| number = ML17233A361 | | number = ML17233A361 | ||
| issue date = 08/21/2017 | | issue date = 08/21/2017 | ||
| title = | | title = NRC Material Control and Accounting Program Inspection Report 05000275/2017406 and 05000323/2017406 | ||
| author name = Gepford H | | author name = Gepford H | ||
| author affiliation = NRC/RGN-IV/DRS/PSB-2 | | author affiliation = NRC/RGN-IV/DRS/PSB-2 | ||
| addressee name = Halpin E | | addressee name = Halpin E | ||
| addressee affiliation = Pacific Gas & Electric Co | | addressee affiliation = Pacific Gas & Electric Co | ||
| docket = 05000275, 05000323 | | docket = 05000275, 05000323 | ||
| Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter | {{#Wiki_filter:August 21, 2017 | ||
==SUBJECT:== | |||
DIABLO CANYON POWER PLANT, UNITS 1 AND 2 - NRC MATERIAL CONTROL AND ACCOUNTING PROGRAM INSPECTION REPORT 05000275/2017406 AND 05000323/2017406 | |||
==Dear Mr. Halpin:== | |||
On August 3, 2017, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at Diablo Canyon. The inspection covered a key attribute of the Security Cornerstone of the NRCs Reactor Oversight Process, Material Control and Accounting of Special Nuclear Material. The enclosed inspection report documents the inspection results, which were discussed on August 3, 2017, with Mr. K. Johnston, Acting Site Director, and other members of your staff. | |||
The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license. | |||
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel. | |||
Based on the results of this inspection, no findings were identified. | |||
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRCs document system, (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection. | |||
UNITED STATES NUCLEAR REGULATORY COMMISSION | |||
==REGION IV== | |||
1600 E. LAMAR BLVD ARLINGTON, TX 76011-4511 In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRCs document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response "Security-Related Information-Withhold Under 10 CFR 2.390" and follow the instructions for withholding in 10 CFR 2.390(b)(1). | |||
Sincerely, | |||
/RA/ | |||
Heather J. Gepford, PhD., CHP, Chief | |||
Plant Support Branch 2 | |||
Division of Reactor Safety | |||
Docket Nos. 50-275 and 50-323 License Nos. DPR-80 and DPR-82 | Docket Nos. 50-275 and 50-323 License Nos. DPR-80 and DPR-82 | ||
Nonpublic | Nonpublic Enclosure: | ||
NRC Inspection Report 05000275/2010406; 05000323/2010406 w/Attachment: | |||
1. Supplemental Information 2. Request for Information | |||
cc w/o enclosure: Electronic Distribution | |||
ML17233A360 Entire Report: | |||
ADAMS: | |||
Non-Publicly Available Non-Sensitive Keyword: | |||
SUNSI Review By: | |||
Yes No Publicly Available Sensitive _______MD 3.4 A.3 | |||
ADAMS ACCESSION NUMBER: ML17233A361 Cover Letter Only: | |||
NRC | ADAMS: | ||
Non-Publicly Available Non-Sensitive Keyword: | |||
SUNSI Review By: | |||
Yes No Publicly Available Sensitive NRC-002 OFFICE HP:PSB2 C:PSB2 C:PBA C:PSB2 | |||
NAME JODonnell HGepford MHaire HGepford | |||
SIGNATURE | |||
/RA/ | |||
/RA/ | |||
/RA/ | |||
/RA/ | |||
DATE 8/17/17 8/21/17 8/21/17 8/ 21/17 | DATE 8/17/17 8/21/17 8/21/17 8/ 21/17 | ||
}} | }} | ||
Latest revision as of 12:54, 8 January 2025
| ML17233A361 | |
| Person / Time | |
|---|---|
| Site: | Diablo Canyon |
| Issue date: | 08/21/2017 |
| From: | Heather Gepford NRC/RGN-IV/DRS/PSB-2 |
| To: | Halpin E Pacific Gas & Electric Co |
| References | |
| IR 2017406 | |
| Download: ML17233A361 (3) | |
Text
August 21, 2017
SUBJECT:
DIABLO CANYON POWER PLANT, UNITS 1 AND 2 - NRC MATERIAL CONTROL AND ACCOUNTING PROGRAM INSPECTION REPORT 05000275/2017406 AND 05000323/2017406
Dear Mr. Halpin:
On August 3, 2017, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at Diablo Canyon. The inspection covered a key attribute of the Security Cornerstone of the NRCs Reactor Oversight Process, Material Control and Accounting of Special Nuclear Material. The enclosed inspection report documents the inspection results, which were discussed on August 3, 2017, with Mr. K. Johnston, Acting Site Director, and other members of your staff.
The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
Based on the results of this inspection, no findings were identified.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRCs document system, (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.
UNITED STATES NUCLEAR REGULATORY COMMISSION
REGION IV
1600 E. LAMAR BLVD ARLINGTON, TX 76011-4511 In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRCs document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response "Security-Related Information-Withhold Under 10 CFR 2.390" and follow the instructions for withholding in 10 CFR 2.390(b)(1).
Sincerely,
/RA/
Heather J. Gepford, PhD., CHP, Chief
Plant Support Branch 2
Division of Reactor Safety
Docket Nos. 50-275 and 50-323 License Nos. DPR-80 and DPR-82
Nonpublic Enclosure:
NRC Inspection Report 05000275/2010406; 05000323/2010406 w/Attachment:
1. Supplemental Information 2. Request for Information
cc w/o enclosure: Electronic Distribution
ML17233A360 Entire Report:
ADAMS:
Non-Publicly Available Non-Sensitive Keyword:
SUNSI Review By:
Yes No Publicly Available Sensitive _______MD 3.4 A.3
ADAMS ACCESSION NUMBER: ML17233A361 Cover Letter Only:
ADAMS:
Non-Publicly Available Non-Sensitive Keyword:
SUNSI Review By:
Yes No Publicly Available Sensitive NRC-002 OFFICE HP:PSB2 C:PSB2 C:PBA C:PSB2
NAME JODonnell HGepford MHaire HGepford
SIGNATURE
/RA/
/RA/
/RA/
/RA/
DATE 8/17/17 8/21/17 8/21/17 8/ 21/17