{{#Wiki_filter:November 4, 2020
{{#Wiki_filter:November 4, 2020  
Mr. Ken Peters
Senior Vice President and
   Chief Nuclear Officer
Attention: Regulatory Affairs
Mr. Ken Peters  
Vistra Operations Company LLC
Senior Vice President and
P.O. Box 1002
   Chief Nuclear Officer  
Glen Rose, TX 76043
Attention: Regulatory Affairs  
SUBJECT:       COMANCHE PEAK NUCLEAR POWER PLANT, UNITS 1 AND 2 -
Vistra Operations Company LLC  
                NOTIFICATION OF NRC DESIGN BASES ASSURANCE INSPECTION (TEAMS)
P.O. Box 1002  
                (INSPECTION REPORT 05000445/2021011 AND 05000446/2021011) AND
Glen Rose, TX 76043  
                INITIAL REQUEST FOR INFORMATION
Dear Mr. Peters:
SUBJECT: COMANCHE PEAK NUCLEAR POWER PLANT, UNITS 1 AND 2 -  
On February 8, 2021, the Nuclear Regulatory Commission (NRC) will begin a triennial
NOTIFICATION OF NRC DESIGN BASES ASSURANCE INSPECTION (TEAMS)  
baseline component design bases inspection at the Comanche Peak Nuclear Power Plant.
(INSPECTION REPORT 05000445/2021011 AND 05000446/2021011) AND  
A six-person team will perform this inspection using NRC Inspection Procedure 71111,
INITIAL REQUEST FOR INFORMATION  
Attachment 21M, Design Bases Assurance Inspection (Teams).
The inspection focuses on the maintenance of component design bases and modifications
Dear Mr. Peters:  
made to structures, systems, and components. The samples reviewed during this inspection
will be identified during an information gathering visit and during the subsequent in-office
On February 8, 2021, the Nuclear Regulatory Commission (NRC) will begin a triennial  
preparation week. In addition, operating experience issues will also be selected for review.
baseline component design bases inspection at the Comanche Peak Nuclear Power Plant.
The inspection will include an information gathering site visit by the team leader and
A six-person team will perform this inspection using NRC Inspection Procedure 71111,  
two weeks of onsite inspection by the team. The inspection will consist of a team lead
Attachment 21M, Design Bases Assurance Inspection (Teams).  
inspector, two mechanical inspectors, two electrical inspectors, and an operations inspector.
The current inspection schedule is as follows:
The inspection focuses on the maintenance of component design bases and modifications  
          Information Gathering Visit: January 4-8, 2021
made to structures, systems, and components. The samples reviewed during this inspection  
          Preparation Week: February 1-5, 2021
will be identified during an information gathering visit and during the subsequent in-office  
          Onsite Weeks: February 8-12 and February 22-26, 2021
preparation week. In addition, operating experience issues will also be selected for review.  
The purpose of the information gathering visit is to meet with members of your staff to identify
potential risk-significant components and operator actions. The lead inspector will also request
The inspection will include an information gathering site visit by the team leader and  
a tour of the plant with members of your operations staff and probabilistic safety assessment
two weeks of onsite inspection by the team. The inspection will consist of a team lead  
staff. During the inspection, up to 16 hours will be needed on the plant-referenced simulator in
inspector, two mechanical inspectors, two electrical inspectors, and an operations inspector.
order to facilitate the development and inspection of operator action-based scenarios. It has not
The current inspection schedule is as follows:  
yet been determined if the inspection will be onsite or conducted remotely. If the inspection is
performed remotely, we are requesting that, as a minimum, actual on-site time be made
Information Gathering Visit: January 4-8, 2021  
available for 1-2 days to perform component and modification walkdowns. Simulator activities
Preparation Week: February 1-5, 2021  
Onsite Weeks: February 8-12 and February 22-26, 2021  
The purpose of the information gathering visit is to meet with members of your staff to identify  
potential risk-significant components and operator actions. The lead inspector will also request  
a tour of the plant with members of your operations staff and probabilistic safety assessment  
staff. During the inspection, up to 16 hours will be needed on the plant-referenced simulator in  
order to facilitate the development and inspection of operator action-based scenarios. It has not  
yet been determined if the inspection will be onsite or conducted remotely. If the inspection is  
performed remotely, we are requesting that, as a minimum, actual on-site time be made  
available for 1-2 days to perform component and modification walkdowns. Simulator activities  


K. Peters                                       2
K. Peters  
would have to be performed on site. Additional information and documentation needed to
2  
support the inspection will be identified during the inspection, including interviews with
engineering managers, engineers, and probabilistic safety assessment staff.
Our experience with these inspections has shown that they are extremely resource intensive,
both for the NRC inspectors and the licensee staff. In order to minimize the inspection impact
would have to be performed on site. Additional information and documentation needed to  
on the site and to ensure a productive inspection, we have enclosed a request for information
support the inspection will be identified during the inspection, including interviews with  
needed for the inspection. The request has been divided into two groups. The first group lists
engineering managers, engineers, and probabilistic safety assessment staff.  
information necessary for the information gathering visit and for general preparation. This
information should be available to the regional office no later than January 4, 2021, unless
Our experience with these inspections has shown that they are extremely resource intensive,  
otherwise stated. If possible, this information should be provided electronically to the lead
both for the NRC inspectors and the licensee staff. In order to minimize the inspection impact  
inspector. Since the inspection will be concentrated on high-risk/low-margin components and
on the site and to ensure a productive inspection, we have enclosed a request for information  
modifications, calculations associated with your list of high-risk components and modifications
needed for the inspection. The request has been divided into two groups. The first group lists  
should be available to review during the information gathering visit to assist in our selection of
information necessary for the information gathering visit and for general preparation. This  
components based on available design margin.
information should be available to the regional office no later than January 4, 2021, unless  
The second group of documents requested lists information necessary to aid the inspection
otherwise stated. If possible, this information should be provided electronically to the lead  
team in tracking issues identified as a result of the inspection. It is requested that this
inspector. Since the inspection will be concentrated on high-risk/low-margin components and  
information be provided to the lead inspector as the information is generated during the
modifications, calculations associated with your list of high-risk components and modifications  
inspection. An additional request will be made by the team during the preparation week once
should be available to review during the information gathering visit to assist in our selection of  
the specific components and modifications have been selected. Additional requests by
components based on available design margin.  
inspectors will also be made throughout the onsite weeks for specific documents needed to
complete the review. It is important that all of these documents are up-to-date and complete in
The second group of documents requested lists information necessary to aid the inspection  
order to minimize the number of additional documents requested during the preparation and/or
team in tracking issues identified as a result of the inspection. It is requested that this  
onsite portions of the inspection. In order to facilitate the inspection, we request that a contact
information be provided to the lead inspector as the information is generated during the  
individual be assigned to each inspector to ensure information requests, questions, and
inspection. An additional request will be made by the team during the preparation week once  
concerns are addressed in a timely manner.
the specific components and modifications have been selected. Additional requests by  
The lead inspector for this inspection is Ronald A. Kopriva, Senior Reactor Inspector. If there
inspectors will also be made throughout the onsite weeks for specific documents needed to  
are any questions about the inspection or the requested materials, please contact the lead
complete the review. It is important that all of these documents are up-to-date and complete in  
inspector by telephone at 817-200-1104 or by e-mail at Ron.Kopriva@nrc.gov. It is our
order to minimize the number of additional documents requested during the preparation and/or  
understanding that Mr. Gary Merka will be our licensing contact for the inspection.
onsite portions of the inspection. In order to facilitate the inspection, we request that a contact  
PAPERWORK REDUCTION ACT STATEMENT
individual be assigned to each inspector to ensure information requests, questions, and  
This letter contains mandatory information collections that are subject to the Paperwork
concerns are addressed in a timely manner.  
Reduction Act of 1995 (44 U.S.C. 3501 et seq.). The Office of Management and Budget (OMB)
approved these information collections (approval number 3150-0011). Send comments
The lead inspector for this inspection is Ronald A. Kopriva, Senior Reactor Inspector. If there  
regarding this information collection to the Information Services Branch, Office of the Chief
are any questions about the inspection or the requested materials, please contact the lead  
Information Officer, Mail Stop: T6 A10M, U.S. Nuclear Regulatory Commission, Washington,
inspector by telephone at 817-200-1104 or by e-mail at Ron.Kopriva@nrc.gov. It is our  
DC 20555-0001, or by e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office
understanding that Mr. Gary Merka will be our licensing contact for the inspection.  
of Information and Regulatory Affairs, NEOB-10202, (3150-0011) Office of Management and
Budget, Washington, DC 20503.
PAPERWORK REDUCTION ACT STATEMENT  
PUBLIC PROTECTION NOTIFICATION
The NRC may not conduct nor sponsor, and a person is not required to respond to, a request
This letter contains mandatory information collections that are subject to the Paperwork  
for information or an information collection requirement unless the requesting document
Reduction Act of 1995 (44 U.S.C. 3501 et seq.). The Office of Management and Budget (OMB)  
displays a currently valid OMB control number.
approved these information collections (approval number 3150-0011). Send comments  
regarding this information collection to the Information Services Branch, Office of the Chief  
Information Officer, Mail Stop: T6 A10M, U.S. Nuclear Regulatory Commission, Washington,  
DC 20555-0001, or by e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office  
of Information and Regulatory Affairs, NEOB-10202, (3150-0011) Office of Management and  
Budget, Washington, DC 20503.  
PUBLIC PROTECTION NOTIFICATION  
The NRC may not conduct nor sponsor, and a person is not required to respond to, a request  
for information or an information collection requirement unless the requesting document  
displays a currently valid OMB control number.  


K. Peters                                       3
K. Peters  
This letter, its enclosure, and your response (if any) will be made available for public inspection
3  
and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document
Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public
Inspections, Exemptions, Requests for Withholding.
                                                Sincerely,
This letter, its enclosure, and your response (if any) will be made available for public inspection  
                                                Vincent G.      Digitally signed by Vincent
and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document  
                                                                  G. Gaddy
Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public  
                                                Gaddy            Date: 2020.11.04 10:53:56
Inspections, Exemptions, Requests for Withholding.  
                                                                  -06'00'
                                                Vincent G. Gaddy, Chief
                                                Engineering Branch 1
Sincerely,  
                                                Division of Reactor Safety
Docket Nos. 05000445 and 05000446
License Nos. NPF-87 and NPF-89
Enclosure:
Design Bases Assurance
Inspection (Teams) Request for
Information
cc w/ encl: Distribution via LISTSERV
Vincent G. Gaddy, Chief
Engineering Branch 1
Division of Reactor Safety  
Docket Nos. 05000445 and 05000446  
License Nos. NPF-87 and NPF-89  
Enclosure:  
Design Bases Assurance  
Inspection (Teams) Request for  
Information  
cc w/ encl: Distribution via LISTSERV  
Vincent G.
Gaddy
Digitally signed by Vincent
G. Gaddy
Date: 2020.11.04 10:53:56
-06'00'




  ML20309A360
  ML20309A360
  SUNSI Review:         ADAMS:           Non-Publicly Available  Non-Sensitive Keyword:
   
By: RAK                 Yes  No        Publicly Available     Sensitive     NRC-002
SUNSI Review:  
OFFICE       SRI:EB1       C:EB1
ADAMS:  
  NAME         RAKopriva     VGGaddy
Non-Publicly Available  
  SIGNATURE     /RA/           /RA/
  Non-Sensitive  
  DATE         11/04/2020     11/04/2020
Keyword:  
                                     
By: RAK  
                                    Initial Request for Information
Yes     No
                          Design Bases Assurance Inspection (Teams)
  Publicly Available  
                              Comanche Peak Nuclear Power Plant
  Sensitive  
Inspection Report:                          05000445/2021011 and 05000446/2021011
NRC-002  
EPID ID:                                    I-2021-011-0002
OFFICE  
Information Gathering Date:                  January 4-8, 2021
SRI:EB1  
Inspection Dates:                            February 8-12, 2021, and February 22-26, 2021
C:EB1  
Inspection Procedure:                        IP 71111, Attachment 21M, Design Bases Assurance
   
                                              Inspection (Teams)
Lead Inspector:                              Ronald A. Kopriva, Senior Reactor Inspector
I.    Information Requested Prior to Information Gathering Visit (January 4, 2021)
      The following information (Section I of this enclosure) should be sent to the Region IV
NAME  
      office in hard copy or electronic format (electronic database preferred), to the
RAKopriva  
      attention of Ronald A. Kopriva, Senior Reactor Inspector, by January 4, 2021, to
VGGaddy  
      facilitate the reduction in the items to be selected for a final list. The inspection team
   
      will finalize the selected list during the prep week using the additional documents
      requested in Section II of this enclosure. The specific items selected from the lists
      shall be available and ready for review on the day indicated in this request. Please
      provide requested documentation electronically in pdf files, Excel, or other
SIGNATURE  
      searchable formats, if possible. The information should contain descriptive names
/RA/  
      and be indexed and hyperlinked to facilitate ease of use. Information in lists should
/RA/  
      contain enough information to be easily understood by someone who has knowledge
   
      of boiling water reactor technology. If requested documents are large and only hard
      copy formats are available, please inform the inspector and provide subject
      documentation during the first day of the onsite inspection.
      1. An Excel spreadsheet of equipment basic events (with definitions), including
DATE  
            importance measures sorted by risk achievement worth and Fussell-Vesely
11/04/2020  
            from your internal events probabilistic risk assessment. Include basic events
11/04/2020  
            with risk achievement worth value of 1.3 or greater.
      2. A list of the top 50 cut-sets from your PRA.
      3. Copies of probabilistic risk assessment system notebooks and the
            latest probabilistic risk assessment summary document.
      4. An Excel spreadsheet of probabilistic risk assessment human action basic
            events or risk ranking of operator actions from your site-specific PSA sorted by
            risk achievement worth and Fussell-Vesely. Provide copies of your human
            reliability worksheets for these items.
                                                                                            Enclosure


5. If you have an external events or fire PSA model, provide the information
    requested in items 1-4 for external events and fire.
6. A list of high large early release frequency impact events and
Enclosure
    associated components.
Initial Request for Information 
7. Structures, systems, and components in the Maintenance Rule (a)(1) Category.
Design Bases Assurance Inspection (Teams)
8. A list of high risk maintenance rule systems/components and functions; based
Comanche Peak Nuclear Power Plant
    on engineering or expert panel judgment.
9. Site top 10 issues list, if available.
10. Any pre-existing list of components and associated calculations with low
Inspection Report:
    design margins.
05000445/2021011 and 05000446/2021011
11. A list of operating experience evaluations for the last 3 years.
12. A list of all time-critical operator actions in procedures.
EPID ID:
13. A list of current operator work arounds/burdens.
I-2021-011-0002 
14. Procedures, including emergency and abnormal, used to accomplish
    operator actions associated with the basic events credited in your PRA.
Information Gathering Date:
15. Lists of permanent and temporary modifications performed in the past 5
January 4-8, 2021
    years to structures, systems, and components sorted by component
    identified in Item 1.
Inspection Dates:
16. List of root cause evaluations associated with component failures or design
February 8-12, 2021, and February 22-26, 2021
    issues initiated/completed in the last 5 years.
17. A list of any common-cause failures of components in the last 3 years.
Inspection Procedure:
18. A copy of any internal/external self-assessments and associated corrective
IP 71111, Attachment 21M, Design Bases Assurance
    action documents generated in preparation for this inspection.
Inspection (Teams)  
19. A copy of engineering/operations-related audits completed in the last 2 years.
20. Electronic copies of the Technical Specifications, Technical Specifications
Lead Inspector:
    Bases, and the Final Safety Analysis Report, as updated.
Ronald A. Kopriva, Senior Reactor Inspector
21. A copy of the Individual Plant Examination of External Events, if
    available electronically.
I.  
22. One-line drawings of emergency core cooling system, ultimate heat sink,
Information Requested Prior to Information Gathering Visit (January 4, 2021)
    emergency feedwater, safety-related electrical systems.
                                              2
The following information (Section I of this enclosure) should be sent to the Region IV
office in hard copy or electronic format (electronic database preferred), to the
attention of Ronald A. Kopriva, Senior Reactor Inspector, by January 4, 2021, to  
facilitate the reduction in the items to be selected for a final list. The inspection team
will finalize the selected list during the prep week using the additional documents
requested in Section II of this enclosure. The specific items selected from the lists
shall be available and ready for review on the day indicated in this request.  Please
provide requested documentation electronically in pdf files, Excel, or other
searchable formats, if possible. The information should contain descriptive names
and be indexed and hyperlinked to facilitate ease of use. Information in lists should
contain enough information to be easily understood by someone who has knowledge
of boiling water reactor technology.  If requested documents are large and only hard
copy formats are available, please inform the inspector and provide subject
documentation during the first day of the onsite inspection.  
1. An Excel spreadsheet of equipment basic events (with definitions), including
importance measures sorted by risk achievement worth and Fussell-Vesely
from your internal events probabilistic risk assessment.  Include basic events
with risk achievement worth value of 1.3 or greater.  
2. A list of the top 50 cut-sets from your PRA.  
3. Copies of probabilistic risk assessment system notebooks and the  
latest probabilistic risk assessment summary document.  
4. An Excel spreadsheet of probabilistic risk assessment human action basic
events or risk ranking of operator actions from your site-specific PSA sorted by
risk achievement worth and Fussell-Vesely. Provide copies of your human
reliability worksheets for these items.  


          23. A copy of condition reports associated with inspection findings from the
              previous NRC Inspection Procedure 71111.21 (or 71111.21 Attachment M
2
              inspection).
5. If you have an external events or fire PSA model, provide the information
          24. A list of licensee contacts for the inspection team with phone numbers.
requested in items 1-4 for external events and fire.
          25. A copy of the current management and engineering organizational charts.
II.       Information Requested to be provided throughout the inspection.
6. A list of high large early release frequency impact events and
          1. Electronic copies of the design bases documents for selected components
associated components.
              and modifications.
          2. Electronic copies of the system health notebooks for selected components
7. Structures, systems, and components in the Maintenance Rule (a)(1) Category.
              and modifications.
          3. A list of the design calculations that provide the design margin information for
8. A list of high risk maintenance rule systems/components and functions; based
              selected components. (Calculations for selected components should be
on engineering or expert panel judgment.
              available during the information gathering visit.)
          4. Calculations and drawings associated with selected components.
9. Site top 10 issues list, if available.
          5. Modification documentation associated with modifications selected from
              Item I.15, this includes:
10. Any pre-existing list of components and associated calculations with low
              a. Post-modification testing, including performance characteristics affected,
design margins.
                  assumptions, and acceptance criteria associated with modifications
                  selected.
11. A list of operating experience evaluations for the last 3 years.
              b. Updated maintenance and surveillance procedures associated with
                  modifications.
12. A list of all time-critical operator actions in procedures.
              c. Updated operation procedures and training plans associated with the
                  modifications.
13. A list of current operator work arounds/burdens.
          6. Copies of any corrective action documents generated as a result of the
              teams questions or queries during this inspection.
14. Procedures, including emergency and abnormal, used to accomplish
          7. Copies of the list of questions submitted by the team members and the
operator actions associated with the basic events credited in your PRA.
              status/resolution of the information requested (provide daily during the
              inspection to each team member).
15. Lists of permanent and temporary modifications performed in the past 5
    Inspector Contact Information:                       Mailing Address:
years to structures, systems, and components sorted by component
    Ronald A. Kopriva                                     U.S. NRC, Region IV
identified in Item 1.
    Senior Reactor Inspector                              ATTN: Ronald A. Kopriva
    817-200-1104 - Work                                  1600 East Lamar Blvd.
16. List of root cause evaluations associated with component failures or design
    Ron.Kopriva@nrc.gov                                  Arlington, TX 76011-4511
issues initiated/completed in the last 5 years.
                                                      3
17. A list of any common-cause failures of components in the last 3 years.
18. A copy of any internal/external self-assessments and associated corrective
action documents generated in preparation for this inspection.
19. A copy of engineering/operations-related audits completed in the last 2 years.
20. Electronic copies of the Technical Specifications, Technical Specifications
Bases, and the Final Safety Analysis Report, as updated.
21. A copy of the Individual Plant Examination of External Events, if
available electronically.
22. One-line drawings of emergency core cooling system, ultimate heat sink,
emergency feedwater, safety-related electrical systems.
 
3
23. A copy of condition reports associated with inspection findings from the  
previous NRC Inspection Procedure 71111.21 (or 71111.21 Attachment M  
inspection).  
24. A list of licensee contacts for the inspection team with phone numbers.  
25. A copy of the current management and engineering organizational charts.  
II.  
Information Requested to be provided throughout the inspection.  
1. Electronic copies of the design bases documents for selected components  
and modifications.  
2. Electronic copies of the system health notebooks for selected components  
and modifications.  
3. A list of the design calculations that provide the design margin information for  
selected components. (Calculations for selected components should be  
available during the information gathering visit.)  
4. Calculations and drawings associated with selected components.  
5. Modification documentation associated with modifications selected from  
Item I.15, this includes:  
a. Post-modification testing, including performance characteristics affected,  
assumptions, and acceptance criteria associated with modifications  
selected.  
b. Updated maintenance and surveillance procedures associated with  
modifications.  
c. Updated operation procedures and training plans associated with the  
modifications.  
6. Copies of any corrective action documents generated as a result of the  
teams questions or queries during this inspection.  
7. Copies of the list of questions submitted by the team members and the  
status/resolution of the information requested (provide daily during the  
inspection to each team member).  
Inspector Contact Information:
Ronald A. Kopriva  
Senior Reactor Inspector 
817-200-1104 - Work
Ron.Kopriva@nrc.gov
Mailing Address:
U.S. NRC, Region IV
ATTN: Ronald A. Kopriva
1600 East Lamar Blvd.
Arlington, TX 76011-4511
}}
}}

Latest revision as of 14:02, 29 November 2024

Notification of NRC Design Bases Assurance Inspection (Teams) (Inspection Report 05000445/2021011 and 05000446/2021011) and Initial Request for Information
ML20309A360
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 11/04/2020
From: Vincent Gaddy
Region 4 Engineering Branch 1
To: Peters K
Vistra Operations Company
References
IR 2020011
Download: ML20309A360 (7)


See also: IR 05000445/2021011

Text

November 4, 2020

Mr. Ken Peters

Senior Vice President and

Chief Nuclear Officer

Attention: Regulatory Affairs

Vistra Operations Company LLC

P.O. Box 1002

Glen Rose, TX 76043

SUBJECT: COMANCHE PEAK NUCLEAR POWER PLANT, UNITS 1 AND 2 -

NOTIFICATION OF NRC DESIGN BASES ASSURANCE INSPECTION (TEAMS)

(INSPECTION REPORT 05000445/2021011 AND 05000446/2021011) AND

INITIAL REQUEST FOR INFORMATION

Dear Mr. Peters:

On February 8, 2021, the Nuclear Regulatory Commission (NRC) will begin a triennial

baseline component design bases inspection at the Comanche Peak Nuclear Power Plant.

A six-person team will perform this inspection using NRC Inspection Procedure 71111,

Attachment 21M, Design Bases Assurance Inspection (Teams).

The inspection focuses on the maintenance of component design bases and modifications

made to structures, systems, and components. The samples reviewed during this inspection

will be identified during an information gathering visit and during the subsequent in-office

preparation week. In addition, operating experience issues will also be selected for review.

The inspection will include an information gathering site visit by the team leader and

two weeks of onsite inspection by the team. The inspection will consist of a team lead

inspector, two mechanical inspectors, two electrical inspectors, and an operations inspector.

The current inspection schedule is as follows:

Information Gathering Visit: January 4-8, 2021

Preparation Week: February 1-5, 2021

Onsite Weeks: February 8-12 and February 22-26, 2021

The purpose of the information gathering visit is to meet with members of your staff to identify

potential risk-significant components and operator actions. The lead inspector will also request

a tour of the plant with members of your operations staff and probabilistic safety assessment

staff. During the inspection, up to 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> will be needed on the plant-referenced simulator in

order to facilitate the development and inspection of operator action-based scenarios. It has not

yet been determined if the inspection will be onsite or conducted remotely. If the inspection is

performed remotely, we are requesting that, as a minimum, actual on-site time be made

available for 1-2 days to perform component and modification walkdowns. Simulator activities

K. Peters

2

would have to be performed on site. Additional information and documentation needed to

support the inspection will be identified during the inspection, including interviews with

engineering managers, engineers, and probabilistic safety assessment staff.

Our experience with these inspections has shown that they are extremely resource intensive,

both for the NRC inspectors and the licensee staff. In order to minimize the inspection impact

on the site and to ensure a productive inspection, we have enclosed a request for information

needed for the inspection. The request has been divided into two groups. The first group lists

information necessary for the information gathering visit and for general preparation. This

information should be available to the regional office no later than January 4, 2021, unless

otherwise stated. If possible, this information should be provided electronically to the lead

inspector. Since the inspection will be concentrated on high-risk/low-margin components and

modifications, calculations associated with your list of high-risk components and modifications

should be available to review during the information gathering visit to assist in our selection of

components based on available design margin.

The second group of documents requested lists information necessary to aid the inspection

team in tracking issues identified as a result of the inspection. It is requested that this

information be provided to the lead inspector as the information is generated during the

inspection. An additional request will be made by the team during the preparation week once

the specific components and modifications have been selected. Additional requests by

inspectors will also be made throughout the onsite weeks for specific documents needed to

complete the review. It is important that all of these documents are up-to-date and complete in

order to minimize the number of additional documents requested during the preparation and/or

onsite portions of the inspection. In order to facilitate the inspection, we request that a contact

individual be assigned to each inspector to ensure information requests, questions, and

concerns are addressed in a timely manner.

The lead inspector for this inspection is Ronald A. Kopriva, Senior Reactor Inspector. If there

are any questions about the inspection or the requested materials, please contact the lead

inspector by telephone at 817-200-1104 or by e-mail at Ron.Kopriva@nrc.gov. It is our

understanding that Mr. Gary Merka will be our licensing contact for the inspection.

PAPERWORK REDUCTION ACT STATEMENT

This letter contains mandatory information collections that are subject to the Paperwork

Reduction Act of 1995 (44 U.S.C. 3501 et seq.). The Office of Management and Budget (OMB)

approved these information collections (approval number 3150-0011). Send comments

regarding this information collection to the Information Services Branch, Office of the Chief

Information Officer, Mail Stop: T6 A10M, U.S. Nuclear Regulatory Commission, Washington,

DC 20555-0001, or by e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office

of Information and Regulatory Affairs, NEOB-10202, (3150-0011) Office of Management and

Budget, Washington, DC 20503.

PUBLIC PROTECTION NOTIFICATION

The NRC may not conduct nor sponsor, and a person is not required to respond to, a request

for information or an information collection requirement unless the requesting document

displays a currently valid OMB control number.

K. Peters

3

This letter, its enclosure, and your response (if any) will be made available for public inspection

and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document

Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public

Inspections, Exemptions, Requests for Withholding.

Sincerely,

Vincent G. Gaddy, Chief

Engineering Branch 1

Division of Reactor Safety

Docket Nos. 05000445 and 05000446

License Nos. NPF-87 and NPF-89

Enclosure:

Design Bases Assurance

Inspection (Teams) Request for

Information

cc w/ encl: Distribution via LISTSERV

Vincent G.

Gaddy

Digitally signed by Vincent

G. Gaddy

Date: 2020.11.04 10:53:56

-06'00'

ML20309A360

SUNSI Review:

ADAMS:

Non-Publicly Available

Non-Sensitive

Keyword:

By: RAK

Yes No

Publicly Available

Sensitive

NRC-002

OFFICE

SRI:EB1

C:EB1

NAME

RAKopriva

VGGaddy

SIGNATURE

/RA/

/RA/

DATE

11/04/2020

11/04/2020

Enclosure

Initial Request for Information

Design Bases Assurance Inspection (Teams)

Comanche Peak Nuclear Power Plant

Inspection Report: 05000445/2021011 and 05000446/2021011

EPID ID:

I-2021-011-0002

Information Gathering Date:

January 4-8, 2021

Inspection Dates:

February 8-12, 2021, and February 22-26, 2021

Inspection Procedure:

IP 71111, Attachment 21M, Design Bases Assurance

Inspection (Teams)

Lead Inspector:

Ronald A. Kopriva, Senior Reactor Inspector

I.

Information Requested Prior to Information Gathering Visit (January 4, 2021)

The following information (Section I of this enclosure) should be sent to the Region IV

office in hard copy or electronic format (electronic database preferred), to the

attention of Ronald A. Kopriva, Senior Reactor Inspector, by January 4, 2021, to

facilitate the reduction in the items to be selected for a final list. The inspection team

will finalize the selected list during the prep week using the additional documents

requested in Section II of this enclosure. The specific items selected from the lists

shall be available and ready for review on the day indicated in this request. Please

provide requested documentation electronically in pdf files, Excel, or other

searchable formats, if possible. The information should contain descriptive names

and be indexed and hyperlinked to facilitate ease of use. Information in lists should

contain enough information to be easily understood by someone who has knowledge

of boiling water reactor technology. If requested documents are large and only hard

copy formats are available, please inform the inspector and provide subject

documentation during the first day of the onsite inspection.

1. An Excel spreadsheet of equipment basic events (with definitions), including

importance measures sorted by risk achievement worth and Fussell-Vesely

from your internal events probabilistic risk assessment. Include basic events

with risk achievement worth value of 1.3 or greater.

2. A list of the top 50 cut-sets from your PRA.

3. Copies of probabilistic risk assessment system notebooks and the

latest probabilistic risk assessment summary document.

4. An Excel spreadsheet of probabilistic risk assessment human action basic

events or risk ranking of operator actions from your site-specific PSA sorted by

risk achievement worth and Fussell-Vesely. Provide copies of your human

reliability worksheets for these items.

2

5. If you have an external events or fire PSA model, provide the information

requested in items 1-4 for external events and fire.

6. A list of high large early release frequency impact events and

associated components.

7. Structures, systems, and components in the Maintenance Rule (a)(1) Category.

8. A list of high risk maintenance rule systems/components and functions; based

on engineering or expert panel judgment.

9. Site top 10 issues list, if available.

10. Any pre-existing list of components and associated calculations with low

design margins.

11. A list of operating experience evaluations for the last 3 years.

12. A list of all time-critical operator actions in procedures.

13. A list of current operator work arounds/burdens.

14. Procedures, including emergency and abnormal, used to accomplish

operator actions associated with the basic events credited in your PRA.

15. Lists of permanent and temporary modifications performed in the past 5

years to structures, systems, and components sorted by component

identified in Item 1.

16. List of root cause evaluations associated with component failures or design

issues initiated/completed in the last 5 years.

17. A list of any common-cause failures of components in the last 3 years.

18. A copy of any internal/external self-assessments and associated corrective

action documents generated in preparation for this inspection.

19. A copy of engineering/operations-related audits completed in the last 2 years.

20. Electronic copies of the Technical Specifications, Technical Specifications

Bases, and the Final Safety Analysis Report, as updated.

21. A copy of the Individual Plant Examination of External Events, if

available electronically.

22. One-line drawings of emergency core cooling system, ultimate heat sink,

emergency feedwater, safety-related electrical systems.

3

23. A copy of condition reports associated with inspection findings from the

previous NRC Inspection Procedure 71111.21 (or 71111.21 Attachment M

inspection).

24. A list of licensee contacts for the inspection team with phone numbers.

25. A copy of the current management and engineering organizational charts.

II.

Information Requested to be provided throughout the inspection.

1. Electronic copies of the design bases documents for selected components

and modifications.

2. Electronic copies of the system health notebooks for selected components

and modifications.

3. A list of the design calculations that provide the design margin information for

selected components. (Calculations for selected components should be

available during the information gathering visit.)

4. Calculations and drawings associated with selected components.

5. Modification documentation associated with modifications selected from

Item I.15, this includes:

a. Post-modification testing, including performance characteristics affected,

assumptions, and acceptance criteria associated with modifications

selected.

b. Updated maintenance and surveillance procedures associated with

modifications.

c. Updated operation procedures and training plans associated with the

modifications.

6. Copies of any corrective action documents generated as a result of the

teams questions or queries during this inspection.

7. Copies of the list of questions submitted by the team members and the

status/resolution of the information requested (provide daily during the

inspection to each team member).

Inspector Contact Information:

Ronald A. Kopriva

Senior Reactor Inspector

817-200-1104 - Work

Ron.Kopriva@nrc.gov

Mailing Address:

U.S. NRC, Region IV

ATTN: Ronald A. Kopriva

1600 East Lamar Blvd.

Arlington, TX 76011-4511