ML18117A393: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(StriderTol Bot change)
 
Line 2: Line 2:
| number = ML18117A393
| number = ML18117A393
| issue date = 04/06/2018
| issue date = 04/06/2018
| title = Revision 24 to Updated Final Safety Analysis Report, Chapter 6, Appendix 06B, Table of Contents
| title = 4 to Updated Final Safety Analysis Report, Chapter 6, Appendix 06B, Table of Contents
| author name =  
| author name =  
| author affiliation = Exelon Generation Co, LLC
| author affiliation = Exelon Generation Co, LLC
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter:TMI-1 UFSAR APPENDIX 6B 6B-i REV. 20, APRIL 2010
{{#Wiki_filter:TMI-1 UFSAR APPENDIX 6B 6B-i REV. 20, APRIL 2010 APPENDIX 6B


APPENDIX  6B 
TMI-1 UFSAR APPENDIX 6B 6B-ii REV. 20, APRIL 2010 TABLE OF CONTENTS SECTION TITLE 1.1 HYDRAULIC MODEL 1.2 REACTOR BUILDING DESIGN BASIS ACCIDENT 2.0 ENVIRONMENTAL QUALIFICATION PROGRAM  
 
TMI-1 UFSAR APPENDIX 6B 6B-ii REV. 20, APRIL 2010 TABLE OF CONTENTS
 
SECTION TITLE 1.1 HYDRAULIC MODEL
 
===1.2 REACTOR===
BUILDING DESIGN BASIS ACCIDENT
 
===2.0 ENVIRONMENTAL===
QUALIFICATION PROGRAM


==2.1 INTRODUCTION==
==2.1 INTRODUCTION==
 
2.2 EQ ORGANIZATION 2.3 EQ MASTER LIST 2.4 ENVIRONMENTAL PARAMETERS 2.5 QUALIFICATION OF EQUIPMENT  
2.2 EQ ORGANIZATION 2.3 EQ MASTER LIST
 
===2.4 ENVIRONMENTAL===
PARAMETERS
 
===2.5 QUALIFICATION===
OF EQUIPMENT


==3.0 REFERENCES==
==3.0 REFERENCES==
TMI-1 UFSAR APPENDIX 6B 6B-iii REV. 20, APRIL 2010 LIST OF TABLES TABLE TITLE 6B-1 Heat Transfer Coefficients Applied to the Reactor Coolant System and to the Reactor Building for LOCA analysis 6B-2 Engineered Safeguards Data 6B-3 Summary of Reactor Building LOCA Pressure Analysis 6B-4 Deleted 6B-5 Isotopic Core Inventory 6B-6 Assumptions Used In Development of LOCA Temperature Profile 6B-7 Assumptions Used in Development of RB MSLB Temperature Profile


TMI-1 UFSAR APPENDIX 6B 6B-iii REV. 20, APRIL 2010 LIST OF TABLES
TMI-1 UFSAR APPENDIX 6B 6B-iv REV. 20, APRIL 2010 LIST OF FIGURES FIGURE TITLE 6B-1 Loft Semiscale Blowdown Test No. 546 Vessel Pressure Vs Time (LOCA) 6B-2 Loft Test No. 546 Predicted Percent Mass Remaining Vs Time (LOCA) 6B-3 Envelope of Peak Reactor Building Pressure Versus Rupture Sizes With 3 Air Coolers Operating (LOCA) 6B-4 Reactor Building Pressure Versus Time for the DBA (LOCA) 8.5 FT2 Rupture with 3 Reactor Building Air Coolers 6B-5 Reactor Building Vapor and Sump Coolant Temperatures Versus Time for the DBA (LOCA) With 3 Reactor Building Air Coolers 6B-6 Reactor Building Energy Inventory Versus Time for the DBA (LOCA) with 3 Reactor Building Air Coolers 6B-7 Reactor Building Pressure Versus Time After Rupture (14.1 FT2 LOCA) 6B-8 Reactor Building Pressure Versus Time After Rupture (5.0 FT2 LOCA) 6B-9 Reactor Building Pressure Versus Time After Rupture (3.0 FT2 LOCA) 6B-10 Reactor Building Pressure Versus Time After Rupture (1.0 FT2 LOCA) 6B-11 Reactor Building Pressure Versus Time for the DBA (LOCA) With 2 Air Coolers and 1,500 GPM Spray 6B-12 Maximum Hot Spot Clad Temperature Vs Variable Heat Transfer Coefficient After DNB for a 36 inch ID, Double-Ended, Hot Leg Pipe Rupture (LOCA) 6B-13 Reactor Building Vapor and Sump Coolant Temperatures Versus Time for the DBA (LOCA) with Two Reactor Building Air Coolers & 1500 GPM Sprays 6B-13A Deleted 6B-13B Deleted 6B-13C Deleted 6B-14 Deleted 6B-15 RB MSLB EQ Temperature Profile  
 
TABLE TITLE 6B-1 Heat Transfer Coefficients Applied to the Reactor Coolant System and to the Reactor Building for LOCA analysis
 
6B-2 Engineered Safeguards Data
 
6B-3 Summary of Reactor Building LOCA Pressure Analysis 6B-4 Deleted
 
6B-5 Isotopic Core Inventory
 
6B-6 Assumptions Used In Development of LOCA Temperature Profile
 
6B-7 Assumptions Used in Development of RB MSLB Temperature Profile
 
TMI-1 UFSAR APPENDIX 6B 6B-iv REV. 20, APRIL 2010 LIST OF FIGURES
 
FIGURE TITLE 6B-1 Loft Semiscale Blowdown Test No. 546 Vessel Pressure Vs Time (LOCA) 6B-2 Loft Test No. 546 Predicted Percent Mass Remaining Vs Time (LOCA)  
 
6B-3 Envelope of Peak Reactor Building Pressure Versus Rupture Sizes With 3 Air Coolers Operating (LOCA) 6B-4 Reactor Building Pressure Versus Time for the DBA (LOCA
) 8.5 FT 2 Rupture with 3 Reactor Building Air Coolers  
 
6B-5 Reactor Building Vapor and Sump Coolant Temperatures Versus Time for the DBA (LOCA) With 3 Reactor Building Air Coolers  
 
6B-6 Reactor Building Energy Inventory Versus Time for the DBA (LOCA) with 3 Reactor Building Air Coolers 6B-7 Reactor Building Pressure Versus Time After Rupture (14.1 FT 2 LOCA) 6B-8 Reactor Building Pressure Versus Time After Rupture (5.0 FT 2 LOCA) 6B-9 Reactor Building Pressure Versus Time After Rupture (3.0 FT 2 LOCA) 6B-10 Reactor Building Pressure Versus Time After Rupture (1.0 FT 2 LOCA) 6B-11 Reactor Building Pressure Versus Time for the DBA (LOCA) With 2 Air Coolers and 1,500 GPM Spray  
 
6B-12 Maximum Hot Spot Clad Temperature Vs Variable Heat Transfer Coefficient After DNB for a 36 inch ID, Double-Ended, Hot Leg Pipe Rupture (LOCA)  
 
6B-13 Reactor Building Vapor and Sump Coolant Temperatures Versus Time for the DBA (LOCA) with Two Reactor Building Air Coolers & 1500 GPM Sprays 6B-13A Deleted  
 
6B-13B Deleted  
 
6B-13C Deleted  
 
6B-14 Deleted 6B-15 RB MSLB EQ Temperature Profile TMI-1 UFSAR APPENDIX 6B 6B-v REV. 20, APRIL 2010 LIST OF FIGURES (cont'd)
FIGURE TITLE 6B-16  LOCA EQ Temperature Profile 6B-17  LOCA RB Pressure From EQ Model
 
6B-18  RB MSLB EQ Pressure Profile
 
6B-19  RB EQ Temperature Profile  


6B-20 RB EQ Pressure Profile}}
TMI-1 UFSAR APPENDIX 6B 6B-v REV. 20, APRIL 2010 LIST OF FIGURES (cont'd)
FIGURE TITLE 6B-16 LOCA EQ Temperature Profile 6B-17 LOCA RB Pressure From EQ Model 6B-18 RB MSLB EQ Pressure Profile 6B-19 RB EQ Temperature Profile 6B-20 RB EQ Pressure Profile}}

Latest revision as of 23:17, 5 January 2025

4 to Updated Final Safety Analysis Report, Chapter 6, Appendix 06B, Table of Contents
ML18117A393
Person / Time
Site: Crane Constellation icon.png
Issue date: 04/06/2018
From:
Exelon Generation Co
To:
Office of Nuclear Reactor Regulation
Shared Package
ML18117A343 List: ... further results
References
TMI-18-047
Download: ML18117A393 (5)


Text

TMI-1 UFSAR APPENDIX 6B 6B-i REV. 20, APRIL 2010 APPENDIX 6B

TMI-1 UFSAR APPENDIX 6B 6B-ii REV. 20, APRIL 2010 TABLE OF CONTENTS SECTION TITLE 1.1 HYDRAULIC MODEL 1.2 REACTOR BUILDING DESIGN BASIS ACCIDENT 2.0 ENVIRONMENTAL QUALIFICATION PROGRAM

2.1 INTRODUCTION

2.2 EQ ORGANIZATION 2.3 EQ MASTER LIST 2.4 ENVIRONMENTAL PARAMETERS 2.5 QUALIFICATION OF EQUIPMENT

3.0 REFERENCES

TMI-1 UFSAR APPENDIX 6B 6B-iii REV. 20, APRIL 2010 LIST OF TABLES TABLE TITLE 6B-1 Heat Transfer Coefficients Applied to the Reactor Coolant System and to the Reactor Building for LOCA analysis 6B-2 Engineered Safeguards Data 6B-3 Summary of Reactor Building LOCA Pressure Analysis 6B-4 Deleted 6B-5 Isotopic Core Inventory 6B-6 Assumptions Used In Development of LOCA Temperature Profile 6B-7 Assumptions Used in Development of RB MSLB Temperature Profile

TMI-1 UFSAR APPENDIX 6B 6B-iv REV. 20, APRIL 2010 LIST OF FIGURES FIGURE TITLE 6B-1 Loft Semiscale Blowdown Test No. 546 Vessel Pressure Vs Time (LOCA) 6B-2 Loft Test No. 546 Predicted Percent Mass Remaining Vs Time (LOCA) 6B-3 Envelope of Peak Reactor Building Pressure Versus Rupture Sizes With 3 Air Coolers Operating (LOCA) 6B-4 Reactor Building Pressure Versus Time for the DBA (LOCA) 8.5 FT2 Rupture with 3 Reactor Building Air Coolers 6B-5 Reactor Building Vapor and Sump Coolant Temperatures Versus Time for the DBA (LOCA) With 3 Reactor Building Air Coolers 6B-6 Reactor Building Energy Inventory Versus Time for the DBA (LOCA) with 3 Reactor Building Air Coolers 6B-7 Reactor Building Pressure Versus Time After Rupture (14.1 FT2 LOCA) 6B-8 Reactor Building Pressure Versus Time After Rupture (5.0 FT2 LOCA) 6B-9 Reactor Building Pressure Versus Time After Rupture (3.0 FT2 LOCA) 6B-10 Reactor Building Pressure Versus Time After Rupture (1.0 FT2 LOCA) 6B-11 Reactor Building Pressure Versus Time for the DBA (LOCA) With 2 Air Coolers and 1,500 GPM Spray 6B-12 Maximum Hot Spot Clad Temperature Vs Variable Heat Transfer Coefficient After DNB for a 36 inch ID, Double-Ended, Hot Leg Pipe Rupture (LOCA) 6B-13 Reactor Building Vapor and Sump Coolant Temperatures Versus Time for the DBA (LOCA) with Two Reactor Building Air Coolers & 1500 GPM Sprays 6B-13A Deleted 6B-13B Deleted 6B-13C Deleted 6B-14 Deleted 6B-15 RB MSLB EQ Temperature Profile

TMI-1 UFSAR APPENDIX 6B 6B-v REV. 20, APRIL 2010 LIST OF FIGURES (cont'd)

FIGURE TITLE 6B-16 LOCA EQ Temperature Profile 6B-17 LOCA RB Pressure From EQ Model 6B-18 RB MSLB EQ Pressure Profile 6B-19 RB EQ Temperature Profile 6B-20 RB EQ Pressure Profile