ML16204A039: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter:ES-201                                   Examination Preparation Checklist                                         Form ES-201-1 Facility: _Prairie Island Nuclear Generating Plant U1/U2                                 Date of Examination: _06/09/2016 Developed by: Written:         Facility               NRC             // Operating     Facility             NRC Chief Target                                         Task Description (Reference)                                       Examiners Date*
{{#Wiki_filter:ES-201 Examination Preparation Checklist Form ES-201-1 Facility: _Prairie Island Nuclear Generating Plant U1/U2 Date of Examination: _06/09/2016 Developed by: Written:
Initials
Facility NRC  
      -180       1. Examination administration date confirmed (C.1.a; C.2.a and b)                                   dm
//
      -150       2. NRC examiners and facility contact assigned (C.1.d; C.2.e)                                       dm
Operating Facility NRC Target Date*
      -150       3. Facility contact briefed on security and other requirements (C.2.c)                             dm
Task Description (Reference)
      -150       4. Corporate notification letter sent (C.2.d)                                                       dm
Chief Examiners Initials  
[-120]       5. Reference material due (C.1.e; C.3.c; Attachment 3)                                             n/a
-180
{-90}       6. Integrated examination outline(s) due, including Forms ES-201-2, ES-201-3, ES-301-1, ES-301-2, ES-301-5, ES-D-1, ES-401-1/2, ES-401N-1/2, ES-401-3, ES-401N-3,                       dm ES-401-4, and ES-401N-4, as applicable (C.1.e and f; C.3.d)
: 1.
{-85}       7. Examination outline(s) reviewed by NRC and feedback provided to facility licensee dm (C.2.h; C.3.e)
Examination administration date confirmed (C.1.a; C.2.a and b) dm  
{-60}       8. Proposed examinations (including written, walk-through JPMs, and scenarios, as applicable), supporting documentation (including Forms ES-301-3, ES-301-4, ES-301-5, ES-301-6, and ES-401-6, ES-401N-6, and any Form ES-201-2, ES-201-3,                       dm ES-301-1, or ES-301-2 updates), and reference materials due (C.1.e, f, g and h; C.3.d)
-150
        -45       9. Written exam and operating test reviews completed. (C.3.f)                                       dm
: 2.
        -30       10. Preliminary license applications (NRC Form 398's) due (C.1.l; C.2.g; ES-202)                     dm
NRC examiners and facility contact assigned (C.1.d; C.2.e) dm  
        -21       11. Examination approved by NRC supervisor for facility licensee review (C.2.h; C.3.f)               dm
-150
        -21       12. Examinations reviewed with facility licensee (C.1.j; C.2.f and h; C.3.g)                         dm
: 3.
        -14       13. Final license applications due and Form ES-201-4 prepared (C.1.l; C.2.i; ES-202)                 dm
Facility contact briefed on security and other requirements (C.2.c) dm  
        -14       14. Written examinations and operating tests approved by NRC supervisor (C.2.i; dm C.3.h)
-150
        -7       15. Facility licensee management queried regarding the licensees views on the dm examination. (C.2 j)
: 4.
        -7       16. Final applications reviewed; 1 or 2 (if >10) applications audited to confirm qualifications / eligibility; and examination approval and waiver letters sent (C.2.i;         dm Attachment 5; ES-202, C.2.e; ES-204)
Corporate notification letter sent (C.2.d) dm
        -7       17. Proctoring/written exam administration guidelines reviewed with facility licensee dm (C.3.k)
[-120]
        -7       18. Approved scenarios, job performance measures, and questions distributed to NRC dm examiners (C.3.i)
: 5.
Reference material due (C.1.e; C.3.c; Attachment 3) n/a
{-90}
: 6.
Integrated examination outline(s) due, including Forms ES-201-2, ES-201-3, ES-301-1, ES-301-2, ES-301-5, ES-D-1, ES-401-1/2, ES-401N-1/2, ES-401-3, ES-401N-3, ES-401-4, and ES-401N-4, as applicable (C.1.e and f; C.3.d) dm
{-85}
: 7.
Examination outline(s) reviewed by NRC and feedback provided to facility licensee (C.2.h; C.3.e) dm
{-60}
: 8.
Proposed examinations (including written, walk-through JPMs, and scenarios, as applicable), supporting documentation (including Forms ES-301-3, ES-301-4, ES-301-5, ES-301-6, and ES-401-6, ES-401N-6, and any Form ES-201-2, ES-201-3, ES-301-1, or ES-301-2 updates), and reference materials due (C.1.e, f, g and h; C.3.d) dm
-45
: 9.
Written exam and operating test reviews completed. (C.3.f) dm  
-30
: 10.
Preliminary license applications (NRC Form 398's) due (C.1.l; C.2.g; ES-202) dm  
-21
: 11.
Examination approved by NRC supervisor for facility licensee review (C.2.h; C.3.f) dm  
-21
: 12.
Examinations reviewed with facility licensee (C.1.j; C.2.f and h; C.3.g) dm  
-14
: 13.
Final license applications due and Form ES-201-4 prepared (C.1.l; C.2.i; ES-202) dm  
-14
: 14.
Written examinations and operating tests approved by NRC supervisor (C.2.i; C.3.h) dm
-7
: 15.
Facility licensee management queried regarding the licensees views on the examination. (C.2 j) dm
-7
: 16.
Final applications reviewed; 1 or 2 (if >10) applications audited to confirm qualifications / eligibility; and examination approval and waiver letters sent (C.2.i; ; ES-202, C.2.e; ES-204) dm
-7
: 17.
Proctoring/written exam administration guidelines reviewed with facility licensee (C.3.k) dm
-7
: 18.
Approved scenarios, job performance measures, and questions distributed to NRC examiners (C.3.i) dm
* Target dates are generally based on facility-prepared examinations and are keyed to the examination date identified in the corporate notification letter. They are for planning purposes and may be adjusted on a case-by-case basis in coordination with the facility licensee.
* Target dates are generally based on facility-prepared examinations and are keyed to the examination date identified in the corporate notification letter. They are for planning purposes and may be adjusted on a case-by-case basis in coordination with the facility licensee.
[Applies only] {Does not apply} to examinations prepared by the NRC.}}
[Applies only] {Does not apply} to examinations prepared by the NRC.}}

Latest revision as of 21:47, 9 January 2025

2016 Prairie Island Nuclear Generating Plant Initial License Examination Form ES-201-1
ML16204A039
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 06/10/2016
From: Mcneil D
NRC/RGN-III/DRS/OLB
To:
Northern States Power Company, Minnesota
Shared Package
ML15274A272 List:
References
50-282/OL-16-301, 50-306/OL-16-301
Download: ML16204A039 (1)


Text

ES-201 Examination Preparation Checklist Form ES-201-1 Facility: _Prairie Island Nuclear Generating Plant U1/U2 Date of Examination: _06/09/2016 Developed by: Written:

Facility NRC

//

Operating Facility NRC Target Date*

Task Description (Reference)

Chief Examiners Initials

-180

1.

Examination administration date confirmed (C.1.a; C.2.a and b) dm

-150

2.

NRC examiners and facility contact assigned (C.1.d; C.2.e) dm

-150

3.

Facility contact briefed on security and other requirements (C.2.c) dm

-150

4.

Corporate notification letter sent (C.2.d) dm

[-120]

5.

Reference material due (C.1.e; C.3.c; Attachment 3) n/a

{-90}

6.

Integrated examination outline(s) due, including Forms ES-201-2, ES-201-3, ES-301-1, ES-301-2, ES-301-5, ES-D-1, ES-401-1/2, ES-401N-1/2, ES-401-3, ES-401N-3, ES-401-4, and ES-401N-4, as applicable (C.1.e and f; C.3.d) dm

{-85}

7.

Examination outline(s) reviewed by NRC and feedback provided to facility licensee (C.2.h; C.3.e) dm

{-60}

8.

Proposed examinations (including written, walk-through JPMs, and scenarios, as applicable), supporting documentation (including Forms ES-301-3, ES-301-4, ES-301-5, ES-301-6, and ES-401-6, ES-401N-6, and any Form ES-201-2, ES-201-3, ES-301-1, or ES-301-2 updates), and reference materials due (C.1.e, f, g and h; C.3.d) dm

-45

9.

Written exam and operating test reviews completed. (C.3.f) dm

-30

10.

Preliminary license applications (NRC Form 398's) due (C.1.l; C.2.g; ES-202) dm

-21

11.

Examination approved by NRC supervisor for facility licensee review (C.2.h; C.3.f) dm

-21

12.

Examinations reviewed with facility licensee (C.1.j; C.2.f and h; C.3.g) dm

-14

13.

Final license applications due and Form ES-201-4 prepared (C.1.l; C.2.i; ES-202) dm

-14

14.

Written examinations and operating tests approved by NRC supervisor (C.2.i; C.3.h) dm

-7

15.

Facility licensee management queried regarding the licensees views on the examination. (C.2 j) dm

-7

16.

Final applications reviewed; 1 or 2 (if >10) applications audited to confirm qualifications / eligibility; and examination approval and waiver letters sent (C.2.i; ; ES-202, C.2.e; ES-204) dm

-7

17.

Proctoring/written exam administration guidelines reviewed with facility licensee (C.3.k) dm

-7

18.

Approved scenarios, job performance measures, and questions distributed to NRC examiners (C.3.i) dm

  • Target dates are generally based on facility-prepared examinations and are keyed to the examination date identified in the corporate notification letter. They are for planning purposes and may be adjusted on a case-by-case basis in coordination with the facility licensee.

[Applies only] {Does not apply} to examinations prepared by the NRC.