance deficiency was associated with the Mitigating Systems Cornerstone
associated Non-Cited Violation of 10 CFR Part 50, Appendix B, Criterion III, Design  
  attribute of design control and was determined to be more than minor because, if left
Control, for the failure to ensure a minimum AFW flow of 275 gpm as specified in the  
  uncorrected, it would have the potential to lead to a more significant safety concern.
accident analysis for the Loss of Normal Feedwater event. This finding was entered into  
  Specifically, an AFW flow rate of less than 275 gpm as specified in the procedures did
the licensees corrective action program.  
  not ensure the pressurizer would not become water solid and cause an over-pressure
The performance deficiency was associated with the Mitigating Systems Cornerstone  
  condition within the Reactor Coolant System during the Loss of Normal Feedwater. The
attribute of design control and was determined to be more than minor because, if left  
  finding screened as of very low safety significance (Green) because the finding was not
uncorrected, it would have the potential to lead to a more significant safety concern.
  a design or qualification deficiency, did not represent a loss of system safety function,
Specifically, an AFW flow rate of less than 275 gpm as specified in the procedures did  
  and did not screen as potentially risk-significant due to a seismic, flooding, or severe
not ensure the pressurizer would not become water solid and cause an over-pressure  
  weather initiating event. This finding had a cross-cutting aspect in the area of human
condition within the Reactor Coolant System during the Loss of Normal Feedwater. The  
  performance, resources because the licensee did not maintain design documentation in
finding screened as of very low safety significance (Green) because the finding was not  
  a complete and accurate manner. Specifically, the licensee failed to maintain
a design or qualification deficiency, did not represent a loss of system safety function,  
  Emergency Procedures consistent with the design basis analysis for LONF. [H.2(c)].
and did not screen as potentially risk-significant due to a seismic, flooding, or severe  
  (Section 1R21.6.b.(1))
weather initiating event. This finding had a cross-cutting aspect in the area of human  
  Cornerstone: Barrier Integrity
performance, resources because the licensee did not maintain design documentation in  
* Green. The inspectors identified a finding of very low safety significance (Green) and
a complete and accurate manner. Specifically, the licensee failed to maintain  
  associated Non-Cited Violation of 10 CFR Part 50, Appendix B, Criterion III, Design
Emergency Procedures consistent with the design basis analysis for LONF. [H.2(c)].  
  Control, involving the licensees failure to ensure the Containment Spray Pipe Support
(Section 1R21.6.b.(1))  
  2S-249 and Containment Spray Pipe Anchor 2A-35 meet Seismic Category I
Cornerstone: Barrier Integrity  
  requirements. This finding was entered into the licensees corrective action program.
*  
  The performance deficiency was determined to be more than minor because it was
Green. The inspectors identified a finding of very low safety significance (Green) and  
  associated with the Barrier Integrity Cornerstone attribute of design control and
associated Non-Cited Violation of 10 CFR Part 50, Appendix B, Criterion III, Design  
  adversely affected the cornerstone objective to provide reasonable assurance that
Control, involving the licensees failure to ensure the Containment Spray Pipe Support  
  physical design barriers (fuel cladding, reactor coolant system, and containment) protect
2S-249 and Containment Spray Pipe Anchor 2A-35 meet Seismic Category I  
  the public from radionuclide releases caused by accidents or events. This finding is of
requirements. This finding was entered into the licensees corrective action program.  
  very low safety significance (Green) because there was no actual barrier degradation.
The performance deficiency was determined to be more than minor because it was  
  The inspectors did not identify a cross-cutting aspect associated with this finding
associated with the Barrier Integrity Cornerstone attribute of design control and  
  because this was a legacy design issue; and therefore, was not reflective of current
adversely affected the cornerstone objective to provide reasonable assurance that  
  performance. [P.1(a)]. (Section 4OA5.1.b.(1))
physical design barriers (fuel cladding, reactor coolant system, and containment) protect  
                                        2                                          Enclosure
the public from radionuclide releases caused by accidents or events. This finding is of  
very low safety significance (Green) because there was no actual barrier degradation.
The inspectors did not identify a cross-cutting aspect associated with this finding  
because this was a legacy design issue; and therefore, was not reflective of current  
performance. [P.1(a)]. (Section 4OA5.1.b.(1))  


B. Licensee-Identified Violations
  Violations of very low safety significance that were identified by the licensee have been
3
  reviewed by inspectors. Corrective actions planned or taken by the licensee have been
Enclosure
  entered into the licensees corrective action program. These violations and corrective
B.  
  action tracking numbers are listed in Section 4OA7 of this report.
Licensee-Identified Violations  
                                        3                                          Enclosure
Violations of very low safety significance that were identified by the licensee have been  
reviewed by inspectors. Corrective actions planned or taken by the licensee have been  
entered into the licensees corrective action program. These violations and corrective  
action tracking numbers are listed in Section 4OA7 of this report.  


                                      REPORT DETAILS
1.   REACTOR SAFETY
4
    Cornerstone: Initiating Events, Mitigating Systems, and Barrier Integrity
Enclosure
1R21 Component Design Bases Inspection (71111.21)
REPORT DETAILS  
.1  Introduction
1.  
    The objective of the component design bases inspection is to verify the design bases
REACTOR SAFETY  
    have been correctly implemented for the selected risk significant components and that
Cornerstone: Initiating Events, Mitigating Systems, and Barrier Integrity  
    operating procedures and operator actions are consistent with design and licensing
1R21 Component Design Bases Inspection (71111.21)  
    bases. As plants age, their design bases may be difficult to determine and an
.1  
    important design feature may be altered or disabled during a modification. The
Introduction  
    Probabilistic Risk-Assessment (PRA) model assumes the capability of safety systems
The objective of the component design bases inspection is to verify the design bases  
    and components to perform their intended safety function successfully. This inspectable
have been correctly implemented for the selected risk significant components and that  
    area verifies aspects of the Initiating Events, Mitigating Systems, and Barrier Integrity
operating procedures and operator actions are consistent with design and licensing  
    cornerstones for which there are no indicators to measure performance.
bases. As plants age, their design bases may be difficult to determine and an  
    Specific documents reviewed during the inspection are listed in the Attachment to the
important design feature may be altered or disabled during a modification. The  
    report.
Probabilistic Risk-Assessment (PRA) model assumes the capability of safety systems  
.2 Inspection Sample Selection Process
and components to perform their intended safety function successfully. This inspectable  
    Point Beach Nuclear Plant implemented major modifications to the existing Auxiliary
area verifies aspects of the Initiating Events, Mitigating Systems, and Barrier Integrity  
    Feedwater System in support of the extended power uprate and to resolve other system
cornerstones for which there are no indicators to measure performance.  
    low margin issues. The modification included the addition of two higher capacity motor
Specific documents reviewed during the inspection are listed in the Attachment to the  
    driven pumps and their associated valves and piping. The inspectors used information
report.  
    contained in the licensees PRA, the Point Beachs Standardized Plant Analysis Risk
.2  
    Model as the basis for component selection from the AFW System. Using the system
Inspection Sample Selection Process  
    approach as specified in the inspection procedures, a number of risk significant
Point Beach Nuclear Plant implemented major modifications to the existing Auxiliary  
    components were selected for the inspection including components used to support the
Feedwater System in support of the extended power uprate and to resolve other system  
    AFW system.
low margin issues. The modification included the addition of two higher capacity motor  
    The inspectors also used additional component information such as a margin
driven pumps and their associated valves and piping. The inspectors used information  
    assessment in the selection process. This design margin assessment considered
contained in the licensees PRA, the Point Beachs Standardized Plant Analysis Risk  
    original design reductions caused by design modification, power uprates, or reductions
Model as the basis for component selection from the AFW System. Using the system  
    due to degraded material condition. Equipment reliability issues were also considered in
approach as specified in the inspection procedures, a number of risk significant  
    the selection of components for detailed review. These included items such as
components were selected for the inspection including components used to support the  
    performance test results, significant corrective actions, repeated maintenance activities,
AFW system.
    Maintenance Rule (a)(1) status, components requiring an operability evaluation, NRC
The inspectors also used additional component information such as a margin  
    resident inspector input of problem areas/equipment, and system health reports.
assessment in the selection process. This design margin assessment considered  
    Consideration was also given to the uniqueness and complexity of the design, operating
original design reductions caused by design modification, power uprates, or reductions  
    experience, and the available defense in depth margins. A summary of the reviews
due to degraded material condition. Equipment reliability issues were also considered in  
    performed and the specific inspection findings identified are included in the following
the selection of components for detailed review. These included items such as  
    sections of the report.
performance test results, significant corrective actions, repeated maintenance activities,  
                                            4                                          Enclosure
Maintenance Rule (a)(1) status, components requiring an operability evaluation, NRC  
resident inspector input of problem areas/equipment, and system health reports.
Consideration was also given to the uniqueness and complexity of the design, operating  
experience, and the available defense in depth margins. A summary of the reviews  
performed and the specific inspection findings identified are included in the following  
sections of the report.  


    The inspectors also identified procedures and modifications for review that were
    associated with the selected components. In addition, the inspectors selected operating
5
    experience issues associated with the selected components.
Enclosure
    This inspection constituted 22 samples as defined in IP 71111.21-05.
The inspectors also identified procedures and modifications for review that were  
.3   Component Design
associated with the selected components. In addition, the inspectors selected operating  
  a. Inspection Scope
experience issues associated with the selected components.
    The inspectors reviewed the Updated Final Safety Analysis Report (UFSAR), Technical
This inspection constituted 22 samples as defined in IP 71111.21-05.  
    Specifications (TS), design basis documents, drawings, calculations and other available
.3  
    design basis information, to determine the performance requirements of the selected
Component Design  
    components. The inspectors used applicable industry standards, such as the American
a.  
    Society of Mechanical Engineers (ASME) Code, Institute of Electrical and Electronics
Inspection Scope  
    Engineers Standards and the National Electric Code, to evaluate acceptability of the
The inspectors reviewed the Updated Final Safety Analysis Report (UFSAR), Technical  
    systems design. The NRC also evaluated licensee actions, if any, taken in response to
Specifications (TS), design basis documents, drawings, calculations and other available  
    NRC issued operating experience, such as Bulletins, Generic Letters (GLs), Regulatory
design basis information, to determine the performance requirements of the selected  
    Issue Summaries (RISs), and Information Notices (INs). The review was to verify the
components. The inspectors used applicable industry standards, such as the American  
    selected components would function as designed when required and support proper
Society of Mechanical Engineers (ASME) Code, Institute of Electrical and Electronics  
    operation of the associated systems. The attributes that were needed for a component
Engineers Standards and the National Electric Code, to evaluate acceptability of the  
    to perform its required function included process medium, energy sources, control
systems design. The NRC also evaluated licensee actions, if any, taken in response to  
    systems, operator actions, and heat removal. The attributes to verify the component
NRC issued operating experience, such as Bulletins, Generic Letters (GLs), Regulatory  
    condition and tested capability was consistent with the design bases and was
Issue Summaries (RISs), and Information Notices (INs). The review was to verify the  
    appropriate may include installed configuration, system operation, detailed design,
selected components would function as designed when required and support proper  
    system testing, equipment and environmental qualification, equipment protection,
operation of the associated systems. The attributes that were needed for a component  
    component inputs and outputs, operating experience, and component degradation.
to perform its required function included process medium, energy sources, control  
    For each of the components selected, the inspectors reviewed the maintenance history,
systems, operator actions, and heat removal. The attributes to verify the component  
    preventive maintenance activities, system health reports, operating experience-related
condition and tested capability was consistent with the design bases and was  
    information, vendor manuals, electrical and mechanical drawings, and licensee
appropriate may include installed configuration, system operation, detailed design,  
    corrective action program documents. Field walkdowns were conducted for all
system testing, equipment and environmental qualification, equipment protection,  
    accessible components to assess material condition and to verify the as-built condition
component inputs and outputs, operating experience, and component degradation.  
    was consistent with the design. Other attributes reviewed are included as part of the
For each of the components selected, the inspectors reviewed the maintenance history,  
    scope for each individual component.
preventive maintenance activities, system health reports, operating experience-related  
    The following 18 components were reviewed:
information, vendor manuals, electrical and mechanical drawings, and licensee  
    *       4.16 kV Switchgear Bus (2A06): The inspectors reviewed electrical distribution
corrective action program documents. Field walkdowns were conducted for all  
            system load flow/voltage drop, degraded voltage protection, short-circuit, and
accessible components to assess material condition and to verify the as-built condition  
            electrical protection and coordination associated with the safety-related 4.16 KV
was consistent with the design. Other attributes reviewed are included as part of the  
            Bus. This review was conducted to assess the adequacy and appropriateness of
scope for each individual component.  
            design assumptions, and to verify the bus capacity was not exceeded and bus
The following 18 components were reviewed:  
            voltages remained above minimum acceptable values under design basis
*  
            conditions. The review included switchgears protective device settings and
4.16 kV Switchgear Bus (2A06): The inspectors reviewed electrical distribution  
            breaker ratings to ensure the selective coordination was adequate for protection
system load flow/voltage drop, degraded voltage protection, short-circuit, and  
            of connected equipment during worst-case, short-circuit conditions. The 125Vdc
electrical protection and coordination associated with the safety-related 4.16 KV  
            voltage calculations were reviewed to determine if adequate voltage would be
Bus. This review was conducted to assess the adequacy and appropriateness of  
            available for the breaker open/close coils and spring charging motors during
design assumptions, and to verify the bus capacity was not exceeded and bus  
                                          5                                          Enclosure
voltages remained above minimum acceptable values under design basis  
conditions. The review included switchgears protective device settings and  
breaker ratings to ensure the selective coordination was adequate for protection  
of connected equipment during worst-case, short-circuit conditions. The 125Vdc  
voltage calculations were reviewed to determine if adequate voltage would be  
available for the breaker open/close coils and spring charging motors during  


  events. The stations interface and coordination with the transmission system
  operator for plant voltage requirements and notification set points were reviewed.
6
  The inspectors evaluated selected portions of the licensees response to NRC
Enclosure
  Generic Letter (GL) 2006-02, Grid Reliability and the Impact on Plant Risk and
events. The stations interface and coordination with the transmission system  
  the Operability of Offsite Power, dated February 1, 2006. The inspectors
operator for plant voltage requirements and notification set points were reviewed.
  reviewed the degraded and loss of voltage relay protection schemes and bus
The inspectors evaluated selected portions of the licensees response to NRC  
  transfer schemes between offsite power supplies and the associated emergency
Generic Letter (GL) 2006-02, Grid Reliability and the Impact on Plant Risk and  
  diesel generators. In addition, the inspectors reviewed the preventive
the Operability of Offsite Power, dated February 1, 2006. The inspectors  
  maintenance inspection and testing procedures to verify the breakers were
reviewed the degraded and loss of voltage relay protection schemes and bus  
  maintained in accordance with industry and vendor recommendations. System
transfer schemes between offsite power supplies and the associated emergency  
  health reports, component maintenance history, and licensees corrective action
diesel generators. In addition, the inspectors reviewed the preventive  
  program reports were reviewed to verify correction of potential degradation and
maintenance inspection and testing procedures to verify the breakers were  
  deficiencies were appropriately identified and resolved. The inspectors reviewed
maintained in accordance with industry and vendor recommendations. System  
  selected industry operating experiences and plant actions to address the
health reports, component maintenance history, and licensees corrective action  
  applicable issues to ensure the appropriate insights from operating experience
program reports were reviewed to verify correction of potential degradation and  
  have been applied.
deficiencies were appropriately identified and resolved. The inspectors reviewed  
* 480 VAC Switchgear Bus (2B-04): The inspectors inspected the 480V
selected industry operating experiences and plant actions to address the  
  switchgear to verify it would operate during design basis events. The inspectors
applicable issues to ensure the appropriate insights from operating experience  
  reviewed selected calculations for electrical distribution system load flow/voltage
have been applied.  
  drop, short-circuit, and electrical protection and coordination. The adequacy and
*  
  appropriateness of design assumptions and calculations were reviewed to verify
480 VAC Switchgear Bus (2B-04): The inspectors inspected the 480V  
  the bus and circuit breaker capacity was not exceeded and bus voltages
switchgear to verify it would operate during design basis events. The inspectors  
  remained above minimum acceptable values under design basis conditions. The
reviewed selected calculations for electrical distribution system load flow/voltage  
  switchgears protective device settings and breaker ratings were reviewed to
drop, short-circuit, and electrical protection and coordination. The adequacy and  
  ensure the selective coordination was adequate for protection of connected
appropriateness of design assumptions and calculations were reviewed to verify  
  equipment during worst-case short-circuit conditions. To ensure the breakers
the bus and circuit breaker capacity was not exceeded and bus voltages  
  were maintained in accordance with industry and vendor recommendations, the
remained above minimum acceptable values under design basis conditions. The  
  inspectors reviewed the vendor manuals, preventive maintenance inspection,
switchgears protective device settings and breaker ratings were reviewed to  
  and testing procedures. The 125Vdc voltage calculations were reviewed to
ensure the selective coordination was adequate for protection of connected  
  determine if adequate voltage would be available for the breaker open/close
equipment during worst-case short-circuit conditions. To ensure the breakers  
  coils during events. System health reports, component maintenance history
were maintained in accordance with industry and vendor recommendations, the  
  and licensees corrective action program reports were reviewed to verify
inspectors reviewed the vendor manuals, preventive maintenance inspection,  
  correction of potential degradation and deficiencies were appropriately identified
and testing procedures. The 125Vdc voltage calculations were reviewed to  
  and resolved. The inspectors reviewed selected industry OE and any plant
determine if adequate voltage would be available for the breaker open/close  
  actions to address the applicable issues to ensure the appropriate insights from
coils during events. System health reports, component maintenance history  
  operating experience have been applied. Finally, the inspectors performed a
and licensees corrective action program reports were reviewed to verify  
  visual non-intrusive inspection of observable portions of the safety-related 480V
correction of potential degradation and deficiencies were appropriately identified  
  Switchgear Bus 2B-04 to assess the installation configuration, material condition,
and resolved. The inspectors reviewed selected industry OE and any plant  
  and the potential vulnerability to hazards.
actions to address the applicable issues to ensure the appropriate insights from  
* 480 VAC Motor Control Center (MCC 2B-42): The inspectors inspected the
operating experience have been applied. Finally, the inspectors performed a  
  480V MCC to verify it would operate during design basis events. The inspectors
visual non-intrusive inspection of observable portions of the safety-related 480V  
  reviewed selected calculations for electrical distribution system load flow/voltage
Switchgear Bus 2B-04 to assess the installation configuration, material condition,  
  drop, short-circuit, and electrical protection and coordination. The adequacy and
and the potential vulnerability to hazards.
  appropriateness of design assumptions and calculations were reviewed to verify
*  
  the bus and circuit breaker capacity was not exceeded and bus voltages
480 VAC Motor Control Center (MCC 2B-42): The inspectors inspected the  
  remained above minimum acceptable values under design basis conditions. The
480V MCC to verify it would operate during design basis events. The inspectors  
                                6                                          Enclosure
reviewed selected calculations for electrical distribution system load flow/voltage  
drop, short-circuit, and electrical protection and coordination. The adequacy and  
appropriateness of design assumptions and calculations were reviewed to verify  
the bus and circuit breaker capacity was not exceeded and bus voltages  
remained above minimum acceptable values under design basis conditions. The  


  MCCs protective device settings and breaker ratings were reviewed to ensure
  the selective coordination was adequate for protection of connected equipment
7
  during worst-case short-circuit conditions. To ensure the breakers were
Enclosure
  maintained in accordance with industry and vendor recommendations, the
MCCs protective device settings and breaker ratings were reviewed to ensure  
  inspectors reviewed the vendor manuals, preventive maintenance inspection,
the selective coordination was adequate for protection of connected equipment  
  and testing procedures. System health reports, component maintenance history
during worst-case short-circuit conditions. To ensure the breakers were  
  and licensees corrective action program reports were reviewed to verify
maintained in accordance with industry and vendor recommendations, the  
  correction of potential degradation and deficiencies were appropriately identified
inspectors reviewed the vendor manuals, preventive maintenance inspection,  
  and resolved. The inspectors reviewed selected industry OE and any plant
and testing procedures. System health reports, component maintenance history  
  actions to address the applicable issues to ensure appropriate insights from
and licensees corrective action program reports were reviewed to verify  
  operating experience have been applied. Finally, the inspectors performed a
correction of potential degradation and deficiencies were appropriately identified  
  visual non-intrusive inspection of observable portions of the safety-related 480V
and resolved. The inspectors reviewed selected industry OE and any plant  
  MCC 2B-42 to assess the installation configuration, material condition, and the
actions to address the applicable issues to ensure appropriate insights from  
  potential vulnerability to hazards.
operating experience have been applied. Finally, the inspectors performed a  
* 125 VDC Battery (D06): The inspectors reviewed various electrical calculations
visual non-intrusive inspection of observable portions of the safety-related 480V  
  and analyses associated with the safety-related battery to verify the battery was
MCC 2B-42 to assess the installation configuration, material condition, and the  
  designed and capable to perform its function and provide adequate voltage for
potential vulnerability to hazards.  
  required loads during design basis accident and station blackout (SBO) event.
*  
  These calculations included battery sizing and capacity, voltage drop, minimum
125 VDC Battery (D06): The inspectors reviewed various electrical calculations  
  voltage, hydrogen generation, SBO loading, and battery room transient
and analyses associated with the safety-related battery to verify the battery was  
  temperature. The inspectors also reviewed a sampling of completed weekly,
designed and capable to perform its function and provide adequate voltage for  
  monthly, semi-annual surveillance tests including performance discharge tests,
required loads during design basis accident and station blackout (SBO) event.
  and modified performance tests. The review was performed to ascertain that
These calculations included battery sizing and capacity, voltage drop, minimum  
  acceptance criteria were met and performance degradation would be identified.
voltage, hydrogen generation, SBO loading, and battery room transient  
* 125 VDC Bus (D02): The inspectors reviewed various electrical calculations and
temperature. The inspectors also reviewed a sampling of completed weekly,  
  analysis associated with the safety-related 125 Vdc bus including voltage drop,
monthly, semi-annual surveillance tests including performance discharge tests,  
  short circuit and fuse interrupting ratings to verify sufficient power and voltage
and modified performance tests. The review was performed to ascertain that  
  was available at the safety-related equipment supplied by this bus to perform
acceptance criteria were met and performance degradation would be identified.  
  their safety function; and the interrupting ratings of the fuses were well above the
*  
  calculated short circuit currents. The inspectors also reviewed schematic and
125 VDC Bus (D02): The inspectors reviewed various electrical calculations and  
  elementary diagrams for motor control logic to ensure adequate voltage would be
analysis associated with the safety-related 125 Vdc bus including voltage drop,  
  available for the control circuit components under all design basis conditions.
short circuit and fuse interrupting ratings to verify sufficient power and voltage  
* 1/2P-53 Pumps Main Feeder Breakers (1A52-83 and 2A52-68): The inspectors
was available at the safety-related equipment supplied by this bus to perform  
  inspected the 4kV circuit breakers 1P-53 and 2P-53 to verify the capability to
their safety function; and the interrupting ratings of the fuses were well above the  
  meet the design basis requirements, which is to supply power to the safety-
calculated short circuit currents. The inspectors also reviewed schematic and  
  related motor driven Auxiliary Feedwater Pump motors (MDAFWP) 1P-53 and
elementary diagrams for motor control logic to ensure adequate voltage would be  
  2P-53, MDAFWP 1P-53 is fed from 4160V Safeguards Bus Train B 1A-06
available for the control circuit components under all design basis conditions.  
  through 4kV breaker 1A52-83. MDAFWP 2P-53 is fed from 4160V Safeguards
*  
  Bus Train A 2A-05 through 4kV breaker 2A52-68. The inspectors reviewed one
1/2P-53 Pumps Main Feeder Breakers (1A52-83 and 2A52-68): The inspectors  
  line diagrams and vendor equipment data to confirm the breaker ratings were
inspected the 4kV circuit breakers 1P-53 and 2P-53 to verify the capability to  
  sufficient to meet design basis conditions. The inspectors reviewed the electrical
meet the design basis requirements, which is to supply power to the safety-
  analyses for loading and protection and coordination requirements to confirm the
related motor driven Auxiliary Feedwater Pump motors (MDAFWP) 1P-53 and  
  adequacy of the protective device settings for motor operation and circuit
2P-53, MDAFWP 1P-53 is fed from 4160V Safeguards Bus Train B 1A-06  
  protection and coordination with upstream power supplies. The inspectors
through 4kV breaker 1A52-83. MDAFWP 2P-53 is fed from 4160V Safeguards  
  reviewed manufacturer vendor manuals, periodic maintenance and testing
Bus Train A 2A-05 through 4kV breaker 2A52-68. The inspectors reviewed one  
                                7                                            Enclosure
line diagrams and vendor equipment data to confirm the breaker ratings were  
sufficient to meet design basis conditions. The inspectors reviewed the electrical  
analyses for loading and protection and coordination requirements to confirm the  
adequacy of the protective device settings for motor operation and circuit  
protection and coordination with upstream power supplies. The inspectors  
reviewed manufacturer vendor manuals, periodic maintenance and testing  


  practices to ensure the equipment is maintained in accordance with industry
  practices. The associated breaker closure and opening control logic diagrams
8
  and the 125Vdc voltage calculations were reviewed to verify adequate voltage
Enclosure
  would be available for the breaker open/close coils and spring charging motors
practices to ensure the equipment is maintained in accordance with industry  
  under accident/event conditions. System health reports, component
practices. The associated breaker closure and opening control logic diagrams  
  maintenance history and licensees corrective action program reports were
and the 125Vdc voltage calculations were reviewed to verify adequate voltage  
  reviewed to verify correction of potential degradation and deficiencies were
would be available for the breaker open/close coils and spring charging motors  
  appropriately identified and resolved. The inspectors reviewed selected industry
under accident/event conditions. System health reports, component  
  OE and any plant actions to address the applicable issues to ensure appropriate
maintenance history and licensees corrective action program reports were  
  insights from operating experience have been applied. The inspectors performed
reviewed to verify correction of potential degradation and deficiencies were  
  a visual non-intrusive inspection of 4kV circuit breakers 1P-53 and 2P-53 to
appropriately identified and resolved. The inspectors reviewed selected industry  
  assess the installation configuration, material condition, and potential
OE and any plant actions to address the applicable issues to ensure appropriate  
  vulnerability to hazards.
insights from operating experience have been applied. The inspectors performed  
* Motor-Driven AFW Pump (2P-53): The inspectors reviewed design documents,
a visual non-intrusive inspection of 4kV circuit breakers 1P-53 and 2P-53 to  
  including drawings and calculations to determine the design requirements for the
assess the installation configuration, material condition, and potential  
  new MDAFW pump. The inspectors reviewed the Safety Analysis Report, and
vulnerability to hazards.  
  recent addendum, to determine the licensing basis requirements for the system,
*  
  in order to determine the hydraulic requirements for the pump. Hydraulic
Motor-Driven AFW Pump (2P-53): The inspectors reviewed design documents,  
  analyses were reviewed to verify adequacy of Net Positive Suction Head (NPSH)
including drawings and calculations to determine the design requirements for the  
  and to verify the adequacy of surveillance test acceptance criteria for pump
new MDAFW pump. The inspectors reviewed the Safety Analysis Report, and  
  minimum discharge pressure at required flow rate. The results of the inservice
recent addendum, to determine the licensing basis requirements for the system,  
  testing (IST) performed during start-up of 2P-53, were reviewed to verify
in order to determine the hydraulic requirements for the pump. Hydraulic  
  acceptance criteria were met and performance degradation would be identified.
analyses were reviewed to verify adequacy of Net Positive Suction Head (NPSH)  
  Pump actuation logic test results were reviewed to ensure the MDAFW pump
and to verify the adequacy of surveillance test acceptance criteria for pump  
  would start in accidents and events as described in the UFSAR. The inspectors
minimum discharge pressure at required flow rate. The results of the inservice  
  reviewed condensate storage tank (CST) design criteria, including usable volume
testing (IST) performed during start-up of 2P-53, were reviewed to verify  
  calculations to ensure the MDAFW pump, in conjunction with the turbine driven
acceptance criteria were met and performance degradation would be identified.
  AFW pump had adequate water supply to prevent vortexing prior to switchover of
Pump actuation logic test results were reviewed to ensure the MDAFW pump  
  pump suction to the service water supply. Seismic calculation of the pump
would start in accidents and events as described in the UFSAR. The inspectors  
  mounting bolts was reviewed for adequacy. Condition Reports were reviewed to
reviewed condensate storage tank (CST) design criteria, including usable volume  
  ensure problems were identified and corrected in a timely manner. The
calculations to ensure the MDAFW pump, in conjunction with the turbine driven  
  inspectors reviewed the pipe stress analysis and pipe support calculations
AFW pump had adequate water supply to prevent vortexing prior to switchover of  
  associated with these pumps to verify the pumps meet the design basis
pump suction to the service water supply. Seismic calculation of the pump  
  requirements.
mounting bolts was reviewed for adequacy. Condition Reports were reviewed to  
* 2P-53 Pump Minimum Flow Valves (2AF-04073A/B): The MDAFW pump has
ensure problems were identified and corrected in a timely manner. The  
  two minimum flow control valves (in parallel). Minimum pump flow is required to
inspectors reviewed the pipe stress analysis and pipe support calculations  
  remove pump heat, and ensure hydraulic stability when the pump is running.
associated with these pumps to verify the pumps meet the design basis  
  This review included design analyses of the valves and associated air receiver
requirements.
  tank to verify the capability of the valves to perform their required function.
*  
  Specifically, the inspectors reviewed air-operated valve thrust calculations,
2P-53 Pump Minimum Flow Valves (2AF-04073A/B): The MDAFW pump has  
  reviewed the required air pressure to open the valve, and reviewed the capacity
two minimum flow control valves (in parallel). Minimum pump flow is required to  
  and allowable leakage limits of the associated air receiver to verify the capability
remove pump heat, and ensure hydraulic stability when the pump is running.
  of the valves to perform their function when required. The inspectors verified the
This review included design analyses of the valves and associated air receiver  
  valves were sized to provide adequate pump minimum flow to preclude pump
tank to verify the capability of the valves to perform their required function.
  degradation and heat-up when operating under minimum flow conditions. The
Specifically, the inspectors reviewed air-operated valve thrust calculations,  
                                8                                            Enclosure
reviewed the required air pressure to open the valve, and reviewed the capacity  
and allowable leakage limits of the associated air receiver to verify the capability  
of the valves to perform their function when required. The inspectors verified the  
valves were sized to provide adequate pump minimum flow to preclude pump  
degradation and heat-up when operating under minimum flow conditions. The  


  inspectors reviewed start-up testing of the P-53 pumps to ensure the minimum
  flow valves were functionally tested to open and close at the required setpoints.
9
* 2P-53 Pump Discharge Flow Control Valves (2AF-04074A/B): These valves
Enclosure
  have an automatic function to throttle MDAFW pump discharge flow to each
inspectors reviewed start-up testing of the P-53 pumps to ensure the minimum  
  steam generator to maintain a set discharge flow rate. This review included
flow valves were functionally tested to open and close at the required setpoints.  
  design analyses of the valves and associated air receiver tank to verify the
*  
  capability of the valves to perform their required function. Specifically, the
2P-53 Pump Discharge Flow Control Valves (2AF-04074A/B): These valves  
  inspectors reviewed air-operated valve thrust calculations, reviewed the required
have an automatic function to throttle MDAFW pump discharge flow to each  
  air pressure to open the valve, and reviewed the capacity and allowable leakage
steam generator to maintain a set discharge flow rate. This review included  
  limits of the associated air receiver to verify the capability of the valves to perform
design analyses of the valves and associated air receiver tank to verify the  
  their function when required. The inspectors reviewed start-up testing of the 2P-
capability of the valves to perform their required function. Specifically, the  
  53 pump to ensure the discharge flow control valves were functionally tested to
inspectors reviewed air-operated valve thrust calculations, reviewed the required  
  throttle flow to the steam generators. The inspectors also reviewed the design of
air pressure to open the valve, and reviewed the capacity and allowable leakage  
  the valve internals to ensure potential blockage by debris would not inhibit AFW
limits of the associated air receiver to verify the capability of the valves to perform  
  flow to the steam generators.
their function when required. The inspectors reviewed start-up testing of the 2P-
* Service Water Cross-Tie Valve to 2P-53 Pump Suction Line (2AF-4067): The
53 pump to ensure the discharge flow control valves were functionally tested to  
  inspectors reviewed the service water cross-tie valve to verify it was capable of
throttle flow to the steam generators. The inspectors also reviewed the design of  
  performing its design basis requirement of providing safety grade water to the
the valve internals to ensure potential blockage by debris would not inhibit AFW  
  MDAFW pump suction line when required. The review included service water
flow to the steam generators.  
  hydraulic calculations and MOV analysis to ensure thrust and torque limits and
*  
  actuator settings were appropriate. The inspectors reviewed start-up testing of
Service Water Cross-Tie Valve to 2P-53 Pump Suction Line (2AF-4067): The  
  the 2P-53 pump to ensure the valve was functionally tested to stroke open based
inspectors reviewed the service water cross-tie valve to verify it was capable of  
  on minimum CST level, and pump low suction pressure instrumentation.
performing its design basis requirement of providing safety grade water to the  
  Additionally, the inspectors reviewed the MOV voltage drop calculation to ensure
MDAFW pump suction line when required. The review included service water  
  appropriate voltage values were used in the thrust calculation. The inspectors
hydraulic calculations and MOV analysis to ensure thrust and torque limits and  
  also reviewed surveillance procedures, and results of the periodic flushing of
actuator settings were appropriate. The inspectors reviewed start-up testing of  
  service water suction lines to the valve to ensure the lines are maintained free of
the 2P-53 pump to ensure the valve was functionally tested to stroke open based  
  debris. In addition, the inspectors reviewed electrical calculation to verify the
on minimum CST level, and pump low suction pressure instrumentation.
  adequacy of feeder circuit including breaker, cable, breaker settings, electrical
Additionally, the inspectors reviewed the MOV voltage drop calculation to ensure  
  schematic, control switch settings, 125 VDC power and control voltage drop,
appropriate voltage values were used in the thrust calculation. The inspectors  
  thermal overload relay settings, thermal overload relay testing, breaker/fuse
also reviewed surveillance procedures, and results of the periodic flushing of  
  coordination.
service water suction lines to the valve to ensure the lines are maintained free of  
* Turbine Driven Auxiliary Feedwater (TDAFW) Pump/Turbine (2P-29): The
debris. In addition, the inspectors reviewed electrical calculation to verify the  
  inspectors reviewed the AFW system to verify the pump and associated
adequacy of feeder circuit including breaker, cable, breaker settings, electrical  
  peripherals could meet the design and performance requirements identified in the
schematic, control switch settings, 125 VDC power and control voltage drop,  
  AFW system design/licensees basis and the FSAR. The inspection included a
thermal overload relay settings, thermal overload relay testing, breaker/fuse  
  review of required flows for transients and postulated SBO events, as well as
coordination.  
  minimum flow provisions. The inspectors evaluated flow calculations, net
*  
  positive suction head (NPSH) calculations, and test data to ensure the design
Turbine Driven Auxiliary Feedwater (TDAFW) Pump/Turbine (2P-29): The  
  basis requirements were met. The inspectors reviewed completed surveillance
inspectors reviewed the AFW system to verify the pump and associated  
  test results to verify the acceptance criteria and test results demonstrated pump
peripherals could meet the design and performance requirements identified in the  
  operability was being maintained. The inspectors also reviewed room heat-up
AFW system design/licensees basis and the FSAR. The inspection included a  
  calculations, procedures used to mitigate the effects of loss of normal ventilation,
review of required flows for transients and postulated SBO events, as well as  
  and surveillances conducted on temporary fan units. In addition, the inspectors
minimum flow provisions. The inspectors evaluated flow calculations, net  
                                9                                              Enclosure
positive suction head (NPSH) calculations, and test data to ensure the design  
basis requirements were met. The inspectors reviewed completed surveillance  
test results to verify the acceptance criteria and test results demonstrated pump  
operability was being maintained. The inspectors also reviewed room heat-up  
calculations, procedures used to mitigate the effects of loss of normal ventilation,  
and surveillances conducted on temporary fan units. In addition, the inspectors  


  reviewed normal and abnormal operating procedures to ensure these would
  perform their objectives.
10
* TDAFW 2P-29 Minimum Flow Valve (2AF-4002): The inspectors reviewed
Enclosure
  information related to the air-operated valve (AOV) installed in the minimum flow
reviewed normal and abnormal operating procedures to ensure these would  
  line of the TDAFW pump. This review included inservice test procedures and
perform their objectives.  
  results to verify the capability of the valve to perform its required function under
*  
  postulated accident conditions. The inspectors also reviewed the design of the
TDAFW 2P-29 Minimum Flow Valve (2AF-4002): The inspectors reviewed  
  instrument air supply line and accumulator to verify the valve would function as
information related to the air-operated valve (AOV) installed in the minimum flow  
  designed.
line of the TDAFW pump. This review included inservice test procedures and  
* Suction Pressure Transmitters to AFW pumps (2PT-4044 and 2PT-4071): The
results to verify the capability of the valve to perform its required function under  
  inspectors reviewed the piping and instrumentation diagram (P&ID), Technical
postulated accident conditions. The inspectors also reviewed the design of the  
  Specification requirements, setpoint calculation including the verification of
instrument air supply line and accumulator to verify the valve would function as  
  instrument and loop uncertainty, completed calibration procedures to ensure the
designed.  
  transmitter was capable of functioning under design conditions.
*  
* Service Water Supply to TDAFW Pump 2P-29 (2AF-4006): The inspectors
Suction Pressure Transmitters to AFW pumps (2PT-4044 and 2PT-4071): The  
  reviewed MOV calculations and analysis to ensure the valve was capable of
inspectors reviewed the piping and instrumentation diagram (P&ID), Technical  
  functioning under design conditions. These included calculations for required
Specification requirements, setpoint calculation including the verification of  
  thrust. Diagnostic testing and IST surveillance results, including stroke time,
instrument and loop uncertainty, completed calibration procedures to ensure the  
  were reviewed to verify acceptance criteria were met and performance
transmitter was capable of functioning under design conditions.  
  degradation could be identified. In addition, the inspectors reviewed electrical
*  
  calculation to verify the adequacy of feeder circuit including breaker, cable,
Service Water Supply to TDAFW Pump 2P-29 (2AF-4006): The inspectors  
  breaker settings, electrical schematic, control switch settings, 125 VDC power
reviewed MOV calculations and analysis to ensure the valve was capable of  
  and control voltage drop, thermal overload relay settings, thermal overload relay
functioning under design conditions. These included calculations for required  
  testing, and breaker/fuse coordination.
thrust. Diagnostic testing and IST surveillance results, including stroke time,  
* TDAFW 2P-29 Bearing Oil Cooling (2MS-2090S): The inspectors reviewed
were reviewed to verify acceptance criteria were met and performance  
  information related to the bearing oil cooler on the turbine side of the TDAFW
degradation could be identified. In addition, the inspectors reviewed electrical  
  pump. The review included design configuration and specification. The
calculation to verify the adequacy of feeder circuit including breaker, cable,  
  inspectors also evaluated the adequacy of the stations GL 89-13 program in
breaker settings, electrical schematic, control switch settings, 125 VDC power  
  maintaining the heat removal efficiency of the bearing oil cooler. The inspectors
and control voltage drop, thermal overload relay settings, thermal overload relay  
  reviewed a sample of completed surveillances to verify acceptance criteria were
testing, and breaker/fuse coordination.  
  met and performance degradation could be identified.
*  
* TDAFW Pump 2P-29 Steam Supply Valves (2MS-2019 and 2MS-2020): The
TDAFW 2P-29 Bearing Oil Cooling (2MS-2090S): The inspectors reviewed  
  inspectors reviewed motor-operated valve (MOV) calculations and analysis to
information related to the bearing oil cooler on the turbine side of the TDAFW  
  ensure the valves were capable of functioning under design conditions.
pump. The review included design configuration and specification. The  
  Diagnostic testing and IST surveillance results, including stroke time and
inspectors also evaluated the adequacy of the stations GL 89-13 program in  
  available thrust, were reviewed to verify acceptance criteria were met and
maintaining the heat removal efficiency of the bearing oil cooler. The inspectors  
  performance degradation could be identified.
reviewed a sample of completed surveillances to verify acceptance criteria were  
* TDAFW Pump 2P-29 Discharge Valves (2AF-4000 and 2AF-4001): The
met and performance degradation could be identified.  
  inspectors reviewed motor-operated valve (MOV) calculations and analysis to
*  
  ensure the valves were capable of functioning under design conditions. These
TDAFW Pump 2P-29 Steam Supply Valves (2MS-2019 and 2MS-2020): The  
  included calculations for required thrust and maximum differential pressure.
inspectors reviewed motor-operated valve (MOV) calculations and analysis to  
  Diagnostic testing and IST surveillance results, including stroke time and
ensure the valves were capable of functioning under design conditions.
                                10                                            Enclosure
Diagnostic testing and IST surveillance results, including stroke time and  
available thrust, were reviewed to verify acceptance criteria were met and  
performance degradation could be identified.  
*  
TDAFW Pump 2P-29 Discharge Valves (2AF-4000 and 2AF-4001): The  
inspectors reviewed motor-operated valve (MOV) calculations and analysis to  
ensure the valves were capable of functioning under design conditions. These  
included calculations for required thrust and maximum differential pressure.
Diagnostic testing and IST surveillance results, including stroke time and  


            available thrust, were reviewed to verify acceptance criteria were met and
            performance degradation could be identified. In addition, the inspectors
11
            reviewed electrical calculation to verify the adequacy of feeder circuit including
Enclosure
            breaker, cable, breaker settings, electrical schematic, control switch settings,
available thrust, were reviewed to verify acceptance criteria were met and  
            125 VDC power and control voltage drop, thermal overload relay settings,
performance degradation could be identified. In addition, the inspectors  
            thermal overload relay testing, breaker/fuse coordination.
reviewed electrical calculation to verify the adequacy of feeder circuit including  
    *       Auxiliary Feedwater Pumps Discharge Check Valves (2AF-148 and 2AF-107):
breaker, cable, breaker settings, electrical schematic, control switch settings,  
            The inspectors reviewed the IST surveillance results to verify the acceptance
125 VDC power and control voltage drop, thermal overload relay settings,  
            criteria were met and to identify any performance degradation. Also, the
thermal overload relay testing, breaker/fuse coordination.
            inspectors reviewed the pipe stress analysis and pipe support calculations to
*  
            verify the piping and pipe supports, which support this check valve, meet the
Auxiliary Feedwater Pumps Discharge Check Valves (2AF-148 and 2AF-107):
            design basis requirements. The inspectors reviewed the condition reports and
The inspectors reviewed the IST surveillance results to verify the acceptance  
            analyses to ensure the issue was adequately evaluated and corrective actions
criteria were met and to identify any performance degradation. Also, the  
            were performed or scheduled to address the concern.
inspectors reviewed the pipe stress analysis and pipe support calculations to  
b. Findings
verify the piping and pipe supports, which support this check valve, meet the  
(1) Failure to Monitor Average Outside Temperature
design basis requirements. The inspectors reviewed the condition reports and  
    Introduction: The inspectors identified a finding of very low safety significance (Green)
analyses to ensure the issue was adequately evaluated and corrective actions  
    and associated Non-Cited Violation of 10 CFR Part 50, Appendix B, Criterion III, Design
were performed or scheduled to address the concern.
    Control, involving the licensees failure to correctly translate design basis assumption
b.  
    into procedures or instructions. Specifically, the licensee failed to monitor the average
Findings  
    outside air temperature which was one of the design inputs to temperature heat-up
(1) Failure to Monitor Average Outside Temperature  
    calculation associated with rooms that housed vital equipment required during design
Introduction: The inspectors identified a finding of very low safety significance (Green)  
    basis events.
and associated Non-Cited Violation of 10 CFR Part 50, Appendix B, Criterion III, Design  
    Description: Design Basis Calculation 2005-0054, Control Building GOTHIC
Control, involving the licensees failure to correctly translate design basis assumption  
    Temperature Calculation, evaluated the heat-up rate of various rooms including the
into procedures or instructions. Specifically, the licensee failed to monitor the average  
    TDAFW pumps room and vital switchgear room. This calculation also determined the
outside air temperature which was one of the design inputs to temperature heat-up  
    required number of temporary fans needed to maintain the temperature below the
calculation associated with rooms that housed vital equipment required during design  
    maximum allowed. Calculation 2005-0054 used two temperature inputs to the code: (1)
basis events.
    maximum outside temperature at a specific time of 95 degrees Fahrenheit (oF); and, (2)
Description: Design Basis Calculation 2005-0054, Control Building GOTHIC  
    maximum outside temperature averaged over a 24 hour period of 86.6 oF. These
Temperature Calculation, evaluated the heat-up rate of various rooms including the  
    temperature inputs were used in the calculation to determine the maximum temperature
TDAFW pumps room and vital switchgear room. This calculation also determined the  
    in the above mentioned rooms given different accident scenarios including design basis,
required number of temporary fans needed to maintain the temperature below the  
    SBO and Appendix R fire. The maximum outside temperature of 95 oF was used as an
maximum allowed. Calculation 2005-0054 used two temperature inputs to the code: (1)  
    input to the calculation in order to bound the most limiting environmental conditions the
maximum outside temperature at a specific time of 95 degrees Fahrenheit (oF); and, (2)  
    station was allowed. The maximum average outside temperature was used as an input
maximum outside temperature averaged over a 24 hour period of 86.6 oF. These  
    because the calculation was time-dependent and it credited the drop in temperature over
temperature inputs were used in the calculation to determine the maximum temperature  
    night. Using the average outside temperature allowed the licensee to have a more
in the above mentioned rooms given different accident scenarios including design basis,  
    accurate calculation in lieu of conservatisms.
SBO and Appendix R fire. The maximum outside temperature of 95 oF was used as an  
    On August 24, 2011, while reviewing Calculation 2005-0054, the inspectors noticed the
input to the calculation in order to bound the most limiting environmental conditions the  
    licensee was monitoring the maximum outside temperature for 95 oF. The licensee
station was allowed. The maximum average outside temperature was used as an input  
    provided instructions to perform a prompt engineering evaluation in the event the
because the calculation was time-dependent and it credited the drop in temperature over  
    outside temperature exceeded 95 oF to ensure the calculation was still bounded by
night. Using the average outside temperature allowed the licensee to have a more  
                                          11                                          Enclosure
accurate calculation in lieu of conservatisms.
On August 24, 2011, while reviewing Calculation 2005-0054, the inspectors noticed the  
licensee was monitoring the maximum outside temperature for 95 oF. The licensee  
provided instructions to perform a prompt engineering evaluation in the event the  
outside temperature exceeded 95 oF to ensure the calculation was still bounded by  


other conservatisms. However, the inspectors noticed the licensee did not monitor the
average outside temperature over a 24 hour period to ensure it did not exceed the
12
value of 86.6 oF. The inspectors were concerned the failure to monitor the average
Enclosure
outside temperature could result in a condition where the temperature in these vital
other conservatisms. However, the inspectors noticed the licensee did not monitor the  
rooms would be outside the design basis calculation. Specifically, the temperature
average outside temperature over a 24 hour period to ensure it did not exceed the  
could be below 95 oF, but the average temperature over a 24 hour period could exceed
value of 86.6 oF. The inspectors were concerned the failure to monitor the average  
86.6 oF. In addition, by the time the maximum temperature of the outside air reaches
outside temperature could result in a condition where the temperature in these vital  
95 oF, the average temperature over a 24 hour period could have already been
rooms would be outside the design basis calculation. Specifically, the temperature  
exceeded. In addition, by not monitoring average outside air temperature over a 24 hour
could be below 95 oF, but the average temperature over a 24 hour period could exceed  
period, the licensee would not be able to take adequate compensatory measures to
86.6 oF. In addition, by the time the maximum temperature of the outside air reaches  
ensure the potential degraded condition does not result in a more significant concern.
95 oF, the average temperature over a 24 hour period could have already been  
The licensee acknowledged the inspectors concerns and initiated corrective action
exceeded. In addition, by not monitoring average outside air temperature over a 24 hour  
program document AR 01680705 to address the issue. As part of their corrective
period, the licensee would not be able to take adequate compensatory measures to  
actions, the licensees recommendation included performing an evaluation and
ensure the potential degraded condition does not result in a more significant concern.  
additional monitoring once the outside temperature reaches 86.6F. The inspectors
The licensee acknowledged the inspectors concerns and initiated corrective action  
reviewed the licensees action request and had no concerns.
program document AR 01680705 to address the issue. As part of their corrective  
In addition, during the licensee apparent cause evaluation (ACE) for this issue, the
actions, the licensees recommendation included performing an evaluation and  
licensee discovered when the calculation was generated, there was a recommended
additional monitoring once the outside temperature reaches 86.6F. The inspectors  
action to revise the operator logs, but the action was not implemented. The
reviewed the licensees action request and had no concerns.  
recommendation was made in an operational decision making (ODM) document. The
In addition, during the licensee apparent cause evaluation (ACE) for this issue, the  
action was canceled when the ODM document was canceled because licensed
licensee discovered when the calculation was generated, there was a recommended  
operators incorrectly determined the condition was a functionality, not an operability
action to revise the operator logs, but the action was not implemented. The  
issue.
recommendation was made in an operational decision making (ODM) document. The  
Analysis: The inspectors determined the failure to correctly translate the average
action was canceled when the ODM document was canceled because licensed  
outside temperature into procedures and instructions were contrary to 10 CFR Part 50,
operators incorrectly determined the condition was a functionality, not an operability  
Appendix B, Criterion III, Design Control, and was a performance deficiency. The
issue.  
performance deficiency was determined to be more than minor because it was
Analysis: The inspectors determined the failure to correctly translate the average  
associated with the Mitigating Systems Cornerstone and if left uncorrected, it would have
outside temperature into procedures and instructions were contrary to 10 CFR Part 50,  
the potential to lead to a more significant safety concern. Specifically, because the
Appendix B, Criterion III, Design Control, and was a performance deficiency. The  
average outside temperature over a 24 hour period was not being monitored, the
performance deficiency was determined to be more than minor because it was  
licensee failed to ensure the maximum allowed temperature in the TDAFW pumps room
associated with the Mitigating Systems Cornerstone and if left uncorrected, it would have  
and vital switchgear room would not be exceeded and affect equipment relied upon to
the potential to lead to a more significant safety concern. Specifically, because the  
perform a safety function during a design basis.
average outside temperature over a 24 hour period was not being monitored, the  
The inspectors determined the finding could be evaluated using the SDP in accordance
licensee failed to ensure the maximum allowed temperature in the TDAFW pumps room  
with IMC 0609, Significance Determination Process, Attachment 0609.04, Phase 1 -
and vital switchgear room would not be exceeded and affect equipment relied upon to  
Initial Screening and Characterization of Findings, Table 4a for the Mitigating System
perform a safety function during a design basis.  
cornerstone. The finding screened as of very low safety significance (Green) because
The inspectors determined the finding could be evaluated using the SDP in accordance  
the finding was not a design or qualification deficiency, did not represent a loss of
with IMC 0609, Significance Determination Process, Attachment 0609.04, Phase 1 -  
system safety function, and did not screen as potentially risk-significant due to a seismic,
Initial Screening and Characterization of Findings, Table 4a for the Mitigating System  
flooding, or severe weather initiating event. Specifically, the licensee provided historical
cornerstone. The finding screened as of very low safety significance (Green) because  
data showed the average maximum temperature over a 24 hour period did not exceed
the finding was not a design or qualification deficiency, did not represent a loss of  
86.6 oF since the calculation was issued.
system safety function, and did not screen as potentially risk-significant due to a seismic,  
The inspectors determined the finding had a cross-cutting aspect in the area of human
flooding, or severe weather initiating event. Specifically, the licensee provided historical  
performance because the licensee did not ensure adequate training and qualification of
data showed the average maximum temperature over a 24 hour period did not exceed  
                                      12                                          Enclosure
86.6 oF since the calculation was issued.  
The inspectors determined the finding had a cross-cutting aspect in the area of human  
performance because the licensee did not ensure adequate training and qualification of  


    personnel to ensure nuclear safety. Specifically, the licensee failed to adequately train
    licensed operators to ensure adequate knowledge with respect to the interface between
13
    functionality of a non-safety system component and the impact of a failure on the
Enclosure
    operability of safety-related equipment. [H.2(b)]
personnel to ensure nuclear safety. Specifically, the licensee failed to adequately train  
    Enforcement: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control requires,
licensed operators to ensure adequate knowledge with respect to the interface between  
    in part, that measures be established to ensure the design basis requirements are
functionality of a non-safety system component and the impact of a failure on the  
    correctly translated into specifications, drawings, procedures, and instructions.
operability of safety-related equipment. [H.2(b)]  
    Contrary to the above, as of March 24, 2009, the licensees design control measures
Enforcement: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control requires,  
    failed to verify the design inputs were incorporated into instructions. Specifically, the
in part, that measures be established to ensure the design basis requirements are  
    licensee failed to monitor average outside air temperature which was an input to a
correctly translated into specifications, drawings, procedures, and instructions.  
    design basis calculation associated with the TDAFW pumps room and vital switchgear
Contrary to the above, as of March 24, 2009, the licensees design control measures  
    room temperature heat-up. Because this violation was of very low safety significance
failed to verify the design inputs were incorporated into instructions. Specifically, the  
    and because the issue was entered into the licensees corrective action program as
licensee failed to monitor average outside air temperature which was an input to a  
    AR 01680705, this violation is being treated as an NCV, consistent with Section 2.3.2 of
design basis calculation associated with the TDAFW pumps room and vital switchgear  
    the NRC Enforcement Policy (NCV 05000266/2011009-01; 05000301/2011009-01,
room temperature heat-up. Because this violation was of very low safety significance  
    Failure to Monitor Outside Air Temperature).
and because the issue was entered into the licensees corrective action program as  
.4   Operating Experience
AR 01680705, this violation is being treated as an NCV, consistent with Section 2.3.2 of  
  a. Inspection Scope
the NRC Enforcement Policy (NCV 05000266/2011009-01; 05000301/2011009-01,  
    The inspectors reviewed 4 operating experience issues to ensure the NRC generic
Failure to Monitor Outside Air Temperature).  
    concerns had been adequately evaluated and addressed by the licensee. The operating
.4  
    experience issues listed below were reviewed as part of this inspection:
Operating Experience  
    *       IN 1987-53, AFW Pump Trips Resulting from Low Suction Pressure;
a.  
    *       IN 2007-34, Operating Experience Regarding Electrical Circuit Breakers;
Inspection Scope  
    *       IN 2006-31, Inadequate Fault Interrupting Rating of Breakers; and
The inspectors reviewed 4 operating experience issues to ensure the NRC generic  
    *       GL 89-13, Service Water System Problems Affecting Safety-Related Systems.
concerns had been adequately evaluated and addressed by the licensee. The operating  
  b. Findings
experience issues listed below were reviewed as part of this inspection:  
    No findings of significance were identified.
*  
.5   Operating Procedure Accident Scenario Reviews
IN 1987-53, AFW Pump Trips Resulting from Low Suction Pressure;  
  a. Inspection Scope
*  
    The inspectors performed a detailed reviewed of the procedures listed below associated
IN 2007-34, Operating Experience Regarding Electrical Circuit Breakers;
    with the Auxiliary Feedwater System. For the procedures listed, the time critical operator
*  
    actions were reviewed for reasonableness, in plant actions were walked down with a
IN 2006-31, Inadequate Fault Interrupting Rating of Breakers; and  
    licensed operator, and any interfaces with other departments were evaluated. The
*  
    procedures were compared to UFSAR, design assumptions, and training materials to
GL 89-13, Service Water System Problems Affecting Safety-Related Systems.  
    ensure for constancy. In addition, the inspectors also observed operator actions during
b.  
                                          13                                          Enclosure
Findings  
No findings of significance were identified.  
.5  
Operating Procedure Accident Scenario Reviews  
a.  
Inspection Scope  
The inspectors performed a detailed reviewed of the procedures listed below associated  
with the Auxiliary Feedwater System. For the procedures listed, the time critical operator  
actions were reviewed for reasonableness, in plant actions were walked down with a  
licensed operator, and any interfaces with other departments were evaluated. The  
procedures were compared to UFSAR, design assumptions, and training materials to  
ensure for constancy. In addition, the inspectors also observed operator actions during  


    the performance of four selected scenarios on the station simulator, the station blackout
    (SBO) event, the anticipated transient without a scram (ATWS) event, the steam
14
    generator tube rupture (SGTR) event, and a faulted steam generator event.
Enclosure
    The following operating procedures were reviewed in detail:
the performance of four selected scenarios on the station simulator, the station blackout  
    *       EOP-0, Reactor Trip of Safety Injection;
(SBO) event, the anticipated transient without a scram (ATWS) event, the steam  
    *       EOP-0.1, Reactor Trip Response;
generator tube rupture (SGTR) event, and a faulted steam generator event.  
    *       EOP-1, Loss of Reactor or Secondary Coolant;
The following operating procedures were reviewed in detail:  
    *       EOP-1.1, Safety Injection (SI) Termination;
*  
    *       EOP-1.2, Post LOCA Cooldown and Depressurization;
EOP-0, Reactor Trip of Safety Injection;  
    *       EOP-2, Faulted Steam Generator;
*  
    *       EOP-3, Steam Generator Tube Rupture;
EOP-0.1, Reactor Trip Response;  
    *       EOP-3.1, Post-SGTR Cooldown using Backfill;
*  
    *       ECA-0.0, Loss of All AC Power; and
EOP-1, Loss of Reactor or Secondary Coolant;  
    *       CSP-S.1, Response to Nuclear Power Generation/ATWS.
*  
b. Findings
EOP-1.1, Safety Injection (SI) Termination;  
(1) Failure to Incorporate Minimum AFW Flow Rate Requirement Into Emergency
*  
    Procedures
EOP-1.2, Post LOCA Cooldown and Depressurization;  
    Introduction: The inspectors identified a finding of very low safety significance (Green)
*  
    and associated Non-Cited Violation of 10 CFR Part 50, Appendix B, Criterion III, Design
EOP-2, Faulted Steam Generator;  
    Control, involving the licensees failure to maintain Emergency Procedures consistent
*  
    with the Loss of Normal Feedwater (LONF) Accident Analysis. The accident analysis of
EOP-3, Steam Generator Tube Rupture;  
    record assumed an Auxiliary Feedwater flow rate of 275 gpm, while the inadequate
*  
    Emergency Procedure allowed the operator to inject AFW flow at a rate greater than
EOP-3.1, Post-SGTR Cooldown using Backfill;  
    230 gpm, which would allow less than the required amount of 275 gpm of AFW flow.
*  
    Description: The AFW system was redesigned, in part, to support implementation of the
ECA-0.0, Loss of All AC Power; and  
    extended power uprate (EPU). The licensee installed one new motor-driven auxiliary
*  
    feedwater (MDAFW) pump for each unit in a new location in the auxiliary building. The
CSP-S.1, Response to Nuclear Power Generation/ATWS.
    pumps, 1P-53 and 2P-53, replaced the safety-related function of the old MDAFW pumps
b.  
    which had been shared between the two units. The new pumps are unitized, capable of
Findings  
    a higher flow capacity, and capable of delivering flow to either or both of the units two
(1) Failure to Incorporate Minimum AFW Flow Rate Requirement Into Emergency  
    steam generators (SGs). The new pumps were designed to deliver the minimum flow
Procedures  
    requirement of 275 gpm at the lowest SG safety relief valve setpoint. The old AFW
Introduction: The inspectors identified a finding of very low safety significance (Green)  
    pumps were not removed from the plant, however; they were reclassified as non-safety-
and associated Non-Cited Violation of 10 CFR Part 50, Appendix B, Criterion III, Design  
                                          14                                          Enclosure
Control, involving the licensees failure to maintain Emergency Procedures consistent  
with the Loss of Normal Feedwater (LONF) Accident Analysis. The accident analysis of  
record assumed an Auxiliary Feedwater flow rate of 275 gpm, while the inadequate  
Emergency Procedure allowed the operator to inject AFW flow at a rate greater than  
230 gpm, which would allow less than the required amount of 275 gpm of AFW flow.  
Description: The AFW system was redesigned, in part, to support implementation of the  
extended power uprate (EPU). The licensee installed one new motor-driven auxiliary  
feedwater (MDAFW) pump for each unit in a new location in the auxiliary building. The  
pumps, 1P-53 and 2P-53, replaced the safety-related function of the old MDAFW pumps  
which had been shared between the two units. The new pumps are unitized, capable of  
a higher flow capacity, and capable of delivering flow to either or both of the units two  
steam generators (SGs). The new pumps were designed to deliver the minimum flow  
requirement of 275 gpm at the lowest SG safety relief valve setpoint. The old AFW  
pumps were not removed from the plant, however; they were reclassified as non-safety-


related pumps and are used during plant start up and shut down. The currently installed
safety-related turbine-driven auxiliary feedwater (TDAFW) pumps for each unit meet
15
EPU design flow requirements, and the new MDAFW pumps will not affect operation of
Enclosure
the TDAFW pumps.
related pumps and are used during plant start up and shut down. The currently installed  
In addition, as part of the modification, the licensee installed cavitating venturis in the
safety-related turbine-driven auxiliary feedwater (TDAFW) pumps for each unit meet  
flow path between the new MDAFW pump to each SG. These venturis were installed as
EPU design flow requirements, and the new MDAFW pumps will not affect operation of  
pump runout protection. Specifically, in the event of a failed flow control valve, the
the TDAFW pumps.  
venturi would limit the flow from the MDAFW pump to 230 gpm, even while delivering
In addition, as part of the modification, the licensee installed cavitating venturis in the  
flow to a depressurized SG. The other intact SG would still receive the required flow
flow path between the new MDAFW pump to each SG. These venturis were installed as  
rate, since the flow rate of 230 gpm would be limited to the faulted SG.
pump runout protection. Specifically, in the event of a failed flow control valve, the  
The inspectors reviewed the bounding analysis for AFW flow rate requirements; the Loss
venturi would limit the flow from the MDAFW pump to 230 gpm, even while delivering  
of Normal Feedwater (LONF)/Loss of AC Power (LOAC) for EPU. This calculation was
flow to a depressurized SG. The other intact SG would still receive the required flow  
performed by Westinghouse, as documented in calculation CN-TA-08-79, Revision 1.
rate, since the flow rate of 230 gpm would be limited to the faulted SG.  
Here, it was determined the required AFW flow during the LONF event, which bounds
The inspectors reviewed the bounding analysis for AFW flow rate requirements; the Loss  
the LOAC event, was 275 gpm, split between the two SGs (137.5 gpm flow split). The
of Normal Feedwater (LONF)/Loss of AC Power (LOAC) for EPU. This calculation was  
calculation concluded the LONF event did not cause any adverse condition in the core,
performed by Westinghouse, as documented in calculation CN-TA-08-79, Revision 1.
since it did not result in water relief from neither the pressurizer power operated relief
Here, it was determined the required AFW flow during the LONF event, which bounds  
valves, or ASME Code safety valves.
the LOAC event, was 275 gpm, split between the two SGs (137.5 gpm flow split). The  
The inspectors also reviewed procedure EOP-0.1,Reactor Trip Response, which would
calculation concluded the LONF event did not cause any adverse condition in the core,  
be entered on a LONF event. The procedure was revised as part of EPU, and included
since it did not result in water relief from neither the pressurizer power operated relief  
a new required AFW flow rate of greater than 230 gpm when the pumps are aligned to
valves, or ASME Code safety valves.
the steam generators. The 230 gpm flow rate was based on the maximum flow rate that
The inspectors also reviewed procedure EOP-0.1,Reactor Trip Response, which would  
could be delivered to one SG, with only the MDAFW pump available, because of the
be entered on a LONF event. The procedure was revised as part of EPU, and included  
cavitating venturis installed in the flow path between the new MDAFW pump to each SG.
a new required AFW flow rate of greater than 230 gpm when the pumps are aligned to  
However, in contrast to what was stated in EOP-0.1, the inspectors concluded 275 gpm
the steam generators. The 230 gpm flow rate was based on the maximum flow rate that  
was required to be delivered to the SGs when both SGs were available during a LONF
could be delivered to one SG, with only the MDAFW pump available, because of the  
event.
cavitating venturis installed in the flow path between the new MDAFW pump to each SG.  
In response to the inspectors concern, the licensee initiated AR01678638 to revise the
However, in contrast to what was stated in EOP-0.1, the inspectors concluded 275 gpm  
EOPs to incorporate the design value for the minimum AFW flow of 275 gpm when
was required to be delivered to the SGs when both SGs were available during a LONF  
supplying both SGs during a LONF event, as specified in the design basis calculations.
event.  
In addition, the inspectors also reviewed the licensing basis for the new MDAFW pumps
In response to the inspectors concern, the licensee initiated AR01678638 to revise the  
discussed in the Safety Evaluation Report (SER) for power uprate. This document
EOPs to incorporate the design value for the minimum AFW flow of 275 gpm when  
stated the new MDAFW pump could deliver 275 gpm to one, or both, SGs (emphasis
supplying both SGs during a LONF event, as specified in the design basis calculations.  
added) for a steam generator tube rupture event. However, due to the cavitating
In addition, the inspectors also reviewed the licensing basis for the new MDAFW pumps  
venturis installed in the flowpath to each SG, the MDAFW pumps could only deliver a
discussed in the Safety Evaluation Report (SER) for power uprate. This document  
maximum of 230 gpm to the intact SG, which is in conflict to what was stated in the SER.
stated the new MDAFW pump could deliver 275 gpm to one, or both, SGs (emphasis  
Upon discussion with NRR technical reviewers, and the licensee, it was determined the
added) for a steam generator tube rupture event. However, due to the cavitating  
SER required a clarification to state the flow to a single SG was limited to 230 gpm when
venturis installed in the flowpath to each SG, the MDAFW pumps could only deliver a  
the MDAFW pump is operating without the TDAFW pump. Additional analysis was
maximum of 230 gpm to the intact SG, which is in conflict to what was stated in the SER.
provided to the inspectors which indicated 230 gpm was sufficient flow rate to the intact
Upon discussion with NRR technical reviewers, and the licensee, it was determined the  
SG.
SER required a clarification to state the flow to a single SG was limited to 230 gpm when  
                                        15                                        Enclosure
the MDAFW pump is operating without the TDAFW pump. Additional analysis was  
provided to the inspectors which indicated 230 gpm was sufficient flow rate to the intact  
SG.  


Analysis: The inspectors determined the failure to ensure a minimum AFW flow of 275
gpm as specified in the accident analysis for the Loss of Normal Feedwater event was
16
contrary to 10 CFR Part 50, Appendix B, Criterion III, Design Control, and was a
Enclosure
performance deficiency. The performance deficiency was associated with the Mitigating
Analysis: The inspectors determined the failure to ensure a minimum AFW flow of 275  
System Cornerstone attribute of design control and determined to be more than minor
gpm as specified in the accident analysis for the Loss of Normal Feedwater event was  
because if left uncorrected, could become a more significant safety concern.
contrary to 10 CFR Part 50, Appendix B, Criterion III, Design Control, and was a  
Specifically, the failure to properly implement the minimum AFW flow rate of 275 gpm
performance deficiency. The performance deficiency was associated with the Mitigating  
into the Emergency Procedures for the Loss of Normal Feedwater event did not ensure
System Cornerstone attribute of design control and determined to be more than minor  
the pressurizer would not become water solid and cause an over-pressure condition
because if left uncorrected, could become a more significant safety concern.
within the Reactor Coolant System during the event. This over-pressure condition may
Specifically, the failure to properly implement the minimum AFW flow rate of 275 gpm  
cause liquid water to pass through the Pressurizer Safety Valves which could lead to a
into the Emergency Procedures for the Loss of Normal Feedwater event did not ensure  
more serious Loss of Coolant Accident (LOCA) event.
the pressurizer would not become water solid and cause an over-pressure condition  
The inspectors determined the finding could be evaluated using the SDP in accordance
within the Reactor Coolant System during the event. This over-pressure condition may  
with IMC 0609, Significance Determination Process, Attachment 0609.04, Phase 1 -
cause liquid water to pass through the Pressurizer Safety Valves which could lead to a  
Initial Screening and Characterization of Findings, Table 4a for the Mitigating System
more serious Loss of Coolant Accident (LOCA) event.  
cornerstone. The finding screened as of very low safety significance (Green) because
The inspectors determined the finding could be evaluated using the SDP in accordance  
the finding was not a design or qualification deficiency, did not represent a loss of safety
with IMC 0609, Significance Determination Process, Attachment 0609.04, Phase 1 -  
function, and did not screen as potentially risk-significant due to a seismic, flooding, or
Initial Screening and Characterization of Findings, Table 4a for the Mitigating System  
severe weather initiating event. Specifically, although the procedure stated a flow rate
cornerstone. The finding screened as of very low safety significance (Green) because  
of 230 gpm, the operators could increase flow if needed since the MDAFW pumps were
the finding was not a design or qualification deficiency, did not represent a loss of safety  
capable of providing greater than 275 gpm to two steam generators if required.
function, and did not screen as potentially risk-significant due to a seismic, flooding, or  
The inspectors determined the finding had a cross-cutting aspect in the area of human
severe weather initiating event. Specifically, although the procedure stated a flow rate  
performance, resources because the licensee failed to ensure the emergency
of 230 gpm, the operators could increase flow if needed since the MDAFW pumps were  
procedures were adequate and included the design basis values. Specifically, the
capable of providing greater than 275 gpm to two steam generators if required.  
licensee incorporated a non-conservative design value for the minimum AFW flow rate of
The inspectors determined the finding had a cross-cutting aspect in the area of human  
230 gpm instead of the design analysis value of 275 gpm specified for LONF event.
performance, resources because the licensee failed to ensure the emergency  
[H.2.c]
procedures were adequate and included the design basis values. Specifically, the  
Enforcement: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control requires,
licensee incorporated a non-conservative design value for the minimum AFW flow rate of  
in part, that measures shall be established to ensure the applicable regulatory
230 gpm instead of the design analysis value of 275 gpm specified for LONF event.  
requirements and the design basis are correctly translated into specifications, drawings,
[H.2.c]  
procedures and instructions. A Loss of Normal Feedwater is an analyzed accident in
Enforcement: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control requires,  
Chapter 14.1.10 of the Point Beach UFSAR. Technical Specification 5.4.1 requires, in
in part, that measures shall be established to ensure the applicable regulatory  
part, that Emergency Procedures will implement the requirements of NUREG-0737.
requirements and the design basis are correctly translated into specifications, drawings,  
NUREG-0737 states, in part, that emergency procedures are required to be consistent
procedures and instructions. A Loss of Normal Feedwater is an analyzed accident in  
with the actions necessary to cope with the transients and accidents analyzed.
Chapter 14.1.10 of the Point Beach UFSAR. Technical Specification 5.4.1 requires, in  
Contrary to the above as of September 2, 2011, the licensees design control measures
part, that Emergency Procedures will implement the requirements of NUREG-0737.
failed to correctly incorporate the correct AFW flow rate into the stations emergency
NUREG-0737 states, in part, that emergency procedures are required to be consistent  
operating procedures. Specifically, the accident analysis of record assumes an AFW
with the actions necessary to cope with the transients and accidents analyzed.  
flow rate of 275 gpm, while the Emergency Procedure allows the operator to inject AFW
Contrary to the above as of September 2, 2011, the licensees design control measures  
flow at a rate greater than 230 gpm which would allow less than the required amount
failed to correctly incorporate the correct AFW flow rate into the stations emergency  
of 275 gpm of AFW flow. Because this violation was of very low safety significance
operating procedures. Specifically, the accident analysis of record assumes an AFW  
and because the issue was entered into the licensees corrective action program as
flow rate of 275 gpm, while the Emergency Procedure allows the operator to inject AFW  
AR 01678638, this violation is being treated as an NCV, consistent with Section 2.3.2 of
flow at a rate greater than 230 gpm which would allow less than the required amount  
the NRC Enforcement Policy. (NCV 05000266/2011009-02; 05000301/2011009-02;
of 275 gpm of AFW flow. Because this violation was of very low safety significance  
                                      16                                          Enclosure
and because the issue was entered into the licensees corrective action program as  
AR 01678638, this violation is being treated as an NCV, consistent with Section 2.3.2 of  
the NRC Enforcement Policy. (NCV 05000266/2011009-02; 05000301/2011009-02;  


      Failure to Incorporate Minimum AFW Flow Rate Requirement into Emergency
      Procedures).
17
4.   OTHER ACTIVITIES
Enclosure
4OA2 Identification and Resolution of Problems
Failure to Incorporate Minimum AFW Flow Rate Requirement into Emergency  
.1   Review of Items Entered Into the Corrective Action Program
Procedures).  
  a. Inspection Scope
4.  
      The inspectors reviewed a sample of the selected component problems that were
OTHER ACTIVITIES  
      identified by the licensee and entered into the corrective action program. The inspectors
4OA2 Identification and Resolution of Problems  
      reviewed these issues to verify an appropriate threshold for identifying issues and to
.1  
      evaluate the effectiveness of corrective actions related to design issues. In addition,
Review of Items Entered Into the Corrective Action Program  
      corrective action documents written on issues identified during the inspection were
a.  
      reviewed to verify adequate problem identification and incorporation of the problem into
Inspection Scope  
      the corrective action program. The specific corrective action documents that were
The inspectors reviewed a sample of the selected component problems that were  
      sampled and reviewed by the inspectors are listed in the Attachment to this report.
identified by the licensee and entered into the corrective action program. The inspectors  
      The inspectors also selected 3 issues that were identified during previous CDBIs to
reviewed these issues to verify an appropriate threshold for identifying issues and to  
      verify the concern was adequately evaluated and corrective actions were identified and
evaluate the effectiveness of corrective actions related to design issues. In addition,  
      implemented to resolve the concern, as necessary. The following issues were reviewed:
corrective action documents written on issues identified during the inspection were  
      *   NCV 05000266/2008009-01; 05000301/2008009-01, Equalizing Charge Voltage Not
reviewed to verify adequate problem identification and incorporation of the problem into  
          Bounded by Battery Room Hydrogen Generation Calculation;
the corrective action program. The specific corrective action documents that were  
      *   NCV 05000266/2008009-02; 05000301/2008009-02, Non-Conservative Design
sampled and reviewed by the inspectors are listed in the Attachment to this report.  
          Basis for Primary Auxiliary Building Heat-up; and
The inspectors also selected 3 issues that were identified during previous CDBIs to  
      *   NCV 05000266/2008009-03; 05000301/2008009-03, Ability to Transfer Fuel Oil
verify the concern was adequately evaluated and corrective actions were identified and  
          between EDG Fuel Oil Tanks T-175A/B has not been demonstrated by Testing.
implemented to resolve the concern, as necessary. The following issues were reviewed:  
  b. Findings
*  
      No findings of significance were identified.
NCV 05000266/2008009-01; 05000301/2008009-01, Equalizing Charge Voltage Not  
4OA5 Power Uprate (71004)
Bounded by Battery Room Hydrogen Generation Calculation;  
.1   Plant Modifications (2 samples)
*  
  a. Inspection Scope
NCV 05000266/2008009-02; 05000301/2008009-02, Non-Conservative Design  
      The inspectors reviewed plant modifications for those implemented for the extended
Basis for Primary Auxiliary Building Heat-up; and  
      power uprate. This includes seismic qualification of balance of plant piping and pipe
*  
      supports for extended power uprate.
NCV 05000266/2008009-03; 05000301/2008009-03, Ability to Transfer Fuel Oil  
      *     Engineering Change EC-12070, Unit 2 Main Steam and Feedwater pipe support,
between EDG Fuel Oil Tanks T-175A/B has not been demonstrated by Testing.
            Revision 0; and
b.  
                                          17                                          Enclosure
Findings  
No findings of significance were identified.  
4OA5 Power Uprate (71004)  
.1  
Plant Modifications (2 samples)  
a.  
Inspection Scope  
The inspectors reviewed plant modifications for those implemented for the extended  
power uprate. This includes seismic qualification of balance of plant piping and pipe  
supports for extended power uprate.
*  
Engineering Change EC-12070, Unit 2 Main Steam and Feedwater pipe support,  
Revision 0; and  


    *     EC-11795, Unit 2 Containment Spray Piping Supports, Revision 0
b. Findings
18
(1) Containment Spray Pipe Support Deficiencies
Enclosure
    Introduction: The inspectors identified a finding of very low safety significance (Green)
*  
    and an associated Non-Cited Violation of 10 CFR Part 50, Appendix B, Criterion III,
EC-11795, Unit 2 Containment Spray Piping Supports, Revision 0  
    Design Control, for failure to meet Seismic Category I requirements for containment
b.  
    spray piping. Specifically, the licensee failed to provide sufficient justification for the
Findings  
    design margin in the Containment Spray Pipe Support 2S-249 and Containment Spray
(1) Containment Spray Pipe Support Deficiencies  
    Pipe Anchor 2A-35 despite the applied bending stress being greater than the allowable
Introduction: The inspectors identified a finding of very low safety significance (Green)  
    bending stress.
and an associated Non-Cited Violation of 10 CFR Part 50, Appendix B, Criterion III,  
    Description: The containment spray system per UFSAR Section 6.4.1 has the following
Design Control, for failure to meet Seismic Category I requirements for containment  
    safety-related design basis functions: provide sufficient heat removal capability to
spray piping. Specifically, the licensee failed to provide sufficient justification for the  
    maintain the post accident containment pressure below the design pressure, to remove
design margin in the Containment Spray Pipe Support 2S-249 and Containment Spray  
    iodine from the containment atmosphere should it be released in the event of a loss-of-
Pipe Anchor 2A-35 despite the applied bending stress being greater than the allowable  
    coolant accident and to provide sufficient sodium hydroxide from spray additive tank to
bending stress.  
    achieve the required sump Ph level in order to prevent chloride induced stress corrosion
Description: The containment spray system per UFSAR Section 6.4.1 has the following  
    cracking. The containment spray piping and pipe supports were designed to Seismic
safety-related design basis functions: provide sufficient heat removal capability to  
    Category I requirements as described in UFSAR Section A.5.2.
maintain the post accident containment pressure below the design pressure, to remove  
    Calculation WE-200074, Subsystem 6-SI-301R-1: Containment Spray System from
iodine from the containment atmosphere should it be released in the event of a loss-of-
    Containment Penetration P-54 to Anchors 2A-34 and 2A-35, Revision 1, evaluated
coolant accident and to provide sufficient sodium hydroxide from spray additive tank to  
    Containment Spray Pipe Support 2S-249 and Containment Spray Pipe Anchor 2A-35 in
achieve the required sump Ph level in order to prevent chloride induced stress corrosion  
    accordance with Seismic Category I requirements for all design basis loading. The pipe
cracking. The containment spray piping and pipe supports were designed to Seismic  
    support and pipe anchor support were analyzed to withstand applied stress due to dead
Category I requirements as described in UFSAR Section A.5.2.  
    loads, live loads, seismic loads, and thermal loads. The inspectors noticed in
Calculation WE-200074, Subsystem 6-SI-301R-1: Containment Spray System from  
    Calculation WE-200074, Revision 1, Attachment D, the licensee used an allowable
Containment Penetration P-54 to Anchors 2A-34 and 2A-35, Revision 1, evaluated  
    overstress condition, the applied stress was greater than allowable stress, to
Containment Spray Pipe Support 2S-249 and Containment Spray Pipe Anchor 2A-35 in  
    demonstrate seismic Category I compliance which was not in accordance with the
accordance with Seismic Category I requirements for all design basis loading. The pipe  
    design and licensing basis. The Seismic Category I requirements were based on the
support and pipe anchor support were analyzed to withstand applied stress due to dead  
    applied stress less than allowable stress for the evaluation of the Containment Spray
loads, live loads, seismic loads, and thermal loads. The inspectors noticed in  
    Pipe Support 2S-249 and Containment Spray Pipe Anchor 2A-35. The inspectors
Calculation WE-200074, Revision 1, Attachment D, the licensee used an allowable  
    determined the use of an allowable overstress condition for Containment Spray Pipe
overstress condition, the applied stress was greater than allowable stress, to  
    Support 2S-249 and Containment Spray Pipe Anchor 2A-35 did not meet Seismic
demonstrate seismic Category I compliance which was not in accordance with the  
    Category I requirements.
design and licensing basis. The Seismic Category I requirements were based on the  
    Upon the inspectors identification of this issue, the license concurred with the
applied stress less than allowable stress for the evaluation of the Containment Spray  
    inspectors concern and entered the issue into their corrective action program as
Pipe Support 2S-249 and Containment Spray Pipe Anchor 2A-35. The inspectors  
    AR01678643, Overstress of Pipe Supports Analyzed in WE-200074. The licensee
determined the use of an allowable overstress condition for Containment Spray Pipe  
    performed an additional analysis and determined the pipe support and the pipe anchor
Support 2S-249 and Containment Spray Pipe Anchor 2A-35 did not meet Seismic  
    were operable but nonconforming.
Category I requirements.  
    Analysis: The inspectors determined the licensees failure to meet Seismic Category I
Upon the inspectors identification of this issue, the license concurred with the  
    requirements for the Containment Spray Pipe Support 2S-249 and Containment Spray
inspectors concern and entered the issue into their corrective action program as  
    Anchor 2A-35 was contrary to 10 CFR Part 50, Appendix B, Criterion III, Design
AR01678643, Overstress of Pipe Supports Analyzed in WE-200074. The licensee  
    Control, and was a performance deficiency. The performance deficiency was
performed an additional analysis and determined the pipe support and the pipe anchor  
                                          18                                              Enclosure
were operable but nonconforming.  
Analysis: The inspectors determined the licensees failure to meet Seismic Category I  
requirements for the Containment Spray Pipe Support 2S-249 and Containment Spray  
Anchor 2A-35 was contrary to 10 CFR Part 50, Appendix B, Criterion III, Design  
Control, and was a performance deficiency. The performance deficiency was  


    determined to be more than minor because the finding was associated with the Barrier
    Integrity Cornerstone attribute of design control and adversely affected the cornerstone
19
    objective to provide reasonable assurance that physical design barriers (fuel cladding,
Enclosure
    reactor coolant system, and containment) protect the public from radionuclide releases
determined to be more than minor because the finding was associated with the Barrier  
    caused by accidents or events. Specifically, failure to comply with Seismic Category I
Integrity Cornerstone attribute of design control and adversely affected the cornerstone  
    requirements did not ensure the Containment Spray Pipe Support 2S-249 and
objective to provide reasonable assurance that physical design barriers (fuel cladding,  
    Containment Spray Pipe Anchor 2A-35 would function during a Seismic Category I
reactor coolant system, and containment) protect the public from radionuclide releases  
    design basis event and adversely affect the containment spray piping system and
caused by accidents or events. Specifically, failure to comply with Seismic Category I  
    containment barrier.
requirements did not ensure the Containment Spray Pipe Support 2S-249 and  
    The inspectors determined the finding could be evaluated using the Significance
Containment Spray Pipe Anchor 2A-35 would function during a Seismic Category I  
    Determination Process (SDP) in accordance with IMC 0609, Significance Determination
design basis event and adversely affect the containment spray piping system and  
    Process, Attachment 0609.04, Phase 1-Initial Screening and Characterization of
containment barrier.  
    Findings, Table 4a for Barrier Integrity (Containment Barrier). The finding screened as
The inspectors determined the finding could be evaluated using the Significance  
    of very low safety significance (Green) because the inspectors answered no to all four
Determination Process (SDP) in accordance with IMC 0609, Significance Determination  
    questions in the containment barrier column. Specifically, the licensee was able to show
Process, Attachment 0609.04, Phase 1-Initial Screening and Characterization of  
    the Containment Spray Pipe Support 2S-249 and Containment Spray Pipe Anchor 2A-35
Findings, Table 4a for Barrier Integrity (Containment Barrier). The finding screened as  
    were operable but nonconforming.
of very low safety significance (Green) because the inspectors answered no to all four  
    The inspectors determined there was no cross-cutting aspect associated with this finding
questions in the containment barrier column. Specifically, the licensee was able to show  
    because the deficiency was a legacy design calculational issue and, therefore, was not
the Containment Spray Pipe Support 2S-249 and Containment Spray Pipe Anchor 2A-35  
    indicative of licensees current performance.
were operable but nonconforming.  
    Enforcement: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, requires,
The inspectors determined there was no cross-cutting aspect associated with this finding  
    in part, that measures be established to ensure the applicable regulatory requirements
because the deficiency was a legacy design calculational issue and, therefore, was not  
    and the design basis are correctly translated into specifications, drawings, procedures,
indicative of licensees current performance.  
    and instructions. The design control measures shall provide for verifying or checking the
Enforcement: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, requires,  
    adequacy of design.
in part, that measures be established to ensure the applicable regulatory requirements  
    Contrary to the above, as of August 17, 2011, the design control measures failed to
and the design basis are correctly translated into specifications, drawings, procedures,  
    conform to Seismic Category I requirements and also failed to verify the adequacy of the
and instructions. The design control measures shall provide for verifying or checking the  
    design. Specifically, calculation WE-200074 failed to verify the adequacy of the design
adequacy of design.  
    for the Containment Spray Pipe Support 2S-249 and Containment Spray Pipe Anchor
Contrary to the above, as of August 17, 2011, the design control measures failed to  
    2A-35 to ensure it met the Seismic Category I requirements. Because this violation was
conform to Seismic Category I requirements and also failed to verify the adequacy of the  
    of very low safety significance (Green) and it was entered into the licensees corrective
design. Specifically, calculation WE-200074 failed to verify the adequacy of the design  
    action program as AR01678643, this violation is being treated as a Non-Cited Violation,
for the Containment Spray Pipe Support 2S-249 and Containment Spray Pipe Anchor  
    consistent with Section 2.3.2 of the NRC Enforcement Policy (NCV 05000266/2011009-
2A-35 to ensure it met the Seismic Category I requirements. Because this violation was  
    03; 05000301/2011009-03, Containment Spray Pipe Support Deficiencies).
of very low safety significance (Green) and it was entered into the licensees corrective  
(2) Turbine Building Structural Steel Floor Beams did not meet AISC requirements
action program as AR01678643, this violation is being treated as a Non-Cited Violation,  
    Introduction: The inspectors identified a finding of very low safety significance (Green)
consistent with Section 2.3.2 of the NRC Enforcement Policy (NCV 05000266/2011009-
    involving the licensees failure to meet the requirements of American Institute of Steel
03; 05000301/2011009-03, Containment Spray Pipe Support Deficiencies).  
    Construction (AISC) Specifications in the design basis calculation. Specifically, the
    licensee did not ensure the turbine building structural steel floor beams meet the AISC
(2) Turbine Building Structural Steel Floor Beams did not meet AISC requirements  
    specifications. No violations of NRC requirements were identified.
Introduction: The inspectors identified a finding of very low safety significance (Green)  
    Description: Design Bases Calculation 12918709-C-0033, Evaluation of Structural
involving the licensees failure to meet the requirements of American Institute of Steel  
    Steel Turbine Building Operating Floor EL. 44 for Change in Pipe Support Reactions,
Construction (AISC) Specifications in the design basis calculation. Specifically, the  
                                          19                                          Enclosure
licensee did not ensure the turbine building structural steel floor beams meet the AISC  
specifications. No violations of NRC requirements were identified.  
Description: Design Bases Calculation 12918709-C-0033, Evaluation of Structural  
Steel Turbine Building Operating Floor EL. 44 for Change in Pipe Support Reactions,  


Unit 2, Revision 0 evaluated the Turbine Building structural steel floor beams at
Elevation 44-0. The structural steel beams support dead loads, laydown live loads, as
20
well pipe support loads from the main steam and feedwater piping system which are
Enclosure
supported from these beams. The licensee used the American Institute of Steel
Unit 2, Revision 0 evaluated the Turbine Building structural steel floor beams at  
Construction (AISC) standards to demonstrate structural adequacy of the structural steel
Elevation 44-0. The structural steel beams support dead loads, laydown live loads, as  
floor beams. Calculation 129187-C-0033 justified, based on engineering judgment, that
well pipe support loads from the main steam and feedwater piping system which are  
a 5 percent overstressed condition of the turbine building structural steel floor beams
supported from these beams. The licensee used the American Institute of Steel  
was acceptable. Specifically, the licensee stated the maximum interaction ratio (IR)
Construction (AISC) standards to demonstrate structural adequacy of the structural steel  
used for acceptance was less than 1.05. The structure was non-safety-related and the
floor beams. Calculation 129187-C-0033 justified, based on engineering judgment, that  
design uses minimum specified yield strength. The actual yield strength of the steel
a 5 percent overstressed condition of the turbine building structural steel floor beams  
based on mill specification is expected to be higher.
was acceptable. Specifically, the licensee stated the maximum interaction ratio (IR)  
The AISC required the allowable stress to be based on the specified minimum yield
used for acceptance was less than 1.05. The structure was non-safety-related and the  
strength of the material. The licensee used certified material test report strength or
design uses minimum specified yield strength. The actual yield strength of the steel  
actual material yield strength as a basis for an allowable overstress condition (applied
based on mill specification is expected to be higher.  
stress greater than allowable stress) for the evaluation of the turbine building structural
The AISC required the allowable stress to be based on the specified minimum yield  
steel floor beams. The use of actual material yield strength as a basis for an allowable
strength of the material. The licensee used certified material test report strength or  
overstress condition did not meet the AISC requirements. This issue was entered into
actual material yield strength as a basis for an allowable overstress condition (applied  
the licensees corrective action program as AR 01682352, Inadequate Justification for
stress greater than allowable stress) for the evaluation of the turbine building structural  
Non-Compliance.
steel floor beams. The use of actual material yield strength as a basis for an allowable  
Analysis: The inspectors determined the licensees failure to meet AISC requirements
overstress condition did not meet the AISC requirements. This issue was entered into  
for the turbine building structural steel floor beams was a performance deficiency. The
the licensees corrective action program as AR 01682352, Inadequate Justification for  
performance deficiency was determined to be more than minor because the finding was
Non-Compliance.  
associated with the Initiating Events Cornerstone attribute of design control and
Analysis: The inspectors determined the licensees failure to meet AISC requirements  
adversely affected the cornerstone objective to limit the likelihood of those events that
for the turbine building structural steel floor beams was a performance deficiency. The  
upset the plant stability and challenge critical safety functions during shutdown, as well
performance deficiency was determined to be more than minor because the finding was  
as power operations. Specifically, compliance with AISC requirements for the turbine
associated with the Initiating Events Cornerstone attribute of design control and  
building structural steel floor beams ensures the main steam and feedwater piping
adversely affected the cornerstone objective to limit the likelihood of those events that  
system would not be affected during a design basis event. The failure to comply could
upset the plant stability and challenge critical safety functions during shutdown, as well  
impact the piping systems and potentially result in a turbine trip/reactor trip.
as power operations. Specifically, compliance with AISC requirements for the turbine  
The inspectors determined the finding could be evaluated using the Significance
building structural steel floor beams ensures the main steam and feedwater piping  
Determination Process (SDP) in accordance with IMC 0609, Significance Determination
system would not be affected during a design basis event. The failure to comply could  
Process, Attachment 0609.04, Phase I-Initial Screening and Characterization of
impact the piping systems and potentially result in a turbine trip/reactor trip.  
Findings, Table 4a for Initiating Events. The finding screened as of very low safety
The inspectors determined the finding could be evaluated using the Significance  
significance (Green) because the transient initiator would not contribute to both the
Determination Process (SDP) in accordance with IMC 0609, Significance Determination  
likelihood of a reactor trip and the likelihood that mitigation equipment or functions will
Process, Attachment 0609.04, Phase I-Initial Screening and Characterization of  
not be available.
Findings, Table 4a for Initiating Events. The finding screened as of very low safety  
The inspectors determined this finding had a cross-cutting aspect in the area of human
significance (Green) because the transient initiator would not contribute to both the  
performance, work practices because the licensee did not ensure effective supervisory
likelihood of a reactor trip and the likelihood that mitigation equipment or functions will  
and management oversight of work activities, including contractors, such that nuclear
not be available.  
safety was supported. Specifically, the licensee failed to have adequate oversight of
The inspectors determined this finding had a cross-cutting aspect in the area of human  
design calculation and documentation for establishing structural adequacy of the turbine
performance, work practices because the licensee did not ensure effective supervisory  
building structural steel beams at EL. 44-0. [H.4(c)]
and management oversight of work activities, including contractors, such that nuclear  
Enforcement: Since the equipment involved with the performance deficiency were not
safety was supported. Specifically, the licensee failed to have adequate oversight of  
safety-related, there were no violations of NRC regulations associated with this finding
design calculation and documentation for establishing structural adequacy of the turbine  
                                        20                                          Enclosure
building structural steel beams at EL. 44-0. [H.4(c)]  
Enforcement: Since the equipment involved with the performance deficiency were not  
safety-related, there were no violations of NRC regulations associated with this finding  


    (FIN) and as such, no enforcement. (FIN 05000266/2011009-04; 05000301/2011009-
    04, Turbine Building Structural Steel Floor Beams did not meet AISC requirements)
21
4OA6 Meeting(s)
Enclosure
.1 Exit Meeting Summary
(FIN) and as such, no enforcement. (FIN 05000266/2011009-04; 05000301/2011009-
    On September 2, 2011, the inspectors presented the inspection results to Mr. T. Vehec,
04, Turbine Building Structural Steel Floor Beams did not meet AISC requirements)  
    and other members of the licensee staff. The licensee acknowledged the issues
4OA6 Meeting(s)  
    presented. The inspectors asked the licensee whether any materials examined during
.1  
    the inspection should be considered proprietary. Several documents reviewed by the
Exit Meeting Summary  
    inspectors were considered proprietary information and were either returned to the
On September 2, 2011, the inspectors presented the inspection results to Mr. T. Vehec,  
    licensee or handled in accordance with NRC policy on proprietary information.
and other members of the licensee staff. The licensee acknowledged the issues  
4OA7 Licensee-Identified Violations
presented. The inspectors asked the licensee whether any materials examined during  
    The following violation of very low safety significance (Green) was identified by
the inspection should be considered proprietary. Several documents reviewed by the  
    the licensee and was a violation of NRC requirements, which meets the criteria of
inspectors were considered proprietary information and were either returned to the  
    Section VI.A.1 of the NRC Enforcement Policy for being dispositioned as an NCV.
licensee or handled in accordance with NRC policy on proprietary information.  
    *   A finding of very low safety significance (Green) and associated NCV of 10 CFR
4OA7 Licensee-Identified Violations  
        Part 50, Appendix B, Criterion V, Instructions, Procedures and Drawings, was
The following violation of very low safety significance (Green) was identified by  
        identified by the licensee for the failure to ensure adequate instructions were
the licensee and was a violation of NRC requirements, which meets the criteria of  
        adequately prescribed in procedures. Specifically, the licensee failed to ensure the
Section VI.A.1 of the NRC Enforcement Policy for being dispositioned as an NCV.  
        receptacle 2PR-49 listed in Procedure AOP-30, Temporary Ventilation for Vital
*  
        Areas, as one of the three potential power sources for transformer X-71 adequate
A finding of very low safety significance (Green) and associated NCV of 10 CFR  
        for the transformer plug, was acceptable, in that the receptacle and transformer had
Part 50, Appendix B, Criterion V, Instructions, Procedures and Drawings, was  
        difference phase connections. This transformer would be used to power temporary
identified by the licensee for the failure to ensure adequate instructions were  
        fans relied upon for design basis accident and the loss of the normal/fixed
adequately prescribed in procedures. Specifically, the licensee failed to ensure the  
        ventilations in the AFW and switchgear rooms. The performance deficiency was
receptacle 2PR-49 listed in Procedure AOP-30, Temporary Ventilation for Vital  
        determined to be more than minor because it was associated with the Mitigating
Areas, as one of the three potential power sources for transformer X-71 adequate  
        Systems Cornerstone attribute of Equipment Performance, and affected the
for the transformer plug, was acceptable, in that the receptacle and transformer had  
        cornerstone objective of ensuring the availability, reliability, and capability of systems
difference phase connections. This transformer would be used to power temporary  
        that respond to initiating events to prevent undesirable consequences. The SDP
fans relied upon for design basis accident and the loss of the normal/fixed  
        Phase I evaluation concluded the finding screened as of very low safety significance.
ventilations in the AFW and switchgear rooms. The performance deficiency was  
        This issue was entered into the licensees corrective action as AR01652555, as a
determined to be more than minor because it was associated with the Mitigating  
        corrective action, the licensee prepared an EC 271778 to modify the receptacle
Systems Cornerstone attribute of Equipment Performance, and affected the  
        during the next Unit Refueling Outage. The inspectors also noticed procedure AOP-
cornerstone objective of ensuring the availability, reliability, and capability of systems  
        30 still showed 2PR-49 as one of the potential power sources. The inspectors were
that respond to initiating events to prevent undesirable consequences. The SDP  
        concerned there were no compensatory measures in place identifying that this power
Phase I evaluation concluded the finding screened as of very low safety significance.
        source could not be used and also identifying other receptacles in the area that could
This issue was entered into the licensees corrective action as AR01652555, as a  
        be utilized as an interim measure. The licensee entered the inspectors concern into
corrective action, the licensee prepared an EC 271778 to modify the receptacle  
        their corrective action program as AR01682644.
during the next Unit Refueling Outage. The inspectors also noticed procedure AOP-
ATTACHMENT: SUPPLEMENTAL INFORMATION
30 still showed 2PR-49 as one of the potential power sources. The inspectors were  
                                          21                                            Enclosure
concerned there were no compensatory measures in place identifying that this power  
source could not be used and also identifying other receptacles in the area that could  
be utilized as an interim measure. The licensee entered the inspectors concern into  
their corrective action program as AR01682644.  
ATTACHMENT: SUPPLEMENTAL INFORMATION


                                SUPPLEMENTAL INFORMATION
                                  KEY POINTS OF CONTACT
1
Licensee
Attachment
T. Vehec, Plant General Manager
SUPPLEMENTAL INFORMATION  
J. Atkins, Operational Assistant Manager
KEY POINTS OF CONTACT  
S. Brown, Program Engineering Manager
Licensee  
L. Bruster, Engineering
T. Vehec, Plant General Manager  
D. Craine, Radiation Protection Manager
J. Atkins, Operational Assistant Manager  
F. Flentje, Licensing Supervisor
S. Brown, Program Engineering Manager  
V. Kanal, Engineering Supervisor
L. Bruster, Engineering  
T. Kendall, Engineering
D. Craine, Radiation Protection Manager  
J. Kenney, Mechanical Department
F. Flentje, Licensing Supervisor  
J. Lewandowski, Quality Assurance Supervisor
V. Kanal, Engineering Supervisor  
T. Lensmire, Electrical Design Engineering
T. Kendall, Engineering  
A. Mitchell, Performance Improvement Manager
J. Kenney, Mechanical Department  
M. Moran, EPU Engineering manager
J. Lewandowski, Quality Assurance Supervisor  
L. Nicholson, Licensing Director
T. Lensmire, Electrical Design Engineering  
  J. Pierce, Training Assistant Manager
A. Mitchell, Performance Improvement Manager  
B. Scherwinski, Licensing
M. Moran, EPU Engineering manager  
P. Wild, Design Engineering Manager
L. Nicholson, Licensing Director  
B. Woyak, Engineering Supervisor
  J. Pierce, Training Assistant Manager  
Nuclear Regulatory Commission
B. Scherwinski, Licensing  
S. Burton, Senior Resident Inspector
P. Wild, Design Engineering Manager  
B. Woyak, Engineering Supervisor  
Nuclear Regulatory Commission  
S. Burton, Senior Resident Inspector  
M. Thorpe-Kavanaugh, Resident Inspector
M. Thorpe-Kavanaugh, Resident Inspector
                                          1              Attachment


                LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
Opened and Closed
Attachment
05000266/2011009-01;   NCV     Failure to Monitor outside Air Temperature (Section
2
05000301/2011009-01            1R21.3.b (1))
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED  
05000266/2011009-02;   NCV     Failure to Incorporate Minimum AFW Flow Requirement
Opened and Closed  
05000301/2011009-02            into Emergency Procedures (Section 1R21.6.b (1))
05000266/2011009-01;  
05000266/2011009-03;   NCV     Containment Spray Pipe Support Deficiencies (Section
05000301/2011009-01
05000301/2011009-03            4OA5.1.b (1))
NCV  
05000266/2011009-04;   FIN     Turbine Building Structural Steel Floor Beams Did Not Meet
Failure to Monitor outside Air Temperature (Section  
05000301/2011009-04            AISC Requirements (Section 4OA5.1.b (2))
1R21.3.b (1))  
                                          2                                  Attachment
05000266/2011009-02;  
05000301/2011009-02
NCV  
Failure to Incorporate Minimum AFW Flow Requirement  
into Emergency Procedures (Section 1R21.6.b (1))  
05000266/2011009-03;  
05000301/2011009-03
NCV  
Containment Spray Pipe Support Deficiencies (Section  
4OA5.1.b (1))  
05000266/2011009-04;  
05000301/2011009-04
FIN  
Turbine Building Structural Steel Floor Beams Did Not Meet  
AISC Requirements (Section 4OA5.1.b (2))  


                                  LIST OF DOCUMENTS REVIEWED
The following is a list of documents reviewed during the inspection. Inclusion on this list does
Attachment
not imply the NRC inspectors reviewed the documents in their entirety, but rather, that selected
3
sections of portions of the documents were evaluated as part of the overall inspection effort.
LIST OF DOCUMENTS REVIEWED  
Inclusion of a document on this list does not imply NRC acceptance of the document or any part
The following is a list of documents reviewed during the inspection. Inclusion on this list does  
of it, unless this is stated in the body of the inspection report.
not imply the NRC inspectors reviewed the documents in their entirety, but rather, that selected  
  CALCULATIONS
sections of portions of the documents were evaluated as part of the overall inspection effort.
  Number                 Description or Title                                         Revision
Inclusion of a document on this list does not imply NRC acceptance of the document or any part  
  N-93-057               Battery D-06 DC System Sizing, Voltage Drop, and Short             6
of it, unless this is stated in the body of the inspection report.  
                        Circuit Calculations
CALCULATIONS  
  N-93-041               Hydrogen buildup in the Battery Rooms                               3
Number  
  2003-046               Battery Chargers Sizing and Current Limit Set Point                 4
Description or Title  
  P-94-004               MOV Overload Heater Evaluation                                     13
Revision
  P-94-004               MOV Overload Heater Evaluation                                   13C
N-93-057  
  P-89-031               Voltage Drop Across MOV Power Lines                               12
Battery D-06 DC System Sizing, Voltage Drop, and Short  
  N-98-095               Minimum DC Control Voltage Available at CC and TC of               3
Circuit Calculations  
                        Circuit Breakers at 4160 Safety Switchgears and 480 Safety
6
                        Load Centers
N-93-041  
  2009-0027             Cable Ampacity and Voltage Drop for DC Power Cables               0
Hydrogen buildup in the Battery Rooms  
  N-92-005               125 VDC Coordination Analysis                                     2A
3  
  P-90-017               Motor Operated Valve Undervoltage Stem Thrust and Torque           22
2003-046
  97-0231               Auxiliary Feedwater Pump Low Suction Pressure SW                   2
Battery Chargers Sizing and Current Limit Set Point  
                        Switchover and Pump Trip Instrument Loop
4  
                        Uncertainty/Setpoint Calculation
P-94-004  
  97-0231               Auxiliary Feedwater Pump Low Suction Pressure SW               002-B
MOV Overload Heater Evaluation  
                        Switchover and Pump Trip Instrument Loop
13  
                        Uncertainty/Setpoint Calculation
P-94-004  
  PBNP-IC-42             Condensate Storage Tank Water Level Instrument Scaling       Rev 002-
MOV Overload Heater Evaluation
                        and Loop Uncertainty/Setpoint Calculation                         A
13C  
  2008-0024             AFWP Room Flood Basis Calculation                               Rev 0
P-89-031  
  2010-0022             Flow Parameter EOP Setpoints Calculation                       Rev 0
Voltage Drop Across MOV Power Lines  
  2005-0008             Minimum Voltage Requirements for SR MCC Control Circuits           0
12  
  P-94-004               MOV Overload Heater Evaluation                               13 & 13C
N-98-095  
  2004-0009             13.8KV and 4.16KV Protection and Coordination                     2-N
Minimum DC Control Voltage Available at CC and TC of  
  P-90-017               MOV UV Stem Thrust and Torque Calculation                         22
Circuit Breakers at 4160 Safety Switchgears and 480 Safety  
  P-89-031               Voltage Drop Across MOV Power Lines                               12
Load Centers  
  2001-0033             Electrical Input Calc, 345kV - 480V SWGR Circuits                   9
3
  2001-0049             480V Switchgear Coordination and Protection                       2
2009-0027  
  2004-0001             AC Electrical System Analysis - Model Inputs                       9
Cable Ampacity and Voltage Drop for DC Power Cables  
  2004-0002             AC Electrical System Analysis                                     4
0  
  2008-0014             Determination of Power Cable Ampacities and Verification of         0
N-92-005  
                        Overload Protection
125 VDC Coordination Analysis  
  2005-0007             Electrical System Transient Analysis                               3
2A  
                                                    3                                 Attachment
P-90-017  
Motor Operated Valve Undervoltage Stem Thrust and Torque  
22  
97-0231  
Auxiliary Feedwater Pump Low Suction Pressure SW  
Switchover and Pump Trip Instrument Loop  
Uncertainty/Setpoint Calculation  
2
97-0231  
Auxiliary Feedwater Pump Low Suction Pressure SW  
Switchover and Pump Trip Instrument Loop  
Uncertainty/Setpoint Calculation  
002-B
PBNP-IC-42  
Condensate Storage Tank Water Level Instrument Scaling  
and Loop Uncertainty/Setpoint Calculation  
Rev 002-
A  
2008-0024  
AFWP Room Flood Basis Calculation  
Rev 0  
2010-0022  
Flow Parameter EOP Setpoints Calculation  
Rev 0  
2005-0008  
Minimum Voltage Requirements for SR MCC Control Circuits  
0  
P-94-004  
MOV Overload Heater Evaluation  
13 & 13C
2004-0009  
13.8KV and 4.16KV Protection and Coordination  
2-N  
P-90-017  
MOV UV Stem Thrust and Torque Calculation  
22  
P-89-031  
Voltage Drop Across MOV Power Lines  
12  
2001-0033  
Electrical Input Calc, 345kV - 480V SWGR Circuits  
9  
2001-0049  
480V Switchgear Coordination and Protection  
2  
2004-0001  
AC Electrical System Analysis - Model Inputs  
9  
2004-0002  
AC Electrical System Analysis  
4  
2008-0014  
Determination of Power Cable Ampacities and Verification of  
Overload Protection  
0
2005-0007  
Electrical System Transient Analysis  
3  


CALCULATIONS
Number         Description or Title                                       Revision
Attachment
N-94-007       MOV Motor Brake Voltage Evaluation                             0
4
2008-0005     4160/480V Loss of Voltage and Under-Frequency Relay             2
CALCULATIONS  
              Settings
Number  
2003-0014     MOV Operating Parameters                                   6
Description or Title  
2005-0053     Primary Aux Building GOTHIC Temperature Calculation         0
Revision
  2009-06020   Maximum Allowable Working Pressure and Evaluation of       1
N-94-007  
              Valves and Components of the AFW System
MOV Motor Brake Voltage Evaluation  
2009-08450     AFW Air Operated Valves Component Level Calculation         0
0  
2009-06929     AFW Air Operated Valves Functional and MEDP Calculation     0
2008-0005  
2009-06932     Nitrogen or Compressed Air Backup System for MDAFP         1
4160/480V Loss of Voltage and Under-Frequency Relay  
              (1,2-P53) Discharge Valves and Flow Recirc. Valves
Settings  
P-94-005       MOV Stem Thrust Calculation                                 11
2
97-0231       AFW Pump Low Suction Pressure SW Switchover and Pump       2
2003-0014  
              Trip Inst. Loop Uncertainty/Setpoint Calc
MOV Operating Parameters  
2010-0010     AFW Low-Low-Low SW Switchover Instrument Loop               0
6  
              Unc/Setpoint Calc.,
2005-0053  
WEP-SPT-33     AFW Flow Indication Uncertainty                             4
Primary Aux Building GOTHIC Temperature Calculation  
CN-CPS-07-6   Point Beach S/G Narrow Range Level Instr. Uncertainty and   3
0  
              Setpoint Calc. as Modified to Reflect Operations at Pre EPU
  2009-06020  
              and Post EPU Conditions (IC-25)
Maximum Allowable Working Pressure and Evaluation of  
CN-TA-08-79   Point Beach Units 1 and 2 Loss of Normal Feedwater/Loss of 1
Valves and Components of the AFW System  
              AC Power (LONF/LOAC) Analysis for the EPU Program
1
CN-CRA-08-40   SGTR Thermal Hydraulic Input to Dose Analysis for Point     0
2009-08450  
              Beach Units 1 and 2 to Support EPU
AFW Air Operated Valves Component Level Calculation  
CN-CRA-08-10   Point Beach EPU Steam Line Break Inside Containment         1
0  
              Mass/Energy Release
2009-06929  
2003-0062     AFW Pump NPSH Calculation and CST Volume Required to       2-B
AFW Air Operated Valves Functional and MEDP Calculation  
              Prevent Vortexing
0  
2009-06582     Available Water in Volume of Piping in Protected Portion of 0
2009-06932  
              MDAFW Pump Suction
Nitrogen or Compressed Air Backup System for MDAFP  
S-11165-116-05 AFW Pump Anchorage Design and Foundation Analysis           1
(1,2-P53) Discharge Valves and Flow Recirc. Valves  
96-0244       Minimum Allowable IST Acceptance Criteria for TDAFW and     3
1
              MDAFW Pump Performance
P-94-005  
N-94-019       Determination of Conditions for MOV Pressure Locking and   000-B
MOV Stem Thrust Calculation  
              Thermal Binding
11  
2005-0054     Control Building GOTHIC Temperature Calculation                 1
97-0231  
WE-300089     MDAFW Pump Suction Piping from CSTs T-24A and T-24B             0
AFW Pump Low Suction Pressure SW Switchover and Pump  
              to Anchor
Trip Inst. Loop Uncertainty/Setpoint Calc  
WE-300090     MDAFW Common Recirculation Piping from CST to Anchor           00-A
2
              HD-8-026-3A
2010-0010  
WE-300089     MDAFW Common Suction Piping from CST's to Anchor               00-A
AFW Low-Low-Low SW Switchover Instrument Loop  
              HD-8-049-3A
Unc/Setpoint Calc.,  
                                          4                                Attachment
0
WEP-SPT-33
AFW Flow Indication Uncertainty  
4  
CN-CPS-07-6
Point Beach S/G Narrow Range Level Instr. Uncertainty and  
Setpoint Calc. as Modified to Reflect Operations at Pre EPU  
and Post EPU Conditions (IC-25)  
3
CN-TA-08-79  
Point Beach Units 1 and 2 Loss of Normal Feedwater/Loss of  
AC Power (LONF/LOAC) Analysis for the EPU Program  
1
CN-CRA-08-40  
SGTR Thermal Hydraulic Input to Dose Analysis for Point  
Beach Units 1 and 2 to Support EPU  
0
CN-CRA-08-10  
Point Beach EPU Steam Line Break Inside Containment  
Mass/Energy Release  
1
2003-0062  
AFW Pump NPSH Calculation and CST Volume Required to  
Prevent Vortexing
2-B  
2009-06582  
Available Water in Volume of Piping in Protected Portion of  
MDAFW Pump Suction  
0
S-11165-116-05  
AFW Pump Anchorage Design and Foundation Analysis  
1  
96-0244  
Minimum Allowable IST Acceptance Criteria for TDAFW and  
MDAFW Pump Performance  
3
N-94-019  
Determination of Conditions for MOV Pressure Locking and  
Thermal Binding
000-B  
2005-0054  
Control Building GOTHIC Temperature Calculation  
1  
WE-300089  
MDAFW Pump Suction Piping from CSTs T-24A and T-24B  
to Anchor  
0
WE-300090  
MDAFW Common Recirculation Piping from CST to Anchor  
HD-8-026-3A  
00-A
WE-300089  
MDAFW Common Suction Piping from CST's to Anchor  
HD-8-049-3A  
00-A


CALCULATIONS
Number         Description or Title                                           Revision
Attachment
WE-200052     Auxiliary Feedwater System from Structural Anchors             00-B/C/D
5
              DB3-2H7 and DB3-2H4 to Containment Penetration P5
CALCULATIONS  
              (EB10-A13)
Number  
WE-200051S     Emergency FW from Penet. P-5 & 6 to Anchors H-11, 2H2,           00-C
Description or Title  
              2H4 & 2H7
Revision
S-11165-116-07 Pipe Support Qualification for AFW Margin Improvements             1
WE-200052  
129187-P-0011 Unit 2, Main Steam outside Containment - Piping                   6
Auxiliary Feedwater System from Structural Anchors  
              Qualification for Extended Power Uprate Conditions
DB3-2H7 and DB3-2H4 to Containment Penetration P5  
129187-P-0018 Unit 2, Fedwater outside Containment - Piping Qualification       6
(EB10-A13)  
              for Extended Power Uprate Conditions
00-B/C/D
PBNP-994-21-   HELB Reconstitution Program - Task 6 Break and Crack               2
WE-200051S  
06            Size/Location Selection
Emergency FW from Penet. P-5 & 6 to Anchors H-11, 2H2,  
129187-C-0055 Evaluation of Main Steam Pipe Supporting Structure of Unit         0
2H4 & 2H7  
              #2 Façade and Turbine Buildings for Changes in Pipe
00-C
              Support Reactions Associated with Uprate Conditions (EC-
S-11165-116-07  
              12070)
Pipe Support Qualification for AFW Margin Improvements  
129187-C-0054 Evaluations of Pipe Supporting Structures of Unit #2 Auxiliary     0
1  
              Building for Changes in Pipe Support Reactions Associated
129187-P-0011  
              with Uprate Conditions
Unit 2, Main Steam outside Containment - Piping  
12918709-C-   Evaluation of Main Steam and Feedwater Pipe Supporting             0
Qualification for Extended Power Uprate Conditions  
0052          Structures of Unit 2 Containment Building for Changes in
6
              Pipe Support Reactions
129187-P-0018  
12918709-C-   Evaluation of Structural Steel Turbine Building Operating         0
Unit 2, Fedwater outside Containment - Piping Qualification  
0033          Floor EL. 44 for Change in Pipe Support Reactions, Unit 2
for Extended Power Uprate Conditions  
129187-C-0080 Corrective Action Report of Structural Steel Turbine Building     0
6
              Operating Floor EL. 44 for Legacy Issue, Unit 2
PBNP-994-21-
WE-200074     Subsystem 6-SI-301R-1: Containment Spray System from             1
06
              Containment Penetration P-54 to Anchors 2A-34 and 2A-35
HELB Reconstitution Program - Task 6 Break and Crack  
WE-300048     Subsystem AC-601R/SI-151R: Suction Piping from RWST to           0-H
Size/Location Selection  
              SI, CS and RHR
2
WE-200040     Containment Spray Pump 2-P14A Discharge to P-54                   0-A
129187-C-0055  
WE-200074     Subsystem 6-SI-301R-1: Containment Spray System from             1-C
Evaluation of Main Steam Pipe Supporting Structure of Unit  
              Containment Penetration P-54 to Anchors 2A-34 and 2A-35
#2 Façade and Turbine Buildings for Changes in Pipe  
WE-200104     Subsystem AC-601R/SI-151R: Suction Piping from RWST to           0-F
Support Reactions Associated with Uprate Conditions (EC-
              Safety Injection, Containment Spray and RHR Pumps
12070)  
WE-200073     Subsystem 6-SI-301R-1: Containment Spray System from             1-C
0
              Containment Penetration P-55 to Anchors 2A-36 and 2A-37
129187-C-0054  
WE-100092     Containment Spray System Line 3-SI-301R-1 between               0-A
Evaluations of Pipe Supporting Structures of Unit #2 Auxiliary  
              Anchors 1A-34 and 1A-35
Building for Changes in Pipe Support Reactions Associated  
WE-100093     Subsystem 6-SI-301R-1-9: Containment Spray System               0-D
with Uprate Conditions  
              from Containment Penetration P-55 to Anchors 1A-34 and
0
              1A-35
12918709-C-
                                          5                                  Attachment
0052
Evaluation of Main Steam and Feedwater Pipe Supporting  
Structures of Unit 2 Containment Building for Changes in  
Pipe Support Reactions  
0
12918709-C-
0033
Evaluation of Structural Steel Turbine Building Operating  
Floor EL. 44 for Change in Pipe Support Reactions, Unit 2  
0
129187-C-0080  
Corrective Action Report of Structural Steel Turbine Building  
Operating Floor EL. 44 for Legacy Issue, Unit 2  
0
WE-200074  
Subsystem 6-SI-301R-1: Containment Spray System from  
Containment Penetration P-54 to Anchors 2A-34 and 2A-35  
1
WE-300048  
Subsystem AC-601R/SI-151R: Suction Piping from RWST to  
SI, CS and RHR  
0-H
WE-200040  
Containment Spray Pump 2-P14A Discharge to P-54  
0-A  
WE-200074  
Subsystem 6-SI-301R-1: Containment Spray System from  
Containment Penetration P-54 to Anchors 2A-34 and 2A-35  
1-C
WE-200104  
Subsystem AC-601R/SI-151R: Suction Piping from RWST to  
Safety Injection, Containment Spray and RHR Pumps  
0-F
WE-200073  
Subsystem 6-SI-301R-1: Containment Spray System from  
Containment Penetration P-55 to Anchors 2A-36 and 2A-37  
1-C
WE-100092  
Containment Spray System Line 3-SI-301R-1 between  
Anchors 1A-34 and 1A-35  
0-A
WE-100093  
Subsystem 6-SI-301R-1-9: Containment Spray System  
from Containment Penetration P-55 to Anchors 1A-34 and  
1A-35  
0-D


CORRECTIVE ACTION DOCUMENTS GENERATED DUE TO THE INSPECTION
Number     Description or Title                                       Date
Attachment
AR01674251 Anti-Sweat Insulation Found Removed                       8/02/11
6
AR01674327 Fire Hose Staged Between CSTs for Unknown Activity       8/02/11
CORRECTIVE ACTION DOCUMENTS GENERATED DUE TO THE INSPECTION  
AR01674473 OM 3.27 to NP 1.9.6 Process to Process GAP               8/03/11
Number  
AR01674481 No Temporary Information Tag on Cubical 2B2-427M
Description or Title  
AR01674616 Miscellaneous Parts Attached to Body of 2AF-4073         8/03/11
Date  
AR01674696 Error Identified in Calculation N-93-057                 8/03/11
AR01674251  
AR01674699 Damaged Wiring in Plant for Excessively Long Time         8/03/11
Anti-Sweat Insulation Found Removed  
AR01674726 NRC Comments on AR Operability Screening                 8/03/11
8/02/11  
AR01674739 PBNP Response to Prairie Island OE32688                   8/03/11
AR01674327  
AR01674806 TSB 3.7.5 Potential Changes During FSAR Revisions         8/04/11
Fire Hose Staged Between CSTs for Unknown Activity  
AR01675019 Temporary Storage Tag Missing                             8/04/11
8/02/11  
AR01675023 During a Wlakdown with CDBI NRC Inspectors, Noted two
AR01674473  
            Instances That are in Question
OM 3.27 to NP 1.9.6 Process to Process GAP  
AR01675066 RMP 9353 Question by NRC                                 8/04/11
8/03/11  
AR01675074 Emergency Lighting                                       8/04/11
AR01674481  
AR01675094 D-105 Intertier Connection Cable Bend Radios             8/04/11
No Temporary Information Tag on Cubical 2B2-427M  
AR01675253 CL-13E Part 2 Inconsistencies                             8/05/11
AR01675812 CL 13E Part2 AFW Valve Lineup Motor Drive                 8/08/11
AR01674616  
AR01676059 125 Vdc Fuse Issue                                       8/08/11
Miscellaneous Parts Attached to Body of 2AF-4073  
AR01677153 Calculation for Vital 120 Vac System                     8/11/11
8/03/11  
AR01677805 Error in Control Circuit Voltage Drop                     8/15/11
AR01674696  
AR01677914 Inadequate Documentation of Containment Dome Truss       8/15/11
Error Identified in Calculation N-93-057  
AR01678123 Lack of Basis Documented in Calculation 2004-0002         8/16/11
8/03/11  
AR01678283 2SAF-4000 Thermal Overload Testing                       8/16/11
AR01674699  
AR01678285 Preventive Maintenance for 2SAF-4000                     8/16/11
Damaged Wiring in Plant for Excessively Long Time  
AR01678535 Discrepancy in 125 Vdc Drawing                           8/17/11
8/03/11  
AR01678638 Evaluate ERG Setpoint Deviation for AFW Flow Setpoint in 8/17/11
AR01674726  
            EOP
NRC Comments on AR Operability Screening  
AR01678643  Overstress of Pipe Support Analyzed in WE-200074         8/17/11
8/03/11  
AR01679081 New EOP Setpoint for AFW Flow During LONF/LOCA Events     8/18/11
AR01674739  
AR01679387 IT 08A and IT 09A Note Require Update                     8/19/11
PBNP Response to Prairie Island OE32688  
AR01679408 CR for Tracking Priority 1 PCR 01678831 Unit 2           8/19/11
8/03/11  
AR01679412 CR for Tracking Priority 1 PCR 01678829 Unit 1           8/19/11
AR01674806  
AR01679758 Issue Identified in Calculation P-94-004                 8/22/11
TSB 3.7.5 Potential Changes During FSAR Revisions
AR01679907 ARB C01 A-2-9 T-24A/B Condensate Storage Tanks Level     8/22/11
8/04/11  
AR01680185 TLB 34 Condensate Storage Tank T-24A/B                   8/23/11
AR01675019  
AR01680201 ICP 13.009-2 Condensate Storage Tank Loop Instrument 18   8/23/11
Temporary Storage Tag Missing  
            Months
8/04/11  
AR01680705  Need to Add Operator Action to Logs                       8/24/11
AR01675023  
AR01680951 Possible Error Trap in Calculations                       8/25/11
During a Wlakdown with CDBI NRC Inspectors, Noted two  
AR01681176 CST Low Level Alarm Setpoint have Procedure Issues       8/25/11
Instances That are in Question  
AR01681178 Incorrect Snubber Capacity used in EPU Calculation       8/25/11
                                          6                        Attachment
AR01675066  
RMP 9353 Question by NRC  
8/04/11  
AR01675074  
Emergency Lighting  
8/04/11  
AR01675094  
D-105 Intertier Connection Cable Bend Radios  
8/04/11  
AR01675253  
CL-13E Part 2 Inconsistencies  
8/05/11  
AR01675812  
CL 13E Part2 AFW Valve Lineup Motor Drive  
8/08/11  
AR01676059  
125 Vdc Fuse Issue  
8/08/11  
AR01677153  
Calculation for Vital 120 Vac System  
8/11/11  
AR01677805  
Error in Control Circuit Voltage Drop  
8/15/11  
AR01677914  
Inadequate Documentation of Containment Dome Truss  
8/15/11  
AR01678123  
Lack of Basis Documented in Calculation 2004-0002  
8/16/11  
AR01678283  
2SAF-4000 Thermal Overload Testing  
8/16/11  
AR01678285  
Preventive Maintenance for 2SAF-4000  
8/16/11  
AR01678535  
Discrepancy in 125 Vdc Drawing  
8/17/11  
AR01678638  
Evaluate ERG Setpoint Deviation for AFW Flow Setpoint in  
EOP
8/17/11  
AR01678643
Overstress of Pipe Support Analyzed in WE-200074  
8/17/11  
AR01679081  
New EOP Setpoint for AFW Flow During LONF/LOCA Events  
8/18/11  
AR01679387  
IT 08A and IT 09A Note Require Update  
8/19/11  
AR01679408  
CR for Tracking Priority 1 PCR 01678831 Unit 2  
8/19/11  
AR01679412  
CR for Tracking Priority 1 PCR 01678829 Unit 1  
8/19/11  
AR01679758  
Issue Identified in Calculation P-94-004  
8/22/11  
AR01679907  
ARB C01 A-2-9 T-24A/B Condensate Storage Tanks Level  
8/22/11  
AR01680185  
TLB 34 Condensate Storage Tank T-24A/B  
8/23/11  
AR01680201  
ICP 13.009-2 Condensate Storage Tank Loop Instrument 18  
Months
8/23/11  
AR01680705
Need to Add Operator Action to Logs  
8/24/11  
AR01680951  
Possible Error Trap in Calculations  
8/25/11  
AR01681176  
CST Low Level Alarm Setpoint have Procedure Issues  
8/25/11  
AR01681178  
Incorrect Snubber Capacity used in EPU Calculation  
8/25/11  


CORRECTIVE ACTION DOCUMENTS GENERATED DUE TO THE INSPECTION
Number     Description or Title                                           Date
Attachment
AR01682352 Inadequate Justification for non-compliance                   8/30/11
7
AR01682644 Issues Identified with AOP-30                                 8/31/11
CORRECTIVE ACTION DOCUMENTS GENERATED DUE TO THE INSPECTION  
AR01682729 Process Issues with Procedure Changes for CST Level           8/31/11
Number  
            Setpoint
Description or Title  
CORRECTIVE ACTION DOCUMENTS REVIEWED DURING THE INSPECTION
Date  
Number       Description or Title                                           Date
AR01682352  
AR 01232138 Comments on 125VDC Vendor Calc.s After Owners Review       08/12/03
Inadequate Justification for non-compliance  
AR 01311121 Equipment Outside Short Circuit Rating                       01/19/07
8/30/11  
AR 01394317 2010 NRC URI-Inverter Transfers to Alt Power During Test     08/07/10
AR01682644  
AR01612401   480V SWGR Coordination Recommended Settings
Issues Identified with AOP-30  
            not implemented
8/31/11  
AR01334024   IN 2007-34 Review for applicability                         12/17/07
AR01682729  
AR01315278   IN 2006-31 Review for applicability                         04/04/07
Process Issues with Procedure Changes for CST Level  
AR01347091   LOV relays may trip during grid faults
Setpoint
AR01657810   2B-04 Was De-energized on overcurrent
8/31/11  
AR01281343   Calculated SC Exceed Equipment Ratings and Capabilities
AR01281432   Potential Protective Device Tripping for LOCA with degraded
CORRECTIVE ACTION DOCUMENTS REVIEWED DURING THE INSPECTION  
            voltage
Number  
AR01047353   2006 CDBI Violation - OPR153 did not address Seismic event
Description or Title  
            for identified condition
Date  
AR01303493   2006 CDBI Violation - Calculated SC exceeds equipment       09/21/06
AR 01232138  
            ratings
Comments on 125VDC Vendor Calc.s After Owners Review  
AR01302261  2006 CDBI Violation - Calculated SC exceeds equipment       08/30/06
08/12/03  
            ratings
AR 01311121  
AR01226467  Cable Overload Protection for existing design not documented
Equipment Outside Short Circuit Rating  
AR01331133   Cable Overload Commitments
01/19/07  
AR01366948   1P-29 TDAFP Outboard Bearing Reached Alert Alarm             06/15/09
AR 01394317  
AR01371971   1P-29 Turbine Outboard Bearing Temp High                     09/15/09
2010 NRC URI-Inverter Transfers to Alt Power During Test  
AR01379586   1P-29 TDAFW Pump Outboard Turbine bearing Temp High         01/04/10
08/07/10  
AR01392619   1P-29 Turbine Outboard Bearing High Temp Alarm               07/12/10
AR01612401  
AR01397577   Engineering Evaluation for 1P-29 Temperature Alert           10/04/10
480V SWGR Coordination Recommended Settings  
AR01607140   1TR-2000B PT 19 1P-29 Temperature High Alarm                 01/10/11
not implemented  
AR01652555   Test Cables in CSR and 2PR-49 Usability Issue               05/17/11
AR01661563   Pump Secured Due to Outbrd Turb Bearing Temp > 250           06/16/11
AR01334024  
            Degrees F
IN 2007-34 Review for applicability  
AR01669101  Potential Overstresses Beams at EL. 26 of U2 Turbine         7/13/11
12/17/07  
            Building
AR01315278  
AR01402167  Calculation 12918709-C-0033 Rev. 1 Existing Conditions       12/21/10
IN 2006-31 Review for applicability  
                                          7                              Attachment
04/04/07  
AR01347091  
LOV relays may trip during grid faults  
AR01657810  
2B-04 Was De-energized on overcurrent  
AR01281343  
Calculated SC Exceed Equipment Ratings and Capabilities  
AR01281432  
Potential Protective Device Tripping for LOCA with degraded  
voltage  
AR01047353  
2006 CDBI Violation - OPR153 did not address Seismic event  
for identified condition  
AR01303493  
2006 CDBI Violation - Calculated SC exceeds equipment  
ratings
09/21/06  
AR01302261
2006 CDBI Violation - Calculated SC exceeds equipment  
ratings
08/30/06  
AR01226467
Cable Overload Protection for existing design not documented  
AR01331133  
Cable Overload Commitments  
AR01366948  
1P-29 TDAFP Outboard Bearing Reached Alert Alarm  
06/15/09  
AR01371971  
1P-29 Turbine Outboard Bearing Temp High  
09/15/09  
AR01379586  
1P-29 TDAFW Pump Outboard Turbine bearing Temp High  
01/04/10  
AR01392619  
1P-29 Turbine Outboard Bearing High Temp Alarm  
07/12/10  
AR01397577  
Engineering Evaluation for 1P-29 Temperature Alert  
10/04/10  
AR01607140  
1TR-2000B PT 19 1P-29 Temperature High Alarm  
01/10/11  
AR01652555  
Test Cables in CSR and 2PR-49 Usability Issue  
05/17/11  
AR01661563  
Pump Secured Due to Outbrd Turb Bearing Temp > 250  
Degrees F
06/16/11  
AR01669101
Potential Overstresses Beams at EL. 26 of U2 Turbine  
Building
7/13/11  
AR01402167
Calculation 12918709-C-0033 Rev. 1 Existing Conditions  
12/21/10  


DRAWINGS
   
Number              Description or Title                                Revision
Attachment
6118 E-6, Sheet 1  125V DC Dist. System                                    55
6118 E-6, Sheet 2 125 V DC System                                        19
499B4676, Sheet 840 Elementary Wiring Diagram Turbine Driven Auxiliary      01
                    Feedwater Pump Discharge Valve 2AF-4001
499B466, Sheet 863  Elementary Wiring Diagram 2P-29 Auxiliary Feed Pump    14
                    Suction from Service Water Supply
499B466, Sheet 867  Elementary Wiring Diagram Turbine Driven Auxiliary      15
                    Feedwater Pump Discharge Valve 2AF-4000
499B466, Sheet 1803 Elementary Wiring Diagram Condensate Storage Tank      00
                    AFW Suction Valve Control
499B466, Sheet 899  Elementary Wiring Diagram 2P-053 AFW Pump Service      00
                    Water Suction Valve 2AF-4067
499B466, Sheet 744  Elementary Wiring Diagram Turbine Driven Auxiliary      06
                    Feedwater Trip/Throttle Valve 2Ms-02082
62550 CD2-15-1      Connection Diagram Rack 2C173B-F/2C-197                02
6118 M-2217        P&ID Auxiliary Feedwater System                        02
6118 M-217, Sh 1    P&ID Auxiliary Feedwater System                        94
6118 M-217, Sh 2    P&ID Auxiliary Feedwater System                        25
E-98, Sheet 50D    Panel Schedule 125V DC Panel D-28 (D-40)                12
6704-D-323115      Schematic Diagram 4160V Swgr Bus 1-A06 (2-A06)          13
                    Output Breaker 1A52-86 (2A52-87) from Diesel
                    Generator G-04 (G-03)
6704-D-323101      Schematic Diagram 4160V Swgr Bus 1-A06 (2-A06)          15
                    Output Breaker 1A52-80 (2A52-93) from Diesel
                    Generator G-03 (G-04)
EPB02EAPW128002    Three Line Diagram - 2A06 and EDG G-04                  9
09
EPB02EAPK0000013    480V One Line Diagram, 2B03/2B04                        30
0
EPB01EAPS2400010    Schematic 4160V 1A05                                    8
8
8
EPB02EAPK2400011   Schematic 4160V 2A05                                   12
DRAWINGS
2
Number
EPB02EAPK1660021    One Line Diagram MCC 2B42                               11
Description or Title
5
Revision
PB07322            Simplified Electrical Power Distribution Single Line     1
6118 E-6, Sheet 1
PB07322             Simplified Electrical Power Distribution                 1
125V DC Dist. System
018995             P&ID Service Water                                     77
55
019016             P&ID Auxiliary Feedwater System                         94
6118 E-6, Sheet 2
275460             P&ID Auxiliary Feedwater System                         20
125 V DC System
                                          8                            Attachment
19
499B4676, Sheet 840 Elementary Wiring Diagram Turbine Driven Auxiliary
Feedwater Pump Discharge Valve 2AF-4001
01
499B466, Sheet 863
Elementary Wiring Diagram 2P-29 Auxiliary Feed Pump
Suction from Service Water Supply
14
499B466, Sheet 867
Elementary Wiring Diagram Turbine Driven Auxiliary
Feedwater Pump Discharge Valve 2AF-4000
15
499B466, Sheet 1803 Elementary Wiring Diagram Condensate Storage Tank
AFW Suction Valve Control
00
499B466, Sheet 899
Elementary Wiring Diagram 2P-053 AFW Pump Service
Water Suction Valve 2AF-4067
00
499B466, Sheet 744
Elementary Wiring Diagram Turbine Driven Auxiliary
Feedwater Trip/Throttle Valve 2Ms-02082
06
62550 CD2-15-1
Connection Diagram Rack 2C173B-F/2C-197
02
6118 M-2217
P&ID Auxiliary Feedwater System
02
6118 M-217, Sh 1
P&ID Auxiliary Feedwater System
94
6118 M-217, Sh 2
P&ID Auxiliary Feedwater System
25
E-98, Sheet 50D
Panel Schedule 125V DC Panel D-28 (D-40)
12
6704-D-323115
Schematic Diagram 4160V Swgr Bus 1-A06 (2-A06)
Output Breaker 1A52-86 (2A52-87) from Diesel
Generator G-04 (G-03)
13
6704-D-323101
Schematic Diagram 4160V Swgr Bus 1-A06 (2-A06)
Output Breaker 1A52-80 (2A52-93) from Diesel
Generator G-03 (G-04)
15
EPB02EAPW128002
09
Three Line Diagram - 2A06 and EDG G-04
9
EPB02EAPK0000013
0
480V One Line Diagram, 2B03/2B04
30
EPB01EAPS2400010
8
Schematic 4160V 1A05
8
EPB02EAPK2400011
2
Schematic 4160V 2A05  
12  
EPB02EAPK1660021
5
One Line Diagram MCC 2B42  
11  
PB07322
Simplified Electrical Power Distribution Single Line  
1  
PB07322  
Simplified Electrical Power Distribution  
1  
018995  
P&ID Service Water  
77  
019016  
P&ID Auxiliary Feedwater System  
94  
275460  
P&ID Auxiliary Feedwater System  
20  


MISCELLANEOUS
Number               Description or Title                               Date or
Attachment
                                                                        Revision
9
WO 00370104         DC Starter Verification & TOL Test for 2SMS-2019,   04/10/20
MISCELLANEOUS
                    2SAF-4001 and 2SAF-4006                               11
Number  
WO 40061953-01       ICP 6.6 Service Water Instrumentation - Controlled
Description or Title  
WO 40061953-02       ICP 6.6 Service Water Instrumentation - Clean Side
Date or  
345KV               System Health Report                               06/30/11
Revision  
U1/2 4160V           System Health Report                               06/30/11
WO 00370104  
U1/2 480V           System Health Report                               06/30/11
DC Starter Verification & TOL Test for 2SMS-2019,  
OPR00153             Calculated SC currents exceed equipment ratings         1
2SAF-4001 and 2SAF-4006
DBD-22               Design Basis Document - 4160VAC System                 5
04/10/20
DBD-21               Design Basis Document - 480VAC System                   5
11  
SE 2008-021         Creation of Procedures for Supplemental Ventilation 04/03/09
WO 40061953-01  
Spec No. 6118-M-37   Turbine Building Feed Water Pump Room Ventilation       1
ICP 6.6 Service Water Instrumentation - Controlled  
                    Unit (Stand By) W-46
MODIFICATIONS
WO 40061953-02  
Number           Description or Title                                   Date or
ICP 6.6 Service Water Instrumentation - Clean Side  
                                                                        Revision
EC 16640         MOV Capacity during LOOP/LOCA                               0
345KV  
MR 02-039* A/B   Aux Feed Water Pump 2-29 Recirculation Line Orifice     03/08/03
System Health Report  
EC 12070         Unit 2 Main Steam and Feedwater Pipe Supports               0
06/30/11  
EC 11795         Unit 2 Containment Spray Piping Supports                   0
U1/2 4160V  
                                            9                            Attachment
System Health Report  
06/30/11  
U1/2 480V  
System Health Report  
06/30/11  
OPR00153  
Calculated SC currents exceed equipment ratings  
1  
DBD-22  
Design Basis Document - 4160VAC System  
5  
DBD-21  
Design Basis Document - 480VAC System  
5  
SE 2008-021  
Creation of Procedures for Supplemental Ventilation  
04/03/09  
Spec No. 6118-M-37  
Turbine Building Feed Water Pump Room Ventilation  
Unit (Stand By) W-46  
1
MODIFICATIONS
Number  
Description or Title  
Date or  
Revision  
EC 16640  
MOV Capacity during LOOP/LOCA  
0  
MR 02-039* A/B  
Aux Feed Water Pump 2-29 Recirculation Line Orifice  
03/08/03  
EC 12070  
Unit 2 Main Steam and Feedwater Pipe Supports  
0  
EC 11795  
Unit 2 Containment Spray Piping Supports  
0  


PROCEDURES
Number       Description or Title                                     Revision
Attachment
RMP 9046-2   Station Battery Individual Cell Charging                   13
10
NP 8.4.13     Fuse Replacement                                             8
PROCEDURES
2ICP 04.003-5 Auxiliary Feedwater Flow and Pressure Instruments           16
Number  
              Outage Calibration
Description or Title  
2ICP 02.031   2P-53 Motor Driven Auxiliary Feedwater Suction Header       0
Revision  
              Pressure Trip Channel Operability Test
RMP 9046-2  
AOP-13C       Severe Weather Conditions                                 Rev 22
Station Battery Individual Cell Charging  
ICP06.006     Service Water System Non-Outage Instruments               Rev 11
13  
              Calibrations
NP 8.4.13  
NP 5.2.6     FSAR Maintenance                                         Rev 14
Fuse Replacement  
NP 5.2.15     Technical Specification Bases Control                     Rev 11
8  
FP-E-MOD-03   Temporary Modifications                                   Rev 9
2ICP 04.003-5  
BG-ECA-2.1   Uncontrolled Depressuratization of Both Steam Generators Rev 33
Auxiliary Feedwater Flow and Pressure Instruments  
2ICP 02.031   2P-53 Motor Driven Auxiliary Feedwater Suction Header     Rev 0
Outage Calibration  
              Pressure Trip Channel Operability Test
16
TLB 34       Tank Level Book - Condensate Storage Tank T-24           Rev 9
2ICP 02.031  
2RMP 9133     Motor Driven and Turbine Drive Auxiliary Feedwater Pump   Rev 15
2P-53 Motor Driven Auxiliary Feedwater Suction Header  
              Start on Bus A-01 and A-02 Undervoltage Refuel
Pressure Trip Channel Operability Test  
              Calibration
0
STPT 25.1     Emergency Operating Procedure (EOP) Setpoints             Rev 4
AOP-13C  
NP 1.9.6     Plant Cleanliness and Storage                             Rev 36
Severe Weather Conditions  
ORT 3C       Auxiliary Feedwater System and AMSAC Actuation Unit 2     Rev 16
Rev 22  
TS 87         Primary Auxiliary Building Ventilation System Monthly     Rev 2
ICP06.006  
              Checks
Service Water System Non-Outage Instruments  
STPT 14.11   Auxiliary Feedwater Setpoint Document                     Rev 23
Calibrations
EOP-0         Reactor Trip of Safety Injection
Rev 11  
EOP-0.1       Reactor Trip Response                                     Rev 38
NP 5.2.6  
EOP-1         Loss of Reactor or Secondary Coolant
FSAR Maintenance  
EOP-1.1       SI Termination
Rev 14  
EOP-1.2       Post LOCA Cooldown and Depressurization
NP 5.2.15  
EOP-2         Faulted Steam Generator
Technical Specification Bases Control  
EOP-3         Steam Generator Tube Rupture
Rev 11  
EOP-3.1       Post-SGTR Cooldown using Backfill
FP-E-MOD-03  
ECA-0.0       Loss of All AC Power                                     Rev 56
Temporary Modifications  
ECA-1.1       Loss of Emergency Coolant Recirculation
Rev 9  
ECA-1.2       LOCA Outside Containment
BG-ECA-2.1  
ECA-1.3       Containment Sump Blockage
Uncontrolled Depressuratization of Both Steam Generators  
CSP-S.1       Response to Nuclear Power Generation/ATWS
Rev 33  
AOP-10A       Safe Shutdown - Local Control
2ICP 02.031  
RMP 9366     50VCP-WR350 4.16KV Vacuum Breaker Routine                   18
2P-53 Motor Driven Auxiliary Feedwater Suction Header  
              Maintenance
Pressure Trip Channel Operability Test  
                                      10                              Attachment
Rev 0
TLB 34  
Tank Level Book - Condensate Storage Tank T-24  
Rev 9  
2RMP 9133  
Motor Driven and Turbine Drive Auxiliary Feedwater Pump  
Start on Bus A-01 and A-02 Undervoltage Refuel  
Calibration  
Rev 15
STPT 25.1  
Emergency Operating Procedure (EOP) Setpoints  
Rev 4  
NP 1.9.6  
Plant Cleanliness and Storage  
Rev 36  
ORT 3C  
Auxiliary Feedwater System and AMSAC Actuation Unit 2  
Rev 16  
TS 87  
Primary Auxiliary Building Ventilation System Monthly  
Checks
Rev 2  
STPT 14.11  
Auxiliary Feedwater Setpoint Document  
Rev 23  
EOP-0  
Reactor Trip of Safety Injection  
EOP-0.1  
Reactor Trip Response  
Rev 38  
EOP-1  
Loss of Reactor or Secondary Coolant  
EOP-1.1  
SI Termination  
EOP-1.2  
Post LOCA Cooldown and Depressurization  
EOP-2  
Faulted Steam Generator  
EOP-3
Steam Generator Tube Rupture  
EOP-3.1  
Post-SGTR Cooldown using Backfill  
ECA-0.0  
Loss of All AC Power  
Rev 56  
ECA-1.1  
Loss of Emergency Coolant Recirculation  
ECA-1.2  
LOCA Outside Containment  
ECA-1.3  
Containment Sump Blockage  
CSP-S.1  
Response to Nuclear Power Generation/ATWS  
AOP-10A  
Safe Shutdown - Local Control  
RMP 9366  
50VCP-WR350 4.16KV Vacuum Breaker Routine  
Maintenance  
18


  PROCEDURES
   
Number           Description or Title                                     Revision
Attachment
RMP 9353         ABB 5-HK-350 4.16KV Breaker Routine Maintenance               13
11
RMP 9374-5       Molded Case Circuit Breaker Testing                           5
PROCEDURES
RMP 9369-1       Westector/Amptector Overload Setpoint Check LV               21
Number  
                  Breakers
Description or Title  
RMP 9303         Westinghouse DB-50 Breaker Routine Maintenance               23
Revision  
RMP 9305         Westinghouse DB-75 Breaker Routine Maintenance               20
RMP 9353  
2ICP 02.032       2P-29 Auxiliary Feedwater Suction Header Pressure Trip         0
ABB 5-HK-350 4.16KV Breaker Routine Maintenance  
                  Channel Operability Test
13  
AOP-10           Control Room Inaccessibility                                   6
RMP 9374-5  
AOP-30           Temporary Ventilation for Vital Areas                         7
Molded Case Circuit Breaker Testing  
ARP 2C04 2C 4-4   2TR-2000A or B Temperature Monitor Unit 2                     7
5  
STPT 14.11       Setpoint Document Auxiliary Feed Water General               23
RMP 9369-1  
                  Instrumentation Channels
Westector/Amptector Overload Setpoint Check LV  
SURVEILLANCES (COMPLETED)
Breakers  
Number           Description or Title                                           Date
21
WO 00370423     Loop 2PT-4069 Functional Check                             04/20/2011
RMP 9303  
RMP 9200-2       Station Battery D-06 Discharge Tests, Recovery and         03/24/2009
Westinghouse DB-50 Breaker Routine Maintenance  
                Equalizing Charge
23  
WO 40066812     125V Station Tech Spec Batteries Weekly Inspection         07/12/2011
RMP 9305  
WO 40066815     125V Station Tech Spec Batteries Weekly Inspection         08/12/2011
Westinghouse DB-75 Breaker Routine Maintenance  
WO 40066814     125V Station Tech Spec Batteries Weekly Inspection         07/26/2011
20  
WO 00390946     D-06, Quarterly Station Battery Inspection                 01/10/2011
2ICP 02.032  
WO 00384768     D-06, Quarterly Station Battery Inspection                 04/12/2011
2P-29 Auxiliary Feedwater Suction Header Pressure Trip  
WO 00395882     D-06, Quarterly Station Battery Inspection per RMP 9046-1 06/21/2011
Channel Operability Test  
WO 00368194     D-06, Annual Station Battery Inspection per RMP 9046-1     05/17/2010
0
WO 00358159     D-06, Annual Station Battery Inspection per RMP 9046-1     05/04/2009
AOP-10  
WO 00395879     D-06, Annual Station Battery Inspection per RMP 9046-1     06/21/2011
Control Room Inaccessibility  
RMP 9359-5B     D-06 Station Battery, D-08 Battery Charger Maintenance     05/04/2009
6  
                and Surveillances
AOP-30  
RMP 9359-5B     125V Station Tech Spec Batteries Weekly Inspection         07/30/2010
Temporary Ventilation for Vital Areas  
WO 0366265       D-06 Modified Performance Test                             05/04/2009
7  
WO 00384765     D-06, Station Battery Service Test                         01/06/2010
ARP 2C04 2C 4-4  
2ICP 02.031     2P-53 Motor Driven Auxiliary Feedwater Suction Header       08/16/110
2TR-2000A or B Temperature Monitor Unit 2  
                pressure Trip Channel Operability Test
7  
IT 09A           Cold Start of Turbine-Driven Auxiliary Feed Pump and Valve   02/15/11
STPT 14.11  
                Test (Quarterly) Unit 2
Setpoint Document Auxiliary Feed Water General  
IT 09A           Cold Start of Turbine-Driven Auxiliary Feed Pump and Valve   06/16/11
Instrumentation Channels  
                Test (Quarterly) Unit 2
23
PC 75 Part 8     AOP Fan and Air Compressor Surveillance Test                 05/14/10
                                            11                              Attachment
SURVEILLANCES (COMPLETED)  
Number  
Description or Title  
Date
WO 00370423  
Loop 2PT-4069 Functional Check  
04/20/2011  
RMP 9200-2  
Station Battery D-06 Discharge Tests, Recovery and  
Equalizing Charge
03/24/2009  
WO 40066812  
125V Station Tech Spec Batteries Weekly Inspection
07/12/2011  
WO 40066815  
125V Station Tech Spec Batteries Weekly Inspection  
08/12/2011  
WO 40066814  
125V Station Tech Spec Batteries Weekly Inspection  
07/26/2011  
WO 00390946  
D-06, Quarterly Station Battery Inspection  
01/10/2011  
WO 00384768  
D-06, Quarterly Station Battery Inspection  
04/12/2011  
WO 00395882  
D-06, Quarterly Station Battery Inspection per RMP 9046-1  
06/21/2011  
WO 00368194  
D-06, Annual Station Battery Inspection per RMP 9046-1  
05/17/2010  
WO 00358159  
D-06, Annual Station Battery Inspection per RMP 9046-1  
05/04/2009  
WO 00395879  
D-06, Annual Station Battery Inspection per RMP 9046-1  
06/21/2011  
RMP 9359-5B  
D-06 Station Battery, D-08 Battery Charger Maintenance  
and Surveillances
05/04/2009  
RMP 9359-5B  
125V Station Tech Spec Batteries Weekly Inspection  
07/30/2010  
WO 0366265  
D-06 Modified Performance Test
05/04/2009  
WO 00384765  
D-06, Station Battery Service Test  
01/06/2010  
2ICP 02.031  
2P-53 Motor Driven Auxiliary Feedwater Suction Header  
pressure Trip Channel Operability Test  
08/16/110
IT 09A  
Cold Start of Turbine-Driven Auxiliary Feed Pump and Valve  
Test (Quarterly) Unit 2  
02/15/11
IT 09A  
Cold Start of Turbine-Driven Auxiliary Feed Pump and Valve  
Test (Quarterly) Unit 2  
06/16/11
PC 75 Part 8  
AOP Fan and Air Compressor Surveillance Test  
05/14/10  


SURVEILLANCES (COMPLETED)
Number       Description or Title                                       Date
Attachment
ORT 59       Operations Refueling Test for Unit 1 and 2 Train A Spray
12
              System CIV Leakage Test
SURVEILLANCES (COMPLETED)  
ORT 60       Operations Refueling Test for Unit 1 and 2 Train B Spray
Number  
              System CIV Leakage Test
Description or Title  
IT 05         Inservice Test for Unit 1 Train A and B Containment Spray
Date
              Pump and Valves
ORT 59  
IT 06         Inservice Test for Unit 2 Train A and B Containment Spray
Operations Refueling Test for Unit 1 and 2 Train A Spray  
              Pump and Valves
System CIV Leakage Test  
  WORK DOCUMENTS
Number       Description or Title                                       Date
ORT 60  
380449 01     2X-14 Obtain Oil Sample for Dissolved Gas               03/24/11
Operations Refueling Test for Unit 1 and 2 Train B Spray  
380477 01     2B-42 MCCB Primary Current Injection Testing             03/21/11
System CIV Leakage Test  
333020 01     A52-HK-1200-08 Breaker Maintenance Per RMP 9353         02/18/08
378410 01     B52-DB50-006 Breaker Maintenance Per RMP 9303 (Feeder   11/09/10
IT 05  
              Bkr)
Inservice Test for Unit 1 Train A and B Containment Spray  
359726 01     B52-DB75-004 Breaker Maintenance Per RMP 9305 (Supply   06/07/11
Pump and Valves  
              Bkr)
382090 01     4160V A-05 SWGR Infrared Survey                         02/15/11
IT 06  
392343 01     4160V A-06 SWGR Infrared Survey                         02/09/11
Inservice Test for Unit 2 Train A and B Containment Spray  
                                          12                            Attachment
Pump and Valves  
   
WORK DOCUMENTS
Number  
Description or Title  
Date
380449 01  
2X-14 Obtain Oil Sample for Dissolved Gas  
03/24/11  
380477 01  
2B-42 MCCB Primary Current Injection Testing  
03/21/11  
333020 01  
A52-HK-1200-08 Breaker Maintenance Per RMP 9353  
02/18/08  
378410 01  
B52-DB50-006 Breaker Maintenance Per RMP 9303 (Feeder  
Bkr)
11/09/10  
359726 01  
B52-DB75-004 Breaker Maintenance Per RMP 9305 (Supply  
Bkr)
06/07/11  
382090 01  
4160V A-05 SWGR Infrared Survey  
02/15/11  
392343 01  
4160V A-06 SWGR Infrared Survey  
02/09/11  


                        LIST OF ACRONYMS USED
AC   Alternating Current
Attachment
ACE   Apparent Cause Evaluation
13
ADAMS Agencywide Document Access Management System
LIST OF ACRONYMS USED  
AFW   Auxiliary Feedwater
AC  
AOP   Abnormal Operating Procedure
Alternating Current  
AR   Action Request
ACE  
AISC American Institute of Steal Construction
Apparent Cause Evaluation  
ASME American Society of Mechanical Engineers
ADAMS  
CDBI Component Design Bases Inspection
Agencywide Document Access Management System  
CFR   Code of Federal Regulations
AFW  
CST   Condensate Storage Tank
Auxiliary Feedwater  
DRS   Division of Reactor Safety
AOP  
EOP   Emergency Operating Procedure
Abnormal Operating Procedure  
EPU   Extended Power Uprate
AR  
°F   Fahrenheit Degrees
Action Request  
FIN   Finding
AISC  
GL   Generic Letter
American Institute of Steal Construction  
IMC   Inspection Manual Chapter
ASME  
IN   Information Notice
American Society of Mechanical Engineers  
IR   Inspection Report
CDBI  
IST   Inservice Testing
Component Design Bases Inspection  
kV   Kilovolt
CFR  
LOCA Loss of Coolant Accident
Code of Federal Regulations  
LONF Loss of Normal Feedwater
CST  
LOOP Loss of Off-site Power
Condensate Storage Tank  
MDAFW Motor Driven Auxiliary Feedwater
DRS  
MOV   Motor-Operated Valve
Division of Reactor Safety  
NCV   Non-Cited Violation
EOP  
NPSH Net Positive Suction Head
Emergency Operating Procedure  
NRC   U.S. Nuclear Regulatory Commission
EPU  
ODM   Operational Decision Making
Extended Power Uprate  
OM   Operation and Maintenance
°F  
PARS Publicly Available Records System
Fahrenheit Degrees  
psig Pressure Per Square Inch Gage
FIN  
RIS   Regulatory Issue Summary
Finding  
SBO   Station Blackout
GL  
SDP   Significance Determination Process
Generic Letter  
TDAFW Turbine Driven Auxiliary Feedwater
IMC  
TS   Technical Specification
Inspection Manual Chapter  
UFSAR Updated Final Safety Analysis Report
IN  
VAC   Volts Alternating Current
Information Notice  
VDC   Volts Direct Current
IR  
                                      13          Attachment
Inspection Report  
IST  
Inservice Testing  
kV  
Kilovolt
LOCA  
Loss of Coolant Accident  
LONF  
Loss of Normal Feedwater  
LOOP  
Loss of Off-site Power  
MDAFW  
Motor Driven Auxiliary Feedwater  
MOV  
Motor-Operated Valve  
NCV  
Non-Cited Violation  
NPSH  
Net Positive Suction Head  
NRC  
U.S. Nuclear Regulatory Commission  
ODM  
Operational Decision Making  
OM  
Operation and Maintenance  
PARS  
Publicly Available Records System  
psig  
Pressure Per Square Inch Gage  
RIS  
Regulatory Issue Summary  
SBO  
Station Blackout  
SDP  
Significance Determination Process  
TDAFW  
Turbine Driven Auxiliary Feedwater  
TS  
Technical Specification  
UFSAR  
Updated Final Safety Analysis Report  
VAC  
Volts Alternating Current  
VDC  
Volts Direct Current


L. Meyer                                                                   -2-
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and
your response (if any) will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records System (PARS) component of NRC's document system
L. Meyer  
(ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html
(the Public Electronic Reading Room).
                                                                          Sincerely,
                                                                          Ann Marie Stone, Chief
                                                                          Engineering Branch 2
-2-  
                                                                          Division of Reactor Safety
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and  
Docket Nos.               50-266; 50-301
your response (if any) will be available electronically for public inspection in the NRC Public Document  
License No.               DPR-24; DPR-27
Room or from the Publicly Available Records System (PARS) component of NRC's document system  
Enclosure:               Inspection Report 05000266/2011009; 05000301/2011009
(ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html  
                            w/Attachment: Supplemental Information
(the Public Electronic Reading Room).  
cc w/encl:               Distribution via ListServ
Sincerely,  
DISTRIBUTION:
Daniel Merzke
RidsNrrDorlLpl3-1 Resource
RidsNrrPMPoint Beach Resource
Ann Marie Stone, Chief  
RidsNrrDirsIrib Resource
Engineering Branch 2  
Cynthia Pederson
Division of Reactor Safety  
Steven Orth
Docket Nos.  
Jared Heck
50-266; 50-301  
Allan Barker
License No.  
Carole Ariano
DPR-24; DPR-27  
Linda Linn
Enclosure:  
DRPIII
Inspection Report 05000266/2011009; 05000301/2011009  
DRSIII
  w/Attachment: Supplemental Information  
Patricia Buckley
cc w/encl:  
Tammy Tomczak
Distribution via ListServ  
ROPreports Resource
DISTRIBUTION:  
DOCUMENT NAME: G:\DRSIII\DRS\Work in Progress\-PTBCH 2011 009 CDBI AKD.docx
Daniel Merzke  
  Publicly Available                         Non-Publicly Available                   Sensitive               Non-Sensitive
RidsNrrDorlLpl3-1 Resource  
To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy
RidsNrrPMPoint Beach Resource  
OFFICE                 RIII                       RIII
RidsNrrDirsIrib Resource  
  NAME                   ADahbur:ls                 AMStone
Cynthia Pederson  
  DATE                   10/17/11                   10/17/11
Steven Orth  
                                                          OFFICIAL RECORD COPY
Jared Heck  
Allan Barker  
Carole Ariano  
Linda Linn  
DRPIII  
DRSIII  
Patricia Buckley  
Tammy Tomczak  
ROPreports Resource  
DOCUMENT NAME: G:\\DRSIII\\DRS\\Work in Progress\\-PTBCH 2011 009 CDBI AKD.docx  
  Publicly Available  
Non-Publicly Available  
Sensitive  
Non-Sensitive  
To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy  
OFFICE  
RIII  
RIII  
   
NAME  
ADahbur:ls  
AMStone  
   
DATE  
10/17/11  
10/17/11  
OFFICIAL RECORD COPY
}}
}}

Latest revision as of 01:31, 13 January 2025

IR 05000266-11-009, 05000301-11-009; on 08/01/11 - 9/2/11, Point Beach Nuclear Plant, Units 1 and 2; Component Design Bases Inspection (CDBI)
ML11291A094
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 10/17/2011
From: Ann Marie Stone
NRC/RGN-III/DRS/EB2
To: Meyer L
Point Beach
References
IR-11-009
Download: ML11291A094 (38)


See also: IR 05000266/2011009

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE ROAD, SUITE 210

LISLE, IL 60532-4352

October 17, 2011

Mr. Larry Meyer

Site Vice President

NextEra Energy Point Beach, LLC

6610 Nuclear Road

Two Rivers, WI 54241

SUBJECT:

POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2; COMPONENT DESIGN

BASES INSPECTION (CDBI) REPORT 05000266/2011009; 05000301/2011009

Dear Mr. Meyer:

On September 2, 2011, the U.S. Nuclear Regulatory Commission (NRC) completed a

Component Design Bases Inspection (CDBI) at your Point Beach Nuclear Plant. The enclosed

report documents the results of this inspection, which were discussed on September 2, 2011,

with Mr. T. Vehec and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed

personnel.

Based on the results of this inspection, four NRC-identified findings of very low safety

significance were identified. Three of the findings involved violations of NRC requirements.

However, because of their very low safety significance, and because the issues were entered

into your corrective action program, the NRC is treating the issues as Non-Cited Violations

(NCVs) in accordance with Section 2.3.2 of the NRC Enforcement Policy.

If you contest the subject or severity of this NCV, you should provide a response within 30 days

of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear

Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001, with a

copy to the Regional Administrator, U.S. Nuclear Regulatory Commission - Region III,

2443 Warrenville Road, Suite 210, Lisle, IL 60532-4352; the Director, Office of Enforcement,

U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the Resident Inspector

Office at the Point Beach Nuclear Plant. In addition, if you disagree with the cross-cutting

aspect assigned to any finding in this report, you should provide a response within 30 days of

the date of this inspection report, with the basis for your disagreement, to the Regional

Administrator, Region III, and the NRC Resident Inspector at the Point Beach Nuclear Plant.

L. Meyer

-2-

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its

enclosure, and your response (if any) will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records System (PARS)

component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Website

at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Ann Marie Stone, Chief

Engineering Branch 2

Division of Reactor Safety

Docket Nos.

50-266; 50-301

License No.

DPR-24; DPR-27

Enclosure:

Inspection Report 05000266/2011009; 05000301/2011009

w/Attachment: Supplemental Information

cc w/encl:

Distribution via ListServ

Enclosure

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Docket No:

05000266; 05000301

License No:

DPR-24; DPR-27

Report No:

05000266/2011009; 05000301/2011009

Licensee:

NextEra Energy Point Beach, LLC

Facility:

Point Beach Nuclear Plant, Units 1 and 2

Location:

Two Rivers, WI

Dates:

August 1 through September 2, 2011

Inspectors:

Alan Dahbur, Senior Engineering Inspector, Lead

Caroline Tilton, Senior Engineering Inspector, Mechanical

Mohammad Munir, Engineering Inspector, Electrical

Carl Moore, Operations Inspector

John Bozga, Civil Structural Inspector

Jerry Nicely, Electrical Contractor

Bill Sherbin, Mechanical Contractor

Trainee:

Cimberly Nickell, Nuclear Safety Professional

Development Program, NRR

Approved by:

Ann Marie Stone, Chief

Engineering Branch 2

Division of Reactor Safety

1

Enclosure

SUMMARY OF FINDINGS

IR 05000266/2011009, 05000301/2011009; 8/01/2011 - 9/02/2011; Point Beach Nuclear Plant,

Units 1 and 2; Component Design Bases Inspection (CDBI).

The inspection was a 3-week onsite baseline inspection that focused on the design of

components. The inspection was conducted by regional engineering inspectors and two

consultants. Four Green findings were identified by the inspectors. Three of the findings were

considered Non-Cited Violations (NCVs) of NRC regulations. The significance of most findings

is indicated by their color (Green, White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609, Significance Determination Process (SDP). Findings for which the SDP does not apply

may be (Green) or be assigned a severity level after NRC management review. The NRCs

program for overseeing the safe operation of commercial nuclear power reactors is described in

NUREG-1649, Reactor Oversight Process, Revision 4, dated December 2006.

A.

NRC-Identified and Self-Revealed Findings

Cornerstone: Initiating Events

Green. The inspectors identified a finding of very low safety significance involving the

licensees failure to meet the requirements of the American Institute of Steel

Construction (AISC) Specification. Specifically, the licensees design basis calculation

failed to ensure the turbine building structural steel floor beams met the AISC

specification. This finding was entered into the licensees corrective action program. No

violation of NRC requirements was identified.

The performance deficiency was determined to be more than minor because the finding

was associated with the Initiating Events Cornerstone attribute of design control and

adversely affected the cornerstone objective to limit the likelihood of those events that

upset the plants stability and challenged critical safety functions during shutdown, as

well as power operations. The finding screened as very low safety significance (Green),

because the transient initiator would not contribute to both the likelihood of a reactor trip

and the likelihood that mitigation equipment or functions will not be available. This

finding had a cross-cutting aspect in human performance and work practice because the

licensee did not ensure effective supervisory and management oversight of work

activities, including contractors, such that nuclear safety was supported. Specifically, the

licensee failed to have adequate oversight of design calculation and documentation for

establishing structural adequacy of the turbine building structural steel beams at EL. 44-

0. H.2(c) (Section 4OA5.1.b.(2))

Cornerstone: Mitigating Systems

Green. The inspectors identified a finding of very low safety significance (Green) and

associated Non-Cited Violation of 10 CFR Part 50, Appendix B, Criterion III, Design

Control, involving the licensees failure to correctly translate design basis assumptions

into procedures or instructions. Specifically, the licensee failed to monitor average

outside air temperature which was one of the design input criteria for the temperature

heat-up calculation associated with rooms which housed safety-related equipment. This

finding was entered into the licensees corrective action program.

2

Enclosure

The performance deficiency was associated with Mitigating System Cornerstone and

determined to be more than minor because, if left uncorrected, it could lead to a more

significant safety concern. The finding screened as very low safety significance (Green)

because the finding was not a design or qualification deficiency, did not represent a loss

of system safety function, and did not screen as potentially risk significant due to a

seismic, flooding, or severe weather initiating event. The finding had a cross-cutting

aspect in the area of human performance, resources because the licensee did not

ensure adequate training and qualification of personnel. Specifically, the licensee failed

to adequately train licensed operators to ensure adequate knowledge with respect to the

interface between functionality of a non-safety system component and the impact of a

failure on the operability of safety-related equipment. H.2(b). (Section 1R21.3.b.(1))

Green. The inspectors identified a finding of very low safety significance (Green) and

associated Non-Cited Violation of 10 CFR Part 50, Appendix B, Criterion III, Design

Control, for the failure to ensure a minimum AFW flow of 275 gpm as specified in the

accident analysis for the Loss of Normal Feedwater event. This finding was entered into

the licensees corrective action program.

The performance deficiency was associated with the Mitigating Systems Cornerstone

attribute of design control and was determined to be more than minor because, if left

uncorrected, it would have the potential to lead to a more significant safety concern.

Specifically, an AFW flow rate of less than 275 gpm as specified in the procedures did

not ensure the pressurizer would not become water solid and cause an over-pressure

condition within the Reactor Coolant System during the Loss of Normal Feedwater. The

finding screened as of very low safety significance (Green) because the finding was not

a design or qualification deficiency, did not represent a loss of system safety function,

and did not screen as potentially risk-significant due to a seismic, flooding, or severe

weather initiating event. This finding had a cross-cutting aspect in the area of human

performance, resources because the licensee did not maintain design documentation in

a complete and accurate manner. Specifically, the licensee failed to maintain

Emergency Procedures consistent with the design basis analysis for LONF. H.2(c).

(Section 1R21.6.b.(1))

Cornerstone: Barrier Integrity

Green. The inspectors identified a finding of very low safety significance (Green) and

associated Non-Cited Violation of 10 CFR Part 50, Appendix B, Criterion III, Design

Control, involving the licensees failure to ensure the Containment Spray Pipe Support

2S-249 and Containment Spray Pipe Anchor 2A-35 meet Seismic Category I

requirements. This finding was entered into the licensees corrective action program.

The performance deficiency was determined to be more than minor because it was

associated with the Barrier Integrity Cornerstone attribute of design control and

adversely affected the cornerstone objective to provide reasonable assurance that

physical design barriers (fuel cladding, reactor coolant system, and containment) protect

the public from radionuclide releases caused by accidents or events. This finding is of

very low safety significance (Green) because there was no actual barrier degradation.

The inspectors did not identify a cross-cutting aspect associated with this finding

because this was a legacy design issue; and therefore, was not reflective of current

performance. P.1(a). (Section 4OA5.1.b.(1))

3

Enclosure

B.

Licensee-Identified Violations

Violations of very low safety significance that were identified by the licensee have been

reviewed by inspectors. Corrective actions planned or taken by the licensee have been

entered into the licensees corrective action program. These violations and corrective

action tracking numbers are listed in Section 4OA7 of this report.

4

Enclosure

REPORT DETAILS

1.

REACTOR SAFETY

Cornerstone: Initiating Events, Mitigating Systems, and Barrier Integrity

1R21 Component Design Bases Inspection (71111.21)

.1

Introduction

The objective of the component design bases inspection is to verify the design bases

have been correctly implemented for the selected risk significant components and that

operating procedures and operator actions are consistent with design and licensing

bases. As plants age, their design bases may be difficult to determine and an

important design feature may be altered or disabled during a modification. The

Probabilistic Risk-Assessment (PRA) model assumes the capability of safety systems

and components to perform their intended safety function successfully. This inspectable

area verifies aspects of the Initiating Events, Mitigating Systems, and Barrier Integrity

cornerstones for which there are no indicators to measure performance.

Specific documents reviewed during the inspection are listed in the Attachment to the

report.

.2

Inspection Sample Selection Process

Point Beach Nuclear Plant implemented major modifications to the existing Auxiliary

Feedwater System in support of the extended power uprate and to resolve other system

low margin issues. The modification included the addition of two higher capacity motor

driven pumps and their associated valves and piping. The inspectors used information

contained in the licensees PRA, the Point Beachs Standardized Plant Analysis Risk

Model as the basis for component selection from the AFW System. Using the system

approach as specified in the inspection procedures, a number of risk significant

components were selected for the inspection including components used to support the

AFW system.

The inspectors also used additional component information such as a margin

assessment in the selection process. This design margin assessment considered

original design reductions caused by design modification, power uprates, or reductions

due to degraded material condition. Equipment reliability issues were also considered in

the selection of components for detailed review. These included items such as

performance test results, significant corrective actions, repeated maintenance activities,

Maintenance Rule (a)(1) status, components requiring an operability evaluation, NRC

resident inspector input of problem areas/equipment, and system health reports.

Consideration was also given to the uniqueness and complexity of the design, operating

experience, and the available defense in depth margins. A summary of the reviews

performed and the specific inspection findings identified are included in the following

sections of the report.

5

Enclosure

The inspectors also identified procedures and modifications for review that were

associated with the selected components. In addition, the inspectors selected operating

experience issues associated with the selected components.

This inspection constituted 22 samples as defined in IP 71111.21-05.

.3

Component Design

a.

Inspection Scope

The inspectors reviewed the Updated Final Safety Analysis Report (UFSAR), Technical

Specifications (TS), design basis documents, drawings, calculations and other available

design basis information, to determine the performance requirements of the selected

components. The inspectors used applicable industry standards, such as the American

Society of Mechanical Engineers (ASME) Code, Institute of Electrical and Electronics

Engineers Standards and the National Electric Code, to evaluate acceptability of the

systems design. The NRC also evaluated licensee actions, if any, taken in response to

NRC issued operating experience, such as Bulletins, Generic Letters (GLs), Regulatory

Issue Summaries (RISs), and Information Notices (INs). The review was to verify the

selected components would function as designed when required and support proper

operation of the associated systems. The attributes that were needed for a component

to perform its required function included process medium, energy sources, control

systems, operator actions, and heat removal. The attributes to verify the component

condition and tested capability was consistent with the design bases and was

appropriate may include installed configuration, system operation, detailed design,

system testing, equipment and environmental qualification, equipment protection,

component inputs and outputs, operating experience, and component degradation.

For each of the components selected, the inspectors reviewed the maintenance history,

preventive maintenance activities, system health reports, operating experience-related

information, vendor manuals, electrical and mechanical drawings, and licensee

corrective action program documents. Field walkdowns were conducted for all

accessible components to assess material condition and to verify the as-built condition

was consistent with the design. Other attributes reviewed are included as part of the

scope for each individual component.

The following 18 components were reviewed:

4.16 kV Switchgear Bus (2A06): The inspectors reviewed electrical distribution

system load flow/voltage drop, degraded voltage protection, short-circuit, and

electrical protection and coordination associated with the safety-related 4.16 KV

Bus. This review was conducted to assess the adequacy and appropriateness of

design assumptions, and to verify the bus capacity was not exceeded and bus

voltages remained above minimum acceptable values under design basis

conditions. The review included switchgears protective device settings and

breaker ratings to ensure the selective coordination was adequate for protection

of connected equipment during worst-case, short-circuit conditions. The 125Vdc

voltage calculations were reviewed to determine if adequate voltage would be

available for the breaker open/close coils and spring charging motors during

6

Enclosure

events. The stations interface and coordination with the transmission system

operator for plant voltage requirements and notification set points were reviewed.

The inspectors evaluated selected portions of the licensees response to NRC

Generic Letter (GL) 2006-02, Grid Reliability and the Impact on Plant Risk and

the Operability of Offsite Power, dated February 1, 2006. The inspectors

reviewed the degraded and loss of voltage relay protection schemes and bus

transfer schemes between offsite power supplies and the associated emergency

diesel generators. In addition, the inspectors reviewed the preventive

maintenance inspection and testing procedures to verify the breakers were

maintained in accordance with industry and vendor recommendations. System

health reports, component maintenance history, and licensees corrective action

program reports were reviewed to verify correction of potential degradation and

deficiencies were appropriately identified and resolved. The inspectors reviewed

selected industry operating experiences and plant actions to address the

applicable issues to ensure the appropriate insights from operating experience

have been applied.

480 VAC Switchgear Bus (2B-04): The inspectors inspected the 480V

switchgear to verify it would operate during design basis events. The inspectors

reviewed selected calculations for electrical distribution system load flow/voltage

drop, short-circuit, and electrical protection and coordination. The adequacy and

appropriateness of design assumptions and calculations were reviewed to verify

the bus and circuit breaker capacity was not exceeded and bus voltages

remained above minimum acceptable values under design basis conditions. The

switchgears protective device settings and breaker ratings were reviewed to

ensure the selective coordination was adequate for protection of connected

equipment during worst-case short-circuit conditions. To ensure the breakers

were maintained in accordance with industry and vendor recommendations, the

inspectors reviewed the vendor manuals, preventive maintenance inspection,

and testing procedures. The 125Vdc voltage calculations were reviewed to

determine if adequate voltage would be available for the breaker open/close

coils during events. System health reports, component maintenance history

and licensees corrective action program reports were reviewed to verify

correction of potential degradation and deficiencies were appropriately identified

and resolved. The inspectors reviewed selected industry OE and any plant

actions to address the applicable issues to ensure the appropriate insights from

operating experience have been applied. Finally, the inspectors performed a

visual non-intrusive inspection of observable portions of the safety-related 480V

Switchgear Bus 2B-04 to assess the installation configuration, material condition,

and the potential vulnerability to hazards.

480 VAC Motor Control Center (MCC 2B-42): The inspectors inspected the

480V MCC to verify it would operate during design basis events. The inspectors

reviewed selected calculations for electrical distribution system load flow/voltage

drop, short-circuit, and electrical protection and coordination. The adequacy and

appropriateness of design assumptions and calculations were reviewed to verify

the bus and circuit breaker capacity was not exceeded and bus voltages

remained above minimum acceptable values under design basis conditions. The

7

Enclosure

MCCs protective device settings and breaker ratings were reviewed to ensure

the selective coordination was adequate for protection of connected equipment

during worst-case short-circuit conditions. To ensure the breakers were

maintained in accordance with industry and vendor recommendations, the

inspectors reviewed the vendor manuals, preventive maintenance inspection,

and testing procedures. System health reports, component maintenance history

and licensees corrective action program reports were reviewed to verify

correction of potential degradation and deficiencies were appropriately identified

and resolved. The inspectors reviewed selected industry OE and any plant

actions to address the applicable issues to ensure appropriate insights from

operating experience have been applied. Finally, the inspectors performed a

visual non-intrusive inspection of observable portions of the safety-related 480V

MCC 2B-42 to assess the installation configuration, material condition, and the

potential vulnerability to hazards.

125 VDC Battery (D06): The inspectors reviewed various electrical calculations

and analyses associated with the safety-related battery to verify the battery was

designed and capable to perform its function and provide adequate voltage for

required loads during design basis accident and station blackout (SBO) event.

These calculations included battery sizing and capacity, voltage drop, minimum

voltage, hydrogen generation, SBO loading, and battery room transient

temperature. The inspectors also reviewed a sampling of completed weekly,

monthly, semi-annual surveillance tests including performance discharge tests,

and modified performance tests. The review was performed to ascertain that

acceptance criteria were met and performance degradation would be identified.

125 VDC Bus (D02): The inspectors reviewed various electrical calculations and

analysis associated with the safety-related 125 Vdc bus including voltage drop,

short circuit and fuse interrupting ratings to verify sufficient power and voltage

was available at the safety-related equipment supplied by this bus to perform

their safety function; and the interrupting ratings of the fuses were well above the

calculated short circuit currents. The inspectors also reviewed schematic and

elementary diagrams for motor control logic to ensure adequate voltage would be

available for the control circuit components under all design basis conditions.

1/2P-53 Pumps Main Feeder Breakers (1A52-83 and 2A52-68): The inspectors

inspected the 4kV circuit breakers 1P-53 and 2P-53 to verify the capability to

meet the design basis requirements, which is to supply power to the safety-

related motor driven Auxiliary Feedwater Pump motors (MDAFWP) 1P-53 and

2P-53, MDAFWP 1P-53 is fed from 4160V Safeguards Bus Train B 1A-06

through 4kV breaker 1A52-83. MDAFWP 2P-53 is fed from 4160V Safeguards

Bus Train A 2A-05 through 4kV breaker 2A52-68. The inspectors reviewed one

line diagrams and vendor equipment data to confirm the breaker ratings were

sufficient to meet design basis conditions. The inspectors reviewed the electrical

analyses for loading and protection and coordination requirements to confirm the

adequacy of the protective device settings for motor operation and circuit

protection and coordination with upstream power supplies. The inspectors

reviewed manufacturer vendor manuals, periodic maintenance and testing

8

Enclosure

practices to ensure the equipment is maintained in accordance with industry

practices. The associated breaker closure and opening control logic diagrams

and the 125Vdc voltage calculations were reviewed to verify adequate voltage

would be available for the breaker open/close coils and spring charging motors

under accident/event conditions. System health reports, component

maintenance history and licensees corrective action program reports were

reviewed to verify correction of potential degradation and deficiencies were

appropriately identified and resolved. The inspectors reviewed selected industry

OE and any plant actions to address the applicable issues to ensure appropriate

insights from operating experience have been applied. The inspectors performed

a visual non-intrusive inspection of 4kV circuit breakers 1P-53 and 2P-53 to

assess the installation configuration, material condition, and potential

vulnerability to hazards.

Motor-Driven AFW Pump (2P-53): The inspectors reviewed design documents,

including drawings and calculations to determine the design requirements for the

new MDAFW pump. The inspectors reviewed the Safety Analysis Report, and

recent addendum, to determine the licensing basis requirements for the system,

in order to determine the hydraulic requirements for the pump. Hydraulic

analyses were reviewed to verify adequacy of Net Positive Suction Head (NPSH)

and to verify the adequacy of surveillance test acceptance criteria for pump

minimum discharge pressure at required flow rate. The results of the inservice

testing (IST) performed during start-up of 2P-53, were reviewed to verify

acceptance criteria were met and performance degradation would be identified.

Pump actuation logic test results were reviewed to ensure the MDAFW pump

would start in accidents and events as described in the UFSAR. The inspectors

reviewed condensate storage tank (CST) design criteria, including usable volume

calculations to ensure the MDAFW pump, in conjunction with the turbine driven

AFW pump had adequate water supply to prevent vortexing prior to switchover of

pump suction to the service water supply. Seismic calculation of the pump

mounting bolts was reviewed for adequacy. Condition Reports were reviewed to

ensure problems were identified and corrected in a timely manner. The

inspectors reviewed the pipe stress analysis and pipe support calculations

associated with these pumps to verify the pumps meet the design basis

requirements.

2P-53 Pump Minimum Flow Valves (2AF-04073A/B): The MDAFW pump has

two minimum flow control valves (in parallel). Minimum pump flow is required to

remove pump heat, and ensure hydraulic stability when the pump is running.

This review included design analyses of the valves and associated air receiver

tank to verify the capability of the valves to perform their required function.

Specifically, the inspectors reviewed air-operated valve thrust calculations,

reviewed the required air pressure to open the valve, and reviewed the capacity

and allowable leakage limits of the associated air receiver to verify the capability

of the valves to perform their function when required. The inspectors verified the

valves were sized to provide adequate pump minimum flow to preclude pump

degradation and heat-up when operating under minimum flow conditions. The

9

Enclosure

inspectors reviewed start-up testing of the P-53 pumps to ensure the minimum

flow valves were functionally tested to open and close at the required setpoints.

2P-53 Pump Discharge Flow Control Valves (2AF-04074A/B): These valves

have an automatic function to throttle MDAFW pump discharge flow to each

steam generator to maintain a set discharge flow rate. This review included

design analyses of the valves and associated air receiver tank to verify the

capability of the valves to perform their required function. Specifically, the

inspectors reviewed air-operated valve thrust calculations, reviewed the required

air pressure to open the valve, and reviewed the capacity and allowable leakage

limits of the associated air receiver to verify the capability of the valves to perform

their function when required. The inspectors reviewed start-up testing of the 2P-

53 pump to ensure the discharge flow control valves were functionally tested to

throttle flow to the steam generators. The inspectors also reviewed the design of

the valve internals to ensure potential blockage by debris would not inhibit AFW

flow to the steam generators.

Service Water Cross-Tie Valve to 2P-53 Pump Suction Line (2AF-4067): The

inspectors reviewed the service water cross-tie valve to verify it was capable of

performing its design basis requirement of providing safety grade water to the

MDAFW pump suction line when required. The review included service water

hydraulic calculations and MOV analysis to ensure thrust and torque limits and

actuator settings were appropriate. The inspectors reviewed start-up testing of

the 2P-53 pump to ensure the valve was functionally tested to stroke open based

on minimum CST level, and pump low suction pressure instrumentation.

Additionally, the inspectors reviewed the MOV voltage drop calculation to ensure

appropriate voltage values were used in the thrust calculation. The inspectors

also reviewed surveillance procedures, and results of the periodic flushing of

service water suction lines to the valve to ensure the lines are maintained free of

debris. In addition, the inspectors reviewed electrical calculation to verify the

adequacy of feeder circuit including breaker, cable, breaker settings, electrical

schematic, control switch settings, 125 VDC power and control voltage drop,

thermal overload relay settings, thermal overload relay testing, breaker/fuse

coordination.

Turbine Driven Auxiliary Feedwater (TDAFW) Pump/Turbine (2P-29): The

inspectors reviewed the AFW system to verify the pump and associated

peripherals could meet the design and performance requirements identified in the

AFW system design/licensees basis and the FSAR. The inspection included a

review of required flows for transients and postulated SBO events, as well as

minimum flow provisions. The inspectors evaluated flow calculations, net

positive suction head (NPSH) calculations, and test data to ensure the design

basis requirements were met. The inspectors reviewed completed surveillance

test results to verify the acceptance criteria and test results demonstrated pump

operability was being maintained. The inspectors also reviewed room heat-up

calculations, procedures used to mitigate the effects of loss of normal ventilation,

and surveillances conducted on temporary fan units. In addition, the inspectors

10

Enclosure

reviewed normal and abnormal operating procedures to ensure these would

perform their objectives.

TDAFW 2P-29 Minimum Flow Valve (2AF-4002): The inspectors reviewed

information related to the air-operated valve (AOV) installed in the minimum flow

line of the TDAFW pump. This review included inservice test procedures and

results to verify the capability of the valve to perform its required function under

postulated accident conditions. The inspectors also reviewed the design of the

instrument air supply line and accumulator to verify the valve would function as

designed.

Suction Pressure Transmitters to AFW pumps (2PT-4044 and 2PT-4071): The

inspectors reviewed the piping and instrumentation diagram (P&ID), Technical

Specification requirements, setpoint calculation including the verification of

instrument and loop uncertainty, completed calibration procedures to ensure the

transmitter was capable of functioning under design conditions.

Service Water Supply to TDAFW Pump 2P-29 (2AF-4006): The inspectors

reviewed MOV calculations and analysis to ensure the valve was capable of

functioning under design conditions. These included calculations for required

thrust. Diagnostic testing and IST surveillance results, including stroke time,

were reviewed to verify acceptance criteria were met and performance

degradation could be identified. In addition, the inspectors reviewed electrical

calculation to verify the adequacy of feeder circuit including breaker, cable,

breaker settings, electrical schematic, control switch settings, 125 VDC power

and control voltage drop, thermal overload relay settings, thermal overload relay

testing, and breaker/fuse coordination.

TDAFW 2P-29 Bearing Oil Cooling (2MS-2090S): The inspectors reviewed

information related to the bearing oil cooler on the turbine side of the TDAFW

pump. The review included design configuration and specification. The

inspectors also evaluated the adequacy of the stations GL 89-13 program in

maintaining the heat removal efficiency of the bearing oil cooler. The inspectors

reviewed a sample of completed surveillances to verify acceptance criteria were

met and performance degradation could be identified.

TDAFW Pump 2P-29 Steam Supply Valves (2MS-2019 and 2MS-2020): The

inspectors reviewed motor-operated valve (MOV) calculations and analysis to

ensure the valves were capable of functioning under design conditions.

Diagnostic testing and IST surveillance results, including stroke time and

available thrust, were reviewed to verify acceptance criteria were met and

performance degradation could be identified.

TDAFW Pump 2P-29 Discharge Valves (2AF-4000 and 2AF-4001): The

inspectors reviewed motor-operated valve (MOV) calculations and analysis to

ensure the valves were capable of functioning under design conditions. These

included calculations for required thrust and maximum differential pressure.

Diagnostic testing and IST surveillance results, including stroke time and

11

Enclosure

available thrust, were reviewed to verify acceptance criteria were met and

performance degradation could be identified. In addition, the inspectors

reviewed electrical calculation to verify the adequacy of feeder circuit including

breaker, cable, breaker settings, electrical schematic, control switch settings,

125 VDC power and control voltage drop, thermal overload relay settings,

thermal overload relay testing, breaker/fuse coordination.

Auxiliary Feedwater Pumps Discharge Check Valves (2AF-148 and 2AF-107):

The inspectors reviewed the IST surveillance results to verify the acceptance

criteria were met and to identify any performance degradation. Also, the

inspectors reviewed the pipe stress analysis and pipe support calculations to

verify the piping and pipe supports, which support this check valve, meet the

design basis requirements. The inspectors reviewed the condition reports and

analyses to ensure the issue was adequately evaluated and corrective actions

were performed or scheduled to address the concern.

b.

Findings

(1) Failure to Monitor Average Outside Temperature

Introduction: The inspectors identified a finding of very low safety significance (Green)

and associated Non-Cited Violation of 10 CFR Part 50, Appendix B, Criterion III, Design

Control, involving the licensees failure to correctly translate design basis assumption

into procedures or instructions. Specifically, the licensee failed to monitor the average

outside air temperature which was one of the design inputs to temperature heat-up

calculation associated with rooms that housed vital equipment required during design

basis events.

Description: Design Basis Calculation 2005-0054, Control Building GOTHIC

Temperature Calculation, evaluated the heat-up rate of various rooms including the

TDAFW pumps room and vital switchgear room. This calculation also determined the

required number of temporary fans needed to maintain the temperature below the

maximum allowed. Calculation 2005-0054 used two temperature inputs to the code: (1)

maximum outside temperature at a specific time of 95 degrees Fahrenheit (oF); and, (2)

maximum outside temperature averaged over a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period of 86.6 oF. These

temperature inputs were used in the calculation to determine the maximum temperature

in the above mentioned rooms given different accident scenarios including design basis,

SBO and Appendix R fire. The maximum outside temperature of 95 oF was used as an

input to the calculation in order to bound the most limiting environmental conditions the

station was allowed. The maximum average outside temperature was used as an input

because the calculation was time-dependent and it credited the drop in temperature over

night. Using the average outside temperature allowed the licensee to have a more

accurate calculation in lieu of conservatisms.

On August 24, 2011, while reviewing Calculation 2005-0054, the inspectors noticed the

licensee was monitoring the maximum outside temperature for 95 oF. The licensee

provided instructions to perform a prompt engineering evaluation in the event the

outside temperature exceeded 95 oF to ensure the calculation was still bounded by

12

Enclosure

other conservatisms. However, the inspectors noticed the licensee did not monitor the

average outside temperature over a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period to ensure it did not exceed the

value of 86.6 oF. The inspectors were concerned the failure to monitor the average

outside temperature could result in a condition where the temperature in these vital

rooms would be outside the design basis calculation. Specifically, the temperature

could be below 95 oF, but the average temperature over a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period could exceed

86.6 oF. In addition, by the time the maximum temperature of the outside air reaches

95 oF, the average temperature over a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period could have already been

exceeded. In addition, by not monitoring average outside air temperature over a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />

period, the licensee would not be able to take adequate compensatory measures to

ensure the potential degraded condition does not result in a more significant concern.

The licensee acknowledged the inspectors concerns and initiated corrective action

program document AR 01680705 to address the issue. As part of their corrective

actions, the licensees recommendation included performing an evaluation and

additional monitoring once the outside temperature reaches 86.6F. The inspectors

reviewed the licensees action request and had no concerns.

In addition, during the licensee apparent cause evaluation (ACE) for this issue, the

licensee discovered when the calculation was generated, there was a recommended

action to revise the operator logs, but the action was not implemented. The

recommendation was made in an operational decision making (ODM) document. The

action was canceled when the ODM document was canceled because licensed

operators incorrectly determined the condition was a functionality, not an operability

issue.

Analysis: The inspectors determined the failure to correctly translate the average

outside temperature into procedures and instructions were contrary to 10 CFR Part 50,

Appendix B, Criterion III, Design Control, and was a performance deficiency. The

performance deficiency was determined to be more than minor because it was

associated with the Mitigating Systems Cornerstone and if left uncorrected, it would have

the potential to lead to a more significant safety concern. Specifically, because the

average outside temperature over a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period was not being monitored, the

licensee failed to ensure the maximum allowed temperature in the TDAFW pumps room

and vital switchgear room would not be exceeded and affect equipment relied upon to

perform a safety function during a design basis.

The inspectors determined the finding could be evaluated using the SDP in accordance

with IMC 0609, Significance Determination Process, Attachment 0609.04, Phase 1 -

Initial Screening and Characterization of Findings, Table 4a for the Mitigating System

cornerstone. The finding screened as of very low safety significance (Green) because

the finding was not a design or qualification deficiency, did not represent a loss of

system safety function, and did not screen as potentially risk-significant due to a seismic,

flooding, or severe weather initiating event. Specifically, the licensee provided historical

data showed the average maximum temperature over a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period did not exceed

86.6 oF since the calculation was issued.

The inspectors determined the finding had a cross-cutting aspect in the area of human

performance because the licensee did not ensure adequate training and qualification of

13

Enclosure

personnel to ensure nuclear safety. Specifically, the licensee failed to adequately train

licensed operators to ensure adequate knowledge with respect to the interface between

functionality of a non-safety system component and the impact of a failure on the

operability of safety-related equipment. H.2(b)

Enforcement: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control requires,

in part, that measures be established to ensure the design basis requirements are

correctly translated into specifications, drawings, procedures, and instructions.

Contrary to the above, as of March 24, 2009, the licensees design control measures

failed to verify the design inputs were incorporated into instructions. Specifically, the

licensee failed to monitor average outside air temperature which was an input to a

design basis calculation associated with the TDAFW pumps room and vital switchgear

room temperature heat-up. Because this violation was of very low safety significance

and because the issue was entered into the licensees corrective action program as

AR 01680705, this violation is being treated as an NCV, consistent with Section 2.3.2 of

the NRC Enforcement Policy (NCV 05000266/2011009-01; 05000301/2011009-01,

Failure to Monitor Outside Air Temperature).

.4

Operating Experience

a.

Inspection Scope

The inspectors reviewed 4 operating experience issues to ensure the NRC generic

concerns had been adequately evaluated and addressed by the licensee. The operating

experience issues listed below were reviewed as part of this inspection:

IN 1987-53, AFW Pump Trips Resulting from Low Suction Pressure;

IN 2007-34, Operating Experience Regarding Electrical Circuit Breakers;

IN 2006-31, Inadequate Fault Interrupting Rating of Breakers; and

GL 89-13, Service Water System Problems Affecting Safety-Related Systems.

b.

Findings

No findings of significance were identified.

.5

Operating Procedure Accident Scenario Reviews

a.

Inspection Scope

The inspectors performed a detailed reviewed of the procedures listed below associated

with the Auxiliary Feedwater System. For the procedures listed, the time critical operator

actions were reviewed for reasonableness, in plant actions were walked down with a

licensed operator, and any interfaces with other departments were evaluated. The

procedures were compared to UFSAR, design assumptions, and training materials to

ensure for constancy. In addition, the inspectors also observed operator actions during

14

Enclosure

the performance of four selected scenarios on the station simulator, the station blackout

(SBO) event, the anticipated transient without a scram (ATWS) event, the steam

generator tube rupture (SGTR) event, and a faulted steam generator event.

The following operating procedures were reviewed in detail:

EOP-0, Reactor Trip of Safety Injection;

EOP-0.1, Reactor Trip Response;

EOP-1, Loss of Reactor or Secondary Coolant;

EOP-1.1, Safety Injection (SI) Termination;

EOP-1.2, Post LOCA Cooldown and Depressurization;

EOP-2, Faulted Steam Generator;

EOP-3, Steam Generator Tube Rupture;

EOP-3.1, Post-SGTR Cooldown using Backfill;

ECA-0.0, Loss of All AC Power; and

CSP-S.1, Response to Nuclear Power Generation/ATWS.

b.

Findings

(1) Failure to Incorporate Minimum AFW Flow Rate Requirement Into Emergency

Procedures

Introduction: The inspectors identified a finding of very low safety significance (Green)

and associated Non-Cited Violation of 10 CFR Part 50, Appendix B, Criterion III, Design

Control, involving the licensees failure to maintain Emergency Procedures consistent

with the Loss of Normal Feedwater (LONF) Accident Analysis. The accident analysis of

record assumed an Auxiliary Feedwater flow rate of 275 gpm, while the inadequate

Emergency Procedure allowed the operator to inject AFW flow at a rate greater than

230 gpm, which would allow less than the required amount of 275 gpm of AFW flow.

Description: The AFW system was redesigned, in part, to support implementation of the

extended power uprate (EPU). The licensee installed one new motor-driven auxiliary

feedwater (MDAFW) pump for each unit in a new location in the auxiliary building. The

pumps, 1P-53 and 2P-53, replaced the safety-related function of the old MDAFW pumps

which had been shared between the two units. The new pumps are unitized, capable of

a higher flow capacity, and capable of delivering flow to either or both of the units two

steam generators (SGs). The new pumps were designed to deliver the minimum flow

requirement of 275 gpm at the lowest SG safety relief valve setpoint. The old AFW

pumps were not removed from the plant, however; they were reclassified as non-safety-

15

Enclosure

related pumps and are used during plant start up and shut down. The currently installed

safety-related turbine-driven auxiliary feedwater (TDAFW) pumps for each unit meet

EPU design flow requirements, and the new MDAFW pumps will not affect operation of

the TDAFW pumps.

In addition, as part of the modification, the licensee installed cavitating venturis in the

flow path between the new MDAFW pump to each SG. These venturis were installed as

pump runout protection. Specifically, in the event of a failed flow control valve, the

venturi would limit the flow from the MDAFW pump to 230 gpm, even while delivering

flow to a depressurized SG. The other intact SG would still receive the required flow

rate, since the flow rate of 230 gpm would be limited to the faulted SG.

The inspectors reviewed the bounding analysis for AFW flow rate requirements; the Loss

of Normal Feedwater (LONF)/Loss of AC Power (LOAC) for EPU. This calculation was

performed by Westinghouse, as documented in calculation CN-TA-08-79, Revision 1.

Here, it was determined the required AFW flow during the LONF event, which bounds

the LOAC event, was 275 gpm, split between the two SGs (137.5 gpm flow split). The

calculation concluded the LONF event did not cause any adverse condition in the core,

since it did not result in water relief from neither the pressurizer power operated relief

valves, or ASME Code safety valves.

The inspectors also reviewed procedure EOP-0.1,Reactor Trip Response, which would

be entered on a LONF event. The procedure was revised as part of EPU, and included

a new required AFW flow rate of greater than 230 gpm when the pumps are aligned to

the steam generators. The 230 gpm flow rate was based on the maximum flow rate that

could be delivered to one SG, with only the MDAFW pump available, because of the

cavitating venturis installed in the flow path between the new MDAFW pump to each SG.

However, in contrast to what was stated in EOP-0.1, the inspectors concluded 275 gpm

was required to be delivered to the SGs when both SGs were available during a LONF

event.

In response to the inspectors concern, the licensee initiated AR01678638 to revise the

EOPs to incorporate the design value for the minimum AFW flow of 275 gpm when

supplying both SGs during a LONF event, as specified in the design basis calculations.

In addition, the inspectors also reviewed the licensing basis for the new MDAFW pumps

discussed in the Safety Evaluation Report (SER) for power uprate. This document

stated the new MDAFW pump could deliver 275 gpm to one, or both, SGs (emphasis

added) for a steam generator tube rupture event. However, due to the cavitating

venturis installed in the flowpath to each SG, the MDAFW pumps could only deliver a

maximum of 230 gpm to the intact SG, which is in conflict to what was stated in the SER.

Upon discussion with NRR technical reviewers, and the licensee, it was determined the

SER required a clarification to state the flow to a single SG was limited to 230 gpm when

the MDAFW pump is operating without the TDAFW pump. Additional analysis was

provided to the inspectors which indicated 230 gpm was sufficient flow rate to the intact

SG.

16

Enclosure

Analysis: The inspectors determined the failure to ensure a minimum AFW flow of 275

gpm as specified in the accident analysis for the Loss of Normal Feedwater event was

contrary to 10 CFR Part 50, Appendix B, Criterion III, Design Control, and was a

performance deficiency. The performance deficiency was associated with the Mitigating

System Cornerstone attribute of design control and determined to be more than minor

because if left uncorrected, could become a more significant safety concern.

Specifically, the failure to properly implement the minimum AFW flow rate of 275 gpm

into the Emergency Procedures for the Loss of Normal Feedwater event did not ensure

the pressurizer would not become water solid and cause an over-pressure condition

within the Reactor Coolant System during the event. This over-pressure condition may

cause liquid water to pass through the Pressurizer Safety Valves which could lead to a

more serious Loss of Coolant Accident (LOCA) event.

The inspectors determined the finding could be evaluated using the SDP in accordance

with IMC 0609, Significance Determination Process, Attachment 0609.04, Phase 1 -

Initial Screening and Characterization of Findings, Table 4a for the Mitigating System

cornerstone. The finding screened as of very low safety significance (Green) because

the finding was not a design or qualification deficiency, did not represent a loss of safety

function, and did not screen as potentially risk-significant due to a seismic, flooding, or

severe weather initiating event. Specifically, although the procedure stated a flow rate

of 230 gpm, the operators could increase flow if needed since the MDAFW pumps were

capable of providing greater than 275 gpm to two steam generators if required.

The inspectors determined the finding had a cross-cutting aspect in the area of human

performance, resources because the licensee failed to ensure the emergency

procedures were adequate and included the design basis values. Specifically, the

licensee incorporated a non-conservative design value for the minimum AFW flow rate of

230 gpm instead of the design analysis value of 275 gpm specified for LONF event.

H.2.c]

Enforcement: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control requires,

in part, that measures shall be established to ensure the applicable regulatory

requirements and the design basis are correctly translated into specifications, drawings,

procedures and instructions. A Loss of Normal Feedwater is an analyzed accident in

Chapter 14.1.10 of the Point Beach UFSAR. Technical Specification 5.4.1 requires, in

part, that Emergency Procedures will implement the requirements of NUREG-0737.

NUREG-0737 states, in part, that emergency procedures are required to be consistent

with the actions necessary to cope with the transients and accidents analyzed.

Contrary to the above as of September 2, 2011, the licensees design control measures

failed to correctly incorporate the correct AFW flow rate into the stations emergency

operating procedures. Specifically, the accident analysis of record assumes an AFW

flow rate of 275 gpm, while the Emergency Procedure allows the operator to inject AFW

flow at a rate greater than 230 gpm which would allow less than the required amount

of 275 gpm of AFW flow. Because this violation was of very low safety significance

and because the issue was entered into the licensees corrective action program as

AR 01678638, this violation is being treated as an NCV, consistent with Section 2.3.2 of

the NRC Enforcement Policy. (NCV 05000266/2011009-02; 05000301/2011009-02;

17

Enclosure

Failure to Incorporate Minimum AFW Flow Rate Requirement into Emergency

Procedures).

4.

OTHER ACTIVITIES

4OA2 Identification and Resolution of Problems

.1

Review of Items Entered Into the Corrective Action Program

a.

Inspection Scope

The inspectors reviewed a sample of the selected component problems that were

identified by the licensee and entered into the corrective action program. The inspectors

reviewed these issues to verify an appropriate threshold for identifying issues and to

evaluate the effectiveness of corrective actions related to design issues. In addition,

corrective action documents written on issues identified during the inspection were

reviewed to verify adequate problem identification and incorporation of the problem into

the corrective action program. The specific corrective action documents that were

sampled and reviewed by the inspectors are listed in the Attachment to this report.

The inspectors also selected 3 issues that were identified during previous CDBIs to

verify the concern was adequately evaluated and corrective actions were identified and

implemented to resolve the concern, as necessary. The following issues were reviewed:

NCV 05000266/2008009-01; 05000301/2008009-01, Equalizing Charge Voltage Not

Bounded by Battery Room Hydrogen Generation Calculation;

NCV 05000266/2008009-02; 05000301/2008009-02, Non-Conservative Design

Basis for Primary Auxiliary Building Heat-up; and

NCV 05000266/2008009-03; 05000301/2008009-03, Ability to Transfer Fuel Oil

between EDG Fuel Oil Tanks T-175A/B has not been demonstrated by Testing.

b.

Findings

No findings of significance were identified.

4OA5 Power Uprate (71004)

.1

Plant Modifications (2 samples)

a.

Inspection Scope

The inspectors reviewed plant modifications for those implemented for the extended

power uprate. This includes seismic qualification of balance of plant piping and pipe

supports for extended power uprate.

Engineering Change EC-12070, Unit 2 Main Steam and Feedwater pipe support,

Revision 0; and

18

Enclosure

EC-11795, Unit 2 Containment Spray Piping Supports, Revision 0

b.

Findings

(1) Containment Spray Pipe Support Deficiencies

Introduction: The inspectors identified a finding of very low safety significance (Green)

and an associated Non-Cited Violation of 10 CFR Part 50, Appendix B, Criterion III,

Design Control, for failure to meet Seismic Category I requirements for containment

spray piping. Specifically, the licensee failed to provide sufficient justification for the

design margin in the Containment Spray Pipe Support 2S-249 and Containment Spray

Pipe Anchor 2A-35 despite the applied bending stress being greater than the allowable

bending stress.

Description: The containment spray system per UFSAR Section 6.4.1 has the following

safety-related design basis functions: provide sufficient heat removal capability to

maintain the post accident containment pressure below the design pressure, to remove

iodine from the containment atmosphere should it be released in the event of a loss-of-

coolant accident and to provide sufficient sodium hydroxide from spray additive tank to

achieve the required sump Ph level in order to prevent chloride induced stress corrosion

cracking. The containment spray piping and pipe supports were designed to Seismic

Category I requirements as described in UFSAR Section A.5.2.

Calculation WE-200074, Subsystem 6-SI-301R-1: Containment Spray System from

Containment Penetration P-54 to Anchors 2A-34 and 2A-35, Revision 1, evaluated

Containment Spray Pipe Support 2S-249 and Containment Spray Pipe Anchor 2A-35 in

accordance with Seismic Category I requirements for all design basis loading. The pipe

support and pipe anchor support were analyzed to withstand applied stress due to dead

loads, live loads, seismic loads, and thermal loads. The inspectors noticed in

Calculation WE-200074, Revision 1, Attachment D, the licensee used an allowable

overstress condition, the applied stress was greater than allowable stress, to

demonstrate seismic Category I compliance which was not in accordance with the

design and licensing basis. The Seismic Category I requirements were based on the

applied stress less than allowable stress for the evaluation of the Containment Spray

Pipe Support 2S-249 and Containment Spray Pipe Anchor 2A-35. The inspectors

determined the use of an allowable overstress condition for Containment Spray Pipe

Support 2S-249 and Containment Spray Pipe Anchor 2A-35 did not meet Seismic

Category I requirements.

Upon the inspectors identification of this issue, the license concurred with the

inspectors concern and entered the issue into their corrective action program as

AR01678643, Overstress of Pipe Supports Analyzed in WE-200074. The licensee

performed an additional analysis and determined the pipe support and the pipe anchor

were operable but nonconforming.

Analysis: The inspectors determined the licensees failure to meet Seismic Category I

requirements for the Containment Spray Pipe Support 2S-249 and Containment Spray

Anchor 2A-35 was contrary to 10 CFR Part 50, Appendix B, Criterion III, Design

Control, and was a performance deficiency. The performance deficiency was

19

Enclosure

determined to be more than minor because the finding was associated with the Barrier

Integrity Cornerstone attribute of design control and adversely affected the cornerstone

objective to provide reasonable assurance that physical design barriers (fuel cladding,

reactor coolant system, and containment) protect the public from radionuclide releases

caused by accidents or events. Specifically, failure to comply with Seismic Category I

requirements did not ensure the Containment Spray Pipe Support 2S-249 and

Containment Spray Pipe Anchor 2A-35 would function during a Seismic Category I

design basis event and adversely affect the containment spray piping system and

containment barrier.

The inspectors determined the finding could be evaluated using the Significance

Determination Process (SDP) in accordance with IMC 0609, Significance Determination

Process, Attachment 0609.04, Phase 1-Initial Screening and Characterization of

Findings, Table 4a for Barrier Integrity (Containment Barrier). The finding screened as

of very low safety significance (Green) because the inspectors answered no to all four

questions in the containment barrier column. Specifically, the licensee was able to show

the Containment Spray Pipe Support 2S-249 and Containment Spray Pipe Anchor 2A-35

were operable but nonconforming.

The inspectors determined there was no cross-cutting aspect associated with this finding

because the deficiency was a legacy design calculational issue and, therefore, was not

indicative of licensees current performance.

Enforcement: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, requires,

in part, that measures be established to ensure the applicable regulatory requirements

and the design basis are correctly translated into specifications, drawings, procedures,

and instructions. The design control measures shall provide for verifying or checking the

adequacy of design.

Contrary to the above, as of August 17, 2011, the design control measures failed to

conform to Seismic Category I requirements and also failed to verify the adequacy of the

design. Specifically, calculation WE-200074 failed to verify the adequacy of the design

for the Containment Spray Pipe Support 2S-249 and Containment Spray Pipe Anchor

2A-35 to ensure it met the Seismic Category I requirements. Because this violation was

of very low safety significance (Green) and it was entered into the licensees corrective

action program as AR01678643, this violation is being treated as a Non-Cited Violation,

consistent with Section 2.3.2 of the NRC Enforcement Policy (NCV 05000266/2011009-

03;05000301/2011009-03, Containment Spray Pipe Support Deficiencies).

(2) Turbine Building Structural Steel Floor Beams did not meet AISC requirements

Introduction: The inspectors identified a finding of very low safety significance (Green)

involving the licensees failure to meet the requirements of American Institute of Steel

Construction (AISC) Specifications in the design basis calculation. Specifically, the

licensee did not ensure the turbine building structural steel floor beams meet the AISC

specifications. No violations of NRC requirements were identified.

Description: Design Bases Calculation 12918709-C-0033, Evaluation of Structural

Steel Turbine Building Operating Floor EL. 44 for Change in Pipe Support Reactions,

20

Enclosure

Unit 2, Revision 0 evaluated the Turbine Building structural steel floor beams at

Elevation 44-0. The structural steel beams support dead loads, laydown live loads, as

well pipe support loads from the main steam and feedwater piping system which are

supported from these beams. The licensee used the American Institute of Steel

Construction (AISC) standards to demonstrate structural adequacy of the structural steel

floor beams. Calculation 129187-C-0033 justified, based on engineering judgment, that

a 5 percent overstressed condition of the turbine building structural steel floor beams

was acceptable. Specifically, the licensee stated the maximum interaction ratio (IR)

used for acceptance was less than 1.05. The structure was non-safety-related and the

design uses minimum specified yield strength. The actual yield strength of the steel

based on mill specification is expected to be higher.

The AISC required the allowable stress to be based on the specified minimum yield

strength of the material. The licensee used certified material test report strength or

actual material yield strength as a basis for an allowable overstress condition (applied

stress greater than allowable stress) for the evaluation of the turbine building structural

steel floor beams. The use of actual material yield strength as a basis for an allowable

overstress condition did not meet the AISC requirements. This issue was entered into

the licensees corrective action program as AR 01682352, Inadequate Justification for

Non-Compliance.

Analysis: The inspectors determined the licensees failure to meet AISC requirements

for the turbine building structural steel floor beams was a performance deficiency. The

performance deficiency was determined to be more than minor because the finding was

associated with the Initiating Events Cornerstone attribute of design control and

adversely affected the cornerstone objective to limit the likelihood of those events that

upset the plant stability and challenge critical safety functions during shutdown, as well

as power operations. Specifically, compliance with AISC requirements for the turbine

building structural steel floor beams ensures the main steam and feedwater piping

system would not be affected during a design basis event. The failure to comply could

impact the piping systems and potentially result in a turbine trip/reactor trip.

The inspectors determined the finding could be evaluated using the Significance

Determination Process (SDP) in accordance with IMC 0609, Significance Determination

Process, Attachment 0609.04, Phase I-Initial Screening and Characterization of

Findings, Table 4a for Initiating Events. The finding screened as of very low safety

significance (Green) because the transient initiator would not contribute to both the

likelihood of a reactor trip and the likelihood that mitigation equipment or functions will

not be available.

The inspectors determined this finding had a cross-cutting aspect in the area of human

performance, work practices because the licensee did not ensure effective supervisory

and management oversight of work activities, including contractors, such that nuclear

safety was supported. Specifically, the licensee failed to have adequate oversight of

design calculation and documentation for establishing structural adequacy of the turbine

building structural steel beams at EL. 44-0. H.4(c)

Enforcement: Since the equipment involved with the performance deficiency were not

safety-related, there were no violations of NRC regulations associated with this finding

21

Enclosure

(FIN) and as such, no enforcement. (FIN 05000266/2011009-04; 05000301/2011009-

04, Turbine Building Structural Steel Floor Beams did not meet AISC requirements)

4OA6 Meeting(s)

.1

Exit Meeting Summary

On September 2, 2011, the inspectors presented the inspection results to Mr. T. Vehec,

and other members of the licensee staff. The licensee acknowledged the issues

presented. The inspectors asked the licensee whether any materials examined during

the inspection should be considered proprietary. Several documents reviewed by the

inspectors were considered proprietary information and were either returned to the

licensee or handled in accordance with NRC policy on proprietary information.

4OA7 Licensee-Identified Violations

The following violation of very low safety significance (Green) was identified by

the licensee and was a violation of NRC requirements, which meets the criteria of

Section VI.A.1 of the NRC Enforcement Policy for being dispositioned as an NCV.

A finding of very low safety significance (Green) and associated NCV of 10 CFR

Part 50, Appendix B, Criterion V, Instructions, Procedures and Drawings, was

identified by the licensee for the failure to ensure adequate instructions were

adequately prescribed in procedures. Specifically, the licensee failed to ensure the

receptacle 2PR-49 listed in Procedure AOP-30, Temporary Ventilation for Vital

Areas, as one of the three potential power sources for transformer X-71 adequate

for the transformer plug, was acceptable, in that the receptacle and transformer had

difference phase connections. This transformer would be used to power temporary

fans relied upon for design basis accident and the loss of the normal/fixed

ventilations in the AFW and switchgear rooms. The performance deficiency was

determined to be more than minor because it was associated with the Mitigating

Systems Cornerstone attribute of Equipment Performance, and affected the

cornerstone objective of ensuring the availability, reliability, and capability of systems

that respond to initiating events to prevent undesirable consequences. The SDP

Phase I evaluation concluded the finding screened as of very low safety significance.

This issue was entered into the licensees corrective action as AR01652555, as a

corrective action, the licensee prepared an EC 271778 to modify the receptacle

during the next Unit Refueling Outage. The inspectors also noticed procedure AOP-

30 still showed 2PR-49 as one of the potential power sources. The inspectors were

concerned there were no compensatory measures in place identifying that this power

source could not be used and also identifying other receptacles in the area that could

be utilized as an interim measure. The licensee entered the inspectors concern into

their corrective action program as AR01682644.

ATTACHMENT: SUPPLEMENTAL INFORMATION

1

Attachment

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee

T. Vehec, Plant General Manager

J. Atkins, Operational Assistant Manager

S. Brown, Program Engineering Manager

L. Bruster, Engineering

D. Craine, Radiation Protection Manager

F. Flentje, Licensing Supervisor

V. Kanal, Engineering Supervisor

T. Kendall, Engineering

J. Kenney, Mechanical Department

J. Lewandowski, Quality Assurance Supervisor

T. Lensmire, Electrical Design Engineering

A. Mitchell, Performance Improvement Manager

M. Moran, EPU Engineering manager

L. Nicholson, Licensing Director

J. Pierce, Training Assistant Manager

B. Scherwinski, Licensing

P. Wild, Design Engineering Manager

B. Woyak, Engineering Supervisor

Nuclear Regulatory Commission

S. Burton, Senior Resident Inspector

M. Thorpe-Kavanaugh, Resident Inspector

Attachment

2

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened and Closed 05000266/2011009-01; 05000301/2011009-01

NCV

Failure to Monitor outside Air Temperature (Section

1R21.3.b (1))05000266/2011009-02; 05000301/2011009-02

NCV

Failure to Incorporate Minimum AFW Flow Requirement

into Emergency Procedures (Section 1R21.6.b (1))05000266/2011009-03; 05000301/2011009-03

NCV

Containment Spray Pipe Support Deficiencies (Section

4OA5.1.b (1))05000266/2011009-04; 05000301/2011009-04

FIN

Turbine Building Structural Steel Floor Beams Did Not Meet

AISC Requirements (Section 4OA5.1.b (2))

Attachment

3

LIST OF DOCUMENTS REVIEWED

The following is a list of documents reviewed during the inspection. Inclusion on this list does

not imply the NRC inspectors reviewed the documents in their entirety, but rather, that selected

sections of portions of the documents were evaluated as part of the overall inspection effort.

Inclusion of a document on this list does not imply NRC acceptance of the document or any part

of it, unless this is stated in the body of the inspection report.

CALCULATIONS

Number

Description or Title

Revision

N-93-057

Battery D-06 DC System Sizing, Voltage Drop, and Short

Circuit Calculations

6

N-93-041

Hydrogen buildup in the Battery Rooms

3

2003-046

Battery Chargers Sizing and Current Limit Set Point

4

P-94-004

MOV Overload Heater Evaluation

13

P-94-004

MOV Overload Heater Evaluation

13C

P-89-031

Voltage Drop Across MOV Power Lines

12

N-98-095

Minimum DC Control Voltage Available at CC and TC of

Circuit Breakers at 4160 Safety Switchgears and 480 Safety

Load Centers

3

2009-0027

Cable Ampacity and Voltage Drop for DC Power Cables

0

N-92-005

125 VDC Coordination Analysis

2A

P-90-017

Motor Operated Valve Undervoltage Stem Thrust and Torque

22

97-0231

Auxiliary Feedwater Pump Low Suction Pressure SW

Switchover and Pump Trip Instrument Loop

Uncertainty/Setpoint Calculation

2

97-0231

Auxiliary Feedwater Pump Low Suction Pressure SW

Switchover and Pump Trip Instrument Loop

Uncertainty/Setpoint Calculation

002-B

PBNP-IC-42

Condensate Storage Tank Water Level Instrument Scaling

and Loop Uncertainty/Setpoint Calculation

Rev 002-

A

2008-0024

AFWP Room Flood Basis Calculation

Rev 0

2010-0022

Flow Parameter EOP Setpoints Calculation

Rev 0

2005-0008

Minimum Voltage Requirements for SR MCC Control Circuits

0

P-94-004

MOV Overload Heater Evaluation

13 & 13C

2004-0009

13.8KV and 4.16KV Protection and Coordination

2-N

P-90-017

MOV UV Stem Thrust and Torque Calculation

22

P-89-031

Voltage Drop Across MOV Power Lines

12

2001-0033

Electrical Input Calc, 345kV - 480V SWGR Circuits

9

2001-0049

480V Switchgear Coordination and Protection

2

2004-0001

AC Electrical System Analysis - Model Inputs

9

2004-0002

AC Electrical System Analysis

4

2008-0014

Determination of Power Cable Ampacities and Verification of

Overload Protection

0

2005-0007

Electrical System Transient Analysis

3

Attachment

4

CALCULATIONS

Number

Description or Title

Revision

N-94-007

MOV Motor Brake Voltage Evaluation

0

2008-0005

4160/480V Loss of Voltage and Under-Frequency Relay

Settings

2

2003-0014

MOV Operating Parameters

6

2005-0053

Primary Aux Building GOTHIC Temperature Calculation

0

2009-06020

Maximum Allowable Working Pressure and Evaluation of

Valves and Components of the AFW System

1

2009-08450

AFW Air Operated Valves Component Level Calculation

0

2009-06929

AFW Air Operated Valves Functional and MEDP Calculation

0

2009-06932

Nitrogen or Compressed Air Backup System for MDAFP

(1,2-P53) Discharge Valves and Flow Recirc. Valves

1

P-94-005

MOV Stem Thrust Calculation

11

97-0231

AFW Pump Low Suction Pressure SW Switchover and Pump

Trip Inst. Loop Uncertainty/Setpoint Calc

2

2010-0010

AFW Low-Low-Low SW Switchover Instrument Loop

Unc/Setpoint Calc.,

0

WEP-SPT-33

AFW Flow Indication Uncertainty

4

CN-CPS-07-6

Point Beach S/G Narrow Range Level Instr. Uncertainty and

Setpoint Calc. as Modified to Reflect Operations at Pre EPU

and Post EPU Conditions (IC-25)

3

CN-TA-08-79

Point Beach Units 1 and 2 Loss of Normal Feedwater/Loss of

AC Power (LONF/LOAC) Analysis for the EPU Program

1

CN-CRA-08-40

SGTR Thermal Hydraulic Input to Dose Analysis for Point

Beach Units 1 and 2 to Support EPU

0

CN-CRA-08-10

Point Beach EPU Steam Line Break Inside Containment

Mass/Energy Release

1

2003-0062

AFW Pump NPSH Calculation and CST Volume Required to

Prevent Vortexing

2-B

2009-06582

Available Water in Volume of Piping in Protected Portion of

MDAFW Pump Suction

0

S-11165-116-05

AFW Pump Anchorage Design and Foundation Analysis

1

96-0244

Minimum Allowable IST Acceptance Criteria for TDAFW and

MDAFW Pump Performance

3

N-94-019

Determination of Conditions for MOV Pressure Locking and

Thermal Binding

000-B

2005-0054

Control Building GOTHIC Temperature Calculation

1

WE-300089

MDAFW Pump Suction Piping from CSTs T-24A and T-24B

to Anchor

0

WE-300090

MDAFW Common Recirculation Piping from CST to Anchor

HD-8-026-3A

00-A

WE-300089

MDAFW Common Suction Piping from CST's to Anchor

HD-8-049-3A

00-A

Attachment

5

CALCULATIONS

Number

Description or Title

Revision

WE-200052

Auxiliary Feedwater System from Structural Anchors

DB3-2H7 and DB3-2H4 to Containment Penetration P5

(EB10-A13)

00-B/C/D

WE-200051S

Emergency FW from Penet. P-5 & 6 to Anchors H-11, 2H2,

2H4 & 2H7

00-C

S-11165-116-07

Pipe Support Qualification for AFW Margin Improvements

1

129187-P-0011

Unit 2, Main Steam outside Containment - Piping

Qualification for Extended Power Uprate Conditions

6

129187-P-0018

Unit 2, Fedwater outside Containment - Piping Qualification

for Extended Power Uprate Conditions

6

PBNP-994-21-

06

HELB Reconstitution Program - Task 6 Break and Crack

Size/Location Selection

2

129187-C-0055

Evaluation of Main Steam Pipe Supporting Structure of Unit

  1. 2 Façade and Turbine Buildings for Changes in Pipe

Support Reactions Associated with Uprate Conditions (EC- 12070)

0

129187-C-0054

Evaluations of Pipe Supporting Structures of Unit #2 Auxiliary

Building for Changes in Pipe Support Reactions Associated

with Uprate Conditions

0

12918709-C-

0052

Evaluation of Main Steam and Feedwater Pipe Supporting

Structures of Unit 2 Containment Building for Changes in

Pipe Support Reactions

0

12918709-C-

0033

Evaluation of Structural Steel Turbine Building Operating

Floor EL. 44 for Change in Pipe Support Reactions, Unit 2

0

129187-C-0080

Corrective Action Report of Structural Steel Turbine Building

Operating Floor EL. 44 for Legacy Issue, Unit 2

0

WE-200074

Subsystem 6-SI-301R-1: Containment Spray System from

Containment Penetration P-54 to Anchors 2A-34 and 2A-35

1

WE-300048

Subsystem AC-601R/SI-151R: Suction Piping from RWST to

SI, CS and RHR

0-H

WE-200040

Containment Spray Pump 2-P14A Discharge to P-54

0-A

WE-200074

Subsystem 6-SI-301R-1: Containment Spray System from

Containment Penetration P-54 to Anchors 2A-34 and 2A-35

1-C

WE-200104

Subsystem AC-601R/SI-151R: Suction Piping from RWST to

Safety Injection, Containment Spray and RHR Pumps

0-F

WE-200073

Subsystem 6-SI-301R-1: Containment Spray System from

Containment Penetration P-55 to Anchors 2A-36 and 2A-37

1-C

WE-100092

Containment Spray System Line 3-SI-301R-1 between

Anchors 1A-34 and 1A-35

0-A

WE-100093

Subsystem 6-SI-301R-1-9: Containment Spray System

from Containment Penetration P-55 to Anchors 1A-34 and

1A-35

0-D

Attachment

6

CORRECTIVE ACTION DOCUMENTS GENERATED DUE TO THE INSPECTION

Number

Description or Title

Date

AR01674251

Anti-Sweat Insulation Found Removed

8/02/11

AR01674327

Fire Hose Staged Between CSTs for Unknown Activity

8/02/11

AR01674473

OM 3.27 to NP 1.9.6 Process to Process GAP

8/03/11

AR01674481

No Temporary Information Tag on Cubical 2B2-427M

AR01674616

Miscellaneous Parts Attached to Body of 2AF-4073

8/03/11

AR01674696

Error Identified in Calculation N-93-057

8/03/11

AR01674699

Damaged Wiring in Plant for Excessively Long Time

8/03/11

AR01674726

NRC Comments on AR Operability Screening

8/03/11

AR01674739

PBNP Response to Prairie Island OE32688

8/03/11

AR01674806

TSB 3.7.5 Potential Changes During FSAR Revisions

8/04/11

AR01675019

Temporary Storage Tag Missing

8/04/11

AR01675023

During a Wlakdown with CDBI NRC Inspectors, Noted two

Instances That are in Question

AR01675066

RMP 9353 Question by NRC

8/04/11

AR01675074

Emergency Lighting

8/04/11

AR01675094

D-105 Intertier Connection Cable Bend Radios

8/04/11

AR01675253

CL-13E Part 2 Inconsistencies

8/05/11

AR01675812

CL 13E Part2 AFW Valve Lineup Motor Drive

8/08/11

AR01676059

125 Vdc Fuse Issue

8/08/11

AR01677153

Calculation for Vital 120 Vac System

8/11/11

AR01677805

Error in Control Circuit Voltage Drop

8/15/11

AR01677914

Inadequate Documentation of Containment Dome Truss

8/15/11

AR01678123

Lack of Basis Documented in Calculation 2004-0002

8/16/11

AR01678283

2SAF-4000 Thermal Overload Testing

8/16/11

AR01678285

Preventive Maintenance for 2SAF-4000

8/16/11

AR01678535

Discrepancy in 125 Vdc Drawing

8/17/11

AR01678638

Evaluate ERG Setpoint Deviation for AFW Flow Setpoint in

EOP

8/17/11

AR01678643

Overstress of Pipe Support Analyzed in WE-200074

8/17/11

AR01679081

New EOP Setpoint for AFW Flow During LONF/LOCA Events

8/18/11

AR01679387

IT 08A and IT 09A Note Require Update

8/19/11

AR01679408

CR for Tracking Priority 1 PCR 01678831 Unit 2

8/19/11

AR01679412

CR for Tracking Priority 1 PCR 01678829 Unit 1

8/19/11

AR01679758

Issue Identified in Calculation P-94-004

8/22/11

AR01679907

ARB C01 A-2-9 T-24A/B Condensate Storage Tanks Level

8/22/11

AR01680185

TLB 34 Condensate Storage Tank T-24A/B

8/23/11

AR01680201

ICP 13.009-2 Condensate Storage Tank Loop Instrument 18

Months

8/23/11

AR01680705

Need to Add Operator Action to Logs

8/24/11

AR01680951

Possible Error Trap in Calculations

8/25/11

AR01681176

CST Low Level Alarm Setpoint have Procedure Issues

8/25/11

AR01681178

Incorrect Snubber Capacity used in EPU Calculation

8/25/11

Attachment

7

CORRECTIVE ACTION DOCUMENTS GENERATED DUE TO THE INSPECTION

Number

Description or Title

Date

AR01682352

Inadequate Justification for non-compliance

8/30/11

AR01682644

Issues Identified with AOP-30

8/31/11

AR01682729

Process Issues with Procedure Changes for CST Level

Setpoint

8/31/11

CORRECTIVE ACTION DOCUMENTS REVIEWED DURING THE INSPECTION

Number

Description or Title

Date

AR 01232138

Comments on 125VDC Vendor Calc.s After Owners Review

08/12/03

AR 01311121

Equipment Outside Short Circuit Rating

01/19/07

AR 01394317

2010 NRC URI-Inverter Transfers to Alt Power During Test

08/07/10

AR01612401

480V SWGR Coordination Recommended Settings

not implemented

AR01334024

IN 2007-34 Review for applicability

12/17/07

AR01315278

IN 2006-31 Review for applicability

04/04/07

AR01347091

LOV relays may trip during grid faults

AR01657810

2B-04 Was De-energized on overcurrent

AR01281343

Calculated SC Exceed Equipment Ratings and Capabilities

AR01281432

Potential Protective Device Tripping for LOCA with degraded

voltage

AR01047353

2006 CDBI Violation - OPR153 did not address Seismic event

for identified condition

AR01303493

2006 CDBI Violation - Calculated SC exceeds equipment

ratings

09/21/06

AR01302261

2006 CDBI Violation - Calculated SC exceeds equipment

ratings

08/30/06

AR01226467

Cable Overload Protection for existing design not documented

AR01331133

Cable Overload Commitments

AR01366948

1P-29 TDAFP Outboard Bearing Reached Alert Alarm

06/15/09

AR01371971

1P-29 Turbine Outboard Bearing Temp High

09/15/09

AR01379586

1P-29 TDAFW Pump Outboard Turbine bearing Temp High

01/04/10

AR01392619

1P-29 Turbine Outboard Bearing High Temp Alarm

07/12/10

AR01397577

Engineering Evaluation for 1P-29 Temperature Alert

10/04/10

AR01607140

1TR-2000B PT 19 1P-29 Temperature High Alarm

01/10/11

AR01652555

Test Cables in CSR and 2PR-49 Usability Issue

05/17/11

AR01661563

Pump Secured Due to Outbrd Turb Bearing Temp > 250

Degrees F

06/16/11

AR01669101

Potential Overstresses Beams at EL. 26 of U2 Turbine

Building

7/13/11

AR01402167

Calculation 12918709-C-0033 Rev. 1 Existing Conditions

12/21/10

Attachment

8

DRAWINGS

Number

Description or Title

Revision

6118 E-6, Sheet 1

125V DC Dist. System

55

6118 E-6, Sheet 2

125 V DC System

19

499B4676, Sheet 840 Elementary Wiring Diagram Turbine Driven Auxiliary

Feedwater Pump Discharge Valve 2AF-4001

01

499B466, Sheet 863

Elementary Wiring Diagram 2P-29 Auxiliary Feed Pump

Suction from Service Water Supply

14

499B466, Sheet 867

Elementary Wiring Diagram Turbine Driven Auxiliary

Feedwater Pump Discharge Valve 2AF-4000

15

499B466, Sheet 1803 Elementary Wiring Diagram Condensate Storage Tank

AFW Suction Valve Control

00

499B466, Sheet 899

Elementary Wiring Diagram 2P-053 AFW Pump Service

Water Suction Valve 2AF-4067

00

499B466, Sheet 744

Elementary Wiring Diagram Turbine Driven Auxiliary

Feedwater Trip/Throttle Valve 2Ms-02082

06

62550 CD2-15-1

Connection Diagram Rack 2C173B-F/2C-197

02

6118 M-2217

P&ID Auxiliary Feedwater System

02

6118 M-217, Sh 1

P&ID Auxiliary Feedwater System

94

6118 M-217, Sh 2

P&ID Auxiliary Feedwater System

25

E-98, Sheet 50D

Panel Schedule 125V DC Panel D-28 (D-40)

12

6704-D-323115

Schematic Diagram 4160V Swgr Bus 1-A06 (2-A06)

Output Breaker 1A52-86 (2A52-87) from Diesel

Generator G-04 (G-03)

13

6704-D-323101

Schematic Diagram 4160V Swgr Bus 1-A06 (2-A06)

Output Breaker 1A52-80 (2A52-93) from Diesel

Generator G-03 (G-04)

15

EPB02EAPW128002

09

Three Line Diagram - 2A06 and EDG G-04

9

EPB02EAPK0000013

0

480V One Line Diagram, 2B03/2B04

30

EPB01EAPS2400010

8

Schematic 4160V 1A05

8

EPB02EAPK2400011

2

Schematic 4160V 2A05

12

EPB02EAPK1660021

5

One Line Diagram MCC 2B42

11

PB07322

Simplified Electrical Power Distribution Single Line

1

PB07322

Simplified Electrical Power Distribution

1

018995

P&ID Service Water

77

019016

P&ID Auxiliary Feedwater System

94

275460

P&ID Auxiliary Feedwater System

20

Attachment

9

MISCELLANEOUS

Number

Description or Title

Date or

Revision

WO 00370104

DC Starter Verification & TOL Test for 2SMS-2019,

2SAF-4001 and 2SAF-4006

04/10/20

11

WO 40061953-01

ICP 6.6 Service Water Instrumentation - Controlled

WO 40061953-02

ICP 6.6 Service Water Instrumentation - Clean Side

345KV

System Health Report

06/30/11

U1/2 4160V

System Health Report

06/30/11

U1/2 480V

System Health Report

06/30/11

OPR00153

Calculated SC currents exceed equipment ratings

1

DBD-22

Design Basis Document - 4160VAC System

5

DBD-21

Design Basis Document - 480VAC System

5

SE 2008-021

Creation of Procedures for Supplemental Ventilation

04/03/09

Spec No. 6118-M-37

Turbine Building Feed Water Pump Room Ventilation

Unit (Stand By) W-46

1

MODIFICATIONS

Number

Description or Title

Date or

Revision

EC 16640

MOV Capacity during LOOP/LOCA

0

MR 02-039* A/B

Aux Feed Water Pump 2-29 Recirculation Line Orifice

03/08/03

EC 12070

Unit 2 Main Steam and Feedwater Pipe Supports

0

EC 11795

Unit 2 Containment Spray Piping Supports

0

Attachment

10

PROCEDURES

Number

Description or Title

Revision

RMP 9046-2

Station Battery Individual Cell Charging

13

NP 8.4.13

Fuse Replacement

8

2ICP 04.003-5

Auxiliary Feedwater Flow and Pressure Instruments

Outage Calibration

16

2ICP 02.031

2P-53 Motor Driven Auxiliary Feedwater Suction Header

Pressure Trip Channel Operability Test

0

AOP-13C

Severe Weather Conditions

Rev 22

ICP06.006

Service Water System Non-Outage Instruments

Calibrations

Rev 11

NP 5.2.6

FSAR Maintenance

Rev 14

NP 5.2.15

Technical Specification Bases Control

Rev 11

FP-E-MOD-03

Temporary Modifications

Rev 9

BG-ECA-2.1

Uncontrolled Depressuratization of Both Steam Generators

Rev 33

2ICP 02.031

2P-53 Motor Driven Auxiliary Feedwater Suction Header

Pressure Trip Channel Operability Test

Rev 0

TLB 34

Tank Level Book - Condensate Storage Tank T-24

Rev 9

2RMP 9133

Motor Driven and Turbine Drive Auxiliary Feedwater Pump

Start on Bus A-01 and A-02 Undervoltage Refuel

Calibration

Rev 15

STPT 25.1

Emergency Operating Procedure (EOP) Setpoints

Rev 4

NP 1.9.6

Plant Cleanliness and Storage

Rev 36

ORT 3C

Auxiliary Feedwater System and AMSAC Actuation Unit 2

Rev 16

TS 87

Primary Auxiliary Building Ventilation System Monthly

Checks

Rev 2

STPT 14.11

Auxiliary Feedwater Setpoint Document

Rev 23

EOP-0

Reactor Trip of Safety Injection

EOP-0.1

Reactor Trip Response

Rev 38

EOP-1

Loss of Reactor or Secondary Coolant

EOP-1.1

SI Termination

EOP-1.2

Post LOCA Cooldown and Depressurization

EOP-2

Faulted Steam Generator

EOP-3

Steam Generator Tube Rupture

EOP-3.1

Post-SGTR Cooldown using Backfill

ECA-0.0

Loss of All AC Power

Rev 56

ECA-1.1

Loss of Emergency Coolant Recirculation

ECA-1.2

LOCA Outside Containment

ECA-1.3

Containment Sump Blockage

CSP-S.1

Response to Nuclear Power Generation/ATWS

AOP-10A

Safe Shutdown - Local Control

RMP 9366

50VCP-WR350 4.16KV Vacuum Breaker Routine

Maintenance

18

Attachment

11

PROCEDURES

Number

Description or Title

Revision

RMP 9353

ABB 5-HK-350 4.16KV Breaker Routine Maintenance

13

RMP 9374-5

Molded Case Circuit Breaker Testing

5

RMP 9369-1

Westector/Amptector Overload Setpoint Check LV

Breakers

21

RMP 9303

Westinghouse DB-50 Breaker Routine Maintenance

23

RMP 9305

Westinghouse DB-75 Breaker Routine Maintenance

20

2ICP 02.032

2P-29 Auxiliary Feedwater Suction Header Pressure Trip

Channel Operability Test

0

AOP-10

Control Room Inaccessibility

6

AOP-30

Temporary Ventilation for Vital Areas

7

ARP 2C04 2C 4-4

2TR-2000A or B Temperature Monitor Unit 2

7

STPT 14.11

Setpoint Document Auxiliary Feed Water General

Instrumentation Channels

23

SURVEILLANCES (COMPLETED)

Number

Description or Title

Date

WO 00370423

Loop 2PT-4069 Functional Check

04/20/2011

RMP 9200-2

Station Battery D-06 Discharge Tests, Recovery and

Equalizing Charge

03/24/2009

WO 40066812

125V Station Tech Spec Batteries Weekly Inspection

07/12/2011

WO 40066815

125V Station Tech Spec Batteries Weekly Inspection

08/12/2011

WO 40066814

125V Station Tech Spec Batteries Weekly Inspection

07/26/2011

WO 00390946

D-06, Quarterly Station Battery Inspection

01/10/2011

WO 00384768

D-06, Quarterly Station Battery Inspection

04/12/2011

WO 00395882

D-06, Quarterly Station Battery Inspection per RMP 9046-1

06/21/2011

WO 00368194

D-06, Annual Station Battery Inspection per RMP 9046-1

05/17/2010

WO 00358159

D-06, Annual Station Battery Inspection per RMP 9046-1

05/04/2009

WO 00395879

D-06, Annual Station Battery Inspection per RMP 9046-1

06/21/2011

RMP 9359-5B

D-06 Station Battery, D-08 Battery Charger Maintenance

and Surveillances

05/04/2009

RMP 9359-5B

125V Station Tech Spec Batteries Weekly Inspection

07/30/2010

WO 0366265

D-06 Modified Performance Test

05/04/2009

WO 00384765

D-06, Station Battery Service Test

01/06/2010

2ICP 02.031

2P-53 Motor Driven Auxiliary Feedwater Suction Header

pressure Trip Channel Operability Test

08/16/110

IT 09A

Cold Start of Turbine-Driven Auxiliary Feed Pump and Valve

Test (Quarterly) Unit 2

02/15/11

IT 09A

Cold Start of Turbine-Driven Auxiliary Feed Pump and Valve

Test (Quarterly) Unit 2

06/16/11

PC 75 Part 8

AOP Fan and Air Compressor Surveillance Test

05/14/10

Attachment

12

SURVEILLANCES (COMPLETED)

Number

Description or Title

Date

ORT 59

Operations Refueling Test for Unit 1 and 2 Train A Spray

System CIV Leakage Test

ORT 60

Operations Refueling Test for Unit 1 and 2 Train B Spray

System CIV Leakage Test

IT 05

Inservice Test for Unit 1 Train A and B Containment Spray

Pump and Valves

IT 06

Inservice Test for Unit 2 Train A and B Containment Spray

Pump and Valves

WORK DOCUMENTS

Number

Description or Title

Date

380449 01

2X-14 Obtain Oil Sample for Dissolved Gas

03/24/11

380477 01

2B-42 MCCB Primary Current Injection Testing

03/21/11

333020 01

A52-HK-1200-08 Breaker Maintenance Per RMP 9353

02/18/08

378410 01

B52-DB50-006 Breaker Maintenance Per RMP 9303 (Feeder

Bkr)

11/09/10

359726 01

B52-DB75-004 Breaker Maintenance Per RMP 9305 (Supply

Bkr)

06/07/11

382090 01

4160V A-05 SWGR Infrared Survey

02/15/11

392343 01

4160V A-06 SWGR Infrared Survey

02/09/11

Attachment

13

LIST OF ACRONYMS USED

AC

Alternating Current

ACE

Apparent Cause Evaluation

ADAMS

Agencywide Document Access Management System

AFW

Auxiliary Feedwater

AOP

Abnormal Operating Procedure

AR

Action Request

AISC

American Institute of Steal Construction

ASME

American Society of Mechanical Engineers

CDBI

Component Design Bases Inspection

CFR

Code of Federal Regulations

CST

Condensate Storage Tank

DRS

Division of Reactor Safety

EOP

Emergency Operating Procedure

EPU

Extended Power Uprate

°F

Fahrenheit Degrees

FIN

Finding

GL

Generic Letter

IMC

Inspection Manual Chapter

IN

Information Notice

IR

Inspection Report

IST

Inservice Testing

kV

Kilovolt

LOCA

Loss of Coolant Accident

LONF

Loss of Normal Feedwater

LOOP

Loss of Off-site Power

MDAFW

Motor Driven Auxiliary Feedwater

MOV

Motor-Operated Valve

NCV

Non-Cited Violation

NPSH

Net Positive Suction Head

NRC

U.S. Nuclear Regulatory Commission

ODM

Operational Decision Making

OM

Operation and Maintenance

PARS

Publicly Available Records System

psig

Pressure Per Square Inch Gage

RIS

Regulatory Issue Summary

SBO

Station Blackout

SDP

Significance Determination Process

TDAFW

Turbine Driven Auxiliary Feedwater

TS

Technical Specification

UFSAR

Updated Final Safety Analysis Report

VAC

Volts Alternating Current

VDC

Volts Direct Current

L. Meyer

-2-

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and

your response (if any) will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records System (PARS) component of NRC's document system

(ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html

(the Public Electronic Reading Room).

Sincerely,

Ann Marie Stone, Chief

Engineering Branch 2

Division of Reactor Safety

Docket Nos.

50-266; 50-301

License No.

DPR-24; DPR-27

Enclosure:

Inspection Report 05000266/2011009; 05000301/2011009

w/Attachment: Supplemental Information

cc w/encl:

Distribution via ListServ

DISTRIBUTION:

Daniel Merzke

RidsNrrDorlLpl3-1 Resource

RidsNrrPMPoint Beach Resource

RidsNrrDirsIrib Resource

Cynthia Pederson

Steven Orth

Jared Heck

Allan Barker

Carole Ariano

Linda Linn

DRPIII

DRSIII

Patricia Buckley

Tammy Tomczak

ROPreports Resource

DOCUMENT NAME: G:\\DRSIII\\DRS\\Work in Progress\\-PTBCH 2011 009 CDBI AKD.docx

Publicly Available

Non-Publicly Available

Sensitive

Non-Sensitive

To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE

RIII

RIII

NAME

ADahbur:ls

AMStone

DATE

10/17/11

10/17/11

OFFICIAL RECORD COPY