ML13309A859: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(StriderTol Bot change)
 
(4 intermediate revisions by the same user not shown)
Line 9: Line 9:
| docket = 05000395, 05200027, 05200028
| docket = 05000395, 05200027, 05200028
| license number =  
| license number =  
| contact person = Bloom S D, NRO/DCIP/IGCB, 415-2431
| contact person = Bloom S, NRO/DCIP/IGCB, 415-2431
| document type = Meeting Briefing Package/Handouts, Slides and Viewgraphs
| document type = Meeting Briefing Package/Handouts, Slides and Viewgraphs
| page count = 26
| page count = 26
}}
}}
=Text=
{{#Wiki_filter:V C Summer Construction Status V C Summer Construction Status and Lesson Learned AD Torres
Unit 2 & 3 Construction Status
j il Major Milestones
* Completed Unit 2 Concrete Basemat
* Unit 2 Pouring of Major Auxiliary Building Walls
* Set U2 containment vessel bottom head F b i d
d S U2 C d
d T bi Bld S l
* Fabricated and Set U2 Condensers and Turbine Bld Steel
* Fabricated and Set Reactor Cavity Module
* Received Unit 2 Reactor vessel on site
* Received Unit 2 Reactor vessel on site
* Installed Unit 3 basemat rebar and completed Basemat Pour
i i
l
(
)
Unit 2 First Nuclear Concrete (FNC)
* First safety-related nuclear concrete nuclear concrete placed in over 30 years
* 7,000 yds3 of continuously placed concrete concrete
* Placement began on March 9, 2011 and l
t d i
t l lasted approximately 52 hours
Setting of U2 CR10
Setting of Unit2 Containment Vessel Bottom Head g
(CVBH)
*Set Date: 05/22/13
*Design Weight: 936 Tons
*Linear Feet of Weld: 2,253 Li F
t f R i
d W ld 22
*Linear Feet of Repaired Weld: 22
* Weld Acceptance Rate: 99.02%
Setting of U2 CVBH g
U2 Containment Vessel (CV) Rings U2 Containment Vessel (CV) Rings CV Lower Ring is made up of:
F C
* Four Courses
*A lower and an Upper Equipment Hatch
*A lower and an Upper Personnel Hatch ff
* An external Stiffener CV Lower Ring CV Middle Ring is made up of:
* Four Courses
*An internal Stiffener CV Middle Ring An internal Stiffener
U2 Containment Vessel Ring 1 Coatings g
g Steel surface preparation for inorganic zinc application Inorganic zinc application in progress on U2 CV Ring 1
Unit 3 Containment Vessel Bottom Head (CVBH)
Unit 3 Containment Vessel Bottom Head (CVBH)
June 2013 October 2013 October 2013
Inside Containment CB65 R
t C
l t D i T k R CB66 RCDT/ R t
C t
t P CB65 - Reactor Coolant Drain Tank Room CB66 - RCDT/ Reactor Compartment Passageway CB65 CA04 CB66
Unit 2 CA04 Module
* Reactor Vessel Cavity
* Dimensions: 21-0 W x 26-6 H
* Approx. Design Weight: 90,000 lbs.
* Approx. 7,661 linear feet of weld
* Installed 1 436 shear studs Installed 1,436 shear studs
Unit 2 CA04 Module
* Lift and set with the Heavy Lift Derrick (HLD)
* Date: 09/27/13 Date: 09/27/13
U i 2 A ili W ll Pl Unit 2 Auxiliary Wall Placements 16 feet tall 3 feet thick 16 feet tall, 3 feet thick Top Elevation is 826 Line I, Area 5 completed 8/24/13 Line I, Area 2-3 completed 9/28/13 9/28/13 Line I, Area 4-7 completed 10/17/13
Unit 2 Aux Building Rebar Installation Column Lines I, 2, 4, 5, 11, and Q, up to El 82 6 is substantially complete Column Line Q Column Line 11 looking east to west Column Line Q Column Line 11, looking east to west.
U2 TB Major Component Installation j
p Condenser B Lower Shell July 2013 700 Tons South TG Support CH80 August 2013 South TG Support CH80 August 2013 650 Tons
U2 TB Major Component Installation j
p Center TG Support CH81A C
t TG S t CH81B Center TG Support CH81A October 2013 220 Tons Center TG Support CH81B October 2013 220 Tons
U2 TB Major Equipment Deliveries j
q p Deaerator MSR LP Turbine Rotor
Unit 3 Basemat Unit 3 Basemat Unit 3 Basemat in June 2013 Unit 3 Basemat in Oct 2013
U i 3 B R b I
ll i
Unit 3 Basemat Rebar Installation Shield Building Rebar, looking North to South Battery Room Rebar, looking west to east North to South west to east
U i 3 B Unit 3 Base mat pour
Unit 2 CA20 Module Unit 2 CA20 Module
* Approx. 85% of sub-modules have been d li d
delivered
* Assembly is ongoing within the Module Assembly Building (MAB)
* To date 11 wall sub-modules have been erected on the platen
Toshiba Main Step Up Transformers - 230/26kV Toshiba Main Step Up Transformers 230/26kV Assembly weight with oil - 529,800lbs each Main Tanks
* 3 in service, 1 spare
* 12,720 gallons each
* Stored Air Filled Conservator Tanks
* Oil reservoir
* 730 gallons each
* Stored Air Filled Stored Air Filled Stored Air Filled
VC Summer Units 2 and 3 Switchyard VC Summer Units 2 and 3 Switchyard
* Online February 12, 2013
* Connection of 230kV transmission lines for SCE&G, and Santee Cooper
* Largest switchyard in the SCE&G System g
y y
L L
d Lesson Learned C
di ti f
t h l d
t d
* Coordination of groups to help understand ITAAC
* Strengthening the procedural controls of ITAAC programs
- Roles and responsibilities for groups
- Stakeholder buy in
* Review of corrective action programs
L L
d Lesson Learned U d t
di d
di ti f ITAAC i
* Understanding and coordination of ITAAC issues away from site.
- Vendor inspections(NRC and Consortium)
- Vendor corrective actions that have a material ff ITAAC effect ITAAC
* Development of a common understanding of what is meant by material effects on an ITAACs acceptance criteria.}}

Latest revision as of 03:42, 11 January 2025

V. C. Summer Construction Status and Lesson Learned AD Torres
ML13309A859
Person / Time
Site: Summer  South Carolina Electric & Gas Company icon.png
Issue date: 11/05/2013
From:
South Carolina Electric & Gas Co
To:
Office of New Reactors
Bloom S, NRO/DCIP/IGCB, 415-2431
References
Download: ML13309A859 (26)


Text

V C Summer Construction Status V C Summer Construction Status and Lesson Learned AD Torres

Unit 2 & 3 Construction Status

j il Major Milestones

  • Completed Unit 2 Concrete Basemat
  • Unit 2 Pouring of Major Auxiliary Building Walls
  • Set U2 containment vessel bottom head F b i d

d S U2 C d

d T bi Bld S l

  • Fabricated and Set U2 Condensers and Turbine Bld Steel
  • Fabricated and Set Reactor Cavity Module
  • Received Unit 2 Reactor vessel on site
  • Received Unit 2 Reactor vessel on site
  • Installed Unit 3 basemat rebar and completed Basemat Pour

i i

l

(

)

Unit 2 First Nuclear Concrete (FNC)

  • First safety-related nuclear concrete nuclear concrete placed in over 30 years
  • 7,000 yds3 of continuously placed concrete concrete
  • Placement began on March 9, 2011 and l

t d i

t l lasted approximately 52 hours6.018519e-4 days <br />0.0144 hours <br />8.597884e-5 weeks <br />1.9786e-5 months <br />

Setting of U2 CR10

Setting of Unit2 Containment Vessel Bottom Head g

(CVBH)

  • Set Date: 05/22/13
  • Design Weight: 936 Tons
  • Linear Feet of Weld: 2,253 Li F

t f R i

d W ld 22

  • Linear Feet of Repaired Weld: 22
  • Weld Acceptance Rate: 99.02%

Setting of U2 CVBH g

U2 Containment Vessel (CV) Rings U2 Containment Vessel (CV) Rings CV Lower Ring is made up of:

F C

  • Four Courses
  • A lower and an Upper Equipment Hatch
  • A lower and an Upper Personnel Hatch ff
  • An external Stiffener CV Lower Ring CV Middle Ring is made up of:
  • Four Courses

U2 Containment Vessel Ring 1 Coatings g

g Steel surface preparation for inorganic zinc application Inorganic zinc application in progress on U2 CV Ring 1

Unit 3 Containment Vessel Bottom Head (CVBH)

Unit 3 Containment Vessel Bottom Head (CVBH)

June 2013 October 2013 October 2013

Inside Containment CB65 R

t C

l t D i T k R CB66 RCDT/ R t

C t

t P CB65 - Reactor Coolant Drain Tank Room CB66 - RCDT/ Reactor Compartment Passageway CB65 CA04 CB66

Unit 2 CA04 Module

  • Reactor Vessel Cavity
  • Dimensions: 21-0 W x 26-6 H
  • Approx. Design Weight: 90,000 lbs.
  • Approx. 7,661 linear feet of weld
  • Installed 1 436 shear studs Installed 1,436 shear studs

Unit 2 CA04 Module

  • Lift and set with the Heavy Lift Derrick (HLD)
  • Date: 09/27/13 Date: 09/27/13

U i 2 A ili W ll Pl Unit 2 Auxiliary Wall Placements 16 feet tall 3 feet thick 16 feet tall, 3 feet thick Top Elevation is 826 Line I, Area 5 completed 8/24/13 Line I, Area 2-3 completed 9/28/13 9/28/13 Line I, Area 4-7 completed 10/17/13

Unit 2 Aux Building Rebar Installation Column Lines I, 2, 4, 5, 11, and Q, up to El 82 6 is substantially complete Column Line Q Column Line 11 looking east to west Column Line Q Column Line 11, looking east to west.

U2 TB Major Component Installation j

p Condenser B Lower Shell July 2013 700 Tons South TG Support CH80 August 2013 South TG Support CH80 August 2013 650 Tons

U2 TB Major Component Installation j

p Center TG Support CH81A C

t TG S t CH81B Center TG Support CH81A October 2013 220 Tons Center TG Support CH81B October 2013 220 Tons

U2 TB Major Equipment Deliveries j

q p Deaerator MSR LP Turbine Rotor

Unit 3 Basemat Unit 3 Basemat Unit 3 Basemat in June 2013 Unit 3 Basemat in Oct 2013

U i 3 B R b I

ll i

Unit 3 Basemat Rebar Installation Shield Building Rebar, looking North to South Battery Room Rebar, looking west to east North to South west to east

U i 3 B Unit 3 Base mat pour

Unit 2 CA20 Module Unit 2 CA20 Module

  • Approx. 85% of sub-modules have been d li d

delivered

  • Assembly is ongoing within the Module Assembly Building (MAB)
  • To date 11 wall sub-modules have been erected on the platen

Toshiba Main Step Up Transformers - 230/26kV Toshiba Main Step Up Transformers 230/26kV Assembly weight with oil - 529,800lbs each Main Tanks

  • 3 in service, 1 spare
  • 12,720 gallons each
  • Stored Air Filled Conservator Tanks
  • Oil reservoir
  • 730 gallons each
  • Stored Air Filled Stored Air Filled Stored Air Filled

VC Summer Units 2 and 3 Switchyard VC Summer Units 2 and 3 Switchyard

  • Online February 12, 2013
  • Connection of 230kV transmission lines for SCE&G, and Santee Cooper

y y

L L

d Lesson Learned C

di ti f

t h l d

t d

  • Coordination of groups to help understand ITAAC
  • Strengthening the procedural controls of ITAAC programs

- Roles and responsibilities for groups

- Stakeholder buy in

  • Review of corrective action programs

L L

d Lesson Learned U d t

di d

di ti f ITAAC i

  • Understanding and coordination of ITAAC issues away from site.

- Vendor inspections(NRC and Consortium)

- Vendor corrective actions that have a material ff ITAAC effect ITAAC

  • Development of a common understanding of what is meant by material effects on an ITAACs acceptance criteria.