{{#Wiki_filter:Millstone Power Station Unit 3 Safety Analysis Report Chapter 17: Quality Assurance
{{#Wiki_filter:Millstone Power Station Unit 3 Safety Analysis Report


Table of Contents tion Title                                                      Page QUALITY ASSURANCE PROGRAM TOPICAL REPORT ................. 17.1-1
Chapter 17: Quality Assurance Revision 3606/29/23 MPS-3 FSAR 17-i


QUALITY ASSURANCE PROGRAM TOPICAL REPORT omprehensive Quality Assurance Program (QAP) has been developed to assure conformance h established regulatory requirements, set forth by the Nuclear Regulatory Commission, and epted industry standards. The participants in the QAP assure that the design, procurement, struction, testing, operation, maintenance, repair, and modification of nuclear power plants are ormed in a safe and effective manner.
CHAPTER 17QUALITY ASSURANCE
QAPD Topical Report complies with the requirements set forth in Appendix B of 10 CFR 50, along with applicable sections of the Safety Analysis Report (SAR) for each license lication, and is responsive to NUREG-0800, which describes the information presented in the lity Assurance Section of the SARs for nuclear power plants. The QAPD Topical Report is rporated herein by reference.
 
s QAPD is also established, maintained, and executed with regard to Radioactive Material nsport Packages as allowed by 10 CFR 71.101(f).
Table of Contents
QAPD Topical Report is submitted periodically to the NRC in accordance with CFR 50.54(a).}}
 
Section Title Page
 
17.1 QUALITY ASSURANCE PROGRAM TOPICAL REPORT................. 17.1-1 Revision 3606/29/23 MPS-3 FSAR 17.1-1
 
CHAPTER 17 - QUALITY ASSURANCE
 
17.1 QUALITY ASSURANCE PROGRAM TOPICAL REPORT
 
A comprehensive Quality Assurance Program (QAP) has been developed to assure conformance with established regulatory requirements, set forth by the Nuclear Regulatory Commission, and accepted industry standards. The participants in the QAP assure that the design, procurement, construction, testing, operation, maintenance, repair, and modification of nuclear pow er plants are performed in a safe and effective manner.
 
The QAPD Topical Report complies with the requirements set forth in Appendix B of 10 CFR Part 50, along with applicable sections of the Safety Analysis Report (SAR) for each license application, and is responsive to NUREG-0800, which describes the information presented in the Quality Assurance Section of the SARs for nuclear power plants. The QAPD Topical Report is incorporated herein by reference.
 
This QAPD is also established, maintained, and executed with regard to Radioactive Material Transport Packages as allowed by 10 CFR 71.101(f).
 
The QAPD Topical Report is submitted periodically to the NRC in accordance with 10 CFR 50.54(a).}}

Revision as of 18:57, 13 November 2024

6 to Updated Final Safety Analysis Report, Chapter 17, Quality Assurance
ML23193A899
Person / Time
Site: Millstone Dominion icon.png
Issue date: 06/28/2023
From:
Dominion Energy Nuclear Connecticut
To:
Office of Nuclear Reactor Regulation
Shared Package
ML23193A862 List:
References
23-169
Download: ML23193A899 (1)


Text

Millstone Power Station Unit 3 Safety Analysis Report

Chapter 17: Quality Assurance Revision 3606/29/23 MPS-3 FSAR 17-i

CHAPTER 17QUALITY ASSURANCE

Table of Contents

Section Title Page

17.1 QUALITY ASSURANCE PROGRAM TOPICAL REPORT................. 17.1-1 Revision 3606/29/23 MPS-3 FSAR 17.1-1

CHAPTER 17 - QUALITY ASSURANCE

17.1 QUALITY ASSURANCE PROGRAM TOPICAL REPORT

A comprehensive Quality Assurance Program (QAP) has been developed to assure conformance with established regulatory requirements, set forth by the Nuclear Regulatory Commission, and accepted industry standards. The participants in the QAP assure that the design, procurement, construction, testing, operation, maintenance, repair, and modification of nuclear pow er plants are performed in a safe and effective manner.

The QAPD Topical Report complies with the requirements set forth in Appendix B of 10 CFR Part 50, along with applicable sections of the Safety Analysis Report (SAR) for each license application, and is responsive to NUREG-0800, which describes the information presented in the Quality Assurance Section of the SARs for nuclear power plants. The QAPD Topical Report is incorporated herein by reference.

This QAPD is also established, maintained, and executed with regard to Radioactive Material Transport Packages as allowed by 10 CFR 71.101(f).

The QAPD Topical Report is submitted periodically to the NRC in accordance with 10 CFR 50.54(a).