| {{#Wiki_filter:FAQ Number 06-0005 Revision 2 FAQ Title Definition of a Fire Protection Program (FPP) Change Plant: Harris Nuclear Submittal Date: 10/8/07 Plant Submitter Robert Rishel Phone: 919.546.2662 Contact: | | {{#Wiki_filter:FAQ Number 06-0005 Revision 2 FAQ Title Definition of a Fire Protection Program (FPP) Change Plant: Harris Nuclear Submittal Date: 10/8/07 Plant Submitter Robert Rishel Phone: 919.546.2662 |
| | |
| | ==Contact:== |
| Submitter Robert.rishel@pgnmail.com Email: | | Submitter Robert.rishel@pgnmail.com Email: |
| Distribution: (NEI Internal Use) 805 TF FPWG RATF RIRWG BWROG PWROG | | Distribution: (NEI Internal Use) 805 TF FPWG RATF RIRWG BWROG PWROG |
Letter Sequence Request |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance
- Supplement
|
MONTHYEARML0725500632007-08-30030 August 2007 NFPA 805 Transition Pilot Plant FAQ 06-0019, Revision 2 Project stage: Request ML0730605502007-09-0707 September 2007 NFPA 805 Transition Pilot Plant FAQ 07-0040 Project stage: Request ML0727402622007-09-20020 September 2007 NFPA-805 Transition Pilot Plant FAQ 07-0038 Project stage: Request ML0727402482007-09-20020 September 2007 NFPA-805 Transition Pilot Plant FAQ 06-0011, Revision 2 Project stage: Request ML0727402682007-09-20020 September 2007 NFPA-805 Transition Pilot Plant FAQ 07-0039 Project stage: Request ML0727402552007-09-28028 September 2007 NFPA-805 Transition Pilot Plant FAQ 06-0019, Revision 3 Project stage: Request ML0728200152007-10-0808 October 2007 NFPA-805 Transition Pilot Plant FAQ 06-0005, Revision 2 - Definition of a Fire Protection Program (FPP) Change for Harris Project stage: Request ML0735100822007-11-12012 November 2007 NFPA 805 Transition Pilot Plant FAQ 06-0025, Revision 3 (Corrected Version) Project stage: Request ML0735500232007-11-12012 November 2007 NFPA 805 Transition Pilot Plant FAQ 07-0033, Revision 1 Project stage: Request ML0733200282007-11-26026 November 2007 NFPA 805 Transition Pilot Plant FAQ 06-0012, Revision 5, Determining Manual Actions That Require a Change Evaluation During Transition Project stage: Request ML0733700252007-12-0303 December 2007 NFPA 805 Transition Pilot Plant FAQ 06-0008, Revision 8, Alternative Method for Fire Protection Engineering Analyses Project stage: Request ML0734001472007-12-0606 December 2007 NFPA 805 Transition Pilot Plant FAQ 06-0025, Revision 3 Project stage: Request ML0735500252007-12-20020 December 2007 NFPA 805 Transition Pilot Plant FAQ 07-0036, Revision 1 Project stage: Request ML0807004112008-03-10010 March 2008 NFPA 805 Transition Pilot Plant FAQ 07-0032, Revision 1, Clarification of 10 CFR 50.48(c), 50.48(a), and GDC 3 Project stage: Request ML0809101362008-03-28028 March 2008 NFPA 805 Transition Pilot Plant FAQ 07-0039, Revision 1, Lessons Learned - NEI 04-02 B-2 and B-3 Tables Project stage: Request ML0813006972008-05-0909 May 2008 NFPA 805 Transition Pilot Plant FAQ 07-0032, Revision 2 Project stage: Request ML0814300412008-05-22022 May 2008 NFPA 805 Transition Pilot Plant FAQ 07-0040, Revision 2 Project stage: Request ML0815606412008-05-29029 May 2008 Request for License Amendment to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition) Project stage: Request HNP-08-061, Redacted Public Version of Transition Report NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition2008-05-29029 May 2008 Redacted Public Version of Transition Report NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition Project stage: Request ML0816504752008-05-30030 May 2008 License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition). License Amendment Request (LAR) No. 2008-01 Project stage: Request ML0820410142008-05-30030 May 2008 Public Version of Enclosures 2 Through 6 of License Amendment Request to Adopt NFPA-805 Project stage: Request ML0816901212008-06-17017 June 2008 Forthcoming Closed Meeting with Progress Energy Carolinas, Inc., to Discuss the May 29, 2008, License Amendment Request (LAR) to Transition the Shearon Harris Nuclear Plant, Unit 1 (Harris) to National Fire Protection Association (Nfpa) Project stage: Meeting ML0818901932008-06-30030 June 2008 Completion Schedule for Part 2 of License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001) Edition, License Amendment Request No. 2008-01 Project stage: Request ML0818401392008-06-30030 June 2008 Submittal of 10 CFR 50.59 Annual Report Project stage: Request ML0818406962008-07-0707 July 2008 Meeting with Progress Energy Carolinas, Inc. and Duke Energy Carolinas, LLC, to Discuss the 05/29&30/2008, License Amendment Requests to Transition Shearon Harris, Unit 1, and Oconee, Units 1, 2, & 3 to NFPA Standard 805 Project stage: Meeting ML0818905292008-07-11011 July 2008 Summary of Closed Meeting with Progress Energy Carolinas Regarding May 29, 2008, License Amendment Request to Transition the Shearon Harris Nuclear Plant Unit 1, to National Fire Protection Association Standard 805, Performance-Based.. Project stage: Meeting ML0820703912008-07-17017 July 2008 Meeting Handouts from 7/17/08 Public Meeting on the Harris and Oconee LARs to Transition to NFPA-805 Project stage: Meeting ML0820605362008-08-0707 August 2008 Summary of Mtg. with Progress Energy Carolinas, and Duke Energy Carolinas to Discuss the LARs to Transition the Shearon Harris and Oconee Nuclear Plants to National Fire Protection Association Standard NFPA-805 Project stage: Approval ML0824202652008-09-0808 September 2008 Summary of Conference Call with Progress Energy Re License Amendment Request HNP-08-061 for Shearon Harris Project stage: Other ML0826007362008-09-17017 September 2008 Notice of Meeting with Progress Energy Carolinas, Inc. (Pec), to Discuss the Shearon Harris Nuclear Plant, Unit 1 (HNP) National Fire Protection Association (NFPA) Standard 805 License Amendment Request (LAR) Project stage: Meeting ML0827011582008-09-26026 September 2008 Acceptance Review Regarding the License Amendment Request to Transition to NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants Project stage: Acceptance Review ML0828700162008-09-26026 September 2008 Nc Warns Response to Board Notification - Enclosure P-1 - Shearon Harris Nuclear Power Plant, Unit 1 - Acceptance Review NFPA-805 License Amendment Request, September 26, 2008 Project stage: Request ML0828804552008-09-30030 September 2008 Preliminary Oconee LAR Acceptance Review Matrix Project stage: Acceptance Review ML0828902592008-10-16016 October 2008 And 10/08/2008 - Summary of Conference Calls with Duke Energy Carolinas to Discuss the Acceptance Review of the May 30, 2008, License Amendment Request (LAR) to Adopt National Fire Protection Association (NFPA) 805 for Oconee Project stage: Acceptance Review ML0830900742008-11-12012 November 2008 Summary of Category 2 Public Meeting Held to Discuss National Fire Protection Association Standard 805 Pilot Plant Process: Current Lessons Learned from the Pilot License Amendment Request Reviews (TAC Nos. MD8807, MD8832, MD8833, & MD8834) Project stage: Meeting HNP-08-113, Supplement to Request for License Amendment, to Adopt NFPA 805 Performance-Based Standards for Fire Protection for Light Water Reactor Generating Plants (2001 Edition)2008-11-14014 November 2008 Supplement to Request for License Amendment, to Adopt NFPA 805 Performance-Based Standards for Fire Protection for Light Water Reactor Generating Plants (2001 Edition) Project stage: Supplement ML0829601532008-11-17017 November 2008 Summary of Meeting with Progress Energy Carolinas, Inc., to Discuss Shearon Harris Unit 1 National Fire Protection Association Standard 805 License Amendment Request Project stage: Meeting HNP-08-121, To Request for License Amendment to Adopt NFPA 805 Performance-based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition)2008-12-11011 December 2008 To Request for License Amendment to Adopt NFPA 805 Performance-based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition) Project stage: Request ML0903000302009-01-30030 January 2009 Acceptance Review Regarding Amendment to Adopt National Fire Protection Association 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: Acceptance Review ML0903304962009-02-0202 February 2009 Acceptance Review of License Amendment Request to Adopt the National Fire Protection Association Standard No. 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, Project stage: Acceptance Review ML0902903272009-03-10010 March 2009 Regulatory Audit in Support of the License Amendment Request to Implement a Risk-Informed, Performance-Based Fire Protection Program as Allowed by Title 10 of the Code of Federal Regulations, Paragraph 50.48(c) Fire Protection Project stage: Other ML0909900182009-04-10010 April 2009 04/21-22/2009, Notice of Meeting with Progress Energy Carolinas, Inc., and Duke Energy Carolinas, LLC, to Discuss Topics Involving the License Amendment Requests to Transition the Shearon, Unit 1 and the Oconee, Units 1, 2 and 3 Project stage: Meeting ML0916002812009-06-11011 June 2009 Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity for a Hearing Project stage: Other ML0921707152009-08-0606 August 2009 Request for Additional Information Regarding Amendment to Adopt National Fire Protection Association Standard 805 (NFPA 805), Performance-Based Standard for Fire Protection for Light Water Reactor . Project stage: RAI HNP-09-076, 90-Day Inservice Inspection (ISI) Summary Report2009-08-0606 August 2009 90-Day Inservice Inspection (ISI) Summary Report Project stage: Request HNP-09-084, Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-based Standard for Fire Protection for Light Water Generating Plants2009-08-13013 August 2009 Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-based Standard for Fire Protection for Light Water Generating Plants Project stage: Response to RAI HNP-09-086, Second Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-based Standard for Fire Protection for Light Water Reactor.2009-08-28028 August 2009 Second Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-based Standard for Fire Protection for Light Water Reactor. Project stage: Response to RAI HNP-09-094, Third Response to Request for Additional Information License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor..2009-10-0909 October 2009 Third Response to Request for Additional Information License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor.. Project stage: Response to RAI HNP-09-096, Additional Information Re License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants2009-12-16016 December 2009 Additional Information Re License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants Project stage: Request 05000400/LER-2010-002, Manual Actuation of the Reactor Protection System Due to Hydrogen Seal Oil Leak2010-01-14014 January 2010 Manual Actuation of the Reactor Protection System Due to Hydrogen Seal Oil Leak Project stage: Request 2008-05-09
[Table View] |
Text
FAQ Number 06-0005 Revision 2 FAQ Title Definition of a Fire Protection Program (FPP) Change Plant: Harris Nuclear Submittal Date: 10/8/07 Plant Submitter Robert Rishel Phone: 919.546.2662
Contact:
Submitter Robert.rishel@pgnmail.com Email:
Distribution: (NEI Internal Use) 805 TF FPWG RATF RIRWG BWROG PWROG
Subject:
Definition of a Fire Protection Program (FPP) Change Is this interpretation of current guidance? Yes / No Proposed new guidance not in NEI 04-02? Yes / No Details:
NEI 04-02 guidance needing interpretation (include section, paragraph, and line numbers as applicable):
NEI 04-02 Sections 4.4 and 5.3 require revision to clarify what is considered a fire protection program-related change with respect to a Fire PRA.
Circumstances requiring guidance interpretation or new guidance:
Implementation of an NFPA 805 FPP change process requires that the plant have an acceptable fire PRA in order to use the risk acceptance criteria (Regulatory Guide 1.205 Section C.3.1).
Changes to the plants internal events PRA and therefore the Fire PRA occur for various reasons (e.g., model updates, etc). Not all these changes should be considered fire protection program changes subject to the NEI 04-02 change process. Clarification is required to delineate that changes to the Fire PRA should not be considered a FPP-related change.
Note: This FAQ was submitted as Revision 1 on October 26, 2006 (ML0631805444). NRC comments were provided on August 23, 2007 (ML072400021). The comments recommended the FAQ be divided into 3 different FAQs, with one of the issues being how the Fire PRA will be addressed with respect to the FPP. Revision 2 of FAQ 06-0005 is focused on how the Fire PRA will be addressed with respect to the FPP.
Page 1 of 3 FAQ 06-0005 FPP Changes (PRA) Rev 2.doc
FAQ Number 06-0005 Revision 2 FAQ Title Definition of a Fire Protection Program (FPP) Change Detail contentious points if licensee and NRC have not reached consensus on the facts and circumstances:
The area where agreement is requested is statement that changes in the Fire PRA are not considered a FPP-related change.
Potentially relevant existing FAQ numbers:
FAQ 06-0014, Cumulative Risk Response Section:
Proposed resolution of FAQ and the basis for the proposal:
Changes in the fire PRA and the underlying Level I and Level II PRA are not FPP-related changes and also are not considered a plant change.
Basis:
The PRA itself (data, logic, supporting documentation and analysis) is built to reflect the facility as designed and operated. Thus, a change to the PRA itself cannot be a change to the structures, systems, or components or plant procedures and is not a fire protection program-related change. An example of potential changes in the fire PRA would be revising an equipment reliability rate or changing the PRA logic for accident sequences that are not of interest to the Fire PRA (e.g., equipment dependencies for a steam generator tube rupture accident sequence). Plant changes, such as adding an additional high pressure injection pump to the facility and the associated PRA revision is a plant change. If the Nuclear Safety Capability Assessment will not be revised as a result of this change to include this new pump as a success path credited to meet the nuclear safety performance criteria, then it is not considered a fire protection program-related change, and as such, would require the NRC pre-approval per the requirements of RG1.205, if used to offset a FPP-related change with an associated risk increase.
If appropriate, provide proposed rewording of guidance for inclusion in next revision.
See attached changes to Revision 1 of NEI 04-02, Section 5.3.2 (Add as a note after Item 4 at the top of page 46 of NEI 04-02 Revision 1).
Page 2 of 3 FAQ 06-0005 FPP Changes (PRA) Rev 2.doc
Attachment to FAQ 06-0005 Revision 2 Excerpt from NEI 04-02 Revision 1 5.3.2 Defining the Change
Note: Changes to the PRA model, which includes the documentation, data elements and associated logic, do not necessarily constitute a Fire Protection Program-related change.
Additionally, any plant equipment or procedures that are used in the fire PRA or the underlying Level I and Level II PRA, but are not specifically included as part of the nuclear safety capability assessment, are not considered Fire Protection Program-related. The PRA itself (data, logic, supporting documentation and analysis) is built to reflect the facility as designed and operated. Thus a change to the PRA itself would not be a change to the structures, systems, or components or plant procedures and is not a Fire Protection Program-related change.
Page 3 of 3 FAQ 06-0005 FPP Changes (PRA) Rev 2.doc