IR 05000020/2016201: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
(One intermediate revision by the same user not shown)
Line 19: Line 19:


=Text=
=Text=
{{#Wiki_filter:==SUBJECT:==
{{#Wiki_filter:May 11, 2016
MASSACHUSETTS INSTITUTE OF TECHNOLOGY - U.S. NUCLEAR REGULATORY COMMISSION ROUTINE INSPECTION REPORT NO. 50-020/2016-201
 
==SUBJECT:==
MASSACHUSETTS INSTITUTE OF TECHNOLOGY - U.S. NUCLEAR REGULATORY COMMISSION ROUTINE INSPECTION REPORT  
 
NO. 50-020/2016-201


==Dear Dr. Foster:==
==Dear Dr. Foster:==
From April 4-7, 2016, the U.S. Nuclear Regulatory Commission (NRC) conducted an inspection at the Massachusetts Institute of Technology Research Reactor facility. The enclosed report documents the inspection results, which were discussed on April 7, 2016, with you and members of your staff.
From April 4-7, 2016, the U.S. Nuclear Regulatory Commission (NRC) conducted an inspection at the Massachusetts Institute of Technology Research Reactor facility. The enclosed report documents the inspection results, which were discussed on April 7, 2016, with you and members of your staff.


The inspection examined activities conducted under your license as they relate to safety and compliance with NRC's rules and regulations and with the conditions of your license. The inspector reviewed selected procedures and records, observed activities, and interviewed personnel. Based on the results of this inspection, no findings of significance were identified.
The inspection examined activities conducted under your license as they relate to safety and compliance with NRCs rules and regulations and with the conditions of your license. The inspector reviewed selected procedures and records, observed activities, and interviewed personnel. Based on the results of this inspection, no findings of significance were identified.


No response to this letter is required.
No response to this letter is required.


In accordance with Title 10 of the Code of Federal Regulations Section 2.390, "Public inspections, exemptions, requests for withholding," a copy of this letter, its enclosure, and your response (if any) will be available electronica lly for public inspection in the NRC Public Document Room or from the NRC's document system (Agencywide Documents Access and Management System (ADAMS)). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Should you have any questions concerning this inspection, please contact Mr. Johnny H. Eads at (301) 415-0136 or by electronic mail at Johnny.Eads@nrc.gov.
In accordance with Title 10 of the Code of Federal Regulations Section 2.390, Public inspections, exemptions, requests for withholding, a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the NRCs document system (Agencywide Documents Access and Management System (ADAMS)). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Should you have any questions concerning this inspection, please contact Mr. Johnny H. Eads at (301) 415-0136 or by electronic mail at Johnny.Eads@nrc.gov.


Sincerely,
Sincerely,
/RA/
/RA/  
Anthony J. Mendiola, Chief Research and Test Reactors Oversight Branch


Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Docket No. 50-020 License No. R-37  
Anthony J. Mendiola, Chief Research and Test Reactors Oversight Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation  
 
Docket No. 50-020 License No. R-37  


Enclosure:
Enclosure:
Line 42: Line 47:
cc: See next page  
cc: See next page  


ML16127A359; *concurred via e-mail NRC-002 OFFICE NRR/DPR/PROB* NRR/DPR/PROB/LA* NRR/DPR/PROB/BC NAME JEads NParker AMendiola DATE 05/09/2016 05/09/2016 05/11/2016 Massachusetts Institute of Technology Docket No. 50-020 cc:
ML16127A359; *concurred via e-mail NRC-002 OFFICE NRR/DPR/PROB*
City Manager
NRR/DPR/PROB/LA*
NRR/DPR/PROB/BC NAME JEads NParker AMendiola DATE 05/09/2016 05/09/2016 05/11/2016  


City Hall Cambridge, MA 02139  
Massachusetts Institute of Technology Docket No. 50-020
 
cc:
 
City Manager City Hall Cambridge, MA 02139  


Department of Environmental Protection One Winter Street Boston, MA 02108  
Department of Environmental Protection One Winter Street Boston, MA 02108  


Mr. Jack Priest, Director Radiation Control Program Department of Public Health  
Mr. Jack Priest, Director Radiation Control Program Department of Public Health 529 Main Street Schrafft Center, Suite 1M2A Charlestown, MA 02129


529 Main Street
Mr. John Giarrusso, Chief Planning and Preparedness Division Massachusetts Emergency Management Agency 400 Worcester Road Framingham, MA 01702


Schrafft Center, Suite 1M2A Charlestown, MA 02129 Mr. John Giarrusso, Chief Planning and Preparedness Division Massachusetts Emergency Management Agency
Ms. Sarah M. Don (Interim) Superintendent Massachusetts Institute of Technology Nuclear Reactor Laboratory Research Reactor 138 Albany Street, MS NW12-116A Cambridge, MA 02139


400 Worcester Road
Test, Research, and Training Reactor Newsletter University of Florida 202 Nuclear Sciences Center Gainesville, FL 32611


Framingham, MA 01702 Ms. Sarah M. Don (Interim) Superintendent Massachusetts Institute of Technology Nuclear Reactor Laboratory
U. S. NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REACTOR REGULATION


Research Reactor 138 Albany Street, MS NW12-116A Cambridge, MA 02139
Docket No.


Test, Research, and Training
50-020


Reactor Newsletter University of Florida 202 Nuclear Sciences Center Gainesville, FL 32611
License No.


U. S. NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REACTOR REGULATION Docket No. 50-020
R-37


License No. R-37
Report No.


Report No. 50-020/2016-201  
50-020/2016-201  


Licensee: Massachusetts Institute of Technology
Licensee:  


Facility: Nuclear Reactor Laboratory
Massachusetts Institute of Technology


Location: Cambridge, Massachusetts
Facility:  


Dates: April 4-7, 2016
Nuclear Reactor Laboratory


Inspector: Johnny Eads
Location:  


Approved by: Anthony J. Mendiola, Chief Research and Test Reactors Oversight Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation
Cambridge, Massachusetts


EXECUTIVE SUMMARY Massachusetts Institute of Technology Nuclear Reactor Laboratory NRC Inspection Report No. 50-020/2016-201 The primary focus of this routine, announced inspection was the onsite review of selected aspects of the Massachusetts Institute of Technology (the licensee's) Class I six megawatt research reactor safety program including: (1) organization and staffing, (2) reactor operations, (3) operator requalification, (4) maintenance and surveillance, (5) fuel handling, (6) experiments, (7) procedures, and (8) emergency preparedness since the last U.S. Nuclear Regulatory
Dates:  


Commission (NRC) inspection of these areas. The licensee's program was acceptably directed toward the protection of public health and safety and in compliance with NRC requirements.
April 4-7, 2016
 
Inspector:
 
Johnny Eads
 
Approved by:
Anthony J. Mendiola, Chief Research and Test Reactors Oversight Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation
 
EXECUTIVE SUMMARY
 
Massachusetts Institute of Technology Nuclear Reactor Laboratory NRC Inspection Report No. 50-020/2016-201
 
The primary focus of this routine, announced inspection was the onsite review of selected aspects of the Massachusetts Institute of Technology (the licensees) Class I six megawatt research reactor safety program including: (1) organization and staffing, (2) reactor operations, (3) operator requalification, (4) maintenance and surveillance, (5) fuel handling, (6) experiments, (7) procedures, and (8) emergency preparedness since the last U.S. Nuclear Regulatory Commission (NRC) inspection of these areas. The licensees program was acceptably directed toward the protection of public health and safety and in compliance with NRC requirements.


Organization and staffing  
Organization and staffing  
* Organizational structure and staffing were consistent with Technical Specifications (TS)
* Organizational structure and staffing were consistent with Technical Specifications (TS)
requirements.
requirements.


Reactor Operations  
Reactor Operations  
* Reactor operations were conducted in accordance with procedure and the appropriate logs were being maintained.
* Reactor operations were conducted in accordance with procedure and the appropriate logs were being maintained.


Operator Requalification  
Operator Requalification  
* Operator requalification was conducted as required by the Requalification Program and the program was being maintained up-to-date.
* Operator requalification was conducted as required by the Requalification Program and the program was being maintained up-to-date.
 
* Operators were receiving biennial medical examinations as required.
* Operators were receiving biennial medical examinations as required.


Maintenance and Surveillance  
Maintenance and Surveillance  
* The system for tracking and completing maintenance items and surveillance checks and calibrations was adequate and was being maintained as required.
* The system for tracking and completing maintenance items and surveillance checks and calibrations was adequate and was being maintained as required.
 
* Maintenance and surveillance records, performance, and reviews satisfied TS and procedure requirements.
* Maintenance and surveillance records, performance, and reviews satisfied TS and procedure requirements.


Fuel Handling  
Fuel Handling  
* Fuel was being controlled as required and fuel movements were conducted in accordance with TS and procedural requirements.
* Fuel was being controlled as required and fuel movements were conducted in accordance with TS and procedural requirements.


Experiments  
Experiments  
* The program for reviewing and conducting experiments satisfied procedural and TS requirements.
* The program for reviewing and conducting experiments satisfied procedural and TS requirements.


- 2 -Procedures  
- 2 -
* The procedure review, revision, control, and implementation program satisfied TS requirements.
Procedures  
* The procedure review, revision, control, and implementation program satisfied TS requirements.


Emergency Preparedness  
Emergency Preparedness  
* The emergency preparedness program was conduc ted in accordance with the Emergency Plan (E-Plan).
* The emergency preparedness program was conducted in accordance with the Emergency Plan (E-Plan).
 
* Emergency response equipment was being maintained and inventoried as required.
* Emergency response equipment was being maintained and inventoried as required.
* Emergency drills were being conducted annually as required by the E-Plan.
* Emergency drills were being conducted annually as required by the E-Plan.
* Emergency preparedness training for licensed operators and personnel from various support organizations was being completed as required.
* Emergency preparedness training for licensed operators and personnel from various support organizations was being completed as required.


REPORT DETAILS  
REPORT DETAILS  


Summary of Facility Status The Massachusetts Institute of Technology (MIT or the licensee) Nuclear Reactor Laboratory (NRL) six megawatt research reactor continued to be operated in support of experiments, research and service irradiations, reactor operator training, and periodic equipment
Summary of Facility Status  


maintenance and surveillance activities. The reactor has recently been operating Monday through Friday with operations running 24 hours a day. During the inspection the reactor was shutdown for maintenance.
The Massachusetts Institute of Technology (MIT or the licensee) Nuclear Reactor Laboratory (NRL) six megawatt research reactor continued to be operated in support of experiments, research and service irradiations, reactor operator training, and periodic equipment maintenance and surveillance activities. The reactor has recently been operating Monday through Friday with operations running 24 hours a day. During the inspection the reactor was shutdown for maintenance.


1. Organization and Staffing a. Inspection Scope (Inspection Procedure (IP) 69006)
1.
The inspector reviewed the Massachusetts Institute of Technology Reactor (designated as MITR-II) organization and staffing to ensure that the requirements of Technical Specification (TS) 7.1, "Organization," Revision 6, implemented through renewed Facility Operating License R-37, Amendment 40 issued August 13, 2015, were being met regarding the following:  
 
* Management responsibilities  
Organization and Staffing  
* Qualifications of facility operations personnel  
 
* MIT NRL Organization Chart, dated April 1, 2016  
a.
* Reactor Digital Logbook covering the period from March 2015 to present  
 
* Staffing requirements for reactor operation stated in TS 7.1.3  
Inspection Scope (Inspection Procedure (IP) 69006)  
* "MIT Research Reactor, Nuclear Reactor Laboratory, Massachusetts Institute of Technology Annual Report to the U.S. Nuclear Regulatory Commission for the Period January 1, 2015, to December 31, 2015."
 
The inspector reviewed the Massachusetts Institute of Technology Reactor (designated as MITR-II) organization and staffing to ensure that the requirements of Technical Specification (TS) 7.1, Organization, Revision 6, implemented through renewed Facility Operating License R-37, Amendment 40 issued August 13, 2015, were being met regarding the following:  
* Management responsibilities  
*
Qualifications of facility operations personnel  
*
MIT NRL Organization Chart, dated April 1, 2016  
*
Reactor Digital Logbook covering the period from March 2015 to present  
*
Staffing requirements for reactor operation stated in TS 7.1.3  
*
MIT Research Reactor, Nuclear Reactor Laboratory, Massachusetts Institute of Technology Annual Report to the U.S. Nuclear Regulatory Commission for the Period January 1, 2015, to December 31, 2015.
 
b.
 
Observations and Findings
 
The inspector noted that the Director of Reactor Operations (DRO) continued to report to the Director of the MIT NRL, who in turn reported to the President of the university through the Vice President for Research. This organization was consistent with that specified in the TS. The organizational structure and the responsibilities of the reactor staff had not changed since the last inspection.


b. Observations and Findings The inspector noted that the Director of Reactor Operations (DRO) continued to report to the Director of the MIT NRL, who in turn reported to the President of the university through the Vice President for Research. This organization was consistent with that specified in the TS. The organizational structure and the responsibilities of the reactor staff had not changed since the last inspection.
Staffing levels remained consistent with those noted during the last inspection of the facility. The current reactor operations organization consisted of the Interim Director of Reactor Operations, the Assistant Director of Operations and Requalification Program Coordinator, the Interim Superintendent of Operations, the Training Coordinator, a Quality Assurance Supervisor, and various reactor supervisors, and reactor operators (ROs). Since the last inspection, a Director of Reactor Operations - Designate has been assigned. The DRO-Designate is currently completing necessary training per TS to assume the role of DRO. The Interim Director of Reactor Operations, the Assistant Director of Reactor Operations, the Interim Superintendent of Operations, the Quality Assurance


Staffing levels remained consistent with those noted during the last inspection of the facility. The current reactor operations organization consisted of the Interim Director of Reactor Operations, the Assistant Director of Operations and Requalification Program Coordinator, the Interim Superintendent of Operations, the Training Coordinator, a Quality Assurance Supervisor, and various reactor supervisors, and reactor operators (ROs). Since the last inspection, a Director of Reactor Operations - Designate has been assigned. The DRO-Designate is
- 2 -  


currently completing necessary training per TS to assume the role of DRO. The Interim Director of Reactor Operations, the Assistant Director of Reactor Operations, the Interim Superintendent of Operations, the Quality Assurance
Supervisor, the Training Coordinator, and the majority of the reactor supervisors were licensed senior reactor operators (SROs). In addition to the operations staff, there were various support groups, including a research staff, a research development group, a reactor engineering staff, maintenance personnel, and a reactor radiation protection group.
- 2 - Supervisor, the Training Coordinator, and the majority of the reactor supervisors were licensed senior reactor operators (SROs). In addition to the operations staff, there were various support groups, including a research staff, a research development group, a reactor engineering staff, maintenance personnel, and a reactor radiation protection group.


Through a review of reactor operations logs for the period from March 2015 through the present, and through interviews with operations personnel, the inspector determined that the licensee normally operated Monday through Friday, 24 hours a day with three crews and no shift rotation. Each operating crew was staffed with various personnel (with at least two licensed operators on duty at the MITR-II per shift). Operations shifts were scheduled for a period of 8 hours. The review of the reactor (console) logbooks and associated records confirmed that shift staffing during reactor operations met the minimum requirements for duty and on-call personnel specified in TS 7.1.3.
Through a review of reactor operations logs for the period from March 2015 through the present, and through interviews with operations personnel, the inspector determined that the licensee normally operated Monday through Friday, 24 hours a day with three crews and no shift rotation. Each operating crew was staffed with various personnel (with at least two licensed operators on duty at the MITR-II per shift). Operations shifts were scheduled for a period of 8 hours. The review of the reactor (console) logbooks and associated records confirmed that shift staffing during reactor operations met the minimum requirements for duty and on-call personnel specified in TS 7.1.3.


c. Conclusion The licensee's organization and staffing were in compliance with the requirements specified in TS 7.1.
c.
 
Conclusion  
 
The licensees organization and staffing were in compliance with the requirements specified in TS 7.1.
 
2.
 
Reactor Operations
 
a.
 
Inspection Scope (IP 69006)


2. Reactor Operations a. Inspection Scope (IP 69006)
To verify that the licensee was conducting reactor operations in accordance with TS Sections 2 and 3 and procedural requirements, the inspector reviewed selected portions of the following:  
To verify that the licensee was conducting reactor operations in accordance with TS Sections 2 and 3 and procedural requirements, the inspector reviewed selected portions of the following:  
* Reactor Digital Logbook covering the period from March 2015 to present  
* Reactor Digital Logbook covering the period from March 2015 to present  
* "MIT Research Reactor, Nuclear Reactor Laboratory, Massachusetts Institute of Technology Annual Report to the U.S. Nuclear Regulatory Commission for the Period January 1, 2015, to December 31, 2015."
*
MIT Research Reactor, Nuclear Reactor Laboratory, Massachusetts Institute of Technology Annual Report to the U.S. Nuclear Regulatory Commission for the Period January 1, 2015, to December 31, 2015.
 
b.
 
Observations and Findings


b. Observations and Findings (1) Reactor Operation The inspector observed facility activities on various occasions during the week including routine reactor operations and updating the console logs while the reactor was shutdown for maintenance. Written procedures and checklists were used for each activity as required. It was noted that the reactor operators followed the appropriate procedures, were knowledgeable of the required actions, and professional in the conduct of their duties.
(1)
Reactor Operation  


- 3 - (2) Staff Communication During the inspection, the inspector observed reactor operator turnover activities during the shift. The status of the reactor and the facility was discussed on each occasion as required. The oncoming personnel were briefed on the upcoming activities and scheduled events before assuming the operations duty. Through direct observation and records review, the inspector verified that the content of turnover briefings was appropriate and that shift activities and plant conditions were discussed in sufficient
The inspector observed facility activities on various occasions during the week including routine reactor operations and updating the console logs while the reactor was shutdown for maintenance. Written procedures and checklists were used for each activity as required. It was noted that the reactor operators followed the appropriate procedures, were knowledgeable of the required actions, and professional in the conduct of their duties.


detail. c. Conclusion MITR-II reactor operations, as well as turnovers and operator cognizance of facility conditions during routine operations, were acceptable.
- 3 -


3. Operator Requalification a. Inspection Scope (IP 69003)
(2)
To verify that the licensee was complying with the requirements of Title 10 of the
Staff Communication


Code of Federal Regulations (10 CFR) Part 55 and TS 7.2.3.b and conforming to Chapter 12, Sections 12.1 and 12.10 of the facility Safety Analysis Report, the inspector reviewed selected aspects of the following:  
During the inspection, the inspector observed reactor operator turnover activities during the shift. The status of the reactor and the facility was discussed on each occasion as required. The oncoming personnel were briefed on the upcoming activities and scheduled events before assuming the operations duty. Through direct observation and records review, the inspector verified that the content of turnover briefings was appropriate and that shift activities and plant conditions were discussed in sufficient detail.
* Current status of operator licenses  
 
* Reactor Digital Logbook covering the period from March 2015 to present  
c.
* Results of the annual written examinations completed in 2015  
 
* Reactor operator files maintained in the operations office  
Conclusion
* Medical examination records for selected operators for the past 3 years  
 
* Procedure Manual (PM) 1.16, "Requalification and Qualification," latest revision dated February 20, 2013.
MITR-II reactor operations, as well as turnovers and operator cognizance of facility conditions during routine operations, were acceptable.
 
3.
 
Operator Requalification
 
a.
 
Inspection Scope (IP 69003)
 
To verify that the licensee was complying with the requirements of Title 10 of the Code of Federal Regulations (10 CFR) Part 55 and TS 7.2.3.b and conforming to Chapter 12, Sections 12.1 and 12.10 of the facility Safety Analysis Report, the inspector reviewed selected aspects of the following:  
* Current status of operator licenses  
*
Reactor Digital Logbook covering the period from March 2015 to present  
*
Results of the annual written examinations completed in 2015  
*
Reactor operator files maintained in the operations office  
*
Medical examination records for selected operators for the past 3 years  
*
Procedure Manual (PM) 1.16, Requalification and Qualification, latest revision dated February 20, 2013.
 
b.
 
Observations and Findings


b. Observations and Findings There were 22 individuals licensed to operate the reactor at MIT. Of those personnel, 15 were qualified SROs and 7 were ROs. A review of various Requalification Program records indicated that the program was maintained up-to-date and that SRO and RO licenses were current. MITR-II operator files and reactor logs also showed that all operators maintained active duty status with the exception of one SRO and one RO who were designated as inactive by the facility. A review of the MITR Safety Committee (MITRSC) meeting minutes and independent audit results indicated that the program was being audited annually as required by TS 7.2.3.b.
There were 22 individuals licensed to operate the reactor at MIT. Of those personnel, 15 were qualified SROs and 7 were ROs. A review of various Requalification Program records indicated that the program was maintained up-to-date and that SRO and RO licenses were current. MITR-II operator files and reactor logs also showed that all operators maintained active duty status with the exception of one SRO and one RO who were designated as inactive by the facility. A review of the MITR Safety Committee (MITRSC) meeting minutes and independent audit results indicated that the program was being audited annually as required by TS 7.2.3.b.


A review of the pertinent logs and records also showed that training was being conducted in accordance with the licensee's requalification and training program.
A review of the pertinent logs and records also showed that training was being conducted in accordance with the licensees requalification and training program.


A series of lectures were given to operators during the 2 year training and requalification cycle. Information regarding facility changes, procedure changes,  
A series of lectures were given to operators during the 2 year training and requalification cycle. Information regarding facility changes, procedure changes,  
- 4 - and other relevant information was routinely routed to all licensed operators for their review. The inspector verified that the required reactor operations, reactivity manipulations, other operations activities, and reactor supervisor activities were being completed and the appropriate records were being maintained. The inspector also noted that all operators were receiving biennial medical examinations within the time frame allowed as required by the program.


c. Conclusion Operator requalification was up-to-date and being completed as required by the MITR-II Operator Requalification Program. Operators were receiving biennial medical examinations as required.
- 4 -
 
and other relevant information was routinely routed to all licensed operators for their review. The inspector verified that the required reactor operations, reactivity manipulations, other operations activities, and reactor supervisor activities were being completed and the appropriate records were being maintained. The inspector also noted that all operators were receiving biennial medical examinations within the time frame allowed as required by the program.
 
c.
 
Conclusion  
 
Operator requalification was up-to-date and being completed as required by the MITR-II Operator Requalification Program. Operators were receiving biennial medical examinations as required.
 
4.
 
Maintenance and Surveillance
 
a.
 
Inspection Scope (IPs 69006 and 69010)


4. Maintenance and Surveillance a. Inspection Scope (IPs 69006 and 69010)
To verify that the licensee was meeting the surveillance requirements specified in TS Section 4 and that maintenance was being conducted, the inspector reviewed selected aspects of the following:  
To verify that the licensee was meeting the surveillance requirements specified in TS Section 4 and that maintenance was being conducted, the inspector reviewed selected aspects of the following:  
* MITR-II Job Workbook  
* MITR-II Job Workbook  
* MITR-II Daily Operations Schedule  
*
* Reactor Digital Logbook covering the period from March 2015 to present  
MITR-II Daily Operations Schedule  
* "MIT Research Reactor, Nuclear Reactor Laboratory, Massachusetts Institute of Technology Annual Report to the U.S. Nuclear Regulatory Commission for the Period January 1, 2015, to December 31, 2015."
*
Reactor Digital Logbook covering the period from March 2015 to present  
*
MIT Research Reactor, Nuclear Reactor Laboratory, Massachusetts Institute of Technology Annual Report to the U.S. Nuclear Regulatory Commission for the Period January 1, 2015, to December 31, 2015.
 
b.
 
Observations and Findings
 
(1)
Maintenance
 
The inspector reviewed the system that the licensee had developed to track and complete maintenance activities. The system was designed to ensure that all maintenance activities were planned and completed as scheduled, that post maintenance testing was conducted, and that the entire process was documented appropriately. The licensee used a locally developed system called the Test and Calibration Tracker which listed nearly all the tests, checks, and calibrations that were due on a monthly basis, as well as MITR-II Systems, Tests, and Calibrations notebooks to document completion of the various periodic maintenance and surveillance activities. The inspector noted that all such tasks were tracked through this system. The program appeared to be effective.
 
- 5 -
 
(2)
Surveillance
 
Various periodic surveillance verifications and calibration records of equipment, including the testing of various reactor systems, instrumentation, and auxiliary systems were reviewed by the inspector.
 
TS surveillance items were completed on schedule as required by TS and in accordance with licensee procedures. The results of selected tests, checks, and calibrations reviewed by the inspector were noted to be within the TS and procedurally prescribed parameters.


b. Observations and Findings (1) Maintenance The inspector reviewed the system that the licensee had developed to track and complete maintenance activities. The system was designed to ensure that all maintenance activities were planned and completed as scheduled, that post maintenance testing was conducted, and that the entire process was documented appropriately. The licensee used a locally developed system called the "Test and Calibration Tracker" which listed nearly all the tests, checks, and calibrations that were due on a monthly basis, as well as MITR-II "Systems, Tests, and Calibrations" notebooks to document completion of the various periodic maintenance and surveillance activities. The inspector noted that all such tasks were tracked through this system. The program appeared to be effective.
c.


- 5 - (2) Surveillance Various periodic surveillance verifications and calibration records of equipment, including the testing of various reactor systems, instrumentation, and auxiliary systems were reviewed by the inspector. TS surveillance items were completed on schedule as required by TS and in accordance with licensee procedures. The results of selected tests, checks, and calibrations reviewed by the inspector were noted to be within the TS and procedurally prescribed parameters.
Conclusion


c. Conclusion The system for tracking and completing maintenance items and surveillance checks and calibrations was adequate and was being maintained as required.
The system for tracking and completing maintenance items and surveillance checks and calibrations was adequate and was being maintained as required.


Maintenance and surveillance records, performance, and reviews satisfied TS and procedure requirements.
Maintenance and surveillance records, performance, and reviews satisfied TS and procedure requirements.


5. Fuel Handling a. Inspection Scope (IP 69009)
5.
 
Fuel Handling  
 
a.
 
Inspection Scope (IP 69009)  
 
To ensure that the licensee was following the requirements of TS 3.1.4, 3.1.6, 4.1.5, and 5.4, the inspector reviewed selected aspects of the following:  
To ensure that the licensee was following the requirements of TS 3.1.4, 3.1.6, 4.1.5, and 5.4, the inspector reviewed selected aspects of the following:  
* Reactor Digital Logbook covering the period from March 2015 to present  
* Reactor Digital Logbook covering the period from March 2015 to present  
* Approved packets for core configurations completed in 2015 and 2016, including:  
*
"Fuel Loading Permission" Form (form revision dated February 20, 2013), completed for fuel element transfers in 2015 and 2016 to date b. Observations and Findings The inspector reviewed the fuel movement process and verified that fuel moves were conducted according to established procedure and documented on specific fuel movement sheets developed by the previous Director of Reactor Operations or the current Reactor Engineer. The inspector reviewed selected fuel movement sheets for 2015 and to date in 2016. They had been developed and used for each specific core refueling as required.
Approved packets for core configurations completed in 2015 and 2016, including:  


c. Conclusion Fuel was being controlled as required and fuel movements were performed in accordance with approved procedures and TS requirements.
Fuel Loading Permission Form (form revision dated February 20, 2013), completed for fuel element transfers in 2015 and 2016 to date


- 6 - 6. Experiments a. Inspection Scope (IP 69005)
b.
To verify compliance with the licensee's procedures, TS Section 6 and TS 7.5, and 10 CFR 50.59, Changes, Tests and Experiments," the inspector reviewed the follwoing:
* Reactor Digital Logbook covering the period from March 2015 to present
* Experiment Review Process documented in PM 1.10, "Experiment Review and Approval," latest revision dated February 20, 2013.


b. Observations and Findings  
Observations and Findings
 
The inspector reviewed the fuel movement process and verified that fuel moves were conducted according to established procedure and documented on specific fuel movement sheets developed by the previous Director of Reactor Operations or the current Reactor Engineer. The inspector reviewed selected fuel movement sheets for 2015 and to date in 2016. They had been developed and used for each specific core refueling as required.
 
c.
 
Conclusion
 
Fuel was being controlled as required and fuel movements were performed in accordance with approved procedures and TS requirements.
 
- 6 -
 
6.
 
Experiments
 
a.
 
Inspection Scope (IP 69005)
 
To verify compliance with the licensees procedures, TS Section 6 and TS 7.5, and 10 CFR 50.59, Changes, Tests and Experiments, the inspector reviewed the follwoing:
* Reactor Digital Logbook covering the period from March 2015 to present
*
Experiment Review Process documented in PM 1.10, Experiment Review and Approval, latest revision dated February 20, 2013.
 
b.
 
Observations and Findings  


The inspector reviewed the experimental review and approval process described in PM 1.10. The inspector reviewed selected safety review forms and irradiation request forms for experiments that were currently active. The experimental facilities and/or equipment had been evaluated in accordance with TS requirements and the associated data sheets indicated that the experiments would be within the specified limits. The analysis for each had been performed and the reviews and approvals completed. The appropriate reviews and approvals had also been completed for the samples and/or materials to be irradiated and the experiments were conducted under the cognizance of the reactor supervisor and in accordance with the specified requirements.
The inspector reviewed the experimental review and approval process described in PM 1.10. The inspector reviewed selected safety review forms and irradiation request forms for experiments that were currently active. The experimental facilities and/or equipment had been evaluated in accordance with TS requirements and the associated data sheets indicated that the experiments would be within the specified limits. The analysis for each had been performed and the reviews and approvals completed. The appropriate reviews and approvals had also been completed for the samples and/or materials to be irradiated and the experiments were conducted under the cognizance of the reactor supervisor and in accordance with the specified requirements.


c. Conclusion Conduct and control of experiments met the requirements of the TS and the applicable facility procedures.
c.
 
Conclusion  
 
Conduct and control of experiments met the requirements of the TS and the applicable facility procedures.
 
7.
 
Procedures
 
a.
 
Inspection Scope (IP 69008)
 
To verify that the licensee was meeting the requirements of TS Section 7.4, Procedures, the inspectors reviewed selected aspects of the following:
 
PM 1.4, Review and Approval of Plans, Procedures and Facility Equipment and Changes Thereto, which included:
 
-
PM 1.4.1, Plan, Procedure, and Equipment Change Classification, latest revision dated February 20, 2013
-
PM 1.4.2, Class C Review and Approval, latest revision dated February 20, 2013
-
PM 1.4.3, Class B Review and Approval, latest revision dated February 20, 2013
-
PM 1.4.4, Class A Review and Approval, latest revision dated February 20, 2013
 
- 7 -
 
-
PM 1.4.5, Safety Review Form, latest revision dated February 20, 2013
-
PM 1.4.6, Procedure Manuals, latest revision dated February 20, 2013
 
PM 1.5, Procedure Adherence and Temporary Change Method, latest revision dated February 20, 2013


7. Procedures a. Inspection Scope (IP 69008)
b.
To verify that the licensee was meeting the requirements of TS Section 7.4,
"Procedures," the inspectors reviewed selected aspects of the following:
PM 1.4, "Review and Approval of Plans, Procedures and Facility Equipment and Changes Thereto," which included:
- PM 1.4.1, "Plan, Procedure, and Equipment Change Classification," latest revision dated February 20, 2013 - PM 1.4.2, "Class C Review and Approval," latest revision dated February 20, 2013 - PM 1.4.3, "Class B Review and Approval," latest revision dated February 20, 2013 - PM 1.4.4, "Class A Review and Approval," latest revision dated February 20, 2013


- 7 - - PM 1.4.5, "Safety Review Form," latest revision dated February 20, 2013 - PM 1.4.6, "Procedure Manuals," latest revision dated February 20, 2013
Observations and Findings


PM 1.5, "Procedure Adherence and Temporary Change Method," latest revision dated February 20, 2013 b. Observations and Findings The inspector noted that procedures had been developed for reactor operations and safety as required by the TS Section 7.4. The licensee's procedures were found to be acceptable for the current facility status and staffing level. The inspector noted that the administrative procedure specified the responsibilities of the various positions and for the MITRSC.
The inspector noted that procedures had been developed for reactor operations and safety as required by the TS Section 7.4. The licensees procedures were found to be acceptable for the current facility status and staffing level. The inspector noted that the administrative procedure specified the responsibilities of the various positions and for the MITRSC.


Operations procedures were typically reviewed by operators and support personnel prior to being used/implemented and were revised as needed. The inspector noted that abnormal and emergency procedures were reviewed annually by all licensed operators as required and revised when needed. Major procedure revisions were reviewed and approved by the Director of Reactor Operations and submitted to the MITRSC for review. All procedure changes were routinely routed to all operators for review as well.
Operations procedures were typically reviewed by operators and support personnel prior to being used/implemented and were revised as needed. The inspector noted that abnormal and emergency procedures were reviewed annually by all licensed operators as required and revised when needed. Major procedure revisions were reviewed and approved by the Director of Reactor Operations and submitted to the MITRSC for review. All procedure changes were routinely routed to all operators for review as well.
Line 227: Line 401:
It was also noted that management and supervisory oversight was focused on proper implementation and adherence to procedures. Through observation of various activities in progress during the inspection, the inspector noted that adherence to procedures was adequate.
It was also noted that management and supervisory oversight was focused on proper implementation and adherence to procedures. Through observation of various activities in progress during the inspection, the inspector noted that adherence to procedures was adequate.


c. Conclusion Procedures were properly prepared and implemented in compliance with license  
c.
 
Conclusion  
 
Procedures were properly prepared and implemented in compliance with license requirements.
 
8.
 
Emergency Preparedness


requirements.
a.
 
Inspection Scope (IP 69011)
 
The inspector reviewed selected aspects to verify compliance with TS 7.2.3.d and the licensees Emergency Plan and associated procedures of the following:
* Training records for MITR Support Personnel
*
Review and Critique of the 2015 Emergency Exercise conducted on December 16, 2015
*
Review and Critique of the 2015 Medical Emergency Drill conducted on December 8, 2015
*
PM 4.0, MITR-II Emergency Plan and Procedures, revision dated June 20, 2013
*
PM 4.4.4, Emergency Operating Procedures
 
- 8 -
 
b.


8. Emergency Preparedness a. Inspection Scope (IP 69011)
Observations and Findings  
The inspector reviewed selected aspects to verify compliance with TS 7.2.3.d and the licensee's Emergency Plan and associated procedures of the following:
* Training records for MITR Support Personnel
* Review and Critique of the 2015 Emergency Exercise conducted on December 16, 2015
* Review and Critique of the 2015 Medical Emergency Drill conducted on December 8, 2015
* PM 4.0, "MITR-II Emergency Plan and Procedures," revision dated June 20, 2013
* PM 4.4.4, "Emergency Operating Procedures"
- 8 - b. Observations and Findings  


The inspector reviewed the Emergency Plan (E-Plan) and implementing procedures in use at the reactor and verified that the procedures were reviewed annually by all licensed operators in accordance with the Operator Requalification Program.
The inspector reviewed the Emergency Plan (E-Plan) and implementing procedures in use at the reactor and verified that the procedures were reviewed annually by all licensed operators in accordance with the Operator Requalification Program.


Through records reviews and interviews with facility emergency personnel (i.e., licensed operators or emergency responders), the inspector determined that they were knowledgeable of the proper actions to take in case of an emergency.
Through records reviews and interviews with facility emergency personnel (i.e.,
licensed operators or emergency responders), the inspector determined that they were knowledgeable of the proper actions to take in case of an emergency.


Training for staff members had been conducted annually as required and documented acceptably.
Training for staff members had been conducted annually as required and documented acceptably.


Emergency training for MIT Police Department personnel was required to be conducted annually by E-Plan Section 4.10.1.1. The inspector reviewed the training records and noted that the most recent training had been completed as  
Emergency training for MIT Police Department personnel was required to be conducted annually by E-Plan Section 4.10.1.1. The inspector reviewed the training records and noted that the most recent training had been completed as required.
 
The inspector verified that letters of agreement with various emergency support organizations were on file and being maintained.


required.
Communications capabilities with support groups were acceptable and were verified annually through a communications check with the various organizations.


The inspector verified that letters of agreement with various emergency support organizations were on file and being maintained.
Emergency call lists had been revised and updated as needed and were available in various areas of the facility, including in controlled copies of the Emergency Procedures Manuals. The inspector also verified that emergency equipment was being inventoried quarterly as required.
 
The inspector verified compliance with the E-Plan requirement for annual emergency plan drills. The licensee met this requirement by conducting radiological emergency and medical emergency drills each year or by taking credit for an actual emergency. Following each drill, a critique was conducted to identify areas of strength and weakness. Drills and critiques were documented in writing as referenced above. The drills appeared to be challenging and provided a good indication of each organizations responsiveness and capabilities.
 
c.
 
Conclusion


Communications capabilities with support groups were acceptable and were verified annually through a communications check with the various organizations. Emergency call lists had been revised and updated as needed and were available in various areas of the facility, including in controlled copies of the Emergency Procedures Manuals. The inspector also verified that emergency equipment was being inventoried quarterly as required.
The licensee was maintaining acceptable emergency preparedness in accordance with TS and E-Plan requirements.


The inspector verified compliance with the E-Plan requirement for annual emergency plan drills. The licensee met this requirement by conducting radiological emergency and medical emergency drills each year or by taking credit for an actual emergency. Following each drill, a critique was conducted to identify areas of strength and weakness. Drills and critiques were documented in writing as referenced above. The drills appeared to be challenging and provided a good indication of each organization's responsiveness and capabilities.
9.


c. Conclusion The licensee was maintaining acceptable emergency preparedness in accordance with TS and E-Plan requirements.
Exit Interview


9. Exit Interview The inspection scope and results were summarized on April 7, 2016 with members of licensee management. The inspector described the areas inspected and discussed the preliminary inspection findings. The licensee acknowledged the results of the inspection and did not identify as proprietary any of the material provided to or reviewed during the inspection.
The inspection scope and results were summarized on April 7, 2016 with members of licensee management. The inspector described the areas inspected and discussed the preliminary inspection findings. The licensee acknowledged the results of the inspection and did not identify as proprietary any of the material provided to or reviewed during the inspection.


PARTIAL LIST OF PERSONS CONTACTED
PARTIAL LIST OF PERSONS CONTACTED  


Licensee Personnel:  
Licensee Personnel:  


J. Bernard Senior Advisor, Research Staff S. Don Interim Superintendent Operations Interim Director of Reactor Operations E. Lau Assistant Director of Reactor Operations and Requalification Program Coordinator W. McCarthy Reactor Radiation Protection Officer and Deputy Director, MIT Environment, Health, and Safety Office A. Queirolo Director of Reactor Operations - Designate S. Tucker Quality Assurance Supervisor
J. Bernard  
 
Senior Advisor, Research Staff S. Don  
 
Interim Superintendent Operations Interim Director of Reactor Operations E. Lau  
 
Assistant Director of Reactor Operations and Requalification Program  


INSPECTION PROCEDURES USED
Coordinator W. McCarthy Reactor Radiation Protection Officer and Deputy Director, MIT
 
Environment, Health, and Safety Office A. Queirolo
 
Director of Reactor Operations - Designate S. Tucker
 
Quality Assurance Supervisor
 
INSPECTION PROCEDURES USED  


IP 69003 Class 1 Research and Test Reactor Operator Licenses, Requalification, and Medical Examinations IP 69005 Class 1 Research and Test Reactor Experiments IP 69006 Class 1 Research and Test Reactors Organization and Operations and Maintenance Activities IP 69008 Class 1 Procedures IP 69009 Class 1 Research and Test Reactor Fuel Movement IP 69010 Class 1 Research and Test Reactor Surveillance IP 69011 Class 1 Research and Test Reactor Emergency Preparedness  
IP 69003 Class 1 Research and Test Reactor Operator Licenses, Requalification, and Medical Examinations IP 69005 Class 1 Research and Test Reactor Experiments IP 69006 Class 1 Research and Test Reactors Organization and Operations and Maintenance Activities IP 69008 Class 1 Procedures IP 69009 Class 1 Research and Test Reactor Fuel Movement IP 69010 Class 1 Research and Test Reactor Surveillance IP 69011 Class 1 Research and Test Reactor Emergency Preparedness  


ITEMS OPENED, CLOSED, AND DISCUSSED Opened:
ITEMS OPENED, CLOSED, AND DISCUSSED  
None Closed: None LIST OF ACRONYMS USED
 
Opened:  
 
None  
 
Closed:  
 
None  
 
LIST OF ACRONYMS USED  
 
10 CFR Title 10 of the Code of Federal Regulations E-Plan Emergency Plan DRO Director of Reactor Operations IP
 
Inspection Procedure MIT
 
Massachusetts Institute of Technology MITR Massachusetts Institute of Technology Reactor NRC
 
U.S. Nuclear Regulatory Commission NRL
 
Nuclear Reactor Laboratory PM
 
Procedure Manual RO
 
Reactor Operator SRO
 
Senior Reactor Operator TS


10 CFR Title 10 of the Code of Federal Regulations E-Plan Emergency Plan DRO Director of Reactor Operations IP Inspection Procedure MIT Massachusetts Institute of Technology MITR Massachusetts Institute of Technology Reactor NRC U.S. Nuclear Regulatory Commission NRL Nuclear Reactor Laboratory PM Procedure Manual RO Reactor Operator SRO Senior Reactor Operator TS Technical Specification
Technical Specification
}}
}}

Latest revision as of 00:19, 10 January 2025

Massachusetts Institute of Technology, U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000020/2016201, April 4-7, 2016
ML16127A359
Person / Time
Site: MIT Nuclear Research Reactor
Issue date: 05/11/2016
From: Anthony Mendiola
Licensing Processes Branch (DPR)
To: Foster J
Massachusetts Institute of Technology (MIT)
Eads J
References
50-020/2016-201 IR 2016201
Download: ML16127A359 (17)


Text

May 11, 2016

SUBJECT:

MASSACHUSETTS INSTITUTE OF TECHNOLOGY - U.S. NUCLEAR REGULATORY COMMISSION ROUTINE INSPECTION REPORT

NO. 50-020/2016-201

Dear Dr. Foster:

From April 4-7, 2016, the U.S. Nuclear Regulatory Commission (NRC) conducted an inspection at the Massachusetts Institute of Technology Research Reactor facility. The enclosed report documents the inspection results, which were discussed on April 7, 2016, with you and members of your staff.

The inspection examined activities conducted under your license as they relate to safety and compliance with NRCs rules and regulations and with the conditions of your license. The inspector reviewed selected procedures and records, observed activities, and interviewed personnel. Based on the results of this inspection, no findings of significance were identified.

No response to this letter is required.

In accordance with Title 10 of the Code of Federal Regulations Section 2.390, Public inspections, exemptions, requests for withholding, a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the NRCs document system (Agencywide Documents Access and Management System (ADAMS)). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Should you have any questions concerning this inspection, please contact Mr. Johnny H. Eads at (301) 415-0136 or by electronic mail at Johnny.Eads@nrc.gov.

Sincerely,

/RA/

Anthony J. Mendiola, Chief Research and Test Reactors Oversight Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation

Docket No.50-020 License No. R-37

Enclosure:

As stated

cc: See next page

ML16127A359; *concurred via e-mail NRC-002 OFFICE NRR/DPR/PROB*

NRR/DPR/PROB/LA*

NRR/DPR/PROB/BC NAME JEads NParker AMendiola DATE 05/09/2016 05/09/2016 05/11/2016

Massachusetts Institute of Technology Docket No.50-020

cc:

City Manager City Hall Cambridge, MA 02139

Department of Environmental Protection One Winter Street Boston, MA 02108

Mr. Jack Priest, Director Radiation Control Program Department of Public Health 529 Main Street Schrafft Center, Suite 1M2A Charlestown, MA 02129

Mr. John Giarrusso, Chief Planning and Preparedness Division Massachusetts Emergency Management Agency 400 Worcester Road Framingham, MA 01702

Ms. Sarah M. Don (Interim) Superintendent Massachusetts Institute of Technology Nuclear Reactor Laboratory Research Reactor 138 Albany Street, MS NW12-116A Cambridge, MA 02139

Test, Research, and Training Reactor Newsletter University of Florida 202 Nuclear Sciences Center Gainesville, FL 32611

U. S. NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REACTOR REGULATION

Docket No.50-020

License No.

R-37

Report No.

50-020/2016-201

Licensee:

Massachusetts Institute of Technology

Facility:

Nuclear Reactor Laboratory

Location:

Cambridge, Massachusetts

Dates:

April 4-7, 2016

Inspector:

Johnny Eads

Approved by:

Anthony J. Mendiola, Chief Research and Test Reactors Oversight Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation

EXECUTIVE SUMMARY

Massachusetts Institute of Technology Nuclear Reactor Laboratory NRC Inspection Report No. 50-020/2016-201

The primary focus of this routine, announced inspection was the onsite review of selected aspects of the Massachusetts Institute of Technology (the licensees) Class I six megawatt research reactor safety program including: (1) organization and staffing, (2) reactor operations, (3) operator requalification, (4) maintenance and surveillance, (5) fuel handling, (6) experiments, (7) procedures, and (8) emergency preparedness since the last U.S. Nuclear Regulatory Commission (NRC) inspection of these areas. The licensees program was acceptably directed toward the protection of public health and safety and in compliance with NRC requirements.

Organization and staffing

  • Organizational structure and staffing were consistent with Technical Specifications (TS)

requirements.

Reactor Operations

  • Reactor operations were conducted in accordance with procedure and the appropriate logs were being maintained.

Operator Requalification

  • Operator requalification was conducted as required by the Requalification Program and the program was being maintained up-to-date.
  • Operators were receiving biennial medical examinations as required.

Maintenance and Surveillance

  • The system for tracking and completing maintenance items and surveillance checks and calibrations was adequate and was being maintained as required.
  • Maintenance and surveillance records, performance, and reviews satisfied TS and procedure requirements.

Fuel Handling

  • Fuel was being controlled as required and fuel movements were conducted in accordance with TS and procedural requirements.

Experiments

  • The program for reviewing and conducting experiments satisfied procedural and TS requirements.

- 2 -

Procedures

  • The procedure review, revision, control, and implementation program satisfied TS requirements.

Emergency Preparedness

  • Emergency response equipment was being maintained and inventoried as required.
  • Emergency drills were being conducted annually as required by the E-Plan.
  • Emergency preparedness training for licensed operators and personnel from various support organizations was being completed as required.

REPORT DETAILS

Summary of Facility Status

The Massachusetts Institute of Technology (MIT or the licensee) Nuclear Reactor Laboratory (NRL) six megawatt research reactor continued to be operated in support of experiments, research and service irradiations, reactor operator training, and periodic equipment maintenance and surveillance activities. The reactor has recently been operating Monday through Friday with operations running 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> a day. During the inspection the reactor was shutdown for maintenance.

1.

Organization and Staffing

a.

Inspection Scope (Inspection Procedure (IP) 69006)

The inspector reviewed the Massachusetts Institute of Technology Reactor (designated as MITR-II) organization and staffing to ensure that the requirements of Technical Specification (TS) 7.1, Organization, Revision 6, implemented through renewed Facility Operating License R-37, Amendment 40 issued August 13, 2015, were being met regarding the following:

  • Management responsibilities

Qualifications of facility operations personnel

MIT NRL Organization Chart, dated April 1, 2016

Reactor Digital Logbook covering the period from March 2015 to present

Staffing requirements for reactor operation stated in TS 7.1.3

MIT Research Reactor, Nuclear Reactor Laboratory, Massachusetts Institute of Technology Annual Report to the U.S. Nuclear Regulatory Commission for the Period January 1, 2015, to December 31, 2015.

b.

Observations and Findings

The inspector noted that the Director of Reactor Operations (DRO) continued to report to the Director of the MIT NRL, who in turn reported to the President of the university through the Vice President for Research. This organization was consistent with that specified in the TS. The organizational structure and the responsibilities of the reactor staff had not changed since the last inspection.

Staffing levels remained consistent with those noted during the last inspection of the facility. The current reactor operations organization consisted of the Interim Director of Reactor Operations, the Assistant Director of Operations and Requalification Program Coordinator, the Interim Superintendent of Operations, the Training Coordinator, a Quality Assurance Supervisor, and various reactor supervisors, and reactor operators (ROs). Since the last inspection, a Director of Reactor Operations - Designate has been assigned. The DRO-Designate is currently completing necessary training per TS to assume the role of DRO. The Interim Director of Reactor Operations, the Assistant Director of Reactor Operations, the Interim Superintendent of Operations, the Quality Assurance

- 2 -

Supervisor, the Training Coordinator, and the majority of the reactor supervisors were licensed senior reactor operators (SROs). In addition to the operations staff, there were various support groups, including a research staff, a research development group, a reactor engineering staff, maintenance personnel, and a reactor radiation protection group.

Through a review of reactor operations logs for the period from March 2015 through the present, and through interviews with operations personnel, the inspector determined that the licensee normally operated Monday through Friday, 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> a day with three crews and no shift rotation. Each operating crew was staffed with various personnel (with at least two licensed operators on duty at the MITR-II per shift). Operations shifts were scheduled for a period of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. The review of the reactor (console) logbooks and associated records confirmed that shift staffing during reactor operations met the minimum requirements for duty and on-call personnel specified in TS 7.1.3.

c.

Conclusion

The licensees organization and staffing were in compliance with the requirements specified in TS 7.1.

2.

Reactor Operations

a.

Inspection Scope (IP 69006)

To verify that the licensee was conducting reactor operations in accordance with TS Sections 2 and 3 and procedural requirements, the inspector reviewed selected portions of the following:

  • Reactor Digital Logbook covering the period from March 2015 to present

MIT Research Reactor, Nuclear Reactor Laboratory, Massachusetts Institute of Technology Annual Report to the U.S. Nuclear Regulatory Commission for the Period January 1, 2015, to December 31, 2015.

b.

Observations and Findings

(1)

Reactor Operation

The inspector observed facility activities on various occasions during the week including routine reactor operations and updating the console logs while the reactor was shutdown for maintenance. Written procedures and checklists were used for each activity as required. It was noted that the reactor operators followed the appropriate procedures, were knowledgeable of the required actions, and professional in the conduct of their duties.

- 3 -

(2)

Staff Communication

During the inspection, the inspector observed reactor operator turnover activities during the shift. The status of the reactor and the facility was discussed on each occasion as required. The oncoming personnel were briefed on the upcoming activities and scheduled events before assuming the operations duty. Through direct observation and records review, the inspector verified that the content of turnover briefings was appropriate and that shift activities and plant conditions were discussed in sufficient detail.

c.

Conclusion

MITR-II reactor operations, as well as turnovers and operator cognizance of facility conditions during routine operations, were acceptable.

3.

Operator Requalification

a.

Inspection Scope (IP 69003)

To verify that the licensee was complying with the requirements of Title 10 of the Code of Federal Regulations (10 CFR) Part 55 and TS 7.2.3.b and conforming to Chapter 12, Sections 12.1 and 12.10 of the facility Safety Analysis Report, the inspector reviewed selected aspects of the following:

  • Current status of operator licenses

Reactor Digital Logbook covering the period from March 2015 to present

Results of the annual written examinations completed in 2015

Reactor operator files maintained in the operations office

Medical examination records for selected operators for the past 3 years

Procedure Manual (PM) 1.16, Requalification and Qualification, latest revision dated February 20, 2013.

b.

Observations and Findings

There were 22 individuals licensed to operate the reactor at MIT. Of those personnel, 15 were qualified SROs and 7 were ROs. A review of various Requalification Program records indicated that the program was maintained up-to-date and that SRO and RO licenses were current. MITR-II operator files and reactor logs also showed that all operators maintained active duty status with the exception of one SRO and one RO who were designated as inactive by the facility. A review of the MITR Safety Committee (MITRSC) meeting minutes and independent audit results indicated that the program was being audited annually as required by TS 7.2.3.b.

A review of the pertinent logs and records also showed that training was being conducted in accordance with the licensees requalification and training program.

A series of lectures were given to operators during the 2 year training and requalification cycle. Information regarding facility changes, procedure changes,

- 4 -

and other relevant information was routinely routed to all licensed operators for their review. The inspector verified that the required reactor operations, reactivity manipulations, other operations activities, and reactor supervisor activities were being completed and the appropriate records were being maintained. The inspector also noted that all operators were receiving biennial medical examinations within the time frame allowed as required by the program.

c.

Conclusion

Operator requalification was up-to-date and being completed as required by the MITR-II Operator Requalification Program. Operators were receiving biennial medical examinations as required.

4.

Maintenance and Surveillance

a.

Inspection Scope (IPs 69006 and 69010)

To verify that the licensee was meeting the surveillance requirements specified in TS Section 4 and that maintenance was being conducted, the inspector reviewed selected aspects of the following:

  • MITR-II Job Workbook

MITR-II Daily Operations Schedule

Reactor Digital Logbook covering the period from March 2015 to present

MIT Research Reactor, Nuclear Reactor Laboratory, Massachusetts Institute of Technology Annual Report to the U.S. Nuclear Regulatory Commission for the Period January 1, 2015, to December 31, 2015.

b.

Observations and Findings

(1)

Maintenance

The inspector reviewed the system that the licensee had developed to track and complete maintenance activities. The system was designed to ensure that all maintenance activities were planned and completed as scheduled, that post maintenance testing was conducted, and that the entire process was documented appropriately. The licensee used a locally developed system called the Test and Calibration Tracker which listed nearly all the tests, checks, and calibrations that were due on a monthly basis, as well as MITR-II Systems, Tests, and Calibrations notebooks to document completion of the various periodic maintenance and surveillance activities. The inspector noted that all such tasks were tracked through this system. The program appeared to be effective.

- 5 -

(2)

Surveillance

Various periodic surveillance verifications and calibration records of equipment, including the testing of various reactor systems, instrumentation, and auxiliary systems were reviewed by the inspector.

TS surveillance items were completed on schedule as required by TS and in accordance with licensee procedures. The results of selected tests, checks, and calibrations reviewed by the inspector were noted to be within the TS and procedurally prescribed parameters.

c.

Conclusion

The system for tracking and completing maintenance items and surveillance checks and calibrations was adequate and was being maintained as required.

Maintenance and surveillance records, performance, and reviews satisfied TS and procedure requirements.

5.

Fuel Handling

a.

Inspection Scope (IP 69009)

To ensure that the licensee was following the requirements of TS 3.1.4, 3.1.6, 4.1.5, and 5.4, the inspector reviewed selected aspects of the following:

  • Reactor Digital Logbook covering the period from March 2015 to present

Approved packets for core configurations completed in 2015 and 2016, including:

Fuel Loading Permission Form (form revision dated February 20, 2013), completed for fuel element transfers in 2015 and 2016 to date

b.

Observations and Findings

The inspector reviewed the fuel movement process and verified that fuel moves were conducted according to established procedure and documented on specific fuel movement sheets developed by the previous Director of Reactor Operations or the current Reactor Engineer. The inspector reviewed selected fuel movement sheets for 2015 and to date in 2016. They had been developed and used for each specific core refueling as required.

c.

Conclusion

Fuel was being controlled as required and fuel movements were performed in accordance with approved procedures and TS requirements.

- 6 -

6.

Experiments

a.

Inspection Scope (IP 69005)

To verify compliance with the licensees procedures, TS Section 6 and TS 7.5, and 10 CFR 50.59, Changes, Tests and Experiments, the inspector reviewed the follwoing:

  • Reactor Digital Logbook covering the period from March 2015 to present

Experiment Review Process documented in PM 1.10, Experiment Review and Approval, latest revision dated February 20, 2013.

b.

Observations and Findings

The inspector reviewed the experimental review and approval process described in PM 1.10. The inspector reviewed selected safety review forms and irradiation request forms for experiments that were currently active. The experimental facilities and/or equipment had been evaluated in accordance with TS requirements and the associated data sheets indicated that the experiments would be within the specified limits. The analysis for each had been performed and the reviews and approvals completed. The appropriate reviews and approvals had also been completed for the samples and/or materials to be irradiated and the experiments were conducted under the cognizance of the reactor supervisor and in accordance with the specified requirements.

c.

Conclusion

Conduct and control of experiments met the requirements of the TS and the applicable facility procedures.

7.

Procedures

a.

Inspection Scope (IP 69008)

To verify that the licensee was meeting the requirements of TS Section 7.4, Procedures, the inspectors reviewed selected aspects of the following:

PM 1.4, Review and Approval of Plans, Procedures and Facility Equipment and Changes Thereto, which included:

-

PM 1.4.1, Plan, Procedure, and Equipment Change Classification, latest revision dated February 20, 2013

-

PM 1.4.2, Class C Review and Approval, latest revision dated February 20, 2013

-

PM 1.4.3, Class B Review and Approval, latest revision dated February 20, 2013

-

PM 1.4.4, Class A Review and Approval, latest revision dated February 20, 2013

- 7 -

-

PM 1.4.5, Safety Review Form, latest revision dated February 20, 2013

-

PM 1.4.6, Procedure Manuals, latest revision dated February 20, 2013

PM 1.5, Procedure Adherence and Temporary Change Method, latest revision dated February 20, 2013

b.

Observations and Findings

The inspector noted that procedures had been developed for reactor operations and safety as required by the TS Section 7.4. The licensees procedures were found to be acceptable for the current facility status and staffing level. The inspector noted that the administrative procedure specified the responsibilities of the various positions and for the MITRSC.

Operations procedures were typically reviewed by operators and support personnel prior to being used/implemented and were revised as needed. The inspector noted that abnormal and emergency procedures were reviewed annually by all licensed operators as required and revised when needed. Major procedure revisions were reviewed and approved by the Director of Reactor Operations and submitted to the MITRSC for review. All procedure changes were routinely routed to all operators for review as well.

It was also noted that management and supervisory oversight was focused on proper implementation and adherence to procedures. Through observation of various activities in progress during the inspection, the inspector noted that adherence to procedures was adequate.

c.

Conclusion

Procedures were properly prepared and implemented in compliance with license requirements.

8.

Emergency Preparedness

a.

Inspection Scope (IP 69011)

The inspector reviewed selected aspects to verify compliance with TS 7.2.3.d and the licensees Emergency Plan and associated procedures of the following:

  • Training records for MITR Support Personnel

Review and Critique of the 2015 Emergency Exercise conducted on December 16, 2015

Review and Critique of the 2015 Medical Emergency Drill conducted on December 8, 2015

PM 4.0, MITR-II Emergency Plan and Procedures, revision dated June 20, 2013

PM 4.4.4, Emergency Operating Procedures

- 8 -

b.

Observations and Findings

The inspector reviewed the Emergency Plan (E-Plan) and implementing procedures in use at the reactor and verified that the procedures were reviewed annually by all licensed operators in accordance with the Operator Requalification Program.

Through records reviews and interviews with facility emergency personnel (i.e.,

licensed operators or emergency responders), the inspector determined that they were knowledgeable of the proper actions to take in case of an emergency.

Training for staff members had been conducted annually as required and documented acceptably.

Emergency training for MIT Police Department personnel was required to be conducted annually by E-Plan Section 4.10.1.1. The inspector reviewed the training records and noted that the most recent training had been completed as required.

The inspector verified that letters of agreement with various emergency support organizations were on file and being maintained.

Communications capabilities with support groups were acceptable and were verified annually through a communications check with the various organizations.

Emergency call lists had been revised and updated as needed and were available in various areas of the facility, including in controlled copies of the Emergency Procedures Manuals. The inspector also verified that emergency equipment was being inventoried quarterly as required.

The inspector verified compliance with the E-Plan requirement for annual emergency plan drills. The licensee met this requirement by conducting radiological emergency and medical emergency drills each year or by taking credit for an actual emergency. Following each drill, a critique was conducted to identify areas of strength and weakness. Drills and critiques were documented in writing as referenced above. The drills appeared to be challenging and provided a good indication of each organizations responsiveness and capabilities.

c.

Conclusion

The licensee was maintaining acceptable emergency preparedness in accordance with TS and E-Plan requirements.

9.

Exit Interview

The inspection scope and results were summarized on April 7, 2016 with members of licensee management. The inspector described the areas inspected and discussed the preliminary inspection findings. The licensee acknowledged the results of the inspection and did not identify as proprietary any of the material provided to or reviewed during the inspection.

PARTIAL LIST OF PERSONS CONTACTED

Licensee Personnel:

J. Bernard

Senior Advisor, Research Staff S. Don

Interim Superintendent Operations Interim Director of Reactor Operations E. Lau

Assistant Director of Reactor Operations and Requalification Program

Coordinator W. McCarthy Reactor Radiation Protection Officer and Deputy Director, MIT

Environment, Health, and Safety Office A. Queirolo

Director of Reactor Operations - Designate S. Tucker

Quality Assurance Supervisor

INSPECTION PROCEDURES USED

IP 69003 Class 1 Research and Test Reactor Operator Licenses, Requalification, and Medical Examinations IP 69005 Class 1 Research and Test Reactor Experiments IP 69006 Class 1 Research and Test Reactors Organization and Operations and Maintenance Activities IP 69008 Class 1 Procedures IP 69009 Class 1 Research and Test Reactor Fuel Movement IP 69010 Class 1 Research and Test Reactor Surveillance IP 69011 Class 1 Research and Test Reactor Emergency Preparedness

ITEMS OPENED, CLOSED, AND DISCUSSED

Opened:

None

Closed:

None

LIST OF ACRONYMS USED

10 CFR Title 10 of the Code of Federal Regulations E-Plan Emergency Plan DRO Director of Reactor Operations IP

Inspection Procedure MIT

Massachusetts Institute of Technology MITR Massachusetts Institute of Technology Reactor NRC

U.S. Nuclear Regulatory Commission NRL

Nuclear Reactor Laboratory PM

Procedure Manual RO

Reactor Operator SRO

Senior Reactor Operator TS

Technical Specification