ML13263A079: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
(One intermediate revision by the same user not shown)
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:ES-301                                 Competencies Checklist                         Form ES-301-6 Facility Davis Besse               Date of Exam 6/3 thru 6/14 2013             Operating Test No.: ___________
{{#Wiki_filter:NUREG-1021, Revision 9 Supplement 1 FENOC Facsimile Rev.1 ES-301 Competencies Checklist Form ES-301-6 Facility Davis Besse Date of Exam 6/3 thru 6/14 2013 Operating Test No.: ___________
APPLICANTS RO                         SRO-I                       SRO-U Competencies                     SCENARIO                     SCENARIO                   SCENARIO 1       2     3     4       1     2     3     4       1       2       3       4 1,3,4   1,3,4 1,3,1,3,4   1,2,1,3,4 1,3,4 1,3,4  1,2,1,3,4   1,3,1,3,4 Interpret/Diagnosis            5,6,7   5,6,5,6,7 5,6,4,5,6 5,6,7 5,6,5,6,7   4,5,5,6,7   5,6,5,6,7 8,9      8            8    7,8,9    8            8    7,8,9     8                8 Events and Conditions                                                                      10 10                            10 1,3,4   1,3,4 1,3,1,3,4   1,2,1,3,4 1,3,4 1,3,4  1,2,1,3,4   1,3,1,3,4 Comply With and                5,6,7   5,6,5,6,7 5,6,4,5,6 5,6,7 5,6,5,6,7   4,5,5,6,7   5,6,5,6,7 8,9      8            8    7,8,9    8            8    7,8,9    8                8 Use Procedures (1)              10                                                        10 10 1,3,4   1,3,4 1,3,1,4,5                               3,6,7   2,4,6   1,2,5   5,6,7 Operate Control                6,7,8   5,6,5,6,7 6,7,8                                8,9             6,7      8 9,10     8 Boards (2) 1,3,4   1,3,4 1,3,1,3,4   1,2,1,3,4 1,3,4 1,3,4  1,2,1,3,4   1,3,1,3,4 Communicate and                5,6,7   5,6,5,6,7 5,6,4,5,6 5,6,7 5,6,5,6,7   4,5,5,6,7   5,6,5,6,7 8,9      8            8    7,8,9    8            8    7,8,9     8                8 Interact                        10                                                        10 10 1,2,3  1,3,4 1,3,1,3,4   1,2,1,3,4   1,3,1,3,4 Demonstrate                                                  4,5,6 5,6,7 5,6,5,6,7   4,5,5,6,7   5,6,5,6,7 7,8,9    8            8    7,8,9    8                8 Supervisory Ability (3)                                       10                          10 2,5   1,5   2,4   3,4     2,5     1,5     2,4     3,4 Comply With and Use Tech. Specs. (3)
APPLICANTS RO SRO-I SRO-U Competencies SCENARIO SCENARIO SCENARIO 1
Notes:
2 3
4 1
2 3
4 1
2 3
4 Interpret/Diagnosis Events and Conditions 1,3,4 5,6,7 8,9 10 1,3,4 5,6,7 8
1,3,4 5,6,7 1,3,4 5,6,7 8
1,2,3 4,5,6 7,8,9 10 1,3,4 5,6,7 8
1,3,4 5,6,7 1,3,4 5,6,7 8
1,2,3 4,5,6 7,8,9 10 1,3,4 5,6,7 8
1,3,4 5,6,7 1,3,4 5,6,7 8
Comply With and Use Procedures (1) 1,3,4 5,6,7 8,9 10 1,3,4 5,6,7 8
1,3,4 5,6,7 1,3,4 5,6,7 8
1,2,3 4,5,6 7,8,9 10 1,3,4 5,6,7 8
1,3,4 5,6,7 1,3,4 5,6,7 8
1,2,3 4,5,6 7,8,9 10 1,3,4 5,6,7 8
1,3,4 5,6,7 1,3,4 5,6,7 8
Operate Control Boards (2) 1,3,4 6,7,8 9,10 1,3,4 5,6,7 8
1,3,4 5,6,7 1,4,5 6,7,8 3,6,7 8,9 2,4,6 1,2,5 6,7 5,6,7 8
Communicate and Interact 1,3,4 5,6,7 8,9 10 1,3,4 5,6,7 8
1,3,4 5,6,7 1,3,4 5,6,7 8
1,2,3 4,5,6 7,8,9 10 1,3,4 5,6,7 8
1,3,4 5,6,7 1,3,4 5,6,7 8
1,2,3 4,5,6 7,8,9 10 1,3,4 5,6,7 8
1,3,4 5,6,7 1,3,4 5,6,7 8
Demonstrate Supervisory Ability (3) 1,2,3 4,5,6 7,8,9 10 1,3,4 5,6,7 8
1,3,4 5,6,7 1,3,4 5,6,7 8
1,2,3 4,5,6 7,8,9 10 1,3,4 5,6,7 8
1,3,4 5,6,7 1,3,4 5,6,7 8
Comply With and Use Tech. Specs. (3) 2,5 1,5 2,4 3,4 2,5 1,5 2,4 3,4 Notes:
(1) Includes Technical Specification compliance for an RO.
(1) Includes Technical Specification compliance for an RO.
(2) Optional for an SRO-U.
(2) Optional for an SRO-U.
(3) Only applicable to SROs.
(3) Only applicable to SROs.
Instructions:
Instructions:
Check the applicant's license type and enter one or more event numbers that will allow the examiners to evaluate every applicable competency for every applicant.
Check the applicant's license type and enter one or more event numbers that will allow the examiners to evaluate every applicable competency for every applicant.  
NUREG-1021, Revision 9 Supplement 1                                                      FENOC Facsimile Rev.1


ES-301                                 Administrative Topics Outline                                         Form ES-301-1 Facility:   Davis Besse                                                 Date of Examination:_ 6/3 thru 6/14 2013 Examination Level RO                                                             Operating Test Number _
ES-301 Administrative Topics Outline Form ES-301-1 NUREG-1021, Revision 9 Supplement 1 FENOC Facsimile Rev. 1 Facility: Davis Besse Date of Examination:_ 6/3 thru 6/14 2013 Examination Level RO Operating Test Number _
Administrative Topic                 Type                               Describe activity to be performed Code*
Administrative Topic (See Note)
(See Note)
Type Code*
Conduct of                            D, R         2.1.43           (4.1)
Describe activity to be performed Conduct of Operations (RO A1.1)
Operations Ability to use procedures to determine the effects on reactivity of (RO A1.1)                                          plant changes, such as reactor coolant system temperature, secondary plant, fuel depletion, etc.
D, R 2.1.43 (4.1)
JPM 58           Calculate SDM with Tave > 500°F Conduct of                           N, R         2.1.7             (4.4)
Ability to use procedures to determine the effects on reactivity of plant changes, such as reactor coolant system temperature, secondary plant, fuel depletion, etc.
Operations Ability to evaluate plant performance and make operational (RO A1.2)                                          judgments based on operating characteristics, reactor behavior, and instrument interpretation.
JPM 58 Calculate SDM with Tave > 500°F Conduct of Operations (RO A1.2)
JPM New           Plot and evaluate 1/M data Equipment Control                     D, R         2.2.12           (3.7)
N, R 2.1.7 (4.4)
(RO A2)                                            Knowledge of surveillance procedures.
Ability to evaluate plant performance and make operational judgments based on operating characteristics, reactor behavior, and instrument interpretation.
JPM 227           Calculate RCS flow with F744 inoperable Radiation Control                     D, S         2.3.5             (2.9)
JPM New Plot and evaluate 1/M data Equipment Control (RO A2)
(RO A3)                                            Ability to use radiation monitoring systems, such as fixed radiation monitors and alarms, portable survey instruments, personnel monitoring equipment, etc.
D, R 2.2.12 (3.7)
JPM 260           Perform radiation element administrative checks for a radioactive liquid release Emergency                                         NOT EVALUATED Procedures/Plan NOTE: All items (5 total) are required for SROs. RO applicants require only 4 items unless they are retaking only the administrative topics, when all 5 are required.
Knowledge of surveillance procedures.
*Type Codes & Criteria                       (C)ontrol Room, (S)imulator, or Class(R)oom (D)irect from bank (< 3 for ROs; < 4 for SROs & RO retakes)
JPM 227 Calculate RCS flow with F744 inoperable Radiation Control (RO A3)
D, S 2.3.5 (2.9)
Ability to use radiation monitoring systems, such as fixed radiation monitors and alarms, portable survey instruments, personnel monitoring equipment, etc.
JPM 260 Perform radiation element administrative checks for a radioactive liquid release Emergency Procedures/Plan NOT EVALUATED NOTE: All items (5 total) are required for SROs. RO applicants require only 4 items unless they are retaking only the administrative topics, when all 5 are required.  
*Type Codes & Criteria (C)ontrol Room, (S)imulator, or Class(R)oom (D)irect from bank (< 3 for ROs; < 4 for SROs & RO retakes)
(N)ew or (M)odified from bank (> 1)
(N)ew or (M)odified from bank (> 1)
(P)revious 2 exams (< 1; randomly selected)
(P)revious 2 exams (< 1; randomly selected)  
NUREG-1021, Revision 9 Supplement 1                                                                FENOC Facsimile Rev. 1


ES-301                                 Administrative Topics Outline                                         Form ES-301-1 Facility:   Davis Besse                                                   Date of Examination:_ 6/3 thru 6/14 2013 Examination Level SRO                                                             Operating Test Number ________
ES-301 Administrative Topics Outline Form ES-301-1 NUREG-1021, Revision 9 Supplement 1 FENOC Facsimile Rev. 1 Facility: Davis Besse Date of Examination:_ 6/3 thru 6/14 2013 Examination Level SRO Operating Test Number ________
Administrative               Type                                 Describe activity to be performed Topic                  Code*
Administrative Topic (See Note)
(See Note)
Type Code*
Conduct of                      N, R       2.1.43           (4.3)
Describe activity to be performed Conduct of Operations (SRO A1.1)
Operations Ability to use procedures to determine the effects on reactivity (SRO A1.1)                                  of plant changes, such as reactor coolant system temperature, secondary plant, fuel depletion, etc.
N, R 2.1.43 (4.3)
JPM New           Shift Manager Review of SDM calculation with Tave > 500 &deg;F Conduct of                       N, R       2.1.5             (3.9)
Ability to use procedures to determine the effects on reactivity of plant changes, such as reactor coolant system temperature, secondary plant, fuel depletion, etc.
Operations Ability to use procedures related to shift staffing, such as minimum (SRO A1.2)                                  crew complement, overtime limitations, etc.
JPM New Shift Manager Review of SDM calculation with Tave > 500 &deg;F Conduct of Operations (SRO A1.2)
JPM New           Determine Availability For Call-In.
N, R 2.1.5 (3.9)
Equipment Control               N, R       2.2.18           (3.9)
Ability to use procedures related to shift staffing, such as minimum crew complement, overtime limitations, etc.
(SRO A2)                                    Knowledge of the process for managing maintenance activities during shutdown operations, such as risk assessments, work prioritization, etc.
JPM New Determine Availability For Call-In.
JPM New           Shutdown Defense In Depth Assessment Radiation Control               N, R       2.3.6             (3.8)
Equipment Control (SRO A2)
(SRO A3)                                    Ability to approve release permits.
N, R 2.2.18 (3.9)
JPM New           Perform Administrative Checks For Radioactive Liquid Batch Release Emergency                       D, S       2.4.44           (4.4)
Knowledge of the process for managing maintenance activities during shutdown operations, such as risk assessments, work prioritization, etc.
Procedures/Plan Knowledge of emergency plan protective action recommendations.
JPM New Shutdown Defense In Depth Assessment Radiation Control (SRO A3)
(SRO A4)
N, R 2.3.6 (3.8)
JPM 150           Make Protective Action Recommendations NOTE: All items (5 total) are required for SROs. RO applicants require only 4 items unless they are retaking only the administrative topics, when all 5 are required.
Ability to approve release permits.
*Type Codes & Criteria                         (C)ontrol Room, (S)imulator, or Class(R)oom (D)irect from bank (< 3 for ROs; < 4 for SROs & RO retakes)
JPM New Perform Administrative Checks For Radioactive Liquid Batch Release Emergency Procedures/Plan (SRO A4)
D, S 2.4.44 (4.4)
Knowledge of emergency plan protective action recommendations.
JPM 150 Make Protective Action Recommendations NOTE: All items (5 total) are required for SROs. RO applicants require only 4 items unless they are retaking only the administrative topics, when all 5 are required.  
*Type Codes & Criteria (C)ontrol Room, (S)imulator, or Class(R)oom (D)irect from bank (< 3 for ROs; < 4 for SROs & RO retakes)
(N)ew or (M)odified from bank (> 1)
(N)ew or (M)odified from bank (> 1)
(P)revious 2 exams (< 1; randomly selected)
(P)revious 2 exams (< 1; randomly selected)  
NUREG-1021, Revision 9 Supplement 1                                                                FENOC Facsimile Rev. 1


ES-301                         Control Room/In-Plant Systems Outline                               Form ES-301-2 Facility: Davis Besse                                             Date of Examination:           6/3 thru 6/14 2013 Exam Level: RO SRO(I) SRO(U)                                       Operating Test No.: _ ___
ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 NUREG-1021, Revision 9 Supplement 1 FENOC Facsimile Rev. 1 Facility: Davis Besse Date of Examination: 6/3 thru 6/14 2013 Exam Level: RO SRO(I) SRO(U)
                        @
Operating Test No.: _ ___
Control Room Systems (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)
Control Room Systems@ (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)
System / JPM Title                                             Type Code*                 Safety Function S1 Initiate Deboration Using Deborating Demineralizers                   (JPM New)                   N, A, S                  1 004 A4.07         3.9/3.7 S2 De-energize SFAS CH 4 RCS Pressure Transmitter                       (JPM New)                 N, S, EN                  2 013 K2.01         3.6/3.8 S3 Perform HPI Flow Balance                                             (JPM New)                 N, A, S, L,                3 EN 006 A4.02         4.0/3.8 S4 Rapid Cooldown of the RCS                                             (JPM New)                 N, A, S, L                4S 041 A3.01         3.2/3.2 S5 Shift CTMT Air Cooler From Slow to Fast Speed                         (JPM 151                   D, S, L                  5 022 A4.01         3.6/3.8 S6 13.8 KV Bus Transfer to Aux 11 Transformer                           (JPM New)                   N, A, S                  6 062 A4.01         3.3/3.1 S7 Bypass SFRCS Logic Channel Trips                                     (JPM 108)                     D, S                  7 012 A4.03         3.6/3.6 S8 CCW Essential Header Leak Isolation                                   (JPM 125)                   D, A, S                  8 008 A2.02         3.2/3.5 In-Plant Systems@ (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)
System / JPM Title Type Code*
P1 Actions outside the control room of the primary side reactor                                     D, E, R                  8 operator for a serious control room fire                                 (JPM 003) 068 AA1.21       3.9/4.1 P2 Emergency Idle Start EDG 1                                           (JPM 242)                   D, A, E                  6 064 A3.06         3.3/3.4 P3 Service Water Primary Header Pressure Control                         (JPM New)                       N                  4S 076 K1.01         3.4/3.3
Safety Function S1 Initiate Deboration Using Deborating Demineralizers (JPM New) 004 A4.07 3.9/3.7 N, A, S 1
@        All RO and SRO control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.
S2 De-energize SFAS CH 4 RCS Pressure Transmitter (JPM New) 013 K2.01 3.6/3.8 N, S, EN 2
                        *Type Codes                                               Criteria for RO / SRO-I / SRO-U (A)lternate Path                                                                             4-6 /4-6 /2-3 (C)ontrol room (D)irect from bank                                                                           9/8/4 (E)mergency or abnormal in-plant                                                             1/1/1 (EN)gineered safety feature                                                                         - / - / > 1 (Control room system)
S3 Perform HPI Flow Balance (JPM New) 006 A4.02 4.0/3.8 N, A, S, L, EN 3
(L)ow-power / Shutdown                                                                       1/1/1 (N)ew or (M)odified from bank including 1(A)                                                 2/2/1 (P)revious 2 exams                                                                                3/ 3 / 2 (randomly selected)
S4 Rapid Cooldown of the RCS (JPM New) 041 A3.01 3.2/3.2 N, A, S, L 4S S5 Shift CTMT Air Cooler From Slow to Fast Speed (JPM 151 022 A4.01 3.6/3.8 D, S, L 5
(R)CA                                                                                        1/1/1 (S)imulator NUREG-1021, Revision 9 Supplement 1                                                                  FENOC Facsimile Rev. 1
S6 13.8 KV Bus Transfer to Aux 11 Transformer (JPM New) 062 A4.01 3.3/3.1 N, A, S 6
S7 Bypass SFRCS Logic Channel Trips (JPM 108) 012 A4.03 3.6/3.6 D, S 7
S8 CCW Essential Header Leak Isolation (JPM 125) 008 A2.02 3.2/3.5 D, A, S 8
In-Plant Systems@ (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)
P1 Actions outside the control room of the primary side reactor operator for a serious control room fire (JPM 003) 068 AA1.21 3.9/4.1 D, E, R 8
P2 Emergency Idle Start EDG 1 (JPM 242) 064 A3.06 3.3/3.4 D, A, E 6
P3 Service Water Primary Header Pressure Control (JPM New) 076 K1.01 3.4/3.3 N
4S All RO and SRO control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.  
*Type Codes Criteria for RO / SRO-I / SRO-U (A)lternate Path (C)ontrol room (D)irect from bank (E)mergency or abnormal in-plant (EN)gineered safety feature (L)ow-power / Shutdown (N)ew or (M)odified from bank including 1(A)
(P)revious 2 exams (R)CA (S)imulator 4-6 /4-6 /2-3 9 / 8 / 4 1 / 1 / 1
- / - / > 1 (Control room system) 1 / 1 / 1 2 / 2 / 1 3/ 3 / 2 (randomly selected) 1 / 1 / 1  


ES-301                         Control Room/In-Plant Systems Outline                               Form ES-301-2 Facility: Davis Besse                                             Date of Examination:           6/3 thru 6/14 2013 Exam Level: RO SRO(I) SRO(U)                                       Operating Test No.: _ ___
ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 NUREG-1021, Revision 9 Supplement 1 FENOC Facsimile Rev. 1 Facility: Davis Besse Date of Examination: 6/3 thru 6/14 2013 Exam Level: RO SRO(I) SRO(U)
                        @
Operating Test No.: _ ___
Control Room Systems (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)
Control Room Systems@ (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)
System / JPM Title                                             Type Code*                 Safety Function S1 Initiate Deboration Using Deborating Demineralizers                   (JPM New)                   N, A, S                  1 004 A4.07         3.9/3.7 S2 De-energize SFAS CH 4 RCS Pressure Transmitter                       (JPM New)                 N, S, EN                  2 013 K2.01         3.6/3.8 S3 Perform HPI Flow Balance                                             (JPM New)                 N, A, S, L,                3 EN 006 A4.02         4.0/3.8 S4 Rapid Cooldown of the RCS                                             (JPM New)                 N, A, S, L                4S 041 A3.01         3.2/3.2 S6 13.8 KV Bus Transfer to Aux 11 Transformer                           (JPM New)                   N, A, S                  6 062 A4.01         3.3/3.1 S7 Bypass SFRCS Logic Channel Trips                                     (JPM 108)                     D, S                  7 012 A4.03         3.6/3.6 S8 CCW Essential Header Leak Isolation                                   (JPM 125)                   D, A, S                  8 008 A2.02         3.2/3.5 In-Plant Systems@ (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)
System / JPM Title Type Code*
P1 Actions outside the control room of the primary side reactor                                     D, E, R                  8 operator for a serious control room fire                                 (JPM 003) 068 AA1.21       3.9/4.1 P2 Emergency Idle Start EDG 1                                           (JPM 242)                   D, A, E                  6 064 A3.06         3.3/3.4 P3 Service Water Primary Header Pressure Control                         (JPM New)                       N                  4S 076 K1.01         3.4/3.3
Safety Function S1 Initiate Deboration Using Deborating Demineralizers (JPM New) 004 A4.07 3.9/3.7 N, A, S 1
@        All RO and SRO control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.
S2 De-energize SFAS CH 4 RCS Pressure Transmitter (JPM New) 013 K2.01 3.6/3.8 N, S, EN 2
                        *Type Codes                                               Criteria for RO / SRO-I / SRO-U (A)lternate Path                                                                             4-6 /4-6 /2-3 (C)ontrol room (D)irect from bank                                                                           9/8/4 (E)mergency or abnormal in-plant                                                             1/1/1 (EN)gineered safety feature                                                                         - / - / > 1 (Control room system)
S3 Perform HPI Flow Balance (JPM New) 006 A4.02 4.0/3.8 N, A, S, L, EN 3
(L)ow-power / Shutdown                                                                       1/1/1 (N)ew or (M)odified from bank including 1(A)                                                 2/2/1 (P)revious 2 exams                                                                                3/ 3 / 2 (randomly selected)
S4 Rapid Cooldown of the RCS (JPM New) 041 A3.01 3.2/3.2 N, A, S, L 4S S6 13.8 KV Bus Transfer to Aux 11 Transformer (JPM New) 062 A4.01 3.3/3.1 N, A, S 6
(R)CA                                                                                        1/1/1 (S)imulator NUREG-1021, Revision 9 Supplement 1                                                                  FENOC Facsimile Rev. 1
S7 Bypass SFRCS Logic Channel Trips (JPM 108) 012 A4.03 3.6/3.6 D, S 7
S8 CCW Essential Header Leak Isolation (JPM 125) 008 A2.02 3.2/3.5 D, A, S 8
In-Plant Systems@ (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)
P1 Actions outside the control room of the primary side reactor operator for a serious control room fire (JPM 003) 068 AA1.21 3.9/4.1 D, E, R 8
P2 Emergency Idle Start EDG 1 (JPM 242) 064 A3.06 3.3/3.4 D, A, E 6
P3 Service Water Primary Header Pressure Control (JPM New) 076 K1.01 3.4/3.3 N
4S All RO and SRO control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.  
*Type Codes Criteria for RO / SRO-I / SRO-U (A)lternate Path (C)ontrol room (D)irect from bank (E)mergency or abnormal in-plant (EN)gineered safety feature (L)ow-power / Shutdown (N)ew or (M)odified from bank including 1(A)
(P)revious 2 exams (R)CA (S)imulator 4-6 /4-6 /2-3 9 / 8 / 4 1 / 1 / 1
- / - / > 1 (Control room system) 1 / 1 / 1 2 / 2 / 1 3/ 3 / 2 (randomly selected) 1 / 1 / 1  


ES-301                         Control Room/In-Plant Systems Outline                               Form ES-301-2 Facility: Davis Besse                                             Date of Examination:           6/3 thru 6/14 2013 Exam Level: RO SRO(I) SRO(U)                                       Operating Test No.: _ ___
ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 NUREG-1021, Revision 9 Supplement 1 FENOC Facsimile Rev. 1 Facility: Davis Besse Date of Examination: 6/3 thru 6/14 2013 Exam Level: RO SRO(I) SRO(U)
                        @
Operating Test No.: _ ___
Control Room Systems (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)
Control Room Systems@ (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)
System / JPM Title                                             Type Code*                 Safety Function S3 Perform HPI Flow Balance                                             (JPM New)                 N, A, S, L,                3 EN 006 A4.02         4.0/3.8 S4 Rapid Cooldown of the RCS                                             (JPM New)                 N, A, S, L                4S 041 A3.01         3.2/3.2 S7 Bypass SFRCS Logic Channel Trips                                     (JPM 108)                     D, S                  7 012 A4.03         3.6/3.6 In-Plant Systems@ (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)
System / JPM Title Type Code*
P1 Actions outside the control room of the primary side reactor                                     D, E, R                  8 operator for a serious control room fire                                 (JPM 003) 068 AA1.21       3.9/4.1 P2 Emergency Idle Start EDG 1                                           (JPM 242)                   D, A, E                  6 064 A3.06         3.3/3.4
Safety Function S3 Perform HPI Flow Balance (JPM New) 006 A4.02 4.0/3.8 N, A, S, L, EN 3
@        All RO and SRO control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.
S4 Rapid Cooldown of the RCS (JPM New) 041 A3.01 3.2/3.2 N, A, S, L 4S S7 Bypass SFRCS Logic Channel Trips (JPM 108) 012 A4.03 3.6/3.6 D, S 7
                        *Type Codes                                               Criteria for RO / SRO-I / SRO-U (A)lternate Path                                                                             4-6 /4-6 /2-3 (C)ontrol room (D)irect from bank                                                                           9/8/4 (E)mergency or abnormal in-plant                                                             1/1/1 (EN)gineered safety feature                                                                         - / - / > 1 (Control room system)
In-Plant Systems@ (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)
(L)ow-power / Shutdown                                                                       1/1/1 (N)ew or (M)odified from bank including 1(A)                                                 2/2/1 (P)revious 2 exams                                                                                3/ 3 / 2 (randomly selected)
P1 Actions outside the control room of the primary side reactor operator for a serious control room fire (JPM 003) 068 AA1.21 3.9/4.1 D, E, R 8
(R)CA                                                                                        1/1/1 (S)imulator NUREG-1021, Revision 9 Supplement 1                                                                  FENOC Facsimile Rev. 1
P2 Emergency Idle Start EDG 1 (JPM 242) 064 A3.06 3.3/3.4 D, A, E 6
All RO and SRO control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.  
*Type Codes Criteria for RO / SRO-I / SRO-U (A)lternate Path (C)ontrol room (D)irect from bank (E)mergency or abnormal in-plant (EN)gineered safety feature (L)ow-power / Shutdown (N)ew or (M)odified from bank including 1(A)
(P)revious 2 exams (R)CA (S)imulator 4-6 /4-6 /2-3 9 / 8 / 4 1 / 1 / 1
- / - / > 1 (Control room system) 1 / 1 / 1 2 / 2 / 1 3/ 3 / 2 (randomly selected) 1 / 1 / 1  


ES-301                                       Operating Test Quality Checklist                                               Form ES-301-3 Facility: Davis Besse                                               Date of Exam 6/3 thru 6/14 2013       Operating Test No.: _________
NUREG-1021, Revision 9 Supplement 1 FENOC Facsimile Rev.1 ES-301 Operating Test Quality Checklist Form ES-301-3 Facility: Davis Besse Date of Exam 6/3 thru 6/14 2013 Operating Test No.: _________
Initials
: 1. GENERAL CRITERIA Initials a
: 1. GENERAL CRITERIA a     b*     c#
b*
: a.         The operating test conforms with the previously approved outline; changes are consistent with sampling requirements (e.g., 10 CFR 55.45, operational importance, safety function distribution).
c#
: b.         There is no day-to-day repetition between this and other operating tests to be administered during this examination.
: a.
: c.         The operating test shall not duplicate items from the applicants audit test(s) (see Section D.1.a).
The operating test conforms with the previously approved outline; changes are consistent with sampling requirements (e.g., 10 CFR 55.45, operational importance, safety function distribution).
: d.         Overlap with the written examination and between different parts of the operating test is within acceptable limits.
: b.
: e.         It appears that the operating test will differentiate between competent and less-than-competent applicants at the designated license level.
There is no day-to-day repetition between this and other operating tests to be administered during this examination.
: c.
The operating test shall not duplicate items from the applicants audit test(s) (see Section D.1.a).
: d.
Overlap with the written examination and between different parts of the operating test is within acceptable limits.
: e.
It appears that the operating test will differentiate between competent and less-than-competent applicants at the designated license level.
: 2. WALK-THROUGH CRITERIA
: 2. WALK-THROUGH CRITERIA
: a.         Each JPM includes the following, as applicable:
: a.
Each JPM includes the following, as applicable:
* initial conditions
* initial conditions
* initiating cues
* initiating cues
* references and tools, including associated procedures
* references and tools, including associated procedures
* reasonable and validated time limits (average time allowed for completion) and specific designation if deemed to be time critical by the facility licensee
* reasonable and validated time limits (average time allowed for completion) and specific designation if deemed to be time critical by the facility licensee
* specific performance criteria that include:
* specific performance criteria that include:  
                    - detailed expected actions with exact criteria and nomenclature
- detailed expected actions with exact criteria and nomenclature  
                    - system response and other examiner cues
- system response and other examiner cues  
                    - statements describing important observations to be made by the applicant
- statements describing important observations to be made by the applicant  
                    - criteria for successful completion of the task
- criteria for successful completion of the task  
                    - identification of critical steps and their associated performance standards
- identification of critical steps and their associated performance standards  
                    - restrictions on the sequence of steps, if applicable
- restrictions on the sequence of steps, if applicable
: b.         Ensure that any changes from the previously approved systems and administrative walk-through outlines (Forms ES-301-1 and 2) have not caused the test to deviate from any of the acceptance criteria (e.g., item distribution, bank use, repetition from the last 2 NRC examinations) specified on those forms and Form ES-201-2.
: b.
Ensure that any changes from the previously approved systems and administrative walk-through outlines (Forms ES-301-1 and 2) have not caused the test to deviate from any of the acceptance criteria (e.g., item distribution, bank use, repetition from the last 2 NRC examinations) specified on those forms and Form ES-201-2.
: 3. SIMULATOR CRITERIA
: 3. SIMULATOR CRITERIA
: a.         The associated simulator operating tests (scenario sets) have been reviewed in accordance with Form ES-301-4 and a copy is attached.
: a.
Printed Name / Signature                                     Date
The associated simulator operating tests (scenario sets) have been reviewed in accordance with Form ES-301-4 and a copy is attached.
: a. Author                         ________________________________________________________                          _________
Printed Name / Signature Date
: b. Facility Reviewer (*)           ________________________________________________________                          _________
: a. Author
: c. NRC Chief Examiner (#)         ________________________________________________________                          _________
: b. Facility Reviewer (*)
: d. NRC Supervisor                 ________________________________________________________                          _________
: c. NRC Chief Examiner (#)
NOTE:
: d. NRC Supervisor NOTE:
* The facility signature is not applicable for NRC-developed tests.
* The facility signature is not applicable for NRC-developed tests.  
            # Independent NRC reviewer initial items in Column c; chief examiner concurrence required.
# Independent NRC reviewer initial items in Column c; chief examiner concurrence required.  
NUREG-1021, Revision 9 Supplement 1                                                                                          FENOC Facsimile Rev.1


ES-301                         Simulator Scenario Quality Checklist                                   Form ES-301-4 Facility: Davis   Besse                                     Date of Exam 6/3 thru 6/14 2013       Operating Test No.: _____
ES-301 Simulator Scenario Quality Checklist Form ES-301-4 NUREG-1021, Revision 9 Supplement 1 FENOC Facsimile Rev.1 Facility: Davis Besse Date of Exam 6/3 thru 6/14 2013 Operating Test No.: _____
QUALITATIVE ATTRIBUTES                                                         Initials a       b*     c#
QUALITATIVE ATTRIBUTES Initials a
: 1.         The initial conditions are realistic, in that some equipment and/or instrumentation may be out of service, but it does not cue the operators into expected events.
b*
: 2.         The scenarios consist mostly of related events.
c#
: 3.         Each event description consists of
: 1.
* the point in the scenario when it is to be initiated
The initial conditions are realistic, in that some equipment and/or instrumentation may be out of service, but it does not cue the operators into expected events.
* the malfunction(s) that are entered to initiate the event
: 2.
* the symptoms/cues that will be visible to the crew
The scenarios consist mostly of related events.
* the expected operator actions (by shift position)
: 3.
* the event termination point (if applicable)
Each event description consists of the point in the scenario when it is to be initiated the malfunction(s) that are entered to initiate the event the symptoms/cues that will be visible to the crew the expected operator actions (by shift position) the event termination point (if applicable)
: 4.         No more than one non-mechanistic failure (e.g., pipe break) is incorporated into the scenario without a credible preceding incident such as a seismic event.
: 4.
: 5.         The events are valid with regard to physics and thermodynamics.
No more than one non-mechanistic failure (e.g., pipe break) is incorporated into the scenario without a credible preceding incident such as a seismic event.
: 6.         Sequencing and timing of events is reasonable, and allows the examination team to obtain complete evaluation results commensurate with the scenario objectives.
: 5.
: 7.         If time compression techniques are used, the scenario summary clearly so indicates.
The events are valid with regard to physics and thermodynamics.
: 6.
Sequencing and timing of events is reasonable, and allows the examination team to obtain complete evaluation results commensurate with the scenario objectives.
: 7.
If time compression techniques are used, the scenario summary clearly so indicates.
Operators have sufficient time to carry out expected activities without undue time constraints. Cues are given.
Operators have sufficient time to carry out expected activities without undue time constraints. Cues are given.
: 8.         The simulator modeling is not altered.
: 8.
: 9.         The scenarios have been validated. Pursuant to 10 CFR 55.46(d), any open simulator performance deficiencies or deviations from the referenced plant have been evaluated to ensure that functional fidelity is maintained while running the planned scenarios.
The simulator modeling is not altered.
: 10.         Every operator will be evaluated using at least one new or significantly modified scenario. All other scenarios have been altered in accordance with Section D.5 of ES-301.
: 9.
: 11.         All individual operator competencies can be evaluated, as verified using Form ES-301-6 (submit the form along with the simulator scenarios).
The scenarios have been validated. Pursuant to 10 CFR 55.46(d), any open simulator performance deficiencies or deviations from the referenced plant have been evaluated to ensure that functional fidelity is maintained while running the planned scenarios.
: 12.         Each applicant will be significantly involved in the minimum number of transients and events specified on Form ES-301-5 (submit the form with the simulator scenarios).
: 10.
: 13.         The level of difficulty is appropriate to support licensing decisions for each crew position.
Every operator will be evaluated using at least one new or significantly modified scenario. All other scenarios have been altered in accordance with Section D.5 of ES-301.
TARGET QUANTITATIVE ATTRIBUTES (PER SCENARIO; SEE SECTION                     Actual Attributes D.5.d)
: 11.
: 1. Total malfunctions (5-8)                                             6       6         6       5
All individual operator competencies can be evaluated, as verified using Form ES-301-6 (submit the form along with the simulator scenarios).
: 2. Malfunctions after EOP entry (1-2)                                   2       2         1       2
: 12.
: 3. Abnormal events (2-4)                                                 3       3         3       3
Each applicant will be significantly involved in the minimum number of transients and events specified on Form ES-301-5 (submit the form with the simulator scenarios).
: 4. Major transients (1-2)                                               2       1         1       1
: 13.
: 5. EOPs entered/requiring substantive actions (1-2)                     1       1         1       1
The level of difficulty is appropriate to support licensing decisions for each crew position.
: 6. EOP contingencies requiring substantive actions (0-2)                 1       1         0       1
TARGET QUANTITATIVE ATTRIBUTES (PER SCENARIO; SEE SECTION D.5.d)
: 7. Critical tasks (2-3)                                                 3       2         3       3 NUREG-1021, Revision 9 Supplement 1                                                                FENOC Facsimile Rev.1
Actual Attributes
: 1. Total malfunctions (5-8) 6 6
6 5
: 2. Malfunctions after EOP entry (1-2) 2 2
1 2
: 3. Abnormal events (2-4) 3 3
3 3
: 4. Major transients (1-2) 2 1
1 1
: 5. EOPs entered/requiring substantive actions (1-2) 1 1
1 1
: 6. EOP contingencies requiring substantive actions (0-2) 1 1
0 1
: 7. Critical tasks (2-3) 3 2
3 3  


ES-301                                           Transient and Event Checklist                                   Form ES-301-5 Facility Davis Besse         Date of Exam 6/3 thru 6/14 2013                       Operating Test No.: ______
ES-301 Transient and Event Checklist Form ES-301-5 NUREG-1021, Revision 9 Supplement 1 Page 1 of 3 FENOC Facsimile Rev. 1 Facility Davis Besse Date of Exam 6/3 thru 6/14 2013 Operating Test No.: ______
A           E                                                     Scenarios P            V                1                       2                     3                 4 Backup                   M P            E                                                                                                    T      I L            N CREW POSITION           CREW POSITION         CREW POSITION           CREW POSITION           O       N T
A P
I                                                                                                                T      I C           T                                                                                                    A      M A            Y        S      A        B       S      A      B    S       A      B        S        A    B      L      U N            P        R       T        O       R      T       O     R       T      O       R        T   O              M(*)
P L
T            E        O      C       P      O       C      P   O       C     P        O       C    P R   I U RX           1       1                 3     3             4       4               1       1                 1   1 0 M
I C
NOR         3               3                             1               1                                   1   1 1 A
A N
S        I/C       4,6,7,   4,10     6,7     1,2,4 5,7 8   1,2,4 2,3,5   2,3   2,5,7   2,4,5     2,4, 5,7,8         4   4 2 T                    10                      5,7,8                  7                      7,8 E        MAJ         8,9     8,9     8,9       6     6       6     6       6       6       6       6     6           2   2 1 R
T E
TS         2,5                       1,5                 2,4                     3,4                         0   2 2 RX                   1                 3                                                                 2     1   1 0 SROI-1 NOR                                                                         1                             1     1   1 1
V E
N T
T Y
P E
Scenarios 1
2 3
4 Backup T
O T
A L
M I
N I
M U
M(*)
CREW POSITION CREW POSITION CREW POSITION CREW POSITION S
R O
A T
C B
O P
S R
O A
T C
B O
P S
R O
A T
C B
O P
S R
O A
T C
B O
P R
I U
M A
S T
E R
RX 1
1 3
3 4
4 1
1 1
1 0
NOR 3
3 1
1 1
1 1
I/C 4,6,7, 10 4,10 6,7 1,2,4 5,7,8 5,7 8 1,2,4 2,3,5 7
2,3 2,5,7 2,4,5 7,8 2,4, 5,7,8 4
4 2
MAJ 8,9 8,9 8,9 6
6 6
6 6
6 6
6 6
2 2
1 TS 2,5 1,5 2,4 3,4 0
2 2
SROI-1 RX 1
3 2
1 1
0 NOR 1
1 1
1 1
I/C 4,10 1,2,4 5,7,8 2,5,7 11 4
4 2
MAJ 8,9 6
6 4
2 2
1 TS 1,5 2
0 2
2 SROI-2 RX 3
4 2
1 1
0 NOR 3
1 2
1 1
1 I/C 6,7 5,7 8 2,3,5 7
9 4
4 2
MAJ 8,9 6
6 4
2 2
1 TS 2,4 2
0 2
2 SROI-3 RX 1
4 2
1 1
0 NOR 3
1 1
1 1
I/C 4,6,7, 10 1,2,4 2,3 9
4 4
2 MAJ 8,9 6
6 4
2 2
1 TS 2,5 2
0 2
2 Instructions:
: 1.
Check the applicant level and enter the operating test number and Form ES-D-1 event numbers for each event type; TS are not applicable for RO applicants. ROs must serve in both the at-the-controls (ATC) and balance-of-plant (BOP) positions; Instant SROs must serve in both the SRO and the ATC positions, including at least two instrument or component (I/C) malfunctions and one major transient, in the ATC position. If an Instant SRO additionally serves in the BOP position, one I/C malfunction can be credited toward the two I/C malfunctions required for the ATC position.
: 2.
Reactivity manipulations may be conducted under normal or controlled abnormal conditions (refer to Section D.5.d) but must be significant per section C.2.a of Appendix D. (*) Reactivity and normal evolutions may be replaced with additional instrument or component malfunctions on a 1-for-1 basis.
: 3.
Whenever practical, both instrument and component malfunctions should be included; only those that require verifiable actions that provide insight to the applicants competence count toward the minimum requirements specified for the applicants license level in the right hand columns.


I/C                 4,10             1,2,4                                2,5,7                         11    4   4 2 5,7,8 MAJ                 8,9               6                                   6                            4    2   2 1 TS                                   1,5                                                                 2     0   2 2 RX                                           3            4                                            2    1   1 0 SROI-2 NOR                           3                            1                                             2    1   1 1
ES-301 Transient and Event Checklist Form ES-301-5 NUREG-1021, Revision 9 Supplement 1 Page 2 of 3 FENOC Facsimile Rev. 1 Facility Davis Besse Date of Exam 6/3 thru 6/14 2013 Operating Test No.: ______
 
A P
I/C                         6,7            5,7 8        2,3,5                                           9    4   4 2 7
P L
MAJ                         8,9             6             6                                            4    2   2 1 TS                                                         2,4                                            2     0  2  2 RX           1                                                     4                                    2    1   1 0 SROI-3 NOR         3                                                                                           1     1   1 1
I C
 
A N
I/C       4,6,7,                                  1,2,4         2,3                                    9    4   4 2 10 MAJ         8,9                                       6             6                                    4    2   2 1 TS         2,5                                                                                          2     0   2 2 Instructions:
T E
: 1.       Check the applicant level and enter the operating test number and Form ES-D-1 event numbers for each event type; TS are not applicable for RO applicants. ROs must serve in both the at-the-controls (ATC) and balance-of-plant (BOP) positions; Instant SROs must serve in both the SRO and the ATC positions, including at least two instrument or component (I/C) malfunctions and one major transient, in the ATC position. If an Instant SRO additionally serves in the BOP position, one I/C malfunction can be credited toward the two I/C malfunctions required for the ATC position.
V E
: 2.       Reactivity manipulations may be conducted under normal or controlled abnormal conditions (refer to Section D.5.d) but must be significant per section C.2.a of Appendix D. (*) Reactivity and normal evolutions may be replaced with additional instrument or component malfunctions on a 1-for-1 basis.
N T
: 3.       Whenever practical, both instrument and component malfunctions should be included; only those that require verifiable actions that provide insight to the applicants competence count toward the minimum requirements specified for the applicants license level in the right hand columns.
T Y
NUREG-1021, Revision 9 Supplement 1                      Page 1 of 3                                  FENOC Facsimile Rev. 1
P E
Scenarios 1
2 3
4 Backup T
O T
A L
M I
N I
M U
M(*)
CREW POSITION CREW POSITION CREW POSITION CREW POSITION S
R O
A T
C B
O P
S R
O A
T C
B O
P S
R O
A T
C B
O P
S R
O A
T C
B O
P R
I U
SROU -1 RX 1
4 2
1 1
0 NOR 3
1 2
1 1
1 I/C 4,6,7, 10 2,3,5 7
8 4
4 2
MAJ 8,9 6
3 2
2 1
TS 2,5 2,4 4
0 2
2 RO -1 RX 1
1 1
1 0
NOR 1
1 1
1 1
I/C 4,10 2,5,7 5
4 4
2 MAJ 8,9 6
3 2
2 1
TS 0
0 2
2 RO -2 RX 4
1 1
1 0
NOR 3
1 1
1 1
I/C 6,7 2,3 4
4 4
2 MAJ 8,9 6
3 2
2 1
TS 0
0 2
2 RX 1
1 0
NOR 1
1 1
I/C 4
4 2
MAJ 2
2 1
TS 0
2 2
Instructions:
: 1.
Check the applicant level and enter the operating test number and Form ES-D-1 event numbers for each event type; TS are not applicable for RO applicants. ROs must serve in both the at-the-controls (ATC) and balance-of-plant (BOP) positions; Instant SROs must serve in both the SRO and the ATC positions, including at least two instrument or component (I/C) malfunctions and one major transient, in the ATC position. If an Instant SRO additionally serves in the BOP position, one I/C malfunction can be credited toward the two I/C malfunctions required for the ATC position.
: 2.
Reactivity manipulations may be conducted under normal or controlled abnormal conditions (refer to Section D.5.d) but must be significant per section C.2.a of Appendix D. (*) Reactivity and normal evolutions may be replaced with additional instrument or component malfunctions on a 1-for-1 basis.
: 3.
Whenever practical, both instrument and component malfunctions should be included; only those that require verifiable actions that provide insight to the applicants competence count toward the minimum requirements specified for the applicants license level in the right hand columns.  


ES-301                                           Transient and Event Checklist                                   Form ES-301-5 Facility Davis Besse         Date of Exam 6/3 thru 6/14 2013                       Operating Test No.: ______
ES-301 Transient and Event Checklist Form ES-301-5 NUREG-1021, Revision 9 Supplement 1 Page 3 of 3 FENOC Facsimile Rev. 1 Facility Davis Besse Date of Exam 6/3 thru 6/14 2013 Operating Test No.: ______
A           E                                                     Scenarios P            V                1                       2                     3                 4 Backup                   M P            E                                                                                                    T      I L            N CREW POSITION           CREW POSITION       CREW POSITION           CREW POSITION           O       N T
A P
I                                                                                                                T      I C           T                                                                                                    A      M A            Y        S      A        B       S      A      B    S       A      B        S      A    B      L      U N            P        R       T        O       R      T       O     R       T      O       R      T     O              M(*)
P L
T            E        O      C       P      O       C      P   O       C     P        O       C    P R   I U RX           1                                             4                                             2     1   1 0 SROU -1 NOR         3                                             1                                             2     1   1 1
I C
A N
T E
V E
N T
T Y
P E
Scenarios 1
2 3
4 Backup T
O T
A L
M I
N I
M U
M(*)
CREW POSITION CREW POSITION CREW POSITION CREW POSITION S
R O
A T
C B
O P
S R
O A
T C
B O
P S
R O
A T
C B
O P
S R
O A
T C
B O
P R
I U
SROU -2 RX 1
1 1
1 0
NOR 3
1 1
1 1
I/C 4,6,7, 10 4
4 4
2 MAJ 8,9 2
2 2
1 TS 2,5 2
0 2
2 SROU -3 RX 4
1 1
1 0
NOR 1
1 1
1 1
I/C 2,3,5 7
4 4
4 2
MAJ 6
1 2
2 1
TS 2,4 2
0 2
2 RO -3 RX 1
1 1
1 0
NOR 1
1 1
1 1
I/C 4,10 2,5,7 5
4 4
2 MAJ 8,9 6
3 2
2 1
TS 0
0 2
2 RO -4 RX 4
1 1
1 0
NOR 3
1 1
1 1
I/C 6,7 2,3 4
4 4
2 MAJ 8,9 6
3 2
2 1
TS 0
0 2
2 Instructions:
: 1.
Check the applicant level and enter the operating test number and Form ES-D-1 event numbers for each event type; TS are not applicable for RO applicants. ROs must serve in both the at-the-controls (ATC) and balance-of-plant (BOP) positions; Instant SROs must serve in both the SRO and the ATC positions, including at least two instrument or component (I/C) malfunctions and one major transient, in the ATC position. If an Instant SRO additionally serves in the BOP position, one I/C malfunction can be credited toward the two I/C malfunctions required for the ATC position.
: 2.
Reactivity manipulations may be conducted under normal or controlled abnormal conditions (refer to Section D.5.d) but must be significant per section C.2.a of Appendix D. (*) Reactivity and normal evolutions may be replaced with additional instrument or component malfunctions on a 1-for-1 basis.
: 3.
Whenever practical, both instrument and component malfunctions should be included; only those that require verifiable actions that provide insight to the applicants competence count toward the minimum requirements specified for the applicants license level in the right hand columns.


I/C        4,6,7,                                        2,3,5                                          8    4  4  2 10                                            7 MAJ        8,9                                            6                                            3    2  2  1 TS          2,5                                            2,4                                            4    0  2  2 RX                  1                                                                                    1    1  1  0 RO -1 NOR                                                                        1                            1    1  1  1
NUREG-1021, Revision 9 Supplement 1 Page 1 of 1 FENOC Facsimile Rev. 1 ES-401 Record of Rejected K/As Form ES-401-4 Facility: Davis Besse Date of Exam 6/3 thru 6/14 2013 Operating Test No.:
 
Tier /
I/C                4,10                                                  2,5,7                          5    4  4  2 MAJ                8,9                                                    6                            3    2  2  1 TS                                                                                                        0    0  2  2 RX                                                                  4                                    1    1  1  0 RO -2 NOR                          3                                                                          1    1  1  1
Group Randomly Selected K/A Reason for Rejection RO OUTLINE 1/1 000011 EA2.12 Question # 3 Davis Besse does not have a system for throttling or stopping reflux boiling spray. Randomly selected 000011 EA2.10 as a replacement.
 
1/1 000025 AK3.01 Question # 6 Davis Besse does not have an alternate RHR flowpath. Randomly selected 000025 AA1.01 as a replacement.
I/C                          6,7                                  2,3                                    4    4  4  2 MAJ                          8,9                                    6                                    3    2  2  1 TS                                                                                                        0    0  2  2 RX                                                                                                              1  1  0 NOR                                                                                                            1  1  1 I/C                                                                                                            4  4  2 MAJ                                                                                                            2  2  1 TS                                                                                                              0  2  2 Instructions:
1/2 000059 AK2.01 Question # 21 Davis Besse does not have any gas monitors on the liquid waste discharge system. Randomly selected 000059 AK2.01 as a replacement.
: 1.        Check the applicant level and enter the operating test number and Form ES-D-1 event numbers for each event type; TS are not applicable for RO applicants. ROs must serve in both the at-the-controls (ATC) and balance-of-plant (BOP) positions; Instant SROs must serve in both the SRO and the ATC positions, including at least two instrument or component (I/C) malfunctions and one major transient, in the ATC position. If an Instant SRO additionally serves in the BOP position, one I/C malfunction can be credited toward the two I/C malfunctions required for the ATC position.
2/1 025 2.4.4 Question # 40 Davis Besse does not have Ice Condensers. Randomly selected 004 2.4.4 as a replacement.
: 2.        Reactivity manipulations may be conducted under normal or controlled abnormal conditions (refer to Section D.5.d) but must be significant per section C.2.a of Appendix D. (*) Reactivity and normal evolutions may be replaced with additional instrument or component malfunctions on a 1-for-1 basis.
2/1 025 K1.02 Question # 41 Davis Besse does not have Ice Condensers. Randomly selected 062 K1.02 as a replacement.
: 3.        Whenever practical, both instrument and component malfunctions should be included; only those that require verifiable actions that provide insight to the applicants competence count toward the minimum requirements specified for the applicants license level in the right hand columns.
2/1 064 K4.08 Question # 50 Davis Besse does not have any design features or interlocks for EDG fuel isolation valves. Randomly selected 064 K4.03 as a replacement.
NUREG-1021, Revision 9 Supplement 1                       Page 2 of 3                                  FENOC Facsimile Rev. 1
2/1 073 K5.03 Question # 51 Unable to write a discriminatory question for the process radiation monitoring system that depicts the relationship between radiation intensity and exposure limits. Randomly selected 073 K5.01 as a replacement.
 
3 2.4.40 Question # 75 Unable to write an RO discriminatory question regarding SRO responsibilities during E-Plan implementation. Randomly selected 2.4.35 as a replacement.
ES-301                                            Transient and Event Checklist                                  Form ES-301-5 Facility Davis Besse          Date of Exam 6/3 thru 6/14 2013                      Operating Test No.: ______
2/2 034 A3.01 Question # 59. Deleted from the exam to achieve balance. There are too many fuel handling questions (5) already being addressed on this exam.
A            E                                                      Scenarios P            V                1                       2                    3                  4 Backup                  M P            E                                                                                                    T      I L            N CREW POSITION            CREW POSITION        CREW POSITION            CREW POSITION          O      N T
I                                                                                                                T      I C            T                                                                                                    A      M A            Y        S      A        B      S      A      B    S      A      B        S      A    B      L      U N            P        R      T        O      R      T      O    R      T      O        R      T    O              M(*)
T            E        O      C        P      O      C      P    O        C      P        O      C    P R  I  U RX          1                                                                                            1    1  1  0 SROU -2 NOR          3                                                                                            1    1  1  1
 
I/C        4,6,7,                                                                                        4    4  4  2 10 MAJ        8,9                                                                                          2    2  2  1 TS          2,5                                                                                          2    0  2  2 RX                                                          4                                            1    1  1  0 SROU -3 NOR                                                        1                                            1    1  1  1
 
I/C                                                      2,3,5                                          4    4  4  2 7
MAJ                                                        6                                            1    2  2  1 TS                                                        2,4                                            2    0  2  2 RX                  1                                                                                    1    1  1  0 RO -3 NOR                                                                        1                            1    1  1  1
 
I/C                4,10                                                  2,5,7                          5    4  4  2 MAJ                8,9                                                    6                            3    2  2  1 TS                                                                                                        0    0  2  2 RX                                                                  4                                    1    1  1  0 RO -4 NOR                          3                                                                          1    1  1  1
 
I/C                          6,7                                  2,3                                    4    4  4  2 MAJ                          8,9                                    6                                    3    2  2  1 TS                                                                                                        0    0  2  2 Instructions:
: 1.      Check the applicant level and enter the operating test number and Form ES-D-1 event numbers for each event type; TS are not applicable for RO applicants. ROs must serve in both the at-the-controls (ATC) and balance-of-plant (BOP) positions; Instant SROs must serve in both the SRO and the ATC positions, including at least two instrument or component (I/C) malfunctions and one major transient, in the ATC position. If an Instant SRO additionally serves in the BOP position, one I/C malfunction can be credited toward the two I/C malfunctions required for the ATC position.
: 2.      Reactivity manipulations may be conducted under normal or controlled abnormal conditions (refer to Section D.5.d) but must be significant per section C.2.a of Appendix D. (*) Reactivity and normal evolutions may be replaced with additional instrument or component malfunctions on a 1-for-1 basis.
: 3.      Whenever practical, both instrument and component malfunctions should be included; only those that require verifiable actions that provide insight to the applicants competence count toward the minimum requirements specified for the applicants license level in the right hand columns.
NUREG-1021, Revision 9 Supplement 1                      Page 3 of 3                                  FENOC Facsimile Rev. 1
 
ES-401                                             Record of Rejected K/As                             Form ES-401-4 Facility: Davis Besse             Date of Exam 6/3 thru 6/14 2013         Operating Test No.:
Tier /         Randomly                                             Reason for Rejection Group        Selected K/A RO OUTLINE 1/1       000011 EA2.12         Question # 3 Davis Besse does not have a system for throttling or stopping reflux boiling spray. Randomly selected 000011 EA2.10 as a replacement.
1/1       000025 AK3.01         Question # 6 Davis Besse does not have an alternate RHR flowpath. Randomly selected 000025 AA1.01 as a replacement.
1/2       000059 AK2.01         Question # 21 Davis Besse does not have any gas monitors on the liquid waste discharge system. Randomly selected 000059 AK2.01 as a replacement.
2/1           025 2.4.4         Question # 40 Davis Besse does not have Ice Condensers. Randomly selected 004 2.4.4 as a replacement.
2/1           025 K1.02           Question # 41 Davis Besse does not have Ice Condensers. Randomly selected 062 K1.02 as a replacement.
2/1           064 K4.08           Question # 50 Davis Besse does not have any design features or interlocks for EDG fuel isolation valves. Randomly selected 064 K4.03 as a replacement.
2/1           073 K5.03           Question # 51 Unable to write a discriminatory question for the process radiation monitoring system that depicts the relationship between radiation intensity and exposure limits. Randomly selected 073 K5.01 as a replacement.
3               2.4.40           Question # 75 Unable to write an RO discriminatory question regarding SRO responsibilities during E-Plan implementation. Randomly selected 2.4.35 as a replacement.
2/2           034 A3.01           Question # 59. Deleted from the exam to achieve balance. There are too many fuel handling questions (5) already being addressed on this exam.
Discussed with chief examiner and determined that this K/A should be deleted to obtain a better balance. Randomly selected 041 A2.02 as a replacement.
Discussed with chief examiner and determined that this K/A should be deleted to obtain a better balance. Randomly selected 041 A2.02 as a replacement.
SRO OUTLINE 2/2           027 A2.01           Question # 92 Davis Besse does not have an iodine removal system. Iodine is removed with the passive sodium triphosphate baskets. Randomly selected 015 A2.01 as a replacement.
SRO OUTLINE 2/2 027 A2.01 Question # 92 Davis Besse does not have an iodine removal system. Iodine is removed with the passive sodium triphosphate baskets. Randomly selected 015 A2.01 as a replacement.
1/1         057 AA2.16           Question # 77 Unable to write a discriminatory SRO level question for loss of vital AC impact on PZR level. Randomly selected 038 EA2.01 as a replacement.
1/1 057 AA2.16 Question # 77 Unable to write a discriminatory SRO level question for loss of vital AC impact on PZR level. Randomly selected 038 EA2.01 as a replacement.  
NUREG-1021, Revision 9 Supplement 1                        Page 1 of 1                          FENOC Facsimile Rev. 1


ES-401                               Written Examination Quality Checklist                 Form ES-401-6 Facility: Davis Besse                             Date of Exam 6/3 thru 6/14 2013           Exam Level: RO SRO Item Description                                                     Initial
NUREG-1021, Revision 9 Supplement 1 FENOC Facsimile Rev. 1 ES-401 Written Examination Quality Checklist Form ES-401-6 Facility: Davis Besse Date of Exam 6/3 thru 6/14 2013 Exam Level: RO SRO Item Description Initial a
                                                                                                                              #
b*
a        b*   c
c#
: 1.       Questions and answers technically accurate and applicable to facility
: 1.
: 2.       a. NRC K/As referenced for all questions
Questions and answers technically accurate and applicable to facility
: 2.
: a. NRC K/As referenced for all questions
: b. Facility learning objectives referenced as available
: b. Facility learning objectives referenced as available
: 3.       SRO questions are appropriate per Section D.2.d of ES-401
: 3.
: 4.       The sampling process was random and systematic (If more than 4 RO or 2 SRO questions are repeated from the last two NRC licensing exams, consult the NRR OL program office.)
SRO questions are appropriate per Section D.2.d of ES-401
: 5.       Question duplication from the license screening/audit exam was controlled as indicated below (check the item that applies) and appears appropriate:
: 4.
The sampling process was random and systematic (If more than 4 RO or 2 SRO questions are repeated from the last two NRC licensing exams, consult the NRR OL program office.)
: 5.
Question duplication from the license screening/audit exam was controlled as indicated below (check the item that applies) and appears appropriate:
__ the audit exam was systematically and randomly developed; or
__ the audit exam was systematically and randomly developed; or
__ the audit exam was completed before the license exam was started; or
__ the audit exam was completed before the license exam was started; or
Line 239: Line 581:
__ the licensee certifies that there is no duplication; or
__ the licensee certifies that there is no duplication; or
__ other (explain)
__ other (explain)
: 6.       Bank use meets limits (no more than 75               Bank          Modified    New percent from the bank, at least 10 percent new, and the rest new or modified); enter the actual RO / SRO-only question distribution(s) 16/0            0/0        59/25 at right.
: 6.
(21.3%/0%)       (0%/0%)   (78.7%/100%)
Bank use meets limits (no more than 75 percent from the bank, at least 10 percent new, and the rest new or modified); enter the actual RO / SRO-only question distribution(s) at right.
: 7.       Between 50 and 60 percent of the questions                 Memory                  C/A on the RO exam are written at the comprehension/analysis level; the SRO exam may exceed 60 percent If the randomly selected K/As support the higher 32/1                43/24 cognitive levels; enter the actual RO / SRO           (42.7% / 4%)           (57.3% / 96%)
Bank Modified New 16/0 (21.3%/0%)
question distribution(s) at right.
0/0 (0%/0%)
: 8.       References/handouts provided do not give away answers or aid in the elimination of distractors.
59/25 (78.7%/100%)
: 9.       Question content conforms with specific K/A statements in the previously approved examination outline and is appropriate for the Tier to which they are assigned; deviations are justified
: 7.
: 10.       Question psychometric quality and format meet the guidelines in ES Appendix B.
Between 50 and 60 percent of the questions on the RO exam are written at the comprehension/analysis level; the SRO exam may exceed 60 percent If the randomly selected K/As support the higher cognitive levels; enter the actual RO / SRO question distribution(s) at right.
: 11.       The exam contains the required number of one-point, multiple choice items; the total is correct and agrees with value on cover sheet Printed Name / Signature                                     Date
Memory C/A 32/1 (42.7% / 4%)
: a. Author                     ________________________________________________________                      _________
43/24 (57.3% / 96%)
: b. Facility Reviewer (*)     ________________________________________________________                      _________
: 8.
: c. NRC Chief Examiner (#)________________________________________________________                           _________
References/handouts provided do not give away answers or aid in the elimination of distractors.
: d. NRC Supervisor           ________________________________________________________                        _________
: 9.
Question content conforms with specific K/A statements in the previously approved examination outline and is appropriate for the Tier to which they are assigned; deviations are justified
: 10.
Question psychometric quality and format meet the guidelines in ES Appendix B.
: 11.
The exam contains the required number of one-point, multiple choice items; the total is correct and agrees with value on cover sheet Printed Name / Signature Date
: a. Author
: b. Facility Reviewer (*)
: c. NRC Chief Examiner (#)________________________________________________________
: d. NRC Supervisor Note:
* The facility reviewer's initials/signature are not applicable for NRC-developed examinations.
# Independent NRC reviewer initial items in Column c; chief examiner concurrence required.
 
NUREG-1021, Revision 9 Supplement 1 RO Page 1 of 9 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Facility: Davis-Besse RO Date of Exam 6/3 thru 6/14 2013 Tier Group RO K/A Category Points SRO ONLY Points K
1 K
2 K
3 K
4 K
5 K
6 A
1 A
2 A
3 A
4 G
TOTAL A2 G*
TOTAL
: 1.
Emergency Abnormal Plant Evolutions 1
3 3
2 4
3 3
18 6
2 1
2 1
2 2
1 9
4 Tier Totals 4
5 3
6 5
4 27 10
: 2.
Plant Systems 1
3 2
3 3
2 2
3 3
2 2
3 28 5
2 1
1 1
1 0
0 2
2 0
1 1
10 3
Tier Totals 4
3 4
4 2
2 5
5 2
3 4
38 8
: 3. Generic Knowledge and Abilities Category 1
2 3
4 10 1 2 3 4 7
2 3
2 3
Note:
Note:
* The facility reviewer's initials/signature are not applicable for NRC-developed examinations.
: 1.
          # Independent NRC reviewer initial items in Column c; chief examiner concurrence required.
Ensure that at least two topics from every applicable K/A category are sampled within each tier of the RO and SRO-only outlines (i.e., except for one category in Tier 3 of the SRO-only outline, the Tier Totals in each K/A category shall not be less than two).
NUREG-1021, Revision 9 Supplement 1                                                                  FENOC Facsimile Rev. 1
: 2.
 
The point total for each group and tier in the proposed outline must match that specified in the table. The final point total for each group and tier may deviate by +/-1 from that specified in the table based on NRC revisions. The final RO exam must total 75 points and the SRO-only exam must total 25 points.
ES-401                                                  PWR Examination Outline                                  Form ES-401-2 Facility: Davis-Besse RO                                            Date of Exam 6/3 thru 6/14 2013 RO K/A Category Points                                          SRO ONLY Points Tier          Group K    K    K    K    K    K      A    A    A      A    G      TOTAL      A2      G*      TOTAL 1    2    3    4    5    6      1    2    3      4
: 3.
* 1 3      3    2                      4    3                3      18                            6 1.
Systems/evolutions within each group are identified on the associated outline; systems or evolutions that do not apply at the facility should be deleted and justified; operationally important, site-specific systems/evolutions that are not included on the outline should be added. Refer to Section D.1.b of ES-401 for guidance regarding the elimination of inappropriate K/A statements.
Emergency              2
: 4.
            &                        1      2    1                      2    2                1        9                            4 Abnormal Plant              Tier Totals 4      5    3                      6    5                4      27                          10 Evolutions 1
Select topics from as many systems and evolutions as possible; sample every system or evolution in the group before selecting a second topic for any system or evolution.
2.
: 5.
3    2    3    3    2    2      3    3    2      2    3        28                            5 Plant Systems              2 1    1    1    1    0    0      2    2    0      1    1        10                            3 Tier Totals 4    3    4    4    2    2      5    5    2      3    4        38                            8 1          2          3          4                  1 2 3 4
Absent a plant-specific priority, only those K/As having an importance rating (IR) of 2.5 or higher shall be selected.
: 3. Generic Knowledge and Abilities                                                                  10                            7 Category 2          3          2          3 Note:
: 1.      Ensure that at least two topics from every applicable K/A category are sampled within each tier of the RO and SRO-only outlines (i.e., except for one category in Tier 3 of the SRO-only outline, the Tier Totals in each K/A category shall not be less than two).
: 2.       The point total for each group and tier in the proposed outline must match that specified in the table. The final point total for each group and tier may deviate by +/-1 from that specified in the table based on NRC revisions. The final RO exam must total 75 points and the SRO-only exam must total 25 points.
: 3.       Systems/evolutions within each group are identified on the associated outline; systems or evolutions that do not apply at the facility should be deleted and justified; operationally important, site-specific systems/evolutions that are not included on the outline should be added. Refer to Section D.1.b of ES-401 for guidance regarding the elimination of inappropriate K/A statements.
: 4.       Select topics from as many systems and evolutions as possible; sample every system or evolution in the group before selecting a second topic for any system or evolution.
: 5.       Absent a plant-specific priority, only those K/As having an importance rating (IR) of 2.5 or higher shall be selected.
Use the RO and SRO ratings for the RO and SRO-only portions, respectively.
Use the RO and SRO ratings for the RO and SRO-only portions, respectively.
: 6.       Select SRO topics for Tiers 1 and 2 from the shaded systems and K/A categories.
: 6.
7.*     The generic (G) K/As in Tiers 1 and 2 shall be selected from Section 2 of the K/A Catalog, but the topics must be relevant to the applicable evolution or system. Refer to Section D.1.b of ES-401 for the applicable K/As.
Select SRO topics for Tiers 1 and 2 from the shaded systems and K/A categories.
: 8.       On the following pages, enter the K/A numbers, a brief description of each topic, the topics importance ratings (IRs) for the applicable license level, and the point totals (#) for each system and category. Enter the group and tier totals for each category in the table above; if fuel handling equipment is sampled in other than Category A2 or G* on the SRO-only exam, enter it on the left side of Column A2 for Tier 2, Group 2 (Note #1 does not apply). Use duplicate pages for RO and SRO-only exams.
7.*
: 9.       For Tier 3, select topics from Section 2 of the K/A catalog, and enter the K/A numbers, descriptions, IRs, and point totals (#) on Form ES-401-3. Limit SRO selections to K/As that are linked to 10 CFR 55.43.
The generic (G) K/As in Tiers 1 and 2 shall be selected from Section 2 of the K/A Catalog, but the topics must be relevant to the applicable evolution or system. Refer to Section D.1.b of ES-401 for the applicable K/As.
NUREG-1021, Revision 9 Supplement 1                    RO Page 1 of 9                                          FENOC Facsimile Rev. 1
: 8.
On the following pages, enter the K/A numbers, a brief description of each topic, the topics importance ratings (IRs) for the applicable license level, and the point totals (#) for each system and category. Enter the group and tier totals for each category in the table above; if fuel handling equipment is sampled in other than Category A2 or G* on the SRO-only exam, enter it on the left side of Column A2 for Tier 2, Group 2 (Note #1 does not apply). Use duplicate pages for RO and SRO-only exams.
: 9.
For Tier 3, select topics from Section 2 of the K/A catalog, and enter the K/A numbers, descriptions, IRs, and point totals (#) on Form ES-401-3. Limit SRO selections to K/As that are linked to 10 CFR 55.43.  


ES-401                                       PWR Examination Outline                               Form ES-401-2 Davis-Besse 6/2013                     Emergency and Abnormal Plant Evolutions - Tier 1/Group 1(RO)
NUREG-1021, Revision 9 Supplement 1 RO Page 2 of 9 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Davis-Besse 6/2013 Emergency and Abnormal Plant Evolutions - Tier 1/Group 1(RO)
E/APE # / Name / Safety Function   K K   K A A G                           K/A Topic(s)                         IR Points 1  2  3  1 2 000008 Pressurizer (PZR) Vapor Space                         AK1.01 Knowledge of the operational implications         3.2 Accident                                X                    of the following concepts as they apply to a 1
E/APE # / Name / Safety Function K
Question 1                                                  Pressurizer Vapor Space Accident:
1 K
Thermodynamics and flow characteristics of open or leaking valves (CFR 41.8 / 41.10 / 45.3) 000009 Small Break LOCA                                     EK2.03 Knowledge of the interrelations between           3.0 Question 2 X                the small break LOCA and the following: S/Gs 1
2 K
(CFR 41.7 / 45.7) 000011 Large Break LOCA                                     EA2.10 Ability to determine or interpret the             4.5 Question 3                                            X      following as they apply to a Large Break LOCA:
3 A
1 Verification of adequate core cooling (CFR 43.5 / 45.13) 000015/000017 Reactor Coolant Pump                           2.4.11 Knowledge of abnormal condition                   4.0 (RCP) Malfunctions                                        X procedures.
1 A
1 Question 4                                                  (CFR: 41.10 / 43.5 / 45.13) 000022 Loss of Reactor Coolant Makeup                       AK3.02 Knowledge of the reasons for the following       3.5 X            responses as they apply to the Loss of Reactor 1
2 G
Question 5 Coolant Makeup: Actions contained in SOPs and EOPs for RCPs, loss of makeup, loss of charging, and abnormal charging (CFR 41.5, 41.10 / 45.6 / 45.13) 000025 Loss of Residual Heat Removal                         AA1.01 Ability to operate and / or monitor the           3.6 System (RHRS)                                    X          following as they apply to the Loss of Residual Heat 1
K/A Topic(s)
Question 6                                                  Removal System: RCS/RHRS cooldown rate (CFR 41.7 / 45.5 / 45.6) 000026 Loss of Component Cooling Water                       AA1. 07 Ability to operate and / or monitor the         2.9 (CCW)                                            X          following as they apply to the Loss of Component 1
IR Points 000008 Pressurizer (PZR) Vapor Space Accident Question 1 X
Question 7                                                  Cooling Water: Flow rates to the components and systems that are serviced by the CCWS; interactions among the components (CFR 41.7 / 45.5 / 45.6) 000027 Pressurizer Pressure Control                         AK2.03 Knowledge of the interrelations between           2.6 System (PZR PCS) Malfunction              X                the Pressurizer Pressure Control Malfunctions and 1
AK1.01 Knowledge of the operational implications of the following concepts as they apply to a Pressurizer Vapor Space Accident:
Question 8                                                  the following: Controllers and positioners (CFR 41.7 / 45.7) 000029 Anticipated Transient Without                         EK2.06 Knowledge of the interrelations between           2.9*
Thermodynamics and flow characteristics of open or leaking valves (CFR 41.8 / 41.10 / 45.3) 3.2 1
Scram (ATWS)                              X                the and the following an ATWS: Breakers, relays, 1
000009 Small Break LOCA Question 2 X
Question 9                                                  and disconnects (CFR 41.7 / 45.7) 000038 Steam Generator Tube Rupture                         EA2.12 Ability to determine or interpret the             3.9*
EK2.03 Knowledge of the interrelations between the small break LOCA and the following: S/Gs (CFR 41.7 / 45.7) 3.0 1
(SGTR)                                                X      following as they apply to a SGTR: Status of MSIV 1
000011 Large Break LOCA Question 3 X
Question 10                                                  activating system (CFR 43.5 / 45.13) 000040 Steam Line Rupture - Excessive                       2.1.7 Ability to evaluate plant performance and         4.4 Heat Transfer                                              X make operational judgments based on operating 1
EA2.10 Ability to determine or interpret the following as they apply to a Large Break LOCA:
Question 11                                                  characteristics, reactor behavior, and instrument interpretation.
Verification of adequate core cooling (CFR 43.5 / 45.13) 4.5 1
(CFR: 41.5 / 43.5 / 45.12 / 45.13) 000054 Loss of Main Feedwater (MFW)                         AA2.01 Ability to determine and interpret the           4.3 X      following as they apply to the Loss of Main 1
000015/000017 Reactor Coolant Pump (RCP) Malfunctions Question 4 X
Question 12 Feedwater (MFW): Occurrence of reactor and/or turbine trip (CFR: 43.5 / 45.13)
2.4.11 Knowledge of abnormal condition procedures.
NUREG-1021, Revision 9 Supplement 1          RO Page 2 of 9                                        FENOC Facsimile Rev. 1
(CFR: 41.10 / 43.5 / 45.13) 4.0 1
000022 Loss of Reactor Coolant Makeup Question 5 X
AK3.02 Knowledge of the reasons for the following responses as they apply to the Loss of Reactor Coolant Makeup: Actions contained in SOPs and EOPs for RCPs, loss of makeup, loss of charging, and abnormal charging (CFR 41.5, 41.10 / 45.6 / 45.13) 3.5 1
000025 Loss of Residual Heat Removal System (RHRS)
Question 6 X
AA1.01 Ability to operate and / or monitor the following as they apply to the Loss of Residual Heat Removal System: RCS/RHRS cooldown rate (CFR 41.7 / 45.5 / 45.6) 3.6 1
000026 Loss of Component Cooling Water (CCW)
Question 7 X
AA1. 07 Ability to operate and / or monitor the following as they apply to the Loss of Component Cooling Water: Flow rates to the components and systems that are serviced by the CCWS; interactions among the components (CFR 41.7 / 45.5 / 45.6) 2.9 1
000027 Pressurizer Pressure Control System (PZR PCS) Malfunction Question 8 X
AK2.03 Knowledge of the interrelations between the Pressurizer Pressure Control Malfunctions and the following: Controllers and positioners (CFR 41.7 / 45.7) 2.6 1
000029 Anticipated Transient Without Scram (ATWS)
Question 9 X
EK2.06 Knowledge of the interrelations between the and the following an ATWS: Breakers, relays, and disconnects (CFR 41.7 / 45.7) 2.9*
1 000038 Steam Generator Tube Rupture (SGTR)
Question 10 X
EA2.12 Ability to determine or interpret the following as they apply to a SGTR: Status of MSIV activating system (CFR 43.5 / 45.13) 3.9*
1 000040 Steam Line Rupture - Excessive Heat Transfer Question 11 X
2.1.7 Ability to evaluate plant performance and make operational judgments based on operating characteristics, reactor behavior, and instrument interpretation.
(CFR: 41.5 / 43.5 / 45.12 / 45.13) 4.4 1
000054 Loss of Main Feedwater (MFW)
Question 12 X
AA2.01 Ability to determine and interpret the following as they apply to the Loss of Main Feedwater (MFW): Occurrence of reactor and/or turbine trip (CFR: 43.5 / 45.13) 4.3 1  


ES-401                                             PWR Examination Outline                               Form ES-401-2 Davis-Besse 6/2013                         Emergency and Abnormal Plant Evolutions - Tier 1/Group 1(RO) Continued E/APE # / Name / Safety Function       K K K A A G                               K/A Topic(s)                         IR   Points 1 2 3 1 2 000055 Loss of Offsite and Onsite Power                           EA1.06 Ability to operate and monitor the following     4.1 (Station Blackout)                                    X          as they apply to a Station Blackout: Restoration of 1
NUREG-1021, Revision 9 Supplement 1 RO Page 3 of 9 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Davis-Besse 6/2013 Emergency and Abnormal Plant Evolutions - Tier 1/Group 1(RO) Continued E/APE # / Name / Safety Function K
Question 13                                                      power with one ED/G (CFR 41.7 / 45.5 / 45.6) 000056 Loss of Offsite Power                                     AK1.01 Knowledge of the operational implications         3.7 X                    of the following concepts as they apply to Loss of 1
1 K
Question 14 Offsite Power: Principle of cooling by natural convection (CFR 41.8 / 41.10 / 45.3) 000062 Loss of Nuclear Service Water                             AK3.01 Knowledge of the reasons for the following       3.2*
2 K
X            responses as they apply to the Loss of Nuclear 1
3 A
Question 15 Service Water: The conditions that will initiate the automatic opening and closing of the SWS isolation valves to the nuclear service water coolers (CFR 41.4, 41.8 / 45.7 )
1 A
000077 Generator Voltage and Electric Grid                       AK1.03 Knowledge of the operational implications         3.3 Disturbances                                X                    of the following concepts as they apply to 1
2 G
Question 16                                                      Generator Voltage and Electric Grid Disturbances:
K/A Topic(s)
Under-excitation (CFR: 41.4, 41.5, 41.7, 41.10 / 45.8)
IR Points 000055 Loss of Offsite and Onsite Power (Station Blackout)
BW/E04 Inadequate Heat Transfer - Loss                           EA1.1 Ability to operate and / or monitor the           4.4 Of Secondary Heat Sink                                X          following as they apply to the (Inadequate Heat 1
Question 13 X
Question 17                                                      Transfer) Components, and functions of control and safety systems, including instrumentation, signals, interlocks, failure modes, and automatic and manual features.
EA1.06 Ability to operate and monitor the following as they apply to a Station Blackout: Restoration of power with one ED/G (CFR 41.7 / 45.5 / 45.6) 4.1 1
(CFR: 41.7 / 45.5 / 45.6)
000056 Loss of Offsite Power Question 14 X
BW/E10 Post-Trip Stabilization                                   2.1.19 Ability to use plant computers to evaluate       3.9 X system or component status.
AK1.01 Knowledge of the operational implications of the following concepts as they apply to Loss of Offsite Power: Principle of cooling by natural convection (CFR 41.8 / 41.10 / 45.3) 3.7 1
1 Question 18 (CFR: 41.10 / 45.12)
000062 Loss of Nuclear Service Water Question 15 X
K/A Category Point Totals: 3 3   2 4   3   3                                             Group Point Total: 18 NUREG-1021, Revision 9 Supplement 1                RO Page 3 of 9                                        FENOC Facsimile Rev. 1
AK3.01 Knowledge of the reasons for the following responses as they apply to the Loss of Nuclear Service Water: The conditions that will initiate the automatic opening and closing of the SWS isolation valves to the nuclear service water coolers (CFR 41.4, 41.8 / 45.7 )
3.2*
1 000077 Generator Voltage and Electric Grid Disturbances Question 16 X
AK1.03 Knowledge of the operational implications of the following concepts as they apply to Generator Voltage and Electric Grid Disturbances:
Under-excitation (CFR: 41.4, 41.5, 41.7, 41.10 / 45.8) 3.3 1
BW/E04 Inadequate Heat Transfer - Loss Of Secondary Heat Sink Question 17 X
EA1.1 Ability to operate and / or monitor the following as they apply to the (Inadequate Heat Transfer) Components, and functions of control and safety systems, including instrumentation, signals, interlocks, failure modes, and automatic and manual features.
(CFR: 41.7 / 45.5 / 45.6) 4.4 1
BW/E10 Post-Trip Stabilization Question 18 X
2.1.19 Ability to use plant computers to evaluate system or component status.
(CFR: 41.10 / 45.12) 3.9 1
K/A Category Point Totals:
3 3
2 4
3 3
Group Point Total:
18  


ES-401                                             PWR Examination Outline                                 Form ES-401-2 Davis-Besse 6/2013                         Emergency and Abnormal Plant Evolutions - Tier 1/Group 2(RO)
NUREG-1021, Revision 9 Supplement 1 RO Page 4 of 9 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Davis-Besse 6/2013 Emergency and Abnormal Plant Evolutions - Tier 1/Group 2(RO)
E/APE # / Name / Safety Function         K K K A A G                               K/A Topic(s)                         IR Points 1 2 3 1 2 000036 Fuel Handling Incidents                                   AK1.03 Knowledge of the operational implications         4.0 X                    of the following concepts as they apply to Fuel 1
E/APE # / Name / Safety Function K
Question 19 Handling Incidents : Indications of approaching Criticality (CFR 41.8 / 41.10 / 45.3) 000051 Loss of Condenser Vacuum                                   2.2.44 Ability to interpret control room indications to   4.2 X verify the status and operation of a system, and 1
1 K
Question 20                                                      understand how operator actions and directives affect plant and system conditions.
2 K
(CFR: 41.5 / 43.5 / 45.12) 000059 Accidental Liquid Radwaste                                 AK2.01 Knowledge of the interrelations between           2.7 Release X                the Accidental Liquid Radwaste Release and the 1
3 A
following: Radioactive-liquid monitors Question 21 (CFR 41.7 / 45.7) 000060 Accidental Gaseous-Waste                                   AA2.06 Ability to operate and / or monitor the           3.6*
1 A
Release X      following as they apply to the Accidental Gaseous 1
2 G
Radwaste: Valve lineup for release of radioactive Question 22 gases (CFR 41.7 / 45.5 / 45.6) 000061 ARM System Alarms                                         AK3.02 Knowledge of the reasons for the following         3.4 X            responses as they apply to the Area Radiation 1
K/A Topic(s)
Question 23 Monitoring (ARM) System Alarms: Guidance contained in alarm response for ARM system (CFR 41.5,41.10 / 45.6 / 45.13) 000069 Loss of Containment Integrity                             AA1.03 Ability to operate and / or monitor the           2.8 X          following as they apply to the Loss of Containment 1
IR Points 000036 Fuel Handling Incidents Question 19 X
Question 24                                                      Integrity: Fluid systems penetrating containment (CFR 41.7 / 45.5 / 45.6)
AK1.03 Knowledge of the operational implications of the following concepts as they apply to Fuel Handling Incidents : Indications of approaching Criticality (CFR 41.8 / 41.10 / 45.3) 4.0 1
BW/A01 Plant Runback                                             AA2.1 Ability to determine and interpret the             3.0 X      following as they apply to the (Plant Runback) 1 Question 25                                                      Facility conditions and selection of appropriate procedures during abnormal and emergency operations.
000051 Loss of Condenser Vacuum Question 20 X
(CFR: 43.5 / 45.13)
2.2.44 Ability to interpret control room indications to verify the status and operation of a system, and understand how operator actions and directives affect plant and system conditions.
BW/A02 Loss of NNI-X                                             AK2.2 Knowledge of the interrelations between the         3.8 X                (Loss of NNI-X) and the following: Facilitys heat 1
(CFR: 41.5 / 43.5 / 45.12) 4.2 1
Question 26                                                      removal systems, including primary coolant, emergency coolant, the decay heat removal systems, and relations between the proper operation of these systems to the operation of the facility.
000059 Accidental Liquid Radwaste Release Question 21 X
(CFR: 41.7 / 45.7)
AK2.01 Knowledge of the interrelations between the Accidental Liquid Radwaste Release and the following: Radioactive-liquid monitors (CFR 41.7 / 45.7) 2.7 1
BW/E13 EOP Rules                                                 EA1.3 Ability to operate and / or monitor the             3.4 X          following as they apply to the (EOP Rules) Desired 1
000060 Accidental Gaseous-Waste Release Question 22 X
Question 27                                                      operating results during abnormal and emergency situations.
AA2.06 Ability to operate and / or monitor the following as they apply to the Accidental Gaseous Radwaste: Valve lineup for release of radioactive gases (CFR 41.7 / 45.5 / 45.6) 3.6*
(CFR: 41.7 / 45.5 / 45.6)
1 000061 ARM System Alarms Question 23 X
K/A Category Point Totals: 1 2   1 2   2   1                                             Group Point Total:   9 NUREG-1021, Revision 9 Supplement 1                RO Page 4 of 9                                          FENOC Facsimile Rev. 1
AK3.02 Knowledge of the reasons for the following responses as they apply to the Area Radiation Monitoring (ARM) System Alarms: Guidance contained in alarm response for ARM system (CFR 41.5,41.10 / 45.6 / 45.13) 3.4 1
000069 Loss of Containment Integrity Question 24 X
AA1.03 Ability to operate and / or monitor the following as they apply to the Loss of Containment Integrity: Fluid systems penetrating containment (CFR 41.7 / 45.5 / 45.6) 2.8 1
BW/A01 Plant Runback Question 25 X
AA2.1 Ability to determine and interpret the following as they apply to the (Plant Runback)
Facility conditions and selection of appropriate procedures during abnormal and emergency operations.
(CFR: 43.5 / 45.13) 3.0 1
BW/A02 Loss of NNI-X Question 26 X
AK2.2 Knowledge of the interrelations between the (Loss of NNI-X) and the following: Facilitys heat removal systems, including primary coolant, emergency coolant, the decay heat removal systems, and relations between the proper operation of these systems to the operation of the facility.
(CFR: 41.7 / 45.7) 3.8 1
BW/E13 EOP Rules Question 27 X
EA1.3 Ability to operate and / or monitor the following as they apply to the (EOP Rules) Desired operating results during abnormal and emergency situations.
(CFR: 41.7 / 45.5 / 45.6) 3.4 1
K/A Category Point Totals:
1 2
1 2
2 1
Group Point Total:
9  


ES-401                                       PWR Examination Outline                                 Form ES-401-2 Davis-Besse 6/2013                           Plant Systems - Tier 2/Group 1(RO)
NUREG-1021, Revision 9 Supplement 1 RO Page 5 of 9 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Davis-Besse 6/2013 Plant Systems - Tier 2/Group 1(RO)
System # / Name           K K K K K K A A A A G                             K/A Topic(s)                     IR Points 1 2 3 4 5 6 1 2 3 4 003 Reactor Coolant Pump                                           A3.02 Ability to monitor automatic operation     2.6 System (RCPS)
System # / Name K
X        of the RCPS, including: Motor current 1
1 K
Question 28                                                        (CFR: 41.7 / 45.5) 003 Reactor Coolant Pump                                           K3.01 Knowledge of the effect that a loss or     3.7 System (RCPS)
2 K
X                          malfunction of the RCPS will have on the 1
3 K
Question 29                                                        following: RCS (CFR: 41.7 / 45.6) 004 Chemical and Volume                                           K4.14 Knowledge of CVCS design feature(s)         2.8*
4 K
Control System X                        and/or interlock(s) which provide for the 1
5 K
following: Control interlocks on letdown Question 30                                                        system (letdown tank bypass valve)
6 A
(CFR: 41.7) 005 Residual Heat Removal                                         K6.03 Knowledge of the effect of a loss or       2.5 System (RHRS)
1 A
X                    malfunction on the following will have on the 1
2 A
RHRS: RHR heat exchanger Question 31 (CFR: 41.7 / 45.7) 006 Emergency Core Cooling                                         K6.02 Knowledge of the effect of a loss or       3.4 System (ECCS)
3 A
X                    malfunction on the following will have on the 1
4 G
ECCS: Core flood tanks (accumulators)
K/A Topic(s)
Question 32 (CFR: 41.7 / 45.7) 007 Pressurizer Relief                                             K3.01 Knowledge of the effect that a loss or     3.3 Tank/Quench Tank System X                          malfunction of the PRTS will have on the 1
IR Points 003 Reactor Coolant Pump System (RCPS)
(PRTS)                                                            following: Containment Question 33                                                        (CFR: 41.7 / 45.6) 008 Component Cooling Water                                       A2.01 Ability to (a) predict the impacts of the   3.3 System (CCWS)
Question 28 X
X            following malfunctions or operations on the 1
A3.02 Ability to monitor automatic operation of the RCPS, including: Motor current (CFR: 41.7 / 45.5) 2.6 1
CCWS, and (b) based on those predictions, Question 34                                                        use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Loss of CCW pump (CFR: 41.5 / 43.5 / 45.3 / 45.13) 010 Pressurizer Pressure                                           2.2.39 Knowledge of less than or equal to         3.9 Control System (PZR PCS)
003 Reactor Coolant Pump System (RCPS)
one hour Technical Specification action 1
Question 29 X
Question 35                                                        statements for systems.
K3.01 Knowledge of the effect that a loss or malfunction of the RCPS will have on the following: RCS (CFR: 41.7 / 45.6) 3.7 1
(CFR: 41.7 / 41.10 / 43.2 / 45.13) 010 Pressurizer Pressure                                           K4.02 Knowledge of PZR PCS design                 3.0 Control System (PZR PCS)
004 Chemical and Volume Control System Question 30 X
X                        feature(s) and/or interlock(s) which provide 1
K4.14 Knowledge of CVCS design feature(s) and/or interlock(s) which provide for the following: Control interlocks on letdown system (letdown tank bypass valve)
Question 36                                                        for the following: Prevention of uncovering PZR heaters (CFR: 41.7) 012 Reactor Protection System                                     A2.07 Ability to (a) predict the impacts of the   3.2*
(CFR: 41.7) 2.8*
(RPS)
1 005 Residual Heat Removal System (RHRS)
X            following malfunctions or operations on the 1
Question 31 X
Question 37                                                        RPS; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Loss of dc control power (CFR: 41.5 / 43.5 / 45.3 / 45.5)
K6.03 Knowledge of the effect of a loss or malfunction on the following will have on the RHRS: RHR heat exchanger (CFR: 41.7 / 45.7) 2.5 1
NUREG-1021, Revision 9 Supplement 1          RO Page 5 of 9                                        FENOC Facsimile Rev. 1
006 Emergency Core Cooling System (ECCS)
Question 32 X
K6.02 Knowledge of the effect of a loss or malfunction on the following will have on the ECCS: Core flood tanks (accumulators)
(CFR: 41.7 / 45.7) 3.4 1
007 Pressurizer Relief Tank/Quench Tank System (PRTS)
Question 33 X
K3.01 Knowledge of the effect that a loss or malfunction of the PRTS will have on the following: Containment (CFR: 41.7 / 45.6) 3.3 1
008 Component Cooling Water System (CCWS)
Question 34 X
A2.01 Ability to (a) predict the impacts of the following malfunctions or operations on the CCWS, and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Loss of CCW pump (CFR: 41.5 / 43.5 / 45.3 / 45.13) 3.3 1
010 Pressurizer Pressure Control System (PZR PCS)
Question 35 X
2.2.39 Knowledge of less than or equal to one hour Technical Specification action statements for systems.
(CFR: 41.7 / 41.10 / 43.2 / 45.13) 3.9 1
010 Pressurizer Pressure Control System (PZR PCS)
Question 36 X
K4.02 Knowledge of PZR PCS design feature(s) and/or interlock(s) which provide for the following: Prevention of uncovering PZR heaters (CFR: 41.7) 3.0 1
012 Reactor Protection System (RPS)
Question 37 X
A2.07 Ability to (a) predict the impacts of the following malfunctions or operations on the RPS; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Loss of dc control power (CFR: 41.5 / 43.5 / 45.3 / 45.5) 3.2*
1  


ES-401                                       PWR Examination Outline                                 Form ES-401-2 Davis-Besse 6/2013                           Plant Systems - Tier 2/Group 1(RO) Continued System # / Name           K K K K K K A A A       A G                     K/A Topic(s)                     IR Points 1 2 3 4 5 6 1 2 3        4 013 Engineered Safety Features                                     K1.07 Knowledge of the physical                   4.1 Actuation System (ESFAS)
NUREG-1021, Revision 9 Supplement 1 RO Page 6 of 9 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Davis-Besse 6/2013 Plant Systems - Tier 2/Group 1(RO) Continued System # / Name K
X                              connections and/or cause effect 1
1 K
relationships between the ESFAS and the Question 38                                                        following systems: AFW System (CFR: 41.2 to 41.9 / 45.7 to 45.8) 022 Containment Cooling                                           A1.04 Ability to predict and/or monitor           3.2 System (CCS)
2 K
X                changes in parameters (to prevent 1
3 K
exceeding design limits) associated with Question 39                                                        operating the CCS controls including:
4 K
Cooling water flow (CFR: 41.5 / 45.5) 004 Chemical and Volume                                           2.4.4 Ability to recognize abnormal               4.5 Control System X  indications for system operating parameters 1
5 K
that are entry-level conditions for emergency Question 40                                                        and abnormal operating procedures.
6 A
(CFR: 41.10 / 43.2 / 45.6) 062 AC Electrical Distribution                                     K1.02 Knowledge of the physical                   4.1 System X                              connections and/or cause/effect 1
1 A
relationships between the ac distribution Question 41                                                        system and the following systems: ED/G (CFR: 41.2 to 41.9) 026 Containment Spray System                                       K2.02 Knowledge of bus power supplies to         2.7*
2 A
(CSS)
3 A
X                            the following: MOVs 1
4 G
Question 42                                                        (CFR: 41.7) 039 Main and Reheat Steam                                         K5.08 Knowledge of the operational               3.6 System (MRSS)
K/A Topic(s)
X                      implications of the following concepts as the 1
IR Points 013 Engineered Safety Features Actuation System (ESFAS)
apply to the MRSS: Effect of steam removal Question 43 on reactivity (CFR: 441.5 / 45.7) 059 Main Feedwater (MFW)                                           A1.07 Ability to predict and/or monitor           2.5*
Question 38 X
System X                changes in parameters (to prevent 1
K1.07 Knowledge of the physical connections and/or cause effect relationships between the ESFAS and the following systems: AFW System (CFR: 41.2 to 41.9 / 45.7 to 45.8) 4.1 1
Question 44                                                        exceeding design limits) associated with operating the MFW controls including: Feed Pump speed, including normal control speed for ICS (CFR: 41.5 / 45.5) 059 Main Feedwater (MFW)                                           A4.01 Ability to manually operate and             3.1*
022 Containment Cooling System (CCS)
System X      monitor in the control room: MFW turbine 1
Question 39 X
Question 45                                                        trip indication (CFR: 41.7 / 45.5 to 45.8) 061 Auxiliary / Emergency                           X             A2.06 Ability to (a) predict the impacts of the   2.7    1 Feedwater (AFW) System                                            following malfunctions or operations on the AFW; and (b) based on those predictions, Question 46 use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Back leakage of MFW (CFR: 41.5 / 43.5 / 45.3 / 45.13) 062 AC Electrical Distribution                           X       A3.04 Ability to monitor automatic operation     2.7    1 System                                                            of the ac distribution system, including:
A1.04 Ability to predict and/or monitor changes in parameters (to prevent exceeding design limits) associated with operating the CCS controls including:
Operation of inverter (e.g., precharging Question 47 synchronizing light, static transfer)
Cooling water flow (CFR: 41.5 / 45.5) 3.2 1
(CFR: 41.7 / 45.5)
004 Chemical and Volume Control System Question 40 X
NUREG-1021, Revision 9 Supplement 1          RO Page 6 of 9                                        FENOC Facsimile Rev. 1
2.4.4 Ability to recognize abnormal indications for system operating parameters that are entry-level conditions for emergency and abnormal operating procedures.
(CFR: 41.10 / 43.2 / 45.6) 4.5 1
062 AC Electrical Distribution System Question 41 X
K1.02 Knowledge of the physical connections and/or cause/effect relationships between the ac distribution system and the following systems: ED/G (CFR: 41.2 to 41.9) 4.1 1
026 Containment Spray System (CSS)
Question 42 X
K2.02 Knowledge of bus power supplies to the following: MOVs (CFR: 41.7) 2.7*
1 039 Main and Reheat Steam System (MRSS)
Question 43 X
K5.08 Knowledge of the operational implications of the following concepts as the apply to the MRSS: Effect of steam removal on reactivity (CFR: 441.5 / 45.7) 3.6 1
059 Main Feedwater (MFW)
System Question 44 X
A1.07 Ability to predict and/or monitor changes in parameters (to prevent exceeding design limits) associated with operating the MFW controls including: Feed Pump speed, including normal control speed for ICS (CFR: 41.5 / 45.5) 2.5*
1 059 Main Feedwater (MFW)
System Question 45 X
A4.01 Ability to manually operate and monitor in the control room: MFW turbine trip indication (CFR: 41.7 / 45.5 to 45.8) 3.1*
1 061 Auxiliary / Emergency Feedwater (AFW) System Question 46 X
A2.06 Ability to (a) predict the impacts of the following malfunctions or operations on the AFW; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Back leakage of MFW (CFR: 41.5 / 43.5 / 45.3 / 45.13) 2.7 1
062 AC Electrical Distribution System Question 47 X
A3.04 Ability to monitor automatic operation of the ac distribution system, including:
Operation of inverter (e.g., precharging synchronizing light, static transfer)
(CFR: 41.7 / 45.5) 2.7 1  


ES-401                                       PWR Examination Outline                               Form ES-401-2 Davis-Besse 6/2013                           Plant Systems - Tier 2/Group 1(RO) Continued System # / Name             K K K K K K A A A A G                             K/A Topic(s)                     IR   Points 1 2 3 4 5 6 1 2 3 4 063 DC Electrical Distribution                   X                 A1.01 Ability to predict and/or monitor           2.5    1 System                                                              changes in parameters associated with operating the DC electrical system controls Question 48                                                        including: Battery capacity as it is affected by discharge rate (CFR: 41.5 / 45.5) 063 DC Electrical Distribution                               X     A4.02 Ability to manually operate and/or         2.8*    1 System                                                              monitor in the control room: Battery voltage indicator Question 49 (CFR: 41.7 / 45.5 to 45.8) 064 Emergency Diesel                     X                         K4.03 Knowledge of ED/G system design             2.5    1 Generator (ED/G) System                                            feature(s) and/or interlock(s) which provide for the following: Governor valve operation Question 50 (CFR: 41.7) 073 Process Radiation                     X                       K5.01 Knowledge of the operational               2.5    1 Monitoring (PRM) System                                            implications as they apply to concepts as they apply to the PRM system: Radiation Question 51                                                        theory, including sources, types, units, and effects (CFR: 41.5 / 45.7) 076 Service Water System             X                             K2.04 Knowledge of bus power supplies to         2.5*    1 (SWS)                                                              the following: Reactor building closed cooling water Question 52 (CFR: 41.7) 078 Instrument Air System (IAS)   X                               K1.05 Knowledge of the physical                   3.4*    1 connections and/or cause-effect Question 53                                                        relationships between the IAS and the following systems: MSIV air (CFR: 41.2 to 41.9 / 45.7 to 45.8) 103 Containment System                                         X   2.1.28 Knowledge of the purpose and               4.1    1 function of major system components and Question 54                                                        controls.
NUREG-1021, Revision 9 Supplement 1 RO Page 7 of 9 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Davis-Besse 6/2013 Plant Systems - Tier 2/Group 1(RO) Continued System # / Name K
(CFR: 41.7) 103 Containment System                 X                           K3.02 Knowledge of the effect that a loss or     3.8    1 malfunction of the containment system will Question 55                                                        have on the following: Loss of containment integrity under normal operations (CFR: 41.7 / 45.6)
1 K
K/A Category Point Totals:   3 2 3 3 2   2 3   3   2 2 3                                       Group Point Total: 28 NUREG-1021, Revision 9 Supplement 1          RO Page 7 of 9                                        FENOC Facsimile Rev. 1
2 K
3 K
4 K
5 K
6 A
1 A
2 A
3 A
4 G
K/A Topic(s)
IR Points 063 DC Electrical Distribution System Question 48 X
A1.01 Ability to predict and/or monitor changes in parameters associated with operating the DC electrical system controls including: Battery capacity as it is affected by discharge rate (CFR: 41.5 / 45.5) 2.5 1
063 DC Electrical Distribution System Question 49 X
A4.02 Ability to manually operate and/or monitor in the control room: Battery voltage indicator (CFR: 41.7 / 45.5 to 45.8) 2.8*
1 064 Emergency Diesel Generator (ED/G) System Question 50 X
K4.03 Knowledge of ED/G system design feature(s) and/or interlock(s) which provide for the following: Governor valve operation (CFR: 41.7) 2.5 1
073 Process Radiation Monitoring (PRM) System Question 51 X
K5.01 Knowledge of the operational implications as they apply to concepts as they apply to the PRM system: Radiation theory, including sources, types, units, and effects (CFR: 41.5 / 45.7) 2.5 1
076 Service Water System (SWS)
Question 52 X
K2.04 Knowledge of bus power supplies to the following: Reactor building closed cooling water (CFR: 41.7) 2.5*
1 078 Instrument Air System (IAS)
Question 53 X
K1.05 Knowledge of the physical connections and/or cause-effect relationships between the IAS and the following systems: MSIV air (CFR: 41.2 to 41.9 / 45.7 to 45.8) 3.4*
1 103 Containment System Question 54 X 2.1.28 Knowledge of the purpose and function of major system components and controls.
(CFR: 41.7) 4.1 1
103 Containment System Question 55 X
K3.02 Knowledge of the effect that a loss or malfunction of the containment system will have on the following: Loss of containment integrity under normal operations (CFR: 41.7 / 45.6) 3.8 1
K/A Category Point Totals:
3 2
3 3
2 2
3 3
2 2
3 Group Point Total:
28  


ES-401                                       PWR Examination Outline                                 Form ES-401-2 Davis-Besse 6/2013                           Plant Systems - Tier 2/Group 2(RO)
NUREG-1021, Revision 9 Supplement 1 RO Page 8 of 9 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Davis-Besse 6/2013 Plant Systems - Tier 2/Group 2(RO)
System # / Name           K K K K K K A A         A A G                     K/A Topic(s) 1 2 3 4 5 6 1 2        3 4                                                          IR Points 002 Reactor Coolant System         X                               K1.03 Knowledge of the physical                   3.8    1 (RCS)                                                              connections and/or cause-effect relationships between the RCS and the Question 56                                                        following systems: Borated water storage tank (CFR: 41.2 to 41.9 / 45.7 to 45.8) 014 Rod Position Indication             X                         K4.03 Knowledge of RPIS design feature(s)         3.2    1 System                                                              and/or interlock(s) which provide for the following: Rod bottom lights Question 57 (CFR: 41.5 / 45.7) 015 Nuclear Instrumentation                                 X     A4.01 Ability to manually operate and/or         3.6*    1 System                                                              monitor in the control room: Selection of Question 58                                                        controlling NIS channel (CFR: 41.7 / 45.5 to 45.8) 041 Steam Dump System                                               A2.02 Ability to (a) predict the impacts of       3.6 (SDS) and Turbine Bypass X            the following malfunctions or operations                 1 Control                                                            on the SDS; and (b) based on those predictions or mitigate the consequences Question 59                                                        of those malfunctions or operations:
System # / Name K
Steam valve stuck open (CFR: 41.5 / 43.5 / 45.3 / 45.13) 055 Condenser Air Removal             X                           K3.01 Knowledge of the effect that a loss or     2.5    1 System                                                              malfunction of the CARS will have on the following: Main condenser Question 60 (CFR: 41.7 / 45.6) 068 Liquid Radwaste System                           X             A2.02 Ability to (a) predict the impacts of the   2.7*    1 following malfunctions or operations on the Question 61 Liquid Radwaste System; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Lack of tank recirculation prior to release (CFR: 41.5 / 43.5 / 45.3 / 45.13) 072 Area Radiation Monitoring                     X                 A1.01 Ability to predict and/or monitor           3.4    1 System                                                              changes in parameters (to prevent exceeding design limits) associated with Question 62                                                        operating the ARM system controls including: Radiation levels (CFR: 41.5 / 45.5) 075 Circulating Water System         X                             K2.03 Knowledge of bus power supplies to         2.6*    1 the following: Emergency/essential SWS Question 63                                                        pumps (CFR: 41.7) 079 Station Air System                                         X   2.4.2 Knowledge of system set points,             4.5    1 interlocks and automatic actions associated Question 64                                                        with EOP entry conditions.
1 K
(CFR: 41.7 / 45.7 / 45.8) 086 Fire Protection System                       X                 K6.04 Knowledge of the effect of a loss or       2.6    1 (FPS)                                                              malfunction on the Fire Protection System following will have on the : Fire, smoke, and Question 65                                                        heat detectors (CFR: 41.7 / 45.7)
2 K
K/A Category Point Totals:   1 1 1 1 0   0 2   2   0 1 1                                       Group Point Total: 10 NUREG-1021, Revision 9 Supplement 1          RO Page 8 of 9                                        FENOC Facsimile Rev. 1
3 K
4 K
5 K
6 A
1 A
2 A
3 A
4 G
K/A Topic(s)
IR Points 002 Reactor Coolant System (RCS)
Question 56 X
K1.03 Knowledge of the physical connections and/or cause-effect relationships between the RCS and the following systems: Borated water storage tank (CFR: 41.2 to 41.9 / 45.7 to 45.8) 3.8 1
014 Rod Position Indication System Question 57 X
K4.03 Knowledge of RPIS design feature(s) and/or interlock(s) which provide for the following: Rod bottom lights (CFR: 41.5 / 45.7) 3.2 1
015 Nuclear Instrumentation System Question 58 X
A4.01 Ability to manually operate and/or monitor in the control room: Selection of controlling NIS channel (CFR: 41.7 / 45.5 to 45.8) 3.6*
1 041 Steam Dump System (SDS) and Turbine Bypass Control Question 59 X
A2.02 Ability to (a) predict the impacts of the following malfunctions or operations on the SDS; and (b) based on those predictions or mitigate the consequences of those malfunctions or operations:
Steam valve stuck open (CFR: 41.5 / 43.5 / 45.3 / 45.13) 3.6 1
055 Condenser Air Removal System Question 60 X
K3.01 Knowledge of the effect that a loss or malfunction of the CARS will have on the following: Main condenser (CFR: 41.7 / 45.6) 2.5 1
068 Liquid Radwaste System Question 61 X
A2.02 Ability to (a) predict the impacts of the following malfunctions or operations on the Liquid Radwaste System; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Lack of tank recirculation prior to release (CFR: 41.5 / 43.5 / 45.3 / 45.13) 2.7*
1 072 Area Radiation Monitoring System Question 62 X
A1.01 Ability to predict and/or monitor changes in parameters (to prevent exceeding design limits) associated with operating the ARM system controls including: Radiation levels (CFR: 41.5 / 45.5) 3.4 1
075 Circulating Water System Question 63 X
K2.03 Knowledge of bus power supplies to the following: Emergency/essential SWS pumps (CFR: 41.7) 2.6*
1 079 Station Air System Question 64 X 2.4.2 Knowledge of system set points, interlocks and automatic actions associated with EOP entry conditions.
(CFR: 41.7 / 45.7 / 45.8) 4.5 1
086 Fire Protection System (FPS)
Question 65 X
K6.04 Knowledge of the effect of a loss or malfunction on the Fire Protection System following will have on the : Fire, smoke, and heat detectors (CFR: 41.7 / 45.7) 2.6 1
K/A Category Point Totals:
1 1
1 1
0 0
2 2 0
1 1
Group Point Total:
10  


ES 401                     Generic Knowledge and Abilities Outline (Tier 3)                                     Form ES-401-3 Facility: Davis-Besse RO                                                     Date of Exam 6/3 thru 6/14 2013 RO            SRO Only Category     K/A#                                           Topic IR     Points     IR     Points
NUREG-1021, Revision 9 Supplement 1 RO Page 9 of 9 FENOC Facsimile Rev. 1 ES 401 Generic Knowledge and Abilities Outline (Tier 3)
: 1.               2.1.40   Knowledge of refueling administrative requirements. (CFR: 41.10 / 43.5 /         2.8      1 Conduct                    45.13) of Operations Question 66 2.1.45   Ability to identify and interpret diverse indications to validate the             4.3      1 response of another indication. (CFR: 41.7 / 43.5 / 45.4)
Form ES-401-3 Facility: Davis-Besse RO Date of Exam 6/3 thru 6/14 2013 Category K/A#
Question 67 Subtotal   2
Topic RO SRO Only IR Points IR Points
: 2.               2.2.36   Ability to analyze the effect of maintenance activities, such as degraded         3.1      1 Equipment                  power sources, on the status of limiting conditions for operations. (CFR:
: 1.
Control                    41.10 / 43.2 / 45.13)
Conduct of Operations 2.1.40 Knowledge of refueling administrative requirements. (CFR: 41.10 / 43.5 /
Question 68 2.2.7     Knowledge of the process for conducting special or infrequent tests.             2.9      1 (CFR: 41.10 / 43.3 / 45.13)
45.13)
Question 69 2.2.35   Ability to determine Technical Specification Mode of Operation. (CFR:             3.6      1 41.7 / 41.10 / 43.2 / 45.13)
Question 66 2.8 1
Question 70 Subtotal   3
2.1.45 Ability to identify and interpret diverse indications to validate the response of another indication. (CFR: 41.7 / 43.5 / 45.4)
: 3.               2.3.4     Knowledge of radiation exposure limits under normal or emergency                 3.2      1 Radiation                  conditions. (CFR: 41.12 / 43.4 / 45.10)
Question 67 4.3 1
Control Question 71 2.3.5     Ability to use radiation monitoring systems, such as fixed radiation             2.9      1 monitors and alarms, portable survey instruments, personnel monitoring equipment, etc. (CFR: 41.11 / 41.12 / 43.4 / 45.9)
Subtotal 2
Question 72 2.3.13   Knowledge of radiological safety procedures pertaining to licensed               3.4 operator duties, such as response to radiation monitor alarms, containment entry requirements, fuel handling responsibilities, access to locked high-radiation areas, aligning filters, etc. (CFR: 41.12 / 43.4 / 45.9
: 2.
                            / 45.10)
Equipment Control 2.2.36 Ability to analyze the effect of maintenance activities, such as degraded power sources, on the status of limiting conditions for operations. (CFR:
Question 73 Subtotal   2
41.10 / 43.2 / 45.13)
: 4.               2.4.31   Knowledge of annunciator alarms, indications, or response procedures.             4.2      1 Emergency                  (CFR: 41.10 / 45.3)
Question 68 3.1 1
Procedures/
2.2.7 Knowledge of the process for conducting special or infrequent tests.
Question 74 Plan 2.4.35   Knowledge of local auxiliary operator tasks during an emergency and the           3.8      1 resultant operational effects. (CFR: 41.10 / 43.5 / 45.13)
(CFR: 41.10 / 43.3 / 45.13)
Question 75 Subtotal   3 Tier 3 Point Total   10 NUREG-1021, Revision 9 Supplement 1                      RO Page 9 of 9                                        FENOC Facsimile Rev. 1
Question 69 2.9 1
2.2.35 Ability to determine Technical Specification Mode of Operation. (CFR:
41.7 / 41.10 / 43.2 / 45.13)
Question 70 3.6 1
Subtotal 3
: 3.
Radiation Control 2.3.4 Knowledge of radiation exposure limits under normal or emergency conditions. (CFR: 41.12 / 43.4 / 45.10)
Question 71 3.2 1
2.3.5 Ability to use radiation monitoring systems, such as fixed radiation monitors and alarms, portable survey instruments, personnel monitoring equipment, etc. (CFR: 41.11 / 41.12 / 43.4 / 45.9)
Question 72 2.9 1
2.3.13 Knowledge of radiological safety procedures pertaining to licensed operator duties, such as response to radiation monitor alarms, containment entry requirements, fuel handling responsibilities, access to locked high-radiation areas, aligning filters, etc. (CFR: 41.12 / 43.4 / 45.9  
/ 45.10)
Question 73 3.4 Subtotal 2
: 4.
Emergency Procedures/
Plan 2.4.31 Knowledge of annunciator alarms, indications, or response procedures.
(CFR: 41.10 / 45.3)
Question 74 4.2 1
2.4.35 Knowledge of local auxiliary operator tasks during an emergency and the resultant operational effects. (CFR: 41.10 / 43.5 / 45.13)
Question 75 3.8 1
Subtotal 3
Tier 3 Point Total 10  


ES-401                                                 PWR Examination Outline                                 Form ES-401-2 Facility: Davis-Besse SRO                                           Date of Exam 6/3 thru 6/14 2013 RO K/A Category Points                                           SRO ONLY Points Tier          Group K     K   K     K     K     K     A   A   A     A   G     TOTAL     A2       G*     TOTAL 1     2    3    4    5    6      1   2    3      4
NUREG-1021, Revision 9 Supplement 1 SRO Page 1 of 6 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Facility: Davis-Besse SRO Date of Exam 6/3 thru 6/14 2013 Tier Group RO K/A Category Points SRO ONLY Points K
* 1 18       3       3         6 1.
1 K
Emergency              2
2 K
            &                                                                                            9        2       2         4 Abnormal Plant              Tier Totals 27       5       5         10 Evolutions 1
3 K
2.
4 K
28       3       2         5 Plant Systems              2 10     0 2       1         3 Tier Totals 38       5       3         8 1           2         3           4                 1 2 3 4
5 K
: 3. Generic Knowledge and                                                                  10                            7 Abilities Category 1 2 2 2 Note:
6 A
: 1.       Ensure that at least two topics from every applicable K/A category are sampled within each tier of the RO and SRO-only outlines (i.e., except for one category in Tier 3 of the SRO-only outline, the Tier Totals in each K/A category shall not be less than two).
1 A
: 2.       The point total for each group and tier in the proposed outline must match that specified in the table. The final point total for each group and tier may deviate by +/-1 from that specified in the table based on NRC revisions. The final RO exam must total 75 points and the SRO-only exam must total 25 points.
2 A
: 3.       Systems/evolutions within each group are identified on the associated outline; systems or evolutions that do not apply at the facility should be deleted and justified; operationally important, site-specific systems/evolutions that are not included on the outline should be added. Refer to Section D.1.b of ES-401 for guidance regarding the elimination of inappropriate K/A statements.
3 A
: 4.       Select topics from as many systems and evolutions as possible; sample every system or evolution in the group before selecting a second topic for any system or evolution.
4 G
: 5.       Absent a plant-specific priority, only those K/As having an importance rating (IR) of 2.5 or higher shall be selected.
TOTAL A2 G*
TOTAL
: 1.
Emergency Abnormal Plant Evolutions 1
18 3
3 6
2 9
2 2
4 Tier Totals 27 5
5 10
: 2.
Plant Systems 1
28 3
2 5
2 10 0 2 1
3 Tier Totals 38 5
3 8
: 3. Generic Knowledge and Abilities Category 1
2 3
4 10 1 2 3 4 7
1 2 2 2 Note:
: 1.
Ensure that at least two topics from every applicable K/A category are sampled within each tier of the RO and SRO-only outlines (i.e., except for one category in Tier 3 of the SRO-only outline, the Tier Totals in each K/A category shall not be less than two).
: 2.
The point total for each group and tier in the proposed outline must match that specified in the table. The final point total for each group and tier may deviate by +/-1 from that specified in the table based on NRC revisions. The final RO exam must total 75 points and the SRO-only exam must total 25 points.
: 3.
Systems/evolutions within each group are identified on the associated outline; systems or evolutions that do not apply at the facility should be deleted and justified; operationally important, site-specific systems/evolutions that are not included on the outline should be added. Refer to Section D.1.b of ES-401 for guidance regarding the elimination of inappropriate K/A statements.
: 4.
Select topics from as many systems and evolutions as possible; sample every system or evolution in the group before selecting a second topic for any system or evolution.
: 5.
Absent a plant-specific priority, only those K/As having an importance rating (IR) of 2.5 or higher shall be selected.
Use the RO and SRO ratings for the RO and SRO-only portions, respectively.
Use the RO and SRO ratings for the RO and SRO-only portions, respectively.
: 6.       Select SRO topics for Tiers 1 and 2 from the shaded systems and K/A categories.
: 6.
7.*     The generic (G) K/As in Tiers 1 and 2 shall be selected from Section 2 of the K/A Catalog, but the topics must be relevant to the applicable evolution or system. Refer to Section D.1.b of ES-401 for the applicable K/As.
Select SRO topics for Tiers 1 and 2 from the shaded systems and K/A categories.
: 8.       On the following pages, enter the K/A numbers, a brief description of each topic, the topics importance ratings (IRs) for the applicable license level, and the point totals (#) for each system and category. Enter the group and tier totals for each category in the table above; if fuel handling equipment is sampled in other than Category A2 or G* on the SRO-only exam, enter it on the left side of Column A2 for Tier 2, Group 2 (Note #1 does not apply). Use duplicate pages for RO and SRO-only exams.
7.*
: 9.       For Tier 3, select topics from Section 2 of the K/A catalog, and enter the K/A numbers, descriptions, IRs, and point totals (#) on Form ES-401-3. Limit SRO selections to K/As that are linked to 10 CFR 55.43.
The generic (G) K/As in Tiers 1 and 2 shall be selected from Section 2 of the K/A Catalog, but the topics must be relevant to the applicable evolution or system. Refer to Section D.1.b of ES-401 for the applicable K/As.
NUREG-1021, Revision 9 Supplement 1                              SRO Page 1 of 6                                FENOC Facsimile Rev. 1
: 8.
On the following pages, enter the K/A numbers, a brief description of each topic, the topics importance ratings (IRs) for the applicable license level, and the point totals (#) for each system and category. Enter the group and tier totals for each category in the table above; if fuel handling equipment is sampled in other than Category A2 or G* on the SRO-only exam, enter it on the left side of Column A2 for Tier 2, Group 2 (Note #1 does not apply). Use duplicate pages for RO and SRO-only exams.
: 9.
For Tier 3, select topics from Section 2 of the K/A catalog, and enter the K/A numbers, descriptions, IRs, and point totals (#) on Form ES-401-3. Limit SRO selections to K/As that are linked to 10 CFR 55.43.  


ES-401                                             PWR Examination Outline                               Form ES-401-2 Davis-Besse 6/2013                         Emergency and Abnormal Plant Evolutions - Tier 1/Group 1(SRO)
NUREG-1021, Revision 9 Supplement 1 SRO Page 2 of 6 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Davis-Besse 6/2013 Emergency and Abnormal Plant Evolutions - Tier 1/Group 1(SRO)
E/APE # / Name / Safety Function         K K   K A A G                         K/A Topic(s)                         IR Points 1  2  3  1 2 000056 Loss of Offsite Power                                 X 2.1.20 Ability to interpret and execute procedure         4.6  1 steps.
E/APE # / Name / Safety Function K
Question 76 (CFR: 41.10 / 43.5 / 45.12) 000038 Steam Generator Tube Rupture                       X     EA2.01 Ability to determine and interpret the             4.7  1 (SGTR)                                                          following as they apply to SGTR: When to isolate one or more S/Gs Question 77 (CFR: 43.5 / 45.13) 000058 Loss of DC Power                                   X     AA2.03 Ability to determine and interpret the             3.9  1 Question 78                                                    following as they apply to the Loss of DC Power:
1 K
DC loads lost; impact on ability to operate and monitor plant systems (CFR: 43.5 / 45.13) 000065 Loss of Instrument Air                               X 2.4.9 Knowledge of low power/shutdown                     4.2  1 implications in accident (e.g., loss of coolant Question 79 accident or loss of residual heat removal) mitigation strategies.
2 K
(CFR: 41.10 / 43.5 / 45.13)
3 A
BW/E10 Post-Trip Stabilization                           X     EA2.1 Ability to determine and interpret the               4.0  1 following as they apply to the (Post-Trip Question 80 Stabilization) Facility conditions and selection of appropriate procedures during abnormal and emergency operations.
1 A
(CFR: 43.5, 45.13)
2 G
BW/E05 Steam Line Rupture - Excessive                       X 2.4.20 Knowledge of the operational implications of       4.3  1 Heat Transfer                                                  EOP warnings, cautions, and notes.
K/A Topic(s)
Question 81                                                    (CFR: 41.10 / 43.5 / 45.13)
IR Points 000056 Loss of Offsite Power Question 76 X 2.1.20 Ability to interpret and execute procedure steps.
K/A Category Point Totals: 0 0   0 0 3 3                                             Group Point Total:   6 NUREG-1021, Revision 9 Supplement 1                      SRO Page 2 of 6                               FENOC Facsimile Rev. 1
(CFR: 41.10 / 43.5 / 45.12) 4.6 1
000038 Steam Generator Tube Rupture (SGTR)
Question 77 X
EA2.01 Ability to determine and interpret the following as they apply to SGTR: When to isolate one or more S/Gs (CFR: 43.5 / 45.13) 4.7 1
000058 Loss of DC Power Question 78 X
AA2.03 Ability to determine and interpret the following as they apply to the Loss of DC Power:
DC loads lost; impact on ability to operate and monitor plant systems (CFR: 43.5 / 45.13) 3.9 1
000065 Loss of Instrument Air Question 79 X 2.4.9 Knowledge of low power/shutdown implications in accident (e.g., loss of coolant accident or loss of residual heat removal) mitigation strategies.
(CFR: 41.10 / 43.5 / 45.13) 4.2 1
BW/E10 Post-Trip Stabilization Question 80 X
EA2.1 Ability to determine and interpret the following as they apply to the (Post-Trip Stabilization) Facility conditions and selection of appropriate procedures during abnormal and emergency operations.
(CFR: 43.5, 45.13) 4.0 1
BW/E05 Steam Line Rupture - Excessive Heat Transfer Question 81 X 2.4.20 Knowledge of the operational implications of EOP warnings, cautions, and notes.
(CFR: 41.10 / 43.5 / 45.13) 4.3 1
K/A Category Point Totals:
0 0
0 0
3 3
Group Point Total:
6  


ES-401                                             PWR Examination Outline                             Form ES-401-2 Davis-Besse 6/2013                         Emergency and Abnormal Plant Evolutions - Tier 1/Group 2(SRO)
NUREG-1021, Revision 9 Supplement 1 SRO Page 3 of 6 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Davis-Besse 6/2013 Emergency and Abnormal Plant Evolutions - Tier 1/Group 2(SRO)
E/APE # / Name / Safety Function         K K K A A G                             K/A Topic(s)                         IR Points 1 2 3 1 2 000001 Continuous Rod Withdrawal                         X     AA2.03 Ability to determine and interpret the           4.8    1 Question 82                                                    following as they apply to the Continuous Rod Withdrawal : Proper actions to be taken if automatic safety functions have not taken place (CFR: 43.5 / 45.13) 000024 Emergency Boration                                   X 2.2.42 Ability to recognize system parameters that       4.6    1 are entry-level conditions for Technical Question 83                                                    Specifications. (CFR: 41.7 / 41.10 / 43.2 / 43.3 /
E/APE # / Name / Safety Function K
45.3) 000033 Loss of Intermediate Range                         X     AA2.03 Ability to determine and interpret the           3.1    1 Nuclear Instrumentation                                        following as they apply to the Loss of Intermediate Range Nuclear Instrumentation: Indication of blown Question 84 fuse (CFR: 43.5 / 45.13)
1 K
BW/A06 Shutdown Outside Control Room                         X 2.1.32 Ability to explain and apply system limits and   4.0    1 precautions.
2 K
Question 85 (CFR: 41.10 / 43.2 / 45.12)
3 A
K/A Category Point Totals: 0 0   0 0 2 2                                             Group Point Total:   4 NUREG-1021, Revision 9 Supplement 1                      SRO Page 3 of 6                              FENOC Facsimile Rev. 1
1 A
2 G
K/A Topic(s)
IR Points 000001 Continuous Rod Withdrawal Question 82 X
AA2.03 Ability to determine and interpret the following as they apply to the Continuous Rod Withdrawal : Proper actions to be taken if automatic safety functions have not taken place (CFR: 43.5 / 45.13) 4.8 1
000024 Emergency Boration Question 83 X 2.2.42 Ability to recognize system parameters that are entry-level conditions for Technical Specifications. (CFR: 41.7 / 41.10 / 43.2 / 43.3 /
45.3) 4.6 1
000033 Loss of Intermediate Range Nuclear Instrumentation Question 84 X
AA2.03 Ability to determine and interpret the following as they apply to the Loss of Intermediate Range Nuclear Instrumentation: Indication of blown fuse (CFR: 43.5 / 45.13) 3.1 1
BW/A06 Shutdown Outside Control Room Question 85 X 2.1.32 Ability to explain and apply system limits and precautions.
(CFR: 41.10 / 43.2 / 45.12) 4.0 1
K/A Category Point Totals:
0 0
0 0
2 2
Group Point Total:
4  


ES-401                                       PWR Examination Outline                                 Form ES-401-2 Davis-Besse 6/2013                           Plant Systems - Tier 2/Group 1(SRO)
NUREG-1021, Revision 9 Supplement 1 SRO Page 4 of 6 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Davis-Besse 6/2013 Plant Systems - Tier 2/Group 1(SRO)
System # / Name           K K K K K K A A A       A G                       K/A Topic(s)                     IR Points 1 2 3 4 5 6 1 2 3      4 006 Emergency Core Cooling                           X             A2.03 Ability to (a) predict the impacts of the   3.7  1 System (ECCS)                                                      following malfunctions or operations on the ECCS; and (b) based on those predictions, Question 86 use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: System leakage (CFR: 41.5 / 45.5) 013 Engineered Safety Features                                 X   2.4.21 Knowledge of the parameters and             4.6  1 Actuation System (ESFAS)                                            logic used to assess the status of safety Question 87                                                        functions, such as reactivity control, core cooling and heat removal, reactor coolant system integrity, containment conditions, radioactivity release control, etc.
System # / Name K
(CFR: 41.7 / 43.5 / 45.12) 026 Containment Spray System                         X             A2.07 Ability to (a) predict the impacts of the   3.9  1 (CSS)                                                              following malfunctions or operations on the CSS; and (b) based on those predictions, Question 88                                                        use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Loss of containment spray pump suction when in recirculation mode, possibly caused by clogged sump screen, pump inlet high temperature exceeded cavitation, voiding),
1 K
or sump level below cutoff (interlock) limit (CFR: 41.5 / 43.5 / 45.3 / 45.13) 039 Main and Reheat Steam                           X             A2.05 Ability to (a) predict the impacts of the   3.6  1 System (MRSS)                                                      following malfunctions or operations on the Question 89                                                        MRSS; and (b) based on predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Increasing steam demand, its relationship to increases in reactor power (CFR: 41.5 / 43.5 / 45.3 / 45.13) 061 Auxiliary/Emergency                                       X   2.4.6 Knowledge of EOP mitigation                 4.7  1 Feedwater (AFW) System                                              strategies.
2 K
Question 90                                                        (CFR: 41.10 / 43.5 / 45.13)
3 K
K/A Category Point Totals:   0 0 0 0 0 0   0   3 0 0   2                                       Group Point Total:   5 NUREG-1021, Revision 9 Supplement 1                  SRO Page 4 of 6                                FENOC Facsimile Rev. 1
4 K
5 K
6 A
1 A
2 A
3 A
4 G
K/A Topic(s)
IR Points 006 Emergency Core Cooling System (ECCS)
Question 86 X
A2.03 Ability to (a) predict the impacts of the following malfunctions or operations on the ECCS; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: System leakage (CFR: 41.5 / 45.5) 3.7 1
013 Engineered Safety Features Actuation System (ESFAS)
Question 87 X 2.4.21 Knowledge of the parameters and logic used to assess the status of safety functions, such as reactivity control, core cooling and heat removal, reactor coolant system integrity, containment conditions, radioactivity release control, etc.
(CFR: 41.7 / 43.5 / 45.12) 4.6 1
026 Containment Spray System (CSS)
Question 88 X
A2.07 Ability to (a) predict the impacts of the following malfunctions or operations on the CSS; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Loss of containment spray pump suction when in recirculation mode, possibly caused by clogged sump screen, pump inlet high temperature exceeded cavitation, voiding),
or sump level below cutoff (interlock) limit (CFR: 41.5 / 43.5 / 45.3 / 45.13) 3.9 1
039 Main and Reheat Steam System (MRSS)
Question 89 X
A2.05 Ability to (a) predict the impacts of the following malfunctions or operations on the MRSS; and (b) based on predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Increasing steam demand, its relationship to increases in reactor power (CFR: 41.5 / 43.5 / 45.3 / 45.13) 3.6 1
061 Auxiliary/Emergency Feedwater (AFW) System Question 90 X 2.4.6 Knowledge of EOP mitigation strategies.
(CFR: 41.10 / 43.5 / 45.13) 4.7 1
K/A Category Point Totals:
0 0
0 0
0 0
0 3
0 0
2 Group Point Total:
5  


ES-401                                       PWR Examination Outline                                 Form ES-401-2 Davis-Besse 6/2013                           Plant Systems - Tier 2/Group 2(SRO)
NUREG-1021, Revision 9 Supplement 1 SRO Page 5 of 6 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Davis-Besse 6/2013 Plant Systems - Tier 2/Group 2(SRO)
System # / Name             K K K K K K A A A       A G                       K/A Topic(s) 1 2 3 4 5 6 1 2 3      4                                                            IR Points 011 Pressurizer Level Control                       X             A2.07 Ability to (a) predict the impacts of the   3.3  1 System (PZR LCS)                                                    following malfunctions or operations on the Question 91                                                        PZR LCS; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Isolation of letdown (CFR: 41.5 / 43.5 / 45.3 / 45.13) 015 Nuclear Instrumentation                         X             A2.01 Ability to (a) predict the impacts of the   3.9  1 System                                                              following malfunctions or operations on the NIS; and (b based on those predictions, use Question 92 procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Power supply loss or erratic operation (CFR: 41.5 / 43.5 / 45.3 / 45.5) 033 Spent Fuel Pool Cooling                                   X   2.1.20 Ability to interpret and execute           4.6  1 System (SFPCS)                                                      procedure steps.
System # / Name K
Question 93                                                        (CFR: 41.10 / 43.5 / 45.12)
1 K
K/A Category Point Totals:   0 0 0 0 0 0   0   2 0 0   1                                       Group Point Total:   3 NUREG-1021, Revision 9 Supplement 1                  SRO Page 5 of 6                                FENOC Facsimile Rev. 1
2 K
3 K
4 K
5 K
6 A
1 A
2 A
3 A
4 G
K/A Topic(s)
IR Points 011 Pressurizer Level Control System (PZR LCS)
Question 91 X
A2.07 Ability to (a) predict the impacts of the following malfunctions or operations on the PZR LCS; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Isolation of letdown (CFR: 41.5 / 43.5 / 45.3 / 45.13) 3.3 1
015 Nuclear Instrumentation System Question 92 X
A2.01 Ability to (a) predict the impacts of the following malfunctions or operations on the NIS; and (b based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Power supply loss or erratic operation (CFR: 41.5 / 43.5 / 45.3 / 45.5) 3.9 1
033 Spent Fuel Pool Cooling System (SFPCS)
Question 93 X 2.1.20 Ability to interpret and execute procedure steps.
(CFR: 41.10 / 43.5 / 45.12) 4.6 1
K/A Category Point Totals:
0 0
0 0
0 0
0 2
0 0
1 Group Point Total:
3  


ES 401                     Generic Knowledge and Abilities Outline (Tier 3)                             Form ES-401-3 Facility: Davis-Besse SRO                                                   Date of Exam 6/3 thru 6/14 2013 RO            SRO Only Category       K/A#                                         Topic IR       #      IR     #
NUREG-1021, Revision 9 Supplement 1 SRO Page 6 of 6 FENOC Facsimile Rev. 1 ES 401 Generic Knowledge and Abilities Outline (Tier 3)
: 1.               2.1.42   Knowledge of new and spent fuel movement procedures. (CFR: 41.10 /
Form ES-401-3 Facility: Davis-Besse SRO Date of Exam 6/3 thru 6/14 2013 Category K/A#
Conduct                    43.7 / 45.13)                                                                             3.4     1 of Operations Question 94 Subtotal     1
Topic RO SRO Only IR IR
: 2.               2.2.1     Ability to perform pre-startup procedures for the facility, including Equipment                  operating those controls associated with plant equipment that could                       4.4    1 Control                    affect reactivity. (CFR: 41.5 / 41.10 / 43.5 / 43.6 / 45.1)
: 1.
Question 95 2.2.18   Knowledge of the process for managing maintenance activities during shutdown operations, such as risk assessments, work prioritization,                       3.9    1 etc.(CFR: 41.10 / 43.5 / 45.13)
Conduct of Operations 2.1.42 Knowledge of new and spent fuel movement procedures. (CFR: 41.10 /
Question 96 Subtotal     2
43.7 / 45.13)
: 3.               2.3.6     Ability to approve release permits. (CFR: 41.13 / 43.4 / 45.10)
Question 94 3.4 1
Radiation                  Question 97                                                                               3.8     1 Control 2.3.15   Knowledge of radiation monitoring systems, such as fixed radiation monitors and alarms, portable survey instruments, personnel monitoring                   3.1    1 equipment, etc. (CFR: 41.12 / 43.4 / 45.9)
Subtotal 1
Question 98 Subtotal     2
: 2.
: 4.               2.4.27   Knowledge of fire in the plant procedures. (CFR: 41.10 / 43.5 / 45.13)
Equipment Control 2.2.1 Ability to perform pre-startup procedures for the facility, including operating those controls associated with plant equipment that could affect reactivity. (CFR: 41.5 / 41.10 / 43.5 / 43.6 / 45.1)
Emergency                  Question 99                                                                               3.9     1 Procedures/
Question 95 4.4 1
Plan              2.4.44   Knowledge of emergency plan protective action recommendations.
2.2.18 Knowledge of the process for managing maintenance activities during shutdown operations, such as risk assessments, work prioritization, etc.(CFR: 41.10 / 43.5 / 45.13)
(CFR: 41.10 / 41.12 / 43.5 / 45.11)                                                       4.4     1 Question 100 Subtotal     2 Tier 3 Point Total     7 NUREG-1021, Revision 9 Supplement 1                              SRO Page 6 of 6                        FENOC Facsimile Rev. 1}}
Question 96 3.9 1
Subtotal 2
: 3.
Radiation Control 2.3.6 Ability to approve release permits. (CFR: 41.13 / 43.4 / 45.10)
Question 97 3.8 1
2.3.15 Knowledge of radiation monitoring systems, such as fixed radiation monitors and alarms, portable survey instruments, personnel monitoring equipment, etc. (CFR: 41.12 / 43.4 / 45.9)
Question 98 3.1 1
Subtotal 2
: 4.
Emergency Procedures/
Plan 2.4.27 Knowledge of fire in the plant procedures. (CFR: 41.10 / 43.5 / 45.13)
Question 99 3.9 1
2.4.44 Knowledge of emergency plan protective action recommendations.
(CFR: 41.10 / 41.12 / 43.5 / 45.11)
Question 100 4.4 1
Subtotal 2
Tier 3 Point Total 7}}

Latest revision as of 05:27, 11 January 2025

2013 Davis-Besse Initial License Examination Proposed Es 301-6 and Revised Outline Documents
ML13263A079
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 04/12/2013
From:
NRC/RGN-III
To:
Michael Bielby
Shared Package
ML11354A431 List:
References
Download: ML13263A079 (28)


Text

NUREG-1021, Revision 9 Supplement 1 FENOC Facsimile Rev.1 ES-301 Competencies Checklist Form ES-301-6 Facility Davis Besse Date of Exam 6/3 thru 6/14 2013 Operating Test No.: ___________

APPLICANTS RO SRO-I SRO-U Competencies SCENARIO SCENARIO SCENARIO 1

2 3

4 1

2 3

4 1

2 3

4 Interpret/Diagnosis Events and Conditions 1,3,4 5,6,7 8,9 10 1,3,4 5,6,7 8

1,3,4 5,6,7 1,3,4 5,6,7 8

1,2,3 4,5,6 7,8,9 10 1,3,4 5,6,7 8

1,3,4 5,6,7 1,3,4 5,6,7 8

1,2,3 4,5,6 7,8,9 10 1,3,4 5,6,7 8

1,3,4 5,6,7 1,3,4 5,6,7 8

Comply With and Use Procedures (1) 1,3,4 5,6,7 8,9 10 1,3,4 5,6,7 8

1,3,4 5,6,7 1,3,4 5,6,7 8

1,2,3 4,5,6 7,8,9 10 1,3,4 5,6,7 8

1,3,4 5,6,7 1,3,4 5,6,7 8

1,2,3 4,5,6 7,8,9 10 1,3,4 5,6,7 8

1,3,4 5,6,7 1,3,4 5,6,7 8

Operate Control Boards (2) 1,3,4 6,7,8 9,10 1,3,4 5,6,7 8

1,3,4 5,6,7 1,4,5 6,7,8 3,6,7 8,9 2,4,6 1,2,5 6,7 5,6,7 8

Communicate and Interact 1,3,4 5,6,7 8,9 10 1,3,4 5,6,7 8

1,3,4 5,6,7 1,3,4 5,6,7 8

1,2,3 4,5,6 7,8,9 10 1,3,4 5,6,7 8

1,3,4 5,6,7 1,3,4 5,6,7 8

1,2,3 4,5,6 7,8,9 10 1,3,4 5,6,7 8

1,3,4 5,6,7 1,3,4 5,6,7 8

Demonstrate Supervisory Ability (3) 1,2,3 4,5,6 7,8,9 10 1,3,4 5,6,7 8

1,3,4 5,6,7 1,3,4 5,6,7 8

1,2,3 4,5,6 7,8,9 10 1,3,4 5,6,7 8

1,3,4 5,6,7 1,3,4 5,6,7 8

Comply With and Use Tech. Specs. (3) 2,5 1,5 2,4 3,4 2,5 1,5 2,4 3,4 Notes:

(1) Includes Technical Specification compliance for an RO.

(2) Optional for an SRO-U.

(3) Only applicable to SROs.

Instructions:

Check the applicant's license type and enter one or more event numbers that will allow the examiners to evaluate every applicable competency for every applicant.

ES-301 Administrative Topics Outline Form ES-301-1 NUREG-1021, Revision 9 Supplement 1 FENOC Facsimile Rev. 1 Facility: Davis Besse Date of Examination:_ 6/3 thru 6/14 2013 Examination Level RO Operating Test Number _

Administrative Topic (See Note)

Type Code*

Describe activity to be performed Conduct of Operations (RO A1.1)

D, R 2.1.43 (4.1)

Ability to use procedures to determine the effects on reactivity of plant changes, such as reactor coolant system temperature, secondary plant, fuel depletion, etc.

JPM 58 Calculate SDM with Tave > 500°F Conduct of Operations (RO A1.2)

N, R 2.1.7 (4.4)

Ability to evaluate plant performance and make operational judgments based on operating characteristics, reactor behavior, and instrument interpretation.

JPM New Plot and evaluate 1/M data Equipment Control (RO A2)

D, R 2.2.12 (3.7)

Knowledge of surveillance procedures.

JPM 227 Calculate RCS flow with F744 inoperable Radiation Control (RO A3)

D, S 2.3.5 (2.9)

Ability to use radiation monitoring systems, such as fixed radiation monitors and alarms, portable survey instruments, personnel monitoring equipment, etc.

JPM 260 Perform radiation element administrative checks for a radioactive liquid release Emergency Procedures/Plan NOT EVALUATED NOTE: All items (5 total) are required for SROs. RO applicants require only 4 items unless they are retaking only the administrative topics, when all 5 are required.

  • Type Codes & Criteria (C)ontrol Room, (S)imulator, or Class(R)oom (D)irect from bank (< 3 for ROs; < 4 for SROs & RO retakes)

(N)ew or (M)odified from bank (> 1)

(P)revious 2 exams (< 1; randomly selected)

ES-301 Administrative Topics Outline Form ES-301-1 NUREG-1021, Revision 9 Supplement 1 FENOC Facsimile Rev. 1 Facility: Davis Besse Date of Examination:_ 6/3 thru 6/14 2013 Examination Level SRO Operating Test Number ________

Administrative Topic (See Note)

Type Code*

Describe activity to be performed Conduct of Operations (SRO A1.1)

N, R 2.1.43 (4.3)

Ability to use procedures to determine the effects on reactivity of plant changes, such as reactor coolant system temperature, secondary plant, fuel depletion, etc.

JPM New Shift Manager Review of SDM calculation with Tave > 500 °F Conduct of Operations (SRO A1.2)

N, R 2.1.5 (3.9)

Ability to use procedures related to shift staffing, such as minimum crew complement, overtime limitations, etc.

JPM New Determine Availability For Call-In.

Equipment Control (SRO A2)

N, R 2.2.18 (3.9)

Knowledge of the process for managing maintenance activities during shutdown operations, such as risk assessments, work prioritization, etc.

JPM New Shutdown Defense In Depth Assessment Radiation Control (SRO A3)

N, R 2.3.6 (3.8)

Ability to approve release permits.

JPM New Perform Administrative Checks For Radioactive Liquid Batch Release Emergency Procedures/Plan (SRO A4)

D, S 2.4.44 (4.4)

Knowledge of emergency plan protective action recommendations.

JPM 150 Make Protective Action Recommendations NOTE: All items (5 total) are required for SROs. RO applicants require only 4 items unless they are retaking only the administrative topics, when all 5 are required.

  • Type Codes & Criteria (C)ontrol Room, (S)imulator, or Class(R)oom (D)irect from bank (< 3 for ROs; < 4 for SROs & RO retakes)

(N)ew or (M)odified from bank (> 1)

(P)revious 2 exams (< 1; randomly selected)

ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 NUREG-1021, Revision 9 Supplement 1 FENOC Facsimile Rev. 1 Facility: Davis Besse Date of Examination: 6/3 thru 6/14 2013 Exam Level: RO SRO(I) SRO(U)

Operating Test No.: _ ___

Control Room Systems@ (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)

System / JPM Title Type Code*

Safety Function S1 Initiate Deboration Using Deborating Demineralizers (JPM New) 004 A4.07 3.9/3.7 N, A, S 1

S2 De-energize SFAS CH 4 RCS Pressure Transmitter (JPM New) 013 K2.01 3.6/3.8 N, S, EN 2

S3 Perform HPI Flow Balance (JPM New) 006 A4.02 4.0/3.8 N, A, S, L, EN 3

S4 Rapid Cooldown of the RCS (JPM New) 041 A3.01 3.2/3.2 N, A, S, L 4S S5 Shift CTMT Air Cooler From Slow to Fast Speed (JPM 151 022 A4.01 3.6/3.8 D, S, L 5

S6 13.8 KV Bus Transfer to Aux 11 Transformer (JPM New) 062 A4.01 3.3/3.1 N, A, S 6

S7 Bypass SFRCS Logic Channel Trips (JPM 108) 012 A4.03 3.6/3.6 D, S 7

S8 CCW Essential Header Leak Isolation (JPM 125) 008 A2.02 3.2/3.5 D, A, S 8

In-Plant Systems@ (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)

P1 Actions outside the control room of the primary side reactor operator for a serious control room fire (JPM 003) 068 AA1.21 3.9/4.1 D, E, R 8

P2 Emergency Idle Start EDG 1 (JPM 242) 064 A3.06 3.3/3.4 D, A, E 6

P3 Service Water Primary Header Pressure Control (JPM New) 076 K1.01 3.4/3.3 N

4S All RO and SRO control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.

  • Type Codes Criteria for RO / SRO-I / SRO-U (A)lternate Path (C)ontrol room (D)irect from bank (E)mergency or abnormal in-plant (EN)gineered safety feature (L)ow-power / Shutdown (N)ew or (M)odified from bank including 1(A)

(P)revious 2 exams (R)CA (S)imulator 4-6 /4-6 /2-3 9 / 8 / 4 1 / 1 / 1

- / - / > 1 (Control room system) 1 / 1 / 1 2 / 2 / 1 3/ 3 / 2 (randomly selected) 1 / 1 / 1

ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 NUREG-1021, Revision 9 Supplement 1 FENOC Facsimile Rev. 1 Facility: Davis Besse Date of Examination: 6/3 thru 6/14 2013 Exam Level: RO SRO(I) SRO(U)

Operating Test No.: _ ___

Control Room Systems@ (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)

System / JPM Title Type Code*

Safety Function S1 Initiate Deboration Using Deborating Demineralizers (JPM New) 004 A4.07 3.9/3.7 N, A, S 1

S2 De-energize SFAS CH 4 RCS Pressure Transmitter (JPM New) 013 K2.01 3.6/3.8 N, S, EN 2

S3 Perform HPI Flow Balance (JPM New) 006 A4.02 4.0/3.8 N, A, S, L, EN 3

S4 Rapid Cooldown of the RCS (JPM New) 041 A3.01 3.2/3.2 N, A, S, L 4S S6 13.8 KV Bus Transfer to Aux 11 Transformer (JPM New) 062 A4.01 3.3/3.1 N, A, S 6

S7 Bypass SFRCS Logic Channel Trips (JPM 108) 012 A4.03 3.6/3.6 D, S 7

S8 CCW Essential Header Leak Isolation (JPM 125) 008 A2.02 3.2/3.5 D, A, S 8

In-Plant Systems@ (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)

P1 Actions outside the control room of the primary side reactor operator for a serious control room fire (JPM 003) 068 AA1.21 3.9/4.1 D, E, R 8

P2 Emergency Idle Start EDG 1 (JPM 242) 064 A3.06 3.3/3.4 D, A, E 6

P3 Service Water Primary Header Pressure Control (JPM New) 076 K1.01 3.4/3.3 N

4S All RO and SRO control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.

  • Type Codes Criteria for RO / SRO-I / SRO-U (A)lternate Path (C)ontrol room (D)irect from bank (E)mergency or abnormal in-plant (EN)gineered safety feature (L)ow-power / Shutdown (N)ew or (M)odified from bank including 1(A)

(P)revious 2 exams (R)CA (S)imulator 4-6 /4-6 /2-3 9 / 8 / 4 1 / 1 / 1

- / - / > 1 (Control room system) 1 / 1 / 1 2 / 2 / 1 3/ 3 / 2 (randomly selected) 1 / 1 / 1

ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 NUREG-1021, Revision 9 Supplement 1 FENOC Facsimile Rev. 1 Facility: Davis Besse Date of Examination: 6/3 thru 6/14 2013 Exam Level: RO SRO(I) SRO(U)

Operating Test No.: _ ___

Control Room Systems@ (8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)

System / JPM Title Type Code*

Safety Function S3 Perform HPI Flow Balance (JPM New) 006 A4.02 4.0/3.8 N, A, S, L, EN 3

S4 Rapid Cooldown of the RCS (JPM New) 041 A3.01 3.2/3.2 N, A, S, L 4S S7 Bypass SFRCS Logic Channel Trips (JPM 108) 012 A4.03 3.6/3.6 D, S 7

In-Plant Systems@ (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)

P1 Actions outside the control room of the primary side reactor operator for a serious control room fire (JPM 003) 068 AA1.21 3.9/4.1 D, E, R 8

P2 Emergency Idle Start EDG 1 (JPM 242) 064 A3.06 3.3/3.4 D, A, E 6

All RO and SRO control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.

  • Type Codes Criteria for RO / SRO-I / SRO-U (A)lternate Path (C)ontrol room (D)irect from bank (E)mergency or abnormal in-plant (EN)gineered safety feature (L)ow-power / Shutdown (N)ew or (M)odified from bank including 1(A)

(P)revious 2 exams (R)CA (S)imulator 4-6 /4-6 /2-3 9 / 8 / 4 1 / 1 / 1

- / - / > 1 (Control room system) 1 / 1 / 1 2 / 2 / 1 3/ 3 / 2 (randomly selected) 1 / 1 / 1

NUREG-1021, Revision 9 Supplement 1 FENOC Facsimile Rev.1 ES-301 Operating Test Quality Checklist Form ES-301-3 Facility: Davis Besse Date of Exam 6/3 thru 6/14 2013 Operating Test No.: _________

1. GENERAL CRITERIA Initials a

b*

c#

a.

The operating test conforms with the previously approved outline; changes are consistent with sampling requirements (e.g., 10 CFR 55.45, operational importance, safety function distribution).

b.

There is no day-to-day repetition between this and other operating tests to be administered during this examination.

c.

The operating test shall not duplicate items from the applicants audit test(s) (see Section D.1.a).

d.

Overlap with the written examination and between different parts of the operating test is within acceptable limits.

e.

It appears that the operating test will differentiate between competent and less-than-competent applicants at the designated license level.

2. WALK-THROUGH CRITERIA
a.

Each JPM includes the following, as applicable:

  • initial conditions
  • initiating cues
  • references and tools, including associated procedures
  • reasonable and validated time limits (average time allowed for completion) and specific designation if deemed to be time critical by the facility licensee
  • specific performance criteria that include:

- detailed expected actions with exact criteria and nomenclature

- system response and other examiner cues

- statements describing important observations to be made by the applicant

- criteria for successful completion of the task

- identification of critical steps and their associated performance standards

- restrictions on the sequence of steps, if applicable

b.

Ensure that any changes from the previously approved systems and administrative walk-through outlines (Forms ES-301-1 and 2) have not caused the test to deviate from any of the acceptance criteria (e.g., item distribution, bank use, repetition from the last 2 NRC examinations) specified on those forms and Form ES-201-2.

3. SIMULATOR CRITERIA
a.

The associated simulator operating tests (scenario sets) have been reviewed in accordance with Form ES-301-4 and a copy is attached.

Printed Name / Signature Date

a. Author
b. Facility Reviewer (*)
c. NRC Chief Examiner (#)
d. NRC Supervisor NOTE:
  • The facility signature is not applicable for NRC-developed tests.
  1. Independent NRC reviewer initial items in Column c; chief examiner concurrence required.

ES-301 Simulator Scenario Quality Checklist Form ES-301-4 NUREG-1021, Revision 9 Supplement 1 FENOC Facsimile Rev.1 Facility: Davis Besse Date of Exam 6/3 thru 6/14 2013 Operating Test No.: _____

QUALITATIVE ATTRIBUTES Initials a

b*

c#

1.

The initial conditions are realistic, in that some equipment and/or instrumentation may be out of service, but it does not cue the operators into expected events.

2.

The scenarios consist mostly of related events.

3.

Each event description consists of the point in the scenario when it is to be initiated the malfunction(s) that are entered to initiate the event the symptoms/cues that will be visible to the crew the expected operator actions (by shift position) the event termination point (if applicable)

4.

No more than one non-mechanistic failure (e.g., pipe break) is incorporated into the scenario without a credible preceding incident such as a seismic event.

5.

The events are valid with regard to physics and thermodynamics.

6.

Sequencing and timing of events is reasonable, and allows the examination team to obtain complete evaluation results commensurate with the scenario objectives.

7.

If time compression techniques are used, the scenario summary clearly so indicates.

Operators have sufficient time to carry out expected activities without undue time constraints. Cues are given.

8.

The simulator modeling is not altered.

9.

The scenarios have been validated. Pursuant to 10 CFR 55.46(d), any open simulator performance deficiencies or deviations from the referenced plant have been evaluated to ensure that functional fidelity is maintained while running the planned scenarios.

10.

Every operator will be evaluated using at least one new or significantly modified scenario. All other scenarios have been altered in accordance with Section D.5 of ES-301.

11.

All individual operator competencies can be evaluated, as verified using Form ES-301-6 (submit the form along with the simulator scenarios).

12.

Each applicant will be significantly involved in the minimum number of transients and events specified on Form ES-301-5 (submit the form with the simulator scenarios).

13.

The level of difficulty is appropriate to support licensing decisions for each crew position.

TARGET QUANTITATIVE ATTRIBUTES (PER SCENARIO; SEE SECTION D.5.d)

Actual Attributes

1. Total malfunctions (5-8) 6 6

6 5

2. Malfunctions after EOP entry (1-2) 2 2

1 2

3. Abnormal events (2-4) 3 3

3 3

4. Major transients (1-2) 2 1

1 1

5. EOPs entered/requiring substantive actions (1-2) 1 1

1 1

6. EOP contingencies requiring substantive actions (0-2) 1 1

0 1

7. Critical tasks (2-3) 3 2

3 3

ES-301 Transient and Event Checklist Form ES-301-5 NUREG-1021, Revision 9 Supplement 1 Page 1 of 3 FENOC Facsimile Rev. 1 Facility Davis Besse Date of Exam 6/3 thru 6/14 2013 Operating Test No.: ______

A P

P L

I C

A N

T E

V E

N T

T Y

P E

Scenarios 1

2 3

4 Backup T

O T

A L

M I

N I

M U

M(*)

CREW POSITION CREW POSITION CREW POSITION CREW POSITION S

R O

A T

C B

O P

S R

O A

T C

B O

P S

R O

A T

C B

O P

S R

O A

T C

B O

P R

I U

M A

S T

E R

RX 1

1 3

3 4

4 1

1 1

1 0

NOR 3

3 1

1 1

1 1

I/C 4,6,7, 10 4,10 6,7 1,2,4 5,7,8 5,7 8 1,2,4 2,3,5 7

2,3 2,5,7 2,4,5 7,8 2,4, 5,7,8 4

4 2

MAJ 8,9 8,9 8,9 6

6 6

6 6

6 6

6 6

2 2

1 TS 2,5 1,5 2,4 3,4 0

2 2

SROI-1 RX 1

3 2

1 1

0 NOR 1

1 1

1 1

I/C 4,10 1,2,4 5,7,8 2,5,7 11 4

4 2

MAJ 8,9 6

6 4

2 2

1 TS 1,5 2

0 2

2 SROI-2 RX 3

4 2

1 1

0 NOR 3

1 2

1 1

1 I/C 6,7 5,7 8 2,3,5 7

9 4

4 2

MAJ 8,9 6

6 4

2 2

1 TS 2,4 2

0 2

2 SROI-3 RX 1

4 2

1 1

0 NOR 3

1 1

1 1

I/C 4,6,7, 10 1,2,4 2,3 9

4 4

2 MAJ 8,9 6

6 4

2 2

1 TS 2,5 2

0 2

2 Instructions:

1.

Check the applicant level and enter the operating test number and Form ES-D-1 event numbers for each event type; TS are not applicable for RO applicants. ROs must serve in both the at-the-controls (ATC) and balance-of-plant (BOP) positions; Instant SROs must serve in both the SRO and the ATC positions, including at least two instrument or component (I/C) malfunctions and one major transient, in the ATC position. If an Instant SRO additionally serves in the BOP position, one I/C malfunction can be credited toward the two I/C malfunctions required for the ATC position.

2.

Reactivity manipulations may be conducted under normal or controlled abnormal conditions (refer to Section D.5.d) but must be significant per section C.2.a of Appendix D. (*) Reactivity and normal evolutions may be replaced with additional instrument or component malfunctions on a 1-for-1 basis.

3.

Whenever practical, both instrument and component malfunctions should be included; only those that require verifiable actions that provide insight to the applicants competence count toward the minimum requirements specified for the applicants license level in the right hand columns.

ES-301 Transient and Event Checklist Form ES-301-5 NUREG-1021, Revision 9 Supplement 1 Page 2 of 3 FENOC Facsimile Rev. 1 Facility Davis Besse Date of Exam 6/3 thru 6/14 2013 Operating Test No.: ______

A P

P L

I C

A N

T E

V E

N T

T Y

P E

Scenarios 1

2 3

4 Backup T

O T

A L

M I

N I

M U

M(*)

CREW POSITION CREW POSITION CREW POSITION CREW POSITION S

R O

A T

C B

O P

S R

O A

T C

B O

P S

R O

A T

C B

O P

S R

O A

T C

B O

P R

I U

SROU -1 RX 1

4 2

1 1

0 NOR 3

1 2

1 1

1 I/C 4,6,7, 10 2,3,5 7

8 4

4 2

MAJ 8,9 6

3 2

2 1

TS 2,5 2,4 4

0 2

2 RO -1 RX 1

1 1

1 0

NOR 1

1 1

1 1

I/C 4,10 2,5,7 5

4 4

2 MAJ 8,9 6

3 2

2 1

TS 0

0 2

2 RO -2 RX 4

1 1

1 0

NOR 3

1 1

1 1

I/C 6,7 2,3 4

4 4

2 MAJ 8,9 6

3 2

2 1

TS 0

0 2

2 RX 1

1 0

NOR 1

1 1

I/C 4

4 2

MAJ 2

2 1

TS 0

2 2

Instructions:

1.

Check the applicant level and enter the operating test number and Form ES-D-1 event numbers for each event type; TS are not applicable for RO applicants. ROs must serve in both the at-the-controls (ATC) and balance-of-plant (BOP) positions; Instant SROs must serve in both the SRO and the ATC positions, including at least two instrument or component (I/C) malfunctions and one major transient, in the ATC position. If an Instant SRO additionally serves in the BOP position, one I/C malfunction can be credited toward the two I/C malfunctions required for the ATC position.

2.

Reactivity manipulations may be conducted under normal or controlled abnormal conditions (refer to Section D.5.d) but must be significant per section C.2.a of Appendix D. (*) Reactivity and normal evolutions may be replaced with additional instrument or component malfunctions on a 1-for-1 basis.

3.

Whenever practical, both instrument and component malfunctions should be included; only those that require verifiable actions that provide insight to the applicants competence count toward the minimum requirements specified for the applicants license level in the right hand columns.

ES-301 Transient and Event Checklist Form ES-301-5 NUREG-1021, Revision 9 Supplement 1 Page 3 of 3 FENOC Facsimile Rev. 1 Facility Davis Besse Date of Exam 6/3 thru 6/14 2013 Operating Test No.: ______

A P

P L

I C

A N

T E

V E

N T

T Y

P E

Scenarios 1

2 3

4 Backup T

O T

A L

M I

N I

M U

M(*)

CREW POSITION CREW POSITION CREW POSITION CREW POSITION S

R O

A T

C B

O P

S R

O A

T C

B O

P S

R O

A T

C B

O P

S R

O A

T C

B O

P R

I U

SROU -2 RX 1

1 1

1 0

NOR 3

1 1

1 1

I/C 4,6,7, 10 4

4 4

2 MAJ 8,9 2

2 2

1 TS 2,5 2

0 2

2 SROU -3 RX 4

1 1

1 0

NOR 1

1 1

1 1

I/C 2,3,5 7

4 4

4 2

MAJ 6

1 2

2 1

TS 2,4 2

0 2

2 RO -3 RX 1

1 1

1 0

NOR 1

1 1

1 1

I/C 4,10 2,5,7 5

4 4

2 MAJ 8,9 6

3 2

2 1

TS 0

0 2

2 RO -4 RX 4

1 1

1 0

NOR 3

1 1

1 1

I/C 6,7 2,3 4

4 4

2 MAJ 8,9 6

3 2

2 1

TS 0

0 2

2 Instructions:

1.

Check the applicant level and enter the operating test number and Form ES-D-1 event numbers for each event type; TS are not applicable for RO applicants. ROs must serve in both the at-the-controls (ATC) and balance-of-plant (BOP) positions; Instant SROs must serve in both the SRO and the ATC positions, including at least two instrument or component (I/C) malfunctions and one major transient, in the ATC position. If an Instant SRO additionally serves in the BOP position, one I/C malfunction can be credited toward the two I/C malfunctions required for the ATC position.

2.

Reactivity manipulations may be conducted under normal or controlled abnormal conditions (refer to Section D.5.d) but must be significant per section C.2.a of Appendix D. (*) Reactivity and normal evolutions may be replaced with additional instrument or component malfunctions on a 1-for-1 basis.

3.

Whenever practical, both instrument and component malfunctions should be included; only those that require verifiable actions that provide insight to the applicants competence count toward the minimum requirements specified for the applicants license level in the right hand columns.

NUREG-1021, Revision 9 Supplement 1 Page 1 of 1 FENOC Facsimile Rev. 1 ES-401 Record of Rejected K/As Form ES-401-4 Facility: Davis Besse Date of Exam 6/3 thru 6/14 2013 Operating Test No.:

Tier /

Group Randomly Selected K/A Reason for Rejection RO OUTLINE 1/1 000011 EA2.12 Question # 3 Davis Besse does not have a system for throttling or stopping reflux boiling spray. Randomly selected 000011 EA2.10 as a replacement.

1/1 000025 AK3.01 Question # 6 Davis Besse does not have an alternate RHR flowpath. Randomly selected 000025 AA1.01 as a replacement.

1/2 000059 AK2.01 Question # 21 Davis Besse does not have any gas monitors on the liquid waste discharge system. Randomly selected 000059 AK2.01 as a replacement.

2/1 025 2.4.4 Question # 40 Davis Besse does not have Ice Condensers. Randomly selected 004 2.4.4 as a replacement.

2/1 025 K1.02 Question # 41 Davis Besse does not have Ice Condensers. Randomly selected 062 K1.02 as a replacement.

2/1 064 K4.08 Question # 50 Davis Besse does not have any design features or interlocks for EDG fuel isolation valves. Randomly selected 064 K4.03 as a replacement.

2/1 073 K5.03 Question # 51 Unable to write a discriminatory question for the process radiation monitoring system that depicts the relationship between radiation intensity and exposure limits. Randomly selected 073 K5.01 as a replacement.

3 2.4.40 Question # 75 Unable to write an RO discriminatory question regarding SRO responsibilities during E-Plan implementation. Randomly selected 2.4.35 as a replacement.

2/2 034 A3.01 Question # 59. Deleted from the exam to achieve balance. There are too many fuel handling questions (5) already being addressed on this exam.

Discussed with chief examiner and determined that this K/A should be deleted to obtain a better balance. Randomly selected 041 A2.02 as a replacement.

SRO OUTLINE 2/2 027 A2.01 Question # 92 Davis Besse does not have an iodine removal system. Iodine is removed with the passive sodium triphosphate baskets. Randomly selected 015 A2.01 as a replacement.

1/1 057 AA2.16 Question # 77 Unable to write a discriminatory SRO level question for loss of vital AC impact on PZR level. Randomly selected 038 EA2.01 as a replacement.

NUREG-1021, Revision 9 Supplement 1 FENOC Facsimile Rev. 1 ES-401 Written Examination Quality Checklist Form ES-401-6 Facility: Davis Besse Date of Exam 6/3 thru 6/14 2013 Exam Level: RO SRO Item Description Initial a

b*

c#

1.

Questions and answers technically accurate and applicable to facility

2.
a. NRC K/As referenced for all questions
b. Facility learning objectives referenced as available
3.

SRO questions are appropriate per Section D.2.d of ES-401

4.

The sampling process was random and systematic (If more than 4 RO or 2 SRO questions are repeated from the last two NRC licensing exams, consult the NRR OL program office.)

5.

Question duplication from the license screening/audit exam was controlled as indicated below (check the item that applies) and appears appropriate:

__ the audit exam was systematically and randomly developed; or

__ the audit exam was completed before the license exam was started; or

__ the examinations were developed independently; or

__ the licensee certifies that there is no duplication; or

__ other (explain)

6.

Bank use meets limits (no more than 75 percent from the bank, at least 10 percent new, and the rest new or modified); enter the actual RO / SRO-only question distribution(s) at right.

Bank Modified New 16/0 (21.3%/0%)

0/0 (0%/0%)

59/25 (78.7%/100%)

7.

Between 50 and 60 percent of the questions on the RO exam are written at the comprehension/analysis level; the SRO exam may exceed 60 percent If the randomly selected K/As support the higher cognitive levels; enter the actual RO / SRO question distribution(s) at right.

Memory C/A 32/1 (42.7% / 4%)

43/24 (57.3% / 96%)

8.

References/handouts provided do not give away answers or aid in the elimination of distractors.

9.

Question content conforms with specific K/A statements in the previously approved examination outline and is appropriate for the Tier to which they are assigned; deviations are justified

10.

Question psychometric quality and format meet the guidelines in ES Appendix B.

11.

The exam contains the required number of one-point, multiple choice items; the total is correct and agrees with value on cover sheet Printed Name / Signature Date

a. Author
b. Facility Reviewer (*)
c. NRC Chief Examiner (#)________________________________________________________
d. NRC Supervisor Note:
  • The facility reviewer's initials/signature are not applicable for NRC-developed examinations.
  1. Independent NRC reviewer initial items in Column c; chief examiner concurrence required.

NUREG-1021, Revision 9 Supplement 1 RO Page 1 of 9 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Facility: Davis-Besse RO Date of Exam 6/3 thru 6/14 2013 Tier Group RO K/A Category Points SRO ONLY Points K

1 K

2 K

3 K

4 K

5 K

6 A

1 A

2 A

3 A

4 G

TOTAL A2 G*

TOTAL

1.

Emergency Abnormal Plant Evolutions 1

3 3

2 4

3 3

18 6

2 1

2 1

2 2

1 9

4 Tier Totals 4

5 3

6 5

4 27 10

2.

Plant Systems 1

3 2

3 3

2 2

3 3

2 2

3 28 5

2 1

1 1

1 0

0 2

2 0

1 1

10 3

Tier Totals 4

3 4

4 2

2 5

5 2

3 4

38 8

3. Generic Knowledge and Abilities Category 1

2 3

4 10 1 2 3 4 7

2 3

2 3

Note:

1.

Ensure that at least two topics from every applicable K/A category are sampled within each tier of the RO and SRO-only outlines (i.e., except for one category in Tier 3 of the SRO-only outline, the Tier Totals in each K/A category shall not be less than two).

2.

The point total for each group and tier in the proposed outline must match that specified in the table. The final point total for each group and tier may deviate by +/-1 from that specified in the table based on NRC revisions. The final RO exam must total 75 points and the SRO-only exam must total 25 points.

3.

Systems/evolutions within each group are identified on the associated outline; systems or evolutions that do not apply at the facility should be deleted and justified; operationally important, site-specific systems/evolutions that are not included on the outline should be added. Refer to Section D.1.b of ES-401 for guidance regarding the elimination of inappropriate K/A statements.

4.

Select topics from as many systems and evolutions as possible; sample every system or evolution in the group before selecting a second topic for any system or evolution.

5.

Absent a plant-specific priority, only those K/As having an importance rating (IR) of 2.5 or higher shall be selected.

Use the RO and SRO ratings for the RO and SRO-only portions, respectively.

6.

Select SRO topics for Tiers 1 and 2 from the shaded systems and K/A categories.

7.*

The generic (G) K/As in Tiers 1 and 2 shall be selected from Section 2 of the K/A Catalog, but the topics must be relevant to the applicable evolution or system. Refer to Section D.1.b of ES-401 for the applicable K/As.

8.

On the following pages, enter the K/A numbers, a brief description of each topic, the topics importance ratings (IRs) for the applicable license level, and the point totals (#) for each system and category. Enter the group and tier totals for each category in the table above; if fuel handling equipment is sampled in other than Category A2 or G* on the SRO-only exam, enter it on the left side of Column A2 for Tier 2, Group 2 (Note #1 does not apply). Use duplicate pages for RO and SRO-only exams.

9.

For Tier 3, select topics from Section 2 of the K/A catalog, and enter the K/A numbers, descriptions, IRs, and point totals (#) on Form ES-401-3. Limit SRO selections to K/As that are linked to 10 CFR 55.43.

NUREG-1021, Revision 9 Supplement 1 RO Page 2 of 9 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Davis-Besse 6/2013 Emergency and Abnormal Plant Evolutions - Tier 1/Group 1(RO)

E/APE # / Name / Safety Function K

1 K

2 K

3 A

1 A

2 G

K/A Topic(s)

IR Points 000008 Pressurizer (PZR) Vapor Space Accident Question 1 X

AK1.01 Knowledge of the operational implications of the following concepts as they apply to a Pressurizer Vapor Space Accident:

Thermodynamics and flow characteristics of open or leaking valves (CFR 41.8 / 41.10 / 45.3) 3.2 1

000009 Small Break LOCA Question 2 X

EK2.03 Knowledge of the interrelations between the small break LOCA and the following: S/Gs (CFR 41.7 / 45.7) 3.0 1

000011 Large Break LOCA Question 3 X

EA2.10 Ability to determine or interpret the following as they apply to a Large Break LOCA:

Verification of adequate core cooling (CFR 43.5 / 45.13) 4.5 1

000015/000017 Reactor Coolant Pump (RCP) Malfunctions Question 4 X

2.4.11 Knowledge of abnormal condition procedures.

(CFR: 41.10 / 43.5 / 45.13) 4.0 1

000022 Loss of Reactor Coolant Makeup Question 5 X

AK3.02 Knowledge of the reasons for the following responses as they apply to the Loss of Reactor Coolant Makeup: Actions contained in SOPs and EOPs for RCPs, loss of makeup, loss of charging, and abnormal charging (CFR 41.5, 41.10 / 45.6 / 45.13) 3.5 1

000025 Loss of Residual Heat Removal System (RHRS)

Question 6 X

AA1.01 Ability to operate and / or monitor the following as they apply to the Loss of Residual Heat Removal System: RCS/RHRS cooldown rate (CFR 41.7 / 45.5 / 45.6) 3.6 1

000026 Loss of Component Cooling Water (CCW)

Question 7 X

AA1. 07 Ability to operate and / or monitor the following as they apply to the Loss of Component Cooling Water: Flow rates to the components and systems that are serviced by the CCWS; interactions among the components (CFR 41.7 / 45.5 / 45.6) 2.9 1

000027 Pressurizer Pressure Control System (PZR PCS) Malfunction Question 8 X

AK2.03 Knowledge of the interrelations between the Pressurizer Pressure Control Malfunctions and the following: Controllers and positioners (CFR 41.7 / 45.7) 2.6 1

000029 Anticipated Transient Without Scram (ATWS)

Question 9 X

EK2.06 Knowledge of the interrelations between the and the following an ATWS: Breakers, relays, and disconnects (CFR 41.7 / 45.7) 2.9*

1 000038 Steam Generator Tube Rupture (SGTR)

Question 10 X

EA2.12 Ability to determine or interpret the following as they apply to a SGTR: Status of MSIV activating system (CFR 43.5 / 45.13) 3.9*

1 000040 Steam Line Rupture - Excessive Heat Transfer Question 11 X

2.1.7 Ability to evaluate plant performance and make operational judgments based on operating characteristics, reactor behavior, and instrument interpretation.

(CFR: 41.5 / 43.5 / 45.12 / 45.13) 4.4 1

000054 Loss of Main Feedwater (MFW)

Question 12 X

AA2.01 Ability to determine and interpret the following as they apply to the Loss of Main Feedwater (MFW): Occurrence of reactor and/or turbine trip (CFR: 43.5 / 45.13) 4.3 1

NUREG-1021, Revision 9 Supplement 1 RO Page 3 of 9 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Davis-Besse 6/2013 Emergency and Abnormal Plant Evolutions - Tier 1/Group 1(RO) Continued E/APE # / Name / Safety Function K

1 K

2 K

3 A

1 A

2 G

K/A Topic(s)

IR Points 000055 Loss of Offsite and Onsite Power (Station Blackout)

Question 13 X

EA1.06 Ability to operate and monitor the following as they apply to a Station Blackout: Restoration of power with one ED/G (CFR 41.7 / 45.5 / 45.6) 4.1 1

000056 Loss of Offsite Power Question 14 X

AK1.01 Knowledge of the operational implications of the following concepts as they apply to Loss of Offsite Power: Principle of cooling by natural convection (CFR 41.8 / 41.10 / 45.3) 3.7 1

000062 Loss of Nuclear Service Water Question 15 X

AK3.01 Knowledge of the reasons for the following responses as they apply to the Loss of Nuclear Service Water: The conditions that will initiate the automatic opening and closing of the SWS isolation valves to the nuclear service water coolers (CFR 41.4, 41.8 / 45.7 )

3.2*

1 000077 Generator Voltage and Electric Grid Disturbances Question 16 X

AK1.03 Knowledge of the operational implications of the following concepts as they apply to Generator Voltage and Electric Grid Disturbances:

Under-excitation (CFR: 41.4, 41.5, 41.7, 41.10 / 45.8) 3.3 1

BW/E04 Inadequate Heat Transfer - Loss Of Secondary Heat Sink Question 17 X

EA1.1 Ability to operate and / or monitor the following as they apply to the (Inadequate Heat Transfer) Components, and functions of control and safety systems, including instrumentation, signals, interlocks, failure modes, and automatic and manual features.

(CFR: 41.7 / 45.5 / 45.6) 4.4 1

BW/E10 Post-Trip Stabilization Question 18 X

2.1.19 Ability to use plant computers to evaluate system or component status.

(CFR: 41.10 / 45.12) 3.9 1

K/A Category Point Totals:

3 3

2 4

3 3

Group Point Total:

18

NUREG-1021, Revision 9 Supplement 1 RO Page 4 of 9 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Davis-Besse 6/2013 Emergency and Abnormal Plant Evolutions - Tier 1/Group 2(RO)

E/APE # / Name / Safety Function K

1 K

2 K

3 A

1 A

2 G

K/A Topic(s)

IR Points 000036 Fuel Handling Incidents Question 19 X

AK1.03 Knowledge of the operational implications of the following concepts as they apply to Fuel Handling Incidents : Indications of approaching Criticality (CFR 41.8 / 41.10 / 45.3) 4.0 1

000051 Loss of Condenser Vacuum Question 20 X

2.2.44 Ability to interpret control room indications to verify the status and operation of a system, and understand how operator actions and directives affect plant and system conditions.

(CFR: 41.5 / 43.5 / 45.12) 4.2 1

000059 Accidental Liquid Radwaste Release Question 21 X

AK2.01 Knowledge of the interrelations between the Accidental Liquid Radwaste Release and the following: Radioactive-liquid monitors (CFR 41.7 / 45.7) 2.7 1

000060 Accidental Gaseous-Waste Release Question 22 X

AA2.06 Ability to operate and / or monitor the following as they apply to the Accidental Gaseous Radwaste: Valve lineup for release of radioactive gases (CFR 41.7 / 45.5 / 45.6) 3.6*

1 000061 ARM System Alarms Question 23 X

AK3.02 Knowledge of the reasons for the following responses as they apply to the Area Radiation Monitoring (ARM) System Alarms: Guidance contained in alarm response for ARM system (CFR 41.5,41.10 / 45.6 / 45.13) 3.4 1

000069 Loss of Containment Integrity Question 24 X

AA1.03 Ability to operate and / or monitor the following as they apply to the Loss of Containment Integrity: Fluid systems penetrating containment (CFR 41.7 / 45.5 / 45.6) 2.8 1

BW/A01 Plant Runback Question 25 X

AA2.1 Ability to determine and interpret the following as they apply to the (Plant Runback)

Facility conditions and selection of appropriate procedures during abnormal and emergency operations.

(CFR: 43.5 / 45.13) 3.0 1

BW/A02 Loss of NNI-X Question 26 X

AK2.2 Knowledge of the interrelations between the (Loss of NNI-X) and the following: Facilitys heat removal systems, including primary coolant, emergency coolant, the decay heat removal systems, and relations between the proper operation of these systems to the operation of the facility.

(CFR: 41.7 / 45.7) 3.8 1

BW/E13 EOP Rules Question 27 X

EA1.3 Ability to operate and / or monitor the following as they apply to the (EOP Rules) Desired operating results during abnormal and emergency situations.

(CFR: 41.7 / 45.5 / 45.6) 3.4 1

K/A Category Point Totals:

1 2

1 2

2 1

Group Point Total:

9

NUREG-1021, Revision 9 Supplement 1 RO Page 5 of 9 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Davis-Besse 6/2013 Plant Systems - Tier 2/Group 1(RO)

System # / Name K

1 K

2 K

3 K

4 K

5 K

6 A

1 A

2 A

3 A

4 G

K/A Topic(s)

IR Points 003 Reactor Coolant Pump System (RCPS)

Question 28 X

A3.02 Ability to monitor automatic operation of the RCPS, including: Motor current (CFR: 41.7 / 45.5) 2.6 1

003 Reactor Coolant Pump System (RCPS)

Question 29 X

K3.01 Knowledge of the effect that a loss or malfunction of the RCPS will have on the following: RCS (CFR: 41.7 / 45.6) 3.7 1

004 Chemical and Volume Control System Question 30 X

K4.14 Knowledge of CVCS design feature(s) and/or interlock(s) which provide for the following: Control interlocks on letdown system (letdown tank bypass valve)

(CFR: 41.7) 2.8*

1 005 Residual Heat Removal System (RHRS)

Question 31 X

K6.03 Knowledge of the effect of a loss or malfunction on the following will have on the RHRS: RHR heat exchanger (CFR: 41.7 / 45.7) 2.5 1

006 Emergency Core Cooling System (ECCS)

Question 32 X

K6.02 Knowledge of the effect of a loss or malfunction on the following will have on the ECCS: Core flood tanks (accumulators)

(CFR: 41.7 / 45.7) 3.4 1

007 Pressurizer Relief Tank/Quench Tank System (PRTS)

Question 33 X

K3.01 Knowledge of the effect that a loss or malfunction of the PRTS will have on the following: Containment (CFR: 41.7 / 45.6) 3.3 1

008 Component Cooling Water System (CCWS)

Question 34 X

A2.01 Ability to (a) predict the impacts of the following malfunctions or operations on the CCWS, and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Loss of CCW pump (CFR: 41.5 / 43.5 / 45.3 / 45.13) 3.3 1

010 Pressurizer Pressure Control System (PZR PCS)

Question 35 X

2.2.39 Knowledge of less than or equal to one hour Technical Specification action statements for systems.

(CFR: 41.7 / 41.10 / 43.2 / 45.13) 3.9 1

010 Pressurizer Pressure Control System (PZR PCS)

Question 36 X

K4.02 Knowledge of PZR PCS design feature(s) and/or interlock(s) which provide for the following: Prevention of uncovering PZR heaters (CFR: 41.7) 3.0 1

012 Reactor Protection System (RPS)

Question 37 X

A2.07 Ability to (a) predict the impacts of the following malfunctions or operations on the RPS; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Loss of dc control power (CFR: 41.5 / 43.5 / 45.3 / 45.5) 3.2*

1

NUREG-1021, Revision 9 Supplement 1 RO Page 6 of 9 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Davis-Besse 6/2013 Plant Systems - Tier 2/Group 1(RO) Continued System # / Name K

1 K

2 K

3 K

4 K

5 K

6 A

1 A

2 A

3 A

4 G

K/A Topic(s)

IR Points 013 Engineered Safety Features Actuation System (ESFAS)

Question 38 X

K1.07 Knowledge of the physical connections and/or cause effect relationships between the ESFAS and the following systems: AFW System (CFR: 41.2 to 41.9 / 45.7 to 45.8) 4.1 1

022 Containment Cooling System (CCS)

Question 39 X

A1.04 Ability to predict and/or monitor changes in parameters (to prevent exceeding design limits) associated with operating the CCS controls including:

Cooling water flow (CFR: 41.5 / 45.5) 3.2 1

004 Chemical and Volume Control System Question 40 X

2.4.4 Ability to recognize abnormal indications for system operating parameters that are entry-level conditions for emergency and abnormal operating procedures.

(CFR: 41.10 / 43.2 / 45.6) 4.5 1

062 AC Electrical Distribution System Question 41 X

K1.02 Knowledge of the physical connections and/or cause/effect relationships between the ac distribution system and the following systems: ED/G (CFR: 41.2 to 41.9) 4.1 1

026 Containment Spray System (CSS)

Question 42 X

K2.02 Knowledge of bus power supplies to the following: MOVs (CFR: 41.7) 2.7*

1 039 Main and Reheat Steam System (MRSS)

Question 43 X

K5.08 Knowledge of the operational implications of the following concepts as the apply to the MRSS: Effect of steam removal on reactivity (CFR: 441.5 / 45.7) 3.6 1

059 Main Feedwater (MFW)

System Question 44 X

A1.07 Ability to predict and/or monitor changes in parameters (to prevent exceeding design limits) associated with operating the MFW controls including: Feed Pump speed, including normal control speed for ICS (CFR: 41.5 / 45.5) 2.5*

1 059 Main Feedwater (MFW)

System Question 45 X

A4.01 Ability to manually operate and monitor in the control room: MFW turbine trip indication (CFR: 41.7 / 45.5 to 45.8) 3.1*

1 061 Auxiliary / Emergency Feedwater (AFW) System Question 46 X

A2.06 Ability to (a) predict the impacts of the following malfunctions or operations on the AFW; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Back leakage of MFW (CFR: 41.5 / 43.5 / 45.3 / 45.13) 2.7 1

062 AC Electrical Distribution System Question 47 X

A3.04 Ability to monitor automatic operation of the ac distribution system, including:

Operation of inverter (e.g., precharging synchronizing light, static transfer)

(CFR: 41.7 / 45.5) 2.7 1

NUREG-1021, Revision 9 Supplement 1 RO Page 7 of 9 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Davis-Besse 6/2013 Plant Systems - Tier 2/Group 1(RO) Continued System # / Name K

1 K

2 K

3 K

4 K

5 K

6 A

1 A

2 A

3 A

4 G

K/A Topic(s)

IR Points 063 DC Electrical Distribution System Question 48 X

A1.01 Ability to predict and/or monitor changes in parameters associated with operating the DC electrical system controls including: Battery capacity as it is affected by discharge rate (CFR: 41.5 / 45.5) 2.5 1

063 DC Electrical Distribution System Question 49 X

A4.02 Ability to manually operate and/or monitor in the control room: Battery voltage indicator (CFR: 41.7 / 45.5 to 45.8) 2.8*

1 064 Emergency Diesel Generator (ED/G) System Question 50 X

K4.03 Knowledge of ED/G system design feature(s) and/or interlock(s) which provide for the following: Governor valve operation (CFR: 41.7) 2.5 1

073 Process Radiation Monitoring (PRM) System Question 51 X

K5.01 Knowledge of the operational implications as they apply to concepts as they apply to the PRM system: Radiation theory, including sources, types, units, and effects (CFR: 41.5 / 45.7) 2.5 1

076 Service Water System (SWS)

Question 52 X

K2.04 Knowledge of bus power supplies to the following: Reactor building closed cooling water (CFR: 41.7) 2.5*

1 078 Instrument Air System (IAS)

Question 53 X

K1.05 Knowledge of the physical connections and/or cause-effect relationships between the IAS and the following systems: MSIV air (CFR: 41.2 to 41.9 / 45.7 to 45.8) 3.4*

1 103 Containment System Question 54 X 2.1.28 Knowledge of the purpose and function of major system components and controls.

(CFR: 41.7) 4.1 1

103 Containment System Question 55 X

K3.02 Knowledge of the effect that a loss or malfunction of the containment system will have on the following: Loss of containment integrity under normal operations (CFR: 41.7 / 45.6) 3.8 1

K/A Category Point Totals:

3 2

3 3

2 2

3 3

2 2

3 Group Point Total:

28

NUREG-1021, Revision 9 Supplement 1 RO Page 8 of 9 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Davis-Besse 6/2013 Plant Systems - Tier 2/Group 2(RO)

System # / Name K

1 K

2 K

3 K

4 K

5 K

6 A

1 A

2 A

3 A

4 G

K/A Topic(s)

IR Points 002 Reactor Coolant System (RCS)

Question 56 X

K1.03 Knowledge of the physical connections and/or cause-effect relationships between the RCS and the following systems: Borated water storage tank (CFR: 41.2 to 41.9 / 45.7 to 45.8) 3.8 1

014 Rod Position Indication System Question 57 X

K4.03 Knowledge of RPIS design feature(s) and/or interlock(s) which provide for the following: Rod bottom lights (CFR: 41.5 / 45.7) 3.2 1

015 Nuclear Instrumentation System Question 58 X

A4.01 Ability to manually operate and/or monitor in the control room: Selection of controlling NIS channel (CFR: 41.7 / 45.5 to 45.8) 3.6*

1 041 Steam Dump System (SDS) and Turbine Bypass Control Question 59 X

A2.02 Ability to (a) predict the impacts of the following malfunctions or operations on the SDS; and (b) based on those predictions or mitigate the consequences of those malfunctions or operations:

Steam valve stuck open (CFR: 41.5 / 43.5 / 45.3 / 45.13) 3.6 1

055 Condenser Air Removal System Question 60 X

K3.01 Knowledge of the effect that a loss or malfunction of the CARS will have on the following: Main condenser (CFR: 41.7 / 45.6) 2.5 1

068 Liquid Radwaste System Question 61 X

A2.02 Ability to (a) predict the impacts of the following malfunctions or operations on the Liquid Radwaste System; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Lack of tank recirculation prior to release (CFR: 41.5 / 43.5 / 45.3 / 45.13) 2.7*

1 072 Area Radiation Monitoring System Question 62 X

A1.01 Ability to predict and/or monitor changes in parameters (to prevent exceeding design limits) associated with operating the ARM system controls including: Radiation levels (CFR: 41.5 / 45.5) 3.4 1

075 Circulating Water System Question 63 X

K2.03 Knowledge of bus power supplies to the following: Emergency/essential SWS pumps (CFR: 41.7) 2.6*

1 079 Station Air System Question 64 X 2.4.2 Knowledge of system set points, interlocks and automatic actions associated with EOP entry conditions.

(CFR: 41.7 / 45.7 / 45.8) 4.5 1

086 Fire Protection System (FPS)

Question 65 X

K6.04 Knowledge of the effect of a loss or malfunction on the Fire Protection System following will have on the : Fire, smoke, and heat detectors (CFR: 41.7 / 45.7) 2.6 1

K/A Category Point Totals:

1 1

1 1

0 0

2 2 0

1 1

Group Point Total:

10

NUREG-1021, Revision 9 Supplement 1 RO Page 9 of 9 FENOC Facsimile Rev. 1 ES 401 Generic Knowledge and Abilities Outline (Tier 3)

Form ES-401-3 Facility: Davis-Besse RO Date of Exam 6/3 thru 6/14 2013 Category K/A#

Topic RO SRO Only IR Points IR Points

1.

Conduct of Operations 2.1.40 Knowledge of refueling administrative requirements. (CFR: 41.10 / 43.5 /

45.13)

Question 66 2.8 1

2.1.45 Ability to identify and interpret diverse indications to validate the response of another indication. (CFR: 41.7 / 43.5 / 45.4)

Question 67 4.3 1

Subtotal 2

2.

Equipment Control 2.2.36 Ability to analyze the effect of maintenance activities, such as degraded power sources, on the status of limiting conditions for operations. (CFR:

41.10 / 43.2 / 45.13)

Question 68 3.1 1

2.2.7 Knowledge of the process for conducting special or infrequent tests.

(CFR: 41.10 / 43.3 / 45.13)

Question 69 2.9 1

2.2.35 Ability to determine Technical Specification Mode of Operation. (CFR:

41.7 / 41.10 / 43.2 / 45.13)

Question 70 3.6 1

Subtotal 3

3.

Radiation Control 2.3.4 Knowledge of radiation exposure limits under normal or emergency conditions. (CFR: 41.12 / 43.4 / 45.10)

Question 71 3.2 1

2.3.5 Ability to use radiation monitoring systems, such as fixed radiation monitors and alarms, portable survey instruments, personnel monitoring equipment, etc. (CFR: 41.11 / 41.12 / 43.4 / 45.9)

Question 72 2.9 1

2.3.13 Knowledge of radiological safety procedures pertaining to licensed operator duties, such as response to radiation monitor alarms, containment entry requirements, fuel handling responsibilities, access to locked high-radiation areas, aligning filters, etc. (CFR: 41.12 / 43.4 / 45.9

/ 45.10)

Question 73 3.4 Subtotal 2

4.

Emergency Procedures/

Plan 2.4.31 Knowledge of annunciator alarms, indications, or response procedures.

(CFR: 41.10 / 45.3)

Question 74 4.2 1

2.4.35 Knowledge of local auxiliary operator tasks during an emergency and the resultant operational effects. (CFR: 41.10 / 43.5 / 45.13)

Question 75 3.8 1

Subtotal 3

Tier 3 Point Total 10

NUREG-1021, Revision 9 Supplement 1 SRO Page 1 of 6 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Facility: Davis-Besse SRO Date of Exam 6/3 thru 6/14 2013 Tier Group RO K/A Category Points SRO ONLY Points K

1 K

2 K

3 K

4 K

5 K

6 A

1 A

2 A

3 A

4 G

TOTAL A2 G*

TOTAL

1.

Emergency Abnormal Plant Evolutions 1

18 3

3 6

2 9

2 2

4 Tier Totals 27 5

5 10

2.

Plant Systems 1

28 3

2 5

2 10 0 2 1

3 Tier Totals 38 5

3 8

3. Generic Knowledge and Abilities Category 1

2 3

4 10 1 2 3 4 7

1 2 2 2 Note:

1.

Ensure that at least two topics from every applicable K/A category are sampled within each tier of the RO and SRO-only outlines (i.e., except for one category in Tier 3 of the SRO-only outline, the Tier Totals in each K/A category shall not be less than two).

2.

The point total for each group and tier in the proposed outline must match that specified in the table. The final point total for each group and tier may deviate by +/-1 from that specified in the table based on NRC revisions. The final RO exam must total 75 points and the SRO-only exam must total 25 points.

3.

Systems/evolutions within each group are identified on the associated outline; systems or evolutions that do not apply at the facility should be deleted and justified; operationally important, site-specific systems/evolutions that are not included on the outline should be added. Refer to Section D.1.b of ES-401 for guidance regarding the elimination of inappropriate K/A statements.

4.

Select topics from as many systems and evolutions as possible; sample every system or evolution in the group before selecting a second topic for any system or evolution.

5.

Absent a plant-specific priority, only those K/As having an importance rating (IR) of 2.5 or higher shall be selected.

Use the RO and SRO ratings for the RO and SRO-only portions, respectively.

6.

Select SRO topics for Tiers 1 and 2 from the shaded systems and K/A categories.

7.*

The generic (G) K/As in Tiers 1 and 2 shall be selected from Section 2 of the K/A Catalog, but the topics must be relevant to the applicable evolution or system. Refer to Section D.1.b of ES-401 for the applicable K/As.

8.

On the following pages, enter the K/A numbers, a brief description of each topic, the topics importance ratings (IRs) for the applicable license level, and the point totals (#) for each system and category. Enter the group and tier totals for each category in the table above; if fuel handling equipment is sampled in other than Category A2 or G* on the SRO-only exam, enter it on the left side of Column A2 for Tier 2, Group 2 (Note #1 does not apply). Use duplicate pages for RO and SRO-only exams.

9.

For Tier 3, select topics from Section 2 of the K/A catalog, and enter the K/A numbers, descriptions, IRs, and point totals (#) on Form ES-401-3. Limit SRO selections to K/As that are linked to 10 CFR 55.43.

NUREG-1021, Revision 9 Supplement 1 SRO Page 2 of 6 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Davis-Besse 6/2013 Emergency and Abnormal Plant Evolutions - Tier 1/Group 1(SRO)

E/APE # / Name / Safety Function K

1 K

2 K

3 A

1 A

2 G

K/A Topic(s)

IR Points 000056 Loss of Offsite Power Question 76 X 2.1.20 Ability to interpret and execute procedure steps.

(CFR: 41.10 / 43.5 / 45.12) 4.6 1

000038 Steam Generator Tube Rupture (SGTR)

Question 77 X

EA2.01 Ability to determine and interpret the following as they apply to SGTR: When to isolate one or more S/Gs (CFR: 43.5 / 45.13) 4.7 1

000058 Loss of DC Power Question 78 X

AA2.03 Ability to determine and interpret the following as they apply to the Loss of DC Power:

DC loads lost; impact on ability to operate and monitor plant systems (CFR: 43.5 / 45.13) 3.9 1

000065 Loss of Instrument Air Question 79 X 2.4.9 Knowledge of low power/shutdown implications in accident (e.g., loss of coolant accident or loss of residual heat removal) mitigation strategies.

(CFR: 41.10 / 43.5 / 45.13) 4.2 1

BW/E10 Post-Trip Stabilization Question 80 X

EA2.1 Ability to determine and interpret the following as they apply to the (Post-Trip Stabilization) Facility conditions and selection of appropriate procedures during abnormal and emergency operations.

(CFR: 43.5, 45.13) 4.0 1

BW/E05 Steam Line Rupture - Excessive Heat Transfer Question 81 X 2.4.20 Knowledge of the operational implications of EOP warnings, cautions, and notes.

(CFR: 41.10 / 43.5 / 45.13) 4.3 1

K/A Category Point Totals:

0 0

0 0

3 3

Group Point Total:

6

NUREG-1021, Revision 9 Supplement 1 SRO Page 3 of 6 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Davis-Besse 6/2013 Emergency and Abnormal Plant Evolutions - Tier 1/Group 2(SRO)

E/APE # / Name / Safety Function K

1 K

2 K

3 A

1 A

2 G

K/A Topic(s)

IR Points 000001 Continuous Rod Withdrawal Question 82 X

AA2.03 Ability to determine and interpret the following as they apply to the Continuous Rod Withdrawal : Proper actions to be taken if automatic safety functions have not taken place (CFR: 43.5 / 45.13) 4.8 1

000024 Emergency Boration Question 83 X 2.2.42 Ability to recognize system parameters that are entry-level conditions for Technical Specifications. (CFR: 41.7 / 41.10 / 43.2 / 43.3 /

45.3) 4.6 1

000033 Loss of Intermediate Range Nuclear Instrumentation Question 84 X

AA2.03 Ability to determine and interpret the following as they apply to the Loss of Intermediate Range Nuclear Instrumentation: Indication of blown fuse (CFR: 43.5 / 45.13) 3.1 1

BW/A06 Shutdown Outside Control Room Question 85 X 2.1.32 Ability to explain and apply system limits and precautions.

(CFR: 41.10 / 43.2 / 45.12) 4.0 1

K/A Category Point Totals:

0 0

0 0

2 2

Group Point Total:

4

NUREG-1021, Revision 9 Supplement 1 SRO Page 4 of 6 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Davis-Besse 6/2013 Plant Systems - Tier 2/Group 1(SRO)

System # / Name K

1 K

2 K

3 K

4 K

5 K

6 A

1 A

2 A

3 A

4 G

K/A Topic(s)

IR Points 006 Emergency Core Cooling System (ECCS)

Question 86 X

A2.03 Ability to (a) predict the impacts of the following malfunctions or operations on the ECCS; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: System leakage (CFR: 41.5 / 45.5) 3.7 1

013 Engineered Safety Features Actuation System (ESFAS)

Question 87 X 2.4.21 Knowledge of the parameters and logic used to assess the status of safety functions, such as reactivity control, core cooling and heat removal, reactor coolant system integrity, containment conditions, radioactivity release control, etc.

(CFR: 41.7 / 43.5 / 45.12) 4.6 1

026 Containment Spray System (CSS)

Question 88 X

A2.07 Ability to (a) predict the impacts of the following malfunctions or operations on the CSS; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Loss of containment spray pump suction when in recirculation mode, possibly caused by clogged sump screen, pump inlet high temperature exceeded cavitation, voiding),

or sump level below cutoff (interlock) limit (CFR: 41.5 / 43.5 / 45.3 / 45.13) 3.9 1

039 Main and Reheat Steam System (MRSS)

Question 89 X

A2.05 Ability to (a) predict the impacts of the following malfunctions or operations on the MRSS; and (b) based on predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Increasing steam demand, its relationship to increases in reactor power (CFR: 41.5 / 43.5 / 45.3 / 45.13) 3.6 1

061 Auxiliary/Emergency Feedwater (AFW) System Question 90 X 2.4.6 Knowledge of EOP mitigation strategies.

(CFR: 41.10 / 43.5 / 45.13) 4.7 1

K/A Category Point Totals:

0 0

0 0

0 0

0 3

0 0

2 Group Point Total:

5

NUREG-1021, Revision 9 Supplement 1 SRO Page 5 of 6 FENOC Facsimile Rev. 1 ES-401 PWR Examination Outline Form ES-401-2 Davis-Besse 6/2013 Plant Systems - Tier 2/Group 2(SRO)

System # / Name K

1 K

2 K

3 K

4 K

5 K

6 A

1 A

2 A

3 A

4 G

K/A Topic(s)

IR Points 011 Pressurizer Level Control System (PZR LCS)

Question 91 X

A2.07 Ability to (a) predict the impacts of the following malfunctions or operations on the PZR LCS; and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Isolation of letdown (CFR: 41.5 / 43.5 / 45.3 / 45.13) 3.3 1

015 Nuclear Instrumentation System Question 92 X

A2.01 Ability to (a) predict the impacts of the following malfunctions or operations on the NIS; and (b based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Power supply loss or erratic operation (CFR: 41.5 / 43.5 / 45.3 / 45.5) 3.9 1

033 Spent Fuel Pool Cooling System (SFPCS)

Question 93 X 2.1.20 Ability to interpret and execute procedure steps.

(CFR: 41.10 / 43.5 / 45.12) 4.6 1

K/A Category Point Totals:

0 0

0 0

0 0

0 2

0 0

1 Group Point Total:

3

NUREG-1021, Revision 9 Supplement 1 SRO Page 6 of 6 FENOC Facsimile Rev. 1 ES 401 Generic Knowledge and Abilities Outline (Tier 3)

Form ES-401-3 Facility: Davis-Besse SRO Date of Exam 6/3 thru 6/14 2013 Category K/A#

Topic RO SRO Only IR IR

1.

Conduct of Operations 2.1.42 Knowledge of new and spent fuel movement procedures. (CFR: 41.10 /

43.7 / 45.13)

Question 94 3.4 1

Subtotal 1

2.

Equipment Control 2.2.1 Ability to perform pre-startup procedures for the facility, including operating those controls associated with plant equipment that could affect reactivity. (CFR: 41.5 / 41.10 / 43.5 / 43.6 / 45.1)

Question 95 4.4 1

2.2.18 Knowledge of the process for managing maintenance activities during shutdown operations, such as risk assessments, work prioritization, etc.(CFR: 41.10 / 43.5 / 45.13)

Question 96 3.9 1

Subtotal 2

3.

Radiation Control 2.3.6 Ability to approve release permits. (CFR: 41.13 / 43.4 / 45.10)

Question 97 3.8 1

2.3.15 Knowledge of radiation monitoring systems, such as fixed radiation monitors and alarms, portable survey instruments, personnel monitoring equipment, etc. (CFR: 41.12 / 43.4 / 45.9)

Question 98 3.1 1

Subtotal 2

4.

Emergency Procedures/

Plan 2.4.27 Knowledge of fire in the plant procedures. (CFR: 41.10 / 43.5 / 45.13)

Question 99 3.9 1

2.4.44 Knowledge of emergency plan protective action recommendations.

(CFR: 41.10 / 41.12 / 43.5 / 45.11)

Question 100 4.4 1

Subtotal 2

Tier 3 Point Total 7