{{#Wiki_filter:June 16, 2008 | {{#Wiki_filter:June 16, 2008 Mr. Dave Baxter Vice President, Oconee Site Duke Energy Carolinas, LLC 7800 Rochester Highway Seneca, SC 29672 | ||
Mr. Dave Baxter Vice President, Oconee Site Duke Energy Carolinas, LLC 7800 Rochester Highway Seneca, SC | |||
==SUBJECT:== | ==SUBJECT:== | ||
OCONEE NUCLEAR STATION, UNIT 1, RELIEF REQUEST | OCONEE NUCLEAR STATION, UNIT 1, RELIEF REQUEST FROM IMMEDIATE ASME CODE FLAW REPAIR OF LOW PRESSURE SERVICE WATER PIPING RELIEF REQUEST 08-ON-003 (TAC NO. MD8482) | ||
==Dear Mr. Baxter:== | ==Dear Mr. Baxter:== | ||
By letter dated April 7, 2008, you submitted Relief Request (RR) No. 08-ON-003, which proposed an alternative to the American Society of Mechanical Engineers, Boiler and Pressure Vessel Code (Code), Section XI, IWB-3132.2 requirements. In lieu of the ASME Code requirements, you proposed to accept the leaks on the downstream flange of low-pressure service water piping (LPSW) 1LPSW-21 for continued operation until the Unit 1 end-of-cycle (EOC) 24 refueling outage (RFO) using an engineering evaluation as directed by Generic Letter 90-05, | By letter dated April 7, 2008, you submitted Relief Request (RR) No. 08-ON-003, which proposed an alternative to the American Society of Mechanical Engineers, Boiler and Pressure Vessel Code (Code), Section XI, IWB-3132.2 requirements. In lieu of the ASME Code requirements, you proposed to accept the leaks on the downstream flange of low-pressure service water piping (LPSW) 1LPSW-21 for continued operation until the Unit 1 end-of-cycle (EOC) 24 refueling outage (RFO) using an engineering evaluation as directed by Generic Letter 90-05, Guidance for Performing Temporary Non-Code Repair of ASME Code Class 1, 2, and 3 Piping. | ||
You proposed the subject relief request for leaks discovered on or about January 3, 2008, on the downstream flange of 1LPSW-21, a butterfly valve in the LPSW system. You determined that performing a Code compliant repair/replacement activity at the time of the discovery of the leaks was impractical. You proposed RR 08-ON-003 to defer the Code repair/replacement until the Unit 1 EOC24 RFO. | |||
You proposed the subject relief request for leaks discovered on or about January 3, 2008, on the downstream flange of 1LPSW-21, a butterfly valve in the LPSW system. You determined that performing a Code compliant repair/replacement activity at the time of the discovery of the leaks was impractical. You proposed RR 08-ON-003 to defer the Code repair/replacement until the Unit 1 EOC24 RFO. | Your letter proposing RR 08-ON-003 was dated April 7, 2008. The Oconee Nuclear Station, Unit 1 EOC24 RFO began April 12, 2008, and you performed the Code-required repair/replacement activities during this RFO. Therefore, RR 08-ON-003 is moot at this point and no further review will be performed. | ||
If you have any further questions on this matter, please contact me at 301 415-1419. | |||
Your letter proposing RR 08-ON-003 was dated April 7, 2008. The Oconee Nuclear Station, Unit 1 EOC24 RFO began April 12, 2008, and you performed the Code-required repair/replacement activities during this RFO. Therefore, RR 08-ON-003 is moot at this point and no further review will be performed. | Sincerely, | ||
/RA/ | |||
If you have any further questions on this matter, please contact me at 301 415-1419. | Leonard N. Olshan, Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-269 cc: See next page | ||
Sincerely, | |||
Leonard N. Olshan, Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation | |||
Docket No. 50-269 | |||
June 16, 2008 Mr. Dave Baxter Vice President, Oconee Site Duke Energy Carolinas, LLC 7800 Rochester Highway Seneca, SC 29672 | |||
==SUBJECT:== | ==SUBJECT:== | ||
OCONEE NUCLEAR STATION, UNIT 1, RELIEF REQUEST FROM IMMEDIATE ASME CODE FLAW REPAIR OF LOW PRESSURE SERVICE WATER PIPING RELIEF REQUEST | OCONEE NUCLEAR STATION, UNIT 1, RELIEF REQUEST FROM IMMEDIATE ASME CODE FLAW REPAIR OF LOW PRESSURE SERVICE WATER PIPING RELIEF REQUEST 08-ON-003 (TAC NO. MD8482) | ||
==Dear Mr. Baxter:== | ==Dear Mr. Baxter:== | ||
By letter dated April 7, 2008, you submitted Relief Request (RR) No. 08-ON-003, which proposed an alternative to the American Society of Mechanical Engineers, Boiler and Pressure Vessel Code (Code), Section XI, IWB-3132.2 requirements. In lieu of the ASME Code requirements, you proposed to accept the leaks on the downstream flange of low-pressure service water piping (LPSW) 1LPSW-21 for continued operation until the Unit 1 end-of-cycle (EOC) 24 refueling outage (RFO) using an engineering evaluation as directed by Generic Letter 90-05, | By letter dated April 7, 2008, you submitted Relief Request (RR) No. 08-ON-003, which proposed an alternative to the American Society of Mechanical Engineers, Boiler and Pressure Vessel Code (Code), Section XI, IWB-3132.2 requirements. In lieu of the ASME Code requirements, you proposed to accept the leaks on the downstream flange of low-pressure service water piping (LPSW) 1LPSW-21 for continued operation until the Unit 1 end-of-cycle (EOC) 24 refueling outage (RFO) using an engineering evaluation as directed by Generic Letter 90-05,Guidance for Performing Temporary Non-Code Repair of ASME Code Class 1, 2, and 3 Piping. | ||
You proposed the subject relief request for leaks discovered on or about January 3, 2008, on the downstream flange of 1LPSW-21, a butterfly valve in the LPSW system. You determined that performing a Code compliant repair/replacement activity at the time of the discovery of the leaks was impractical. You proposed RR 08-ON-003 to defer the Code repair/replacement until the Unit 1 EOC24 RFO. | |||
You proposed the subject relief request for leaks discovered on or about January 3, 2008, on the downstream flange of 1LPSW-21, a butterfly valve in the LPSW system. You determined that performing a Code compliant repair/replacement activity at the time of the discovery of the leaks was impractical. You proposed RR 08-ON-003 to defer the Code repair/replacement until the Unit 1 EOC24 RFO. | Your letter proposing RR 08-ON-003 was dated April 7, 2008. The Oconee Nuclear Station, Unit 1 EOC24 RFO began April 12, 2008, and you performed the Code-required repair/replacement activities during this RFO. Therefore RR 08-ON-003 is moot at this point and no further review will be performed. | ||
If you have any further questions on this matter, please contact me at 301 415-1419. | |||
Your letter proposing RR 08-ON-003 was dated April 7, 2008. The Oconee Nuclear Station, Unit 1 EOC24 RFO began April 12, 2008, and you performed the Code-required repair/replacement activities during this RFO. Therefore RR 08-ON-003 is moot at this point and no further review will be performed. | Sincerely, | ||
/RA/ | |||
If you have any further questions on this matter, please contact me at 301 415-1419. | Leonard N. Olshan, Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-269 cc: See next page DISTRIBUTION: | ||
Public RidsOgcRp RidsNrrDorlDpr LPL2-1R/F RidsAcrsAcnw&mMailCenter RidsNrrCpnb (TChan) | |||
Sincerely, | RidsNrrPMLOlshan RidsNrrDorlLpl2-1 (MWong) RidsNrrOd RidsNrrLAMOBrien RidsRgn2MailCenter (JMoorman) RidsNrrAdes M. Cox, EDO Rgn II K. Hoffman, NRR Accession Number: ML081570529 memo transmitted | ||
* OFFICE NRR/LPL2-1/PM NRR/LPL2-1/LA NRR/CPNB/BC NRR/DCI/CPNB NRR/LPL2-1/BC NAME LOlshan MOBrien TChan | |||
Leonard N. Olshan, Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation | |||
Docket No. 50-269 | |||
cc: | |||
Public | |||
Accession Number: | |||
* OFFICE | |||
* KHoffman | * KHoffman | ||
* MWong DATE | * MWong DATE 6/16/08 06/12/08 06/03/08 06/03/08 6/16/08 OFFICIAL RECORD COPY | ||
Ms. Kathryn B. Nolan Senior Counsel Duke Energy Carolinas, LLC 526 South Church Street - EC07H Charlotte, NC 28202}} | Oconee Nuclear Station, Units 1, 2, and 3 cc: | ||
Mr. Dave Baxter Mr. Leonard G. Green Vice President, Oconee Site Assistant Attorney General Duke Power Company LLC NC Department of Justice 7800 Rochester Highway P.O. Box 629 Seneca, SC 29672 Raleigh, NC 27602 Ms. Lisa F. Vaughn Mr. R. L. Gill, Jr. | |||
Associate General Counsel and Managing Manager - Nuclear Regulatory Attorney Issues and Industry Affairs Duke Energy Carolinas, LLC Duke Power Company LLC 526 South Church Street - EC07H 526 S. Church St. | |||
Charlotte, North Carolina 28202 Mail Stop EC05P Charlotte, NC 28202 Manager, LIS NUS Corporation Division of Radiation Protection 2650 McCormick Dr., 3rd Floor NC Dept of Environment, Health, & Natural Clearwater, FL 34619-1035 Resources 3825 Barrett Dr. | |||
Senior Resident Inspector Raleigh, NC 27609-7721 U.S. Nuclear Regulatory Commission 7812B Rochester Highway Mr. Peter R. Harden, IV Seneca, SC 29672 VP-Customer Relations and Sales Westinghouse Electric Company Mr. Henry Porter, Director 6000 Fairview Road Division of Radioactive Waste Management 12th Floor Bureau of Land and Waste Management Charlotte, NC 28210 Dept. of Health and Env. Control 2600 Bull St. Mr. Henry Barron Columbia, SC 29201-1708 Group Vice President, Nuclear Generation and Chief Nuclear Officer Mr. B. G. Davenport P.O. Box 1006-EC07H Regulatory Compliance Manager Charlotte, NC 28201-1006 Oconee Nuclear Site Duke Energy Corporation Mr. Charles Brinkman ON03RC Director, Washington Operations 7800 Rochester Highway Westinghouse Electric Company Seneca, SC 29672 12300 Twinbrook Parkway, Suite 330 Rockville, MD 20852 Ronnie L. Gardner, PMP Manager, Site Operations and Corporate Ms. Kathryn B. Nolan Regulatory Affairs Senior Counsel AREVA NP Inc. Duke Energy Carolinas, LLC An AREVA AND Siemens Company 526 South Church Street - EC07H 3315 Old Forest Road OF -16 Charlotte, NC 28202 Lynchburg, VA 24501}} | |||
Revision as of 16:00, 14 November 2019
| ML081570529 | |
| Person / Time | |
|---|---|
| Site: | Oconee |
| Issue date: | 06/16/2008 |
| From: | Olshan L NRC/NRR/ADRO/DORL/LPLII-1 |
| To: | Baxter D Duke Energy Carolinas |
| Olshan L N, NRR/DORL, 415-1419 | |
| References | |
| TAC MD8482 | |
| Download: ML081570529 (3) | |
Text
June 16, 2008 Mr. Dave Baxter Vice President, Oconee Site Duke Energy Carolinas, LLC 7800 Rochester Highway Seneca, SC 29672
SUBJECT:
OCONEE NUCLEAR STATION, UNIT 1, RELIEF REQUEST FROM IMMEDIATE ASME CODE FLAW REPAIR OF LOW PRESSURE SERVICE WATER PIPING RELIEF REQUEST 08-ON-003 (TAC NO. MD8482)
Dear Mr. Baxter:
By letter dated April 7, 2008, you submitted Relief Request (RR) No. 08-ON-003, which proposed an alternative to the American Society of Mechanical Engineers, Boiler and Pressure Vessel Code (Code),Section XI, IWB-3132.2 requirements. In lieu of the ASME Code requirements, you proposed to accept the leaks on the downstream flange of low-pressure service water piping (LPSW) 1LPSW-21 for continued operation until the Unit 1 end-of-cycle (EOC) 24 refueling outage (RFO) using an engineering evaluation as directed by Generic Letter 90-05, Guidance for Performing Temporary Non-Code Repair of ASME Code Class 1, 2, and 3 Piping.
You proposed the subject relief request for leaks discovered on or about January 3, 2008, on the downstream flange of 1LPSW-21, a butterfly valve in the LPSW system. You determined that performing a Code compliant repair/replacement activity at the time of the discovery of the leaks was impractical. You proposed RR 08-ON-003 to defer the Code repair/replacement until the Unit 1 EOC24 RFO.
Your letter proposing RR 08-ON-003 was dated April 7, 2008. The Oconee Nuclear Station, Unit 1 EOC24 RFO began April 12, 2008, and you performed the Code-required repair/replacement activities during this RFO. Therefore, RR 08-ON-003 is moot at this point and no further review will be performed.
If you have any further questions on this matter, please contact me at 301 415-1419.
Sincerely,
/RA/
Leonard N. Olshan, Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-269 cc: See next page
June 16, 2008 Mr. Dave Baxter Vice President, Oconee Site Duke Energy Carolinas, LLC 7800 Rochester Highway Seneca, SC 29672
SUBJECT:
OCONEE NUCLEAR STATION, UNIT 1, RELIEF REQUEST FROM IMMEDIATE ASME CODE FLAW REPAIR OF LOW PRESSURE SERVICE WATER PIPING RELIEF REQUEST 08-ON-003 (TAC NO. MD8482)
Dear Mr. Baxter:
By letter dated April 7, 2008, you submitted Relief Request (RR) No. 08-ON-003, which proposed an alternative to the American Society of Mechanical Engineers, Boiler and Pressure Vessel Code (Code),Section XI, IWB-3132.2 requirements. In lieu of the ASME Code requirements, you proposed to accept the leaks on the downstream flange of low-pressure service water piping (LPSW) 1LPSW-21 for continued operation until the Unit 1 end-of-cycle (EOC) 24 refueling outage (RFO) using an engineering evaluation as directed by Generic Letter 90-05,Guidance for Performing Temporary Non-Code Repair of ASME Code Class 1, 2, and 3 Piping.
You proposed the subject relief request for leaks discovered on or about January 3, 2008, on the downstream flange of 1LPSW-21, a butterfly valve in the LPSW system. You determined that performing a Code compliant repair/replacement activity at the time of the discovery of the leaks was impractical. You proposed RR 08-ON-003 to defer the Code repair/replacement until the Unit 1 EOC24 RFO.
Your letter proposing RR 08-ON-003 was dated April 7, 2008. The Oconee Nuclear Station, Unit 1 EOC24 RFO began April 12, 2008, and you performed the Code-required repair/replacement activities during this RFO. Therefore RR 08-ON-003 is moot at this point and no further review will be performed.
If you have any further questions on this matter, please contact me at 301 415-1419.
Sincerely,
/RA/
Leonard N. Olshan, Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-269 cc: See next page DISTRIBUTION:
Public RidsOgcRp RidsNrrDorlDpr LPL2-1R/F RidsAcrsAcnw&mMailCenter RidsNrrCpnb (TChan)
RidsNrrPMLOlshan RidsNrrDorlLpl2-1 (MWong) RidsNrrOd RidsNrrLAMOBrien RidsRgn2MailCenter (JMoorman) RidsNrrAdes M. Cox, EDO Rgn II K. Hoffman, NRR Accession Number: ML081570529 memo transmitted
- OFFICE NRR/LPL2-1/PM NRR/LPL2-1/LA NRR/CPNB/BC NRR/DCI/CPNB NRR/LPL2-1/BC NAME LOlshan MOBrien TChan
- KHoffman
- MWong DATE 6/16/08 06/12/08 06/03/08 06/03/08 6/16/08 OFFICIAL RECORD COPY
Oconee Nuclear Station, Units 1, 2, and 3 cc:
Mr. Dave Baxter Mr. Leonard G. Green Vice President, Oconee Site Assistant Attorney General Duke Power Company LLC NC Department of Justice 7800 Rochester Highway P.O. Box 629 Seneca, SC 29672 Raleigh, NC 27602 Ms. Lisa F. Vaughn Mr. R. L. Gill, Jr.
Associate General Counsel and Managing Manager - Nuclear Regulatory Attorney Issues and Industry Affairs Duke Energy Carolinas, LLC Duke Power Company LLC 526 South Church Street - EC07H 526 S. Church St.
Charlotte, North Carolina 28202 Mail Stop EC05P Charlotte, NC 28202 Manager, LIS NUS Corporation Division of Radiation Protection 2650 McCormick Dr., 3rd Floor NC Dept of Environment, Health, & Natural Clearwater, FL 34619-1035 Resources 3825 Barrett Dr.
Senior Resident Inspector Raleigh, NC 27609-7721 U.S. Nuclear Regulatory Commission 7812B Rochester Highway Mr. Peter R. Harden, IV Seneca, SC 29672 VP-Customer Relations and Sales Westinghouse Electric Company Mr. Henry Porter, Director 6000 Fairview Road Division of Radioactive Waste Management 12th Floor Bureau of Land and Waste Management Charlotte, NC 28210 Dept. of Health and Env. Control 2600 Bull St. Mr. Henry Barron Columbia, SC 29201-1708 Group Vice President, Nuclear Generation and Chief Nuclear Officer Mr. B. G. Davenport P.O. Box 1006-EC07H Regulatory Compliance Manager Charlotte, NC 28201-1006 Oconee Nuclear Site Duke Energy Corporation Mr. Charles Brinkman ON03RC Director, Washington Operations 7800 Rochester Highway Westinghouse Electric Company Seneca, SC 29672 12300 Twinbrook Parkway, Suite 330 Rockville, MD 20852 Ronnie L. Gardner, PMP Manager, Site Operations and Corporate Ms. Kathryn B. Nolan Regulatory Affairs Senior Counsel AREVA NP Inc. Duke Energy Carolinas, LLC An AREVA AND Siemens Company 526 South Church Street - EC07H 3315 Old Forest Road OF -16 Charlotte, NC 28202 Lynchburg, VA 24501