{{#Wiki_filter:May 28, 2009 Richard L. Anderson Vice President, Duane Arnold Energy Center FPL Energy Duane Arnold, LLC 3277 DAEC Road Palo, IA | {{#Wiki_filter:May 28, 2009 Richard L. Anderson Vice President, Duane Arnold Energy Center FPL Energy Duane Arnold, LLC 3277 DAEC Road Palo, IA 52324 | ||
==SUBJECT:== | ==SUBJECT:== | ||
SCHEDULE FOR THE CONDUCT OF REVIEW OF THE DUANE ARNOLD ENERGY CENTER LICENSE RENEWAL APPLICATION (TAC NO. MD9769) | SCHEDULE FOR THE CONDUCT OF REVIEW OF THE DUANE ARNOLD ENERGY CENTER LICENSE RENEWAL APPLICATION (TAC NO. MD9769) | ||
==Dear Mr. Anderson:== | ==Dear Mr. Anderson:== | ||
On October 1, 2008 the U.S. Nuclear Regulatory Commission (NRC or the staff) received FPL Energy Duane Arnold, | On October 1, 2008 the U.S. Nuclear Regulatory Commission (NRC or the staff) received FPL Energy Duane Arnold, LLCs application for renewal of operating license (Operating License No. | ||
DPR-49) for the Duane Arnold Energy Center. | |||
In letter dated January 23, 2009 the license renewal application (LRA) was supplemented by FPL Energy Duane Arnold, LLC to add additional information which enabled the staff to complete its acceptance review. The license renewal typical schedule is 22 months from the receipt of the application (30 months in case of a hearing). The Duane Arnold schedule reflects a delay associated with the January LRA supplement submittal and the staffs associated acceptance review. Enclosed is the revised review schedule for the Duane Arnold Energy Center LRA. | |||
If you have any questions on the revised schedule, please contact me by telephone at 301-415-3137 or by e-mail at maurice.heath@nrc.gov. | |||
Sincerely, | |||
\RA\ | |||
Maurice Heath, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-331 | |||
==Enclosure:== | |||
As stated cc w/encl: See next page | |||
May 28, 2009 Richard L. Anderson Vice President, Duane Arnold Energy Center FPL Energy Duane Arnold, LLC 3277 DAEC Road Palo, IA 52324 | |||
==SUBJECT:== | ==SUBJECT:== | ||
SCHEDULE FOR THE CONDUCT OF REVIEW OF THE DUANE ARNOLD ENERGY CENTER LICENSE RENEWAL APPLICATION (TAC NO. MD9769) | SCHEDULE FOR THE CONDUCT OF REVIEW OF THE DUANE ARNOLD ENERGY CENTER LICENSE RENEWAL APPLICATION (TAC NO. MD9769) | ||
==Dear Mr. Anderson:== | ==Dear Mr. Anderson:== | ||
On October 1, 2008 the U.S. Nuclear Regulatory Commission (NRC or the staff) received FPL Energy Duane Arnold, | On October 1, 2008 the U.S. Nuclear Regulatory Commission (NRC or the staff) received FPL Energy Duane Arnold, LLCs application for renewal of operating license (Operating License No. | ||
In letter dated January 23, 2009 the license renewal application (LRA) was supplemented by FPL Energy Duane Arnold, LLC to add additional information which enabled the staff to complete its acceptance review. The license renewal typical schedule is 22 months from the receipt of the application (30 months in case of a hearing). The Duane Arnold schedule reflects a delay associated with the January LRA supplement submittal and the | DPR-49) for the Duane Arnold Energy Center. | ||
If you have any questions on the revised schedule, please contact me by telephone at | In letter dated January 23, 2009 the license renewal application (LRA) was supplemented by FPL Energy Duane Arnold, LLC to add additional information which enabled the staff to complete its acceptance review. The license renewal typical schedule is 22 months from the receipt of the application (30 months in case of a hearing). The Duane Arnold schedule reflects a delay associated with the January LRA supplement submittal and the staffs associated acceptance review. Enclosed is a the revised review schedule for the Duane Arnold Energy Center LRA. | ||
If you have any questions on the revised schedule, please contact me by telephone at 301-415-3137 or by e-mail at maurice.heath@nrc.gov. | |||
Sincerely, | |||
\RA\ | |||
Maurice Heath, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-331 | |||
==Enclosure:== | ==Enclosure:== | ||
As stated cc w/encl: See next page DISTRIBUTION: See next page ADAMS Accession no.: ML091200187 OFFICE LA:DLR PM:RPB1 PM:RPB1 BC:RPB1 NAME SFigueroa MHeath CEccelston DPelton (JRobinson for) | |||
DATE 5/5/09 5/28/09 5/6/09 5/28/09 OFFICIAL RECORD COPY | |||
DUANE ARNOLD ENERGY CENTER LICENSE RENEWAL APPLICATION REVIEW SCHEDULE Milestones Schedule Actual Receive License Renewal (LR) Application 10/01/08 10/01/08 Federal Register Notice (FRN) Published- Receipt & Availability 11/17/08 11/17/08 FRN Published - Acceptability/Opportunity for Hearing 2/17/09 2/17/09 FRN Published-Notice of Intent to Conduct Environmental Scoping 3/24/09 3/24/09 Public Meeting - Process Overview and Environmental Scoping 4/22/09 4/22/09 Deadline for Filing Hearing Requests and Petitions for Intervention 4/20/09 4/20/09 Environmental Scoping Period Ends 5/26/09 5/26/09 Audit - Environmental 6/15/09 Audit - Scoping & Screening Methodology 8/24/09 Audit - Aging Management 8/10/09 Issue draft Supplemental Environmental Impact Statement (SEIS) 1/12/10 Publish FRN - draft SEIS available for comments 1/29/10 Public Meeting - draft SEIS meeting 2/24/10 Safety Evaluation Report (SER) with Open Items - Issued 3/19/10 End of draft SEIS Comment Period 4/7/10 ACRS Subcommittee Meeting on SER with Open Items 5/10 SER - Issued 8/23/10 Final SEIS - Issued 10/8/10 U.S. EPA FRN Published - Availability of Final SEIS 10/15/10 ACRS Full Committee Meeting on SER 10/10 Decision Director NRR - Approval (26 months if no hearing) 12/10 ENCLOSURE | |||
Mark E. Warner Vice President, Nuclear Plant Support Florida Power & Light Company P.O. Box 14000 Juno Beach, FL | Duane Arnold Energy Center cc: | ||
Mr. Mano Nazar Mr. D. A. Curtland Executive Vice President, Nuclear and Chief Plant Manager Nuclear Officer Duane Arnold Energy Center Florida Power & Light Company 3277 DAEC Road P.O. Box 14000 Palo, IA 52324-9785 Juno Beach, FL 33408-0420 Abdy Khanpour Mr. M. S. Ross Vice President, Engineering Support Managing Attorney Florida Power & Light Company Florida Power & Light Company P.O. Box 14000 P.O. Box 14000 Juno Beach, FL 33408 Juno Beach, FL 33408-0420 Daniel K. McGhee Ms. Marjan Mashhadi Iowa Department of Public Health Senior Attorney Bureau of Radiological Health Florida Power & Light Company 321 East 12th Street 801 Pennsylvania Avenue, NW Lucas State Office Building, 5th Floor Suite 220 Des Moines, IA 50319-0075 Washington, DC 20004 Chairman, Linn County T. O. Jones Board of Supervisors Vice President, Nuclear Operations 930 1st Street SW Mid-West Region Cedar Rapids, IA 52404 Florida Power & Light Company P.O. Box 14000 Peter Wells, Acting Vice President, Nuclear Juno Beach, FL 33408 Training and Performance Improvement Florida Power & Light Company Steven R. Catron P.O. Box 14000 Manager, Regulatory Affairs Juno Beach, FL 33408-0420 Duane Arnold Energy Center 3277 DAEC Road Mark E. Warner Palo, IA 52324 Vice President, Nuclear Plant Support Florida Power & Light Company U.S. Nuclear Regulatory Commission P.O. Box 14000 Resident Inspector=s Office Juno Beach, FL 33408-0420 Rural Route #1 Palo, IA 52324 Mr. Mano Nazar Senior Vice President and Nuclear Chief Operating Officer Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408 | |||
Letter to R. Anderson from M. Heath, dated May 28, 2009 DISTRIBUTION | Letter to R. Anderson from M. Heath, dated May 28, 2009 DISTRIBUTION: | ||
: | |||
==SUBJECT:== | ==SUBJECT:== | ||
SCHEDULE FOR THE CONDUCT OF REVIEW OF THE DUANE ARNOLD ENERGY CENTER LICENSE RENEWAL APPLICATION (TAC NO. MD9769) | SCHEDULE FOR THE CONDUCT OF REVIEW OF THE DUANE ARNOLD ENERGY CENTER LICENSE RENEWAL APPLICATION (TAC NO. MD9769) | ||
HARD COPY: DLR RF E-MAIL: PUBLIC [or NON-PUBLIC, if appropriate] | HARD COPY: | ||
RidsNrrDlrResource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRer1 Resource RidsNrrDlrRer2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDciCsgb Resource RidsNrrDraAfpb Resource RidsNrrDraApla Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource ------------- M. Heath C. Eccelston M. Baty K. Feintuch}} | DLR RF E-MAIL: | ||
PUBLIC [or NON-PUBLIC, if appropriate] | |||
RidsNrrDlrResource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRer1 Resource RidsNrrDlrRer2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDciCsgb Resource RidsNrrDraAfpb Resource RidsNrrDraApla Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource | |||
------------- | |||
M. Heath C. Eccelston M. Baty K. Feintuch}} | |||
Revision as of 06:35, 14 November 2019
| ML091200187 | |
| Person / Time | |
|---|---|
| Site: | Duane Arnold |
| Issue date: | 05/28/2009 |
| From: | Maurice Heath License Renewal Projects Branch 1 |
| To: | Richard Anderson Duane Arnold |
| Heath, M, NRR/DLR/RLRA, 415-3137 | |
| References | |
| TAC MD9769 | |
| Download: ML091200187 (5) | |
Text
May 28, 2009 Richard L. Anderson Vice President, Duane Arnold Energy Center FPL Energy Duane Arnold, LLC 3277 DAEC Road Palo, IA 52324
SUBJECT:
SCHEDULE FOR THE CONDUCT OF REVIEW OF THE DUANE ARNOLD ENERGY CENTER LICENSE RENEWAL APPLICATION (TAC NO. MD9769)
Dear Mr. Anderson:
On October 1, 2008 the U.S. Nuclear Regulatory Commission (NRC or the staff) received FPL Energy Duane Arnold, LLCs application for renewal of operating license (Operating License No.
DPR-49) for the Duane Arnold Energy Center.
In letter dated January 23, 2009 the license renewal application (LRA) was supplemented by FPL Energy Duane Arnold, LLC to add additional information which enabled the staff to complete its acceptance review. The license renewal typical schedule is 22 months from the receipt of the application (30 months in case of a hearing). The Duane Arnold schedule reflects a delay associated with the January LRA supplement submittal and the staffs associated acceptance review. Enclosed is the revised review schedule for the Duane Arnold Energy Center LRA.
If you have any questions on the revised schedule, please contact me by telephone at 301-415-3137 or by e-mail at maurice.heath@nrc.gov.
Sincerely,
\RA\
Maurice Heath, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-331
Enclosure:
As stated cc w/encl: See next page
May 28, 2009 Richard L. Anderson Vice President, Duane Arnold Energy Center FPL Energy Duane Arnold, LLC 3277 DAEC Road Palo, IA 52324
SUBJECT:
SCHEDULE FOR THE CONDUCT OF REVIEW OF THE DUANE ARNOLD ENERGY CENTER LICENSE RENEWAL APPLICATION (TAC NO. MD9769)
Dear Mr. Anderson:
On October 1, 2008 the U.S. Nuclear Regulatory Commission (NRC or the staff) received FPL Energy Duane Arnold, LLCs application for renewal of operating license (Operating License No.
DPR-49) for the Duane Arnold Energy Center.
In letter dated January 23, 2009 the license renewal application (LRA) was supplemented by FPL Energy Duane Arnold, LLC to add additional information which enabled the staff to complete its acceptance review. The license renewal typical schedule is 22 months from the receipt of the application (30 months in case of a hearing). The Duane Arnold schedule reflects a delay associated with the January LRA supplement submittal and the staffs associated acceptance review. Enclosed is a the revised review schedule for the Duane Arnold Energy Center LRA.
If you have any questions on the revised schedule, please contact me by telephone at 301-415-3137 or by e-mail at maurice.heath@nrc.gov.
Sincerely,
\RA\
Maurice Heath, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-331
Enclosure:
As stated cc w/encl: See next page DISTRIBUTION: See next page ADAMS Accession no.: ML091200187 OFFICE LA:DLR PM:RPB1 PM:RPB1 BC:RPB1 NAME SFigueroa MHeath CEccelston DPelton (JRobinson for)
DATE 5/5/09 5/28/09 5/6/09 5/28/09 OFFICIAL RECORD COPY
DUANE ARNOLD ENERGY CENTER LICENSE RENEWAL APPLICATION REVIEW SCHEDULE Milestones Schedule Actual Receive License Renewal (LR) Application 10/01/08 10/01/08 Federal Register Notice (FRN) Published- Receipt & Availability 11/17/08 11/17/08 FRN Published - Acceptability/Opportunity for Hearing 2/17/09 2/17/09 FRN Published-Notice of Intent to Conduct Environmental Scoping 3/24/09 3/24/09 Public Meeting - Process Overview and Environmental Scoping 4/22/09 4/22/09 Deadline for Filing Hearing Requests and Petitions for Intervention 4/20/09 4/20/09 Environmental Scoping Period Ends 5/26/09 5/26/09 Audit - Environmental 6/15/09 Audit - Scoping & Screening Methodology 8/24/09 Audit - Aging Management 8/10/09 Issue draft Supplemental Environmental Impact Statement (SEIS) 1/12/10 Publish FRN - draft SEIS available for comments 1/29/10 Public Meeting - draft SEIS meeting 2/24/10 Safety Evaluation Report (SER) with Open Items - Issued 3/19/10 End of draft SEIS Comment Period 4/7/10 ACRS Subcommittee Meeting on SER with Open Items 5/10 SER - Issued 8/23/10 Final SEIS - Issued 10/8/10 U.S. EPA FRN Published - Availability of Final SEIS 10/15/10 ACRS Full Committee Meeting on SER 10/10 Decision Director NRR - Approval (26 months if no hearing) 12/10 ENCLOSURE
Duane Arnold Energy Center cc:
Mr. Mano Nazar Mr. D. A. Curtland Executive Vice President, Nuclear and Chief Plant Manager Nuclear Officer Duane Arnold Energy Center Florida Power & Light Company 3277 DAEC Road P.O. Box 14000 Palo, IA 52324-9785 Juno Beach, FL 33408-0420 Abdy Khanpour Mr. M. S. Ross Vice President, Engineering Support Managing Attorney Florida Power & Light Company Florida Power & Light Company P.O. Box 14000 P.O. Box 14000 Juno Beach, FL 33408 Juno Beach, FL 33408-0420 Daniel K. McGhee Ms. Marjan Mashhadi Iowa Department of Public Health Senior Attorney Bureau of Radiological Health Florida Power & Light Company 321 East 12th Street 801 Pennsylvania Avenue, NW Lucas State Office Building, 5th Floor Suite 220 Des Moines, IA 50319-0075 Washington, DC 20004 Chairman, Linn County T. O. Jones Board of Supervisors Vice President, Nuclear Operations 930 1st Street SW Mid-West Region Cedar Rapids, IA 52404 Florida Power & Light Company P.O. Box 14000 Peter Wells, Acting Vice President, Nuclear Juno Beach, FL 33408 Training and Performance Improvement Florida Power & Light Company Steven R. Catron P.O. Box 14000 Manager, Regulatory Affairs Juno Beach, FL 33408-0420 Duane Arnold Energy Center 3277 DAEC Road Mark E. Warner Palo, IA 52324 Vice President, Nuclear Plant Support Florida Power & Light Company U.S. Nuclear Regulatory Commission P.O. Box 14000 Resident Inspector=s Office Juno Beach, FL 33408-0420 Rural Route #1 Palo, IA 52324 Mr. Mano Nazar Senior Vice President and Nuclear Chief Operating Officer Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408
Letter to R. Anderson from M. Heath, dated May 28, 2009 DISTRIBUTION:
SUBJECT:
SCHEDULE FOR THE CONDUCT OF REVIEW OF THE DUANE ARNOLD ENERGY CENTER LICENSE RENEWAL APPLICATION (TAC NO. MD9769)
HARD COPY:
DLR RF E-MAIL:
PUBLIC [or NON-PUBLIC, if appropriate]
RidsNrrDlrResource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRer1 Resource RidsNrrDlrRer2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDciCsgb Resource RidsNrrDraAfpb Resource RidsNrrDraApla Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource
M. Heath C. Eccelston M. Baty K. Feintuch