| issue date = 03/04/2013 | | issue date = 03/04/2013 | ||
| title = Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2012001 and 05000249/2012001) | | title = Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2012001 and 05000249/2012001) | ||
| author name = Cameron J | | author name = Cameron J | ||
| author affiliation = NRC/RGN-III/DRP/B6 | | author affiliation = NRC/RGN-III/DRP/B6 | ||
| addressee name = Pacilio M | | addressee name = Pacilio M | ||
| addressee affiliation = Exelon Generation Co, LLC, Exelon Nuclear | | addressee affiliation = Exelon Generation Co, LLC, Exelon Nuclear | ||
| docket = 05000237, 05000249 | | docket = 05000237, 05000249 | ||
| Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter: | {{#Wiki_filter:March 4, 2013 | ||
== | ==SUBJECT:== | ||
ANNUAL ASSESSMENT LETTER FOR DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 (REPORT 05000237/2012001 AND 05000249/2012001) | |||
==Dear Mr. Pacilio:== | ==Dear Mr. Pacilio:== | ||
On February 13, | On February 13, 2013, the NRC completed its end-of-cycle performance review of Dresden Nuclear Power Station, Units 2 and 3. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2012, through December 31, 2012. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. | ||
The NRC | The NRC determined that overall Dresden Nuclear Power Station, Units 2 and 3, operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Dresden Nuclear Power Station, Units 2 and 3, during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility. | ||
The | The enclosed inspection plan lists the inspections scheduled through December 31, 2014. | ||
Routine inspections performed by resident inspectors are not included in the inspection plan. | |||
The inspections listed during the last 12 months of the inspection plan are tentative and may be revised at the mid-cycle performance review. | The inspections listed during the last 12 months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence. The NRC also plans on performing special and infrequently performed inspections including: Inspection Procedure (IP) 71111.21, Component Design Basis Inspection, IP 71111.11B, Licensed Operator Requalification Program, IP 71152B, Problem Identification and Resolution, and Temporary Instruction (TI) 2515/182, Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). | ||
Please contact me at 630-829-9833 with any questions you may have regarding this letter or the inspection plan. | |||
Sincerely, | |||
/RA/ | |||
Jamnes L. Cameron, Chief Branch 6 Division of Reactor Projects | |||
Docket No. 50-237; 50-249 License No. DPR-19; DPR-25 | |||
- | |||
Enclosure: Dresden Nuclear Power Station Inspection/Activity Plan | |||
/ | |||
cc w/encl: Distribution via ListServ | |||
Distribution via ListServ | |||
}} | }} | ||
Latest revision as of 10:43, 11 January 2025
| ML13063A153 | |
| Person / Time | |
|---|---|
| Site: | Dresden |
| Issue date: | 03/04/2013 |
| From: | Jamnes Cameron NRC/RGN-III/DRP/B6 |
| To: | Pacilio M Exelon Generation Co, Exelon Nuclear |
| References | |
| IR-12-001 | |
| Download: ML13063A153 (6) | |
Text
March 4, 2013
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 (REPORT 05000237/2012001 AND 05000249/2012001)
Dear Mr. Pacilio:
On February 13, 2013, the NRC completed its end-of-cycle performance review of Dresden Nuclear Power Station, Units 2 and 3. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2012, through December 31, 2012. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined that overall Dresden Nuclear Power Station, Units 2 and 3, operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Dresden Nuclear Power Station, Units 2 and 3, during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through December 31, 2014.
Routine inspections performed by resident inspectors are not included in the inspection plan.
The inspections listed during the last 12 months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence. The NRC also plans on performing special and infrequently performed inspections including: Inspection Procedure (IP) 71111.21, Component Design Basis Inspection, IP 71111.11B, Licensed Operator Requalification Program, IP 71152B, Problem Identification and Resolution, and Temporary Instruction (TI) 2515/182, Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 630-829-9833 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Jamnes L. Cameron, Chief Branch 6 Division of Reactor Projects
Docket No. 50-237; 50-249 License No. DPR-19; DPR-25
Enclosure: Dresden Nuclear Power Station Inspection/Activity Plan
cc w/encl: Distribution via ListServ