{{Adams | {{Adams | ||
| number = | | number = ML14013A195 | ||
| issue date = | | issue date = 01/13/2014 | ||
| title = | | title = Er 05000269/13-302, 05000270/13-302 & 05000287/13-302, December 9 - 12, 2013 - December 18, 2013, Oconee, Rev 0 | ||
| author name = Widmann M | | author name = Widmann M | ||
| author affiliation = NRC/RGN-II/DRS | | author affiliation = NRC/RGN-II/DRS | ||
| addressee name = | | addressee name = Batson S | ||
| addressee affiliation = Duke Energy | | addressee affiliation = Duke Energy Carolinas, LLC | ||
| docket = 05000269, 05000270, 05000287 | | docket = 05000269, 05000270, 05000287 | ||
| license number = DPR-038, DPR-047, DPR-055 | | license number = DPR-038, DPR-047, DPR-055 | ||
| contact person = | | contact person = J. Calloway 404-997-4602 entered by lxg2 | ||
| | | document report number = 50-269/13-302, 50-270/13-302, 50-287/13-302 | ||
| document type = Letter, License-Operator | | document type = Letter, License-Operator Examination Report | ||
| page count = | | page count = 9 | ||
}} | }} | ||
| Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter: | {{#Wiki_filter:January 13, 2014 | ||
==SUBJECT:== | |||
OCONEE NUCLEAR STATION - NRC EXAMINATION REPORT | |||
05000269/2013302, 05000270/2013302 AND 05000287/2013302 | |||
==Dear Mr. Batson:== | |||
During the period December 9 - 12, 2013, the Nuclear Regulatory Commission (NRC) | |||
administered operating tests to employees of your company who had applied for licenses to operate the Oconee Nuclear Station. At the conclusion of the tests, the examiners discussed preliminary findings related to the operating tests and the written examination submittal with those members of your staff identified in the enclosed report. The written examination was administered by your staff on December 18, 2013. | |||
Seven Reactor Operator (RO) and five Senior Reactor Operator (SRO) applicants passed both the operating test and written examination. There were no post-administration comments. A Simulator Fidelity Report is included in this report as Enclosure 2. | |||
The | The initial examination operating test submittal was within the range of acceptability expected for a proposed examination. All examination changes agreed upon between the NRC and your staff were made according to NUREG-1021, Operator Licensing Examination Standards for Power Reactors, Revision 9, Supplement 1. | ||
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). If you have any questions concerning this letter, please contact me at (404) 997-4550. | |||
Sincerely, | |||
/RA/ | |||
Malcolm T. Widmann, Chief | |||
Operations Branch 1 | |||
Division of Reactor Safety | |||
Docket Nos.: 50-269, 50-270, 50-287 License Nos.: DPR-38, DPR-47, DPR-55 | |||
===Enclosures:=== | |||
1. Report Details 2. Simulator Fidelity Report | |||
REGION II== | |||
Docket Nos.: | |||
05000269, 05000270, 05000287 | |||
License Nos.: | |||
DPR-38, DPR-47 and DPR-55 | |||
Report No.: | |||
05000269/2013302, 05000270/2013302 and 05000287/2013302 | |||
Licensee: | |||
Duke Energy Carolinas LLC. | |||
Facility: | |||
Oconee Nuclear Station, Units 1, 2, and 3 | |||
Location: | |||
Seneca, SC | |||
Dates: | |||
Operating Tests - December 9 - 12, 2013 | |||
Written Examination - December 18, 2013 | |||
Examiners: | |||
P. Capehart, Chief, Senior Operations Examiner | |||
M. Bates, Senior Operations Engineer | |||
D. Lanyi, Operations Engineer | |||
D. Bacon, Operations Engineer | |||
Approved by: | |||
Malcolm T. Widmann, Chief Operations Branch 1 Division of Reactor Safety | Malcolm T. Widmann, Chief Operations Branch 1 Division of Reactor Safety | ||
SUMMARY OF FINDINGS | |||
ER 05000269/2013302; 05000270/2013302; 05000287/2013302; operating test December 9 - | |||
12, 2013 & written exam December 18, 2013; Oconee Nuclear Station, Units 1, 2, and 3; Operator License Examinations. | |||
Nuclear Regulatory Commission (NRC) examiners conducted an initial examination in accordance with the guidelines in Revision 9, Supplement 1, of NUREG-1021, Operator Licensing Examination Standards for Power Reactors. This examination implemented the operator licensing requirements identified in 10 CFR §55.41, §55.43, and §55.45 as applicable. | |||
Members of the Oconee Nuclear Station staff developed the operating tests and the written examination. The NRC developed the written examination outlines. | |||
The NRC administered the operating tests during the period of December 9 - 12, 2013. | |||
Members of the Oconee Nuclear Station training staff administered the written examination December 18, 2013. Seven Reactor Operator (RO) and five Senior Reactor Operator (SRO) | |||
applicants passed both the written examination and operating test. Twelve applicants were issued licenses commensurate with the level of examination administered. | |||
There were no post-examination comments. | |||
No findings were identified. | |||
Report Details | |||
4. | |||
OTHER ACTIVITIES | |||
4OA5 Operator Licensing Initial Examinations | |||
a. | |||
Inspection Scope | |||
Members of the Oconee Nuclear Station staff developed both the operating tests and the written examination. All examination material was developed in accordance with the guidelines contained in Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors." The NRC examination team reviewed the proposed examination. Examination changes agreed upon between the NRC and the licensee were made per NUREG-1021, and incorporated into the final version of the examination materials. | |||
The examiners reviewed the licensees examination security measures while preparing and administering the examinations to ensure examination security and integrity complied with 10 CFR 55.49, Integrity of Examinations and Tests. | |||
The NRC examiners evaluated seven Reactor Operator (RO) and five Senior Reactor Operator (SRO) applicants using the guidelines contained in NUREG-1021. The examiners administered the operating tests during the period of December 9 - 12, 2013. | |||
Members of the Oconee Nuclear Station training staff administered the written examination on December 18, 2013. Evaluations of applicants and reviews of associated documentation were performed to determine if the applicants, who applied for licenses to operate the Oconee Nuclear Station, met the requirements specified in 10 CFR Part 55, Operators Licenses. | |||
b. | |||
Findings | |||
No findings were identified. The NRC determined that, using NUREG-1021, the licensees initial operating test examination submittal was within the range of acceptability expected for a proposed examination. | |||
Seven RO and five SRO applicants passed both the operating test and written examination. Twelve licenses were issued. | |||
Copies of all individual examination reports were sent to the facility Training Manager for evaluation of weaknesses and determination of appropriate remedial training. | |||
The licensee did not submit any post-examination comments. A copy of the final written examination and answer key may be accessed not earlier than December 18, 2015, in the ADAMS system (ADAMS Accession Number ML13364A335 and ML13364A337). | |||
4OA6 Meetings | |||
Exit Meeting Summary | |||
On December 12, 2013, the NRC examination team discussed generic issues associated with the operating test with Mr. S. Batson, Oconee Plant Vice President, and members of his staff. The examiners asked the licensee if any of the examination material was proprietary. No proprietary information was identified. | |||
PARTIAL LIST OF PERSONS CONTACTED | |||
Licensee personnel | |||
T. Doss, ILT Supervisor P. Fisk, Operations Manager L. Nowell, Supervisor Nuclear OPS Training T. Ray, Oconee Plant Manager C. Rop, Operations Training Manager J. Smith, Licensing Administrator J. Steely, Nuclear Training Manager G. Washburn, Nuclear Station Instructor - Operations K. Welchel, Simulator Supervisor C. Witherspoon, Sr. Operations Specialist | |||
NRC personnel | |||
E. Crowe, Senior Resident Inspector | |||
Enclosure 2 SIMULATOR FIDELITY REPORT | |||
Facility Licensee: Oconee Nuclear Station | |||
Facility Docket No.: 05000269, 05000270, AND 05000287 | |||
Operating Test Administered: December 9 - 12, 2013 | |||
This form is to be used only to report observations. These observations do not constitute audit or inspection findings and, without further verification and review in accordance with Inspection Procedure 71111.11, are not indicative of noncompliance with 10 CFR 55.46. No licensee action is required in response to these observations. | |||
No simulator fidelity or configuration issues were identified. | |||
}} | }} | ||
Latest revision as of 23:56, 10 January 2025
| ML14013A195 | |
| Person / Time | |
|---|---|
| Site: | Oconee |
| Issue date: | 01/13/2014 |
| From: | Widmann M Division of Reactor Safety II |
| To: | Batson S Duke Energy Carolinas |
| J. Calloway 404-997-4602 entered by lxg2 | |
| References | |
| 50-269/13-302, 50-270/13-302, 50-287/13-302 | |
| Download: ML14013A195 (9) | |
Text
January 13, 2014
SUBJECT:
OCONEE NUCLEAR STATION - NRC EXAMINATION REPORT
05000269/2013302, 05000270/2013302 AND 05000287/2013302
Dear Mr. Batson:
During the period December 9 - 12, 2013, the Nuclear Regulatory Commission (NRC)
administered operating tests to employees of your company who had applied for licenses to operate the Oconee Nuclear Station. At the conclusion of the tests, the examiners discussed preliminary findings related to the operating tests and the written examination submittal with those members of your staff identified in the enclosed report. The written examination was administered by your staff on December 18, 2013.
Seven Reactor Operator (RO) and five Senior Reactor Operator (SRO) applicants passed both the operating test and written examination. There were no post-administration comments. A Simulator Fidelity Report is included in this report as Enclosure 2.
The initial examination operating test submittal was within the range of acceptability expected for a proposed examination. All examination changes agreed upon between the NRC and your staff were made according to NUREG-1021, Operator Licensing Examination Standards for Power Reactors, Revision 9, Supplement 1.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). If you have any questions concerning this letter, please contact me at (404) 997-4550.
Sincerely,
/RA/
Malcolm T. Widmann, Chief
Operations Branch 1
Division of Reactor Safety
Docket Nos.: 50-269, 50-270, 50-287 License Nos.: DPR-38, DPR-47, DPR-55
Enclosures:
1. Report Details 2. Simulator Fidelity Report
REGION II==
Docket Nos.:
05000269, 05000270, 05000287
License Nos.:
Report No.:
05000269/2013302, 05000270/2013302 and 05000287/2013302
Licensee:
Duke Energy Carolinas LLC.
Facility:
Oconee Nuclear Station, Units 1, 2, and 3
Location:
Seneca, SC
Dates:
Operating Tests - December 9 - 12, 2013
Written Examination - December 18, 2013
Examiners:
P. Capehart, Chief, Senior Operations Examiner
M. Bates, Senior Operations Engineer
D. Lanyi, Operations Engineer
D. Bacon, Operations Engineer
Approved by:
Malcolm T. Widmann, Chief Operations Branch 1 Division of Reactor Safety
SUMMARY OF FINDINGS
ER 05000269/2013302; 05000270/2013302; 05000287/2013302; operating test December 9 -
12, 2013 & written exam December 18, 2013; Oconee Nuclear Station, Units 1, 2, and 3; Operator License Examinations.
Nuclear Regulatory Commission (NRC) examiners conducted an initial examination in accordance with the guidelines in Revision 9, Supplement 1, of NUREG-1021, Operator Licensing Examination Standards for Power Reactors. This examination implemented the operator licensing requirements identified in 10 CFR §55.41, §55.43, and §55.45 as applicable.
Members of the Oconee Nuclear Station staff developed the operating tests and the written examination. The NRC developed the written examination outlines.
The NRC administered the operating tests during the period of December 9 - 12, 2013.
Members of the Oconee Nuclear Station training staff administered the written examination December 18, 2013. Seven Reactor Operator (RO) and five Senior Reactor Operator (SRO)
applicants passed both the written examination and operating test. Twelve applicants were issued licenses commensurate with the level of examination administered.
There were no post-examination comments.
No findings were identified.
Report Details
4.
OTHER ACTIVITIES
4OA5 Operator Licensing Initial Examinations
a.
Inspection Scope
Members of the Oconee Nuclear Station staff developed both the operating tests and the written examination. All examination material was developed in accordance with the guidelines contained in Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors." The NRC examination team reviewed the proposed examination. Examination changes agreed upon between the NRC and the licensee were made per NUREG-1021, and incorporated into the final version of the examination materials.
The examiners reviewed the licensees examination security measures while preparing and administering the examinations to ensure examination security and integrity complied with 10 CFR 55.49, Integrity of Examinations and Tests.
The NRC examiners evaluated seven Reactor Operator (RO) and five Senior Reactor Operator (SRO) applicants using the guidelines contained in NUREG-1021. The examiners administered the operating tests during the period of December 9 - 12, 2013.
Members of the Oconee Nuclear Station training staff administered the written examination on December 18, 2013. Evaluations of applicants and reviews of associated documentation were performed to determine if the applicants, who applied for licenses to operate the Oconee Nuclear Station, met the requirements specified in 10 CFR Part 55, Operators Licenses.
b.
Findings
No findings were identified. The NRC determined that, using NUREG-1021, the licensees initial operating test examination submittal was within the range of acceptability expected for a proposed examination.
Seven RO and five SRO applicants passed both the operating test and written examination. Twelve licenses were issued.
Copies of all individual examination reports were sent to the facility Training Manager for evaluation of weaknesses and determination of appropriate remedial training.
The licensee did not submit any post-examination comments. A copy of the final written examination and answer key may be accessed not earlier than December 18, 2015, in the ADAMS system (ADAMS Accession Number ML13364A335 and ML13364A337).
4OA6 Meetings
Exit Meeting Summary
On December 12, 2013, the NRC examination team discussed generic issues associated with the operating test with Mr. S. Batson, Oconee Plant Vice President, and members of his staff. The examiners asked the licensee if any of the examination material was proprietary. No proprietary information was identified.
PARTIAL LIST OF PERSONS CONTACTED
Licensee personnel
T. Doss, ILT Supervisor P. Fisk, Operations Manager L. Nowell, Supervisor Nuclear OPS Training T. Ray, Oconee Plant Manager C. Rop, Operations Training Manager J. Smith, Licensing Administrator J. Steely, Nuclear Training Manager G. Washburn, Nuclear Station Instructor - Operations K. Welchel, Simulator Supervisor C. Witherspoon, Sr. Operations Specialist
NRC personnel
E. Crowe, Senior Resident Inspector
Enclosure 2 SIMULATOR FIDELITY REPORT
Facility Licensee: Oconee Nuclear Station
Facility Docket No.: 05000269, 05000270, AND 05000287
Operating Test Administered: December 9 - 12, 2013
This form is to be used only to report observations. These observations do not constitute audit or inspection findings and, without further verification and review in accordance with Inspection Procedure 71111.11, are not indicative of noncompliance with 10 CFR 55.46. No licensee action is required in response to these observations.
No simulator fidelity or configuration issues were identified.