{{#Wiki_filter:July 28, 2015 Docket No.
{{#Wiki_filter:July 28, 2015


05000302License No.
==SUBJECT:==
 
NRC INSPECTION REPORT NO. 05000302/2015008, DUKE ENERGY FLORIDA, INC., CRYSTAL RIVER UNIT 3, CRYSTAL RIVER, FLORIDA
DPR-72 Terry Hobbs Decommissioning General Manager Duke Energy Florida, Inc.
 
Crystal River Unit 3 15760 W. Power Line Road Crystal River, FL 34428-6708 SUBJECT: NRC INSPECTION REPORT NO. 05000302/2015008, DUKE ENERGY FLORIDA, INC., CRYSTAL RIVER UNIT 3, CRYSTAL RIVER, FLORIDA


==Dear Mr. Hobbs:==
==Dear Mr. Hobbs:==
On June 30, 2015, the U.S. Nuclear Regulatory Commission (NRC) completed its quarterly inspection under Inspection Manual Chapter 2561, "Decommissioning Power Reactor Inspection Program," at the permanently shut down Crystal River Nuclear Plant Unit 3 (CR-3). On-site inspections were performed on May 4-7 and June 22-25, 2015. In-office reviews of information supplied by Duke Energy Florida, Inc. were also performed during the inspection period.
On June 30, 2015, the U.S. Nuclear Regulatory Commission (NRC) completed its quarterly inspection under Inspection Manual Chapter 2561, Decommissioning Power Reactor Inspection Program," at the permanently shut down Crystal River Nuclear Plant Unit 3 (CR-3). On-site inspections were performed on May 4-7 and June 22-25, 2015. In-office reviews of information supplied by Duke Energy Florida, Inc. were also performed during the inspection period. The inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations, and the conditions of your license.


The inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations, and the conditions of your license. The inspection consisted of observations by the inspectors, interviews with personnel, and a review of procedures and records. The results of the inspection were discussed with you and other members of the CR-3 staff on July 8, 2015, and are described in the enclosed report.
The inspection consisted of observations by the inspectors, interviews with personnel, and a review of procedures and records. The results of the inspection were discussed with you and other members of the CR-3 staff on July 8, 2015, and are described in the enclosed report.


Based on the results of this inspection, the NRC has determined that one licensee identified Severity Level IV violation of NRC requirements occurred. This violation is being treated as a Non-Cited Violation (NCV), consistent with Section 2.3.2 of the Enforcement Policy. The NCV is described in the subject inspection report. If you contest the violation or significance of the NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001, with copies to: (1) the Regional Administrator, Region I; (2) the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and (3) the NRC Senior Decommissioning Inspector, Region I.
Based on the results of this inspection, the NRC has determined that one licensee identified Severity Level IV violation of NRC requirements occurred. This violation is being treated as a Non-Cited Violation (NCV), consistent with Section 2.3.2 of the Enforcement Policy. The NCV is described in the subject inspection report. If you contest the violation or significance of the NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001, with copies to: (1) the Regional Administrator, Region I; (2) the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and (3) the NRC Senior Decommissioning Inspector, Region I.


In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure(s), and your response, will be made available electronically for public inspection in the NRC Public Document Room or from the NRC document system (ADAMS), accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response should not include any personal privacy, proprietary, or safeguards information so that it can be made available to the Public without redaction.
In accordance with 10 CFR 2.390 of the NRCs "Rules of Practice," a copy of this letter, its enclosure(s), and your response, will be made available electronically for public inspection in the NRC Public Document Room or from the NRC document system (ADAMS), accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response should not include any personal privacy, proprietary, or safeguards information so that it can be made available to the Public without redaction.


UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PA 19406-2713 Current NRC regulations and guidance are included on the NRC's website at www.nrc.gov; select Radioactive Waste; Decommissioning of Nuclear Facilities; then Regulations, Guidance and Communications. The current Enforcement Policy is included on the NRC's website at www.nrc.gov; select About NRC, Organizations & Functions; Office of Enforcement; Enforcement documents; then Enforcement Policy (Under 'Related Information'). You may also obtain these documents by contacting the Government Printing Office (GPO) toll-free at 1-866-512-1800. The GPO is open from 8:00 a.m. to 5:30 p.m. EST, Monday through Friday (except Federal holidays).
UNITED STATES NUCLEAR REGULATORY COMMISSION  
 
==REGION I==
2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PA 19406-2713 Current NRC regulations and guidance are included on the NRC's website at www.nrc.gov; select Radioactive Waste; Decommissioning of Nuclear Facilities; then Regulations, Guidance and Communications. The current Enforcement Policy is included on the NRC's website at www.nrc.gov; select About NRC, Organizations & Functions; Office of Enforcement; Enforcement documents; then Enforcement Policy (Under 'Related Information'). You may also obtain these documents by contacting the Government Printing Office (GPO) toll-free at 1-866-512-1800. The GPO is open from 8:00 a.m. to 5:30 p.m. EST, Monday through Friday (except Federal holidays).


No reply to this letter is required. Please contact Steve Hammann, at 610-337-5399, if you have any questions regarding this matter.
No reply to this letter is required. Please contact Steve Hammann, at 610-337-5399, if you have any questions regarding this matter.


Sincerely,
Sincerely,
/RA/ Marc S. Ferdas, Chief Decommissioning and Technical Support Branch Division of Nuclear Materials Safety Enclosure:
/RA/  
Inspection Report 05000302/2015008 cc w/encl:
 
State of Florida Distribution via ListServ
Marc S. Ferdas, Chief Decommissioning and Technical Support Branch Division of Nuclear Materials Safety  
 
Enclosure:
Inspection Report 05000302/2015008  
 
cc w/encl:
State of Florida  
 
Distribution via ListServ


=EXECUTIVE SUMMARY=
=EXECUTIVE SUMMARY=
Duke Energy  
Duke Energy  


Crystal River Nuclear Plant NRC Inspection Report No. 05000302/2015008 An announced quarterly inspection was completed at CR
Crystal River Nuclear Plant NRC Inspection Report No. 05000302/2015008  
-3 on June 30, 2015. O n-site inspection s were conducted on May 4-7, and June 22
-25, 2015. In-office reviews of information supplied by Duke Energy were also performed during the inspection period. The inspection included a review of operations
, management oversight, adverse weather preparations, radioactive effluent control, radiological environmental monitoring program (REMP), fire protection, and plant support activities.


The inspection consisted of observations by the inspectors, interviews with Duke Energy personnel, a review of procedures and records, and plant walk-downs. The NRC's program for overseeing the safe operation of a shut-down nuclear power reactor is described in Inspection Manual Chapter (IMC) 2561,  
An announced quarterly inspection was completed at CR-3 on June 30, 2015. On-site inspections were conducted on May 4-7, and June 22-25, 2015. In-office reviews of information supplied by Duke Energy were also performed during the inspection period. The inspection included a review of operations, management oversight, adverse weather preparations, radioactive effluent control, radiological environmental monitoring program (REMP), fire protection, and plant support activities. The inspection consisted of observations by the inspectors, interviews with Duke Energy personnel, a review of procedures and records, and plant walk-downs. The NRC's program for overseeing the safe operation of a shut-down nuclear power reactor is described in Inspection Manual Chapter (IMC) 2561,
"Decommissioning Power Reactor Inspection Program."
Decommissioning Power Reactor Inspection Program."


Based on the results of this inspection, a licens ee-identified Severity Level (SL) lV Non-Cited Violation (NCV)of CR-3 Technical Specifications (TS)5.6.2.17 , "Technical Specifications Bases Control Program
Based on the results of this inspection, a licensee-identified Severity Level (SL) lV Non-Cited Violation (NCV) of CR-3 Technical Specifications (TS) 5.6.2.17, Technical Specifications Bases Control Program, was identified. Duke Energy did not submit any TS Bases updates to the NRC from April 30, 2009 to May 27, 2015. This violation is being treated as a NCV, consistent with Section 2.3.2 of the Enforcement Policy. Because this violation resulted in no potential safety consequences and it was entered into CR-3s corrective action program (Condition Report (CR) 749664), this violation is being treated as an NCV, consistent with the NRC Enforcement Policy.
," was identified.


Duke Energy did not submit any TS Bases updates to the NRC from April 30, 2009 to May 27, 2015. This violation is being treated as a NCV, consistent with Section 2.3.2 of the Enforcement Policy.
Inspection Report No. 05000302/2015008 C:\\Users\\ajk\\Documents\\LDPR-72.2015008.docx


Because this violation resulted in no potential safety consequences and it was entered into CR
=REPORT DETAILS=
-3's corrective action program (Condition Report (CR) 749664), this violation is being treated as an NCV, consistent with the NRC Enforcement Policy.


1 Inspection Report No. 05000302/2015008 C:\Users\ajk\Documents\LDPR-72.2015008.docx
1.0 Background


=REPORT DETAILS=
On February 20, 2013, Duke Energy sent a letter (Agency Documentation and Management System (ADAMS) Accession Number: ML13056A005) to the NRC certifying the permanent cessation of activities and certifying that the fuel had been permanently removed from the reactor. This met the requirements of 10 CFR 50.82(a)(1)(i) and 50.82(a)(1)(ii). As of the end of the reporting period, CR-3 was in the Post Operation Transitional Phase of decommissioning as described in IMC 2561.
 
1.0  Background On February 20, 2013, Duke Energy sent a letter (Agency Documentation and Management System (ADAMS) Accession Number
: ML13056A005) to the NRC certifying the permanent cessation of activities and certifying that the fuel had been permanently removed from the reactor. This met the requirements of 10 CFR 50.82(a)(1)(i) and 50.82(a)(1)(ii). As of the end of the reporting period, CR-3 was in the "Post Operation Transitional Phase" of decommissioning as described in IMC 2561.


2.0 Post Operation Transition Phase Performance and Status Review
2.0 Post Operation Transition Phase Performance and Status Review


====a. Inspection Scope====
====a. Inspection Scope====
(Inspection Procedures (IPs) 36801, 37801, 40801, 60801, 71801, 84750)   The inspectors performed a n on-site inspection the week of June 22
(Inspection Procedures (IPs) 36801, 37801, 40801, 60801, 71801, 84750)  
-26, 2015. In-office reviews of information supplied by Duke Energy were also performed during the inspection period.
 
The inspection consisted of observations by the inspectors, interviews with Duke Energy personnel, a review of procedures and records, and plant walk-downs.


The inspectors assessed management oversight of the site's transition to decommissioning status. The inspectors reviewed the sites organization, staffing levels, and personnel qualifications to ensure the safe storage of radioactive materials would not be adversely impacted by organization changes. The inspectors reviewed schedule and scope changes to assess the potential impact on the information contained in CR-3's Post-Shutdown Decommissioning Activities Report (PSDAR) and to ensure changes we re consistent with NRC regulations and guidance.
The inspectors performed an on-site inspection the week of June 22-26, 2015. In-office reviews of information supplied by Duke Energy were also performed during the inspection period. The inspection consisted of observations by the inspectors, interviews with Duke Energy personnel, a review of procedures and records, and plant walk-downs.


The inspectors reviewed the status of system and equipment abandonment activities and plant modifications being made to support CR
The inspectors assessed management oversight of the sites transition to decommissioning status. The inspectors reviewed the sites organization, staffing levels, and personnel qualifications to ensure the safe storage of radioactive materials would not be adversely impacted by organization changes. The inspectors reviewed schedule and scope changes to assess the potential impact on the information contained in CR-3s Post-Shutdown Decommissioning Activities Report (PSDAR) and to ensure changes were consistent with NRC regulations and guidance.
-3's transition to SAFSTOR status. The inspectors also reviewed CR
-3's proposed plans for changes to the reactor building ventilation system (REG-0100, Attachment 1
- Screen, "Partial Abandonment of the RB Purge System," Revision 3).


The inspectors reviewed the CR
The inspectors reviewed the status of system and equipment abandonment activities and plant modifications being made to support CR-3s transition to SAFSTOR status.
-3 requirements for submitting changes to the TS bases to the NRC as required by the regulations and TS 5.6.2.17, "Technical Specifications Bases Control Program.


The inspectors also reviewed corrective action reports to determine if issues were being properly assessed, reviewed, prioritized, and corrective actions were being appropriately implemented.
The inspectors also reviewed CR-3s proposed plans for changes to the reactor building ventilation system (REG-0100, Attachment 1 - Screen, Partial Abandonment of the RB Purge System, Revision 3).


The inspector s observed spent fuel sipping activities being performed. The inspectors reviewed the equipment setup and evaluated CR-3's adherence to procedures, supervisory oversight, and communication and coordination. The inspector reviewed procedures, move sheets, and radiation work permit (RWP) associated with the spent fuel sipping campaign.
The inspectors reviewed the CR-3 requirements for submitting changes to the TS bases to the NRC as required by the regulations and TS 5.6.2.17, Technical Specifications Bases Control Program. The inspectors also reviewed corrective action reports to determine if issues were being properly assessed, reviewed, prioritized, and corrective actions were being appropriately implemented.


Inspection Report No. 05000302/2015008 C:\Users\ajk\Documents\LDPR-72.2015008.docx The inspectors evaluated CR
The inspectors observed spent fuel sipping activities being performed. The inspectors reviewed the equipment setup and evaluated CR-3s adherence to procedures, supervisory oversight, and communication and coordination. The inspector reviewed procedures, move sheets, and radiation work permit (RWP) associated with the spent fuel sipping campaign.
-3's readiness for adverse weather (flooding and hurricanes). The inspectors performed a walk
-down of the site, reviewed procedures and completed work orders to verify the CR
-3 flooding mitigation plans and supplies were consistent with design requirements and risk analysis assumptions.


The inspectors verified that sandbags, equipment, and supplies were properly staged as required by CR
Inspection Report No. 05000302/2015008 C:\\Users\\ajk\\Documents\\LDPR-72.2015008.docx The inspectors evaluated CR-3s readiness for adverse weather (flooding and hurricanes). The inspectors performed a walk-down of the site, reviewed procedures and completed work orders to verify the CR-3 flooding mitigation plans and supplies were consistent with design requirements and risk analysis assumptions. The inspectors verified that sandbags, equipment, and supplies were properly staged as required by CR-3 procedure EM-220D, Violent Weather (Permanently Defueled).
-3 procedure EM
-220D, "Violent Weather (Permanently Defueled)."


The inspectors reviewed documentation associated with radioactive effluent control and site radiological environmental monitoring program (REMP) to determine the effectiveness of site radiological programs. The inspectors reviewed procedures, diagrams of effluent monitoring systems, liquid effluent release analysis (SDT-1, L-2015-0014; WDT-11A, and L-2015-0012), annual REMP report, annual effluent report, and the Off-Site Dose Calculation Manual (ODCM). The inspectors performed a walkdown of groundwater monitoring wells and site liquid and gaseous effluent monitoring points.
The inspectors reviewed documentation associated with radioactive effluent control and site radiological environmental monitoring program (REMP) to determine the effectiveness of site radiological programs. The inspectors reviewed procedures, diagrams of effluent monitoring systems, liquid effluent release analysis (SDT-1, L-2015-0014; WDT-11A, and L-2015-0012), annual REMP report, annual effluent report, and the Off-Site Dose Calculation Manual (ODCM). The inspectors performed a walkdown of groundwater monitoring wells and site liquid and gaseous effluent monitoring points.


====b. Observations and Findings====
====b. Observations and Findings====
The inspectors noted that CR
The inspectors noted that CR-3 made several schedule changes that impacted the information contained in their PSDAR. The changes were related to the timeline for the disposal of legacy waste, the timeline for the demolition of the Ready Warehouse, and an increase in overall construction costs for the Independent Spent Fuel Storage Installation (ISFSI) due to additional security modifications. The changes were documented in a letter to the U.S. Nuclear Regulatory Commission (NRC), dated June 11, 2015 (ML15175A188).
-3 made several schedule changes that impacted the information contained in their PSDAR. The changes were related to the timeline for the disposal of legacy waste, the timeline for the demolition of the Ready Warehouse, and an increase in overall construction costs for th e Independent Spent Fuel Storage Installation (ISFSI)due to additional security modifications. The changes were documented in a letter to the U.S. Nuclear Regulatory Commission (NRC), dated June 11, 2015 (ML15175A188).
 
In preparation for the dry cask storage of spent fuel scheduled to start in 2017, 358 spent fuel assemblies were in the process of undergoing sipping. Sipping was being performed to assess material condition of spent fuel assemblies in preparation for dry cask storage. Previous to this sipping campaign a majority of the fuel assemblies had undergone sipping or ultrasonic (UT) testing. CR
-3 was also going to perform visual inspections of a portion of the fuel assemblies in the SFP to further characterize their condition.
 
The inspectors noted that CR
-3 recently issued a new adverse weather procedure, EM-220D. The procedure was revised to better reflect the permanently shutdown status of the site. The inspectors verified that sandbags, equipment, and supplies were properly staged as required by CR
-3's procedure in preparation for adverse weather conditions that may arise at the site.


The inspectors verified that the annual radiological effluent and the annual REMP reports demonstrated that calculated doses were below regulatory dose criteria of 10 CFR 50, Appendix I.
In preparation for the dry cask storage of spent fuel scheduled to start in 2017, 358 spent fuel assemblies were in the process of undergoing sipping. Sipping was being performed to assess material condition of spent fuel assemblies in preparation for dry cask storage. Previous to this sipping campaign a majority of the fuel assemblies had undergone sipping or ultrasonic (UT) testing. CR-3 was also going to perform visual inspections of a portion of the fuel assemblies in the SFP to further characterize their condition.


The inspectors also determined that waste treatment systems were maintained and operated in accordance with procedures. The inspector verified that liquid and gaseous effluent releases to the environment were being properly controlled, monitored, and quantified as required by NRC regulations.
The inspectors noted that CR-3 recently issued a new adverse weather procedure, EM-220D. The procedure was revised to better reflect the permanently shutdown status of the site. The inspectors verified that sandbags, equipment, and supplies were properly staged as required by CR-3s procedure in preparation for adverse weather conditions that may arise at the site.


The inspectors noted that the reactor vessel was being maintained and filled with water for shielding purposes.
The inspectors verified that the annual radiological effluent and the annual REMP reports demonstrated that calculated doses were below regulatory dose criteria of 10 CFR 50, Appendix I. The inspectors also determined that waste treatment systems were maintained and operated in accordance with procedures. The inspector verified that liquid and gaseous effluent releases to the environment were being properly controlled, monitored, and quantified as required by NRC regulations. The inspectors noted that the reactor vessel was being maintained and filled with water for shielding purposes.


The inspectors confirmed that the water level was being monitored by operations personnel. The inspectors confirmed that abandoned radiation monitors that were no Inspection Report No. 05000302/2015008 C:\Users\ajk\Documents\LDPR-72.2015008.docx longer necessary to support plant operations were properly abandoned and the radiation monitors that remained in
The inspectors confirmed that the water level was being monitored by operations personnel. The inspectors confirmed that abandoned radiation monitors that were no Inspection Report No. 05000302/2015008 C:\\Users\\ajk\\Documents\\LDPR-72.2015008.docx longer necessary to support plant operations were properly abandoned and the radiation monitors that remained in-service were properly being operated and maintained.
-service were properly being operated and maintained.


CR-3 personnel identified that the site had not submitted changes they had made to various bases sections within their TSs as required by TS 5.6.2.17 since 2009. The issue was placed in their corrective action program (CR 749664), evaluated, and appropriate corrective actions were implemented.
CR-3 personnel identified that the site had not submitted changes they had made to various bases sections within their TSs as required by TS 5.6.2.17 since 2009. The issue was placed in their corrective action program (CR 749664), evaluated, and appropriate corrective actions were implemented.


====c. Conclusions====
====c. Conclusions====
Based on the results of this inspection, one licensee-identified SL IV NCV of CR
Based on the results of this inspection, one licensee-identified SL IV NCV of CR-3 TS 5.6.2.17 was identified.
-3 TS 5.6.2.17 was identified.


CR-3 TS 5.6.2.17 , "Technical Specifications (TS) Bases Control Program" states, in part, that changes to the bases implemented without prior NRC approval shall be provided to the NRC on a frequency consistent with 10 CFR 50.71 , "Maintenance of Records, Making of Reports."
CR-3 TS 5.6.2.17, Technical Specifications (TS) Bases Control Program states, in part, that changes to the bases implemented without prior NRC approval shall be provided to the NRC on a frequency consistent with 10 CFR 50.71, Maintenance of Records, Making of Reports. 10 CFR 50.71(e)(4) states, in part, that subsequent revisions must be filed annually or 6 months after each refueling outage provided the interval between successive updates does not exceed 24 months; and the revisions must reflect all changes up to a maximum of 6 months prior to the date of filling. It also states that for nuclear power reactor facilities that have submitted the certifications required by 50.82(a)(1), subsequent revisions must be filed every 24 months. Contrary to the requirement, Duke Energy did not submit changes to the bases of the TS to the NRC at the required time intervals. Specifically, Duke Energy did not submit any TS Bases updates to the NRC from April 30, 2009 to May 27, 2015.


10 CFR 50.71(e)(4) states, in part, that subsequent revisions must be filed annually or 6 months after each refueling outage provided the interval between successive updates does not exceed 24 months; and the revisions must reflect all changes up to a maximum of 6 months prior to the date of filling.
This violation is being treated as a NCV, consistent with Section 2.3.2 of the Enforcement Policy. Because this violation resulted in no potential safety consequences and it was entered into CR-3s corrective action program (Condition Report (CR)749664), this violation is being treated as an NCV, consistent with the NRC Enforcement Policy. (NCV 05000302/2015008-01; TS Bases Updates Not Submitted At Required Frequencies)


It also states that for nuclear power reactor facilities that have submitted the certifications required by 50.82(a)(1), subsequent revisions must be filed every 24 months.
3.0 Decommissioning Fire Protection Program (FPP)


Contrary to the requirement, Duke Energy did not submit changes to the bases of the TS to the NRC at the required time intervals. Specifically, Duke Energy did not submit any TS Bases updates to the NRC from April 30, 2009 to May 27, 2015.
====a. Inspection Scope====
(IP 64704)


This violation is being treated as a NCV, consistent with Section 2.3.2 of the Enforcement Policy.
The inspectors reviewed CR-3s FPP to ensure Duke Energy adequately implemented their program in accordance with 10CFR50.48(f), Fire Protection, the current CR-3 fire protection plan, final safety analysis report (FSAR), and Regulatory Guide 1.191, Fire Protection Program for Nuclear Power Plants During Decommissioning and Permanent Shutdown. The inspectors also verified the FPP had been maintained in a state of operational readiness and changes made to the FFP program continue to meet commitments, NRC requirements, and have not negatively affected the overall state of the FPP at CR-3.


Because this violation resulted in no potential safety consequences and it was entered into CR
Inspection Report No. 05000302/2015008 C:\\Users\\ajk\\Documents\\LDPR-72.2015008.docx
-3's corrective action program (Condition Report (CR) 749664), this violation is being treated as an NCV, consistent with the NRC Enforcement Policy. (NCV 05000302/2015008
-01; TS Bases Updates Not Submitted At Required Frequencies)3.0      Decommissioning Fire Protection Program (FPP)


====a. Inspection Scope====
The inspectors performed an inspection of the FPP at CR-3 to determine whether it had been maintained in a state of operational readiness and whether changes made to the FPP continued to meet commitments, the NRC requirements, and had not negatively affected the overall state of the FPP at CR-3. Specifically, the inspectors:
(IP 64704)  The inspectors reviewed CR
* verified that the licensee had developed and implemented technically adequate procedures to implement the FPP;
-3's FPP to ensure Duke Energy adequately implemented the ir program in accordance with 10CFR50.48(f), "Fire Protection
* verified the proper installation, operability, and maintenance of fire protection systems and equipment; and
," the current CR
* reviewed the adequacy and implementation of the quality assurance program for the FPP.
-3 fire protection plan, final safety analysis report (FSAR), and Regulatory Guide 1.191, "Fire Protection Program for Nuclear Power Plants During Decommissioning and Permanent Shutdown."  The inspectors also verified the FPP had been maintained in a state of operational readiness and changes made to the FFP program continue to meet commitments, NRC requirements, and have not negatively affected the overall state of the FPP at CR
-3.


Inspection Report No. 05000302/2015008 C:\Users\ajk\Documents\LDPR-72.2015008.docx The inspectors performed an inspection of the FPP at CR-3 to determine whether it had been maintained in a state of operational readiness and whether changes made to the FPP continued to meet commitments, the NRC requirements, and had not negatively affected the overall state of the FPP at CR
The inspection consisted of interviews with Duke Energy personnel, a review of procedures and records, and plant walk-downs.
-3. Specifically, the inspectors:
verified that the licensee had developed and implemented technically adequate procedures to implement the FPP;  verified the proper installation, operability, and maintenance of fire protection systems and equipment; and reviewed the adequacy and implementation of the quality assurance program for the FPP. The inspection consisted of interviews with Duke Energy personnel, a review of procedures and records, and plant walk
-downs. The inspectors reviewed changes made to CR
-3's FPP. The inspectors also reviewed a sample of FPP procedures used for the storage of combustibles and flammables, performance of hot-work, control of ignition sources, and control of transient combustibles to ensure they were in compliance with the CR-3 FPP and adequately reflected the current decommissioning status of the facility.


Additionally, the inspectors reviewed fire brigade training, training with off
The inspectors reviewed changes made to CR-3s FPP. The inspectors also reviewed a sample of FPP procedures used for the storage of combustibles and flammables, performance of hot-work, control of ignition sources, and control of transient combustibles to ensure they were in compliance with the CR-3 FPP and adequately reflected the current decommissioning status of the facility. Additionally, the inspectors reviewed fire brigade training, training with off-site responders, qualifications, and responsibilities to ensure they were qualified to participate in firefighting activities. The inspectors performed a walkdown of firefighting equipment and equipment carts to ensure that they were properly maintained, inventoried and ready for use. Pre-fire plans were reviewed to ensure that they were up-dated and reflected the plants decommissioning status.
-site responders, qualifications, and responsibilities to ensure they were qualified to participate in firefighting activities. The inspectors performed a walkdown of firefighting equipment and equipment carts to ensure that they were properly maintained, inventoried and ready for use. Pre
-fire plans were reviewed to ensure that they were up-dated and reflected the plants decommissioning status.


The inspectors reviewed the installed fire detection, suppression systems, and fire barriers in fire areas associated with the SFP, SFP cooling equipment, SFP power supply, and SFP inventory to ensure that they were maintained, surveillances were performed on a periodic basis , and capable of performing their intended function. This included review of fire pump capability and testing to ensure adequate water and water pressure could be supplied to the necessary systems and standpipes for fire suppression/firefighting activities. Part of this review included review of detection and suppression systems for the cable spreading room which contains a gaseous suppression system (Halon) and the "B" diesel generator room which contains a sprinkler suppression system. The inspectors also conducted a walk-down of plant detection systems, suppression systems, fire barriers, and fire pumps/water sources to ensure material condition was maintained.
The inspectors reviewed the installed fire detection, suppression systems, and fire barriers in fire areas associated with the SFP, SFP cooling equipment, SFP power supply, and SFP inventory to ensure that they were maintained, surveillances were performed on a periodic basis, and capable of performing their intended function. This included review of fire pump capability and testing to ensure adequate water and water pressure could be supplied to the necessary systems and standpipes for fire suppression/firefighting activities. Part of this review included review of detection and suppression systems for the cable spreading room which contains a gaseous suppression system (Halon) and the B diesel generator room which contains a sprinkler suppression system. The inspectors also conducted a walk-down of plant detection systems, suppression systems, fire barriers, and fire pumps/water sources to ensure material condition was maintained.


The inspectors revi ew ed a sample of self
The inspectors reviewed a sample of self-assessments and corrective action documents to ensure the licensee was identifying and placing FPP decommissioning deficiencies into the corrective action program.
-assessments and corrective action documents to ensure the licensee was identifying and placing FPP decommissioning deficiencies into the corrective action program.


Inspection Report No. 05000302/2015008 C:\Users\ajk\Documents\LDPR-72.2015008.docx
Inspection Report No. 05000302/2015008 C:\\Users\\ajk\\Documents\\LDPR-72.2015008.docx


====b. Observations and Findings====
====b. Observations and Findings====
The inspectors noted that CR
The inspectors noted that CR-3 maintained the FPP within NRC requirements and the FPP. Fire protection detection systems, suppression systems, barriers, and fire pumps are being maintained and appropriately tested and in a state of operational readiness.
-3 maintained the FPP within NRC requirements and the FPP. Fire protection detection systems, suppression systems, barriers, and fire pumps are being maintained and appropriately tested and in a state of operational readiness.


The fire brigade training, qualifications and conduct of fire drills (announced and unannounced) were being properly implemented. The inspectors determined that proper FPP emphasis was placed on SFP systems and components to minimize the potential for radiological releases in the event of a fire at the plant.
The fire brigade training, qualifications and conduct of fire drills (announced and unannounced) were being properly implemented. The inspectors determined that proper FPP emphasis was placed on SFP systems and components to minimize the potential for radiological releases in the event of a fire at the plant.


The inspectors also noted that changes made to the CR
The inspectors also noted that changes made to the CR-3 FPP did not reduce its effectiveness and that screenings and evaluations contained the appropriate level of detail and sufficient basis to support the changes. However, this review is not a formal safety evaluation and does not constitute formal NRC approval of the changes.
-3 FPP did not reduce its effectiveness and that screenings and evaluations contain ed the appropriate level of detail and sufficient basis to support the change s. However, this review is not a formal safety evaluation and does not constitute formal NRC approval of the changes.


Therefore, these changes remain subject to future NRC inspection s.
Therefore, these changes remain subject to future NRC inspections.


====c. Conclusions====
====c. Conclusions====
Line 183: Line 149:
3.0  
3.0  


=====Exit Meeting Summary=====
===Exit Meeting Summary===
On July 8, 2015 , the inspectors presented the inspection results, via teleconference, to Terry Hobbs, General Manager, and other members of Duke Energy's staff. The inspectors confirmed that proprietary information was not removed from the site
On July 8, 2015, the inspectors presented the inspection results, via teleconference, to Terry Hobbs, General Manager, and other members of Duke Energys staff. The inspectors confirmed that proprietary information was not removed from the site.
.
 
PARTIAL LIST OF PERSONS CONTACTED Licensee B. Akins, Radiation Protection and Chemistry Manager W. Basnight, Procedures D. Demontfort, Maintenance A. Doruff, Fire Protection Specialist F. Frando, Technical Specialist II, Licensing
PARTIAL LIST OF PERSONS CONTACTED  
 
Licensee B. Akins, Radiation Protection and Chemistry Manager W. Basnight, Procedures D. Demontfort, Maintenance A. Doruff, Fire Protection Specialist F. Frando, Technical Specialist II, Licensing P. Gerardin, Nuclear Oversight, Lead Assessor R. Ivey, Nuclear Oversight, Corporate Director of Audit & Programs G. McCallum, Operations P. Rose, Licensing I. Wilson, General Manager Decommissioning (Acting)
T. Worthington, Engineering Manager B. Wunderly, Plant Manager
 
ITEMS OPEN, CLOSED, AND DISCUSSED


P. Gerardin, Nuclear Oversight, Lead Assessor R. Ivey, Nuclear Oversight, Corporate Director of Audit & Programs G. McCallum, Operations P. Rose, Licensing I. Wilson, General Manager Decommissioning (Acting)
05000302/2015008-01 NCV TS Bases Updates Not Submitted At Required Frequencies  
T. Worthington, Engineering Manager B. Wunderly, Plant Manager ITEMS OPEN, CLOSED, AND DISCUS SED  05000302/201 5 00 8-01 NCV TS Bases Updates Not Submitted At Required Frequencies LIST OF  
 
LIST OF  


=DOCUMENTS REVIEWED=
=DOCUMENTS REVIEWED=


Action Request
Action Request (Condition Reports)
(Condition Reports)
664047, 673234, 680894, 685436, 686427, 686967, 690389, 691739, 693222, 694092,
664047, 673234, 680894, 685436, 686427, 686967, 690389, 691739, 693222, 694092, 698726, 700871, 701925, 707158, 708318, 709581, 709689, 714369, 719375, 720264, 721384, 721580, 722097, 724401, 728589, 729925, 730549, 734834, 736107, 737953, 738620, 738973, 740234, 741929, 746903, 747654, 747844, 749664, 753559
698726, 700871, 701925, 707158, 708318, 709581, 709689, 714369, 719375, 720264,
21384, 721580, 722097, 724401, 728589, 729925, 730549, 734834, 736107, 737953,
738620, 738973, 740234, 741929, 746903, 747654, 747844, 749664, 753559
Audits and Reports
Audits and Reports
2014-CR3-FP-01, (NOS) Crystal River Fire Protection Audit, 4/3/14
2014-CR3-FP-01, (NOS) Crystal River Fire Protection Audit, 4/3/14
708467, Self
708467, Self-Assessment Report, B.5.b Spent Fuel Pool Makeup with Two Man Response
-Assessment Report, B.5.b Spent Fuel Pool Makeup with Two Man Response
Team, 9/16/14
Team, 9/16/14
Annual Radioactive Effluent Release Report 2014, Crystal River Unit 3
Annual Radioactive Effluent Release Report 2014, Crystal River Unit 3
Line 206: Line 179:
Calculations
Calculations
F13-0003, CR-3 Spent Fuel Pool Time to Uncover Fuel Analysis, Revision 0
F13-0003, CR-3 Spent Fuel Pool Time to Uncover Fuel Analysis, Revision 0
N13-0003, Public Dose from a Radioactive Waste Event, Revision 0
N13-0003, Public Dose from a Radioactive Waste Event, Revision 0  


Attachment
Design Basis Documents (DBD)
Design Basis Documents (DBD)
DBD, Electrical Support Systems Fire Detection System, Revision 3
DBD, Electrical Support Systems Fire Detection System, Revision 3
Enhanced DBD, Fire Service System, Revision 20
Enhanced DBD, Fire Service System, Revision 20
Drawings B-208-031-FS-00, Elementary Diagram, Fire Service System Index, Revision 9
Drawings
B-208-031-FS-01, Elementary Diagram, Diesel Driven Fire Pump FSP
B-208-031-FS-00, Elementary Diagram, Fire Service System Index, Revision 9
-2A, Revision 20
B-208-031-FS-01, Elementary Diagram, Diesel Driven Fire Pump FSP-2A, Revision 20
B-208-031-FS-02, Elementary Diagram, Diesel Driven Fire Pump FSP
B-208-031-FS-02, Elementary Diagram, Diesel Driven Fire Pump FSP-2B, Revision 13
-2B, Revision 13
B-208-031-FS-03, Elementary Diagram, Motor Driven Fire Service Pump FSP-1, Revision 19
B-208-031-FS-03, Elementary Diagram, Motor Driven Fire Service Pump FSP
-1, Revision 19
FD-302-2321, Fire Service Water, Revision 93
FD-302-2321, Fire Service Water, Revision 93
FD-302-621, Spent Fuel Cooling, Revision 35
FD-302-621, Spent Fuel Cooling, Revision 35
FD-302-751, Revision 64
FD-302-751, Revision 64
FD-302-752, Revision 39
FD-302-752, Revision 39
FD-302-785, Spent Fuel Chilled Water System CH
FD-302-785, Spent Fuel Chilled Water System CH-SF, Revision 2
-SF, Revision 2
L-001-022, Revision 50
L-001-022, Revision 50
L-001-023, Revision 29 P-304-783, Addition to Halon System to Cable Spreading Room, Revision 4
L-001-023, Revision 29
P-304-783, Addition to Halon System to Cable Spreading Room, Revision 4
Evaluations
Evaluations
AI-9003, Attachment 2 (Hazard Identification), System Evaluation, Categorization and
AI-9003, Attachment 2 (Hazard Identification), System Evaluation, Categorization and
Line 232: Line 202:
AI-9003, Attachment 2 (SSC Category Determination), System Evaluation, Categorization and
AI-9003, Attachment 2 (SSC Category Determination), System Evaluation, Categorization and
Abandonment Fire Service Water System, Revision 5
Abandonment Fire Service Water System, Revision 5
Basic Cause Evaluation, Technical Specification Bases Control Program, CR
Basic Cause Evaluation, Technical Specification Bases Control Program, CR-3 Has Not
-3 Has Not
Submitted Updates
Submitted Updates
REG-0100, Attachment 1  
REG-0100, Attachment 1 - Screen, Partial Abandonment of the RB Purge System, Revision 3
- Screen, Partial Abandonment of the RB Purge System, Revision 3
Pre-Fire Plans
Pre-Fire Plans
AI-2205A, Pre
AI-2205A, Pre-Fire Plan-Control Complex, Revision 10
-Fire Plan-Control Complex, Revision 10
AI-2205B, Pre-Fire Plan-Turbine Building, Revision 12
AI-2205B, Pre
AI-2205C, Pre-Fire Plan-Auxiliary Building, Revision12
-Fire Plan-Turbine Building, Revision 12
AI-2205D, Pre-Fire Plan-Intermediate Building, Revision 6
AI-2205C, Pre
AI-2205E, Pre-Fire Plan-Reactor Building, Revision 7
-Fire Plan-Auxiliary Building, Revision12
AI-2205F, Pre-Fire Plan-Miscellaneous Building and Components, Revision 18  
AI-2205D, Pre
-Fire Plan-Intermediate Building, Revision 6
AI-2205E, Pre
-Fire Plan-Reactor Building, Revision 7
AI-2205F, Pre
-Fire Plan-Miscellaneous Building and Components, Revision 18


Attachment
Procedures
Procedures
AAG-005, Contingencies for Loss of SF Pool Level , Revision 3
AAG-005, Contingencies for Loss of SF Pool Level, Revision 3
AI-151, Reporting Requirement Program, Revision 3
AI-151, Reporting Requirement Program, Revision 3
AI-604, Administrative Control of Structures, Material and Equipment Laydown Areas, Revision 17
AI-604, Administrative Control of Structures, Material and Equipment Laydown Areas,
Revision 17
AI-1000, Housekeeping/Material Condition Program, Revision 48
AI-1000, Housekeeping/Material Condition Program, Revision 48
AI-2200, Guidelines for Handling use and Control of Transient Combustibles, Revision 13
AI-2200, Guidelines for Handling use and Control of Transient Combustibles, Revision 13
AI-2205, Administration of CR
AI-2205, Administration of CR-3 Fire Brigade Organization and Duties of the Fire Brigade,
-3 Fire Brigade Organization and Duties of the Fire Brigade, Revision 26
Revision 26
AI-2210, Fire Watch Program, Rev. 13
AI-2210, Fire Watch Program, Rev. 13
AI-9003, System Evaluation, Categorization and Abandonment, Revision 5
AI-9003, System Evaluation, Categorization and Abandonment, Revision 5
Line 265: Line 227:
Areva, FS-156, Fuel Assembly Visual Examination using the Mobile Video Rig, Revision 005
Areva, FS-156, Fuel Assembly Visual Examination using the Mobile Video Rig, Revision 005
Areva, FS-181, Vacuum Sipping Setup and Operation, Revision 008
Areva, FS-181, Vacuum Sipping Setup and Operation, Revision 008
CP-9300, Fire Protection  
CP-9300, Fire Protection - Minimum Requirements, Compensatory Measures, and Surveillance
- Minimum Requirements, Compensatory Measures, and Surveillance
Requirements, Revision 3
Requirements, Revision 3
EM-216, Duties of the Fire Brigade, Revision 28
EM-216, Duties of the Fire Brigade, Revision 28
Line 275: Line 236:
REG-0010, 10CFR50.59 and Selected Regulatory Reviews, Rev. 3
REG-0010, 10CFR50.59 and Selected Regulatory Reviews, Rev. 3
SP-363, Fire Protection System Tests, Revision 45
SP-363, Fire Protection System Tests, Revision 45
SP-365A, Electric Fire Service Pump, FSP
SP-365A, Electric Fire Service Pump, FSP-1 Operability, Revision 25
-1 Operability, Revision 25
SP-365B, Diesel Fire Service Pump, FSP-2A Operability, Revision 28
SP-365B, Diesel Fire Service Pump, FSP
-2A Operability, Revision 28
SP-408, Fire System Flow Test, Revision 21
SP-408, Fire System Flow Test, Revision 21
SP-502, Fire Pump Diesel Batteries Weekly Inspection, Revision 23
SP-502, Fire Pump Diesel Batteries Weekly Inspection, Revision 23
SP-503, Fire Pump Diesel Batteries Quarterly Check, Revision 21
SP-503, Fire Pump Diesel Batteries Quarterly Check, Revision 21
SP-731A, Auxiliary Building Ventilation Continuous Release, Revision 20
SP-731A, Auxiliary Building Ventilation Continuous Release, Revision 20
SP-736L, Liquid Releases to the Discharge Canal Via RM
SP-736L, Liquid Releases to the Discharge Canal Via RM-L2, Revision 8
-L2, Revision 8
SP-736M, Liquid Releases to the Discharge Canal Via RM-L7, Revision 5  
SP-736M, Liquid Releases to the Discharge Canal Via RM
-L7, Revision 5


Attachment
Procedures-Completed Surveillance Procedures
Procedures
-Completed Surveillance Procedures
AI-9003, Revision 6, Attachment 2, SSC Category Determination Document, Reactor Building
AI-9003, Revision 6, Attachment 2, SSC Category Determination Document, Reactor Building
Purge (AH-XC), Revision 1
Purge (AH-XC), Revision 1
Line 296: Line 251:
SP-190J, Cable Spreading Room Fire Detection System Test, Revision 22, Completed 8/6/14
SP-190J, Cable Spreading Room Fire Detection System Test, Revision 22, Completed 8/6/14
SP-363, Fire Protection System (Fire Pump Tests), Revision 44, Completed 5/6/14
SP-363, Fire Protection System (Fire Pump Tests), Revision 44, Completed 5/6/14
SP-365A, Electric Fire Service Pump, FSP
SP-365A, Electric Fire Service Pump, FSP-1 Operability, Revision 25, Completed 3/26/15
-1 Operability, Revision 25, Completed 3/26/15
SP-365B, Diesel Fire Service Pump FSP-2A Operability, Revision 28, Completed 3/18/15
SP-365B, Diesel Fire Service Pump FSP
-2A Operability, Revision 28, Completed 3/18/15
SP-407, Fire and Flood Barrier Penetration Seals Inspection, Revision 41, Completed 7/15/14
SP-407, Fire and Flood Barrier Penetration Seals Inspection, Revision 41, Completed 7/15/14
SP-408, Fire System Flow Test, Revision 19, Completed 9/23/11
SP-408, Fire System Flow Test, Revision 19, Completed 9/23/11
SP-408, Fire System Flow Test, Revision 21, Completed 9/22/14
SP-408, Fire System Flow Test, Revision 21, Completed 9/22/14
SP-411D, Fire Protection for Emergency Diesel Generators, Revision 27, Completed 1/6/15  
SP-411D, Fire Protection for Emergency Diesel Generators, Revision 27, Completed 1/6/15  
  & 1/9/14 SP-501A, Halon ASC Weight and Pressure Check, Revision 18, Completed 6/17/14
& 1/9/14
SP-501A, Halon ASC Weight and Pressure Check, Revision 18, Completed 6/17/14
SP-501B, Halon System Functional Test, Revision 24, Completed 2/10/15
SP-501B, Halon System Functional Test, Revision 24, Completed 2/10/15
SP-502, Fire Pump Diesel Batteries Weekly Inspection, Revision 23, Completed 3/9/15
SP-502, Fire Pump Diesel Batteries Weekly Inspection, Revision 23, Completed 3/9/15
Line 316: Line 270:
Crystal River Unit 3, Licensing Correspondence List
Crystal River Unit 3, Licensing Correspondence List
Degraded/OOS Equipment Log (Fire Protection), 5/5/15
Degraded/OOS Equipment Log (Fire Protection), 5/5/15
EC 0000099162R1, Evaluation of External Flood Re
EC 0000099162R1, Evaluation of External Flood Re-Definition
-Definition
Effluent Release SDT-1, L-2015-0014; WDT-11A, L-2015-0012
Effluent Release SDT
Fire Brigade Roster, 4/16/15
-1, L-2015-0014; WDT-11A, L-2015-0012 Fire Brigade Roster, 4/16/15
Fire Team Leader (Incipient) Roster, 4/15/15
Fire Team Leader (Incipient) Roster, 4/15/15
Key Safety Function Status Sheet, SF Pool, Work Week 15W15 (4/6/15  
Key Safety Function Status Sheet, SF Pool, Work Week 15W15 (4/6/15 - 4/12/15)
- 4/12/15) MOU for Providing Citrus County Fire Protection Support to the CR
MOU for Providing Citrus County Fire Protection Support to the CR-3 Complex, 5/5/14
-3 Complex, 5/5/14
Off-Site Dose Calculation Manual, Crystal River Unit 3, Revision 35
Off-Site Dose Calculation Manual, Crystal River Unit 3, Revision 35
RWP 1060, Fuel Sipping Activities, Revision 2
RWP 1060, Fuel Sipping Activities, Revision 2
Screenings and Reviews
Screenings and Reviews
664047, 50.59 Screen, Remove Appendix R and Safe Shutdown from FSAR (92014
664047, 50.59 Screen, Remove Appendix R and Safe Shutdown from FSAR (92014-007)
-007) 680894, 50.59 Screen, Fire Protection Transition to 50.48(f)
680894, 50.59 Screen, Fire Protection Transition to 50.48(f)
693222, 50.59 Screen, Revise Fire Brigade to Reflect SAFSTOR Plant Status
693222, 50.59 Screen, Revise Fire Brigade to Reflect SAFSTOR Plant Status
693270, 50.59 Screen, Revise Fire Brigade to Reflect SAFSTOR Plant Status
693270, 50.59 Screen, Revise Fire Brigade to Reflect SAFSTOR Plant Status
Line 337: Line 288:
730549, 50.59 Screen, Misc. Fire Service Procedure Changes for SAFSTOR
730549, 50.59 Screen, Misc. Fire Service Procedure Changes for SAFSTOR
740234, 50.59 Screen, Review of Fire Protection Documents for SAFSTOR
740234, 50.59 Screen, Review of Fire Protection Documents for SAFSTOR
Attachment
 
Training-Fire Brigade Lessons and Plans
Training-Fire Brigade Lessons and Plans
FWB01G/FPQ0001G, Hot work Fire Watch Training, Revision 14
FWB01G/FPQ0001G, Hot work Fire Watch Training, Revision 14
TRF-30, CR-3, Off Site Responder Awareness Training, Revision 3
TRF-30, CR-3, Off Site Responder Awareness Training, Revision 3
TR F-050, Initial Incipient Fire Brigade Lesson Plan, Revision 0
TRF-050, Initial Incipient Fire Brigade Lesson Plan, Revision 0
TRF-052, Combustion and Fire Behavior, Revision 0
TRF-052, Combustion and Fire Behavior, Revision 0
TRF-053, Portable Fire Extinguisher 1, Revision 0
TRF-053, Portable Fire Extinguisher 1, Revision 0
Line 349: Line 300:
TRF-057, Fire Hose, Revision 0
TRF-057, Fire Hose, Revision 0
TRF-058, Fire Streams and Nozzles, Revision 0
TRF-058, Fire Streams and Nozzles, Revision 0
TRF-063, Plant Walk Trough's and Drills, Revision 0
TRF-063, Plant Walk Troughs and Drills, Revision 0
TRF-064, Delta Training, Incipient Fire Brigade, Revision 0
TRF-064, Delta Training, Incipient Fire Brigade, Revision 0
Training-Fire Brigade Drills and Critiques
Training-Fire Brigade Drills and Critiques
Unannounced Drill, Control Complex, 4160V ES Switchgear Room "A", Completed 5/10/14
Unannounced Drill, Control Complex, 4160V ES Switchgear Room A, Completed 5/10/14
Unannounced Drill, Control Complex, 4160V ES Switchgear Room "B", Completed 8/16/14
Unannounced Drill, Control Complex, 4160V ES Switchgear Room B, Completed 8/16/14
Unannounced Drill, 119' Auxiliary Building (SFP
Unannounced Drill, 119 Auxiliary Building (SFP-1A), Completed 9/12/14
-1A), Completed
Announced Drill, 119 Auxiliary Building (SFP-1B), Completed 10/20/14
9/12/14 Announced Drill, 119' Auxiliary Building (SFP
Unannounced Drill, CC/Spent Fuel Chiller Systems (CHHE-4A), Completed 1/20/15
-1B), Completed 10/20/14
Training-Competed Records for Fire Brigade and Fire Watch Qualifications
Unannounced Drill, CC/Spent Fuel Chiller Systems (CHHE
-4A), Completed 1/20/15
Training-Competed Records for Fire Brigade and Fire Watch
Qualifications
TRF000, Initial Fire Brigade Training, 1/12/15
TRF000, Initial Fire Brigade Training, 1/12/15
TRF001, Fire Brigade Training, 1/12/15
TRF001, Fire Brigade Training, 1/12/15
Line 367: Line 314:
TRF025, FTL Fire Suppression Techniques, 1/12/15
TRF025, FTL Fire Suppression Techniques, 1/12/15
TRF026, FTL Fire Prevention Techniques, 1/12/15
TRF026, FTL Fire Prevention Techniques, 1/12/15
TRF064, Incipient Fire Brigade Delta Training, 4/20/15 TRFA, Annual Hands On Fire Brigade Training, 4/20/15
TRF064, Incipient Fire Brigade Delta Training, 4/20/15
TRFA, Annual Hands On Fire Brigade Training, 4/20/15
2014 Fire Brigade Annual Drill Completions, 4/20/15
2014 Fire Brigade Annual Drill Completions, 4/20/15
2015 Fire Brigade Drill Completions, 4/20/15
2015 Fire Brigade Drill Completions, 4/20/15
2015 Fire Brigade Annual Training Completions, 4/20/15
2015 Fire Brigade Annual Training Completions, 4/20/15
2015 Fire Watch Training Completions, 4/14
2015 Fire Watch Training Completions, 4/14-4/15
-4/15 2015 Incipient Fire Brigade Qualification Completions, 4/20/15
2015 Incipient Fire Brigade Qualification Completions, 4/20/15
2015 Incipient Fire Brigade Leader Qualification Completions, 4/20/15
2015 Incipient Fire Brigade Leader Qualification Completions, 4/20/15  
 
Work Orders
Work Orders
219232, 00219604, 00219605, 01885333, 01935802, 02216993, 02217532, 02273978, 02276244, 02284984, 13349913, 13313841, 13355289, 13377003, 13395423, 13455854
219232, 00219604, 00219605, 01885333, 01935802, 02216993, 02217532, 02273978,
276244, 02284984, 13349913, 13313841, 13355289, 13377003, 13395423, 13455854  


Attachment
LIST OF ACRONYMS USED
LIST OF ACRONYMS USED
CFR   Code of Federal Regulations
CFR  
CR   Condition Report
 
CR-3   Crystal River Unit 3
Code of Federal Regulations
CR  
 
Condition Report
CR-3
Crystal River Unit 3
Duke Energy
Duke Energy
Duke Energy Florida, Inc
Duke Energy Florida, Inc.
. FPP   Fire Protection Program
FPP  
FSAR   Final Safety Analysis Report IMC   Inspection Manual Chapter
 
ISFSI   Independent Spent Fuel Storage Installation
Fire Protection Program
IP   Inspection Procedure
FSAR
NRC   U.S. Nuclear Regulatory Commission
Final Safety Analysis Report
NCV   Non-Cited Violation
IMC  
ODCM   Off-Site Dose Calculation Manual
 
PSDAR Post Shutdown Decommissioning Activities Report
Inspection Manual Chapter
REMP   Radiological
ISFSI
Environmental
Independent Spent Fuel Storage Installation
Monitoring
IP  
Program RWP   Radiation Work Permit
 
SFP   Spent Fuel Pool
Inspection Procedure
SL   Severity Level
NRC  
TS   Technical Specifications
 
UT   Ultrasonic Testing
U.S. Nuclear Regulatory Commission
NCV  
 
Non-Cited Violation
ODCM
Off-Site Dose Calculation Manual
PSDAR
Post Shutdown Decommissioning Activities Report
REMP
Radiological Environmental Monitoring Program
RWP
Radiation Work Permit
SFP  
 
Spent Fuel Pool
SL  
 
Severity Level
TS  
 
Technical Specifications
UT  
 
Ultrasonic Testing
}}
}}

Latest revision as of 10:16, 10 January 2025

IR 05000302/2015008 on 5/4-7/2015, 6/22-25/2015 and 6/30/2015, Duke Energy Florida, Inc., Crystal River Unit 3, Crystal River, Fl
ML15209A632
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 07/28/2015
From: Marc Ferdas, Stephen Hammann
NRC/RGN-I/DNMS/NMSB3
To: Hobbs T
Duke Energy Florida
References
IR 2015008
Download: ML15209A632 (16)


Text

July 28, 2015

SUBJECT:

NRC INSPECTION REPORT NO. 05000302/2015008, DUKE ENERGY FLORIDA, INC., CRYSTAL RIVER UNIT 3, CRYSTAL RIVER, FLORIDA

Dear Mr. Hobbs:

On June 30, 2015, the U.S. Nuclear Regulatory Commission (NRC) completed its quarterly inspection under Inspection Manual Chapter 2561, Decommissioning Power Reactor Inspection Program," at the permanently shut down Crystal River Nuclear Plant Unit 3 (CR-3). On-site inspections were performed on May 4-7 and June 22-25, 2015. In-office reviews of information supplied by Duke Energy Florida, Inc. were also performed during the inspection period. The inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations, and the conditions of your license.

The inspection consisted of observations by the inspectors, interviews with personnel, and a review of procedures and records. The results of the inspection were discussed with you and other members of the CR-3 staff on July 8, 2015, and are described in the enclosed report.

Based on the results of this inspection, the NRC has determined that one licensee identified Severity Level IV violation of NRC requirements occurred. This violation is being treated as a Non-Cited Violation (NCV), consistent with Section 2.3.2 of the Enforcement Policy. The NCV is described in the subject inspection report. If you contest the violation or significance of the NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001, with copies to: (1) the Regional Administrator, Region I; (2) the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and (3) the NRC Senior Decommissioning Inspector, Region I.

In accordance with 10 CFR 2.390 of the NRCs "Rules of Practice," a copy of this letter, its enclosure(s), and your response, will be made available electronically for public inspection in the NRC Public Document Room or from the NRC document system (ADAMS), accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response should not include any personal privacy, proprietary, or safeguards information so that it can be made available to the Public without redaction.

UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION I

2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PA 19406-2713 Current NRC regulations and guidance are included on the NRC's website at www.nrc.gov; select Radioactive Waste; Decommissioning of Nuclear Facilities; then Regulations, Guidance and Communications. The current Enforcement Policy is included on the NRC's website at www.nrc.gov; select About NRC, Organizations & Functions; Office of Enforcement; Enforcement documents; then Enforcement Policy (Under 'Related Information'). You may also obtain these documents by contacting the Government Printing Office (GPO) toll-free at 1-866-512-1800. The GPO is open from 8:00 a.m. to 5:30 p.m. EST, Monday through Friday (except Federal holidays).

No reply to this letter is required. Please contact Steve Hammann, at 610-337-5399, if you have any questions regarding this matter.

Sincerely,

/RA/

Marc S. Ferdas, Chief Decommissioning and Technical Support Branch Division of Nuclear Materials Safety

Enclosure:

Inspection Report 05000302/2015008

cc w/encl:

State of Florida

Distribution via ListServ

EXECUTIVE SUMMARY

Duke Energy

Crystal River Nuclear Plant NRC Inspection Report No. 05000302/2015008

An announced quarterly inspection was completed at CR-3 on June 30, 2015. On-site inspections were conducted on May 4-7, and June 22-25, 2015. In-office reviews of information supplied by Duke Energy were also performed during the inspection period. The inspection included a review of operations, management oversight, adverse weather preparations, radioactive effluent control, radiological environmental monitoring program (REMP), fire protection, and plant support activities. The inspection consisted of observations by the inspectors, interviews with Duke Energy personnel, a review of procedures and records, and plant walk-downs. The NRC's program for overseeing the safe operation of a shut-down nuclear power reactor is described in Inspection Manual Chapter (IMC) 2561,

Decommissioning Power Reactor Inspection Program."

Based on the results of this inspection, a licensee-identified Severity Level (SL) lV Non-Cited Violation (NCV) of CR-3 Technical Specifications (TS) 5.6.2.17, Technical Specifications Bases Control Program, was identified. Duke Energy did not submit any TS Bases updates to the NRC from April 30, 2009 to May 27, 2015. This violation is being treated as a NCV, consistent with Section 2.3.2 of the Enforcement Policy. Because this violation resulted in no potential safety consequences and it was entered into CR-3s corrective action program (Condition Report (CR) 749664), this violation is being treated as an NCV, consistent with the NRC Enforcement Policy.

Inspection Report No. 05000302/2015008 C:\\Users\\ajk\\Documents\\LDPR-72.2015008.docx

REPORT DETAILS

1.0 Background

On February 20, 2013, Duke Energy sent a letter (Agency Documentation and Management System (ADAMS) Accession Number: ML13056A005) to the NRC certifying the permanent cessation of activities and certifying that the fuel had been permanently removed from the reactor. This met the requirements of 10 CFR 50.82(a)(1)(i) and 50.82(a)(1)(ii). As of the end of the reporting period, CR-3 was in the Post Operation Transitional Phase of decommissioning as described in IMC 2561.

2.0 Post Operation Transition Phase Performance and Status Review

a. Inspection Scope

(Inspection Procedures (IPs) 36801, 37801, 40801, 60801, 71801, 84750)

The inspectors performed an on-site inspection the week of June 22-26, 2015. In-office reviews of information supplied by Duke Energy were also performed during the inspection period. The inspection consisted of observations by the inspectors, interviews with Duke Energy personnel, a review of procedures and records, and plant walk-downs.

The inspectors assessed management oversight of the sites transition to decommissioning status. The inspectors reviewed the sites organization, staffing levels, and personnel qualifications to ensure the safe storage of radioactive materials would not be adversely impacted by organization changes. The inspectors reviewed schedule and scope changes to assess the potential impact on the information contained in CR-3s Post-Shutdown Decommissioning Activities Report (PSDAR) and to ensure changes were consistent with NRC regulations and guidance.

The inspectors reviewed the status of system and equipment abandonment activities and plant modifications being made to support CR-3s transition to SAFSTOR status.

The inspectors also reviewed CR-3s proposed plans for changes to the reactor building ventilation system (REG-0100, Attachment 1 - Screen, Partial Abandonment of the RB Purge System, Revision 3).

The inspectors reviewed the CR-3 requirements for submitting changes to the TS bases to the NRC as required by the regulations and TS 5.6.2.17, Technical Specifications Bases Control Program. The inspectors also reviewed corrective action reports to determine if issues were being properly assessed, reviewed, prioritized, and corrective actions were being appropriately implemented.

The inspectors observed spent fuel sipping activities being performed. The inspectors reviewed the equipment setup and evaluated CR-3s adherence to procedures, supervisory oversight, and communication and coordination. The inspector reviewed procedures, move sheets, and radiation work permit (RWP) associated with the spent fuel sipping campaign.

Inspection Report No. 05000302/2015008 C:\\Users\\ajk\\Documents\\LDPR-72.2015008.docx The inspectors evaluated CR-3s readiness for adverse weather (flooding and hurricanes). The inspectors performed a walk-down of the site, reviewed procedures and completed work orders to verify the CR-3 flooding mitigation plans and supplies were consistent with design requirements and risk analysis assumptions. The inspectors verified that sandbags, equipment, and supplies were properly staged as required by CR-3 procedure EM-220D, Violent Weather (Permanently Defueled).

The inspectors reviewed documentation associated with radioactive effluent control and site radiological environmental monitoring program (REMP) to determine the effectiveness of site radiological programs. The inspectors reviewed procedures, diagrams of effluent monitoring systems, liquid effluent release analysis (SDT-1, L-2015-0014; WDT-11A, and L-2015-0012), annual REMP report, annual effluent report, and the Off-Site Dose Calculation Manual (ODCM). The inspectors performed a walkdown of groundwater monitoring wells and site liquid and gaseous effluent monitoring points.

b. Observations and Findings

The inspectors noted that CR-3 made several schedule changes that impacted the information contained in their PSDAR. The changes were related to the timeline for the disposal of legacy waste, the timeline for the demolition of the Ready Warehouse, and an increase in overall construction costs for the Independent Spent Fuel Storage Installation (ISFSI) due to additional security modifications. The changes were documented in a letter to the U.S. Nuclear Regulatory Commission (NRC), dated June 11, 2015 (ML15175A188).

In preparation for the dry cask storage of spent fuel scheduled to start in 2017, 358 spent fuel assemblies were in the process of undergoing sipping. Sipping was being performed to assess material condition of spent fuel assemblies in preparation for dry cask storage. Previous to this sipping campaign a majority of the fuel assemblies had undergone sipping or ultrasonic (UT) testing. CR-3 was also going to perform visual inspections of a portion of the fuel assemblies in the SFP to further characterize their condition.

The inspectors noted that CR-3 recently issued a new adverse weather procedure, EM-220D. The procedure was revised to better reflect the permanently shutdown status of the site. The inspectors verified that sandbags, equipment, and supplies were properly staged as required by CR-3s procedure in preparation for adverse weather conditions that may arise at the site.

The inspectors verified that the annual radiological effluent and the annual REMP reports demonstrated that calculated doses were below regulatory dose criteria of 10 CFR 50, Appendix I. The inspectors also determined that waste treatment systems were maintained and operated in accordance with procedures. The inspector verified that liquid and gaseous effluent releases to the environment were being properly controlled, monitored, and quantified as required by NRC regulations. The inspectors noted that the reactor vessel was being maintained and filled with water for shielding purposes.

The inspectors confirmed that the water level was being monitored by operations personnel. The inspectors confirmed that abandoned radiation monitors that were no Inspection Report No. 05000302/2015008 C:\\Users\\ajk\\Documents\\LDPR-72.2015008.docx longer necessary to support plant operations were properly abandoned and the radiation monitors that remained in-service were properly being operated and maintained.

CR-3 personnel identified that the site had not submitted changes they had made to various bases sections within their TSs as required by TS 5.6.2.17 since 2009. The issue was placed in their corrective action program (CR 749664), evaluated, and appropriate corrective actions were implemented.

c. Conclusions

Based on the results of this inspection, one licensee-identified SL IV NCV of CR-3 TS 5.6.2.17 was identified.

CR-3 TS 5.6.2.17, Technical Specifications (TS) Bases Control Program states, in part, that changes to the bases implemented without prior NRC approval shall be provided to the NRC on a frequency consistent with 10 CFR 50.71, Maintenance of Records, Making of Reports. 10 CFR 50.71(e)(4) states, in part, that subsequent revisions must be filed annually or 6 months after each refueling outage provided the interval between successive updates does not exceed 24 months; and the revisions must reflect all changes up to a maximum of 6 months prior to the date of filling. It also states that for nuclear power reactor facilities that have submitted the certifications required by 50.82(a)(1), subsequent revisions must be filed every 24 months. Contrary to the requirement, Duke Energy did not submit changes to the bases of the TS to the NRC at the required time intervals. Specifically, Duke Energy did not submit any TS Bases updates to the NRC from April 30, 2009 to May 27, 2015.

This violation is being treated as a NCV, consistent with Section 2.3.2 of the Enforcement Policy. Because this violation resulted in no potential safety consequences and it was entered into CR-3s corrective action program (Condition Report (CR)749664), this violation is being treated as an NCV, consistent with the NRC Enforcement Policy. (NCV 05000302/2015008-01; TS Bases Updates Not Submitted At Required Frequencies)

3.0 Decommissioning Fire Protection Program (FPP)

a. Inspection Scope

(IP 64704)

The inspectors reviewed CR-3s FPP to ensure Duke Energy adequately implemented their program in accordance with 10CFR50.48(f), Fire Protection, the current CR-3 fire protection plan, final safety analysis report (FSAR), and Regulatory Guide 1.191, Fire Protection Program for Nuclear Power Plants During Decommissioning and Permanent Shutdown. The inspectors also verified the FPP had been maintained in a state of operational readiness and changes made to the FFP program continue to meet commitments, NRC requirements, and have not negatively affected the overall state of the FPP at CR-3.

Inspection Report No. 05000302/2015008 C:\\Users\\ajk\\Documents\\LDPR-72.2015008.docx

The inspectors performed an inspection of the FPP at CR-3 to determine whether it had been maintained in a state of operational readiness and whether changes made to the FPP continued to meet commitments, the NRC requirements, and had not negatively affected the overall state of the FPP at CR-3. Specifically, the inspectors:

  • verified that the licensee had developed and implemented technically adequate procedures to implement the FPP;
  • verified the proper installation, operability, and maintenance of fire protection systems and equipment; and
  • reviewed the adequacy and implementation of the quality assurance program for the FPP.

The inspection consisted of interviews with Duke Energy personnel, a review of procedures and records, and plant walk-downs.

The inspectors reviewed changes made to CR-3s FPP. The inspectors also reviewed a sample of FPP procedures used for the storage of combustibles and flammables, performance of hot-work, control of ignition sources, and control of transient combustibles to ensure they were in compliance with the CR-3 FPP and adequately reflected the current decommissioning status of the facility. Additionally, the inspectors reviewed fire brigade training, training with off-site responders, qualifications, and responsibilities to ensure they were qualified to participate in firefighting activities. The inspectors performed a walkdown of firefighting equipment and equipment carts to ensure that they were properly maintained, inventoried and ready for use. Pre-fire plans were reviewed to ensure that they were up-dated and reflected the plants decommissioning status.

The inspectors reviewed the installed fire detection, suppression systems, and fire barriers in fire areas associated with the SFP, SFP cooling equipment, SFP power supply, and SFP inventory to ensure that they were maintained, surveillances were performed on a periodic basis, and capable of performing their intended function. This included review of fire pump capability and testing to ensure adequate water and water pressure could be supplied to the necessary systems and standpipes for fire suppression/firefighting activities. Part of this review included review of detection and suppression systems for the cable spreading room which contains a gaseous suppression system (Halon) and the B diesel generator room which contains a sprinkler suppression system. The inspectors also conducted a walk-down of plant detection systems, suppression systems, fire barriers, and fire pumps/water sources to ensure material condition was maintained.

The inspectors reviewed a sample of self-assessments and corrective action documents to ensure the licensee was identifying and placing FPP decommissioning deficiencies into the corrective action program.

Inspection Report No. 05000302/2015008 C:\\Users\\ajk\\Documents\\LDPR-72.2015008.docx

b. Observations and Findings

The inspectors noted that CR-3 maintained the FPP within NRC requirements and the FPP. Fire protection detection systems, suppression systems, barriers, and fire pumps are being maintained and appropriately tested and in a state of operational readiness.

The fire brigade training, qualifications and conduct of fire drills (announced and unannounced) were being properly implemented. The inspectors determined that proper FPP emphasis was placed on SFP systems and components to minimize the potential for radiological releases in the event of a fire at the plant.

The inspectors also noted that changes made to the CR-3 FPP did not reduce its effectiveness and that screenings and evaluations contained the appropriate level of detail and sufficient basis to support the changes. However, this review is not a formal safety evaluation and does not constitute formal NRC approval of the changes.

Therefore, these changes remain subject to future NRC inspections.

c. Conclusions

Based on the results of this inspection, no findings of safety significance were identified.

3.0

Exit Meeting Summary

On July 8, 2015, the inspectors presented the inspection results, via teleconference, to Terry Hobbs, General Manager, and other members of Duke Energys staff. The inspectors confirmed that proprietary information was not removed from the site.

PARTIAL LIST OF PERSONS CONTACTED

Licensee B. Akins, Radiation Protection and Chemistry Manager W. Basnight, Procedures D. Demontfort, Maintenance A. Doruff, Fire Protection Specialist F. Frando, Technical Specialist II, Licensing P. Gerardin, Nuclear Oversight, Lead Assessor R. Ivey, Nuclear Oversight, Corporate Director of Audit & Programs G. McCallum, Operations P. Rose, Licensing I. Wilson, General Manager Decommissioning (Acting)

T. Worthington, Engineering Manager B. Wunderly, Plant Manager

ITEMS OPEN, CLOSED, AND DISCUSSED 05000302/2015008-01 NCV TS Bases Updates Not Submitted At Required Frequencies

LIST OF

DOCUMENTS REVIEWED

Action Request (Condition Reports)

664047, 673234, 680894, 685436, 686427, 686967, 690389, 691739, 693222, 694092,

698726, 700871, 701925, 707158, 708318, 709581, 709689, 714369, 719375, 720264,

21384, 721580, 722097, 724401, 728589, 729925, 730549, 734834, 736107, 737953,

738620, 738973, 740234, 741929, 746903, 747654, 747844, 749664, 753559

Audits and Reports

2014-CR3-FP-01, (NOS) Crystal River Fire Protection Audit, 4/3/14

708467, Self-Assessment Report, B.5.b Spent Fuel Pool Makeup with Two Man Response

Team, 9/16/14

Annual Radioactive Effluent Release Report 2014, Crystal River Unit 3

Annual Radiological Environmental Operating Report 2014, Crystal River Unit 3

Self-Assessment Report, Review of NEIL Standards Prior to Visit, 1/14

Calculations

F13-0003, CR-3 Spent Fuel Pool Time to Uncover Fuel Analysis, Revision 0

N13-0003, Public Dose from a Radioactive Waste Event, Revision 0

Design Basis Documents (DBD)

DBD, Electrical Support Systems Fire Detection System, Revision 3

Enhanced DBD, Fire Service System, Revision 20

Drawings

B-208-031-FS-00, Elementary Diagram, Fire Service System Index, Revision 9

B-208-031-FS-01, Elementary Diagram, Diesel Driven Fire Pump FSP-2A, Revision 20

B-208-031-FS-02, Elementary Diagram, Diesel Driven Fire Pump FSP-2B, Revision 13

B-208-031-FS-03, Elementary Diagram, Motor Driven Fire Service Pump FSP-1, Revision 19

FD-302-2321, Fire Service Water, Revision 93

FD-302-621, Spent Fuel Cooling, Revision 35

FD-302-751, Revision 64

FD-302-752, Revision 39

FD-302-785, Spent Fuel Chilled Water System CH-SF, Revision 2

L-001-022, Revision 50

L-001-023, Revision 29

P-304-783, Addition to Halon System to Cable Spreading Room, Revision 4

Evaluations

AI-9003, Attachment 2 (Hazard Identification), System Evaluation, Categorization and

Abandonment Fire Service Water System, Revision 5

AI-9003, Attachment 2 (SSC Category Determination), System Evaluation, Categorization and

Abandonment Fire Service Water System, Revision 5

Basic Cause Evaluation, Technical Specification Bases Control Program, CR-3 Has Not

Submitted Updates

REG-0100, Attachment 1 - Screen, Partial Abandonment of the RB Purge System, Revision 3

Pre-Fire Plans

AI-2205A, Pre-Fire Plan-Control Complex, Revision 10

AI-2205B, Pre-Fire Plan-Turbine Building, Revision 12

AI-2205C, Pre-Fire Plan-Auxiliary Building, Revision12

AI-2205D, Pre-Fire Plan-Intermediate Building, Revision 6

AI-2205E, Pre-Fire Plan-Reactor Building, Revision 7

AI-2205F, Pre-Fire Plan-Miscellaneous Building and Components, Revision 18

Procedures

AAG-005, Contingencies for Loss of SF Pool Level, Revision 3

AI-151, Reporting Requirement Program, Revision 3

AI-604, Administrative Control of Structures, Material and Equipment Laydown Areas,

Revision 17

AI-1000, Housekeeping/Material Condition Program, Revision 48

AI-2200, Guidelines for Handling use and Control of Transient Combustibles, Revision 13

AI-2205, Administration of CR-3 Fire Brigade Organization and Duties of the Fire Brigade,

Revision 26

AI-2210, Fire Watch Program, Rev. 13

AI-9003, System Evaluation, Categorization and Abandonment, Revision 5

AP-880, Fire Protection, Revision 32

Areva, FS-156, Fuel Assembly Visual Examination using the Mobile Video Rig, Revision 005

Areva, FS-181, Vacuum Sipping Setup and Operation, Revision 008

CP-9300, Fire Protection - Minimum Requirements, Compensatory Measures, and Surveillance

Requirements, Revision 3

EM-216, Duties of the Fire Brigade, Revision 28

EM-220D, Violent Weather (Permanently Defueled), Revision 0

FIR-0003, Hot Work Permit, Revision 1

OPS-1000, Conduct of Operations during Decommissioning, Revision 7

PM-185, Diesel Fire Pump Engine Inspection and Maintenance, Revision 10

REG-0010, 10CFR50.59 and Selected Regulatory Reviews, Rev. 3

SP-363, Fire Protection System Tests, Revision 45

SP-365A, Electric Fire Service Pump, FSP-1 Operability, Revision 25

SP-365B, Diesel Fire Service Pump, FSP-2A Operability, Revision 28

SP-408, Fire System Flow Test, Revision 21

SP-502, Fire Pump Diesel Batteries Weekly Inspection, Revision 23

SP-503, Fire Pump Diesel Batteries Quarterly Check, Revision 21

SP-731A, Auxiliary Building Ventilation Continuous Release, Revision 20

SP-736L, Liquid Releases to the Discharge Canal Via RM-L2, Revision 8

SP-736M, Liquid Releases to the Discharge Canal Via RM-L7, Revision 5

Procedures-Completed Surveillance Procedures

AI-9003, Revision 6, Attachment 2, SSC Category Determination Document, Reactor Building

Purge (AH-XC), Revision 1

PM-175, Fire Door Maintenance, Revision 12, Completed 1/19/15

SP-190J, Cable Spreading Room Fire Detection System Test, Revision 22, Completed 8/6/14

SP-363, Fire Protection System (Fire Pump Tests), Revision 44, Completed 5/6/14

SP-365A, Electric Fire Service Pump, FSP-1 Operability, Revision 25, Completed 3/26/15

SP-365B, Diesel Fire Service Pump FSP-2A Operability, Revision 28, Completed 3/18/15

SP-407, Fire and Flood Barrier Penetration Seals Inspection, Revision 41, Completed 7/15/14

SP-408, Fire System Flow Test, Revision 19, Completed 9/23/11

SP-408, Fire System Flow Test, Revision 21, Completed 9/22/14

SP-411D, Fire Protection for Emergency Diesel Generators, Revision 27, Completed 1/6/15

& 1/9/14

SP-501A, Halon ASC Weight and Pressure Check, Revision 18, Completed 6/17/14

SP-501B, Halon System Functional Test, Revision 24, Completed 2/10/15

SP-502, Fire Pump Diesel Batteries Weekly Inspection, Revision 23, Completed 3/9/15

SP-503, Fire Pump Diesel Batteries Quarterly Check, Revision 20, Completed 1/19/15

SP-607, Fire Barrier Inspection, Revision 34, Completed 3/18/14

SP-800, Monthly Fire Extinguisher Inspections, Revision 52, Completed 1/25/15

SP-802, Fire Hose Hydro Test and Hose Reel Inspection, Revision 39, Completed 9/4/14

SP-804, Surveillance of Plant Fire Brigade Equipment, Revision 59, Completed 3/8/15

SP-805A, Annual Inspection of Plant Fire Doors, Revision 22, Completed 3/17/14

Miscellaneous

Crystal River Unit 3, Licensing Correspondence List

Degraded/OOS Equipment Log (Fire Protection), 5/5/15

EC 0000099162R1, Evaluation of External Flood Re-Definition

Effluent Release SDT-1, L-2015-0014; WDT-11A, L-2015-0012

Fire Brigade Roster, 4/16/15

Fire Team Leader (Incipient) Roster, 4/15/15

Key Safety Function Status Sheet, SF Pool, Work Week 15W15 (4/6/15 - 4/12/15)

MOU for Providing Citrus County Fire Protection Support to the CR-3 Complex, 5/5/14

Off-Site Dose Calculation Manual, Crystal River Unit 3, Revision 35

RWP 1060, Fuel Sipping Activities, Revision 2

Screenings and Reviews

664047, 50.59 Screen, Remove Appendix R and Safe Shutdown from FSAR (92014-007)

680894, 50.59 Screen, Fire Protection Transition to 50.48(f)

693222, 50.59 Screen, Revise Fire Brigade to Reflect SAFSTOR Plant Status

693270, 50.59 Screen, Revise Fire Brigade to Reflect SAFSTOR Plant Status

707158, 50.59 Screen, Changes to Fire Brigade Equipment

719375, 50.59 Screen, Partial Fire System Abandonment

21580, 50.59 Screen, Reg. Review of Fire Barrier Scope Reduction

730549, 50.59 Screen, Misc. Fire Service Procedure Changes for SAFSTOR

740234, 50.59 Screen, Review of Fire Protection Documents for SAFSTOR

Training-Fire Brigade Lessons and Plans

FWB01G/FPQ0001G, Hot work Fire Watch Training, Revision 14

TRF-30, CR-3, Off Site Responder Awareness Training, Revision 3

TRF-050, Initial Incipient Fire Brigade Lesson Plan, Revision 0

TRF-052, Combustion and Fire Behavior, Revision 0

TRF-053, Portable Fire Extinguisher 1, Revision 0

TRF-054, Portable Fire Extinguisher 2, Revision 0

TRF-055, Fire Alarm Systems, Revision 0

TRF-056, Fixed Extinguishing Systems, Revision 0

TRF-057, Fire Hose, Revision 0

TRF-058, Fire Streams and Nozzles, Revision 0

TRF-063, Plant Walk Troughs and Drills, Revision 0

TRF-064, Delta Training, Incipient Fire Brigade, Revision 0

Training-Fire Brigade Drills and Critiques

Unannounced Drill, Control Complex, 4160V ES Switchgear Room A, Completed 5/10/14

Unannounced Drill, Control Complex, 4160V ES Switchgear Room B, Completed 8/16/14

Unannounced Drill, 119 Auxiliary Building (SFP-1A), Completed 9/12/14

Announced Drill, 119 Auxiliary Building (SFP-1B), Completed 10/20/14

Unannounced Drill, CC/Spent Fuel Chiller Systems (CHHE-4A), Completed 1/20/15

Training-Competed Records for Fire Brigade and Fire Watch Qualifications

TRF000, Initial Fire Brigade Training, 1/12/15

TRF001, Fire Brigade Training, 1/12/15

TRF020, Initial Fire Team Leader Training, 1/12/15

TRF025, FTL Fire Suppression Techniques, 1/12/15

TRF026, FTL Fire Prevention Techniques, 1/12/15

TRF064, Incipient Fire Brigade Delta Training, 4/20/15

TRFA, Annual Hands On Fire Brigade Training, 4/20/15

2014 Fire Brigade Annual Drill Completions, 4/20/15

2015 Fire Brigade Drill Completions, 4/20/15

2015 Fire Brigade Annual Training Completions, 4/20/15

2015 Fire Watch Training Completions, 4/14-4/15

2015 Incipient Fire Brigade Qualification Completions, 4/20/15

2015 Incipient Fire Brigade Leader Qualification Completions, 4/20/15

Work Orders

219232, 00219604, 00219605, 01885333, 01935802, 02216993, 02217532, 02273978,

276244, 02284984, 13349913, 13313841, 13355289, 13377003, 13395423, 13455854

LIST OF ACRONYMS USED

CFR

Code of Federal Regulations

CR

Condition Report

CR-3

Crystal River Unit 3

Duke Energy

Duke Energy Florida, Inc.

FPP

Fire Protection Program

FSAR

Final Safety Analysis Report

IMC

Inspection Manual Chapter

ISFSI

Independent Spent Fuel Storage Installation

IP

Inspection Procedure

NRC

U.S. Nuclear Regulatory Commission

NCV

Non-Cited Violation

ODCM

Off-Site Dose Calculation Manual

PSDAR

Post Shutdown Decommissioning Activities Report

REMP

Radiological Environmental Monitoring Program

RWP

Radiation Work Permit

SFP

Spent Fuel Pool

SL

Severity Level

TS

Technical Specifications

UT

Ultrasonic Testing