Line 3: Line 3:
| issue date = 01/18/2013
| issue date = 01/18/2013
| title = Errata for Columbia Generating Station - NRC Security Inspection Report 05000397-12-201 - Cover Letter
| title = Errata for Columbia Generating Station - NRC Security Inspection Report 05000397-12-201 - Cover Letter
| author name = Buckley M J
| author name = Buckley M
| author affiliation = NRC/NSIR/DSO/DDSO/SPEB
| author affiliation = NRC/NSIR/DSO/DDSO/SPEB
| addressee name = Black A
| addressee name = Black A
Line 14: Line 14:
| page count = 2
| page count = 2
}}
}}
See also: [[followed by::IR 05000397/2012201]]
See also: [[see also::IR 05000397/2012201]]


=Text=
=Text=
{{#Wiki_filter:
{{#Wiki_filter:SAFEGUARDS INFORMATION
[[Issue date::January 18, 2013]]
SAFEGUARDS INFORMATION
January 18, 2013
Mr. Andy Black
Operations Support General Manager
Energy Northwest
Columbia Generating Station
PE-30
North Power Plant Loop
Richland, WA  99352
SUBJECT:  
ERRATA FOR COLUMBIA GENERATING STATION - NRC SECURITY
INSPECTION REPORT 05000397/2012201
Dear Mr. Black:  
This errata corrects the cover letter (page 1) and the enclosure (page 11) in the paragraph
under the section, Exit Meeting Summary, dated January 7, 2013, to include the date of the
telephonic re-exit meeting which occurred on December 20, 2012, with you and other members
of your staff.  Please replace the 1st page of the cover letter and the 11th page of the enclosure
with the enclosed revised pages. 
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs
Rules of Practice, a copy of this letter will be available electronically for public inspection in the
NRC Public Document Room or from the Publicly Available Records System (PARS)
component of the NRCs Agencywide Documents Access and Management System (ADAMS). 
ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html (the
Public Electronic Reading Room).
However, the material enclosed herewith contains Safeguards Information as defined by
10 CFR 73.21 and its disclosure to unauthorized individuals is prohibited by Section 147 of the
Atomic Energy Act of 1954, as amended.  Therefore, the material in the enclosure will not be
made available electronically for public inspection in the NRC Public Document Room or from
the PARS component of ADAMS.  If you choose to provide a response and Safeguards
Information is necessary to provide an acceptable response, please provide the level of
protection described in 10 CFR 73.21.  Otherwise, if Security-Related Information is necessary
to provide an acceptable response, please mark your entire response Security-Related
Information - Withhold from public disclosure under 10 CFR 2.390, in accordance with 
The enclosure transmitted herewith contains Safeguards Information.  When separated from
the enclosure, this transmittal document is decontrolled.


Mr. Andy Black Operations Support General Manager Energy Northwest Columbia Generating Station PE-30 North Power Plant Loop Richland, WA 99352
SAFEGUARDS INFORMATION
A. Black  
-2-
SAFEGUARDS INFORMATION
10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1).  In
accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your
response.
Sincerely,
/RA/
Michael J. Buckley, Acting Chief
Security Performance Evaluation Branch
Division of Security Operations  
Office of Nuclear Security and Incident Response
Docket No. 50-397
License No. NPF-21
Public Enclosure:  Errata page for Cover Letter for Inspection Report 05000397/2012201
Nonpublic Enclosure:  Errata page for Inspection Report 05000397/2012201 
cc w/enclosure:  C. Workman, Columbia Generating Station
cc w/o enclosure:  M. Reddemann, Columbia Generating Station


SUBJECT: ERRATA FOR COLUMBIA GENERATING STATION - NRC SECURITY INSPECTION REPORT 05000397/2012201


==Dear Mr. Black:==
  ML13015A166
This errata corrects the cover letter (page 1) and the enclosure (page 11) in the paragraph under the section, "Exit Meeting Summary," dated January 7, 2013, to include the date of the telephonic re-exit meeting which occurred on December 20, 2012, with you and other members of your staff. Please replace the 1st page of the cover letter and the 11th page of the enclosure with the enclosed revised pages.
OFFICE
 
NSIR/DSO NSIR/DSO/SPEB
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
RIV
 
NSIR/DSO/SPEB
However, the material enclosed herewith contains Safeguards Information as defined by 10 CFR 73.21 and its disclosure to unauthorized individuals is prohibited by Section 147 of the Atomic Energy Act of 1954, as amended. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of ADAMS. If you choose to provide a response and Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, if Security-Related Information is necessary to provide an acceptable response, please mark your entire response "Security-Related Information - Withhold from public disclosure under 10 CFR 2.390," in accordance with CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.
NAME
 
J. Curry
Sincerely,/RA/
D. Willis
Michael J. Buckley, Acting Chief Security Performance Evaluation Branch Division of Security Operations Office of Nuclear Security and Incident Response Docket No. 50-397 License No. NPF-21 Public
M. Haire
 
M. Buckley
===Enclosure:===
DATE
Errata page for Cover Letter for Inspection Report 05000397/2012201
1/15/13
 
1/18/13
Nonpublic
1/18/13
 
1/18/13
===Enclosure:===
Errata page for Inspection Report 05000397/2012201
 
cc w/enclosure: C. Workman, Columbia Generating Station cc w/o enclosure: M. Reddemann, Columbia Generating Station
}}
}}

Latest revision as of 19:15, 11 January 2025

Errata for Columbia Generating Station - NRC Security Inspection Report 05000397-12-201 - Cover Letter
ML13015A095
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 01/18/2013
From: Buckley M
NRC/NSIR/DSO/DDSO/SPEB
To: Black A
Energy Northwest
References
IR 2012201
Download: ML13015A095 (2)


See also: IR 05000397/2012201

Text

SAFEGUARDS INFORMATION

SAFEGUARDS INFORMATION

January 18, 2013

Mr. Andy Black

Operations Support General Manager

Energy Northwest

Columbia Generating Station

PE-30

North Power Plant Loop

Richland, WA 99352

SUBJECT:

ERRATA FOR COLUMBIA GENERATING STATION - NRC SECURITY

INSPECTION REPORT 05000397/2012201

Dear Mr. Black:

This errata corrects the cover letter (page 1) and the enclosure (page 11) in the paragraph

under the section, Exit Meeting Summary, dated January 7, 2013, to include the date of the

telephonic re-exit meeting which occurred on December 20, 2012, with you and other members

of your staff. Please replace the 1st page of the cover letter and the 11th page of the enclosure

with the enclosed revised pages.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs

Rules of Practice, a copy of this letter will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records System (PARS)

component of the NRCs Agencywide Documents Access and Management System (ADAMS).

ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html (the

Public Electronic Reading Room).

However, the material enclosed herewith contains Safeguards Information as defined by

10 CFR 73.21 and its disclosure to unauthorized individuals is prohibited by Section 147 of the

Atomic Energy Act of 1954, as amended. Therefore, the material in the enclosure will not be

made available electronically for public inspection in the NRC Public Document Room or from

the PARS component of ADAMS. If you choose to provide a response and Safeguards

Information is necessary to provide an acceptable response, please provide the level of

protection described in 10 CFR 73.21. Otherwise, if Security-Related Information is necessary

to provide an acceptable response, please mark your entire response Security-Related

Information - Withhold from public disclosure under 10 CFR 2.390, in accordance with

The enclosure transmitted herewith contains Safeguards Information. When separated from

the enclosure, this transmittal document is decontrolled.

SAFEGUARDS INFORMATION

A. Black

-2-

SAFEGUARDS INFORMATION

10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). In

accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your

response.

Sincerely,

/RA/

Michael J. Buckley, Acting Chief

Security Performance Evaluation Branch

Division of Security Operations

Office of Nuclear Security and Incident Response

Docket No. 50-397

License No. NPF-21

Public Enclosure: Errata page for Cover Letter for Inspection Report 05000397/2012201

Nonpublic Enclosure: Errata page for Inspection Report 05000397/2012201

cc w/enclosure: C. Workman, Columbia Generating Station

cc w/o enclosure: M. Reddemann, Columbia Generating Station

ML13015A166

OFFICE

NSIR/DSO NSIR/DSO/SPEB

RIV

NSIR/DSO/SPEB

NAME

J. Curry

D. Willis

M. Haire

M. Buckley

DATE

1/15/13

1/18/13

1/18/13

1/18/13