IR 05000271/2015009: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
Line 2: Line 2:
| number = ML15299A041
| number = ML15299A041
| issue date = 10/22/2015
| issue date = 10/22/2015
| title = IR 05000271/2015009 on 7/20-23/2015, 9/14-17/2015 and 9/30/2015, Entergy Nuclear Operations, Inc., Vermont Yankee Nuclear Power Station, Vernon, VT
| title = Ir 05000271/2015009 on 7/20-23/2015, 9/14-17/2015 and 9/30/2015, Entergy Nuclear Operations, Inc., Vermont Yankee Nuclear Power Station, Vernon, VT
| author name = Powell R J
| author name = Powell R J
| author affiliation = NRC/RGN-I/DNMS/NMSB3
| author affiliation = NRC/RGN-I/DNMS/NMSB3

Revision as of 01:23, 13 February 2018

Ir 05000271/2015009 on 7/20-23/2015, 9/14-17/2015 and 9/30/2015, Entergy Nuclear Operations, Inc., Vermont Yankee Nuclear Power Station, Vernon, VT
ML15299A041
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 10/22/2015
From: Powell R J
NRC/RGN-I/DNMS/NMSB3
To: Wamser C
Entergy Nuclear Operations
References
IR 2015009
Download: ML15299A041 (11)


Text

October 22, 2015

Docket No. 05000271License No. DPR-28 Mr. Christopher Wamser Site Vice President Entergy Nuclear Operations, Inc. Vermont Yankee Nuclear Power Station Vernon, VT 05354

SUBJECT: NRC INSPECTION REPORT NO. 05000271/2015009, ENTERGY NUCLEAR OPERATIONS, INC., VERMONT YANKEE NUCLEAR POWER STATION, VERNON, VERMONT

Dear Mr. Wamser:

On September 30, 2015, the U.S. Nuclear Regulatory Commission (NRC) completed its quarterly inspection under Inspection Manual Chapter 2561, "Decommissioning Power Reactor Inspection Program," at the permanently shut down Vermont Yankee Nuclear Power Station (VY). On-site inspections were performed on July 20-23, and September 14-17, 2015. In-office reviews of information supplied by Entergy Nuclear Operations, Inc. were also performed during the inspection period. The inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations, and the conditions of your license. The inspection consisted of observations by the inspector, interviews with personnel, and a review of procedures and records. The results of the inspection were discussed with Mike Romeo, Plant Manager, and other members of the VY staff on October 5, 2015, and are described in the enclosed report. No findings of safety significance were identified. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure(s), and your response, will be made available electronically for public inspection in the NRC Public Document Room or from the NRC document system (ADAMS), accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response should not include any personal privacy, proprietary, or safeguards information so that it can be made available to the Public without redaction. Current NRC regulations and guidance are included on the NRC's website at www.nrc.gov; select Radioactive Waste; Decommissioning of Nuclear Facilities; then Regulations, Guidance and Communications. The current Enforcement Policy is included on the NRC's website at www.nrc.gov; select About NRC, Organizations & Functions; Office of Enforcement; Enforcement documents; then Enforcement Policy (Under 'Related Information'). You may also obtain these documents by contacting the Government Printing Office (GPO) toll-free at 1-866-512-1800. The GPO is open from 8:00 a.m. to 5:30 p.m. EST, Monday through Friday (except Federal holidays). No reply to this letter is required. Please contact Steve Hammann, at 610-337-5399, if you have any questions regarding this matter.

Sincerely,/RA/ Raymond Powell, Chief Decommissioning and Technical Support Branch Division of Nuclear Materials Safety

Enclosure:

Inspection Report 05000271/2015009 cc w/encl: Distribution via ListServ