| number = ML16336A832
| number = ML16336A832
| issue date = 12/01/2016
| issue date = 12/01/2016
| title = Palo Verde Nuclear Generating Station, Units 1, 2, & 3 - Notification of Evaluations of Changes, Tests, and Experiments, & Permanent Plant Modifications Inspection (05000528/2017007; 05000529/2017007; and 05000530/2017007) & Request for Inf
| title = Notification of Evaluations of Changes, Tests, and Experiments, & Permanent Plant Modifications Inspection (05000528/2017007; 05000529/2017007; and 05000530/2017007) & Request for Information
| author name = Farnholtz T R
| author name = Farnholtz T
| author affiliation = NRC/RGN-IV/DRS/EB-1
| author affiliation = NRC/RGN-IV/DRS/EB-1
| addressee name = Bement R S
| addressee name = Bement R
| addressee affiliation = Arizona Public Service Co
| addressee affiliation = Arizona Public Service Co
| docket = 05000528, 05000529, 05000530
| docket = 05000528, 05000529, 05000530
Line 14: Line 14:
| page count = 6
| page count = 6
}}
}}
See also: [[followed by::IR 05000528/2017007]]
See also: [[see also::IR 05000528/2017007]]


=Text=
=Text=
{{#Wiki_filter: December 1, 2016  
{{#Wiki_filter:December 1, 2016  
Mr. Robert S. Bement  
Mr. Robert S. Bement  
Executive Vice President Nuclear/  
Executive Vice President Nuclear/  
   Chief Nuclear Officer  
   Chief Nuclear Officer  
Mail Station 7602 Arizona Public Service Company P. O. Box 52034  
Mail Station 7602  
Arizona Public Service Company  
P. O. Box 52034  
Phoenix, AZ 85072-2034  
Phoenix, AZ 85072-2034  
   
   
SUBJECT: PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 -  NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND EXPERIMENTS, AND PERMANENT PLANT MODIFICATIONS  
SUBJECT: PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 -  
   
NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND  
EXPERIMENTS, AND PERMANENT PLANT MODIFICATIONS  
INSPECTION (05000528/2017007; 05000529/2017007; AND 05000530/2017007)  
INSPECTION (05000528/2017007; 05000529/2017007; AND 05000530/2017007)  
AND REQUEST FOR INFORMATION   
AND REQUEST FOR INFORMATION  
Dear Mr. Bement:  The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission (NRC)  
   
staff will conduct the baseline inspection of changes, tests, experiments, and permanent plant modifications at your Palo Verde Nuclear Generating Station, Units 1, 2, and 3, from February 27, 2017, to March 3, 2017.  The inspection will consist of three reactor inspectors from the NRC's Region IV office for one on-site week.  The inspection will be conducted in accordance with NRC Inspection Procedure 71111.17T, "Evaluations of Changes, Tests, and  
Dear Mr. Bement:  
Experiments and Permanent Plant Modifications."    
   
The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission (NRC)  
staff will conduct the baseline inspection of changes, tests, experiments, and permanent  
plant modifications at your Palo Verde Nuclear Generating Station, Units 1, 2, and 3, from  
February 27, 2017, to March 3, 2017.  The inspection will consist of three reactor inspectors  
from the NRCs Region IV office for one on-site week.  The inspection will be conducted in  
accordance with NRC Inspection Procedure 71111.17T, Evaluations of Changes, Tests, and  
Experiments and Permanent Plant Modifications.   
Experience has shown that this inspection is resource intensive for both the NRC inspectors
and your staff.  In order to minimize the impact to your on-site resources and to ensure a
productive inspection, we have enclosed a request for documents needed for this inspection. 
Please note that the documents are requested to be provided by February 15, 2017.  Upon
review of these documents, the inspectors will select additional documentation for review upon
arrival.  It is important that all of these documents are up-to-date and complete in order to
minimize the number of additional documents requested during the preparation and/or the 
on-site portions of the inspection.
   
   
Experience has shown that this inspection is resource intensive for both the NRC inspectors and your staff.  In order to minimize the impact to your on-site resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection. 
Please note that the documents are requested to be provided by February 15, 2017.  Upon review of these documents, the inspectors will select additional documentation for review upon arrival.  It is important that all of these documents are up-to-date and complete in order to minimize the number of additional documents requested during the preparation and/or the  on-site portions of the inspection. 
We have discussed the schedule for these inspection activities with your staff.  If there are any  
We have discussed the schedule for these inspection activities with your staff.  If there are any  
questions about this inspection or the material requested, please contact the lead inspector,  
questions about this inspection or the material requested, please contact the lead inspector,  
James Drake, by telephone at 817-200-1558 or by e-mail at James.Drake@nrc.gov.   UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD ARLINGTON, TX 76011-4511
James Drake, by telephone at 817-200-1558 or by e-mail at James.Drake@nrc.gov.  
R. Bement - 2 -   This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.).  Existing information collection requirements were approved by the Office of Management and Budget, control  
UNITED STATES  
NUCLEAR REGULATORY COMMISSION  
REGION IV  
1600 E. LAMAR BLVD  
ARLINGTON, TX 76011-4511  
 
R. Bement  
- 2 -  
This letter does not contain new or amended information collection requirements subject  
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.).  Existing information  
collection requirements were approved by the Office of Management and Budget, control  
number 3150-0011.  The NRC may not conduct or sponsor, and a person is not required to  
number 3150-0011.  The NRC may not conduct or sponsor, and a person is not required to  
respond to, a request for information or an information collection requirement unless the  
respond to, a request for information or an information collection requirement unless the  
requesting document displays a currently valid Office of Management and Budget control  
requesting document displays a currently valid Office of Management and Budget control  
number.  In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice and Procedure," a copy of  
number.  
this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS).  ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).   Sincerely,   /RA/     Thomas R. Farnholtz, Chief  Engineering Branch 1  
   
  Division of Reactor Safety  Docket Nos. 50-528, 50-529, 50-530 License Nos. NPF-41, NPF-51, NPF-74  
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice and Procedure, a copy of  
this letter and its enclosure will be available electronically for public inspection in the NRC Public  
Document Room or from the Publicly Available Records (PARS) component of NRC's document  
system (ADAMS).  ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).  
Sincerely,  
/RA/  
Thomas R. Farnholtz, Chief  
   
Engineering Branch 1  
   
Division of Reactor Safety  
   
Docket Nos. 50-528, 50-529, 50-530  
License Nos. NPF-41, NPF-51, NPF-74  
   
   
Enclosure:   
Enclosure:   
Request for Information  cc:  Electronic Distribution  
Request for Information  
    
   
cc:  Electronic Distribution  
 
 
   ML16336A832
SUNSI Review
By:  JDrake
ADAMS
Yes    No
Publicly Available
Non-Publicly Available
Non-Sensitive
Sensitive
Keyword:
NRC-002
OFFICE
SRI/DRS
C/DRP/D
C/EB1
NAME
JDrake
GMiller
TFarnholtz
SIGNATURE
/RA/
/RA/
/RA/
DATE
11/30/16
12/1/16
12/1/16


  ML16336A832 SUNSI Review By:  JDrake ADAMS  Yes    No  Publicly Available  Non-Publicly Available  Non-Sensitive  Sensitive Keyword: NRC-002 OFFICE SRI/DRS C/DRP/D C/EB1    NAME JDrake GMiller TFarnholtz    SIGNATURE /RA/ /RA/ /RA/    DATE 11/30/16 12/1/16 12/1/16     
   
Letter to Robert S. Bement from Thomas R. Farnholtz, dated December 1, 2016  
Letter to Robert S. Bement from Thomas R. Farnholtz, dated December 1, 2016  
  SUBJECT: PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 -  NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND EXPERIMENTS, AND PERMANENT PLANT MODIFICATIONS  
   
SUBJECT: PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 -  
   
NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND  
EXPERIMENTS, AND PERMANENT PLANT MODIFICATIONS  
INSPECTION (05000528/2017007; 05000529/2017007; AND 05000530/2017007)  
INSPECTION (05000528/2017007; 05000529/2017007; AND 05000530/2017007)  
AND REQUEST FOR INFORMATION  Electronic distribution by RIV: Regional Administrator (Kriss.Kennedy@nrc.gov) Deputy Regional Administrator (Scott.Morris@nrc.gov)  
AND REQUEST FOR INFORMATION  
   
Electronic distribution by RIV:  
Regional Administrator (Kriss.Kennedy@nrc.gov)  
Deputy Regional Administrator (Scott.Morris@nrc.gov)  
DRP Director (Troy.Pruett@nrc.gov)  
DRP Director (Troy.Pruett@nrc.gov)  
DRP Deputy Director (Ryan.Lantz@nrc.gov) DRS Director (Anton.Vegel@nrc.gov) DRS Deputy Director (Jeff.Clark@nrc.gov)   
DRP Deputy Director (Ryan.Lantz@nrc.gov)  
DRS Director (Anton.Vegel@nrc.gov)  
DRS Deputy Director (Jeff.Clark@nrc.gov)   
Senior Resident Inspector (Charles.Peabody@nrc.gov)  
Senior Resident Inspector (Charles.Peabody@nrc.gov)  
Resident Inspector (David.You@nrc.gov)  
Resident Inspector (David.You@nrc.gov)  
Resident Inspector (Dustin.Reinert@nrc.gov) PV Administrative Assistant (Yvonne.Dubay@nrc.gov) Branch Chief, DRP/D (Geoffrey.Miller@nrc.gov)  
Resident Inspector (Dustin.Reinert@nrc.gov)  
PV Administrative Assistant (Yvonne.Dubay@nrc.gov)  
Branch Chief, DRP/D (Geoffrey.Miller@nrc.gov)  
Senior Project Engineer, DRP/D (John.Dixon@nrc.gov)  
Senior Project Engineer, DRP/D (John.Dixon@nrc.gov)  
Project Engineer, DRP/D (Brian.Parks@nrc.gov)  
Project Engineer, DRP/D (Brian.Parks@nrc.gov)  
Project Engineer, DRP/D (Jan.Tice@nrc.gov)  
Project Engineer, DRP/D (Jan.Tice@nrc.gov)  
Public Affairs Officer (Victor.Dricks@nrc.gov) Project Manager (Siva.Lingam@nrc.gov) Team Leader, DRS/IPAT (Thomas.Hipschman@nrc.gov)  
Public Affairs Officer (Victor.Dricks@nrc.gov)  
Project Manager (Siva.Lingam@nrc.gov)  
Team Leader, DRS/IPAT (Thomas.Hipschman@nrc.gov)  
RITS Coordinator (Marisa.Herrera@nrc.gov)  
RITS Coordinator (Marisa.Herrera@nrc.gov)  
ACES (R4Enforcement.Resource@nrc.gov)  
ACES (R4Enforcement.Resource@nrc.gov)  
Regional Counsel (Karla.Fuller@nrc.gov) Project Engineer, DRS/IPAT (Eduardo.Uribe@nrc.gov) Senior Congressional Affairs Officer (Jenny.Weil@nrc.gov)  
Regional Counsel (Karla.Fuller@nrc.gov)  
Project Engineer, DRS/IPAT (Eduardo.Uribe@nrc.gov)  
Senior Congressional Affairs Officer (Jenny.Weil@nrc.gov)  
RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)  
RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)  
RIV/ETA: OEDO (Jeremy.Bowen@nrc.gov)  
RIV/ETA: OEDO (Jeremy.Bowen@nrc.gov)  
RIV RSLO (Bill.Maier@nrc.gov)  
RIV RSLO (Bill.Maier@nrc.gov)  
 
 
  Enclosure Request for Information Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications Inspection Palo Verde Nuclear Generating Station, Units 1, 2, and 3  
Inspection Report:  05000528/2017007, 05000529/2017007, and 05000530/2017007  
  Inspection Dates:  February 27, 2017 to March 3, 2017   
 
Inspection Procedure: IP 71111.17T, "Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications" Lead Inspector:  James Drake, Senior Reactor Inspector   Information Requested for the In-Office Preparation Week  The following information should be provided to the Region IV office in hard copy or electronic format or via CERTREC (preferred) by February 15, 2017, to the attention of Jim Drake.  We request that you categorize the documents in your response with the numbered list below.  If  
Enclosure  
Request for Information  
Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications  
Inspection  
Palo Verde Nuclear Generating Station, Units 1, 2, and 3  
Inspection Report:   
05000528/2017007, 05000529/2017007, and 05000530/2017007  
   
Inspection Dates:  
   
February 27, 2017 to March 3, 2017  
   
Inspection Procedure:  
IP 71111.17T, Evaluations of Changes, Tests, and Experiments  
and Permanent Plant Modifications  
   
Lead Inspector:  
   
James Drake, Senior Reactor Inspector
Information Requested for the In-Office Preparation Week  
   
The following information should be provided to the Region IV office in hard copy or electronic  
format or via CERTREC (preferred) by February 15, 2017, to the attention of Jim Drake.  We  
request that you categorize the documents in your response with the numbered list below.  If  
only hard copies of the requested documents are available or if the electronic format is too  
only hard copies of the requested documents are available or if the electronic format is too  
large, please inform the lead inspector and provide the documents on the first day of the on-site  
large, please inform the lead inspector and provide the documents on the first day of the on-site  
inspection.  Also, the inspectors will select specific items from the information requested below and request from your staff additional documents needed during the on-site inspection week.  We ask that the specific items requested be available and ready for review on the first day of inspection.  If you have any questions regarding this information request, please contact the  
inspection.  Also, the inspectors will select specific items from the information requested below  
and request from your staff additional documents needed during the on-site inspection week.   
We ask that the specific items requested be available and ready for review on the first day of  
inspection.  If you have any questions regarding this information request, please contact the  
lead inspector as soon as possible.  
lead inspector as soon as possible.  
1. Procedure(s) for conducting 10 CFR 50.59 screenings and evaluations.  2. A list with descriptions of all 10 CFR 50.59 screenings (or equivalent) of fully implemented changes, tests, and experiments performed since the last triennial modification inspection that did not result in an evaluation.  3. A list with descriptions of all 10 CFR 50.59 evaluations of fully implemented changes, tests, and experiments performed since the last triennial modification inspection that did not result in an application for a license amendment.    4. A list with descriptions of all corrective action documents related to 10 CFR 50.59 screenings and evaluations since the last triennial modification inspection.    5. A list of personnel qualified to prepare 10 CFR 50.59 screenings and/or evaluations, including qualification dates.  6. A list of personnel qualified to review and approve 10 CFR 50.59 screenings and/or evaluations, including qualification dates.  7. Procedure(s) for implementing permanent plant modifications. 
  - 2 -  8. A list with descriptions of all permanent plant modifications fully implemented since the last triennial modification inspection.  9. A list with descriptions of all corrective action documents related to permanent plant modifications fully implemented since the last triennial modification inspection.  10. Current revisions of the Technical Specifications and bases and the Updated Final Safety Analysis Report.  11. A copy of the most recent audits/self-assessments performed of the 10 CFR 50.59 and permanent plant modification programs.    12. A copy of the most recent submittal of the report containing a brief description of any changes, tests, and experiments, including a summary of the evaluation of each, required by 10 CFR 50.59(d)(2).    13. A list of systems and system designators and a set of one-line (i.e., simplified) system diagrams.  Note: Descriptions should be brief, but of sufficient detail to ensure that inspectors can determine the safety and/or risk significance of the screenings, evaluations, and
modifications. 
Note:  For this inspection, permanent plant modifications include permanent plant changes, design changes, set point changes, procedure changes, equivalency evaluations, suitability analyses, calculations, and commercial grade dedications.   
   
   
  Lead Inspector Contact Information:   
1. Procedure(s) for conducting 10 CFR 50.59 screenings and evaluations.
   
2. A list with descriptions of all 10 CFR 50.59 screenings (or equivalent) of fully
implemented changes, tests, and experiments performed since the last triennial
modification inspection that did not result in an evaluation. 
3. A list with descriptions of all 10 CFR 50.59 evaluations of fully implemented changes,
tests, and experiments performed since the last triennial modification inspection that did
not result in an application for a license amendment. 
4. A list with descriptions of all corrective action documents related to 10 CFR 50.59
screenings and evaluations since the last triennial modification inspection. 
5. A list of personnel qualified to prepare 10 CFR 50.59 screenings and/or evaluations,
including qualification dates.
6. A list of personnel qualified to review and approve 10 CFR 50.59 screenings and/or
evaluations, including qualification dates.
7. Procedure(s) for implementing permanent plant modifications.
 
- 2 -
8. A list with descriptions of all permanent plant modifications fully implemented since the
last triennial modification inspection. 
9. A list with descriptions of all corrective action documents related to permanent plant
modifications fully implemented since the last triennial modification inspection. 
10. Current revisions of the Technical Specifications and bases and the Updated Final
Safety Analysis Report.
11. A copy of the most recent audits/self-assessments performed of the 10 CFR 50.59 and
permanent plant modification programs. 
12. A copy of the most recent submittal of the report containing a brief description of any
changes, tests, and experiments, including a summary of the evaluation of each,
required by 10 CFR 50.59(d)(2). 
13. A list of systems and system designators and a set of one-line (i.e., simplified) system
diagrams.
Note: Descriptions should be brief, but of sufficient detail to ensure that inspectors can
determine the safety and/or risk significance of the screenings, evaluations, and
modifications.
Note:  For this inspection, permanent plant modifications include permanent plant changes,
design changes, set point changes, procedure changes, equivalency evaluations,
suitability analyses, calculations, and commercial grade dedications. 
Lead Inspector Contact Information:  
   
James Drake   
James Drake   
Senior Reactor Inspector  
Senior Reactor Inspector  
817-200-1558  
817-200-1558  
James.Drake@nrc.gov  
James.Drake@nrc.gov  
Mailing Address:  
Mailing Address:  
   
   
U.S. NRC, Region IV ATTN:  James Drake 1600 East Lamar Blvd.  
U.S. NRC, Region IV  
Arlington, TX  76011-4125  
ATTN:  James Drake  
 
1600 East Lamar Blvd.  
 
Arlington, TX  76011-4125
}}
}}

Latest revision as of 18:53, 9 January 2025

Notification of Evaluations of Changes, Tests, and Experiments, & Permanent Plant Modifications Inspection (05000528/2017007; 05000529/2017007; and 05000530/2017007) & Request for Information
ML16336A832
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 12/01/2016
From: Thomas Farnholtz
Region 4 Engineering Branch 1
To: Bement R
Arizona Public Service Co
References
IR 2017007
Download: ML16336A832 (6)


See also: IR 05000528/2017007

Text

December 1, 2016

Mr. Robert S. Bement

Executive Vice President Nuclear/

Chief Nuclear Officer

Mail Station 7602

Arizona Public Service Company

P. O. Box 52034

Phoenix, AZ 85072-2034

SUBJECT: PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 -

NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND

EXPERIMENTS, AND PERMANENT PLANT MODIFICATIONS

INSPECTION (05000528/2017007; 05000529/2017007; AND 05000530/2017007)

AND REQUEST FOR INFORMATION

Dear Mr. Bement:

The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission (NRC)

staff will conduct the baseline inspection of changes, tests, experiments, and permanent

plant modifications at your Palo Verde Nuclear Generating Station, Units 1, 2, and 3, from

February 27, 2017, to March 3, 2017. The inspection will consist of three reactor inspectors

from the NRCs Region IV office for one on-site week. The inspection will be conducted in

accordance with NRC Inspection Procedure 71111.17T, Evaluations of Changes, Tests, and

Experiments and Permanent Plant Modifications.

Experience has shown that this inspection is resource intensive for both the NRC inspectors

and your staff. In order to minimize the impact to your on-site resources and to ensure a

productive inspection, we have enclosed a request for documents needed for this inspection.

Please note that the documents are requested to be provided by February 15, 2017. Upon

review of these documents, the inspectors will select additional documentation for review upon

arrival. It is important that all of these documents are up-to-date and complete in order to

minimize the number of additional documents requested during the preparation and/or the

on-site portions of the inspection.

We have discussed the schedule for these inspection activities with your staff. If there are any

questions about this inspection or the material requested, please contact the lead inspector,

James Drake, by telephone at 817-200-1558 or by e-mail at James.Drake@nrc.gov.

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION IV

1600 E. LAMAR BLVD

ARLINGTON, TX 76011-4511

R. Bement

- 2 -

This letter does not contain new or amended information collection requirements subject

to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information

collection requirements were approved by the Office of Management and Budget, control

number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to

respond to, a request for information or an information collection requirement unless the

requesting document displays a currently valid Office of Management and Budget control

number.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice and Procedure, a copy of

this letter and its enclosure will be available electronically for public inspection in the NRC Public

Document Room or from the Publicly Available Records (PARS) component of NRC's document

system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Thomas R. Farnholtz, Chief

Engineering Branch 1

Division of Reactor Safety

Docket Nos. 50-528, 50-529, 50-530

License Nos. NPF-41, NPF-51, NPF-74

Enclosure:

Request for Information

cc: Electronic Distribution

ML16336A832

SUNSI Review

By: JDrake

ADAMS

Yes No

Publicly Available

Non-Publicly Available

Non-Sensitive

Sensitive

Keyword:

NRC-002

OFFICE

SRI/DRS

C/DRP/D

C/EB1

NAME

JDrake

GMiller

TFarnholtz

SIGNATURE

/RA/

/RA/

/RA/

DATE

11/30/16

12/1/16

12/1/16

Letter to Robert S. Bement from Thomas R. Farnholtz, dated December 1, 2016

SUBJECT: PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 -

NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND

EXPERIMENTS, AND PERMANENT PLANT MODIFICATIONS

INSPECTION (05000528/2017007; 05000529/2017007; AND 05000530/2017007)

AND REQUEST FOR INFORMATION

Electronic distribution by RIV:

Regional Administrator (Kriss.Kennedy@nrc.gov)

Deputy Regional Administrator (Scott.Morris@nrc.gov)

DRP Director (Troy.Pruett@nrc.gov)

DRP Deputy Director (Ryan.Lantz@nrc.gov)

DRS Director (Anton.Vegel@nrc.gov)

DRS Deputy Director (Jeff.Clark@nrc.gov)

Senior Resident Inspector (Charles.Peabody@nrc.gov)

Resident Inspector (David.You@nrc.gov)

Resident Inspector (Dustin.Reinert@nrc.gov)

PV Administrative Assistant (Yvonne.Dubay@nrc.gov)

Branch Chief, DRP/D (Geoffrey.Miller@nrc.gov)

Senior Project Engineer, DRP/D (John.Dixon@nrc.gov)

Project Engineer, DRP/D (Brian.Parks@nrc.gov)

Project Engineer, DRP/D (Jan.Tice@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Project Manager (Siva.Lingam@nrc.gov)

Team Leader, DRS/IPAT (Thomas.Hipschman@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

ACES (R4Enforcement.Resource@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Project Engineer, DRS/IPAT (Eduardo.Uribe@nrc.gov)

Senior Congressional Affairs Officer (Jenny.Weil@nrc.gov)

RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)

RIV/ETA: OEDO (Jeremy.Bowen@nrc.gov)

RIV RSLO (Bill.Maier@nrc.gov)

Enclosure

Request for Information

Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications

Inspection

Palo Verde Nuclear Generating Station, Units 1, 2, and 3

Inspection Report: 05000528/2017007, 05000529/2017007, and 05000530/2017007

Inspection Dates:

February 27, 2017 to March 3, 2017

Inspection Procedure:

IP 71111.17T, Evaluations of Changes, Tests, and Experiments

and Permanent Plant Modifications

Lead Inspector:

James Drake, Senior Reactor Inspector

Information Requested for the In-Office Preparation Week

The following information should be provided to the Region IV office in hard copy or electronic

format or via CERTREC (preferred) by February 15, 2017, to the attention of Jim Drake. We

request that you categorize the documents in your response with the numbered list below. If

only hard copies of the requested documents are available or if the electronic format is too

large, please inform the lead inspector and provide the documents on the first day of the on-site

inspection. Also, the inspectors will select specific items from the information requested below

and request from your staff additional documents needed during the on-site inspection week.

We ask that the specific items requested be available and ready for review on the first day of

inspection. If you have any questions regarding this information request, please contact the

lead inspector as soon as possible.

1. Procedure(s) for conducting 10 CFR 50.59 screenings and evaluations.

2. A list with descriptions of all 10 CFR 50.59 screenings (or equivalent) of fully

implemented changes, tests, and experiments performed since the last triennial

modification inspection that did not result in an evaluation.

3. A list with descriptions of all 10 CFR 50.59 evaluations of fully implemented changes,

tests, and experiments performed since the last triennial modification inspection that did

not result in an application for a license amendment.

4. A list with descriptions of all corrective action documents related to 10 CFR 50.59

screenings and evaluations since the last triennial modification inspection.

5. A list of personnel qualified to prepare 10 CFR 50.59 screenings and/or evaluations,

including qualification dates.

6. A list of personnel qualified to review and approve 10 CFR 50.59 screenings and/or

evaluations, including qualification dates.

7. Procedure(s) for implementing permanent plant modifications.

- 2 -

8. A list with descriptions of all permanent plant modifications fully implemented since the

last triennial modification inspection.

9. A list with descriptions of all corrective action documents related to permanent plant

modifications fully implemented since the last triennial modification inspection.

10. Current revisions of the Technical Specifications and bases and the Updated Final

Safety Analysis Report.

11. A copy of the most recent audits/self-assessments performed of the 10 CFR 50.59 and

permanent plant modification programs.

12. A copy of the most recent submittal of the report containing a brief description of any

changes, tests, and experiments, including a summary of the evaluation of each,

required by 10 CFR 50.59(d)(2).

13. A list of systems and system designators and a set of one-line (i.e., simplified) system

diagrams.

Note: Descriptions should be brief, but of sufficient detail to ensure that inspectors can

determine the safety and/or risk significance of the screenings, evaluations, and

modifications.

Note: For this inspection, permanent plant modifications include permanent plant changes,

design changes, set point changes, procedure changes, equivalency evaluations,

suitability analyses, calculations, and commercial grade dedications.

Lead Inspector Contact Information:

James Drake

Senior Reactor Inspector

817-200-1558

James.Drake@nrc.gov

Mailing Address:

U.S. NRC, Region IV

ATTN: James Drake

1600 East Lamar Blvd.

Arlington, TX 76011-4125