IR 05000293/2012004: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
(3 intermediate revisions by the same user not shown)
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:UNITED STATES ber 31, 2012
{{#Wiki_filter:October 31, 2012


==SUBJECT:==
==SUBJECT:==
Line 35: Line 35:


Sincerely,
Sincerely,
/RA/
/RA/  
Ronald R. Bellamy, Chief Reactor Projects Branch 5 Division of Reactor Projects Docket Nos.: 50-293 License Nos.: DPR-35
 
Ronald R. Bellamy, Chief Reactor Projects Branch 5 Division of Reactor Projects  
 
Docket Nos.: 50-293 License Nos.: DPR-35  


===Enclosure:===
===Enclosure:===
Inspection Report 05000293/2012004 w/Attachment: Supplementary Information
Inspection Report 05000293/2012004  
 
w/Attachment: Supplementary Information  


REGION I==
REGION I==
Docket Nos.: 50-293 License Nos.: DPR-35 Report No.: 05000293/2012004 Licensee: Entergy Nuclear Operations, Inc.
Docket Nos.:
50-293  
 
License Nos.:
DPR-35  
 
Report No.:  
 
05000293/2012004  
 
Licensee:  
 
Entergy Nuclear Operations, Inc.
 
Facility:
 
Pilgrim Nuclear Power Station (PNPS)
 
Location:
 
600 Rocky Hill Road
 
Plymouth, MA 02360
 
Dates:
 
July 1, 2012 through September 30, 2012
 
Inspectors:
M. Schneider, Senior Resident Inspector, Division of Reactor Projects (DRP)
 
B. Smith, Resident Inspector, DRP
 
T. Moslak, Health Physicist, Division of Reactor Safety (DRS)
M. Patel, Reactor Engineer, DRS S. Rutenkroger, Senior Resident Inspector at Vermont Yankee, DRP G. Smith, Physical Security Inspector, DRS
 
Approved By:
Ronald R. Bellamy, Chief
 
Reactor Projects Branch 5
 
Division of Reactor Projects


Facility: Pilgrim Nuclear Power Station (PNPS)
Enclosure  
Location: 600 Rocky Hill Road Plymouth, MA 02360 Dates: July 1, 2012 through September 30, 2012 Inspectors: M. Schneider, Senior Resident Inspector, Division of Reactor Projects (DRP)
B. Smith, Resident Inspector, DRP T. Moslak, Health Physicist, Division of Reactor Safety (DRS)
M. Patel, Reactor Engineer, DRS S. Rutenkroger, Senior Resident Inspector at Vermont Yankee, DRP G. Smith, Physical Security Inspector, DRS Approved By: Ronald R. Bellamy, Chief Reactor Projects Branch 5 Division of Reactor Projects Enclosure


=SUMMARY OF FINDINGS=
=SUMMARY OF FINDINGS=
IR 05000293/2012004; 07/01/201209/30/2012; Pilgrim Nuclear Power Station; Follow-Up of
IR 05000293/2012004; 07/01/201209/30/2012; Pilgrim Nuclear Power Station; Follow-Up of  


Events and Notices of Enforcement Discretion.
Events and Notices of Enforcement Discretion.
Line 64: Line 107:
The finding was determined to be more than minor because it was associated with the Configuration Control (i.e., Operating Equipment Lineup) attribute of the Initiating Events cornerstone, and adversely affected the cornerstones objective to limit the likelihood of those events that upset plant stability and challenge critical safety functions during power operations.
The finding was determined to be more than minor because it was associated with the Configuration Control (i.e., Operating Equipment Lineup) attribute of the Initiating Events cornerstone, and adversely affected the cornerstones objective to limit the likelihood of those events that upset plant stability and challenge critical safety functions during power operations.


The inspectors screened the issue for significance using IMC 0609.04, Phase 1 - Initiating Screening and Characterization of Findings and IMC 0609 Appendix A, Exhibit 1, Initiating Events Screening. The finding was determined to be of very low safety significance (Green)because although the performance deficiency did result in a reactor scram, it did not cause a reactor scram combined with the loss of mitigating equipment relied upon to transition the plant from the onset of the trip to a stable shutdown condition. This finding has a cross-cutting aspect in the Human Performance cross-cutting area, Work Control component, because Entergy did not appropriately plan and coordinate the repair of the SJAE steam supply valve by incorporating the operational impact of the work activity consistent with nuclear safety. [H.3(b)]
The inspectors screened the issue for significance using IMC 0609.04, Phase 1 - Initiating Screening and Characterization of Findings and IMC 0609 Appendix A, Exhibit 1, Initiating Events Screening. The finding was determined to be of very low safety significance (Green)because although the performance deficiency did result in a reactor scram, it did not cause a reactor scram combined with the loss of mitigating equipment relied upon to transition the plant from the onset of the trip to a stable shutdown condition. This finding has a cross-cutting aspect in the Human Performance cross-cutting area, Work Control component, because Entergy did not appropriately plan and coordinate the repair of the SJAE steam supply valve by incorporating the operational impact of the work activity consistent with nuclear safety. [H.3(b)]  
(Section 4OA3)
(Section 4OA3)


Line 70: Line 113:


===Summary of Plant Status===
===Summary of Plant Status===
Pilgrim Nuclear Power Station began the inspection period operating at 33 percent reactor power. On July 2, 2012, Pilgrim returned to 100 percent reactor power following repairs to the main generator rectifier bank cooling system. On July 3, operators reduced reactor power to 76 percent to support a control rod pattern adjustment and returned to 100 percent reactor power later that same day. On July 12, operators reduced reactor power to 99 percent to support a brush replacement on the Vital Motor-Generator Set and returned to 100 percent reactor power following the evolution. On July 19, operators reduced power to 60 percent to perform a deep/shallow control rod sequence exchange and returned to 100 percent reactor power.
Pilgrim Nuclear Power Station began the inspection period operating at 33 percent reactor power. On July 2, 2012, Pilgrim returned to 100 percent reactor power following repairs to the main generator rectifier bank cooling system. On July 3, operators reduced reactor power to 76 percent to support a control rod pattern adjustment and returned to 100 percent reactor power later that same day. On July 12, operators reduced reactor power to 99 percent to support a brush replacement on the Vital Motor-Generator Set and returned to 100 percent reactor power following the evolution. On July 19, operators reduced power to 60 percent to perform a deep/shallow control rod sequence exchange and returned to 100 percent reactor power.


Line 76: Line 118:


==REACTOR SAFETY==
==REACTOR SAFETY==
Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity
Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity  
{{a|1R04}}


{{a|1R04}}
==1R04 Equipment Alignment
==1R04 Equipment Alignment==


==
===.1 Partial System Walkdowns===
===.1 Partial System Walkdowns===
{{IP sample|IP=IP 71111.04Q|count=3}}
{{IP sample|IP=IP 71111.04Q|count=3}}


====a. Inspection Scope====
====a. Inspection Scope====
The inspectors performed partial walkdowns of the following systems:
The inspectors performed partial walkdowns of the following systems:  
B emergency diesel generator (EDG) during maintenance on the A core spray (CS) system A CS system during testing on the B CS system Station blackout diesel generator manual fuel oil transfer system The inspectors selected these systems based on their risk-significance relative to the reactor safety cornerstones at the time they were inspected. The inspectors reviewed applicable operating procedures, system diagrams, the Updated Final Safety Analysis Report (UFSAR), technical specifications (TS), work orders, condition reports, and the impact of ongoing work activities on redundant trains of equipment in order to identify conditions that could have impacted system performance of their intended safety functions. The inspectors also performed field walkdowns of accessible portions of the systems to verify system components and support equipment were aligned correctly and were operable. The inspectors examined the material condition of the components and observed operating parameters of equipment to verify that there were no deficiencies.
 
B emergency diesel generator (EDG) during maintenance on the A core spray (CS) system  
 
A CS system during testing on the B CS system  
 
Station blackout diesel generator manual fuel oil transfer system  
 
The inspectors selected these systems based on their risk-significance relative to the reactor safety cornerstones at the time they were inspected. The inspectors reviewed applicable operating procedures, system diagrams, the Updated Final Safety Analysis Report (UFSAR), technical specifications (TS), work orders, condition reports, and the impact of ongoing work activities on redundant trains of equipment in order to identify conditions that could have impacted system performance of their intended safety functions. The inspectors also performed field walkdowns of accessible portions of the systems to verify system components and support equipment were aligned correctly and were operable. The inspectors examined the material condition of the components and observed operating parameters of equipment to verify that there were no deficiencies.


The inspectors also reviewed whether Entergy staff had properly identified equipment issues and entered them into the corrective action program for resolution with the appropriate significance characterization.
The inspectors also reviewed whether Entergy staff had properly identified equipment issues and entered them into the corrective action program for resolution with the appropriate significance characterization.
Line 100: Line 150:


====b. Findings====
====b. Findings====
No findings were identified.
No findings were identified. {{a|1R05}}
{{a|1R05}}
 
==1R05 Fire Protection==
==1R05 Fire Protection  


Resident Inspector Quarterly Walkdowns (71111.05Q - 5 samples)
Resident Inspector Quarterly Walkdowns (71111.05Q - 5 samples)  


==
====a. Inspection Scope====
====a. Inspection Scope====
The inspectors performed tours of the areas listed below to assess the material condition and operational status of fire protection features. The inspectors verified that Entergy controlled combustible materials and ignition sources in accordance with administrative procedures. The inspectors verified that fire protection and suppression equipment was available for use as specified in the area pre-fire plan, and passive fire barriers were maintained in good material condition. The inspectors also verified that station personnel implemented compensatory measures for out-of-service, degraded, or inoperable fire protection equipment, as applicable, in accordance with procedures.
The inspectors performed tours of the areas listed below to assess the material condition and operational status of fire protection features. The inspectors verified that Entergy controlled combustible materials and ignition sources in accordance with administrative procedures. The inspectors verified that fire protection and suppression equipment was available for use as specified in the area pre-fire plan, and passive fire barriers were maintained in good material condition. The inspectors also verified that station personnel implemented compensatory measures for out-of-service, degraded, or inoperable fire protection equipment, as applicable, in accordance with procedures.


Fire Area 1.9, Fire Zone 1.6, control rod drive (CRD) pump quadrant Fire Area 1.9, Fire Zone 1.9, CRD hydraulic control units, east side Fire Area 1.10, Fire Zone 2.11, feedwater pump A area Fire Area 3.3, Fire Zone 3.3, plant computer room Fire Area 5.3, Fire Zone 5.3, C salt service water pump room
Fire Area 1.9, Fire Zone 1.6, control rod drive (CRD) pump quadrant  
 
Fire Area 1.9, Fire Zone 1.9, CRD hydraulic control units, east side  
 
Fire Area 1.10, Fire Zone 2.11, feedwater pump A area  
 
Fire Area 3.3, Fire Zone 3.3, plant computer room  
 
Fire Area 5.3, Fire Zone 5.3, C salt service water pump room


====b. Findings====
====b. Findings====
No findings were identified.
No findings were identified. {{a|1R07}}
{{a|1R07}}
 
==1R07 Heat Sink Performance (711111.07A - 1 sample)==
==1R07 Heat Sink Performance (711111.07A - 1 sample)


====a. Inspection Scope====
====a. Inspection Scope====
==
The inspectors reviewed one sample of Entergys program for maintenance, testing, and monitoring of risk significant heat exchangers (HXs) to assess the capability of the HXs to perform their design functions. The inspectors also evaluated whether potential common cause problems could affect multiple HXs. Based on its risk significance and performance history, the B residual heat removal heat exchanger was selected for detailed review by the inspectors.
The inspectors reviewed one sample of Entergys program for maintenance, testing, and monitoring of risk significant heat exchangers (HXs) to assess the capability of the HXs to perform their design functions. The inspectors also evaluated whether potential common cause problems could affect multiple HXs. Based on its risk significance and performance history, the B residual heat removal heat exchanger was selected for detailed review by the inspectors.


Line 122: Line 182:
No findings were identified.
No findings were identified.


{{a|1R11}}
{{a|1R11}}
 
==1R11 Licensed Operator Requalification Program==
==1R11 Licensed Operator Requalification Program==
{{IP sample|IP=IP 71111.11Q|count=2}}
{{IP sample|IP=IP 71111.11Q|count=2}}


===.1 Requalification Review by Resident Inspectors===
===.1 Requalification Review by Resident Inspectors===
====a. Inspection Scope====
====a. Inspection Scope====
The inspectors observed licensed operator simulator as found training on August 20, which included a loss of offsite power event complicated by the loss of an emergency diesel generator and a small break loss of coolant accident. The inspectors evaluated operator performance during the simulated events and verified completion of risk significant operator actions, including the use of abnormal and emergency operating procedures. The inspectors verified that emergency classifications within the scenario were declared accurately and timely. The inspectors assessed the clarity and effectiveness of communications, implementation of actions in response to alarms and degrading plant conditions, and the oversight and direction provided by the Control Room Supervisor. Additionally, the inspectors assessed the ability of the crew and training staff to identify and document crew performance problems. Finally, the inspectors performed a simulator fidelity review to determine if the arrangement of the simulator instrumentation, controls, and tagging closely paralleled that of the control room.
The inspectors observed licensed operator simulator as found training on August 20, which included a loss of offsite power event complicated by the loss of an emergency diesel generator and a small break loss of coolant accident. The inspectors evaluated operator performance during the simulated events and verified completion of risk significant operator actions, including the use of abnormal and emergency operating procedures. The inspectors verified that emergency classifications within the scenario were declared accurately and timely. The inspectors assessed the clarity and effectiveness of communications, implementation of actions in response to alarms and degrading plant conditions, and the oversight and direction provided by the Control Room Supervisor. Additionally, the inspectors assessed the ability of the crew and training staff to identify and document crew performance problems. Finally, the inspectors performed a simulator fidelity review to determine if the arrangement of the simulator instrumentation, controls, and tagging closely paralleled that of the control room.
Line 135: Line 195:


===.2 Main Control Room Review by Resident Inspectors===
===.2 Main Control Room Review by Resident Inspectors===
====a. Inspection Scope====
====a. Inspection Scope====
The inspectors observed main control room activities during replacement of a vital motor generator set DC brush, a control rod pattern adjustment, repair of main generator rectifier bank #4, and the restoration from the loss of a feedwater heater during a 120VAC power supply fast transfer. See section 4OA3 for specific discussion of these activities. The inspectors reviewed procedural guidance for station power changes and the power maneuver plan, and observed control room conduct and control of these evolutions.
The inspectors observed main control room activities during replacement of a vital motor generator set DC brush, a control rod pattern adjustment, repair of main generator rectifier bank #4, and the restoration from the loss of a feedwater heater during a 120VAC power supply fast transfer. See section 4OA3 for specific discussion of these activities. The inspectors reviewed procedural guidance for station power changes and the power maneuver plan, and observed control room conduct and control of these evolutions.
Line 142: Line 201:
No findings were identified.
No findings were identified.


{{a|1R12}}
{{a|1R12}}
 
==1R12 Maintenance Effectiveness==
==1R12 Maintenance Effectiveness==
{{IP sample|IP=IP 71111.12Q|count=2}}
{{IP sample|IP=IP 71111.12Q|count=2}}
Line 149: Line 209:
The inspectors reviewed the two samples listed below to assess the effectiveness of maintenance activities on structures, systems, and components (SSC) performance and reliability. The inspectors reviewed system health reports, corrective action program documents, maintenance work orders, and maintenance rule basis documents to ensure that Entergy was identifying and properly evaluating performance problems within the scope of the maintenance rule. For each sample selected, the inspectors verified that the SSC was properly scoped into the maintenance rule in accordance with 10 CFR 50.65 and verified that the (a)(2) performance criteria established by Entergy staff was reasonable. As applicable, for SSCs classified as (a)(1), the inspectors assessed the adequacy of goals and corrective actions to return these SSCs to (a)(2). Additionally, the inspectors ensured that Entergy staff was identifying and addressing common cause failures that occurred within and across maintenance rule system boundaries.
The inspectors reviewed the two samples listed below to assess the effectiveness of maintenance activities on structures, systems, and components (SSC) performance and reliability. The inspectors reviewed system health reports, corrective action program documents, maintenance work orders, and maintenance rule basis documents to ensure that Entergy was identifying and properly evaluating performance problems within the scope of the maintenance rule. For each sample selected, the inspectors verified that the SSC was properly scoped into the maintenance rule in accordance with 10 CFR 50.65 and verified that the (a)(2) performance criteria established by Entergy staff was reasonable. As applicable, for SSCs classified as (a)(1), the inspectors assessed the adequacy of goals and corrective actions to return these SSCs to (a)(2). Additionally, the inspectors ensured that Entergy staff was identifying and addressing common cause failures that occurred within and across maintenance rule system boundaries.


          (a)(1) evaluation of emergency lighting exceeding functional failure performance criteria (a)(1) evaluation for repeat failures of the K-117 diesel driven air compressor
(a)(1) evaluation of emergency lighting exceeding functional failure performance criteria  
 
(a)(1) evaluation for repeat failures of the K-117 diesel driven air compressor


====b. Findings====
====b. Findings====
No findings were identified.
No findings were identified.


{{a|1R13}}
{{a|1R13}}
 
==1R13 Maintenance Risk Assessments and Emergent Work Control==
==1R13 Maintenance Risk Assessments and Emergent Work Control==
{{IP sample|IP=IP 71111.13|count=4}}
{{IP sample|IP=IP 71111.13|count=4}}
Line 161: Line 224:
The inspectors reviewed station evaluation and management of plant risk for the maintenance and emergent work activities listed below to verify that Entergy performed the appropriate risk assessments prior to removing equipment for work. The inspectors selected these activities based on potential risk significance relative to the reactor safety cornerstones. As applicable for each activity, the inspectors verified that Entergy personnel performed risk assessments as required by 10 CFR 50.65(a)(4) and that the assessments were accurate and complete. When Entergy performed emergent work, the inspectors verified that operations personnel promptly assessed and managed plant risk. The inspectors reviewed the scope of maintenance work and discussed the results of the assessment with the stations probabilistic risk analyst to verify plant conditions were consistent with the risk assessment. The inspectors also reviewed the TS requirements and inspected portions of redundant safety systems, when applicable, to verify risk analysis assumptions were valid and applicable requirements were met.
The inspectors reviewed station evaluation and management of plant risk for the maintenance and emergent work activities listed below to verify that Entergy performed the appropriate risk assessments prior to removing equipment for work. The inspectors selected these activities based on potential risk significance relative to the reactor safety cornerstones. As applicable for each activity, the inspectors verified that Entergy personnel performed risk assessments as required by 10 CFR 50.65(a)(4) and that the assessments were accurate and complete. When Entergy performed emergent work, the inspectors verified that operations personnel promptly assessed and managed plant risk. The inspectors reviewed the scope of maintenance work and discussed the results of the assessment with the stations probabilistic risk analyst to verify plant conditions were consistent with the risk assessment. The inspectors also reviewed the TS requirements and inspected portions of redundant safety systems, when applicable, to verify risk analysis assumptions were valid and applicable requirements were met.


Green risk during Y1 on its alternate power supply and the second point feedwater heater B out of service Yellow risk for maintenance and testing on the B residual heat removal system Yellow risk for maintenance and testing on the shutdown transformer and station blackout diesel generator Yellow risk for the high pressure coolant injection system out of service and in the presence of main generator rectifier bank leakage.
Green risk during Y1 on its alternate power supply and the second point feedwater heater B out of service  
 
Yellow risk for maintenance and testing on the B residual heat removal system  
 
Yellow risk for maintenance and testing on the shutdown transformer and station blackout diesel generator  
 
Yellow risk for the high pressure coolant injection system out of service and in the presence of main generator rectifier bank leakage.


====b. Findings====
====b. Findings====
No findings were identified.
No findings were identified.


{{a|1R15}}
{{a|1R15}}
 
==1R15 Operability Determinations and Functionality Assessments==
==1R15 Operability Determinations and Functionality Assessments==
{{IP sample|IP=IP 71111.15|count=5}}
{{IP sample|IP=IP 71111.15|count=5}}


====a. Inspection Scope====
====a. Inspection Scope====
The inspectors reviewed operability determinations for the following degraded or non-conforming conditions:
The inspectors reviewed operability determinations for the following degraded or non-conforming conditions:  
Drywell floor sump monitoring equipment not functioning properly First point feedwater heater leak and Operational Decision-Making Issue (ODMI)
 
Increased hotwell conductivity ODMI Standby liquid control tank level increased approximately 300 gallons Three local power range monitors failed calibration The inspectors selected these issues based on the risk significance of the associated components and systems. The inspectors evaluated the technical adequacy of the operability determinations to assess whether TS operability was properly justified and the subject component or system remained available such that no unrecognized increase in risk occurred. The inspectors compared the operability and design criteria in the appropriate sections of the TS and UFSAR to Entergys evaluations to determine whether the components or systems were operable. Where compensatory measures were required to maintain operability, the inspectors determined whether the measures in place would function as intended and were properly controlled by Entergy. The inspectors determined, where appropriate, compliance with bounding limitations associated with the evaluations.
Drywell floor sump monitoring equipment not functioning properly  
 
First point feedwater heater leak and Operational Decision-Making Issue (ODMI)  
 
Increased hotwell conductivity ODMI  
 
Standby liquid control tank level increased approximately 300 gallons  
 
Three local power range monitors failed calibration  
 
The inspectors selected these issues based on the risk significance of the associated components and systems. The inspectors evaluated the technical adequacy of the operability determinations to assess whether TS operability was properly justified and the subject component or system remained available such that no unrecognized increase in risk occurred. The inspectors compared the operability and design criteria in the appropriate sections of the TS and UFSAR to Entergys evaluations to determine whether the components or systems were operable. Where compensatory measures were required to maintain operability, the inspectors determined whether the measures in place would function as intended and were properly controlled by Entergy. The inspectors determined, where appropriate, compliance with bounding limitations associated with the evaluations.


====b. Findings====
====b. Findings====
No findings were identified.
No findings were identified.


{{a|1R19}}
{{a|1R19}}
 
==1R19 Post-Maintenance Testing==
==1R19 Post-Maintenance Testing==
{{IP sample|IP=IP 71111.19|count=6}}
{{IP sample|IP=IP 71111.19|count=6}}
Line 185: Line 266:
The inspectors reviewed the post-maintenance tests for the maintenance activities listed below to verify that procedures and test activities ensured system operability and functional capability. The inspectors reviewed the test procedure to verify that the procedure adequately tested the safety functions that may have been affected by the maintenance activity, that the acceptance criteria in the procedure was consistent with the information in the applicable licensing basis and/or design basis documents, and that the procedure had been properly reviewed and approved. The inspectors also witnessed the test or reviewed test data to verify that the test results adequately demonstrated restoration of the affected safety functions.
The inspectors reviewed the post-maintenance tests for the maintenance activities listed below to verify that procedures and test activities ensured system operability and functional capability. The inspectors reviewed the test procedure to verify that the procedure adequately tested the safety functions that may have been affected by the maintenance activity, that the acceptance criteria in the procedure was consistent with the information in the applicable licensing basis and/or design basis documents, and that the procedure had been properly reviewed and approved. The inspectors also witnessed the test or reviewed test data to verify that the test results adequately demonstrated restoration of the affected safety functions.


A control room high efficiency air filtration system temperature switch replacement Reactor water clean-up motor operated valve maintenance Rebuild B standby gas treatment system damper actuators Replacement of vital motor generator set brushes Residual heat removal torus cooling isolation valve MO-1001-34B maintenance Removal of temporary modification and installation of thermal overloads for the A salt service water pump
A control room high efficiency air filtration system temperature switch replacement  
 
Reactor water clean-up motor operated valve maintenance  
 
Rebuild B standby gas treatment system damper actuators  
 
Replacement of vital motor generator set brushes  
 
Residual heat removal torus cooling isolation valve MO-1001-34B maintenance  
 
Removal of temporary modification and installation of thermal overloads for the A salt service water pump


====b. Findings====
====b. Findings====
No findings were identified.
No findings were identified.


{{a|1R22}}
{{a|1R22}}
 
==1R22 Surveillance Testing==
==1R22 Surveillance Testing==
{{IP sample|IP=IP 71111.22|count=5}}
{{IP sample|IP=IP 71111.22|count=5}}


====a. Inspection Scope====
====a. Inspection Scope====
The inspectors observed performance of surveillance tests and/or reviewed test data of selected risk-significant SSCs to assess whether test results satisfied TS, the UFSAR, and Entergys procedure requirements. The inspectors verified that test acceptance criteria were clear, tests demonstrated operational readiness and were consistent with design documentation, test instrumentation had current calibrations and the range and accuracy for the application, tests were performed as written, and applicable test prerequisites were satisfied. Upon test completion, the inspectors considered whether the test results supported that equipment was capable of performing the required safety functions. The inspectors reviewed the following surveillance tests:
The inspectors observed performance of surveillance tests and/or reviewed test data of selected risk-significant SSCs to assess whether test results satisfied TS, the UFSAR, and Entergys procedure requirements. The inspectors verified that test acceptance criteria were clear, tests demonstrated operational readiness and were consistent with design documentation, test instrumentation had current calibrations and the range and accuracy for the application, tests were performed as written, and applicable test prerequisites were satisfied. Upon test completion, the inspectors considered whether the test results supported that equipment was capable of performing the required safety functions. The inspectors reviewed the following surveillance tests:  
Vital bus protective relay functional test A salt service water flow rate monthly surveillance B core spray pump quarterly inservice test (IST)
 
A low pressure coolant injection system pump and valve quarterly IST Main steam isolation valve operability (CIV)
Vital bus protective relay functional test  
 
A salt service water flow rate monthly surveillance  
 
B core spray pump quarterly inservice test (IST)  
 
A low pressure coolant injection system pump and valve quarterly IST  
 
Main steam isolation valve operability (CIV)


====b. Findings====
====b. Findings====
Line 203: Line 303:


==RADIATION SAFETY==
==RADIATION SAFETY==
Cornerstones: Occupational Radiation Safety
Cornerstones: Occupational Radiation Safety {{a|2RS1}}
{{a|2RS1}}
 
==2RS1 Radiological Hazard Assessment and Exposure Controls==
==2RS1 Radiological Hazard Assessment and Exposure Controls==
{{IP sample|IP=IP 71124.01}}
{{IP sample|IP=IP 71124.01}}
Line 213: Line 313:
Implementation of these controls was reviewed against the criteria contained in 10 CFR Part 20, TS, and Entergy=s procedures.
Implementation of these controls was reviewed against the criteria contained in 10 CFR Part 20, TS, and Entergy=s procedures.


Radiological Hazards Control and Work Coverage The inspector identified work performed in radiological controlled areas and evaluated Entergys assessment of the radiological hazards. Specific work activities evaluated included calibrating a high activity source; i.e., forty-five
Radiological Hazards Control and Work Coverage  
 
The inspector identified work performed in radiological controlled areas and evaluated Entergys assessment of the radiological hazards. Specific work activities evaluated included calibrating a high activity source; i.e., forty-five
: (45) curies of Iridium-192 (Ir-192), and using this source to calibrate high range instruments, such as the turbine building vent monitors and the steam jet air ejector (SJAE) monitors. These activities were classified by Entergy as an Infrequently Performed Test/Evolution (IPTE) and additional administrative controls were implemented.
: (45) curies of Iridium-192 (Ir-192), and using this source to calibrate high range instruments, such as the turbine building vent monitors and the steam jet air ejector (SJAE) monitors. These activities were classified by Entergy as an Infrequently Performed Test/Evolution (IPTE) and additional administrative controls were implemented.


Line 221: Line 323:


====b. Findings====
====b. Findings====
No findings were identified.
No findings were identified. {{a|2RS5}}
{{a|2RS5}}
 
==2RS5 Radiation Monitoring Instrumentation==
==2RS5 Radiation Monitoring Instrumentation==
{{IP sample|IP=IP 71124.05}}
{{IP sample|IP=IP 71124.05}}
This area was inspected August 13 through 16, to verify that Entergy is assuring the accuracy and operability of radiation monitoring instruments used to protect occupational workers and to protect the public from nuclear power plant operations. The inspector used the requirements in 10 CFR Part 20, 10 CFR Part 50, Appendix A , Criterion 60, Control of Release of Radioactivity to the Environment, and Criterion 64 Monitoring Radioactive Releases; 10 CFR 50, Appendix I, Numerical Guides for Design Objectives and Limiting Conditions for Operation to meet the Criterion As Low as is Reasonably Achievable for Radioactive Material in Light-Water-Cooled Nuclear Power Reactor Effluents; 40 CFR Part 190, Environmental Radiation Protection Standards for Nuclear Power Operations; NUREG-0737, Clarification of Three Mile Island Corrective Action Requirements; TS/Offsite Dose Calculation Manual; applicable industry standards; and Entergys procedures required by TS, as criteria for determining compliance.
This area was inspected August 13 through 16, to verify that Entergy is assuring the accuracy and operability of radiation monitoring instruments used to protect occupational workers and to protect the public from nuclear power plant operations. The inspector used the requirements in 10 CFR Part 20, 10 CFR Part 50, Appendix A, Criterion 60, Control of Release of Radioactivity to the Environment, and Criterion 64 Monitoring Radioactive Releases; 10 CFR 50, Appendix I, Numerical Guides for Design Objectives and Limiting Conditions for Operation to meet the Criterion As Low as is Reasonably Achievable for Radioactive Material in Light-Water-Cooled Nuclear Power Reactor Effluents; 40 CFR Part 190, Environmental Radiation Protection Standards for Nuclear Power Operations; NUREG-0737, Clarification of Three Mile Island Corrective Action Requirements; TS/Offsite Dose Calculation Manual; applicable industry standards; and Entergys procedures required by TS, as criteria for determining compliance.


===.1 Inspection Planning===
===.1 Inspection Planning===
====a. Inspection Scope====
====a. Inspection Scope====
The inspector reviewed the UFSAR to identify radiation instruments associated with monitoring area radiation, airborne radioactivity, process streams, effluents, materials/articles, and workers. Additionally, the inspector reviewed the associated TS requirements for post-accident monitoring instrumentation. The inspector reviewed a list of in-service survey instrumentation including air samplers and small article monitors (SAM), along with radiation monitoring instruments used to detect and analyze workers external contamination as well as external dose. Additionally, the inspector reviewed personnel contamination monitors and portal monitors including whole-body counters used to detect workers surface and internal contamination. The inspector assessed whether an adequate number and type of instruments were available to support operations.
The inspector reviewed the UFSAR to identify radiation instruments associated with monitoring area radiation, airborne radioactivity, process streams, effluents, materials/articles, and workers. Additionally, the inspector reviewed the associated TS requirements for post-accident monitoring instrumentation. The inspector reviewed a list of in-service survey instrumentation including air samplers and small article monitors (SAM), along with radiation monitoring instruments used to detect and analyze workers external contamination as well as external dose. Additionally, the inspector reviewed personnel contamination monitors and portal monitors including whole-body counters used to detect workers surface and internal contamination. The inspector assessed whether an adequate number and type of instruments were available to support operations.
Line 242: Line 343:


===.2 Walkdowns and Observations===
===.2 Walkdowns and Observations===
====a. Inspection Scope====
====a. Inspection Scope====
The inspector walked down the SJAE gaseous effluent radiation monitoring system (1705-3A/B) and the liquid radwaste monitor (1705-30). The inspector determined that the effluent/process monitor configurations aligned with descriptions contained in the UFSAR and Offsite Dose Calculation Manual.
The inspector walked down the SJAE gaseous effluent radiation monitoring system (1705-3A/B) and the liquid radwaste monitor (1705-30). The inspector determined that the effluent/process monitor configurations aligned with descriptions contained in the UFSAR and Offsite Dose Calculation Manual.
Line 258: Line 358:


===.3 Calibration and Testing Program===
===.3 Calibration and Testing Program===
 
===Process and Effluent Monitors===
Process and Effluent Monitors
 
====a. Inspection Scope====
====a. Inspection Scope====
The inspector selected three effluent monitor instruments and evaluated whether channel calibration and functional tests were performed consistent with TS and the Offsite Dose Calculation Manual. The inspector assessed whether
The inspector selected three effluent monitor instruments and evaluated whether channel calibration and functional tests were performed consistent with TS and the Offsite Dose Calculation Manual. The inspector assessed whether
Line 273: Line 371:


===.4 Laboratory Instrumentation===
===.4 Laboratory Instrumentation===
====a. Inspection Scope====
====a. Inspection Scope====
The inspector assessed laboratory instruments used for radiological analyses to determine whether daily performance checks and calibration data indicated that the frequency of the calibrations was adequate and there were no indications of degraded performance. The instrumentation inspected included three gamma spectroscopy systems and a scintillation counter.
The inspector assessed laboratory instruments used for radiological analyses to determine whether daily performance checks and calibration data indicated that the frequency of the calibrations was adequate and there were no indications of degraded performance. The instrumentation inspected included three gamma spectroscopy systems and a scintillation counter.
Line 283: Line 380:


===.5 Whole Body Counter===
===.5 Whole Body Counter===
====a. Inspection Scope====
====a. Inspection Scope====
The inspector reviewed the methods and sources used to perform functional checks on the whole body counter (FastScan) before use and assessed whether check sources were appropriate and align with the plants isotopic mix.
The inspector reviewed the methods and sources used to perform functional checks on the whole body counter (FastScan) before use and assessed whether check sources were appropriate and align with the plants isotopic mix.
Line 293: Line 389:


===.6 Post-Accident Monitoring Instrumentation===
===.6 Post-Accident Monitoring Instrumentation===
====a. Inspection Scope====
====a. Inspection Scope====
The inspector reviewed the calibration documentation for the reactor building vent (RT-1001-609) high-range monitor. The inspector assessed whether an electronic calibration was completed for all range decades and was calibrated using an appropriate radiation source. The inspector assessed whether calibration acceptance criteria were reasonable, considering the large measuring range and the intended use of the instrument.
The inspector reviewed the calibration documentation for the reactor building vent (RT-1001-609) high-range monitor. The inspector assessed whether an electronic calibration was completed for all range decades and was calibrated using an appropriate radiation source. The inspector assessed whether calibration acceptance criteria were reasonable, considering the large measuring range and the intended use of the instrument.
Line 303: Line 398:


===.7 Portal Monitors, Personnel Contamination Monitors, and Small Article Monitors===
===.7 Portal Monitors, Personnel Contamination Monitors, and Small Article Monitors===
====a. Inspection Scope====
====a. Inspection Scope====
The inspector selected two PM-7 and two ARGOS 4B portal monitors, two small article monitors (SAM), and observed the daily source checks and verified that the alarm setpoint values were reasonable under the circumstances to ensure that licensed material is not released from the site.
The inspector selected two PM-7 and two ARGOS 4B portal monitors, two small article monitors (SAM), and observed the daily source checks and verified that the alarm setpoint values were reasonable under the circumstances to ensure that licensed material is not released from the site.
Line 313: Line 407:


===.8 Portable Survey Instruments, Area Radiation Monitors, Electronic Dosimetry, and Air===
===.8 Portable Survey Instruments, Area Radiation Monitors, Electronic Dosimetry, and Air===
Samplers/Continuous Air Monitors
Samplers/Continuous Air Monitors


Line 327: Line 420:


===.9 Instrument Calibrator===
===.9 Instrument Calibrator===
====a. Inspection Scope====
====a. Inspection Scope====
The inspector reviewed the current radiation output values for Entergys portable survey and area radiation monitor instrument calibrator units, a bench calibrator (N-273) and a box calibrator (N-360). The inspector assessed whether Entergy periodically verified calibrator output over the range of the exposure rates/dose rates using an ion chamber or an electrometer. The inspector assessed whether the measuring devices had been calibrated by a facility using National Institute of Standards and Technology (NIST)traceable sources and whether decay correction factors for these measuring devices were properly applied by Entergy in its output verification.
The inspector reviewed the current radiation output values for Entergys portable survey and area radiation monitor instrument calibrator units, a bench calibrator (N-273) and a box calibrator (N-360). The inspector assessed whether Entergy periodically verified calibrator output over the range of the exposure rates/dose rates using an ion chamber or an electrometer. The inspector assessed whether the measuring devices had been calibrated by a facility using National Institute of Standards and Technology (NIST)traceable sources and whether decay correction factors for these measuring devices were properly applied by Entergy in its output verification.
Line 335: Line 427:


===.10 Calibration and Check Sources===
===.10 Calibration and Check Sources===
====a. Inspection Scope====
====a. Inspection Scope====
The inspector reviewed Entergys source term or waste stream characterization per 10 CFR Part 61, Licensing Requirements for Land Disposal of Radioactive Waste, to assess whether calibration sources used were representative of the types and energies of radiation encountered in the plant.
The inspector reviewed Entergys source term or waste stream characterization per 10 CFR Part 61, Licensing Requirements for Land Disposal of Radioactive Waste, to assess whether calibration sources used were representative of the types and energies of radiation encountered in the plant.
Line 343: Line 434:


===.11 Problem Identification and Resolution===
===.11 Problem Identification and Resolution===
====a. Inspection Scope====
====a. Inspection Scope====
The inspector evaluated whether problems associated with radiation monitoring instrumentation were being identified by Entergy at an appropriate threshold and were properly addressed for resolution in Entergys corrective action program (CAP). The inspector assessed the appropriateness of the corrective actions for a selected sample of problems documented by Entergy that involve radiation monitoring instrumentation.
The inspector evaluated whether problems associated with radiation monitoring instrumentation were being identified by Entergy at an appropriate threshold and were properly addressed for resolution in Entergys corrective action program (CAP). The inspector assessed the appropriateness of the corrective actions for a selected sample of problems documented by Entergy that involve radiation monitoring instrumentation.
Line 351: Line 441:


==OTHER ACTIVITIES==
==OTHER ACTIVITIES==
{{a|4OA1}}


{{a|4OA1}}
==4OA1 Performance Indicator Verification==
==4OA1 Performance Indicator Verification==
{{IP sample|IP=IP 71151|count=3}}
{{IP sample|IP=IP 71151|count=3}}


===Cornerstone: Mitigating Systems===
===Cornerstone: Mitigating Systems===
====a. Inspection Scope====
The inspectors reviewed Performance Indicator (PI) data to determine the accuracy and completeness of the reported data. The review was accomplished by comparing reported PI data to confirmatory plant records and data available in plant logs, CRs, Licensee Event Reports (LERs), and NRC inspection reports. The acceptance criteria used for the review included Nuclear Energy Institute (NEI) 99-02, Revision 6, Regulatory Assessment Performance Indicator Guidelines, and NUREG-1022, Revision 2, Event Report Guidelines 10 CFR 50.73. The following performance indicators were reviewed:
High pressure coolant injection system from the third quarter of 2011 through the second quarter of 2012 [MS07]
Heat removal system from the third quarter of 2011 through the second quarter of 2012 [MS08]


====a. Inspection Scope====
The inspectors reviewed Performance Indicator (PI) data to determine the accuracy and completeness of the reported data. The review was accomplished by comparing reported PI data to confirmatory plant records and data available in plant logs, CRs, Licensee Event Reports (LERs), and NRC inspection reports. The acceptance criteria used for the review included Nuclear Energy Institute (NEI) 99-02, Revision 6, Regulatory Assessment Performance Indicator Guidelines, and NUREG-1022, Revision 2, Event Report Guidelines 10 CFR 50.73. The following performance indicators were reviewed:
High pressure coolant injection system from the third quarter of 2011 through the second quarter of 2012 [MS07]
Heat removal system from the third quarter of 2011 through the second quarter of 2012 [MS08]
Residual heat removal system from the third quarter of 2011 through the second quarter of 2012 [MS09]
Residual heat removal system from the third quarter of 2011 through the second quarter of 2012 [MS09]


Line 367: Line 459:
No findings were identified.
No findings were identified.


{{a|4OA2}}
{{a|4OA2}}
 
==4OA2 Problem Identification and Resolution==
==4OA2 Problem Identification and Resolution==
{{IP sample|IP=IP 71152|count=2}}
{{IP sample|IP=IP 71152|count=2}}


===.1 Routine Review of Problem Identification and Resolution Activities===
===.1 Routine Review of Problem Identification and Resolution Activities===
====a. Inspection Scope====
====a. Inspection Scope====
As required by Inspection Procedure 71152, Problem Identification and Resolution, the inspectors routinely reviewed issues during baseline inspection activities and plant status reviews to verify that Entergy entered issues into the corrective action program at an appropriate threshold, gave adequate attention to timely corrective actions, and identified and addressed adverse trends. In order to assist with the identification of repetitive equipment failures and specific human performance issues for follow-up, the inspectors performed a daily screening of items entered into the corrective action program and periodically attended condition report group (CRG) screening meetings.
As required by Inspection Procedure 71152, Problem Identification and Resolution, the inspectors routinely reviewed issues during baseline inspection activities and plant status reviews to verify that Entergy entered issues into the corrective action program at an appropriate threshold, gave adequate attention to timely corrective actions, and identified and addressed adverse trends. In order to assist with the identification of repetitive equipment failures and specific human performance issues for follow-up, the inspectors performed a daily screening of items entered into the corrective action program and periodically attended condition report group (CRG) screening meetings.
Line 380: Line 472:


===.2 Annual Sample: Fitness For Duty===
===.2 Annual Sample: Fitness For Duty===
====a. Inspection Scope====
====a. Inspection Scope====
The inspector examined activities performed under Fitness-For-Duty (FFD) hours as an inspection sample for in-depth review to assess the corrective actions taken by Entergy when granting security officers FFD waivers under 10 CFR 26.207. The sample of FFD waivers reviewed was documented in Entergys corrective action program for evaluation and appropriate corrective actions were taken.
The inspector examined activities performed under Fitness-For-Duty (FFD) hours as an inspection sample for in-depth review to assess the corrective actions taken by Entergy when granting security officers FFD waivers under 10 CFR 26.207. The sample of FFD waivers reviewed was documented in Entergys corrective action program for evaluation and appropriate corrective actions were taken.
Line 392: Line 483:


===.3 Annual Sample: Operator Workarounds===
===.3 Annual Sample: Operator Workarounds===
====a. Inspection Scope====
====a. Inspection Scope====
The inspectors performed the annual review of operator workarounds to verify Entergy was identifying operator workaround problems at an appropriate threshold and entering them into the corrective action program. The inspectors reviewed identified workarounds to determine whether the mitigating system function was affected, whether the operators ability to implement abnormal and emergency operating procedures was affected, and whether appropriate procedures had been updated to reflect actual plant conditions. The inspection was accomplished through personnel interviews, plant tours, and review of station documents.
The inspectors performed the annual review of operator workarounds to verify Entergy was identifying operator workaround problems at an appropriate threshold and entering them into the corrective action program. The inspectors reviewed identified workarounds to determine whether the mitigating system function was affected, whether the operators ability to implement abnormal and emergency operating procedures was affected, and whether appropriate procedures had been updated to reflect actual plant conditions. The inspection was accomplished through personnel interviews, plant tours, and review of station documents.
Line 399: Line 489:
No findings were identified.
No findings were identified.


{{a|4OA3}}
{{a|4OA3}}
 
==4OA3 Follow-Up of Events and Notices of Enforcement Discretion==
==4OA3 Follow-Up of Events and Notices of Enforcement Discretion==
{{IP sample|IP=IP 71153|count=7}}
{{IP sample|IP=IP 71153|count=7}}


===.1 Operator and Maintenance Performance during a Downpower to Support Vital Motor===
===.1 Operator and Maintenance Performance during a Downpower to Support Vital Motor===
Generator (MG) Set DC Brush Replacement
Generator (MG) Set DC Brush Replacement


Line 414: Line 504:


===.2 Operator Performance during a Downpower to Support a Control Rod Pattern===
===.2 Operator Performance during a Downpower to Support a Control Rod Pattern===
Adjustment
Adjustment


Line 424: Line 513:


===.3 Operator and Maintenance Performance during a Repair of Main Generator Rectifier===
===.3 Operator and Maintenance Performance during a Repair of Main Generator Rectifier===
Bank #4
Bank #4


====a. Inspection Scope====
====a. Inspection Scope====
The inspectors observed an infrequently performed evolution on August 19. Specifically, the inspectors observed maintenance perform a repair on main generator rectifier bank
The inspectors observed an infrequently performed evolution on August 19. Specifically, the inspectors observed maintenance perform a repair on main generator rectifier bank  
      #4, which included installing a patch to secure a stator cooling water leak. In addition, the inspectors observed the brief, reviewed the contingency plan and operations procedures, and observed the work in the field.
#4, which included installing a patch to secure a stator cooling water leak. In addition, the inspectors observed the brief, reviewed the contingency plan and operations procedures, and observed the work in the field.


====b. Findings====
====b. Findings====
Line 435: Line 523:


===.4 Operator Performance during the loss of the B 2nd point Feedwater Heater during Y1===
===.4 Operator Performance during the loss of the B 2nd point Feedwater Heater during Y1===
fast transfer
fast transfer


Line 445: Line 532:


===.5 (Closed) Licensee Event Report (LER) 05000293/2012-001-00: Safety Relief Valves===
===.5 (Closed) Licensee Event Report (LER) 05000293/2012-001-00: Safety Relief Valves===
 
Test Pressure Exceeded Setpoint Limits The inspectors reviewed Entergys actions and reportability criteria associated with LER  
Test Pressure Exceeded Setpoint Limits The inspectors reviewed Entergys actions and reportability criteria associated with LER


===05000293/2012-001-00, which is addressed in CR-PNP-2011-5228. On March 28, Pilgrim was notified that three of four two-stage Target Rock Safety Relief Valve (SRV)pilot assemblies had exceeded the TS tolerance limit. These two stage SRVs were replaced with three-stage SRVs during Refueling Outage 18 (April 2011) to address sticking SRVs due to setpoint variance and corrosion bonding. In addition, the tolerance limit for the new SRVs was increased to 3 percent. This LER is closed.
===05000293/2012-001-00, which is addressed in CR-PNP-2011-5228. On March 28, Pilgrim was notified that three of four two-stage Target Rock Safety Relief Valve (SRV)pilot assemblies had exceeded the TS tolerance limit. These two stage SRVs were replaced with three-stage SRVs during Refueling Outage 18 (April 2011) to address sticking SRVs due to setpoint variance and corrosion bonding. In addition, the tolerance limit for the new SRVs was increased to 3 percent. This LER is closed.


===.6 (Closed) Licensee Event Report (LER) 05000293/2012-002-00: Manual Reactor Scram===
===.6 (Closed) Licensee Event Report (LER) 05000293/2012-002-00: Manual Reactor Scram===
Due to Degraded Condenser Vacuum
Due to Degraded Condenser Vacuum


Line 457: Line 542:
===
===
{{IP sample|IP=IP 05000|count=1}}
{{IP sample|IP=IP 05000|count=1}}
The inspectors reviewed Entergys actions associated with LER 05000293/2012-002-00, which are addressed in the corrective action program as CR-PNP-2012-2304. The event was discussed in NRC Inspection Report 05000293/2012003. The documents reviewed during the inspection are listed in the Attachment. This LER is closed with the following finding.
The inspectors reviewed Entergys actions associated with LER 05000293/2012-002-00, which are addressed in the corrective action program as CR-PNP-2012-2304. The event was discussed in NRC Inspection Report 05000293/2012003. The documents reviewed during the inspection are listed in the Attachment. This LER is closed with the following finding.


====b. Findings====
====b. Findings====
=====Introduction.=====
=====Introduction.=====
A finding of very low safety significance (Green) was identified for personnel not adequately classifying work in regards to processing an emergent work order. Specifically, personnel classified work on a reach rod position indication for valve 1-HO-163, SJAE steam supply valve, as minor maintenance which resulted in the failure to identify and correct the reach rod indicator and position. This resulted in a degraded vacuum during a power maneuver and a subsequent reactor scram.
A finding of very low safety significance (Green) was identified for personnel not adequately classifying work in regards to processing an emergent work order. Specifically, personnel classified work on a reach rod position indication for valve 1-HO-163, SJAE steam supply valve, as minor maintenance which resulted in the failure to identify and correct the reach rod indicator and position. This resulted in a degraded vacuum during a power maneuver and a subsequent reactor scram.
Line 473: Line 558:
=====Analysis.=====
=====Analysis.=====
The inspectors determined that not adequately classifying work for reach rod 1-HO-163 to the SJAE steam supply valve was a performance deficiency within Entergys ability to foresee and correct, and should have been prevented. This condition did not impact the regulatory process and did not contribute to any actual consequences; therefore, Traditional Enforcement did not apply. The finding was determined to be more than minor because it was associated with the Configuration Control (i.e.,
The inspectors determined that not adequately classifying work for reach rod 1-HO-163 to the SJAE steam supply valve was a performance deficiency within Entergys ability to foresee and correct, and should have been prevented. This condition did not impact the regulatory process and did not contribute to any actual consequences; therefore, Traditional Enforcement did not apply. The finding was determined to be more than minor because it was associated with the Configuration Control (i.e.,
Operating Equipment Lineup) attribute of the Initiating Events cornerstone, and adversely affected the cornerstones objective to limit the likelihood of those events that upset plant stability and challenge critical safety functions during power operations. The inspectors screened the issue for significance using IMC 0609.04, Phase 1 - Initiating Screening and Characterization of Findings, and IMC 0609 Appendix A, Exhibit 1, Initiating Events Screening. The finding was determined to be of very low safety significance (Green) because although the finding did cause a reactor scram, it did not cause a reactor scram combined with the loss of mitigating equipment relied upon to transition the plant from the onset of the trip to a stable shutdown condition. This finding has a cross-cutting aspect in the Human Performance cross-cutting area, Work Control component, because Entergy did not appropriately plan and coordinate the repair of the SJAE steam supply valve by incorporating the operational impact of the work activity consistent with nuclear safety. [H.3(b)]
Operating Equipment Lineup) attribute of the Initiating Events cornerstone, and adversely affected the cornerstones objective to limit the likelihood of those events that upset plant stability and challenge critical safety functions during power operations. The inspectors screened the issue for significance using IMC 0609.04, Phase 1 - Initiating Screening and Characterization of Findings, and IMC 0609 Appendix A, Exhibit 1, Initiating Events Screening. The finding was determined to be of very low safety significance (Green) because although the finding did cause a reactor scram, it did not cause a reactor scram combined with the loss of mitigating equipment relied upon to transition the plant from the onset of the trip to a stable shutdown condition. This finding has a cross-cutting aspect in the Human Performance cross-cutting area, Work Control component, because Entergy did not appropriately plan and coordinate the repair of the SJAE steam supply valve by incorporating the operational impact of the work activity consistent with nuclear safety. [H.3(b)]  


=====Enforcement.=====
=====Enforcement.=====
Line 479: Line 564:


===.7 (Closed) Licensee Event Report (LER) 05000293/2009-002-01: Failure to Meet===
===.7 (Closed) Licensee Event Report (LER) 05000293/2009-002-01: Failure to Meet===
Technical Specification Requirements for Secondary Containment


Technical Specification Requirements for Secondary Containment The inspectors reviewed Entergys actions and reportability criteria associated with LER revision 05000293/2009-002-01, which is also addressed in CR-PNP-2009-5295, CR-PNP-2009-5309 and in NRC Inspection Report 05000293/2010002. The revision updated the 10 CFR 50.73 reportability criteria section of the LER to reflect the appropriate reportability coding. This LER is closed.
The inspectors reviewed Entergys actions and reportability criteria associated with LER revision 05000293/2009-002-01, which is also addressed in CR-PNP-2009-5295, CR-PNP-2009-5309 and in NRC Inspection Report 05000293/2010002. The revision updated the 10 CFR 50.73 reportability criteria section of the LER to reflect the appropriate reportability coding. This LER is closed.


{{a|4OA5}}
{{a|4OA5}}
==4OA5 Other Activities==
==4OA5 Other Activities==
IP 92709 Licensee Strike Contingency Plans, IP 92711 Continued Implementation of Strike Plans During an Extended Strike, and IP 92712 Resumption of Normal Operations after a Strike
IP 92709 Licensee Strike Contingency Plans, IP 92711 Continued Implementation of Strike Plans During an Extended Strike, and IP 92712 Resumption of Normal Operations after a Strike


Line 498: Line 584:


===.2 Temporary Instruction 2515/187 - Inspection of Near-Term Task Force===
===.2 Temporary Instruction 2515/187 - Inspection of Near-Term Task Force===
Recommendation 2.3 - Flooding Walkdowns


Recommendation 2.3 - Flooding Walkdowns On September 24, inspectors commenced activities to independently verify that Entergy conducted external flood protection walkdown activities using an NRC-endorsed walkdown methodology. These flooding walkdowns are being performed at all sites in response to Enclosure 4 of a letter from the NRC to licensees entitled, Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident, dated March 12, 2012 (ADAMS Accession No.
On September 24, inspectors commenced activities to independently verify that Entergy conducted external flood protection walkdown activities using an NRC-endorsed walkdown methodology. These flooding walkdowns are being performed at all sites in response to Enclosure 4 of a letter from the NRC to licensees entitled, Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident, dated March 12, 2012 (ADAMS Accession No.


ML12053A340). The results of this temporary instruction will be documented in a future inspection report.
ML12053A340). The results of this temporary instruction will be documented in a future inspection report.


===.3 Temporary Instruction 2515/188 - Inspection of Near-Term Task Force===
===.3 Temporary Instruction 2515/188 - Inspection of Near-Term Task Force===
Recommendation 2.3 - Seismic Walkdowns


Recommendation 2.3 - Seismic Walkdowns On September 24, inspectors commenced activities to independently verify that Entergy conducted seismic walkdown activities using an NRC-endorsed seismic walkdown methodology. These seismic walkdowns are being performed at all sites in response to 3 of a letter from the NRC to licensees entitled, Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident, dated March 12, 2012 (ADAMS Accession No.
On September 24, inspectors commenced activities to independently verify that Entergy conducted seismic walkdown activities using an NRC-endorsed seismic walkdown methodology. These seismic walkdowns are being performed at all sites in response to 3 of a letter from the NRC to licensees entitled, Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident, dated March 12, 2012 (ADAMS Accession No.


ML12053A340). When complete, the results of this temporary instruction will be documented in a future inspection report.
ML12053A340). When complete, the results of this temporary instruction will be documented in a future inspection report.


{{a|4OA6}}
{{a|4OA6}}
==4OA6 Meetings, Including Exit==
==4OA6 Meetings, Including Exit==
On August 16, the inspector performed a radiation protection exit meeting and presented the results to Mr. Al Dodds, Nuclear Safety Assurance Director. At the exit meeting, the inspector confirmed that no proprietary information was provided to the inspector.
On August 16, the inspector performed a radiation protection exit meeting and presented the results to Mr. Al Dodds, Nuclear Safety Assurance Director. At the exit meeting, the inspector confirmed that no proprietary information was provided to the inspector.


Line 521: Line 609:


==KEY POINTS OF CONTACT==
==KEY POINTS OF CONTACT==
Entergy Personnel
Entergy Personnel
G. Blankenbiller Chemistry Manager
G. Blankenbiller
G. Bradley       Component Engineering
Chemistry Manager
: [[contact::D. Brugman       Supervisor]], ALARA/Technical Support
G. Bradley
D. Burke         Protective Service Department Section Manager
Component Engineering
B. Chenard       System Engineering Manager
D. Brugman
B. Clow           Radiation Protection Technician
Supervisor, ALARA/Technical Support
S. Colburn       Supervisor Access Authorization and Fitness for Duty
D. Burke
J. Cox           Supervisor Radiation Protection Operations
Protective Service Department Section Manager
J. Dent           General Manager Plant Operations
B. Chenard
A. Dodds         Director Nuclear Safety Assurance
System Engineering Manager
K. Drown         Nuclear Oversight Manager
B. Clow
V. Fallacara     Engineering Director
Radiation Protection Technician
A. Felix         Auxiliary Operator
S. Colburn
J. Fitzsimmons   Radiation Protection Supervisor
Supervisor Access Authorization and Fitness for Duty
M. Gatslick       Sr. Security Compliance Supervisor
J. Cox
R. German         Reactor Operator
Supervisor Radiation Protection Operations
R. Hargat         Senior Radiation Protection Technician
J. Dent
T. Hatch         I&C Superintendent
General Manager Plant Operations
R. Heckman       Senior Radiation Protection Technician
A. Dodds
J. House         Superintendent Initial Operations Training
Director Nuclear Safety Assurance
W. Lobo           Licensing Engineer
K. Drown
J. Lynch         Licensing Manager
Nuclear Oversight Manager
J. Macdonald     Assistant Operations Manager-Shift
V. Fallacara
J. McClellan     Quality Assurance Assessor
Engineering Director
: [[contact::M. McDonnell     Assistant Operations Manager]], Support
A. Felix
T. McElhinney     Training Manager
Auxiliary Operator
: [[contact::D. Mannai         Senior Manager]], Nuclear Safety and Licensing
J. Fitzsimmons
W. Mauro         Supervisor Radiation Protection Support
Radiation Protection Supervisor
J. Miketa         Senior Radiation Protection Technician
M. Gatslick
: [[contact::A. Muse           Superintendent]], Operations Training
Sr. Security Compliance Supervisor
D. Noyes         Operations Manager
R. German
J. Priest         Radiation Protection Manager
Reactor Operator
: [[contact::S. Purdy         Superintendent]], Plant Security
R. Hargat
R. Smith         Site Vice President
Senior Radiation Protection Technician
W. Smith         Chemistry Supervisor
T. Hatch
J. Taormina       Maintenance Manager
I&C Superintendent
M. Thornhill     Radiation Protection Supervisor
R. Heckman
D. Twomey         Senior Radiation Protection Technician
Senior Radiation Protection Technician
J. Whalley       Operations Shift Manager
J. House
T. White         Emergency Planning Manager
Superintendent Initial Operations Training
: [[contact::J. Yingling       Senior Engineer]], Systems Engineering
W. Lobo
Licensing Engineer
J. Lynch
Licensing Manager
J. Macdonald
Assistant Operations Manager-Shift
J. McClellan
Quality Assurance Assessor
M. McDonnell
Assistant Operations Manager, Support
T. McElhinney
Training Manager
D. Mannai
Senior Manager, Nuclear Safety and Licensing
W. Mauro
Supervisor Radiation Protection Support
J. Miketa
Senior Radiation Protection Technician
A. Muse
Superintendent, Operations Training
D. Noyes
Operations Manager
J. Priest
Radiation Protection Manager
S. Purdy
Superintendent, Plant Security
R. Smith
Site Vice President
W. Smith
Chemistry Supervisor
J. Taormina
Maintenance Manager
M. Thornhill
Radiation Protection Supervisor
D. Twomey
Senior Radiation Protection Technician
J. Whalley
Operations Shift Manager
T. White
Emergency Planning Manager
J. Yingling
Senior Engineer, Systems Engineering  


==LIST OF ITEMS OPENED, CLOSED, DISCUSSED, AND UPDATED==
==LIST OF ITEMS OPENED, CLOSED, DISCUSSED, AND UPDATED==
===Opened/Closed===
: 05000293/2012004-01 FIN


===Opened/Closed===
Inadequate Processing of Work Package Results  
: 05000293/2012004-01    FIN        Inadequate Processing of Work Package Results in Reactor Scram (Section 4OA3)
 
in Reactor Scram (Section 4OA3)  


===Closed===
===Closed===
: 05000293/2012001-00     LER       Safety Relief Valves Test Pressure Exceeded Setpoint Limits (Section 4OA3)
: 05000293/2012001-00 LER  
: 05000293/2012002-00     LER       Manual Reactor Scram Due to Degraded Condenser Vacuum (Section 4OA3)
 
: 05000293/2009002-01     LER       Failure to Meet Technical Specification Requirements for Secondary Containment (Section 4OA3)
Safety Relief Valves Test Pressure Exceeded  
 
Setpoint Limits (Section 4OA3)  
: 05000293/2012002-00 LER  
 
Manual Reactor Scram Due to Degraded  
 
Condenser Vacuum (Section 4OA3)  
: 05000293/2009002-01 LER  
 
Failure to Meet Technical Specification Requirements for Secondary Containment (Section 4OA3)  


==LIST OF DOCUMENTS REVIEWED==
==LIST OF DOCUMENTS REVIEWED==


}}
}}

Latest revision as of 21:27, 11 January 2025

IR 05000293-12-004; 07/01/2012-09/30/2012; Pilgrim Nuclear Power Station; Follow-Up of Events and Notices of Enforcement Discretion
ML12305A220
Person / Time
Site: Pilgrim
Issue date: 10/31/2012
From: Ronald Bellamy
NRC/RGN-I/DRP/PB5
To: Rich Smith
Entergy Nuclear Operations
Bellamy R
References
IR-12-004
Download: ML12305A220 (36)


Text

October 31, 2012

SUBJECT:

PILGRIM NUCLEAR POWER STATION - NRC INTEGRATED INSPECTION REPORT 05000293/2012004

Dear Mr. Smith:

On September 30, 2012, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Pilgrim Nuclear Power Station (PNPS). The enclosed inspection report documents the inspection results, which were discussed on October 9 with you and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

This report documents one self-revealing finding of very low safety significance (Green). This self-revealing finding was determined to not involve a violation of NRC requirements. If you disagree with the cross-cutting aspect assigned to the finding in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the Regional Administrator, Region I, and the NRC Senior Resident Inspector at PNPS.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs Agencywide Documents Access Management System (ADAMS). ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Ronald R. Bellamy, Chief Reactor Projects Branch 5 Division of Reactor Projects

Docket Nos.: 50-293 License Nos.: DPR-35

Enclosure:

Inspection Report 05000293/2012004

w/Attachment: Supplementary Information

REGION I==

Docket Nos.:

50-293

License Nos.:

DPR-35

Report No.:

05000293/2012004

Licensee:

Entergy Nuclear Operations, Inc.

Facility:

Pilgrim Nuclear Power Station (PNPS)

Location:

600 Rocky Hill Road

Plymouth, MA 02360

Dates:

July 1, 2012 through September 30, 2012

Inspectors:

M. Schneider, Senior Resident Inspector, Division of Reactor Projects (DRP)

B. Smith, Resident Inspector, DRP

T. Moslak, Health Physicist, Division of Reactor Safety (DRS)

M. Patel, Reactor Engineer, DRS S. Rutenkroger, Senior Resident Inspector at Vermont Yankee, DRP G. Smith, Physical Security Inspector, DRS

Approved By:

Ronald R. Bellamy, Chief

Reactor Projects Branch 5

Division of Reactor Projects

Enclosure

SUMMARY OF FINDINGS

IR 05000293/2012004; 07/01/201209/30/2012; Pilgrim Nuclear Power Station; Follow-Up of

Events and Notices of Enforcement Discretion.

This report covered a three-month period of inspection by resident inspectors and announced inspections performed by regional inspectors. One finding of very low safety significance (Green) was identified. The significance of most findings is indicated by their color (Green,

White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609, Significance Determination Process (SDP). The cross-cutting aspect for this finding was determined using IMC 0310,

Components Within Cross-Cutting Areas. Findings for which the SDP does not apply may be Green, or be assigned a severity level after NRC management review. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, Revision 4, dated December 2006.

Cornerstone: Initiating Events

Green.

A finding of very low safety significance (Green) was identified for personnel not adequately classifying work in regards to processing an emergent work order. Specifically, personnel classified work on a reach rod position indication for valve 1-HO-163, Steam Jet Air Ejector (SJAE) steam supply valve, as minor maintenance, which resulted in the failure to identify and correct the reach rod indicator and position. This resulted in a degraded vacuum during a power maneuver and a subsequent reactor scram. Entergy entered this issue in the corrective action program (CR-PNP-2012-2304).

The finding was determined to be more than minor because it was associated with the Configuration Control (i.e., Operating Equipment Lineup) attribute of the Initiating Events cornerstone, and adversely affected the cornerstones objective to limit the likelihood of those events that upset plant stability and challenge critical safety functions during power operations.

The inspectors screened the issue for significance using IMC 0609.04, Phase 1 - Initiating Screening and Characterization of Findings and IMC 0609 Appendix A, Exhibit 1, Initiating Events Screening. The finding was determined to be of very low safety significance (Green)because although the performance deficiency did result in a reactor scram, it did not cause a reactor scram combined with the loss of mitigating equipment relied upon to transition the plant from the onset of the trip to a stable shutdown condition. This finding has a cross-cutting aspect in the Human Performance cross-cutting area, Work Control component, because Entergy did not appropriately plan and coordinate the repair of the SJAE steam supply valve by incorporating the operational impact of the work activity consistent with nuclear safety. H.3(b)

(Section 4OA3)

REPORT DETAILS

Summary of Plant Status

Pilgrim Nuclear Power Station began the inspection period operating at 33 percent reactor power. On July 2, 2012, Pilgrim returned to 100 percent reactor power following repairs to the main generator rectifier bank cooling system. On July 3, operators reduced reactor power to 76 percent to support a control rod pattern adjustment and returned to 100 percent reactor power later that same day. On July 12, operators reduced reactor power to 99 percent to support a brush replacement on the Vital Motor-Generator Set and returned to 100 percent reactor power following the evolution. On July 19, operators reduced power to 60 percent to perform a deep/shallow control rod sequence exchange and returned to 100 percent reactor power.

Following the deep/shallow sequence exchange, on July 20, operators reduced power to 91 percent to support a subsequent control rod pattern adjustment and then returned to 100 percent reactor power. On August 22, operators reduced reactor power to 50 percent to perform a thermal backwash of the main condenser. On August 23, Pilgrim returned to 100 percent reactor power. On August 24, operators reduced reactor power to 88 percent to perform a control rod pattern adjustment and returned to 100 percent reactor power later that same day. On September 22, operators reduced reactor power to 68 percent in response to a fast transfer of the 120VAC non-safety related bus and loss of a feedwater heater. Pilgrim returned to 100 percent reactor power and remained at or near 100 percent through the end of the inspection period.

REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity

==1R04 Equipment Alignment

==

.1 Partial System Walkdowns

a. Inspection Scope

The inspectors performed partial walkdowns of the following systems:

B emergency diesel generator (EDG) during maintenance on the A core spray (CS) system

A CS system during testing on the B CS system

Station blackout diesel generator manual fuel oil transfer system

The inspectors selected these systems based on their risk-significance relative to the reactor safety cornerstones at the time they were inspected. The inspectors reviewed applicable operating procedures, system diagrams, the Updated Final Safety Analysis Report (UFSAR), technical specifications (TS), work orders, condition reports, and the impact of ongoing work activities on redundant trains of equipment in order to identify conditions that could have impacted system performance of their intended safety functions. The inspectors also performed field walkdowns of accessible portions of the systems to verify system components and support equipment were aligned correctly and were operable. The inspectors examined the material condition of the components and observed operating parameters of equipment to verify that there were no deficiencies.

The inspectors also reviewed whether Entergy staff had properly identified equipment issues and entered them into the corrective action program for resolution with the appropriate significance characterization.

b. Findings

No findings were identified.

.2 Full System Walkdown

a. Inspection Scope

During the week of September 24, the inspectors performed a complete system walkdown of accessible portions of the salt service water system to verify the existing equipment lineup was correct. The inspectors reviewed operating procedures, drawings, equipment line-up check-off lists, and the UFSAR to verify the system was aligned to perform its required safety functions. The inspectors also reviewed electrical power availability, hangar and support functionality, applicable temporary modifications, and operability of support systems. The inspectors performed field walkdowns of accessible portions of the system to verify system components and support equipment were aligned correctly and operable. The inspectors examined the material condition of the components and observed operating parameters of equipment to verify that there were no deficiencies. Additionally, the inspectors reviewed a sample of related condition reports and work orders to ensure Entergy appropriately evaluated and resolved any deficiencies.

b. Findings

No findings were identified.

==1R05 Fire Protection

Resident Inspector Quarterly Walkdowns (71111.05Q - 5 samples)

==

a. Inspection Scope

The inspectors performed tours of the areas listed below to assess the material condition and operational status of fire protection features. The inspectors verified that Entergy controlled combustible materials and ignition sources in accordance with administrative procedures. The inspectors verified that fire protection and suppression equipment was available for use as specified in the area pre-fire plan, and passive fire barriers were maintained in good material condition. The inspectors also verified that station personnel implemented compensatory measures for out-of-service, degraded, or inoperable fire protection equipment, as applicable, in accordance with procedures.

Fire Area 1.9, Fire Zone 1.6, control rod drive (CRD) pump quadrant

Fire Area 1.9, Fire Zone 1.9, CRD hydraulic control units, east side

Fire Area 1.10, Fire Zone 2.11, feedwater pump A area

Fire Area 3.3, Fire Zone 3.3, plant computer room

Fire Area 5.3, Fire Zone 5.3, C salt service water pump room

b. Findings

No findings were identified.

==1R07 Heat Sink Performance (711111.07A - 1 sample)

a. Inspection Scope

==

The inspectors reviewed one sample of Entergys program for maintenance, testing, and monitoring of risk significant heat exchangers (HXs) to assess the capability of the HXs to perform their design functions. The inspectors also evaluated whether potential common cause problems could affect multiple HXs. Based on its risk significance and performance history, the B residual heat removal heat exchanger was selected for detailed review by the inspectors.

b. Findings

No findings were identified.

1R11 Licensed Operator Requalification Program

.1 Requalification Review by Resident Inspectors

a. Inspection Scope

The inspectors observed licensed operator simulator as found training on August 20, which included a loss of offsite power event complicated by the loss of an emergency diesel generator and a small break loss of coolant accident. The inspectors evaluated operator performance during the simulated events and verified completion of risk significant operator actions, including the use of abnormal and emergency operating procedures. The inspectors verified that emergency classifications within the scenario were declared accurately and timely. The inspectors assessed the clarity and effectiveness of communications, implementation of actions in response to alarms and degrading plant conditions, and the oversight and direction provided by the Control Room Supervisor. Additionally, the inspectors assessed the ability of the crew and training staff to identify and document crew performance problems. Finally, the inspectors performed a simulator fidelity review to determine if the arrangement of the simulator instrumentation, controls, and tagging closely paralleled that of the control room.

b. Findings

No findings were identified.

.2 Main Control Room Review by Resident Inspectors

a. Inspection Scope

The inspectors observed main control room activities during replacement of a vital motor generator set DC brush, a control rod pattern adjustment, repair of main generator rectifier bank #4, and the restoration from the loss of a feedwater heater during a 120VAC power supply fast transfer. See section 4OA3 for specific discussion of these activities. The inspectors reviewed procedural guidance for station power changes and the power maneuver plan, and observed control room conduct and control of these evolutions.

b. Findings

No findings were identified.

1R12 Maintenance Effectiveness

a. Inspection Scope

The inspectors reviewed the two samples listed below to assess the effectiveness of maintenance activities on structures, systems, and components (SSC) performance and reliability. The inspectors reviewed system health reports, corrective action program documents, maintenance work orders, and maintenance rule basis documents to ensure that Entergy was identifying and properly evaluating performance problems within the scope of the maintenance rule. For each sample selected, the inspectors verified that the SSC was properly scoped into the maintenance rule in accordance with 10 CFR 50.65 and verified that the (a)(2) performance criteria established by Entergy staff was reasonable. As applicable, for SSCs classified as (a)(1), the inspectors assessed the adequacy of goals and corrective actions to return these SSCs to (a)(2). Additionally, the inspectors ensured that Entergy staff was identifying and addressing common cause failures that occurred within and across maintenance rule system boundaries.

(a)(1) evaluation of emergency lighting exceeding functional failure performance criteria

(a)(1) evaluation for repeat failures of the K-117 diesel driven air compressor

b. Findings

No findings were identified.

1R13 Maintenance Risk Assessments and Emergent Work Control

a. Inspection Scope

The inspectors reviewed station evaluation and management of plant risk for the maintenance and emergent work activities listed below to verify that Entergy performed the appropriate risk assessments prior to removing equipment for work. The inspectors selected these activities based on potential risk significance relative to the reactor safety cornerstones. As applicable for each activity, the inspectors verified that Entergy personnel performed risk assessments as required by 10 CFR 50.65(a)(4) and that the assessments were accurate and complete. When Entergy performed emergent work, the inspectors verified that operations personnel promptly assessed and managed plant risk. The inspectors reviewed the scope of maintenance work and discussed the results of the assessment with the stations probabilistic risk analyst to verify plant conditions were consistent with the risk assessment. The inspectors also reviewed the TS requirements and inspected portions of redundant safety systems, when applicable, to verify risk analysis assumptions were valid and applicable requirements were met.

Green risk during Y1 on its alternate power supply and the second point feedwater heater B out of service

Yellow risk for maintenance and testing on the B residual heat removal system

Yellow risk for maintenance and testing on the shutdown transformer and station blackout diesel generator

Yellow risk for the high pressure coolant injection system out of service and in the presence of main generator rectifier bank leakage.

b. Findings

No findings were identified.

1R15 Operability Determinations and Functionality Assessments

a. Inspection Scope

The inspectors reviewed operability determinations for the following degraded or non-conforming conditions:

Drywell floor sump monitoring equipment not functioning properly

First point feedwater heater leak and Operational Decision-Making Issue (ODMI)

Increased hotwell conductivity ODMI

Standby liquid control tank level increased approximately 300 gallons

Three local power range monitors failed calibration

The inspectors selected these issues based on the risk significance of the associated components and systems. The inspectors evaluated the technical adequacy of the operability determinations to assess whether TS operability was properly justified and the subject component or system remained available such that no unrecognized increase in risk occurred. The inspectors compared the operability and design criteria in the appropriate sections of the TS and UFSAR to Entergys evaluations to determine whether the components or systems were operable. Where compensatory measures were required to maintain operability, the inspectors determined whether the measures in place would function as intended and were properly controlled by Entergy. The inspectors determined, where appropriate, compliance with bounding limitations associated with the evaluations.

b. Findings

No findings were identified.

1R19 Post-Maintenance Testing

a. Inspection Scope

The inspectors reviewed the post-maintenance tests for the maintenance activities listed below to verify that procedures and test activities ensured system operability and functional capability. The inspectors reviewed the test procedure to verify that the procedure adequately tested the safety functions that may have been affected by the maintenance activity, that the acceptance criteria in the procedure was consistent with the information in the applicable licensing basis and/or design basis documents, and that the procedure had been properly reviewed and approved. The inspectors also witnessed the test or reviewed test data to verify that the test results adequately demonstrated restoration of the affected safety functions.

A control room high efficiency air filtration system temperature switch replacement

Reactor water clean-up motor operated valve maintenance

Rebuild B standby gas treatment system damper actuators

Replacement of vital motor generator set brushes

Residual heat removal torus cooling isolation valve MO-1001-34B maintenance

Removal of temporary modification and installation of thermal overloads for the A salt service water pump

b. Findings

No findings were identified.

1R22 Surveillance Testing

a. Inspection Scope

The inspectors observed performance of surveillance tests and/or reviewed test data of selected risk-significant SSCs to assess whether test results satisfied TS, the UFSAR, and Entergys procedure requirements. The inspectors verified that test acceptance criteria were clear, tests demonstrated operational readiness and were consistent with design documentation, test instrumentation had current calibrations and the range and accuracy for the application, tests were performed as written, and applicable test prerequisites were satisfied. Upon test completion, the inspectors considered whether the test results supported that equipment was capable of performing the required safety functions. The inspectors reviewed the following surveillance tests:

Vital bus protective relay functional test

A salt service water flow rate monthly surveillance

B core spray pump quarterly inservice test (IST)

A low pressure coolant injection system pump and valve quarterly IST

Main steam isolation valve operability (CIV)

b. Findings

No findings were identified.

RADIATION SAFETY

Cornerstones: Occupational Radiation Safety

2RS1 Radiological Hazard Assessment and Exposure Controls

a. Inspection Scope

During the period August 13 through 16, the inspector performed activities to verify that Entergy was evaluating, monitoring, and controlling radiological hazards for work performed, in locked high radiation areas (LHRA) and other radiological controlled areas.

Implementation of these controls was reviewed against the criteria contained in 10 CFR Part 20, TS, and Entergy=s procedures.

Radiological Hazards Control and Work Coverage

The inspector identified work performed in radiological controlled areas and evaluated Entergys assessment of the radiological hazards. Specific work activities evaluated included calibrating a high activity source; i.e., forty-five

(45) curies of Iridium-192 (Ir-192), and using this source to calibrate high range instruments, such as the turbine building vent monitors and the steam jet air ejector (SJAE) monitors. These activities were classified by Entergy as an Infrequently Performed Test/Evolution (IPTE) and additional administrative controls were implemented.

The inspector attended the pre-job briefings for these tasks and evaluated the survey maps, postings, barrier controls, electronic dosimeter dose/dose rate alarm setpoints, and associated radiation work permits (RWP), to determine if the exposure controls were acceptable. The inspector assessed the adequacy of instructions given to workers regarding the radiological conditions near the source location and the contingency plans.

Additionally, the inspector walked down the job sites and observed the work-in-progress for calibrating the radioactive source in the trash compactor building, and the calibration of the SJAE high range monitors in the turbine building.

b. Findings

No findings were identified.

2RS5 Radiation Monitoring Instrumentation

This area was inspected August 13 through 16, to verify that Entergy is assuring the accuracy and operability of radiation monitoring instruments used to protect occupational workers and to protect the public from nuclear power plant operations. The inspector used the requirements in 10 CFR Part 20, 10 CFR Part 50, Appendix A, Criterion 60, Control of Release of Radioactivity to the Environment, and Criterion 64 Monitoring Radioactive Releases; 10 CFR 50, Appendix I, Numerical Guides for Design Objectives and Limiting Conditions for Operation to meet the Criterion As Low as is Reasonably Achievable for Radioactive Material in Light-Water-Cooled Nuclear Power Reactor Effluents; 40 CFR Part 190, Environmental Radiation Protection Standards for Nuclear Power Operations; NUREG-0737, Clarification of Three Mile Island Corrective Action Requirements; TS/Offsite Dose Calculation Manual; applicable industry standards; and Entergys procedures required by TS, as criteria for determining compliance.

.1 Inspection Planning

a. Inspection Scope

The inspector reviewed the UFSAR to identify radiation instruments associated with monitoring area radiation, airborne radioactivity, process streams, effluents, materials/articles, and workers. Additionally, the inspector reviewed the associated TS requirements for post-accident monitoring instrumentation. The inspector reviewed a list of in-service survey instrumentation including air samplers and small article monitors (SAM), along with radiation monitoring instruments used to detect and analyze workers external contamination as well as external dose. Additionally, the inspector reviewed personnel contamination monitors and portal monitors including whole-body counters used to detect workers surface and internal contamination. The inspector assessed whether an adequate number and type of instruments were available to support operations.

The inspector reviewed Entergy and third-party evaluation reports of the radiation monitoring program since the last inspection.

The inspector reviewed procedures that govern instrument source checks and calibrations, focusing on instruments used for monitoring transient radiological conditions. The inspector reviewed the calibration and source check procedures for adequacy. The inspector reviewed the area radiation monitor alarm setpoint values and bases as provided in the TS and the UFSAR.

The inspector reviewed effluent monitor alarm setpoint bases and the calculation methods provided in the Offsite Dose Calculation Manual.

b. Findings

No findings were identified.

.2 Walkdowns and Observations

a. Inspection Scope

The inspector walked down the SJAE gaseous effluent radiation monitoring system (1705-3A/B) and the liquid radwaste monitor (1705-30). The inspector determined that the effluent/process monitor configurations aligned with descriptions contained in the UFSAR and Offsite Dose Calculation Manual.

The inspector selected seven portable survey instruments in use or available for issuance and assessed calibration and source check stickers for currency, instrument material condition and operability.

The inspector observed Entergy staff performance for source checks for three different types of portable survey instruments. These instruments included Ludlum 3/12, RO-20, and telepoles. The inspector assessed whether high-range instruments were source checked on all appropriate scales.

The inspector walked down three area radiation monitors and three continuous air monitors to determine whether they were appropriately positioned relative to the radiation sources or areas they were intended to monitor.

The inspector selected four personnel contamination monitors and two small article monitors and evaluated whether the periodic source checks were performed in accordance with Entergy procedures and the manufacturers recommendations.

b. Findings

No findings were identified.

.3 Calibration and Testing Program

Process and Effluent Monitors

a. Inspection Scope

The inspector selected three effluent monitor instruments and evaluated whether channel calibration and functional tests were performed consistent with TS and the Offsite Dose Calculation Manual. The inspector assessed whether

(a) Entergy calibrated its monitors with National Institute of Standards and Technology traceable sources;
(b) the primary calibrations adequately represented the plant nuclide mix; (c)when secondary calibration sources were used, the sources were verified by comparison with the primary calibration source; and
(d) Entergys channel calibrations encompassed the instruments alarm set-points.

The inspector assessed whether the effluent monitor alarm setpoints were established as provided in the Offsite Dose Calculation Manual and station procedures. For changes to effluent monitor setpoints, the inspector evaluated the basis for changes to ensure that an adequate justification exists.

b. Findings

No findings were identified.

.4 Laboratory Instrumentation

a. Inspection Scope

The inspector assessed laboratory instruments used for radiological analyses to determine whether daily performance checks and calibration data indicated that the frequency of the calibrations was adequate and there were no indications of degraded performance. The instrumentation inspected included three gamma spectroscopy systems and a scintillation counter.

The inspector assessed whether appropriate corrective actions were implemented in response to indications of degraded performance.

b. Findings

No findings were identified.

.5 Whole Body Counter

a. Inspection Scope

The inspector reviewed the methods and sources used to perform functional checks on the whole body counter (FastScan) before use and assessed whether check sources were appropriate and align with the plants isotopic mix.

The inspector reviewed calibration records for the whole body counter since the last inspection and evaluated whether calibration sources were representative of the plant radionuclide mix and that an appropriate calibration phantom was used. The inspector looked for anomalous results or other indications of instrument performance problems.

b. Findings

No findings were identified.

.6 Post-Accident Monitoring Instrumentation

a. Inspection Scope

The inspector reviewed the calibration documentation for the reactor building vent (RT-1001-609) high-range monitor. The inspector assessed whether an electronic calibration was completed for all range decades and was calibrated using an appropriate radiation source. The inspector assessed whether calibration acceptance criteria were reasonable, considering the large measuring range and the intended use of the instrument.

The inspector selected two high range effluent monitors, the reactor building vent and SJAE monitors, and evaluated the calibration and availability of these instruments, and observed the radiation source calibration of the SJAE detectors. The inspector reviewed Entergys capability to collect high-range, post-accident effluent samples.

b. Findings

No findings were identified.

.7 Portal Monitors, Personnel Contamination Monitors, and Small Article Monitors

a. Inspection Scope

The inspector selected two PM-7 and two ARGOS 4B portal monitors, two small article monitors (SAM), and observed the daily source checks and verified that the alarm setpoint values were reasonable under the circumstances to ensure that licensed material is not released from the site.

The inspector reviewed the calibration documentation for each selected instrument and reviewed the calibration methods to determine consistency with the manufacturers recommendations.

b. Findings

No findings were identified.

.8 Portable Survey Instruments, Area Radiation Monitors, Electronic Dosimetry, and Air

Samplers/Continuous Air Monitors

a. Inspection Scope

The inspector reviewed calibration documentation for a variety of portable instruments having ion chamber, Geiger tube, and sodium iodide detectors. For these portable survey instruments, the inspector reviewed detector measurement geometry and calibration methods and reviewed the source characterization data for the calibrator.

The inspector reviewed the calibration records for selected electronic dosimeters, continuous air samplers, and area monitors to determine that the instruments were calibrated within the required frequency and met the calibration acceptance criteria.

Area monitors reviewed included the spent fuel pool area, new fuel storage area, standby gas treatment system area, control room area, and condensate pump room.

b. Findings

No findings were identified.

.9 Instrument Calibrator

a. Inspection Scope

The inspector reviewed the current radiation output values for Entergys portable survey and area radiation monitor instrument calibrator units, a bench calibrator (N-273) and a box calibrator (N-360). The inspector assessed whether Entergy periodically verified calibrator output over the range of the exposure rates/dose rates using an ion chamber or an electrometer. The inspector assessed whether the measuring devices had been calibrated by a facility using National Institute of Standards and Technology (NIST)traceable sources and whether decay correction factors for these measuring devices were properly applied by Entergy in its output verification.

b. Findings

No findings were identified.

.10 Calibration and Check Sources

a. Inspection Scope

The inspector reviewed Entergys source term or waste stream characterization per 10 CFR Part 61, Licensing Requirements for Land Disposal of Radioactive Waste, to assess whether calibration sources used were representative of the types and energies of radiation encountered in the plant.

b. Findings

No findings were identified.

.11 Problem Identification and Resolution

a. Inspection Scope

The inspector evaluated whether problems associated with radiation monitoring instrumentation were being identified by Entergy at an appropriate threshold and were properly addressed for resolution in Entergys corrective action program (CAP). The inspector assessed the appropriateness of the corrective actions for a selected sample of problems documented by Entergy that involve radiation monitoring instrumentation.

b. Findings

No findings were identified.

OTHER ACTIVITIES

4OA1 Performance Indicator Verification

Cornerstone: Mitigating Systems

a. Inspection Scope

The inspectors reviewed Performance Indicator (PI) data to determine the accuracy and completeness of the reported data. The review was accomplished by comparing reported PI data to confirmatory plant records and data available in plant logs, CRs, Licensee Event Reports (LERs), and NRC inspection reports. The acceptance criteria used for the review included Nuclear Energy Institute (NEI) 99-02, Revision 6, Regulatory Assessment Performance Indicator Guidelines, and NUREG-1022, Revision 2, Event Report Guidelines 10 CFR 50.73. The following performance indicators were reviewed:

High pressure coolant injection system from the third quarter of 2011 through the second quarter of 2012 [MS07]

Heat removal system from the third quarter of 2011 through the second quarter of 2012 [MS08]

Residual heat removal system from the third quarter of 2011 through the second quarter of 2012 [MS09]

b. Findings

No findings were identified.

4OA2 Problem Identification and Resolution

.1 Routine Review of Problem Identification and Resolution Activities

a. Inspection Scope

As required by Inspection Procedure 71152, Problem Identification and Resolution, the inspectors routinely reviewed issues during baseline inspection activities and plant status reviews to verify that Entergy entered issues into the corrective action program at an appropriate threshold, gave adequate attention to timely corrective actions, and identified and addressed adverse trends. In order to assist with the identification of repetitive equipment failures and specific human performance issues for follow-up, the inspectors performed a daily screening of items entered into the corrective action program and periodically attended condition report group (CRG) screening meetings.

b. Findings

No findings were identified.

.2 Annual Sample: Fitness For Duty

a. Inspection Scope

The inspector examined activities performed under Fitness-For-Duty (FFD) hours as an inspection sample for in-depth review to assess the corrective actions taken by Entergy when granting security officers FFD waivers under 10 CFR 26.207. The sample of FFD waivers reviewed was documented in Entergys corrective action program for evaluation and appropriate corrective actions were taken.

The inspector reviewed CRs, FFD waivers, fatigue assessments, work schedules, and interviewed security officers. The inspector assessed Entergys problem identification, evaluation, and corrective action effectiveness to ensure security force personnel were not assigned to duty while in a fatigued condition that could have reduced their alertness or ability to perform functions necessary to identify and promptly respond to plant security threats.

b. Findings and Observations

Entergy granted FFD waivers in accordance with 10 CFR 26 207(a) (1)(i). However, Entergy did not document the specific circumstances on the FFD waiver requiring waivers to be granted. CR-PNP-2012-3906 was issued to document this observation.

The inspectors determined that this did not represent a violation of NRC requirements.

.3 Annual Sample: Operator Workarounds

a. Inspection Scope

The inspectors performed the annual review of operator workarounds to verify Entergy was identifying operator workaround problems at an appropriate threshold and entering them into the corrective action program. The inspectors reviewed identified workarounds to determine whether the mitigating system function was affected, whether the operators ability to implement abnormal and emergency operating procedures was affected, and whether appropriate procedures had been updated to reflect actual plant conditions. The inspection was accomplished through personnel interviews, plant tours, and review of station documents.

b. Findings and Observations

No findings were identified.

4OA3 Follow-Up of Events and Notices of Enforcement Discretion

.1 Operator and Maintenance Performance during a Downpower to Support Vital Motor

Generator (MG) Set DC Brush Replacement

a. Inspection Scope

The inspectors observed an infrequently performed evolution on July 12. Specifically, the inspectors observed an approximate one percent downpower to support locking up the recirculation pumps scoop tube positioner in order to preclude an increase in recirculation pump speed and resultant power increase should the alternating current (AC) power supply to the vital MG set be lost. In addition, the inspectors observed the brief, reviewed electrician qualifications, and observed the work in the field.

b. Findings

No findings were identified.

.2 Operator Performance during a Downpower to Support a Control Rod Pattern

Adjustment

a. Inspection Scope

The inspectors observed a planned downpower on July 19 to approximately 60 percent reactor power to support a control rod pattern adjustment. The inspectors reviewed procedural guidance for station power changes and the power maneuver plan, and observed control room operator conduct and control of the evolution.

b. Findings

No findings were identified.

.3 Operator and Maintenance Performance during a Repair of Main Generator Rectifier

Bank #4

a. Inspection Scope

The inspectors observed an infrequently performed evolution on August 19. Specifically, the inspectors observed maintenance perform a repair on main generator rectifier bank

  1. 4, which included installing a patch to secure a stator cooling water leak. In addition, the inspectors observed the brief, reviewed the contingency plan and operations procedures, and observed the work in the field.

b. Findings

No findings were identified.

.4 Operator Performance during the loss of the B 2nd point Feedwater Heater during Y1

fast transfer

a. Inspection Scope

The inspectors observed operator performance following the loss of the B 2nd point feedwater heater. On September 22, Pilgrims Y1 120 VAC electrical bus automatically transferred from its normal to its alternate power supply. During the transfer, the B 2nd point feedwater heater isolated and operators responded by lowering reactor power to 70 percent. The inspectors observed portions of the power maneuver back to 100 percent reactor power, reviewed operations procedures, and observed the evolutions in the control room.

b. Findings

No findings were identified.

.5 (Closed) Licensee Event Report (LER) 05000293/2012-001-00: Safety Relief Valves

Test Pressure Exceeded Setpoint Limits The inspectors reviewed Entergys actions and reportability criteria associated with LER

===05000293/2012-001-00, which is addressed in CR-PNP-2011-5228. On March 28, Pilgrim was notified that three of four two-stage Target Rock Safety Relief Valve (SRV)pilot assemblies had exceeded the TS tolerance limit. These two stage SRVs were replaced with three-stage SRVs during Refueling Outage 18 (April 2011) to address sticking SRVs due to setpoint variance and corrosion bonding. In addition, the tolerance limit for the new SRVs was increased to 3 percent. This LER is closed.

.6 (Closed) Licensee Event Report (LER) 05000293/2012-002-00: Manual Reactor Scram

Due to Degraded Condenser Vacuum

a. Inspection Scope

=

The inspectors reviewed Entergys actions associated with LER 05000293/2012-002-00, which are addressed in the corrective action program as CR-PNP-2012-2304. The event was discussed in NRC Inspection Report 05000293/2012003. The documents reviewed during the inspection are listed in the Attachment. This LER is closed with the following finding.

b. Findings

Introduction.

A finding of very low safety significance (Green) was identified for personnel not adequately classifying work in regards to processing an emergent work order. Specifically, personnel classified work on a reach rod position indication for valve 1-HO-163, SJAE steam supply valve, as minor maintenance which resulted in the failure to identify and correct the reach rod indicator and position. This resulted in a degraded vacuum during a power maneuver and a subsequent reactor scram.

Description.

On May 22, 2012, Entergy initiated a manual reactor scram while performing a thermal backwash on the main condenser when degrading condenser vacuum conditions became apparent (See NRC inspection report 05000293/2012003, Section 4OA3). Following the reactor scram, a root cause was performed and identified the cause of the scram to be a partially open SJAE steam supply valve, 1-HO-163. The partially open valve contributed to the loss of the SJAE inter-condenser loop seal and subsequent degrading main condenser vacuum. For the May 22 thermal backwash configuration, 1-HO-163s correct position would have been closed.

A discrepancy between 1-HO-163s reach rod position and actual position had been identified during the December 2011 forced outage. A work package was processed to correct this discrepancy; however, the classification of the package was inappropriately processed as minor maintenance. The work package did not contain sufficient work plan steps or post work test criteria to adequately address and correct the deficiency.

Furthermore, for a work package to be classified as minor maintenance per Entergys work process, the work requires that no complex work be performed and no plant configuration changes take place. This was not the case. The discrepancy was not resolved and the SJAE steam supply valve was left partially open during the planned thermal backwash.

Analysis.

The inspectors determined that not adequately classifying work for reach rod 1-HO-163 to the SJAE steam supply valve was a performance deficiency within Entergys ability to foresee and correct, and should have been prevented. This condition did not impact the regulatory process and did not contribute to any actual consequences; therefore, Traditional Enforcement did not apply. The finding was determined to be more than minor because it was associated with the Configuration Control (i.e.,

Operating Equipment Lineup) attribute of the Initiating Events cornerstone, and adversely affected the cornerstones objective to limit the likelihood of those events that upset plant stability and challenge critical safety functions during power operations. The inspectors screened the issue for significance using IMC 0609.04, Phase 1 - Initiating Screening and Characterization of Findings, and IMC 0609 Appendix A, Exhibit 1, Initiating Events Screening. The finding was determined to be of very low safety significance (Green) because although the finding did cause a reactor scram, it did not cause a reactor scram combined with the loss of mitigating equipment relied upon to transition the plant from the onset of the trip to a stable shutdown condition. This finding has a cross-cutting aspect in the Human Performance cross-cutting area, Work Control component, because Entergy did not appropriately plan and coordinate the repair of the SJAE steam supply valve by incorporating the operational impact of the work activity consistent with nuclear safety. H.3(b)

Enforcement.

This finding does not involve enforcement action because no violation of a regulatory requirement was identified. Corrective actions (CR-PNP-2012-2304) included applying a caution tag to the steam supply valve reach rod stating to verify position locally when position is changed, and incorporating into pre-outage training a case study that will enforce the expectation for effective work order screening in accordance with the requirements of Entergys work process. Because this finding does not involve a violation and has very low safety significance, it is identified as a finding (FIN). FIN 05000293/2012004-01, Inadequate Processing of Work Package Results in Reactor Scram

.7 (Closed) Licensee Event Report (LER) 05000293/2009-002-01: Failure to Meet

Technical Specification Requirements for Secondary Containment

The inspectors reviewed Entergys actions and reportability criteria associated with LER revision 05000293/2009-002-01, which is also addressed in CR-PNP-2009-5295, CR-PNP-2009-5309 and in NRC Inspection Report 05000293/2010002. The revision updated the 10 CFR 50.73 reportability criteria section of the LER to reflect the appropriate reportability coding. This LER is closed.

4OA5 Other Activities

IP 92709 Licensee Strike Contingency Plans, IP 92711 Continued Implementation of Strike Plans During an Extended Strike, and IP 92712 Resumption of Normal Operations after a Strike

a. Inspection Scope

Entergy developed a Staffing Contingency Plan to ensure a sufficient number of qualified personnel were available to continue operations in the event that the Utility Workers Union of America (UWUA), Local 369 personnel engaged in a job action upon the expiration of their contract on May 15, 2012. Using the guidance contained in NRC Inspection Procedure (IP) 92709, Licensee Strike Contingency Plans, the inspectors reviewed Entergys plans to address a potential job action at the site. The inspection included an evaluation of the Staffing Contingency Plan content and the actions needed to implement the plan; a review to determine whether the number of qualified personnel needed for the proper operation of the facility would be available; a review to determine if reactor operations would be maintained, as required, and; a review to determine if the plan complied with TS requirements and other NRC requirements. On May 15, Entergy and UWUA, Local 369 had not come to an agreement on a new contract. The existing contract was subsequently extended until a May 25 deadline. On May 25, Entergy and UWUA, Local 369 had not come to an agreement on a new contract and further extended the existing contract until June 5.

On June 5, Entergy and UWUA, Local 369 engaged in a job action. Using the guidance contained in IP 92711, Continued Implementation of Strike Plans during an Extended Strike, the resident inspectors, with supplemental inspectors from the Region 1 office, reviewed Entergys long term implementation of the strike contingency plans and verified that operations were proceeding in a safe manner during the strike. The inspectors implemented continuous coverage as specified in IP 92711 and observed contingency crews for operations, maintenance, health physics, and chemistry. By June 30, an agreement on a new contract between Entergy and UWUA, Local 369 had not been reached and the job action was still in place. The inspectors continued to implement IP 92711.

On July 7, Entergy and UWUA, Local 369 tentatively agreed to a new contract and union members approved the contract on July 8. During the reintegration of Entergy employees, the inspectors implemented IP 92712, Resumption of Normal Operations after a Strike, and verified that operations were proceeding in a safe manner.

b. Findings

No findings were identified.

.2 Temporary Instruction 2515/187 - Inspection of Near-Term Task Force

Recommendation 2.3 - Flooding Walkdowns

On September 24, inspectors commenced activities to independently verify that Entergy conducted external flood protection walkdown activities using an NRC-endorsed walkdown methodology. These flooding walkdowns are being performed at all sites in response to Enclosure 4 of a letter from the NRC to licensees entitled, Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident, dated March 12, 2012 (ADAMS Accession No.

ML12053A340). The results of this temporary instruction will be documented in a future inspection report.

.3 Temporary Instruction 2515/188 - Inspection of Near-Term Task Force

Recommendation 2.3 - Seismic Walkdowns

On September 24, inspectors commenced activities to independently verify that Entergy conducted seismic walkdown activities using an NRC-endorsed seismic walkdown methodology. These seismic walkdowns are being performed at all sites in response to 3 of a letter from the NRC to licensees entitled, Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident, dated March 12, 2012 (ADAMS Accession No.

ML12053A340). When complete, the results of this temporary instruction will be documented in a future inspection report.

4OA6 Meetings, Including Exit

On August 16, the inspector performed a radiation protection exit meeting and presented the results to Mr. Al Dodds, Nuclear Safety Assurance Director. At the exit meeting, the inspector confirmed that no proprietary information was provided to the inspector.

On October 9, the inspectors presented the inspection results to Mr. Robert Smith, Site Vice President, and other members of the PNPS staff. The inspectors verified that no proprietary information was retained by the inspectors or documented in this report.

ATTACHMENT:

SUPPLEMENTARY INFORMATION

KEY POINTS OF CONTACT

Entergy Personnel

G. Blankenbiller

Chemistry Manager

G. Bradley

Component Engineering

D. Brugman

Supervisor, ALARA/Technical Support

D. Burke

Protective Service Department Section Manager

B. Chenard

System Engineering Manager

B. Clow

Radiation Protection Technician

S. Colburn

Supervisor Access Authorization and Fitness for Duty

J. Cox

Supervisor Radiation Protection Operations

J. Dent

General Manager Plant Operations

A. Dodds

Director Nuclear Safety Assurance

K. Drown

Nuclear Oversight Manager

V. Fallacara

Engineering Director

A. Felix

Auxiliary Operator

J. Fitzsimmons

Radiation Protection Supervisor

M. Gatslick

Sr. Security Compliance Supervisor

R. German

Reactor Operator

R. Hargat

Senior Radiation Protection Technician

T. Hatch

I&C Superintendent

R. Heckman

Senior Radiation Protection Technician

J. House

Superintendent Initial Operations Training

W. Lobo

Licensing Engineer

J. Lynch

Licensing Manager

J. Macdonald

Assistant Operations Manager-Shift

J. McClellan

Quality Assurance Assessor

M. McDonnell

Assistant Operations Manager, Support

T. McElhinney

Training Manager

D. Mannai

Senior Manager, Nuclear Safety and Licensing

W. Mauro

Supervisor Radiation Protection Support

J. Miketa

Senior Radiation Protection Technician

A. Muse

Superintendent, Operations Training

D. Noyes

Operations Manager

J. Priest

Radiation Protection Manager

S. Purdy

Superintendent, Plant Security

R. Smith

Site Vice President

W. Smith

Chemistry Supervisor

J. Taormina

Maintenance Manager

M. Thornhill

Radiation Protection Supervisor

D. Twomey

Senior Radiation Protection Technician

J. Whalley

Operations Shift Manager

T. White

Emergency Planning Manager

J. Yingling

Senior Engineer, Systems Engineering

LIST OF ITEMS OPENED, CLOSED, DISCUSSED, AND UPDATED

Opened/Closed

05000293/2012004-01 FIN

Inadequate Processing of Work Package Results

in Reactor Scram (Section 4OA3)

Closed

05000293/2012001-00 LER

Safety Relief Valves Test Pressure Exceeded

Setpoint Limits (Section 4OA3)

05000293/2012002-00 LER

Manual Reactor Scram Due to Degraded

Condenser Vacuum (Section 4OA3)

05000293/2009002-01 LER

Failure to Meet Technical Specification Requirements for Secondary Containment (Section 4OA3)

LIST OF DOCUMENTS REVIEWED