ML16063A036: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
(5 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML16063A036
| number = ML16063A036
| issue date = 03/21/2016
| issue date = 03/21/2016
| title = 02/05/2016 Summary of Public Meeting with Tennessee Valley Authority Regarding Watts Bar Nuclear Plant, Unit 1, License Amendment Request to Increase Tritium Production (CAC No. MF6050)
| title = Summary of Public Meeting with Tennessee Valley Authority Regarding Watts Bar Nuclear Plant, Unit 1, License Amendment Request to Increase Tritium Production
| author name = Dion J A
| author name = Dion J
| author affiliation = NRC/NRR/DORL/LPLIII-2
| author affiliation = NRC/NRR/DORL/LPLIII-2
| addressee name =  
| addressee name =  
Line 9: Line 9:
| docket = 05000390
| docket = 05000390
| license number = NPF-090
| license number = NPF-090
| contact person = Dion J A
| contact person = Dion J
| case reference number = CAC MF6050
| case reference number = CAC MF6050
| document type = Meeting Summary
| document type = Meeting Summary
Line 23: Line 23:


==SUBJECT:==
==SUBJECT:==
 
==SUMMARY==
SUMMARY OF FEBRUARY 5, 2016, PUBLIC MEETING WITH TENNESSEE VALLEY AUTHORITY REGARDING WATTS BAR NUCLEAR PLANT, UNIT 1, LICENSE AMENDMENT REQUEST TO INCREASE TRITIUM PRODUCTION (CAC NO. MF6050) On February 5, 2016, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Tennessee Valley Authority (TVA) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland.
OF FEBRUARY 5, 2016, PUBLIC MEETING WITH TENNESSEE VALLEY AUTHORITY REGARDING WATTS BAR NUCLEAR PLANT, UNIT 1, LICENSE AMENDMENT REQUEST TO INCREASE TRITIUM PRODUCTION (CAC NO. MF6050)
The purpose of the meeting was to discuss a license amendment request (LAR) to increase the maximum number of tritium-producing burnable absorber rods (TPBARs) permitted to be loaded into the reactor core at the Watts Bar Nuclear Plant (WBN), Unit 1. The meeting notice and agenda, dated January 7, 2016, are available in the Agencywide Documents Access and Management System (ADAMS) under Accession No. ML 16021A349.
On February 5, 2016, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Tennessee Valley Authority (TVA) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss a license amendment request (LAR) to increase the maximum number of tritium-producing burnable absorber rods (TPBARs) permitted to be loaded into the reactor core at the Watts Bar Nuclear Plant (WBN), Unit 1. The meeting notice and agenda, dated January 7, 2016, are available in the Agencywide Documents Access and Management System (ADAMS) under Accession No. ML16021A349. Representatives from the Department of Energy also attended the meeting. A list of attendees is enclosed.
Representatives from the Department of Energy also attended the meeting.
The March 31, 2015 LAR (ADAMS Accession No. ML15098A446), proposed to increase the number of TPBARs allowed to be loaded from 704 to 1,792. TVA supplemented its March 2015 submittal with letters dated May 27, 2015, and June 15, 2015 (ADAMS Accession Nos. ML15147A611 and ML15167A359, respectively). The NRC staff identified several outstanding technical issues in TVA's response dated December 22, 2015 (ADAMS Accession No. ML16054A661 ), to the staff's request for additional information issued on October 2, 2015 (ADAMS Accession No. ML15278A048). The outstanding issues related to demonstrating the adequacy of TVA's tritium control and monitoring to ensure onsite exposures will not result in occupational doses above Title 10 of the Code of Federal Regulations Part 20 limits, and demonstrating that effluent releases under the proposed design-basis assumptions will not exceed the dose limit to a member of the public. These issues were communicated to TVA by e-mail dated January 14, 2016 (ADAMS Accession No. ML16053A023).
A list of attendees is enclosed.
TVA's presentation (ADAMS Accession No. ML16063A025) included a brief summary of the tritium production program background and previous amendments related to tritium production at WBN, Unit 1. The presentation also addressed operating experience, monitoring programs, the proposed tritium source term in the current amendment request, and liquid waste management.
The March 31, 2015 LAR (ADAMS Accession No. ML 15098A446),
TVA's presentation included information regarding its plans to supplement the submittal. TVA stated that the tritium control and monitoring program and the proposed design-basis source term would be revised to address the staff's outstanding issues. In response to a question from the staff, TVA indicated that the proposed source term for the evaluation of accidents in the current submittal would not be changed.
proposed to increase the number of TPBARs allowed to be loaded from 704 to 1 ,792. TVA supplemented its March 2015 submittal with letters dated May 27, 2015, and June 15, 2015 (ADAMS Accession Nos. ML 15147A611 and ML 15167A359, respectively).
TVA indicated it was in the process of evaluating its schedule for providing the supplement and would give the anticipated date for providing the supplement when this evaluation has been completed. Subsequent to the meeting, TVA informed the staff that it would provide the supplement no later than March 31, 2016.
The NRC staff identified several outstanding technical issues in TVA's response dated December 22, 2015 (ADAMS Accession No. ML 16054A661
Members of the public were not in attendance and no Public Meeting Feedback forms were received.
), to the staff's request for additional information issued on October 2, 2015 (ADAMS Accession No. ML 15278A048).
The outstanding issues related to demonstrating the adequacy of TVA's tritium control and monitoring to ensure onsite exposures will not result in occupational doses above Title 10 of the Code of Federal Regulations Part 20 limits, and demonstrating that effluent releases under the proposed design-basis assumptions will not exceed the dose limit to a member of the public. These issues were communicated to TVA by e-mail dated January 14, 2016 (ADAMS Accession No. ML 16053A023).
TVA's presentation (ADAMS Accession No. ML 16063A025) included a brief summary of the tritium production program background and previous amendments related to tritium production at WBN, Unit 1. The presentation also addressed operating experience, monitoring  
: programs, the proposed tritium source term in the current amendment  
: request, and liquid waste management.
TVA's presentation included information regarding its plans to supplement the submittal.
TVA stated that the tritium control and monitoring program and the proposed design-basis source   term would be revised to address the staff's outstanding issues. In response to a question from the staff, TVA indicated that the proposed source term for the evaluation of accidents in the current submittal would not be changed.
TVA indicated it was in the process of evaluating its schedule for providing the supplement and would give the anticipated date for providing the supplement when this evaluation has been completed.
Subsequent to the meeting, TVA informed the staff that it would provide the supplement no later than March 31, 2016. Members of the public were not in attendance and no Public Meeting Feedback forms were received.
Please direct any inquiries to me at (301) 415-1349 or Jeanne.Dion@nrc.gov.
Please direct any inquiries to me at (301) 415-1349 or Jeanne.Dion@nrc.gov.
Docket No. 50-390  
Docket No. 50-390  


==Enclosure:==
==Enclosure:==
List of Attendees cc w/enclosure: Distribution via Listserv
/f)
(',-C'v*--- ~
anne A. Dion, Project Manager Plant Licensing Branch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation


List of Attendees cc w/enclosure:
LIST OF ATTENDEES Licensee:  
Distribution via Listserv
/f) (',-C'v*---anne A. Dion, Project Manager Plant Licensing Branch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation LIST OF ATTENDEES Licensee:  


==Subject:==
==Subject:==
 
Tennessee Valley Authority (TVA)
Tennessee Valley Authority (TVA) License Amendment to Increase Tritium Production Plant: Watts Bar Nuclear Plant, Unit 1 Date: February 5, 2016 Location:
License Amendment to Increase Tritium Production Plant: Watts Bar Nuclear Plant, Unit 1 Date:
U.S. Nuclear Regulatory Commission Time: 9:00 a.m. -10:30 a.m. (NRC) Headquarters, One White Flint North, Room 07-804 NAME TITLE ORGANIZATION NRC/Office of Nuclear Reactor Paul Krohn Acting Deputy Director Regulation (NRR)/Division of Operating Reactor Licensing (DORL) Alex Klein Acting Deputy Director NRC/NRR/Division of Risk Assessment (ORA) Ben Beasley Branch Chief NRC/NRR/DORL/Plant Licensing Branch 11-2 (LPL2-2)
February 5, 2016 Location:
Undine Shoop Branch Chief NRC/NRR/DRA/Radiation Protection and Consequence Branch (ARCS) Robert Schaaf Project Manager NRC/NRR/DORL/LPL2-2 Jeanne Dion Project Manager NRC/NRR/DORL/Plant Licensing Branch 111-2 NRC/NRR/Division of License William Rautzen Health Physicist Renewal/Environmental Review and Project Management Branch Roger Pedersen Senior Health Physicist NRC/NRR/DRA/ARCB Enclosure   NAME TITLE ORGANIZATION Erin Henderson Senior Manager, Fleet Tennessee Valley Authority (TVA) Regulatory Operations Carla Borrelli Senior Program Manager TVA Tritium Production David Brown General Manager, Reactor TVA Engineering and Fuels Doug Pollock Safety Analysis Project TVA Manager Clint Szabo* TVA Ed Schrull*
U.S. Nuclear Regulatory Commission Time: 9:00 a.m. -10:30 a.m.
TVA Bill Sitten* TVA Nanette Founds* Department of Energy (DOE) Curtis Chambellan*
(NRC) Headquarters, One White Flint North, Room 07-804 NAME TITLE ORGANIZATION NRC/Office of Nuclear Reactor Paul Krohn Acting Deputy Director Regulation (NRR)/Division of Operating Reactor Licensing (DORL)
DOE Thomas Hiltz* DOE James Smith* Westinghouse  
Alex Klein Acting Deputy Director NRC/NRR/Division of Risk Assessment (ORA)
*participated via teleconference   term would be revised to address the staff's outstanding issues. In response to a question from the staff, TVA indicated that the proposed source term for the evaluation of accidents in the current submittal would not be changed.
Ben Beasley Branch Chief NRC/NRR/DORL/Plant Licensing Branch 11-2 (LPL2-2)
TVA indicated it was in the process of evaluating its schedule for providing the supplement and would give the anticipated date for providing the supplement when this evaluation has been completed.
Undine Shoop Branch Chief NRC/NRR/DRA/Radiation Protection and Consequence Branch (ARCS)
Subsequent to the meeting, TVA informed the staff that it would provide the supplement no later than March 31, 2016. Members of the public were not in attendance and no Public Meeting Feedback forms were received.
Robert Schaaf Project Manager NRC/NRR/DORL/LPL2-2 Jeanne Dion Project Manager NRC/NRR/DORL/Plant Licensing Branch 111-2 NRC/NRR/Division of License William Rautzen Health Physicist Renewal/Environmental Review and Project Management Branch Roger Pedersen Senior Health Physicist NRC/NRR/DRA/ARCB Enclosure NAME TITLE ORGANIZATION Erin Henderson Senior Manager, Fleet Tennessee Valley Authority (TVA)
Regulatory Operations Carla Borrelli Senior Program Manager TVA Tritium Production David Brown General Manager, Reactor TVA Engineering and Fuels Doug Pollock Safety Analysis Project TVA Manager Clint Szabo*
TVA Ed Schrull*
TVA Bill Sitten*
TVA Nanette Founds*
Department of Energy (DOE)
Curtis Chambellan*
DOE Thomas Hiltz*
DOE James Smith*
Westinghouse  
*participated via teleconference term would be revised to address the staff's outstanding issues. In response to a question from the staff, TVA indicated that the proposed source term for the evaluation of accidents in the current submittal would not be changed.
TVA indicated it was in the process of evaluating its schedule for providing the supplement and would give the anticipated date for providing the supplement when this evaluation has been completed. Subsequent to the meeting, TVA informed the staff that it would provide the supplement no later than March 31, 2016.
Members of the public were not in attendance and no Public Meeting Feedback forms were received.
Please direct any inquiries to me at (301) 415-1349 or Jeanne.Dion@nrc.gov.
Please direct any inquiries to me at (301) 415-1349 or Jeanne.Dion@nrc.gov.
Docket No. 50-390  
Docket No. 50-390  


==Enclosure:==
==Enclosure:==
 
List of Attendees IRA!
List of Attendees IRA! Jeanne A. Dion, Project Manager Plant Licensing Branch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation cc w/enclosure:
Jeanne A. Dion, Project Manager Plant Licensing Branch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation cc w/enclosure: Distribution via Listserv DISTRIBUTION:
Distribution via Listserv DISTRIBUTION:
PUBLIC LPL2-2 R/F RidsNrrPMWattsBar Resource RidsNrrDlrRerb Resource RidsNrrDraArcb Resource RidsOpaMail Resource RidsNrrDorl Resource WRautzen, NRR TWertz, NRR KBucholtz, NRR RPedersen, NRR Watts Bar Resident Inspector RidsNrrLABClayton Resource TClark, OEDO RidsNrrDorllpl2-2 Resource RidsRgn2MailCenter Resource RidsACRS_MailCTR Resource ADAMS A ccess1on N o.: ML16063A036 Pk ML16063A025
PUBLIC LPL2-2 R/F RidsNrrPMWattsBar Resource RidsNrrDlrRerb Resource RidsNrrDraArcb Resource RidsOpaMail Resource RidsNrrDorl Resource  
;g:  
: WRautzen, NRR TWertz, NRR KBucholtz, NRR RPedersen, NRR Watts Bar Resident Inspector RidsNrrLABClayton Resource TClark, OEDO RidsNrrDorllpl2-2 Resource RidsRgn2MailCenter Resource RidsACRS_MailCTR Resource ADAMS A ccess1on N o.: ML 16063A036 Pk ML 16063A025
*1 ema1 concurrence OFFICE NRR/DORL/LPLI 11-2/PM NRR/DORL/LPLll-2/LA NRR/DRNARCB/BC NAME JDion (LRonewicz for) BClayton UShoop*
;g: * *1 ema1 concurrence OFFICE NRR/DORL/LPLI 11-2/PM NRR/DORL/LPLll-2/LA NRR/DRNARCB/BC NAME JDion (LRonewicz for) BClayton UShoop* DATE 3/14/2016 3/07/2016 3/14/2016 OFFICE NRR/DLR/RERB/BC NRR/DORL/LPLll-2/BC N RR/DORL/LP LI 11-2/PM NAME JDanna* BBeasley JDion DATE 3/17/2016 3/17/2016 3/21/2016 OFFICIAL RECORD COPY}}
DATE 3/14/2016 3/07/2016 3/14/2016 OFFICE NRR/DLR/RERB/BC NRR/DORL/LPLll-2/BC N RR/DORL/LP LI 11-2/PM NAME JDanna*
BBeasley JDion DATE 3/17/2016 3/17/2016 3/21/2016 OFFICIAL RECORD COPY}}

Latest revision as of 02:32, 10 January 2025

Summary of Public Meeting with Tennessee Valley Authority Regarding Watts Bar Nuclear Plant, Unit 1, License Amendment Request to Increase Tritium Production
ML16063A036
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 03/21/2016
From: Dion J
Plant Licensing Branch III
To:
Dion J
References
CAC MF6050
Download: ML16063A036 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 M:m:h 21 I 2016 LICENSEE:

Tennessee Valley Authority FACILITY:

Watts Bar Nuclear Plant, Unit 1

SUBJECT:

SUMMARY

OF FEBRUARY 5, 2016, PUBLIC MEETING WITH TENNESSEE VALLEY AUTHORITY REGARDING WATTS BAR NUCLEAR PLANT, UNIT 1, LICENSE AMENDMENT REQUEST TO INCREASE TRITIUM PRODUCTION (CAC NO. MF6050)

On February 5, 2016, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Tennessee Valley Authority (TVA) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss a license amendment request (LAR) to increase the maximum number of tritium-producing burnable absorber rods (TPBARs) permitted to be loaded into the reactor core at the Watts Bar Nuclear Plant (WBN), Unit 1. The meeting notice and agenda, dated January 7, 2016, are available in the Agencywide Documents Access and Management System (ADAMS) under Accession No. ML16021A349. Representatives from the Department of Energy also attended the meeting. A list of attendees is enclosed.

The March 31, 2015 LAR (ADAMS Accession No. ML15098A446), proposed to increase the number of TPBARs allowed to be loaded from 704 to 1,792. TVA supplemented its March 2015 submittal with letters dated May 27, 2015, and June 15, 2015 (ADAMS Accession Nos. ML15147A611 and ML15167A359, respectively). The NRC staff identified several outstanding technical issues in TVA's response dated December 22, 2015 (ADAMS Accession No. ML16054A661 ), to the staff's request for additional information issued on October 2, 2015 (ADAMS Accession No. ML15278A048). The outstanding issues related to demonstrating the adequacy of TVA's tritium control and monitoring to ensure onsite exposures will not result in occupational doses above Title 10 of the Code of Federal Regulations Part 20 limits, and demonstrating that effluent releases under the proposed design-basis assumptions will not exceed the dose limit to a member of the public. These issues were communicated to TVA by e-mail dated January 14, 2016 (ADAMS Accession No. ML16053A023).

TVA's presentation (ADAMS Accession No. ML16063A025) included a brief summary of the tritium production program background and previous amendments related to tritium production at WBN, Unit 1. The presentation also addressed operating experience, monitoring programs, the proposed tritium source term in the current amendment request, and liquid waste management.

TVA's presentation included information regarding its plans to supplement the submittal. TVA stated that the tritium control and monitoring program and the proposed design-basis source term would be revised to address the staff's outstanding issues. In response to a question from the staff, TVA indicated that the proposed source term for the evaluation of accidents in the current submittal would not be changed.

TVA indicated it was in the process of evaluating its schedule for providing the supplement and would give the anticipated date for providing the supplement when this evaluation has been completed. Subsequent to the meeting, TVA informed the staff that it would provide the supplement no later than March 31, 2016.

Members of the public were not in attendance and no Public Meeting Feedback forms were received.

Please direct any inquiries to me at (301) 415-1349 or Jeanne.Dion@nrc.gov.

Docket No. 50-390

Enclosure:

List of Attendees cc w/enclosure: Distribution via Listserv

/f)

(',-C'v*--- ~

anne A. Dion, Project Manager Plant Licensing Branch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

LIST OF ATTENDEES Licensee:

Subject:

Tennessee Valley Authority (TVA)

License Amendment to Increase Tritium Production Plant: Watts Bar Nuclear Plant, Unit 1 Date:

February 5, 2016 Location:

U.S. Nuclear Regulatory Commission Time: 9:00 a.m. -10:30 a.m.

(NRC) Headquarters, One White Flint North, Room 07-804 NAME TITLE ORGANIZATION NRC/Office of Nuclear Reactor Paul Krohn Acting Deputy Director Regulation (NRR)/Division of Operating Reactor Licensing (DORL)

Alex Klein Acting Deputy Director NRC/NRR/Division of Risk Assessment (ORA)

Ben Beasley Branch Chief NRC/NRR/DORL/Plant Licensing Branch 11-2 (LPL2-2)

Undine Shoop Branch Chief NRC/NRR/DRA/Radiation Protection and Consequence Branch (ARCS)

Robert Schaaf Project Manager NRC/NRR/DORL/LPL2-2 Jeanne Dion Project Manager NRC/NRR/DORL/Plant Licensing Branch 111-2 NRC/NRR/Division of License William Rautzen Health Physicist Renewal/Environmental Review and Project Management Branch Roger Pedersen Senior Health Physicist NRC/NRR/DRA/ARCB Enclosure NAME TITLE ORGANIZATION Erin Henderson Senior Manager, Fleet Tennessee Valley Authority (TVA)

Regulatory Operations Carla Borrelli Senior Program Manager TVA Tritium Production David Brown General Manager, Reactor TVA Engineering and Fuels Doug Pollock Safety Analysis Project TVA Manager Clint Szabo*

TVA Ed Schrull*

TVA Bill Sitten*

TVA Nanette Founds*

Department of Energy (DOE)

Curtis Chambellan*

DOE Thomas Hiltz*

DOE James Smith*

Westinghouse

  • participated via teleconference term would be revised to address the staff's outstanding issues. In response to a question from the staff, TVA indicated that the proposed source term for the evaluation of accidents in the current submittal would not be changed.

TVA indicated it was in the process of evaluating its schedule for providing the supplement and would give the anticipated date for providing the supplement when this evaluation has been completed. Subsequent to the meeting, TVA informed the staff that it would provide the supplement no later than March 31, 2016.

Members of the public were not in attendance and no Public Meeting Feedback forms were received.

Please direct any inquiries to me at (301) 415-1349 or Jeanne.Dion@nrc.gov.

Docket No. 50-390

Enclosure:

List of Attendees IRA!

Jeanne A. Dion, Project Manager Plant Licensing Branch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation cc w/enclosure: Distribution via Listserv DISTRIBUTION:

PUBLIC LPL2-2 R/F RidsNrrPMWattsBar Resource RidsNrrDlrRerb Resource RidsNrrDraArcb Resource RidsOpaMail Resource RidsNrrDorl Resource WRautzen, NRR TWertz, NRR KBucholtz, NRR RPedersen, NRR Watts Bar Resident Inspector RidsNrrLABClayton Resource TClark, OEDO RidsNrrDorllpl2-2 Resource RidsRgn2MailCenter Resource RidsACRS_MailCTR Resource ADAMS A ccess1on N o.: ML16063A036 Pk ML16063A025

g
  • 1 ema1 concurrence OFFICE NRR/DORL/LPLI 11-2/PM NRR/DORL/LPLll-2/LA NRR/DRNARCB/BC NAME JDion (LRonewicz for) BClayton UShoop*

DATE 3/14/2016 3/07/2016 3/14/2016 OFFICE NRR/DLR/RERB/BC NRR/DORL/LPLll-2/BC N RR/DORL/LP LI 11-2/PM NAME JDanna*

BBeasley JDion DATE 3/17/2016 3/17/2016 3/21/2016 OFFICIAL RECORD COPY