{{#Wiki_filter: | {{#Wiki_filter:December 12, 2017 | ||
05000324/2017302 | ==SUBJECT:== | ||
BRUNSWICK NUCLEAR POWER PLANT - (RETAKE) OPERATOR LICENSING EXAMINATION APPROVAL 05000325/2017302 AND 05000324/2017302 | |||
==Dear Mr. Hicks:== | ==Dear Mr. Hicks:== | ||
The purpose of this letter is to confirm the final arrangements for the upcoming retake operator licensing examination at the Brunswick Nuclear Power Plant. | The purpose of this letter is to confirm the final arrangements for the upcoming retake operator licensing examination at the Brunswick Nuclear Power Plant. | ||
The U.S. Nuclear Regulatory Commission (NRC) has approved the subject examination. The NRC staff will administer the operating test during the week of December 11, 2017. The list of the applicants approved to take the examination has been provided to Mr. Mark Similey, Operations Training Manager. The examination has undergone extensive review by my staff and representatives responsible for licensed operator training at your facility. Based on this | The U.S. Nuclear Regulatory Commission (NRC) has approved the subject examination. The NRC staff will administer the operating test during the week of December 11, 2017. The list of the applicants approved to take the examination has been provided to Mr. Mark Similey, Operations Training Manager. The examination has undergone extensive review by my staff and representatives responsible for licensed operator training at your facility. Based on this review, I have concluded that the examination meets the guidelines of Revision 11 to NUREG-1021, Operator Licensing Examination Standards for Power Reactors, for content, operational, and discrimination validity. By administering this examination, you also agree that it meets NUREG-1021 guidelines and is appropriate for measuring the qualifications of licensed operator applicants at your facility. If you determine that this examination is not appropriate for licensing operators at your facility, do not administer the examination and contact me at 404-997-4662. | ||
review, I have concluded that the examination meets the guidelines of Revision 11 to NUREG-1021, | |||
Please contact your Chief Examiner, Daniel Bacon, at 404-997-4518, if you have questions or identify any errors or changes in the license level (reactor operator or senior reactor operator) or type of examination (partial or complete written examination or operating test, or both) specified for each applicant approved to take the examination. | Please contact your Chief Examiner, Daniel Bacon, at 404-997-4518, if you have questions or identify any errors or changes in the license level (reactor operator or senior reactor operator) or type of examination (partial or complete written examination or operating test, or both) specified for each applicant approved to take the examination. | ||
Sincerely, | Sincerely, | ||
/RA/ | /RA/ | ||
Eugene F. Guthrie, Chief Operations Branch 2 Division of Reactor Safety | Eugene F. Guthrie, Chief Operations Branch 2 Division of Reactor Safety | ||
Docket Nos.: 50-325, 50-324 License Nos.: DPR-71, DPR-62 | Docket Nos.: 50-325, 50-324 License Nos.: DPR-71, DPR-62 | ||
SUNSI REVIEW COMPLETE FORM 665 ATTACHED | |||
OFFICE RII:DRS RII:DRS RII:DRS | |||
SIGNATURE JCV DXB2 EFG | |||
NAME JVINCENT DBACON EGUTHRIE | |||
DATE 12/12/2017 12/12 /2017 12/12/2017 | |||
E-MAIL COPY? | |||
YES NO YES NO YES NO | |||
}} | }} | ||
Latest revision as of 08:07, 7 January 2025
| ML17354B215 | |
| Person / Time | |
|---|---|
| Site: | Brunswick |
| Issue date: | 12/12/2017 |
| From: | Eugene Guthrie Division of Reactor Safety II |
| To: | Hicks J Duke Energy Progress |
| References | |
| IR 2017302 | |
| Download: ML17354B215 (2) | |
Text
December 12, 2017
SUBJECT:
BRUNSWICK NUCLEAR POWER PLANT - (RETAKE) OPERATOR LICENSING EXAMINATION APPROVAL 05000325/2017302 AND 05000324/2017302
Dear Mr. Hicks:
The purpose of this letter is to confirm the final arrangements for the upcoming retake operator licensing examination at the Brunswick Nuclear Power Plant.
The U.S. Nuclear Regulatory Commission (NRC) has approved the subject examination. The NRC staff will administer the operating test during the week of December 11, 2017. The list of the applicants approved to take the examination has been provided to Mr. Mark Similey, Operations Training Manager. The examination has undergone extensive review by my staff and representatives responsible for licensed operator training at your facility. Based on this review, I have concluded that the examination meets the guidelines of Revision 11 to NUREG-1021, Operator Licensing Examination Standards for Power Reactors, for content, operational, and discrimination validity. By administering this examination, you also agree that it meets NUREG-1021 guidelines and is appropriate for measuring the qualifications of licensed operator applicants at your facility. If you determine that this examination is not appropriate for licensing operators at your facility, do not administer the examination and contact me at 404-997-4662.
Please contact your Chief Examiner, Daniel Bacon, at 404-997-4518, if you have questions or identify any errors or changes in the license level (reactor operator or senior reactor operator) or type of examination (partial or complete written examination or operating test, or both) specified for each applicant approved to take the examination.
Sincerely,
/RA/
Eugene F. Guthrie, Chief Operations Branch 2 Division of Reactor Safety
Docket Nos.: 50-325, 50-324 License Nos.: DPR-71, DPR-62
SUNSI REVIEW COMPLETE FORM 665 ATTACHED
OFFICE RII:DRS RII:DRS RII:DRS
SIGNATURE JCV DXB2 EFG
NAME JVINCENT DBACON EGUTHRIE
DATE 12/12/2017 12/12 /2017 12/12/2017
E-MAIL COPY?
YES NO YES NO YES NO