{{#Wiki_filter:U.S. NUCLEAR REGULATORY COMMISSION REGULATORY GUIDE OFFICE OF STANDARDS DEVELOPMENT REGULATORY GUIDE 1.14 REACTOR COOLANT PUMP FLYWHEEL | {{#Wiki_filter:U.S. NUCLEAR REGULATORY COMMISSION REGULATORY GUIDE OFFICE OF STANDARDS DEVELOPMENT REGULATORY GUIDE 1.14 REACTOR COOLANT PUMP FLYWHEEL INTEGRITY | ||
==A. INTRODUCTION== | |||
General Design Criterion 4, "Environmental and Missile Design Bases," of Appendix A, "General Design Criteria for Nuclear Power Plants," to 10 CFR Part 50, "Licensing of Production and Utilization Facilities," requires that nuclear power plant structures, systems, and components important to safety be protected against the effects of missiles that might result from equipment failures. This guide describes a method acceptable to the NRC staff of implementing this requirement with regard to minimizing the potential for failures of the flywheels of reactor coolant pump motors in light-water-cooled power reactor | |||
==B. DISCUSSION== | |||
The flywheels on reactor coolant pump motors provide inertia to ensure a slow decrease in coolant flow in order to prevent fuel damage as a result of a loss of power to the pump motors. During operation at normal speed, a flywheel has sufficient kinetic energy to produce high-energy missiles and excessive vibration of the reactor coolant pump assembly if the flywheel should fail. Overspeed of the pump rotor assembly during a transient increases both the potential for failure and the kinetic energ3T of the flywheel. The safety consequences could be significant because of possible damage to the reactor coolant system, the containment, or other equipment or systems important to safet Methods of predicting the loss-of-coolant accident (LOCA) overspeed conditions are under continuing investigation. The limit on predicted pump overspeed in the event of a LOCA should be less than the calculated critical speed for failure of the flywheel. The conservatism inherent in the latter calculation, coupled with a realistic prediction of maximum rotational speed, is considered to provide adequate margin because of the low probability of occurrence of the specific LOCAconditions that would cause such overspeed. Methods of limiting potential pump overspeed are also under investigatio If the flywheel of the reactor coolant pump is conservatively designed and made from suitable materials with closely controlled quality, if adequate design review of new configurations is provided, and if adequate inservice inspection is provided, the probability of a flywheel failure is sufficiently small that the consequences of failure need not be protected agains Materials for pump flywheels should be manufactured by processes that minimize flaws and result in adequate fracture toughness in both the transverse and longitudinal rolling directions. Materials produced by vacuum melting and degassing or the electroslag remelting process are known to have improved cleanliness and toughness. Plate material should be cross rolled to a ratio of at least I to 3, sufficient to achieve acceptable isotropy. Fracture toughness is achieved more readily in thinner plates, and fabrication of laminated flywheels by assembling them from several plates is acceptabl As an example, past evaluations have shown that ASME SA-533-B Class 1 and SA-508 Classes 2 and 3 materials generally have suitable toughness for typical flywheel applications provided stress concentrations are kept within reasonable limits and the reference temperature RTNDT, determined in accordance with Article NB-2331(a) of Section HI of the ASME Code,' is at least 500C (900F) below the lowest temperature at which operating speed is achieved. For other materials that may be considered for flywheels, the strength and toughness properties should be evaluated and justified for this applicatio 'Copies may be obbtined from the American Society of Mechanical Engineers, United Engineering Center, 345 East 47th Street, New York, New York 10017.USNRC REGULATORY GUIDES Comments should be sent to the Secretary of the Commission, U.S. Nciler Regulatory Guides are issued to describe and make available to the public Regulatory Commission. Washongton. D.C. 2 , Attention: Dockeling end methods acceptable to the NRC staff of implementing specific parts of the Commission's regulations, to delineate techniques used by the staff In evalu- The guides are issued in the following ten broad divisions: sting specific problems or postulated accidents. or to provide guidance to applicents. Regulatory Guides are not substitutes for regulations, end compliance 1: Power Reactors S. Products with them is not required. Methods and solutions different from those set out in 2. Research end Test Reactors 7. Transportation the guides will be acceptable if they provide a basis for the findings requisite to 3' Fuels and Materiasi Facilities "8. Occupational Health the issuance or continuance of a permit or license by the Commission. 4. Environmental end Siting 9. Antitrust Review Comments and suggestions for improvements in these guides are encouraged 5. Materials and Plant Protection 10. General at all times, and guides will be revised. as appropriate, to accommodate comments and to reflect new information or experience. However. comments on Copies of published guides may be obtained by written requeat indicating the this guide, if received within about two months after its issuance, will be par. divisions desired to the U.S. Nuclear Regulatory Commission. Washington. ticularly useful in evaluating the need for an early revision. 21, Attention: Director, Office of Standards Development.Revision 1 Au"ust 1975 The non-ductile fracture analysis called for in regulatory position C.2.d should be based on appropriate conservative assumptions for stress level, flaw size, temperature, and fracture toughness at the location of interest. The non-ductile fracture criterion used to predict the critical fracture speed should be based on initial instability of the flaw as defined in ASTM E-39 The justification for the stress analysis method used in the fracture analysis should describe the treatment of stresses arising from interference fits and thermal stresses when they are superimposed on the stresses caused by rotational forces. Justification for the flaw size estimate should consider it to be the maximum expected size of flaw that could conceivably escape detection, and should consider material thickness, method and frequency of nondestructive inspection, and analysis of flaw growth in fatigue if that is significant. The effect of cracks emanating from such structural discontinuities as keyways and bolt holes should be evaluated. Justification for the fracture toughness assumed for the material should describe the properties to be measured transverse to the rolling direction in the tests of each plate of material. The range of fracture toughness test temperatures should include the lowest service temperature at which overspeed could occur. If not, the basis used for any extrapolation should be justifie In doing the fracture analysis described in regulatory position C.2.d, engineering judgment should be used to select for analysis only those locations that appear to have the most severe sets of conditions. Severity is a function of stress level, flaw size, and fracture toughness at the location of interest. Comparison of perhaps three or four cases in terms of KI/KIC, the ratio of the imposed stress intensity factor at some nominal speed to the material toughness, should locate to most severe sets of conditions. Evaluation of the critical speed for fracture, which may require techniques that go beyond linear elastic fracture mechanics, may then focus on one critical locatio Excessive deformation during overspeed of the flywheel is of concern because damage could be caused by separation of the flywheel from the shaft. For the purpose of this guide, excessive deformation means any deformation such as an enlargement of the bore that could cause such separation directly or could cause an unbalance of the flywheel leading to structural failure or separation of the flywheel from the shaft. The calculation of deformation should employ elastic-plastic methods unless it can be shown that stresses remain within the elastic rang The geometry of the flywheel and pump motor design should facilitate preservice and inservice inspection of all high-stress regions (bore, keyway, and bolt hole regions) without the need for removal of the flywheel from its shaft and preferably without the need for removing the rotor from the motor assembly.The desired results of the analyses described in regulatory positions C.2.c, d, and e are quantitative estimates of the margins against fracture or excessive deformation during overspeed because such estimates, coupled with adequate provisions against overspeed, provide the best basis for assurance that the probability of failure under normal and transient conditions is sufficiently small that the consequences of failure need not be protected agains | |||
==C. REGULATORY POSITION== | |||
1. Material and Fabrication a. The flywheel material should be of closely controlled quality. Plates' should conform to ASTM A20 and should be produced by the vacuum-melting and degassing process or the electroslag remelting proces Plate material should be cross-rolled to a ratio of at least 1 to b. Fracture toughness and tensile properties of each plate of flywheel material should be checked by tests that yield results2 suitable to confirm the applicability to that flywheel of the properties used in the fracture analyses called for in regulatory positions C.2.c, d, and c. All flame-cut surfaces should be removed by machining to a depth at least 12 mm (1/2 inch) below the flame-cut surfac d. Welding, including tack welding and repair welding, should not be permitted in the finished flywheel unless the welds are inspectable and considered as potential sources of flaws in the fracture analysi . Design a. The flywheel assembly, including any speedlimiting and antirotation devices, the shaft, and the bearings, should be designed to withstand normal conditions, anticipated transients, the design basis loss-ofcoolant accident, and the Safe Shutdown Earthquake loads without loss of structural integrit b. Design speed should be at least 125% of normal speed but not less than the speed that could be attained during a turbine overspeed transient. Normal speed is defined as the synchronous speed of the a.c. drive motor at 60 hert c. An analysis should be conducted to predict the critical speed for ductile fracture of the flywheel. The methods and limits of paragraph F-1323.1(b) in Section III of the ASME Code are acceptable. If another method 2These results should be included as part of the'FSAR.1.14-2 is used, justification should be provided. The anal ,sis should be submitted to the NRC staff for evaluation.7 d. An analysis should be conducted to predict the critical speed for nonductile fracture of the flywhee Justification should be given for the stress analysis method, the estimate of flaw size and location, which should take into account initial size and flaw growth in service, and the values of fracture toughness assumed for the material. The analysis should be submitted to the NRC staff for evaluation.3 e. An analysis should be conducted to predict the critical speed for excessive4 deformation of the flywheel. The analysis should be submitted to the NRC staff for evaluation.3 f. The normal speed should be less than one-half of the lowest of the critical speeds calculated in regulatory positions C.2.c, d, and e abov g. The predicted LOCA overspeed should be less than the lowest of the critical speeds calculated in regulatory positions C.2.c., d, and . Testing Each flywheel assembly should be spin tested at the design speed of the flywhee . Inspection a. Following the spin test described in regulatory position C.3, each finished flywheel should receive a check of critical dimensions and a nondestructive examination as follows: (1) Areas of higher stress concentrations, bores, keyways, splines, and drilled holes, and surfaces adjacent to these areas on the finished flywheel should be examined for surface defects in accordance with paragraph NB-2545 or NB-2546 of Section III of the ASME Code using the procedures of paragraph NB-254 No linear indications more than 1.6 mm (1/16 inch) long, other than laminations, should be permitte (2) Each finished flywheel should be subjected to a 100% volumetric examination by ultrasonic methods using procedures and acceptance criteria specified in paragraph NB-2530 (for plates) or paragraph NB-2540 (for forgings) of Section III of the ASME Cod 'The analyses outlined in regulatory positions C.2.c, d, and e should preferably be submitted in topical reports rather than on a case-by-case basis for those flywheel designs that will have multiple application As defined in the Discussion.b. Inservice inspection should be performed for each flywheel as follows: (1) An in-place ultrasonic volumetric examination of the areas of higher stress concentration at the bore and: keyway at approximately 3-year intervals, during the refueling or maintenance shutdown coinciding with the inservice inspection schedule as required by Section XI of the ASME Cod (2) A surface examination of all exposed surfaces and complete ultrasonic volumetric examination at approximately 10-year intervals, during the plant shutdown coinciding with the inservice inspection schedule as required by Section XI of the ASME Cod (3) Examination procedures should be in accordance with the requirements of Subarticle IWA-2200 of Section XI of the ASME Cod (4) Acceptance criteria should conform to the recommendations of regulatory position C. (5) If the examination and evaluation indicate an increase in flaw size or growth rate greater than predicted for the service life of the flywheel, the results of the examination and evaluation should be submitted, to the staff for evaluatio | |||
==D. IMPLEMENTATION== | |||
The purpose of this section is to provide information to applicants and licensees regarding the staff's plans for utilizing this regulatory guid Except in those cases in which the applicant proposes an acceptable alternative method for complying with specified portions' of the Commission's regulations, the positions of this guide will be used by the NRC staff as follow . The recommendations of regulatory positions C.A, C.2, C.3, and C.4.a will be used in evaluating submittals for construction permit applications docketed on or after January 1, 1976. If an applicant wishes to use the recommendations of regulatory positions C.1, C.2, C.3, and C.4.a of this regulatory guide in developing submittals for an application docketed before January 1, 1976, the pertinent portions of the application will be evaluated on the basis of this guid . The recommendations of regulatory position C.4.b will be used in evaluating procedures used in inservice inspections conducted on all plants after January 1, 1976. If a licensee wishes to use the recommendations of regulatory position C.4.b of this1.14-3 regulatory guide in performing the inspection before January 1, 1976, the pertinent portions of the inspe tid procedures will be evaluated on the bosb of this guide. Where requirements of Section X) are recommended, examinations conducted during each 40-month inspection period should meet the code edition and all addenda that were in effect per paragraph (b) of 10 CFR § 50.55a 6 months prior to the inspection period. If a licensee wishes to use editions and addenda that subseUNITED STATES NUCLEAR REGULATORY COMMISSON WASHINGTON, 0. C. 20U OFFICIAL ]MUSINE9S PENALTY FOR PRIVATE USE. 630quently become effective per paragraph (b) of § 50.55a for any portion of the inspection, the pertinent portions of the inspection procedures will be evaluated on the basis of those editions and addend . The recommendations of this guide will be used in evaluating all topical reports on flywheel integrity after January 1, 197 POSTAGE AND FIES PAID UNITED STATES NUCLEAR REGULATORY COMMISSION}} | |||
{{RG-Nav}} | {{RG-Nav}} | ||
Revision as of 01:59, 6 March 2018
| ML003739936 | |
| Person / Time | |
|---|---|
| Issue date: | 08/31/1975 |
| From: | Office of Nuclear Regulatory Research |
| To: | |
| References | |
| RG-1.14, Rev 1 | |
| Download: ML003739936 (4) | |
U.S. NUCLEAR REGULATORY COMMISSION REGULATORY GUIDE OFFICE OF STANDARDS DEVELOPMENT REGULATORY GUIDE 1.14 REACTOR COOLANT PUMP FLYWHEEL INTEGRITY
A. INTRODUCTION
General Design Criterion 4, "Environmental and Missile Design Bases," of Appendix A, "General Design Criteria for Nuclear Power Plants," to 10 CFR Part 50, "Licensing of Production and Utilization Facilities," requires that nuclear power plant structures, systems, and components important to safety be protected against the effects of missiles that might result from equipment failures. This guide describes a method acceptable to the NRC staff of implementing this requirement with regard to minimizing the potential for failures of the flywheels of reactor coolant pump motors in light-water-cooled power reactor
B. DISCUSSION
The flywheels on reactor coolant pump motors provide inertia to ensure a slow decrease in coolant flow in order to prevent fuel damage as a result of a loss of power to the pump motors. During operation at normal speed, a flywheel has sufficient kinetic energy to produce high-energy missiles and excessive vibration of the reactor coolant pump assembly if the flywheel should fail. Overspeed of the pump rotor assembly during a transient increases both the potential for failure and the kinetic energ3T of the flywheel. The safety consequences could be significant because of possible damage to the reactor coolant system, the containment, or other equipment or systems important to safet Methods of predicting the loss-of-coolant accident (LOCA) overspeed conditions are under continuing investigation. The limit on predicted pump overspeed in the event of a LOCA should be less than the calculated critical speed for failure of the flywheel. The conservatism inherent in the latter calculation, coupled with a realistic prediction of maximum rotational speed, is considered to provide adequate margin because of the low probability of occurrence of the specific LOCAconditions that would cause such overspeed. Methods of limiting potential pump overspeed are also under investigatio If the flywheel of the reactor coolant pump is conservatively designed and made from suitable materials with closely controlled quality, if adequate design review of new configurations is provided, and if adequate inservice inspection is provided, the probability of a flywheel failure is sufficiently small that the consequences of failure need not be protected agains Materials for pump flywheels should be manufactured by processes that minimize flaws and result in adequate fracture toughness in both the transverse and longitudinal rolling directions. Materials produced by vacuum melting and degassing or the electroslag remelting process are known to have improved cleanliness and toughness. Plate material should be cross rolled to a ratio of at least I to 3, sufficient to achieve acceptable isotropy. Fracture toughness is achieved more readily in thinner plates, and fabrication of laminated flywheels by assembling them from several plates is acceptabl As an example, past evaluations have shown that ASME SA-533-B Class 1 and SA-508 Classes 2 and 3 materials generally have suitable toughness for typical flywheel applications provided stress concentrations are kept within reasonable limits and the reference temperature RTNDT, determined in accordance with Article NB-2331(a) of Section HI of the ASME Code,' is at least 500C (900F) below the lowest temperature at which operating speed is achieved. For other materials that may be considered for flywheels, the strength and toughness properties should be evaluated and justified for this applicatio 'Copies may be obbtined from the American Society of Mechanical Engineers, United Engineering Center, 345 East 47th Street, New York, New York 10017.USNRC REGULATORY GUIDES Comments should be sent to the Secretary of the Commission, U.S. Nciler Regulatory Guides are issued to describe and make available to the public Regulatory Commission. Washongton. D.C. 2 , Attention: Dockeling end methods acceptable to the NRC staff of implementing specific parts of the Commission's regulations, to delineate techniques used by the staff In evalu- The guides are issued in the following ten broad divisions: sting specific problems or postulated accidents. or to provide guidance to applicents. Regulatory Guides are not substitutes for regulations, end compliance 1: Power Reactors S. Products with them is not required. Methods and solutions different from those set out in 2. Research end Test Reactors 7. Transportation the guides will be acceptable if they provide a basis for the findings requisite to 3' Fuels and Materiasi Facilities "8. Occupational Health the issuance or continuance of a permit or license by the Commission. 4. Environmental end Siting 9. Antitrust Review Comments and suggestions for improvements in these guides are encouraged 5. Materials and Plant Protection 10. General at all times, and guides will be revised. as appropriate, to accommodate comments and to reflect new information or experience. However. comments on Copies of published guides may be obtained by written requeat indicating the this guide, if received within about two months after its issuance, will be par. divisions desired to the U.S. Nuclear Regulatory Commission. Washington. ticularly useful in evaluating the need for an early revision. 21, Attention: Director, Office of Standards Development.Revision 1 Au"ust 1975 The non-ductile fracture analysis called for in regulatory position C.2.d should be based on appropriate conservative assumptions for stress level, flaw size, temperature, and fracture toughness at the location of interest. The non-ductile fracture criterion used to predict the critical fracture speed should be based on initial instability of the flaw as defined in ASTM E-39 The justification for the stress analysis method used in the fracture analysis should describe the treatment of stresses arising from interference fits and thermal stresses when they are superimposed on the stresses caused by rotational forces. Justification for the flaw size estimate should consider it to be the maximum expected size of flaw that could conceivably escape detection, and should consider material thickness, method and frequency of nondestructive inspection, and analysis of flaw growth in fatigue if that is significant. The effect of cracks emanating from such structural discontinuities as keyways and bolt holes should be evaluated. Justification for the fracture toughness assumed for the material should describe the properties to be measured transverse to the rolling direction in the tests of each plate of material. The range of fracture toughness test temperatures should include the lowest service temperature at which overspeed could occur. If not, the basis used for any extrapolation should be justifie In doing the fracture analysis described in regulatory position C.2.d, engineering judgment should be used to select for analysis only those locations that appear to have the most severe sets of conditions. Severity is a function of stress level, flaw size, and fracture toughness at the location of interest. Comparison of perhaps three or four cases in terms of KI/KIC, the ratio of the imposed stress intensity factor at some nominal speed to the material toughness, should locate to most severe sets of conditions. Evaluation of the critical speed for fracture, which may require techniques that go beyond linear elastic fracture mechanics, may then focus on one critical locatio Excessive deformation during overspeed of the flywheel is of concern because damage could be caused by separation of the flywheel from the shaft. For the purpose of this guide, excessive deformation means any deformation such as an enlargement of the bore that could cause such separation directly or could cause an unbalance of the flywheel leading to structural failure or separation of the flywheel from the shaft. The calculation of deformation should employ elastic-plastic methods unless it can be shown that stresses remain within the elastic rang The geometry of the flywheel and pump motor design should facilitate preservice and inservice inspection of all high-stress regions (bore, keyway, and bolt hole regions) without the need for removal of the flywheel from its shaft and preferably without the need for removing the rotor from the motor assembly.The desired results of the analyses described in regulatory positions C.2.c, d, and e are quantitative estimates of the margins against fracture or excessive deformation during overspeed because such estimates, coupled with adequate provisions against overspeed, provide the best basis for assurance that the probability of failure under normal and transient conditions is sufficiently small that the consequences of failure need not be protected agains
C. REGULATORY POSITION
1. Material and Fabrication a. The flywheel material should be of closely controlled quality. Plates' should conform to ASTM A20 and should be produced by the vacuum-melting and degassing process or the electroslag remelting proces Plate material should be cross-rolled to a ratio of at least 1 to b. Fracture toughness and tensile properties of each plate of flywheel material should be checked by tests that yield results2 suitable to confirm the applicability to that flywheel of the properties used in the fracture analyses called for in regulatory positions C.2.c, d, and c. All flame-cut surfaces should be removed by machining to a depth at least 12 mm (1/2 inch) below the flame-cut surfac d. Welding, including tack welding and repair welding, should not be permitted in the finished flywheel unless the welds are inspectable and considered as potential sources of flaws in the fracture analysi . Design a. The flywheel assembly, including any speedlimiting and antirotation devices, the shaft, and the bearings, should be designed to withstand normal conditions, anticipated transients, the design basis loss-ofcoolant accident, and the Safe Shutdown Earthquake loads without loss of structural integrit b. Design speed should be at least 125% of normal speed but not less than the speed that could be attained during a turbine overspeed transient. Normal speed is defined as the synchronous speed of the a.c. drive motor at 60 hert c. An analysis should be conducted to predict the critical speed for ductile fracture of the flywheel. The methods and limits of paragraph F-1323.1(b) in Section III of the ASME Code are acceptable. If another method 2These results should be included as part of the'FSAR.1.14-2 is used, justification should be provided. The anal ,sis should be submitted to the NRC staff for evaluation.7 d. An analysis should be conducted to predict the critical speed for nonductile fracture of the flywhee Justification should be given for the stress analysis method, the estimate of flaw size and location, which should take into account initial size and flaw growth in service, and the values of fracture toughness assumed for the material. The analysis should be submitted to the NRC staff for evaluation.3 e. An analysis should be conducted to predict the critical speed for excessive4 deformation of the flywheel. The analysis should be submitted to the NRC staff for evaluation.3 f. The normal speed should be less than one-half of the lowest of the critical speeds calculated in regulatory positions C.2.c, d, and e abov g. The predicted LOCA overspeed should be less than the lowest of the critical speeds calculated in regulatory positions C.2.c., d, and . Testing Each flywheel assembly should be spin tested at the design speed of the flywhee . Inspection a. Following the spin test described in regulatory position C.3, each finished flywheel should receive a check of critical dimensions and a nondestructive examination as follows: (1) Areas of higher stress concentrations, bores, keyways, splines, and drilled holes, and surfaces adjacent to these areas on the finished flywheel should be examined for surface defects in accordance with paragraph NB-2545 or NB-2546 of Section III of the ASME Code using the procedures of paragraph NB-254 No linear indications more than 1.6 mm (1/16 inch) long, other than laminations, should be permitte (2) Each finished flywheel should be subjected to a 100% volumetric examination by ultrasonic methods using procedures and acceptance criteria specified in paragraph NB-2530 (for plates) or paragraph NB-2540 (for forgings) of Section III of the ASME Cod 'The analyses outlined in regulatory positions C.2.c, d, and e should preferably be submitted in topical reports rather than on a case-by-case basis for those flywheel designs that will have multiple application As defined in the Discussion.b. Inservice inspection should be performed for each flywheel as follows: (1) An in-place ultrasonic volumetric examination of the areas of higher stress concentration at the bore and: keyway at approximately 3-year intervals, during the refueling or maintenance shutdown coinciding with the inservice inspection schedule as required by Section XI of the ASME Cod (2) A surface examination of all exposed surfaces and complete ultrasonic volumetric examination at approximately 10-year intervals, during the plant shutdown coinciding with the inservice inspection schedule as required by Section XI of the ASME Cod (3) Examination procedures should be in accordance with the requirements of Subarticle IWA-2200 of Section XI of the ASME Cod (4) Acceptance criteria should conform to the recommendations of regulatory position C. (5) If the examination and evaluation indicate an increase in flaw size or growth rate greater than predicted for the service life of the flywheel, the results of the examination and evaluation should be submitted, to the staff for evaluatio
D. IMPLEMENTATION
The purpose of this section is to provide information to applicants and licensees regarding the staff's plans for utilizing this regulatory guid Except in those cases in which the applicant proposes an acceptable alternative method for complying with specified portions' of the Commission's regulations, the positions of this guide will be used by the NRC staff as follow . The recommendations of regulatory positions C.A, C.2, C.3, and C.4.a will be used in evaluating submittals for construction permit applications docketed on or after January 1, 1976. If an applicant wishes to use the recommendations of regulatory positions C.1, C.2, C.3, and C.4.a of this regulatory guide in developing submittals for an application docketed before January 1, 1976, the pertinent portions of the application will be evaluated on the basis of this guid . The recommendations of regulatory position C.4.b will be used in evaluating procedures used in inservice inspections conducted on all plants after January 1, 1976. If a licensee wishes to use the recommendations of regulatory position C.4.b of this1.14-3 regulatory guide in performing the inspection before January 1, 1976, the pertinent portions of the inspe tid procedures will be evaluated on the bosb of this guide. Where requirements of Section X) are recommended, examinations conducted during each 40-month inspection period should meet the code edition and all addenda that were in effect per paragraph (b) of 10 CFR § 50.55a 6 months prior to the inspection period. If a licensee wishes to use editions and addenda that subseUNITED STATES NUCLEAR REGULATORY COMMISSON WASHINGTON, 0. C. 20U OFFICIAL ]MUSINE9S PENALTY FOR PRIVATE USE. 630quently become effective per paragraph (b) of § 50.55a for any portion of the inspection, the pertinent portions of the inspection procedures will be evaluated on the basis of those editions and addend . The recommendations of this guide will be used in evaluating all topical reports on flywheel integrity after January 1, 197 POSTAGE AND FIES PAID UNITED STATES NUCLEAR REGULATORY COMMISSION