{{#Wiki_filter:NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE     JPM: RO ADMIN 1a TITLE: DETERMINE QUADRANT POWER TILT PER PO-3     CANDIDATE:   EXAMINER:
{{#Wiki_filter:NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO ADMIN 1a TITLE: DETERMINE QUADRANT POWER TILT PER PO-3 CANDIDATE:
JPM RO ADMIN 1a PALISADES NUCLEAR PLANT Page 2 of 8 SEPTEMBER 2014  JOB PERFORMANCE MEASURE DATA PAGE   Task: Determine Quadrant Power Tilt per PO-3 Alternate Path: N/A Facility JPM #: 2010 NRC EXAM K/A: G2.1.7           Importance: RO: 4.4   SRO: 4.7 K/A Statement: Ability to evaluate plant performance and make operational judgments based on operating characteristics, reactor behavior, and instrument interpretation. Task Standard: Four NI Power readings recorded within +/- 1% of key and Quadrant Power Tilt calculated correctly per PO-3 Preferred Evaluation Location: Simulator __X__ In Plant _____ Preferred Evaluation Method: Perform __X__ Simulate _____
EXAMINER:
 
JPM RO ADMIN 1a JOB PERFORMANCE MEASURE DATA PAGE Task: Determine Quadrant Power Tilt per PO-3 Alternate Path: N/A Facility JPM #: 2010 NRC EXAM K/A: G2.1.7       Importance: RO: 4.4 SRO: 4.7 K/A Statement: Ability to evaluate plant performance and make operational judgments based on operating characteristics, reactor behavior, and instrument interpretation.
Task Standard: Four NI Power readings recorded within +/- 1% of key and Quadrant Power Tilt calculated correctly per PO-3 Preferred Evaluation Location: Simulator       __X__   In Plant   _____
Preferred Evaluation Method:       Perform     __X__   Simulate   _____


==References:==
==References:==
PO-3, Alternate Incore and Excore Applications Validation Time: 22 minutes Time Critical: NO   Candidate:   Time Start: ________ Time Finish: ________ Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______ Comments:         Examiner: _______________________________ Date: ______________ Signature JPM RO ADMIN 1a PALISADES NUCLEAR PLANT Page 3 of 8 SEPTEMBER 2014 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed: PO-3, Incore and Excore Applications Also see Simulator Operator Instructions (last page of this document). READ TO CANDIDATE DIRECTION TO CANDIDATE: I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:   Plant was at full power. Incores #9 and #35 are inoperable. Control Rod #11 has dropped into the core. INITIATING CUES: During performance of PO-3, Alternate Incore and Excore Applications, the Control Room Supervisor directs you to perform Excore Quadrant Power Tilt per section 5.2 of PO-3.
PO-3, Alternate Incore and Excore Applications Validation Time:     22 minutes       Time Critical: NO Candidate:
JPM RO ADMIN 1a PALISADES NUCLEAR PLANT Page 4 of 8 SEPTEMBER 2014 EVALUATOR CUE: Provide candidate with a working copy of PO-3 entire procedure with SRO approval indicated in section 3.1.1 Proc. Step TASK ELEMENT 1 STANDARD Grade 5.2.1 Obtain lower and upper excore readings as required. (SAL, SBL, SCL, SDL and SAU, SBU, SCU, SDU). Lower and upper excore readings from the Upper and Lower NI Detector meters on EC-06 are entered on PO-3, Attachment 2 per the answer key. S  U Comment:   CRITICAL STEP   Proc. Step TASK ELEMENT 2 STANDARD Grade 5.2.1 Calculate the sum from the Lower + Upper excore readings (SA, SB, SC, SD)  Lower + Upper excore readings (SA, SB, SC, SD) summed and entered on PO-3, Attachment #2, within per the answer key. S  U Comment:   CRITICAL STEP   Proc. Step TASK ELEMENT 3 STANDARD Grade 5.2.1 1. Calculate the sum of all excore readings divided by 4: (S =  all detectors/4). Sum of all excores reading divided by 4 calculated and entered on PO-3, Attachment 2. S  U Comment:   CRITICAL STEP JPM RO ADMIN 1a PALISADES NUCLEAR PLANT Page 5 of 8 SEPTEMBER 2014 Proc. Step TASK ELEMENT 4 STANDARD Grade Att 2 Note Calculate the Quadrant Tilt. Using the formula TEX = [(SX - S)/S], calculate the tilt for each Quadrant. S U Comment: EVALUATOR NOTE: All four Quadrant Tilts should add up to approximately zero (0). CRITICAL STEP   Proc. Step TASK ELEMENT 5 STANDARD Grade 5.2.1 Have calculations verified. Have another qualified individual verify the calculations. S U Comment: EVALUATOR NOTE: Sign-off as the other qualified individual verifying the calculation.     Proc. Step TASK ELEMENT 6 STANDARD Grade n/a Notify the CRS that Excore Quadrant Power Tilt has been completed per PO-3, Attachment 2. Operator notifies CRS of completion of PO-3, Attachment 2, Excore Quadrant Power Tilt and recognizes Tech Spec limits are exceeded. S  U Comment: EVALUATOR CUE: If candidate does NOT indicate values above 0.05 as being out of tolerance readings, then ask the following: A Answer should include that Flux Tilt limit of less than or equal to 0.05 is specified in LCO CRITICAL STEP (recognize Tech Specs are exceeded) END OF TASK JPM RO ADMIN 1a PALISADES NUCLEAR PLANT Page 6 of 8 SEPTEMBER 2014 SIMULATOR OPERATOR INSTRUCTIONS SIMULATOR SET UP: Simulator Setup Instructions: Full power IC Drop Control Rod #11 fully into the core with RD-11 (Final Value = 2) on PIDRD02 When plant has stabilized, freeze the Simulator and SNAP Use PO-3, Attachment 2 and record/calculate from the Upper and Lower NI Detector meters on EC-06 and use as answer key.
Time Start: ________         Time Finish:     ________
JPM RO ADMIN 1a PALISADES NUCLEAR PLANT Page 7 of 8 SEPTEMBER 2014   Excore Lower Reading (%) SAL, SBL, SCL, SDL  Upper Reading (%) SAU, SBU, SCU, SDU  Lower + Upper SA, SB, SC, SD  S = ( All Detectors)/4   = (SA + SB + SC + SD)/4 Excore Quadrant Tilt TEA, TEB, TEC, TED 5 (CH A)   SAL = [NI-005 Lower (A)] 51 (50.5-51.5)   SAU = [NI-005 Upper (B)] 50 (49.5-50.5) SA = SAL + SAU  101 (100-102)       95.75 (94.75-96.75) TEA = [(SA-S)/S] 0.055 (0.034 to 0.076) QUAD 1    6 (CH B)  SBL = [NI-0065 Lower (A)] 41 (40.5-41.5)   SBU = [NI-006 Upper (B)] 40 (39.5-40.5) SB = SBL + SBU  81 (80-82) TEB = [(SB-S)/S]  -0.154 (-0.17 to -0.13) QUAD 3    7 (CH C)   SCL = [NI-007 Lower (A)] 50 (49.5-50.5)  SCU = [NI-007 Upper (B)] 50 (49.5-50.5) SC = SCL + SCU  100 (99-101) TEC = [(SC-S)/S]  0.044 (0.023 to 0.066) QUAD 4    8 (CH D)   SDL = [NI-008 Lower (A)] 52 (51.5-52.5)   SDU = [NI-008 Upper (B)] 49 (48.5-49.5) SD = SDL + SDU  101 (100-102) TED = [(SD-S)/S]  0.055 (0.034 to 0.076) QUAD 2    NOTE: The four QPTs should sum to approximately zero. Comments:       Performed By: ____Pat Person_________________________________ Date: _____Today__________     Time: _______Now______ Calculations Verified By: _____________________________________________________ Date: _______________ After calculations are verified, forward to NSSS and Reactor Engineering Supervisor or designee for final review. Reactor Engineering Supervisor or designee: _______________________________________ Date: _______________ ANSWER KEY ANSWER KEY ANSWER KEY ANSWER KEY ANSWER KEY ANSWER KEY JPM RO ADMIN 1a PALISADES NUCLEAR PLANT Page 8 of 8 SEPTEMBER 2014   CANDIDATE CUE SHEET   (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)   INITIAL CONDITIONS:   Plant was at full power. Incores #9 and #35 are inoperable. Control Rod #11 has dropped into the core. INITIATING CUES: During performance of PO-3, Alternate Incore and Excore Applicationsthe Control Room Supervisor directs you to perform Excore Quadrant Power Tilt per section 5.2 of PO-3.
Performance Time:       ________ minutes Performance Rating:     SAT______         UNSAT ______
NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE     JPM: RO ADMIN 1b TITLE: ESTIMATION OF RIA-0631, CONDENSER OFF GAS MONITOR COUNT RATE     CANDIDATE:   EXAMINER:
Comments:
JPM RO ADMIN 1b PALISADES NUCLEAR PLANT Page 2 of 8 SEPTEMBER 2014  JOB PERFORMANCE MEASURE DATA PAGE   Task: Determine RIA-0631 Count Rate per AOP-24 Alternate Path: N/A Facility JPM #: NEW K/A: G2.1.20           Importance: RO: 4.6   SRO: 4.6 K/A Statement: Ability to interpret and execute procedure steps. Task Standard: RIA-0631 count rate determined for 0.1 gpm leak rate 1.735E4 cpm (1.73E4 to 1.74E4cpm) Preferred Evaluation Location: ANY __X___ Preferred Evaluation Method: Perform __X__ Simulate _____
Examiner: _______________________________               Date:   ______________
Signature PALISADES NUCLEAR PLANT                   Page 2 of 8                   SEPTEMBER 2014
 
JPM RO ADMIN 1a EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:
PO-3, Alternate Incore and Excore Applications Also see Simulator Operator Instructions (last page of this document).
READ TO CANDIDATE DIRECTION TO CANDIDATE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
Plant was at full power.
Incores #9 and #35 are inoperable.
Control Rod #11 has dropped into the core.
INITIATING CUES:
During performance of PO-3, Alternate Incore and Excore Applications, the Control Room Supervisor directs you to perform Excore Quadrant Power Tilt per section 5.2 of PO-3.
PALISADES NUCLEAR PLANT                     Page 3 of 8                     SEPTEMBER 2014
 
JPM RO ADMIN 1a EVALUATOR CUE: Provide candidate with a working copy of PO-3 entire procedure with SRO approval indicated in section 3.1.1 Proc. Step           TASK ELEMENT 1                                 STANDARD                   Grade Lower and upper excore readings from the Obtain lower and upper excore Upper and Lower NI Detector meters on 5.2.1    readings as required. (SAL, SBL, SCL,                                                   S U EC-06 are entered on PO-3, Attachment 2 SDL and SAU, SBU, SCU, SDU).
per the answer key.
Comment:
CRITICAL STEP Proc. Step           TASK ELEMENT 2                                 STANDARD                   Grade Calculate the sum from the Lower +
Upper excore readings (SA, SB, SC,       Lower + Upper excore readings (SA, SB, SC, 5.2.1    SD)                                      SD) summed and entered on PO-3,               S U Attachment #2, within per the answer key.
Comment:
CRITICAL STEP Proc. Step           TASK ELEMENT 3                                 STANDARD                   Grade
: 1. Calculate the sum of all excore       Sum of all excores reading divided by 4 readings divided by 4:                calculated and entered on PO-3, 5.2.1                                              Attachment 2.                               S U (S = all detectors/4).
Comment:
CRITICAL STEP PALISADES NUCLEAR PLANT                         Page 4 of 8                             SEPTEMBER 2014
 
JPM RO ADMIN 1a Proc. Step           TASK ELEMENT 4                                 STANDARD                   Grade Using the formula T EX = [(SX - S)/S],
Att 2                                          calculate the tilt for each Quadrant.
Calculate the Quadrant Tilt.                                                        S U Note Comment:
EVALUATOR NOTE:             All four Quadrant Tilts should add up to approximately zero (0).
CRITICAL STEP Proc. Step           TASK ELEMENT 5                                 STANDARD                   Grade Have another qualified individual verify the Have calculations verified.
5.2.1                                          calculations.                                 S U Comment:
EVALUATOR NOTE:             Sign-off as the other qualified individual verifying the calculation.
Proc. Step           TASK ELEMENT 6                                 STANDARD                   Grade Operator notifies CRS of completion of Notify the CRS that Excore Quadrant PO-3, Attachment 2, Excore Quadrant n/a    Power Tilt has been completed per Power Tilt and recognizes Tech Spec limits S U PO-3, Attachment 2.
are exceeded.
Comment:
EVALUATOR CUE: If candidate does NOT indicate values above 0.05 as being out of tolerance readings, then ask the following:
Are any limits being exceeded?
Answer should include that Flux Tilt limit of less than or equal to 0.05 is specified in LCO 3.2.3, Quadrant Power Tilt CRITICAL STEP (recognize Tech Specs are exceeded)
END OF TASK PALISADES NUCLEAR PLANT                     Page 5 of 8                             SEPTEMBER 2014
 
JPM RO ADMIN 1a SIMULATOR OPERATOR INSTRUCTIONS SIMULATOR SET UP:
Simulator Setup Instructions:
Full power IC Drop Control Rod #11 fully into the core with RD-11 (Final Value = 2) on PIDRD02 When plant has stabilized, freeze the Simulator and SNAP Use PO-3, Attachment 2 and record/calculate from the Upper and Lower NI Detector meters on EC-06 and use as answer key.
PALISADES NUCLEAR PLANT               Page 6 of 8                     SEPTEMBER 2014
 
JPM RO ADMIN 1a Excore       Lower Reading (%)       Upper Reading (%)       Lower + Upper   S = ( All Detectors)/4         Excore Quadrant Tilt SAL, SBL, SCL, SDL      SAU, SBU, SCU, SDU      SA, SB, SC, SD  = (SA + SB + SC + SD)/4         TEA, TEB, TEC, TED 5 (CH A)       SAL =                  SAU =                  SA = SAL + SAU                                  TEA = [(SA-S)/S]           QUAD 1
[NI-005 Lower (A)]      [NI-005 Upper (B)]
51 (50.5-51.5)         50 (49.5-50.5)          101 (100-102)                                   0.055 (0.034 to 0.076) 6 (CH B)       SBL =                  SBU =                  SB = SBL + SBU                                  TEB = [(SB-S)/S]           QUAD 3 95.75 (94.75-96.75)
[NI-0065 Lower (A)]     [NI-006 Upper (B)]
41 (40.5-41.5)         40 (39.5-40.5)           81 (80-82)                                       -0.154 (-0.17 to -0.13) 7 (CH C)       SCL =                   SCU =                  SC = SCL + SCU                                  TEC = [(SC-S)/S]          QUAD 4
[NI-007 Lower (A)]     [NI-007 Upper (B)]
50 (49.5-50.5)         50 (49.5-50.5)           100 (99-101)                                     0.044 (0.023 to 0.066) 8 (CH D)       SDL =                   SDU =                  SD = SDL + SDU                                  TED = [(SD-S)/S]          QUAD 2
[NI-008 Lower (A)]     [NI-008 Upper (B)]
52 (51.5-52.5)         49 (48.5-49.5)           101 (100-102)                                   0.055 (0.034 to 0.076)
NOTE:         The four QPTs should sum to approximately zero.
Comments:
Performed By: ____Pat Person_________________________________                           Date: _____Today__________           Time: _______Now______
Calculations Verified By: _____________________________________________________                                               Date: _______________
After calculations are verified, forward to NSSS and Reactor Engineering Supervisor or designee for final review.
Reactor Engineering Supervisor or designee: _______________________________________                                           Date: _______________
ANSWER KEY           ANSWER KEY           ANSWER KEY           ANSWER KEY     ANSWER KEY               ANSWER KEY PALISADES NUCLEAR PLANT                             Page 7 of 8                             SEPTEMBER 2014
 
JPM RO ADMIN 1a CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
Plant was at full power.
Incores #9 and #35 are inoperable.
Control Rod #11 has dropped into the core.
INITIATING CUES:
During performance of PO-3, Alternate Incore and Excore Applications, the Control Room Supervisor directs you to perform Excore Quadrant Power Tilt per section 5.2 of PO-3.
PALISADES NUCLEAR PLANT                Page 8 of 8                      SEPTEMBER 2014
 
NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO ADMIN 1b TITLE: ESTIMATION OF RIA-0631, CONDENSER OFF GAS MONITOR COUNT RATE CANDIDATE:
EXAMINER:
 
JPM RO ADMIN 1b JOB PERFORMANCE MEASURE DATA PAGE Task: Determine RIA-0631 Count Rate per AOP-24 Alternate Path: N/A Facility JPM #: NEW K/A: G2.1.20         Importance: RO: 4.6 SRO: 4.6 K/A Statement: Ability to interpret and execute procedure steps.
Task Standard: RIA-0631 count rate determined for 0.1 gpm leak rate 1.735E4 cpm (1.73E4 to 1.74E4cpm)
Preferred Evaluation Location: ANY         __X___
Preferred Evaluation Method:       Perform     __X__   Simulate   _____


==References:==
==References:==
AOP-24, Steam Generator Tube Leak Validation Time: 8 minutes Time Critical: NO   Candidate:   Time Start: ________ Time Finish: ________ Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______ Comments:         Examiner: _______________________________ Date: ______________ Signature JPM RO ADMIN 1b PALISADES NUCLEAR PLANT Page 3 of 8 SEPTEMBER 2014 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:   AOP- ESOMS log printout that includes offgas flow reading of 7 scfm Also see Simulator Operator Instructions (last page of this document). READ TO CANDIDATE DIRECTION TO CANDIDATE: I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:   Plant was at full power. A Steam Generator Tube Leak is in progress. Crew has entered AOP- Action Level 2 is in effect. INITIATING CUES: During performance of AOP-the Control Room Supervisor directs you to estimate the count rate for RIA-0631, Condenser Off Gas Monitor that would require entry into Action Level Three, utilizing Attachment 1 of the procedure.
AOP-24, Steam Generator Tube Leak Validation Time:     8 minutes       Time Critical: NO Candidate:
JPM RO ADMIN 1b PALISADES NUCLEAR PLANT Page 4 of 8 SEPTEMBER 2014 EVALUATOR CUE: Provide candidate with a working copy of AOP-24. Proc. Step TASK ELEMENT 1 STANDARD Grade Att 1pg 3 Step 1 DETERMINE maximum Primary to Secondary Leakrate (gpm) based on current Action Level. Candidate determines 0.1 gpm to be value needed based on AOP-24, Attachment 2, page 6 and initiating cue. S  U Comment: EVALUATOR CUE: If asked as CRS, inform candidate that the rate of change in the primary to secondary leakage is stable/unchanged. CRITICAL STEP   Proc. Step TASK ELEMENT 2 STANDARD Grade Att 1 pg 3 Step 2 OBTAIN Condenser Off Gas Monitor flow rate (preferred) OR USE last known reading recorded in ESOMS narrative log if taken within 24 hours. Candidate obtains information. S  U Comment: EVALUATOR CUE: When asked as NPO/CRS, provide ESOMS log sheet that includes Offgas flowrate = 7 SCFM (Cue Sheet #2) CRITICAL STEP   Proc. Step TASK ELEMENT 3 STANDARD Grade Att 1 pg 3 Step 3 NOTIFY Chemistry to obtain the following parameters from Nuclear IQ: Bkg = RIA-0631 background reading, in cpm Rc = Total response factor RIA-0631, (cpm) Candidate obtains information. S  U Comment: EVALUATOR CUE: When asked as Chemistry, provide the following:     Background reading = 20 cpm,       Total Response Factor = 9.1E6 cpm. CRITICAL STEP JPM RO ADMIN 1b PALISADES NUCLEAR PLANT Page 5 of 8 SEPTEMBER 2014 Proc. Step TASK ELEMENT 4 STANDARD Grade Att 1 pg 3 Step 4 CALCULATE RIA-0631 count rate using the equation provided Calculates 1.735E4 cpm (1.73E4 to 1.74E4 cpm) S  U Comment: EVALUATOR NOTE: R (cpm) = 20 cpm + (0.1 gpm x 1440 min/day x 9.1E6 cpm)  (7 SCFM x 1.08E4) R = 20cpm + 1310.4E6  7.56E4 = 20 cpm + 173E2 = 1.735E4 cpm CRITICAL STEP   Proc. Step TASK ELEMENT 5 STANDARD Grade N/A Notify the CRS that RIA-0631 Count Rate estimation has been completed per AOP-24, Attachment 1. Operator notifies CRS of completion of AOP-24, Attachment 1. S  U Comment:     END OF TASK JPM RO ADMIN 1b PALISADES NUCLEAR PLANT Page 6 of 8 SEPTEMBER 2014 SIMULATOR OPERATOR INSTRUCTIONS 1. N/A JPM RO ADMIN 1b PALISADES NUCLEAR PLANT Page 7 of 8 SEPTEMBER 2014   CANDIDATE CUE SHEET #2   (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)   TODAY 06:00:00 Shift 2 has assumed the watch. SM - Mike Kane, CRS - John Mannikko, SE - Bracy Means. SM U/I - Paul Rhodes. NCOs - Aaron Miller and Scott Nichols. NPOs - Gerry Thompson, Joe Hoerle, Larry King, Ernest Wheeler, Keith Myrick, Joe Ford, and Chris McClure. Plant is in Mode 1, Reactor Power @ 100.0%, MWe gross @ 835. RAW = 1.06/Green/Low. Integrated Risk: LOW due to MO-3007, HPSI TO REACTOR COOLANT LOOP 1A TRAIN 1, work and Main Transformer scaffold erection. No items are on the LCO board. [Mannikko, John M, CRS] TODAY 09:04:45 Secondary NPO reports Condenser Off Gas @ 7.0 scfm. Updated PPC pg 540. [Nichols, Scott L, NCO-T] TODAY 09:32:37 Secondary area checks completed satisfactorily. Blewdown F-13A/B SEAL WATER SUPPLY STRAINERS and Instrument air compressor C-2C. [Wheeler IV, Ernest, Secondary - Safe S/D NPO] TODAY 10:00:23 Feedwater area checks completed satisfactorily. Blew down MV-VA50034A, CONTROL ROOM HVAC CAM TRAIN 'A' DRAIN VLV, MV-VA50034B, CONTROL HVAC CAM TRAIN 'B' DRAIN VALVE. Manually primed P-210A, DIESEL GENERATOR 1-1 K-6A FUEL OIL PRIMING, and P-210B, DIESEL GENERATOR 1-2 K-6B FUEL OIL PRIMING. T-939, DEMINERALIZED WATER STORAGE TANK @ 63%. [Ford, Joseph D, Feedwater NPO] TODAY 10:10:00 Authorized MT-10, "CORE MONITORING." No Tech Spec LCO Action entered during this procedure. WO# 52549760-01. [Mannikko, John M, CRS] TODAY 10:15:00 T/G operated IAW NERC/NPOA per SOP-8 section 4.4. [Nichols, Scott L, NCO-T]
Time Start: ________         Time Finish:     ________
JPM RO ADMIN 1b PALISADES NUCLEAR PLANT Page 8 of 8 SEPTEMBER 2014   CANDIDATE CUE SHEET   (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK) INITIAL CONDITIONS:   Plant was at full power. A Steam Generator Tube Leak is in progress. Crew has entered AOP- Action Level 2 is in effect. INITIATING CUES: During performance of AOP-the Control Room Supervisor directs you to estimate the count rate for RIA-0631, Condenser Off Gas Monitor that would require entry into Action Level Three, utilizing Attachment 1 of the procedure.
Performance Time:         ________ minutes Performance Rating:       SAT______       UNSAT ______
REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE     JPM: RO ADMIN 2 TITLE: PERFORM TSST MO-8 COMPARISON OF T POWER VS ACTUAL POWER   CANDIDATE:   EXAMINER:
Comments:
JPM RO ADMIN 2 PALISADES NUCLEAR PLANT Page 2 of 7 SEPTEMBER 2014  JOB PERFORMANCE MEASURE  DATA PAGE  Task:   Perform TSST MO-8 Section 5.2 Comparison of Delta-T Power vs Actual Power Alternate Path: N/A Facility JPM #: BANK K/A: 2.2.12 Importance: RO: 3.7 SRO: 4.1 K/A Statement: Knowledge of surveillance procedures. Task Standard: Delta-T power for PIP and SPI obtained and compared to actual power. Determine that acceptance criteria not met. Preferred Evaluation Location: Simulator __X___ In Plant ______ Preferred Evaluation Method: Perform __X___ Simulate ______
Examiner: _______________________________               Date:   ______________
Signature PALISADES NUCLEAR PLANT                   Page 2 of 8                   SEPTEMBER 2014
 
JPM RO ADMIN 1b EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:
AOP-24, Steam Generator Tube Leak ESOMS log printout that includes offgas flow reading of 7 scfm Also see Simulator Operator Instructions (last page of this document).
READ TO CANDIDATE DIRECTION TO CANDIDATE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
Plant was at full power.
A Steam Generator Tube Leak is in progress.
Crew has entered AOP-24, Steam Generator Tube Leak.
Action Level 2 is in effect.
INITIATING CUES:
During performance of AOP-24, Steam Generator Tube Leak, the Control Room Supervisor directs you to estimate the count rate for RIA-0631, Condenser Off Gas Monitor that would require entry into Action Level Three, utilizing Attachment 1 of the procedure.
PALISADES NUCLEAR PLANT                     Page 3 of 8                     SEPTEMBER 2014
 
JPM RO ADMIN 1b EVALUATOR CUE: Provide candidate with a working copy of AOP-24.
Proc. Step           TASK ELEMENT 1                                 STANDARD                 Grade Att 1pg 3   DETERMINE maximum Primary to             Candidate determines 0.1 gpm to be value Secondary Leakrate (gpm) based on        needed based on AOP-24, Attachment 2,     S U Step 1    current Action Level.                    page 6 and initiating cue.
Comment:
EVALUATOR CUE: If asked as CRS, inform candidate that the rate of change in the primary to secondary leakage is stable/unchanged.
CRITICAL STEP Proc. Step           TASK ELEMENT 2                                 STANDARD                 Grade Att 1 pg   OBTAIN Condenser Off Gas Monitor 3      flow rate (preferred) OR USE last Candidate obtains information.              S U known reading recorded in ESOMS Step 2    narrative log if taken within 24 hours.
Comment:
EVALUATOR CUE: When asked as NPO/CRS, provide ESOMS log sheet that includes Offgas flowrate = 7 SCFM (Cue Sheet #2)
CRITICAL STEP Proc. Step           TASK ELEMENT 3                                 STANDARD                 Grade NOTIFY Chemistry to obtain the following parameters from Nuclear Att 1 pg  IQ:
3      Bkg = RIA-0631 background reading,       Candidate obtains information.              S U Step 3    in cpm Rc = Total response factor RIA-0631, (cpm)
Comment:
EVALUATOR CUE: When asked as Chemistry, provide the following:
Background reading = 20 cpm, Total Response Factor = 9.1E6 cpm.
CRITICAL STEP PALISADES NUCLEAR PLANT                         Page 4 of 8                           SEPTEMBER 2014
 
JPM RO ADMIN 1b Proc. Step           TASK ELEMENT 4                             STANDARD                 Grade Att 1 pg CALCULATE RIA-0631 count rate         Calculates 1.735E4 cpm 3                                                                                      S U using the equation provided           (1.73E4 to 1.74E4 cpm)
Step 4 Comment:
EVALUATOR NOTE:
R (cpm) = 20 cpm + (0.1 gpm x 1440 min/day x 9.1E6 cpm)  (7 SCFM x 1.08E4)
R = 20cpm + 1310.4E6  7.56E4 = 20 cpm + 173E2 = 1.735E4 cpm CRITICAL STEP Proc. Step           TASK ELEMENT 5                             STANDARD                 Grade Notify the CRS that RIA-0631 Count Operator notifies CRS of completion of N/A    Rate estimation has been completed                                               S U AOP-24, Attachment 1.
per AOP-24, Attachment 1.
Comment:
END OF TASK PALISADES NUCLEAR PLANT                     Page 5 of 8                           SEPTEMBER 2014
 
JPM RO ADMIN 1b SIMULATOR OPERATOR INSTRUCTIONS
: 1. N/A PALISADES NUCLEAR PLANT         Page 6 of 8           SEPTEMBER 2014
 
JPM RO ADMIN 1b CANDIDATE CUE SHEET #2 (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)
TODAY             Shift 2 has assumed the watch.
06:00:00          SM - Mike Kane, CRS - John Mannikko, SE - Bracy Means.
SM U/I - Paul Rhodes.
NCOs - Aaron Miller and Scott Nichols.
NPOs - Gerry Thompson, Joe Hoerle, Larry King, Ernest Wheeler, Keith Myrick, Joe Ford, and Chris McClure.
Plant is in Mode 1, Reactor Power @ 100.0%, MWe gross @ 835.
RAW = 1.06/Green/Low. Integrated Risk: LOW due to MO-3007, HPSI TO REACTOR COOLANT LOOP 1A TRAIN 1, work and Main Transformer scaffold erection.
No items are on the LCO board. [Mannikko, John M, CRS]
TODAY             Secondary NPO reports Condenser Off Gas @ 7.0 scfm. Updated PPC pg 540.
09:04:45          [Nichols, Scott L, NCO-T]
TODAY             Secondary area checks completed satisfactorily. Blewdown F-13A/B SEAL 09:32:37          WATER SUPPLY STRAINERS and Instrument air compressor C-2C. [Wheeler IV, Ernest, Secondary - Safe S/D NPO]
TODAY             Feedwater area checks completed satisfactorily.
10:00:23          Blew down MV-VA50034A, CONTROL ROOM HVAC CAM TRAIN 'A' DRAIN VLV, MV-VA50034B, CONTROL HVAC CAM TRAIN 'B' DRAIN VALVE.
Manually primed P-210A, DIESEL GENERATOR 1-1 K-6A FUEL OIL PRIMING, and P-210B, DIESEL GENERATOR 1-2 K-6B FUEL OIL PRIMING.
T-939, DEMINERALIZED WATER STORAGE TANK @ 63%. [Ford, Joseph D, Feedwater NPO]
TODAY             Authorized MT-10, "CORE MONITORING." No Tech Spec LCO Action entered 10:10:00          during this procedure. WO# 52549760-01. [Mannikko, John M, CRS]
TODAY             T/G operated IAW NERC/NPOA per SOP-8 section 4.4. [Nichols, Scott L, NCO-T]
10:15:00 PALISADES NUCLEAR PLANT                   Page 7 of 8                         SEPTEMBER 2014
 
JPM RO ADMIN 1b CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
Plant was at full power.
A Steam Generator Tube Leak is in progress.
Crew has entered AOP-24, Steam Generator Tube Leak.
Action Level 2 is in effect.
INITIATING CUES:
During performance of AOP-24, Steam Generator Tube Leak, the Control Room Supervisor directs you to estimate the count rate for RIA-0631, Condenser Off Gas Monitor that would require entry into Action Level Three, utilizing Attachment 1 of the procedure.
PALISADES NUCLEAR PLANT                  Page 8 of 8                      SEPTEMBER 2014
 
REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO ADMIN 2 TITLE: PERFORM TSST MO-8 COMPARISON OF T POWER VS ACTUAL POWER CANDIDATE:
EXAMINER:
 
JPM RO ADMIN 2 JOB PERFORMANCE MEASURE DATA PAGE Task:               Perform TSST MO-8 Section 5.2 Comparison of Delta-T Power vs Actual Power Alternate Path:     N/A Facility JPM #:     BANK K/A:   2.2.12     Importance: RO:     3.7           SRO: 4.1 K/A Statement:     Knowledge of surveillance procedures.
Task Standard:     Delta-T power for PIP and SPI obtained and compared to actual power. Determine that acceptance criteria not met.
Preferred Evaluation Location:   Simulator     __X___     In Plant     ______
Preferred Evaluation Method:     Perform       __X___     Simulate     ______


==References:==
==References:==
MO-8, Palisades Plant Computer (PPC) - PDIL and PPDIL Check and Control Rod Out-Of-Sequence Alarm. Technical Data Book Figure 1.9   Validation Time: 10 minutes Time Critical: NO   Candidate:   Time Start: ________ Time Finish: ________ Performance Time: ________ minutes Performance Rating: SAT ______ UNSAT ______ Comments:     Examiner: _______________________________ Date: ______________ Signature JPM RO ADMIN 2  PALISADES NUCLEAR PLANT Page 3 of 7 SEPTEMBER 2014 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:   MO-8 Technical Data Book   READ TO CANDIDATE DIRECTION TO CANDIDATE: I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS: The monthly surveillance for PDIL and PPDIL Checks is due. The plant is operating at approximately 100% power. INITIATING CUES: You have been directed to perform Section 5.2, "Comparison of Delta-T Power VS Actual Power," of MO-8, - PDIL and PPDIL Check and Control Rod Out-Of-Sequence Alarm.
MO-8, Palisades Plant Computer (PPC) - PDIL and PPDIL Check and Control Rod Out-Of-Sequence Alarm.
JPM RO ADMIN 2  PALISADES NUCLEAR PLANT Page 4 of 7 SEPTEMBER 2014 Proc. Step TASK ELEMENT 1 STANDARD Grade Locate procedure. MO-8 located. S U Comment:   EVALUATOR CUE: Provide candidate with a working copy of MO-8 with sign-offs and placekeeping completed such that section 5.2 is ready to be performed. Proc. Step TASK ELEMENT 2 STANDARD Grade 5.2.1 T Power for PIP node Obtains POWER_PIP_DELTA_T value from PPC MO-8 Trend Screen and records S  U Comment: EVALUATOR NOTE: Reading should be 94.25+/-0.1% CRITICAL STEP     Proc. Step TASK ELEMENT 3 STANDARD Grade 5.2.1 ObT Power for SPI node Obtains POWER_SPI_DELTA_T value from PPC MO-8 Trend Screen and records S  U Comment: EVALUATOR NOTE: Reading should be 100.98+/-0.1% CRITICAL STEP JPM RO ADMIN 2  PALISADES NUCLEAR PLANT Page 5 of 7 SEPTEMBER 2014 Proc. Step TASK ELEMENT 4 STANDARD Grade 5.2.3 Record Actual Power from the Plant heat balance, HB_PWR_STEADY. Obtains HB_PWR_STEADY value from PPC MO-8 Trend Screen and records S  U Comment: EVALUATOR NOTE: Reading should be 99.98+/-0.1% CRITICAL STEP   Proc. Step TASK ELEMENT 5 STANDARD Grade 5.2.4  step 5.2.1 are NOT lower than Actual Power in Step 5.2.3 by greater than 4% for each node. Recognizes PIP Node T Power is NOT within 4% of actual power, circles in red and notifies CRS. Verifies SPI Node T Power within 4% of actual power (not critical) Does NOT sign step 5.2.4 since step criteria is not met. S  U Comment: EVALUATOR CUE: If candidate informs CRS that PIP node is not within limits, acknowledge same. CRITICAL STEP   END OF TASK JPM RO ADMIN 2  PALISADES NUCLEAR PLANT Page 6 of 7 SEPTEMBER 2014 SIMULATOR OPERATOR INSTRUCTIONS Reset to IC-17. Insert RX22B (PIDRX04) final value = 71. Check the PPC MO-8 Trend Screen to ensure POWER_PIP-DELTA T is more than 4% lower than HB_PWR_STEADY: [may also use Trend Group 53 (DJB) Trends Sets 2 and 4 for this info].
Technical Data Book Figure 1.9 Validation Time:   10 minutes         Time Critical: NO Candidate:
JPM RO ADMIN 2  PALISADES NUCLEAR PLANT Page 7 of 7 SEPTEMBER 2014 CANDIDATE CUE SHEET   (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK) INITIAL CONDITIONS: The monthly surveillance for PDIL and PPDIL Checks is due. The plant is operating at approximately 100% power. INITIATING CUES: You have been directed to perform Section 5.2, "Comparison of Delta-T Power VS Actual Power," of MO-8, - PDIL and PPDIL Check and Control Rod Out-Of-Sequence Alarm.
Time Start:   ________         Time Finish: ________
REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE     JPM: RO ADMIN 4 TITLE: OBTAIN METEOROLOGICAL DATA FOR EMERGENCY NOTIFICATION FORM   CANDIDATE:   EXAMINER:
Performance Time:         ________ minutes Performance Rating:       SAT   ______         UNSAT       ______
JPM RO ADMIN 4 PALISADES NUCLEAR PLANT Page 2 of 9 SEPTEMBER 2014  JOB PERFORMANCE MEASURE DATA PAGE   Task: Obtain Meteorological Data for Emergency Notification Form Alternate Path: N/A Facility JPM #: BANK K/A: 2.4.39         Importance: RO: 3.9   K/A Statement: Knowledge of RO responsibilities in emergency plan implementation Task Standard: EI-6.8, Attachment 2, completed with correct data obtained within 15 minutes per attached key   Preferred Evaluation Location: ANY __X___ Preferred Evaluation Method: Perform __X__ Simulate _____
Comments:
Examiner:     _______________________________             Date: ______________
Signature PALISADES NUCLEAR PLANT               Page 2 of 7                   SEPTEMBER 2014
 
JPM RO ADMIN 2 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:
MO-8 Technical Data Book READ TO CANDIDATE DIRECTION TO CANDIDATE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
The monthly surveillance for PDIL and PPDIL Checks is due. The plant is operating at approximately 100% power.
INITIATING CUES:
You have been directed to perform Section 5.2, "Comparison of Delta-T Power VS Actual Power," of MO-8, Palisades Plant Computer (PPC) - PDIL and PPDIL Check and Control Rod Out-Of-Sequence Alarm.
PALISADES NUCLEAR PLANT                     Page 3 of 7                     SEPTEMBER 2014
 
JPM RO ADMIN 2 Proc. Step           TASK ELEMENT 1                           STANDARD                 Grade Locate procedure.                     MO-8 located.                           S U Comment:
EVALUATOR CUE: Provide candidate with a working copy of MO-8 with sign-offs and placekeeping completed such that section 5.2 is ready to be performed.
Proc. Step           TASK ELEMENT 2                           STANDARD                 Grade Obtains POWER_PIP_DELTA_T value from 5.2.1   Obtain T Power for PIP node                                                   S U PPC MO-8 Trend Screen and records Comment:
EVALUATOR NOTE: Reading should be 94.25+/-0.1%
CRITICAL STEP Proc. Step           TASK ELEMENT 3                           STANDARD                 Grade Obtains POWER_SPI_DELTA_T value from 5.2.1   Obtain T Power for SPI node                                                   S U PPC MO-8 Trend Screen and records Comment:
EVALUATOR NOTE: Reading should be 100.98+/-0.1%
CRITICAL STEP PALISADES NUCLEAR PLANT                 Page 4 of 7                       SEPTEMBER 2014
 
JPM RO ADMIN 2 Proc. Step             TASK ELEMENT 4                                   STANDARD                     Grade Record Actual Power from the Plant heat   Obtains HB_PWR_STEADY value from PPC 5.2.3                                                                                                S U balance, HB_PWR_STEADY.                    MO-8 Trend Screen and records Comment:
EVALUATOR NOTE: Reading should be 99.98+/-0.1%
CRITICAL STEP Proc. Step             TASK ELEMENT 5                                   STANDARD                     Grade Recognizes PIP Node T Power is NOT within 4% of actual power, circles in red and notifies CRS.
VERIFY T Power values in step 5.2.1 are 5.2.4    NOT lower than Actual Power in Step 5.2.3  Verifies SPI Node T Power within 4% of actual   S U by greater than 4% for each node.          power (not critical)
Does NOT sign step 5.2.4 since step criteria is not met.
Comment:
EVALUATOR CUE: If candidate informs CRS that PIP node is not within limits, acknowledge same.
CRITICAL STEP END OF TASK PALISADES NUCLEAR PLANT                     Page 5 of 7                             SEPTEMBER 2014
 
JPM RO ADMIN 2 SIMULATOR OPERATOR INSTRUCTIONS Reset to IC-17.
Insert RX22B (PIDRX04) final value = 71.
Check the PPC MO-8 Trend Screen to ensure POWER_PIP-DELTA T is more than 4%
lower than HB_PWR_STEADY: [may also use Trend Group 53 (DJB) Trends Sets 2 and 4 for this info].
PALISADES NUCLEAR PLANT               Page 6 of 7             SEPTEMBER 2014
 
JPM RO ADMIN 2 CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
The monthly surveillance for PDIL and PPDIL Checks is due. The plant is operating at approximately 100% power.
INITIATING CUES:
You have been directed to perform Section 5.2, "Comparison of Delta-T Power VS Actual Power," of MO-8, Palisades Plant Computer (PPC) - PDIL and PPDIL Check and Control Rod Out-Of-Sequence Alarm.
PALISADES NUCLEAR PLANT              Page 7 of 7                    SEPTEMBER 2014
 
REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO ADMIN 4 TITLE: OBTAIN METEOROLOGICAL DATA FOR EMERGENCY NOTIFICATION FORM CANDIDATE:
EXAMINER:
 
JPM RO ADMIN 4 JOB PERFORMANCE MEASURE DATA PAGE Task:   Obtain Meteorological Data for Emergency Notification Form Alternate Path: N/A Facility JPM #: BANK K/A: 2.4.39     Importance:       RO: 3.9 K/A Statement: Knowledge of RO responsibilities in emergency plan implementation Task Standard: EI-6.8, Attachment 2, completed with correct data obtained within 15 minutes per attached key Preferred Evaluation Location: ANY         __X___
Preferred Evaluation Method:       Perform     __X__   Simulate   _____


==References:==
==References:==
EI-3.0, Communications and Notifications EI-6.0, Offsite Dose Calculation and Recommendations for Protective Actions EI-6.8, Backup and Supplemental Meteorology   Validation Time: 10 minutes Time Critical: YES - 12 Minutes   Candidate:   Time Start: ________ Time Finish: ________ Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______ Comments:     Examiner: _______________________________ Date: ______________ Signature JPM RO ADMIN 4 PALISADES NUCLEAR PLANT Page 3 of 9 SEPTEMBER 2014 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed: EI-6.8 Also see Simulator Operator Instructions (last page of this document). READ TO CANDIDATE DIRECTION TO CANDIDATE: I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:   The Shift Manager, acting as the Site Emergency Director, has declared an Alert condition. A thunderstorm is in progress and the onsite meteorological data system is out of service due to a lightning strike. The Shift Manager has printed out data from the WSI Weather System per EI-6.8, up and Supplemental Meteorology, steps 5.1.1 through 5.1.6. Today is May 24th, the current time is 0810. INITIATING CUES: The Shift Manager has directed you to complete EI-6.8 step 5.1.10 (i.e. fill out Attachment 2 of EI-6.8) by using the WSI data printout and steps 5.1.7 through 5.1.9. The Shift Manager requires this data to complete EI-3, Attachment 1, Palisades Event Notification Form. THIS JPM IS TIME CRITICAL JPM RO ADMIN 4 PALISADES NUCLEAR PLANT Page 4 of 9 SEPTEMBER 2014 EVALUATOR CUE: Provide candidate with a Working Copy of EI-p and and second cue sheet (WSI data printout). Proc. Step TASK ELEMENT 1 STANDARD Grade 5.1.10 Obtain meteorological data from the WSI which means wind direction is from 150 degrees  On EI-6.8 Att. 2 data recorded as follows: Wind Direction = 150 S  U Comment: EVALUATOR NOTE: Applicant uses steps 5.1.7 through 5.1.9 to identify data from the WSI printout and then records data using step 5.1.10. CRITICAL STEP   Proc. Step TASK ELEMENT 2 STANDARD Grade 5.1.10 Obtain meteorological data from the WSI which means wind speed is  11 mph  On EI-6.8 Att. 2 data recorded as follows: Wind Speed = 11 mph S  U Comment:   CRITICAL STEP   Proc. Step TASK ELEMENT 3 STANDARD Grade 5.1.10 Obtain meteorological data from the WSI Benton Harbor  On EI-6.8 Att. 2 data recorded as follows: Stability Class = D S  U Comment:   CRITICAL STEP JPM RO ADMIN 4 PALISADES NUCLEAR PLANT Page 5 of 9 SEPTEMBER 2014 Proc. Step TASK ELEMENT 4 STANDARD Grade n/a EI-6.8, Attachment 2 completed: Date:,  Time:,  Completed By: On EI-6.8 Att. 2 data recorded as follows: Date:  *Time: Current time -within 12 minutes from start of JPM Completed By: S  U Comment:   CRITICAL STEP
EI-3.0, Communications and Notifications EI-6.0, Offsite Dose Calculation and Recommendations for Protective Actions EI-6.8, Backup and Supplemental Meteorology Validation Time:     10 minutes         Time Critical: YES - 12 Minutes Candidate:
* Time is only portion of critical step   Proc. Step TASK ELEMENT 5 STANDARD Grade n/a Notify the CRS that EI-6.8 Attachment 2 completed. Operator notifies CRS of completion of EI-6.8, Attachment 2. S U Comment:     END OF TASK JPM RO ADMIN 4 PALISADES NUCLEAR PLANT Page 6 of 9 SEPTEMBER 2014   SIMULATOR OPERATOR INSTRUCTIONS 1. N/A Proc No EI-6.8 Attachment 2 Revision 6 Page 1 of 1 PALISADES NUCLEAR PLANT Page 7 of 9 SEPTEMBER 2014  BACKUP AND SUPPLEMENTAL METEOROLOGY       WORKSHEET   ANSWER KEY       ANSWER KEY       ANSWER KEY       ANSWER KEY     ANSWER KEY     1. Wind Direction = __150____ Degrees From   2. Wind Speed = ___11_____ mph   3. Stability Class = D       Date: __TODAY_____ Time: __NOW___ Completed By: __JOE OPERATOR_______   ANSWER KEY       ANSWER KEY       ANSWER KEY       ANSWER KEY     ANSWER KEY JPM RO ADMIN 4  PALISADES NUCLEAR PLANT Page 8 of 9 SEPTEMBER 2014   CANDIDATE CUE SHEET   (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)   MOSPAL 00 DATE/GMT 24/18 25/00 25/06 25/12 25/18 26/00 26/06 26/12 DATE/EST 24/13 24/19 25/01 25/07 25/13 25/19 26/01 26/07 WIND-MP 1111 2109 3303 0910 0711 0813 0811 0610 CLDS-1 10 10 10 10 10 10 8 2 HGT-FT 5200 5450 4750 3750 4650 5500 5600 4500 PAS C C C C C D D D   +USINFO BEH, MKG YWZQ OBSERVATIONS FOR 8AM(13Z) 24-MAY-11               STATION NAME WIND PS BENTON HARBOR, MI 1511 D MUSKEGON, MI   1011 D JPM RO ADMIN 4  PALISADES NUCLEAR PLANT Page 9 of 9 SEPTEMBER 2014   CANDIDATE CUE SHEET   (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)   INITIAL CONDITIONS:   The Shift Manager, acting as the Site Emergency Director, has declared an Alert condition. A thunderstorm is in progress and the onsite meteorological data system is out of service due to a lightning strike. The Shift Manager has printed out data from the WSI Weather System per EI-6.8,   Today is May 24th, the current time is 0810. INITIATING CUES: The Shift Manager has directed you to complete EI-6.8 step 5.1.10 (i.e. fill out Attachment 2 of EI-6.8) by using the WSI data printout and steps 5.1.7 through 5.1.9. The Shift Manager requires this data to complete EI-3, Attachment 1, Palisades Event Notification Form. THIS JPM IS TIME CRITICAL NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE     JPM: SRO ADMIN 1a TITLE: DETERMINE AVERAGE QUALIFIED CET TEMPERATURE AND SUB-COOLING VALUE     CANDIDATE:   EXAMINER:
Time Start: ________         Time Finish:       ________
JPM No. SRO ADMIN 1a PALISADES NUCLEAR PLANT Page 2 of 9 September 2014  JOB PERFORMANCE MEASURE DATA PAGE   Task: Determine Primary Coolant System sub-cooled margin using all available methods Alternate Path: N/A Facility JPM #: PL-OPS-EOP-024J K/A: 2.1.7   Importance: RO: 4.4 SRO: 4.7 K/A Statement: Ability to evaluate plant performance and make operational judgments based on operating characteristics, reactor behavior, and instrument interpretation. Task Standard: Average CET Temperature correctly calculated and sub-cooling value determined. Preferred Evaluation Location: Simulator _X_ In Plant ______ Preferred Evaluation Method: Perform _X_ Simulate ______
Performance Time:         ________ minutes Performance Rating:       SAT______         UNSAT ______
Comments:
Examiner: _______________________________                 Date:   ______________
Signature PALISADES NUCLEAR PLANT                   Page 2 of 9                   SEPTEMBER 2014
 
JPM RO ADMIN 4 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:
EI-6.8 Also see Simulator Operator Instructions (last page of this document).
READ TO CANDIDATE DIRECTION TO CANDIDATE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
The Shift Manager, acting as the Site Emergency Director, has declared an Alert condition.
A thunderstorm is in progress and the onsite meteorological data system is out of service due to a lightning strike.
The Shift Manager has printed out data from the WSI Weather System per EI-6.8, Backup and Supplemental Meteorology, steps 5.1.1 through 5.1.6.
Today is May 24th, the current time is 0810.
INITIATING CUES:
The Shift Manager has directed you to complete EI-6.8 step 5.1.10 (i.e. fill out of EI-6.8) by using the WSI data printout and steps 5.1.7 through 5.1.9.
The Shift Manager requires this data to complete EI-3, Attachment 1, Palisades Event Notification Form.
THIS JPM IS TIME CRITICAL PALISADES NUCLEAR PLANT                     Page 3 of 9                     SEPTEMBER 2014
 
JPM RO ADMIN 4 EVALUATOR CUE: Provide candidate with a Working Copy of EI-6.8, Backup and Supplemental Meteorology and second cue sheet (WSI data printout).
Proc. Step             TASK ELEMENT 1                                       STANDARD                   Grade Obtain meteorological data from the WSI Printout: Wind for hourly observation in      On EI-6.8 Att. 2 data recorded as follows:
5.1.10    Benton Harbor is 1511 which means                                                            S U wind direction is from 150 degrees              Wind Direction = 150 Comment:
EVALUATOR NOTE: Applicant uses steps 5.1.7 through 5.1.9 to identify data from the WSI printout and then records data using step 5.1.10.
CRITICAL STEP Proc. Step             TASK ELEMENT 2                                       STANDARD                   Grade Obtain meteorological data from the WSI Printout: Wind for hourly observation in      On EI-6.8 Att. 2 data recorded as follows:
5.1.10    Benton Harbor is 1511 which means                                                            S U wind speed is 11 mph                            Wind Speed = 11 mph Comment:
CRITICAL STEP Proc. Step             TASK ELEMENT 3                                       STANDARD                   Grade Obtain meteorological data from the WSI Printout: PS for hourly observation in        On EI-6.8 Att. 2 data recorded as follows:
5.1.10                                                                                                  S U Benton Harbor is D                            Stability Class = D Comment:
CRITICAL STEP PALISADES NUCLEAR PLANT                         Page 4 of 9                             SEPTEMBER 2014
 
JPM RO ADMIN 4 Proc. Step             TASK ELEMENT 4                                     STANDARD                     Grade On EI-6.8 Att. 2 data recorded as follows:
Date: Todays date EI-6.8, Attachment 2 completed:
n/a                                                  *Time: Current time -within 12 minutes from     S U Date:, Time:, Completed By:
start of JPM Completed By: Operators name Comment:
CRITICAL STEP
* Time is only portion of critical step Proc. Step             TASK ELEMENT 5                                     STANDARD                     Grade Notify the CRS that EI-6.8 Attachment 2     Operator notifies CRS of completion of EI-6.8, n/a    completed.                                  Attachment 2.                                   S U Comment:
END OF TASK PALISADES NUCLEAR PLANT                       Page 5 of 9                             SEPTEMBER 2014
 
JPM RO ADMIN 4 SIMULATOR OPERATOR INSTRUCTIONS
: 1. N/A PALISADES NUCLEAR PLANT          Page 6 of 9          SEPTEMBER 2014
 
Proc No EI-6.8 Attachment 2 Revision 6 Page 1 of 1 BACKUP AND SUPPLEMENTAL METEOROLOGY WORKSHEET ANSWER KEY             ANSWER KEY       ANSWER KEY ANSWER KEY       ANSWER KEY
: 1. Wind Direction = __150____ Degrees From
: 2. Wind Speed = ___11_____ mph
: 3. Stability Class = D Date: __TODAY_____ Time: __NOW___ Completed By: __JOE OPERATOR_______
ANSWER KEY             ANSWER KEY       ANSWER KEY ANSWER KEY       ANSWER KEY PALISADES NUCLEAR PLANT               Page 7 of 9           SEPTEMBER 2014
 
JPM RO ADMIN 4 CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)
MOSPAL 00 DATE/GMT       24/18     25/00     25/06       25/12 25/18 26/00     26/06   26/12 DATE/EST     24/13     24/19     25/01       25/07 25/13 25/19     26/01   26/07 WIND-MP       1111       2109     3303         0910 0711 0813     0811     0610 CLDS-1         10         10       10           10   10   10         8       2 HGT-FT       5200       5450     4750         3750 4650 5500     5600     4500 PAS         C         C         C           C     C     D         D       D
+USINFO BEH, MKG YWZQ OBSERVATIONS FOR 8AM(13Z)       24-MAY-11 STATION NAME     WIND   PS BENTON HARBOR, MI       1511   D MUSKEGON, MI           1011   D PALISADES NUCLEAR PLANT               Page 8 of 9               SEPTEMBER 2014
 
JPM RO ADMIN 4 CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
The Shift Manager, acting as the Site Emergency Director, has declared an Alert condition.
A thunderstorm is in progress and the onsite meteorological data system is out of service due to a lightning strike.
The Shift Manager has printed out data from the WSI Weather System per EI-6.8, Backup and Supplemental Meteorology.
Today is May 24th, the current time is 0810.
INITIATING CUES:
The Shift Manager has directed you to complete EI-6.8 step 5.1.10 (i.e. fill out of EI-6.8) by using the WSI data printout and steps 5.1.7 through 5.1.9.
The Shift Manager requires this data to complete EI-3, Attachment 1, Palisades Event Notification Form.
THIS JPM IS TIME CRITICAL PALISADES NUCLEAR PLANT                Page 9 of 9                      SEPTEMBER 2014
 
NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: SRO ADMIN 1a TITLE: DETERMINE AVERAGE QUALIFIED CET TEMPERATURE AND SUB-COOLING VALUE CANDIDATE:
EXAMINER:
 
JPM No. SRO ADMIN 1a JOB PERFORMANCE MEASURE DATA PAGE Task:   Determine Primary Coolant System sub-cooled margin using all available methods Alternate Path: N/A Facility JPM #: PL-OPS-EOP-024J K/A:     2.1.7           Importance:       RO:4.4     SRO:     4.7 K/A Statement: Ability to evaluate plant performance and make operational judgments based on operating characteristics, reactor behavior, and instrument interpretation.
Task Standard: Average CET Temperature correctly calculated and sub-cooling value determined.
Preferred Evaluation Location: Simulator         _X_   In Plant     ______
Preferred Evaluation Method:       Perform     _X_   Simulate     ______


==References:==
==References:==
SOP-34     EOP Supplement 1 Validation Time: 15 minutes Time Critical: NO   Candidate:   Time Start: ________ Time Finish: ________ Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______ Comments:     Examiner: _______________________________ Date: ______________ Signature JPM No. SRO ADMIN 1a PALISADES NUCLEAR PLANT Page 3 of 9 September 2014 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:   SOP-34, revision 22 EOP Supplement 1, revision 5 Also see Simulator Operator Instructions (last page of this document). READ TO CANDIDATE DIRECTION TO CANDIDATE: I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:   A loss of off-site power has resulted in a Reactor trip from 100% power Buses 1C and 1D are energized from their D/Gs EOP-8.0 is in use The PPC is inoperable INITIATING CUES:   The CRS has directed you to determine PCS sub-cooling value in accordance with SOP-34, Attachment 5, using all available Qualified CET readings.
SOP-34 EOP Supplement 1 Validation Time:     15 minutes         Time Critical: NO Candidate:
JPM No. SRO ADMIN 1a PALISADES NUCLEAR PLANT Page 4 of 9 September 2014 EVALUATOR CUE: Provide candidate with a working copy of SOP-34 Attachment 5. Proc. Step TASK ELEMENT 1 STANDARD Grade 1.a Obtain at least 2 Qualified CET readings per core quadrant from the CET recorders. Operator records qualified CET temperatures as read from the CET recorders (TR-0101A1. TR-0101A2, TR-0101B1, TR-0101B2) on Panel C-11A and the time. At least two (2) qualified CET readings per quadrant required. The readings are recorded in section 2. Per CRS direction in the initiating cue, all 16 readings will be taken. S  U Comment: Evaluator Note: Verify data taken by Operator CRITICAL STEP   Proc. Step TASK ELEMENT 2 STANDARD Grade 1.b CALCULATE the average of the temperature readings used. Operator sums the CET readings (recorded in section 2), then divides the sum by the number of CETs used (8 minimum) to obtain the average CET temperature (recorded in section 2). S  U Comment: Evaluator Note: Verify calculation by Operator with attached answer key. CRITICAL STEP   Proc. Step TASK ELEMENT 3 STANDARD Grade 1.c If any individual temperature readings is greater that 15°F higher or lower from the average, then: Do not utilize that individual temperature reading. Return to Step 1a. CET # 23 (3rd quadrant) will be approximately 19°F higher than the average. The candidate will recalculate excluding this reading. S  U Comment:   CRITICAL STEP JPM No. SRO ADMIN 1a PALISADES NUCLEAR PLANT Page 5 of 9 September 2014 Proc. Step TASK ELEMENT 4 STANDARD Grade 1.d REFER TO EOP Supplement 1, Pressure Temperature Limit Curves, to determine sub-cooling value utilizing the average temperature calculated in step 1.b. Operator performs the following: ___ Obtains PCS Pressure reading from PI-0104 ___ Determines subcooling using one of the following methods: Use EOP Supplement 1 OR Steam Tables to determine saturation temperature for 1750 psia (617F) and subtract average CET calculated (538F) to obtain 79F (+/- 1F) Use EOP Supplement 1 OR Steam Tables to the 25F subcooled value for 1750 psia (617-25 = 592F) and then subtract average CET calculated (538F) to obtain 79F (+/- 1F) S  U Comment:   CRITICAL STEP   Proc. Step TASK ELEMENT 5 STANDARD Grade n/a Operator informs CRS of Average Qualified CET Temperature and sub-cooling value. CRS informed that subcooling value is approximately 80°F. S U Comment:   END OF TASK JPM No. SRO ADMIN 1a PALISADES NUCLEAR PLANT Page 6 of 9 September 2014 SIMULATOR OPERATOR INSTRUCTIONS   Reset to IC-17. Enter ED01 (on PIDED03), reactor should auto trip Perform actions of EOP-1.0 through section 5.0 Restore power to Transformer 13, clear D/G trouble alarms and take manual control of ADVs to stabilize temperature Have SSG turn off PPC monitors Insert overrides for Qualified CET values per attached answer key Insert override for PI-0104 to read 1750 psia. When natural circulation has developed, freeze Simulator Verify qualified CETs data matches answer key Place calculator at operator station Restore power to Transformer 16 Enter Overrides for Qualified CET readings on C-11A (refer to answer key)
Time Start: ________         Time Finish:       ________
JPM No. SRO ADMIN 1a PALISADES NUCLEAR PLANT Page 7 of 9 September 2014 AAANNNSSSWWWEEERRR  KKKEEEYYY  AAANNNSSSWWWEEERRR  KKKEEEYYY  AAANNNSSSWWWEEERRR  KKKEEEYYY  Answer Key QUADRANT QUALIFIED CET # TIME now TIME now     1 2 536 536     9 547 547     10 541 541     19 535 535     2 5 539 539     11 534 534     16 532 532     21 532 532     3 23 559 ----     25 537 537     31 534 534     35 534 534     4 27 537 537     30 547 547     33 540 540     36 548 548     TOTAL 8632 8073     AVERAGE 539.5 538.2 JPM No. SRO ADMIN 1a PALISADES NUCLEAR PLANT Page 8 of 9 September 2014   ~ 80°F JPM No. SRO ADMIN 1a PALISADES NUCLEAR PLANT Page 9 of 9 September 2014 CANDIDATE CUE SHEET   (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)   INITIAL CONDITIONS:   A loss of off-site power has resulted in a Reactor trip from 100% power Buses 1C and 1D are energized from their D/Gs EOP-8.0 is in use The PPC is inoperable INITIATING CUES:   The CRS has directed you to determine PCS sub-cooling value in accordance with SOP-34, Attachment 5, using all available Qualified CET readings.
Performance Time:       ________ minutes Performance Rating:     SAT______         UNSAT ______
NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE     JPM: SRO ADMIN 1b TITLE: MONITOR PCS HEATUP/COOLDOWN WITH THE PPC     CANDIDATE:   EXAMINER:
Comments:
JPM SRO ADMIN 1b PALISADES NUCLEAR PLANT Page 2 of 8 SEPTEMBER 2014  JOB PERFORMANCE MEASURE DATA PAGE   Task: Operate the Palisades Plant Computer System Alternate Path: N/A Facility JPM #: PPC-JPM-02 K/A: 2.1.19   Importance: RO: 3.9   SRO: 3.8 K/A Statement: Ability to use plant computers to evaluate system or component status. Task Standard: PPC setup to monitor the PCS heatup rate and candidate determines that LCO action statement 3.4.3.A needs to be entered due to heatup rate being above the limit. Preferred Evaluation Location: Simulator __X__ In Plant _____ Preferred Evaluation Method: Perform __X__ Simulate _____
Examiner: _______________________________                 Date:   ______________
Signature PALISADES NUCLEAR PLANT                   Page 2 of 9                     September 2014
 
JPM No. SRO ADMIN 1a EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:
SOP-34, revision 22 EOP Supplement 1, revision 5 Also see Simulator Operator Instructions (last page of this document).
READ TO CANDIDATE DIRECTION TO CANDIDATE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
A loss of off-site power has resulted in a Reactor trip from 100% power Buses 1C and 1D are energized from their D/Gs EOP-8.0 is in use The PPC is inoperable INITIATING CUES:
The CRS has directed you to determine PCS sub-cooling value in accordance with SOP-34, Attachment 5, using all available Qualified CET readings.
PALISADES NUCLEAR PLANT                     Page 3 of 9                         September 2014
 
JPM No. SRO ADMIN 1a EVALUATOR CUE: Provide candidate with a working copy of SOP-34 Attachment 5.
Proc. Step               TASK ELEMENT 1                                           STANDARD                           Grade Operator records qualified CET temperatures as read from the CET recorders (TR-0101A1. TR-0101A2, TR-0101B1, TR-0101B2) on Panel C-11A Obtain at least 2 Qualified CET readings per 1.a    core quadrant from the CET recorders.
and the time. At least two (2) qualified CET readings   S U per quadrant required. The readings are recorded in section 2. Per CRS direction in the initiating cue, all 16 readings will be taken.
Comment:
Evaluator Note: Verify data taken by Operator CRITICAL STEP Proc. Step               TASK ELEMENT 2                                           STANDARD                           Grade Operator sums the CET readings (recorded in CALCULATE the average of the temperature            section 2), then divides the sum by the number of 1.b    readings used.                                      CETs used (8 minimum) to obtain the average CET S U temperature (recorded in section 2).
Comment:
Evaluator Note: Verify calculation by Operator with attached answer key.
CRITICAL STEP Proc. Step               TASK ELEMENT 3                                           STANDARD                           Grade If any individual temperature readings is greater that 15°F higher or lower from the                     rd average, then:                                     CET # 23 (3 quadrant) will be approximately 19°F 1.c              Do not utilize that individual          higher than the average. The candidate will             S U temperature reading.                    recalculate excluding this reading.
Return to Step 1a.
Comment:
CRITICAL STEP PALISADES NUCLEAR PLANT                             Page 4 of 9                                     September 2014
 
JPM No. SRO ADMIN 1a Proc. Step               TASK ELEMENT 4                                         STANDARD                         Grade Operator performs the following:
___ Obtains PCS Pressure reading from PI-0104
___ Determines subcooling using one of the following methods:
Use EOP Supplement 1 OR Steam REFER TO EOP Supplement 1, Pressure                            Tables to determine saturation Temperature Limit Curves, to determine sub-1.d    cooling value utilizing the average temperature temperature for 1750 psia (617F) and   S U subtract average CET calculated calculated in step 1.b.
(538F) to obtain 79F (+/- 1F)
Use EOP Supplement 1 OR Steam Tables to the 25F subcooled value for 1750 psia (617-25 = 592F) and then subtract average CET calculated (538F) to obtain 79F (+/- 1F)
Comment:
CRITICAL STEP Proc. Step               TASK ELEMENT 5                                         STANDARD                         Grade Operator informs CRS of Average Qualified         CRS informed that subcooling value is approximately n/a    CET Temperature and sub-cooling value.           80°F.
S U Comment:
END OF TASK PALISADES NUCLEAR PLANT                           Page 5 of 9                                   September 2014
 
JPM No. SRO ADMIN 1a SIMULATOR OPERATOR INSTRUCTIONS Reset to IC-17.
Enter ED01 (on PIDED03), reactor should auto trip Perform actions of EOP-1.0 through section 5.0 Restore power to Transformer 13, clear D/G trouble alarms and take manual control of ADVs to stabilize temperature Have SSG turn off PPC monitors Insert overrides for Qualified CET values per attached answer key Insert override for PI-0104 to read 1750 psia.
When natural circulation has developed, freeze Simulator Verify qualified CETs data matches answer key Place calculator at operator station Restore power to Transformer 16 Enter Overrides for Qualified CET readings on C-11A (refer to answer key)
PALISADES NUCLEAR PLANT                 Page 6 of 9                     September 2014
 
JPM No. SRO ADMIN 1a Answer Key QUALIFIED  TIME    TIME QUADRANT CET #     now     now 1           2       536     536 9       547     547 ANSWER KEY 2
10 19 5
11 541 535 539 534 541 535 539 534 16       532     532 ANSWER KEY 3
21 23 25 31 532 559 537 534 532
                                  ----
537 534 ANSWER KEY 35       534     534 27       537     537 30       547     547 4
33       540     540 36       548     548 TOTAL           8632     8073 AVERAGE         539.5   538.2 PALISADES NUCLEAR PLANT         Page 7 of 9           September 2014
 
JPM No. SRO ADMIN 1a
                                                      ~ 80°F PALISADES NUCLEAR PLANT Page 8 of 9     September 2014
 
JPM No. SRO ADMIN 1a CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
A loss of off-site power has resulted in a Reactor trip from 100% power Buses 1C and 1D are energized from their D/Gs EOP-8.0 is in use The PPC is inoperable INITIATING CUES:
The CRS has directed you to determine PCS sub-cooling value in accordance with SOP-34, Attachment 5, using all available Qualified CET readings.
PALISADES NUCLEAR PLANT                  Page 9 of 9                      September 2014
 
NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: SRO ADMIN 1b TITLE: MONITOR PCS HEATUP/COOLDOWN WITH THE PPC CANDIDATE:
EXAMINER:
 
JPM SRO ADMIN 1b JOB PERFORMANCE MEASURE DATA PAGE Task:   Operate the Palisades Plant Computer System Alternate Path: N/A Facility JPM #: PPC-JPM-02 K/A: 2.1.19         Importance:       RO: 3.9       SRO: 3.8 K/A Statement: Ability to use plant computers to evaluate system or component status.
Task Standard: PPC setup to monitor the PCS heatup rate and candidate determines that LCO action statement 3.4.3.A needs to be entered due to heatup rate being above the limit.
Preferred Evaluation Location: Simulator         __X__   In Plant     _____
Preferred Evaluation Method:       Perform     __X__   Simulate     _____


==References:==
==References:==
GOP-2, MODE 5 To MODE 3     PO-2, PCS Heatup/Cooldown Validation Time: 20 minutes Time Critical: NO   Candidate:   Time Start: ________ Time Finish: ________ Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______ Comments:     Examiner: _______________________________ Date: ______________ Signature JPM SRO ADMIN 1b PALISADES NUCLEAR PLANT Page 3 of 8 SEPTEMBER 2014 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:   PO-2, PCS Heatup/Cooldown Operations PPC Cyclic Printout Pages 391, 392, 393 for at least one-hour showing a heatup rate that exceeds the 40F/hr Tech Spec limit (see Simulator setup page). Separate each set of cycle printouts and staple. Also see Simulator Operator Instructions (later page of this document). READ TO CANDIDATE DIRECTION TO CANDIDATE: I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:   A Plant refueling has just been completed Shutdown Cooling is NOT in service PCS temperature is approximately 190°F GCL-2, MODE 5 to MODE 3   525°F Checklist is in progress Two PCPs are in service Technical Specification Surveillance Procedure PO-2, PCS Heatup/Cooldown Operations, has just been authorized by the CRS No equipment is out of service, all systems are OPERABLE   INITIATING CUES: The Control Room Supervisor directs you to monitor and record PCS parameters during the heatup using the PPC per PO-2, step 5.1.
GOP-2, MODE 5 To MODE 3 525°F PO-2, PCS Heatup/Cooldown Operations Validation Time:     20 minutes         Time Critical: NO Candidate:
JPM SRO ADMIN 1b PALISADES NUCLEAR PLANT Page 4 of 8 SEPTEMBER 2014 EVALUATOR CUE: Provide candidate a working copy of PO-2. Proc. Step TASK ELEMENT 1 STANDARD Grade 5.1.1b 5.1.1c SELECT screen from the main menu SELECT any of the following, as applicable, to monitor PCS heatup/cooldown rate:    Candidate performs one of the following: a. Main menu screen SELECTED, then  from main menu screen. b. SELECTED S  U Comment: EVALUATOR NOTE: Operator may go straight to PPC page 361 (task element 3). Proc. Step TASK ELEMENT 2 STANDARD Grade 5.1.1.d.1 START 15 minute automatic reports as follows: 1. DEPRESS . S  U Comment:   CRITICAL STEP Proc. Step TASK ELEMENT 3 STANDARD Grade 5.1.1.d.2 START 15 minute automatic reports as follows: 2. SELECT response S  U Comment:   CRITICAL STEP JPM SRO ADMIN 1b PALISADES NUCLEAR PLANT Page 5 of 8 SEPTEMBER 2014 Proc. Step TASK ELEMENT 4 STANDARD Grade 5.1.1.d.3 START 15 minute automatic reports as follows: 3. SELECT the HCR Reports page from any of the selected heatup/cooldown pages (361, 362, 372, AND 373). SELECTED S  U Comment:   CRITICAL STEP   Proc. Step TASK ELEMENT 5 STANDARD Grade 5.1.1.d.4 START 15 minute automatic reports as follows: 4. WHEN the HCR Report page is displayed, SELECT the output device at the bottom right corner of the page by performing one of the following depending on the desired print location:  a. TYPE a one (1) AND DEPRESS the "UPDATE" Hardkey to start the reports to print to the control room. b. TYPE a two (2) AND DEPRESS the "UPDATE" Hardkey to start the reports to print to the TSC. Candidate determines that this step is N/A since "PRINTER_1" is already selected in bottom right-hand corner. Candidate may perform the following:  One (1) is TYPED AND DEPRESSED. S  U Comment:  NOTE: The Heatup/Cooldown print out is on a 15 minute timer that is always running. When the printout is enabled, the next print timeout could be anywhere from 1 second to 15 minutes later. EVALUATOR: When candidate has completed this step, hand them the printouts of PPC pages 391, 392, and 393 for the last hour. Tell the candidate that the SE did not review the sheets for the last hour and you have just relieved him/her. Ensure the candidate understands that one hour has elapsed. CRITICAL STEP JPM SRO ADMIN 1b PALISADES NUCLEAR PLANT Page 6 of 8 SEPTEMBER 2014 Proc. Step TASK ELEMENT 6 STANDARD Grade 5.1.1.d.5 5. DETERMINE PCS parameters are within allowable limits at least once every 15 minutes during the heatup/cooldown AND INITIAL the PPC Data Sheet. Refer to Step 5.2 and Step 5.3. Candidate determines that step 5.2 is N/A. Candidate refers to step 5.3 and compares heatup limits in step 6.0 to the heatup rates determined on the PPC printout. Candidate determines that the heatup rate limit of 40°F hour has been exceeded S  U Comment:   CRITICAL STEP (only critical part is determining heatup rate limit has been exceeded.)   Proc. Step TASK ELEMENT 7 STANDARD Grade 5.3.1 IF any PCS parameter exceeds its limit or the heatup/cooldown rate exceeds the maximum allowable rate, THEN PERFORM the following ... Candidate determines that LCO 3.4.3 condition A needs to be entered because the heatup rate limit has been exceeded. S  U Comment:  EVALUATOR: When candidate determines that LCO 3.4.3 condition A needs to be entered, end the JPM. CRITICAL STEP  END OF TASK JPM SRO ADMIN 1b PALISADES NUCLEAR PLANT Page 7 of 8 SEPTEMBER 2014 SIMULATOR OPERATOR INSTRUCTIONS   IC-3, Ready to come off S/D Cooling. Preparation of PPC Pages for this JPM: Turn on PPC Cyclic Printout Remove SDC from service per SOP-3 Allow simulator to run for at least one-hour When at least one-hour of Cyclic Printout pages have finished printing, then preparation is complete Prior to adminstering JPM, remove SDC from service per SOP-3. ENSURE PPC CYCLIC PRINTOUT IS TURNED OFF AFTER EACH JPM.
Time Start: ________         Time Finish:       ________
JPM SRO ADMIN 1b PALISADES NUCLEAR PLANT Page 8 of 8 SEPTEMBER 2014 CANDIDATE CUE SHEET   (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)   INITIAL CONDITIONS:   A Plant refueling has just been completed Shutdown Cooling is NOT in service PCS temperature is approximately 190°F GCL-2, MODE 5 to MODE 3   525°F Checklist is in progress Two PCPs are in service Technical Specification Surveillance Procedure PO-2, PCS Heatup/Cooldown Operations, has just been authorized by the CRS No equipment is out of service, all systems are OPERABLE   INITIATING CUES: The Control Room Supervisor directs you to monitor and record PCS parameters during the heatup using the PPC per PO-2, step 5.1.
Performance Time:       ________ minutes Performance Rating:     SAT______         UNSAT ______
NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE     JPM: SRO ADMIN 2 TITLE: REVIEW AND APPROVE A COMPLETED TECHNICAL SPECIFICATION SURVEILLANCE TEST       CANDIDATE:   EXAMINER:
Comments:
JPM SRO ADMIN 2 PALISADES NUCLEAR PLANT Page 2 of 9 SEPTEMBER 2014  JOB PERFORMANCE MEASURE  DATA PAGE   Task: Conduct Surveillance Testing Alternate Path: N/A   Facility JPM #: 2012 NRC EXAM K/A: 2.2.12   Importance: SRO: 4.1 K/A Statement: Knowledge of Surveillance Procedures Task Standard: Supervisory Review of MO-29 completed in accordance with MO-29, step 5.3 AND LCO 3.6.6.A entered due to left train Containment Spray inoperable. Preferred Evaluation Location: ANY  _X_   Preferred Evaluation Method: Perform  _X_  Simulate ______
Examiner: _______________________________                 Date:   ______________
Signature PALISADES NUCLEAR PLANT                   Page 2 of 8                   SEPTEMBER 2014
 
JPM SRO ADMIN 1b EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:
PO-2, PCS Heatup/Cooldown Operations PPC Cyclic Printout Pages 391, 392, 393 for at least one-hour showing a heatup rate that exceeds the 40F/hr Tech Spec limit (see Simulator setup page).
Separate each set of cycle printouts and staple.
Also see Simulator Operator Instructions (later page of this document).
READ TO CANDIDATE DIRECTION TO CANDIDATE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
A Plant refueling has just been completed Shutdown Cooling is NOT in service PCS temperature is approximately 190°F GCL-2, MODE 5 to MODE 3 525°F Checklist is in progress Two PCPs are in service Technical Specification Surveillance Procedure PO-2, PCS Heatup/Cooldown Operations, has just been authorized by the CRS No equipment is out of service, all systems are OPERABLE INITIATING CUES:
The Control Room Supervisor directs you to monitor and record PCS parameters during the heatup using the PPC per PO-2, step 5.1.
PALISADES NUCLEAR PLANT                     Page 3 of 8                     SEPTEMBER 2014
 
JPM SRO ADMIN 1b EVALUATOR CUE: Provide candidate a working copy of PO-2.
Proc. Step             TASK ELEMENT 1                                       STANDARD                 Grade Candidate performs one of the following:
SELECT the Operator Mode Support screen from the main menu                     a. Main menu screen SELECTED, then 5.1.1b                                                    Operator Mode Support screen SELECTED SELECT any of the following, as applicable,                                                 S U 5.1.1c                                                    from main menu screen.
to monitor PCS heatup/cooldown rate:
Page 361 PCS 15 Minute Rate Trend        b. Page 361 PCS 15 Minute Trend page SELECTED Comment:
EVALUATOR NOTE: Operator may go straight to PPC page 361 (task element 3).
Proc. Step             TASK ELEMENT 2                                       STANDARD                 Grade START 15 minute automatic reports as 5.1.1.d.1 follows:                                      F7 key HCR Reports DEPRESSED                S U
: 1. DEPRESS F7 key HCR Reports.
Comment:
CRITICAL STEP Proc. Step             TASK ELEMENT 3                                       STANDARD                 Grade START 15 minute automatic reports as follows:
5.1.1.d.2                                               Cyclic Printout Enabled SELECTED            S U
: 2. SELECT the Cyclic Printout Enabled response Comment:
CRITICAL STEP PALISADES NUCLEAR PLANT                       Page 4 of 8                             SEPTEMBER 2014
 
JPM SRO ADMIN 1b Proc. Step               TASK ELEMENT 4                                         STANDARD                     Grade START 15 minute automatic reports as follows:
Page 361 PCS 15 Minute Trend page 5.1.1.d.3 3. SELECT the HCR Reports page from                                                                 S U SELECTED any of the selected heatup/cooldown pages (361, 362, 372, AND 373).
Comment:
CRITICAL STEP Proc. Step               TASK ELEMENT 5                                         STANDARD                     Grade START 15 minute automatic reports as follows:
: 4. WHEN the HCR Report page is displayed, SELECT the output device at the bottom right corner of the page     Candidate determines that this step is N/A since by performing one of the following         "PRINTER_1" is already selected in bottom right-depending on the desired print             hand corner. Candidate may perform the 5.1.1.d.4                                                    following:                                        S U location:
: a. TYPE a one (1) AND DEPRESS the                 One (1) is TYPED AND Update Hardkey is "UPDATE" Hardkey to start the reports             DEPRESSED.
to print to the control room.
: b. TYPE a two (2) AND DEPRESS the "UPDATE" Hardkey to start the reports to print to the TSC.
Comment:
NOTE: The Heatup/Cooldown print out is on a 15 minute timer that is always running.
When the printout is enabled, the next print timeout could be anywhere from 1 second to 15 minutes later.
EVALUATOR: When candidate has completed this step, hand them the printouts of PPC pages 391, 392, and 393 for the last hour. Tell the candidate that the SE did not review the sheets for the last hour and you have just relieved him/her. Ensure the candidate understands that one hour has elapsed.
CRITICAL STEP PALISADES NUCLEAR PLANT                           Page 5 of 8                             SEPTEMBER 2014
 
JPM SRO ADMIN 1b Proc. Step             TASK ELEMENT 6                                         STANDARD                       Grade Candidate determines that step 5.2 is N/A.
: 5. DETERMINE PCS parameters are within allowable limits at least once every     Candidate refers to step 5.3 and compares 15 minutes during the heatup/cooldown           heatup limits in step 6.0 to the heatup rates 5.1.1.d.5                                                                                                       S U AND INITIAL the PPC Data Sheet. Refer            determined on the PPC printout.
to Step 5.2 and Step 5.3.                       Candidate determines that the heatup rate limit of 40°F hour has been exceeded Comment:
CRITICAL STEP (only critical part is determining heatup rate limit has been exceeded.)
Proc. Step             TASK ELEMENT 7                                         STANDARD                       Grade IF any PCS parameter exceeds its limit or Candidate determines that LCO 3.4.3 condition A the heatup/cooldown rate exceeds the 5.3.1                                                    needs to be entered because the heatup rate limit  S U maximum allowable rate, THEN PERFORM has been exceeded.
the following ...
Comment:
EVALUATOR: When candidate determines that LCO 3.4.3 condition A needs to be entered, end the JPM.
CRITICAL STEP END OF TASK PALISADES NUCLEAR PLANT                           Page 6 of 8                                 SEPTEMBER 2014
 
JPM SRO ADMIN 1b SIMULATOR OPERATOR INSTRUCTIONS IC-3, Ready to come off S/D Cooling.
Preparation of PPC Pages for this JPM:
Turn on PPC Cyclic Printout Remove SDC from service per SOP-3 Allow simulator to run for at least one-hour When at least one-hour of Cyclic Printout pages have finished printing, then preparation is complete Prior to adminstering JPM, remove SDC from service per SOP-3.
ENSURE PPC CYCLIC PRINTOUT IS TURNED OFF AFTER EACH JPM.
PALISADES NUCLEAR PLANT                 Page 7 of 8                   SEPTEMBER 2014
 
JPM SRO ADMIN 1b CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
A Plant refueling has just been completed Shutdown Cooling is NOT in service PCS temperature is approximately 190°F GCL-2, MODE 5 to MODE 3 525°F Checklist is in progress Two PCPs are in service Technical Specification Surveillance Procedure PO-2, PCS Heatup/Cooldown Operations, has just been authorized by the CRS No equipment is out of service, all systems are OPERABLE INITIATING CUES:
The Control Room Supervisor directs you to monitor and record PCS parameters during the heatup using the PPC per PO-2, step 5.1.
PALISADES NUCLEAR PLANT                Page 8 of 8                  SEPTEMBER 2014
 
NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: SRO ADMIN 2 TITLE: REVIEW AND APPROVE A COMPLETED TECHNICAL SPECIFICATION SURVEILLANCE TEST CANDIDATE:
EXAMINER:
 
JPM SRO ADMIN 2 JOB PERFORMANCE MEASURE DATA PAGE Task:   Conduct Surveillance Testing Alternate Path: N/A Facility JPM #: 2012 NRC EXAM K/A:     2.2.12         Importance:     SRO:       4.1 K/A Statement: Knowledge of Surveillance Procedures Task Standard: Supervisory Review of MO-29 completed in accordance with MO-29, step 5.3 AND LCO 3.6.6.A entered due to left train Containment Spray inoperable.
Preferred Evaluation Location: ANY          _X_
Preferred Evaluation Method:    Perform      _X_            Simulate   ______


==References:==
==References:==
ADMIN 9.20, Technical Specification Surveillance and Special Test Program     MO-29, Engineered Safety System Alignment Validation Time: 20 minutes Time Critical: NO   Candidate:   Time Start: ________ Time Finish: ________ Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______ Comments:     Examiner: _______________________________ Date: ______________ Signature JPM SRO ADMIN 2 PALISADES NUCLEAR PLANT Page 3 of 9 SEPTEMBER 2014 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:   Completed MO-29, ,for Containment Spray Header pressure (PI-3001) below the acceptance range. Also include a missed signature date. ADMIN 9.20 Technical Specifications Technical Specifications Bases RED PEN FOR STUDENT USE   READ TO CANDIDATE DIRECTION TO CANDIDATE: I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:   shift, 2130 hours. You are the on-shift Shift Engineer. MO-29, Engineered Safety System Alignment, was completed at 2115 hours. The plant is in MODE 1. INITIATING CUES:   The Shift Manager directs you to complete a supervisory review of completed MO-in accordance with step 5.3 of MO-29. Evaluator Note: Provide candidate with completed MO-29 with the data point for Containment Spray Header 'B' pressure (PI-3001) below the acceptance range at 61.8 psig. Do not circle the reading in red. Also, include a missed signature date JPM SRO ADMIN 2 PALISADES NUCLEAR PLANT Page 4 of 9 SEPTEMBER 2014 EVALUATOR CUE: Hand candidate a complete MO-29 Surveillance Test with one spray header pressure (PI-3001) indication below the acceptance criteria. Proc. Step TASK ELEMENT 1 STANDARD Grade 5.3.1.a REVIEW MO-29 to ensure all applicable components have been inspected. except for the date field of step 3.1 S U Comment:   EVALUATOR NOTE: The missed signature date is not a critical task   Proc. Step TASK ELEMENT 2 STANDARD Grade 5.3.1.b ENSURE entries on MO-29 are circled in red for any components found in an incorrect position OR acceptance criteria not met. Operator reviews section 6.0 of MO-29 and verifies the following: ___ Containment Air Cooler 'A' Fans operated for greater than or equal to 15 minutes. ___ *Containment Spray Header pressure gauges (PI-3001 and PI-3001) greater than or equal to 62.0 psig. ___ "As Found" position of applicable fans, valves, breakers, and controls agrees with "Required Position" listed in MO-29 Checklist (Attachment 1). ___ *All out of tolerance data shall be circled in red. S  U Comment:   EVALUATOR NOTE: The containment spray header pressure reading for PI-3001 is below the acceptance range. The candidate must recognize this.
ADMIN 9.20, Technical Specification Surveillance and Special Test Program MO-29, Engineered Safety System Alignment Validation Time:   20 minutes     Time Critical:     NO Candidate:
* CRITICAL STEP JPM SRO ADMIN 2 PALISADES NUCLEAR PLANT Page 5 of 9 SEPTEMBER 2014 Proc. Step TASK ELEMENT 3 STANDARD Grade 5.3.1.c INITIATE a Condition Report in accordance with EN-LI-102, Corrective Action Process, for acceptance criteria not met unless at least one of the following conditions exist: 1. Out of tolerance item is controlled by a previously identified LCO. 2. Component is in position resulting from prior Operations review and approval. To allow alternate position of any component, adequate redundancy shall exist to ensure operability of Engineering Safety System Equipment. Operator determines that this step is applicable and recognizes that a CR should be initiated. S  U Comment:   EVALUATOR CUE: Inform candidate that CR has been initiated     Proc. Step TASK ELEMENT 4 STANDARD Grade 5.3.1.d IF spray header pressures are less than 62.8 psig, THEN NOTIFY System Engineer to determine if Containment Spray Header Fill can wait until the next scheduled performance of MO-29 based on MO-29 trend data analysis. 1. System Engineer: NOTIFY Planning/Scheduling and Operations when to schedule ESSO-1, Operator notifies System Engineer. S  U Comment:   EVALUATOR CUE: If asked as System Engineer: report that the containment spray header fill can not wait until the next scheduled performance of MO-29 and they will notify Planning/Scheduling.
Time Start: ________       Time Finish:     ________
JPM SRO ADMIN 2 PALISADES NUCLEAR PLANT Page 6 of 9 SEPTEMBER 2014 Proc. Step TASK ELEMENT 5 STANDARD Grade 5.3.1.e COMPLETE Acceptance Criteria and Operability Sheet. Operator performs the following for the acceptable criteria and operability sheet: ___
Performance Time:       ________ minutes Performance Rating:     SAT______       UNSAT ______
* Answers #1 NO and signs and provides explanation on page 2 (i.e., Spray Header pressure PI-3001 is below acceptance range) (signature is not part of the critical step) ___
Comments:
* Answers #2 NO and signs (signature is not part of the critical step) ___ Completes CAP and WR numbers for #3 ___ Notifies SM/CRS/SE and signs for #4 (signature is not part of the critical step) ___
Examiner: _______________________________                 Date: ______________
* Operator reviews LCO 3.6.6A.1 and determines that left train of Containment Cooling system is inoperable and LCO .1 The Yes or NO box will be checked for #5 and justification filled out on page 2. This justification should explain that the plant has 72 hours to restore left train of containment cooling system back to operable status or place the plant in a MODE where the LCO is not applicable. S  U Comment: EVALUATOR CUE: If asked, supply candidate with the following: WR#: 02004567 (not required since this is an Operations activity, per ESSO-1, and is not controlled by Work Order process.) CR#: CR-PLP-2014-99999. EVALUATOR CUE: Inform candidate that SM/CRS/SE have been notified. EVALUATOR CUE: If asked, candidate also performs Step 5. System Engineer will perform Step 6, Tech. Rev.
Signature PALISADES NUCLEAR PLANT               Page 2 of 9                     SEPTEMBER 2014
* CRITICAL STEP JPM SRO ADMIN 2 PALISADES NUCLEAR PLANT Page 7 of 9 SEPTEMBER 2014 Proc. Step TASK ELEMENT 6 STANDARD Grade 5.3.2 On Shift SRO Reviewed Completed by: Operator signs and dates for SRO Review S U Comment:     END OF TASK JPM SRO ADMIN 2 PALISADES NUCLEAR PLANT Page 8 of 9 SEPTEMBER 2014 SIMULATOR OPERATOR INSTRUCTIONS   N/A JPM SRO ADMIN 2 PALISADES NUCLEAR PLANT Page 9 of 9 SEPTEMBER 2014 CANDIDATE CUE SHEET   (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)   INITIAL CONDITIONS:   shift, 2130 hours. You are the on-shift Shift Engineer. MO-29, Engineered Safety System Alignment, was completed at 2115 hours. The plant is in Mode 1. INITIATING CUES:   The Shift Manager directs you to complete a supervisory review of completed MO-29, in accordance with step 5.3 of MO-29.
 
REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE     JPM: SRO ADMIN 3 TITLE: DETERMINE WASTE GAS RELEASE HIGH ALARM SETPOINT   CANDIDATE:   EXAMINER:
JPM SRO ADMIN 2 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:
JPM SRO ADMIN 3 PALISADES NUCLEAR PLANT Page 2 of 8 SEPTEMBER 2014  JOB PERFORMANCE MEASURE DATA PAGE   Task: Determine setpoint changes to process radiation monitors Alternate Path: N/A Facility JPM #: NEW K/A: 2.3.11   Importance: RO: 3.8 SRO: 4.3 K/A Statement: Ability to control radiation releases. Task Standard: Correct setpoint is calculated for Waste Gas release Preferred Evaluation Location: Simulator _X_ In Plant ______ Preferred Evaluation Method: Perform _X_ Simulate ______
Completed MO-29, Engineered Safety System Alignment, with one data point for Containment Spray Header pressure (PI-3001) below the acceptance range.
Also include a missed signature date.
ADMIN 9.20, Technical Specification Surveillance and Special Test Program Technical Specifications Technical Specifications Bases RED PEN FOR STUDENT USE READ TO CANDIDATE DIRECTION TO CANDIDATE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
Its Friday night shift, 2130 hours.
You are the on-shift Shift Engineer.
MO-29, Engineered Safety System Alignment, was completed at 2115 hours.
The plant is in MODE 1.
INITIATING CUES:
The Shift Manager directs you to complete a supervisory review of completed MO-29, Engineered Safety System Alignment, in accordance with step 5.3 of MO-29.
Evaluator Note: Provide candidate with completed MO-29 with the data point for Containment Spray Header 'B' pressure (PI-3001) below the acceptance range at 61.8 psig. Do not circle the reading in red. Also, include a missed signature date for step 3.1 Authorization.
PALISADES NUCLEAR PLANT                     Page 3 of 9                       SEPTEMBER 2014
 
JPM SRO ADMIN 2 EVALUATOR CUE: Hand candidate a complete MO-29 Surveillance Test with one spray header pressure (PI-3001) indication below the acceptance criteria.
Proc. Step             TASK ELEMENT 1                                       STANDARD                         Grade All pages present with all blanks filled in or N/A REVIEW MO-29 to ensure all applicable 5.3.1.a                                                  except for the date field of step 3.1                 S U components have been inspected.
Authorization.
Comment:
EVALUATOR NOTE: The missed signature date is not a critical task Proc. Step             TASK ELEMENT 2                                       STANDARD                         Grade Operator reviews section 6.0 of MO-29 and verifies the following:
___ Containment Air Cooler 'A' Fans operated for greater than or equal to 15 minutes.
___ *Containment Spray Header pressure ENSURE entries on MO-29 are circled in gauges (PI-3001 and PI-3001) greater than red for any components found in an 5.3.1.b                                                        or equal to 62.0 psig.                         S U incorrect position OR acceptance criteria not met.                                       ___ "As Found" position of applicable fans, valves, breakers, and controls agrees with "Required Position" listed in MO-29 Checklist (Attachment 1).
___ *All out of tolerance data shall be circled in red.
Comment:
EVALUATOR NOTE: The containment spray header pressure reading for PI-3001 is below the acceptance range. The candidate must recognize this.
* CRITICAL STEP PALISADES NUCLEAR PLANT                         Page 4 of 9                               SEPTEMBER 2014
 
JPM SRO ADMIN 2 Proc. Step               TASK ELEMENT 3                                         STANDARD                     Grade INITIATE a Condition Report in accordance with EN-LI-102, Corrective Action Process, for acceptance criteria not met unless at least one of the following conditions exist:
: 1. Out of tolerance item is controlled by a previously identified LCO.
Operator determines that this step is applicable 5.3.1.c        2. Component is in position resulting                                                         S U and recognizes that a CR should be initiated.
from prior Operations review and approval. To allow alternate position of any component, adequate redundancy shall exist to ensure operability of Engineering Safety System Equipment.
Comment:
EVALUATOR CUE: Inform candidate that CR has been initiated Proc. Step               TASK ELEMENT 4                                         STANDARD                     Grade IF spray header pressures are less than 62.8 psig, THEN NOTIFY System Engineer to determine if Containment Spray Header Fill can wait until the next scheduled performance of MO-29 based on MO-29 5.3.1.d  trend data analysis.                             Operator notifies System Engineer.                S U
: 1. System Engineer: NOTIFY Planning/Scheduling and Operations when to schedule ESSO-1, Containment Spray Header Fill.
Comment:
EVALUATOR CUE: If asked as System Engineer: report that the containment spray header fill can not wait until the next scheduled performance of MO-29 and they will notify Planning/Scheduling.
PALISADES NUCLEAR PLANT                           Page 5 of 9                             SEPTEMBER 2014
 
JPM SRO ADMIN 2 Proc. Step               TASK ELEMENT 5                                 STANDARD                         Grade Operator performs the following for the acceptable criteria and operability sheet:
___
* Answers #1 NO and signs and provides explanation on page 2 (i.e., Spray Header pressure PI-3001 is below acceptance range) (signature is not part of the critical step)
___
* Answers #2 NO and signs (signature is not part of the critical step)
___ Completes CAP and WR numbers for #3 COMPLETE Acceptance Criteria and          ___ Notifies SM/CRS/SE and signs for #4 5.3.1.e                                                                                                  S U Operability Sheet.                            (signature is not part of the critical step)
___
* Operator reviews LCO 3.6.6A.1 and determines that left train of Containment Cooling system is inoperable and LCO Action A.1 of LCO 3.6.6 has been entered.
The Yes or NO box will be checked for #5 and justification filled out on page 2. This justification should explain that the plant has 72 hours to restore left train of containment cooling system back to operable status or place the plant in a MODE where the LCO is not applicable.
Comment:
EVALUATOR CUE: If asked, supply candidate with the following:
WR#: 02004567 (not required since this is an Operations activity, per ESSO-1, and is not controlled by Work Order process.)
CR#: CR-PLP-2014-99999.
EVALUATOR CUE: Inform candidate that SM/CRS/SE have been notified.
EVALUATOR CUE: If asked, candidate also performs Step 5. System Engineer will perform Step 6, Tech. Rev.
* CRITICAL STEP PALISADES NUCLEAR PLANT                     Page 6 of 9                               SEPTEMBER 2014
 
JPM SRO ADMIN 2 Proc. Step           TASK ELEMENT 6                                 STANDARD                   Grade 5.3.2   On Shift SRO Reviewed Completed by:       Operator signs and dates for SRO Review       S U Comment:
END OF TASK PALISADES NUCLEAR PLANT                   Page 7 of 9                             SEPTEMBER 2014
 
JPM SRO ADMIN 2 SIMULATOR OPERATOR INSTRUCTIONS N/A PALISADES NUCLEAR PLANT         Page 8 of 9         SEPTEMBER 2014
 
JPM SRO ADMIN 2 CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
Its Friday night shift, 2130 hours.
You are the on-shift Shift Engineer.
MO-29, Engineered Safety System Alignment, was completed at 2115 hours.
The plant is in Mode 1.
INITIATING CUES:
The Shift Manager directs you to complete a supervisory review of completed MO-29, Engineered Safety System Alignment, in accordance with step 5.3 of MO-29.
PALISADES NUCLEAR PLANT                  Page 9 of 9                SEPTEMBER 2014
 
REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: SRO ADMIN 3 TITLE: DETERMINE WASTE GAS RELEASE HIGH ALARM SETPOINT CANDIDATE:
EXAMINER:
 
JPM SRO ADMIN 3 JOB PERFORMANCE MEASURE DATA PAGE Task:   Determine setpoint changes to process radiation monitors Alternate Path: N/A Facility JPM #: NEW K/A:     2.3.11         Importance:       RO:       3.8     SRO:     4.3 K/A Statement: Ability to control radiation releases.
Task Standard: Correct setpoint is calculated for Waste Gas release Preferred Evaluation Location: Simulator       _X_       In Plant     ______
Preferred Evaluation Method:       Perform     _X_       Simulate     ______


==References:==
==References:==
SOP-18A, Radioactive Waste System     CH 6.23, Waste Gas Decay Tank Release     SOP-38, Gaseous Process Monitoring System Validation Time: 10 minutes Time Critical: NO   Candidate:   Time Start: ________ Time Finish: ________ Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______ Comments:     Examiner: _______________________________ Date: ______________ Signature JPM SRO ADMIN 3 PALISADES NUCLEAR PLANT Page 3 of 8 SEPTEMBER 2014 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:   SOP-, section 7.5 with placekeeping completed through step g. Partially completed form CH 6.23-3 Calculator Also see Simulator Operator Instructions (later page of this document). READ TO CANDIDATE DIRECTION TO CANDIDATE: I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:   A Containment purge is not in progress. RIA-1113, Waste Gas Monitor is operable per DWO-1. T-101C, Waste Gas Decay Tank, has been authorized for release. INITIATING CUES:   The Shift Manager asks you to determine RIA-1113 HIGH alarm setpoint per SOP-18A steps 7.5.h through 7.5.j.
SOP-18A, Radioactive Waste System CH 6.23, Waste Gas Decay Tank Release SOP-38, Gaseous Process Monitoring System Validation Time:   10 minutes         Time Critical: NO Candidate:
JPM SRO ADMIN 3 PALISADES NUCLEAR PLANT Page 4 of 8 SEPTEMBER 2014 Evaluator Cue: Provide Operator a working copy of SOP-18A, section 7.5 placekept through step g AND batch release order, Form CH 6.23-3, page 1 only (last page of JPM) Proc. Step TASK ELEMENT 1 STANDARD Grade 7.5.h Operator reads RIA-1113 background ___ Operator depresses HS-2317 for >1 minute and releases ___ Operator reads background cpm ___ RECORD cpm on CH Form 6.23- RIA-1113 S  U Comment: Evaluator Note: Reading should be ~8.3 x 101 to 9.5 x 101 cpm CRITICAL STEP   Proc. Step TASK ELEMENT 2 STANDARD Grade 7.5.i PERFORM a source check of RE- ___ DEPRESS and HOLD the Check Source pushbutton on RE-1113 ___ Verify the meter indication rises ___ RELEASE the Check Source pushbutton ___ RECORD cpm on CH Form 6.23- S  U Comment:     Proc. Step TASK ELEMENT 3 STANDARD Grade 7.5.j DETERMINE Hi Alarm setpoint. (This is the sum of the observed background and the established release limit provided on Form CH 6.23-3.) ___ Candidate adds RIA-1113 background to the release limit to obtain high alarm setpoint: 8.3 x 101  to 9.5 x 101 cpm + 8.5 x 103 cpm ___ Determines high alarm setpoint to be 8.6 x 103 cpm S  U Comment: Evaluator Note: (Acceptable range is 8.5 8.6 x 103 cpm). CRITICAL STEP JPM SRO ADMIN 3 PALISADES NUCLEAR PLANT Page 5 of 8 SEPTEMBER 2014 Proc. Step TASK ELEMENT 4 STANDARD Grade n/a Operator returns CH form 6.23-3 to Shift Manager for verification of calculation. Operator reports task is complete. S U Comment: Evaluator Note: Role play as SM and inform candidate that you will verify calculation. END OF TASK JPM SRO ADMIN 3 PALISADES NUCLEAR PLANT Page 6 of 8 SEPTEMBER 2014   SIMULATOR OPERATOR INSTRUCTIONS   Reset to any IC Ensure V-6A, Main Exhaust Fan, is in service JPM SRO ADMIN 3 PALISADES NUCLEAR PLANT Page 7 of 8 SEPTEMBER 2014 CANDIDATE CUE SHEET   (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)   INITIAL CONDITIONS:   A Containment purge is not in progress. RIA-1113, Waste Gas Monitor is operable per DWO-1. T-101C, Waste Gas Decay Tank, has been authorized for release. INITIATING CUES:   The Shift Manager asks you to determine RIA-1113 HIGH alarm setpoint per SOP-18A steps 7.5.h through 7.5.j.
Time Start: ________         Time Finish:       ________
PALISADES NUCLEAR PLANT Page 8 of 8 SEPTEMBER 2014 FORM CH 6.23-3 Proc No CH 6.23 Attachment 3 WGDT RELEASE AUTHORIZATION Revision 6 Page 1 of 2   Batch Number     WG-TODAY WGDT Number T-101C Release Pressure 93 psig Release Volume 32.5 m3  Calculated RIA-1113 Reading       9.5 x 101 cpm                               10 RIA-1113 Alarm Setpoint > Bkg     8.5 x 103 cpm   Release Authorization Authorized By                 Jane Retssup Jane Retssup           Today                                       Printed Name and Signature Date Shift Manager/CRS          Ralph Manager Ralph Manager      Today                                       Printed Name and Signature Date   Control Room Operator Main Exhaust Fan in Service     V-6A     V-6B Ensure at least one exhaust fan is operating prior to releasing a WGDT Purge RIA-1113     Source Check RIA-1113   cpm RIA-1113 Alarm Setpoint > Bkg cpm RIA-1113 Background         +   cpm RIA-1113 Alarm Setpt          =     cpm Alarm Set By                             Alarm Verified By Purge RIA-1113 After Release Reset Alarm to 2500 Alarm Reset By Alarm Reset Verified By Remarks     If RIA-1113 is not operational, effluent releases may continue provided that prior to release: 1. At least two independent samples are analyzed; and 2. At least two technically qualified members of the Facility Staff independently verify the release rate calculations and discharge line valving. Palisades ODCM Appnedix A, Table A-1, Item 1.a, Action 1 REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE     JPM: SRO ADMIN 4 TITLE: CLASSIFY EVENT     CANDIDATE:   EXAMINER:
Performance Time:       ________ minutes Performance Rating:     SAT______         UNSAT ______
JPM SRO ADMIN 4 PALISADES NUCLEAR PLANT Page 2 of 9 SEPTEMBER 2014  JOB PERFORMANCE MEASURE DATA PAGE Task: Classify an Event Alternate Path: N/A Facility JPM #: NEW K/A: 2.4.41   Importance: SRO: 4.6 K/A Statement: (2.4.41) Knowledge of the emergency action level thresholds and classifications. Task Standard: Event classified as an Alert within 15 minutes and completion of Event Notification Form within an additional 12 minutes. Preferred Evaluation Location: ANY __X__ Preferred Evaluation Method: Perform __X__ Simulate _____
Comments:
Examiner: _______________________________                 Date:   ______________
Signature PALISADES NUCLEAR PLANT                   Page 2 of 8                     SEPTEMBER 2014
 
JPM SRO ADMIN 3 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:
SOP-18A, Radioactive Waste System, section 7.5 with placekeeping completed through step g.
Partially completed form CH 6.23-3 Calculator Also see Simulator Operator Instructions (later page of this document).
READ TO CANDIDATE DIRECTION TO CANDIDATE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
A Containment purge is not in progress.
RIA-1113, Waste Gas Monitor is operable per DWO-1.
T-101C, Waste Gas Decay Tank, has been authorized for release.
INITIATING CUES:
The Shift Manager asks you to determine RIA-1113 HIGH alarm setpoint per SOP-18A steps 7.5.h through 7.5.j.
PALISADES NUCLEAR PLANT                     Page 3 of 8                       SEPTEMBER 2014
 
JPM SRO ADMIN 3 Evaluator Cue: Provide Operator a working copy of SOP-18A, section 7.5 placekept through step g AND batch release order, Form CH 6.23-3, page 1 only (last page of JPM)
Proc. Step             TASK ELEMENT 1                                       STANDARD                     Grade
___ Operator depresses HS-2317 for >1 minute and releases
___ Operator reads background cpm 7.5.h    Operator reads RIA-1113 background                                                              S U
___ RECORD cpm on CH Form 6.23-3, WGDT Release Authorization and checks Purge RIA-1113 Box Comment:
Evaluator Note: Reading should be ~8.3 x 101 to 9.5 x 101 cpm CRITICAL STEP Proc. Step             TASK ELEMENT 2                                       STANDARD                     Grade
___ DEPRESS and HOLD the Check Source pushbutton on RE-1113
___ Verify the meter indication rises 7.5.i    PERFORM a source check of RE-1113                                                              S U
___ RELEASE the Check Source pushbutton
___ RECORD cpm on CH Form 6.23-3, WGDT Release Authorization Comment:
Proc. Step             TASK ELEMENT 3                                       STANDARD                     Grade
___ Candidate adds RIA-1113 background to the release limit to obtain high alarm DETERMINE Hi Alarm setpoint. (This is the setpoint:
sum of the observed background and the 8.3 x 10 to 9.5 x 10 cpm + 8.5 x 10 1            1            3 7.5.j                                                                                                    S U established release limit provided on Form cpm CH 6.23-3.)
___ Determines high alarm setpoint to be 3
8.6 x 10 cpm Comment:
Evaluator Note: (Acceptable range is 8.5 - 8.6 x 103 cpm).
CRITICAL STEP PALISADES NUCLEAR PLANT                         Page 4 of 8                               SEPTEMBER 2014
 
JPM SRO ADMIN 3 Proc. Step             TASK ELEMENT 4                                         STANDARD                   Grade Operator returns CH form 6.23-3 to Shift n/a                                                      Operator reports task is complete.           S U Manager for verification of calculation.
Comment:
Evaluator Note: Role play as SM and inform candidate that you will verify calculation.
END OF TASK PALISADES NUCLEAR PLANT                           Page 5 of 8                             SEPTEMBER 2014
 
JPM SRO ADMIN 3 SIMULATOR OPERATOR INSTRUCTIONS Reset to any IC Ensure V-6A, Main Exhaust Fan, is in service PALISADES NUCLEAR PLANT             Page 6 of 8     SEPTEMBER 2014
 
JPM SRO ADMIN 3 CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
A Containment purge is not in progress.
RIA-1113, Waste Gas Monitor is operable per DWO-1.
T-101C, Waste Gas Decay Tank, has been authorized for release.
INITIATING CUES:
The Shift Manager asks you to determine RIA-1113 HIGH alarm setpoint per SOP-18A steps 7.5.h through 7.5.j.
PALISADES NUCLEAR PLANT               Page 7 of 8                 SEPTEMBER 2014
 
FORM CH 6.23-3                               Proc No CH 6.23 Attachment 3 WGDT RELEASE AUTHORIZATION                             Revision 6 Page 1 of 2 Batch Number                         WG-TODAY WGDT Number                                     T-101C Release Pressure                               93 psig 3
Release Volume                                 32.5 m Calculated RIA-1113 1
Reading                                   9.5 x 10 cpm b factor                                  10 RIA-1113 Alarm 3
Setpoint > Bkg                             8.5 x 10 cpm Release Authorization Authorized By           Jane Retssup Jane Retssup           Today Printed Name and Signature               Date Shift Manager/CRS          Ralph Manager Ralph Manager      Today Printed Name and Signature               Date Control Room Operator Main Exhaust Fan in Service       V-6A       V-6B             Ensure at least one exhaust fan is operating prior to releasing a WGDT Purge RIA-1113 Source Check RIA-1113                         cpm RIA-1113 Alarm Setpoint > Bkg                 cpm RIA-1113 Background           +               cpm RIA-1113 Alarm Setpt          =               cpm Alarm Set By Alarm Verified By Purge RIA-1113 After Release Reset Alarm to 2500 Alarm Reset By Alarm Reset Verified By Remarks If RIA-1113 is not operational, effluent releases may continue provided that prior to release:
: 1. At least two independent samples are analyzed; and
: 2. At least two technically qualified members of the Facility Staff independently verify the release rate calculations and discharge line valving.
Palisades ODCM Appnedix A, Table A-1, Item 1.a, Action 1 PALISADES NUCLEAR PLANT                            Page 8 of 8                              SEPTEMBER 2014
 
REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: SRO ADMIN 4 TITLE: CLASSIFY EVENT CANDIDATE:
EXAMINER:
 
JPM SRO ADMIN 4 JOB PERFORMANCE MEASURE DATA PAGE Task:   Classify an Event Alternate Path: N/A Facility JPM #: NEW K/A:     2.4.41           Importance:     SRO:       4.6 K/A Statement: (2.4.41) Knowledge of the emergency action level thresholds and classifications.
Task Standard: Event classified as an Alert within 15 minutes and completion of Event Notification Form within an additional 12 minutes.
Preferred Evaluation Location: ANY             __X__
Preferred Evaluation Method:     Perform       __X__         Simulate   _____


==References:==
==References:==
EI-3, Communications and Notification Procedure     EI-1, Emergency Classification and Actions Procedure Validation Time: 20 minutes Time Critical: YES Evaluation Location: Simulator __X__ In Plant ______   Candidate:   Time Start: ________ Time Finish: ________ Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______ Comments:   Examiner: _______________________________ Date: ______________ Signature JPM SRO ADMIN 4  PALISADES NUCLEAR PLANT Page 3 of 9 SEPTEMBER 2014 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:     EI- EI- Also see Simulator Operator Instructions (later page of this document). READ TO CANDIDATE DIRECTION TO CANDIDATE: I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS: The Plant is in MODE 6 and fuel shuffles in progress, the following events occur: All offsite power is lost o Buses 1C and 1D are reenergized by D/G 1-1 and D/G 1-2 respectively Air to the Steam Generator (S/G) nozzle dams was lost for several minutes and approximately 90 gallons of PCS drained to the Containment floor o Air to S/G nozzle dams has been restored: dams are no longer leaking Containment closure was established with the exception that the Equipment Hatch was not closed due to the hatch being inadvertently knocked off it's track Shutdown Cooling restoration is delayed and the PCS has risen to 212°F and PCS boil-off has commenced Rising counts indicated on RIA-2326 (Normal Range RGEM) INITIATING CUES: You are the Shift Manager (acting as the Emergency Plant Manager). You are to classify the event given the above information and complete the Event Notification Form. No previous event declaration has been made. This JPM is Time Critical.
EI-3, Communications and Notification Procedure EI-1, Emergency Classification and Actions Procedure Validation Time:     20 minutes       Time Critical:     YES Evaluation Location:     Simulator   __X__           In Plant   ______
JPM SRO ADMIN 4  PALISADES NUCLEAR PLANT Page 4 of 9 SEPTEMBER 2014 EVALUATOR CUE: Candidate may use placard of site emergency plan classifications or provide working copy of EI-1 SEP Supp 1. Proc.Step TASK ELEMENT 1 STANDARD Grade EI-1 6.1.b.1 SEP SUPP 1 1. Determine the Category in which the Initiating Conditions/symptoms best fit from the list of Categories below: A - Abnormal Rad Levels / Radiological Effluent C - Cold Shutdown / Refueling System Malfunction E - Independent Spent Fuel Storage Installation (ISFSI) F - Fission Product Barrier Degradation H - Hazards S - System Malfunction Refers to SEP Supp 1MODE 5, 6, or DEFpage and determines Category C applies. S  U Comment: START TIME FOR CLASSIFICATION:_________     Proc.Step TASK ELEMENT 2 STANDARD Grade EI-1 6.1.b.2 SEP SUPP 1 2. Use the Category identified above and SEP Supplement 1 to determine which Emergency Action Level (EAL) threshold has been exceeded. Move from the highest classification (left) to lowest classification (right) when determining the classification. ___ Refers to CA4 ___ Determines per Table C-3 that with CONTAINMENT CLOSURE and PCS integrity not established that  an UNPLANNED event results in PCS temperature > 200°F for > Table C-3 duration S  U Comment:   CRITICAL STEP JPM SRO ADMIN 4  PALISADES NUCLEAR PLANT Page 5 of 9 SEPTEMBER 2014  Proc.Step TASK ELEMENT 3 STANDARD Grade SEP SUPP 1 Declares Emergency Classification. Declares an Alert per CA4 based on status of event. S U Comment: END TIME FOR CLASSIFICATION:_________ (START TIME FOR FORM COMPLETION) CRITICAL STEP - must be performed within 15 minutes of start of JPM. Proc.Step TASK ELEMENT 4 STANDARD Grade EI-1 6.2.b Att 1 b. Using the "Action" column of Attachment 1, perform each action as M (Mandatory), S (Subsequent), or I (If Needed). Obtains EI-1, Attachment 1 and performs or delegates actions. S  U Comment:  EVALUATOR CUE: Another SRO will perform this task.
Candidate:
JPM SRO ADMIN 4  PALISADES NUCLEAR PLANT Page 6 of 9 SEPTEMBER 2014  Proc.Step TASK ELEMENT 5 STANDARD Grade EI-3 Att 1 Completes filling out Palisades Event Notification Form. Palisades Event Notification Form completely filled per attached KEY AND form is approved (Candidate signature/initials, date, and time entered  at bottom of form)
Time Start: ________           Time Finish:     ________
* S  U Comment: EVALUATOR CUE (provide when applicable as Candidate fills out form):  Hand Candidate EI-6.7 Attachment 1 (meteorological data)  It is a hot sunny day with no rain in the forecast EVALUATOR NOTE:  KEY is attached to this JPM. EVALUATOR NOTE:  EI-3, Attachment 2, "Palisades Event Technical Data Sheet" is NOT required during this JPM. EVALUATOR NOTE:  If JPM is conducted in the Simulator, then Candidate may use computer on Control Room island area to prepare this form. EVALUATOR NOTE:  If JPM is conducted in the Simulator, then Candidate may use computer on back-bar of Control Room island area to complete and print this form.
Performance Time:         ________ minutes Performance Rating:       SAT______       UNSAT ______
* The following are the critical parts of this step:  ALERT is checked in "current classification" section  Date and time filled in "current classification" section  CA4.1 filled in "reason for classification" section OR Cold Shutdown/Refueling System Malfunction checked in "reason for classification" section  YES END TIME FOR FORM COMPLETION:_________ CRITICAL STEP (must be completed within 12 minutes of time listed in Task Element 3)  END OF TASK PALISADES NUCLEAR PLANT Page 7 of 9 SEPTEMBER 2014 PALISADES EVENT NOTIFICATION FORM    Actual Event                                                                          Drill Plant Contact Information Nuclear Power Plant: _________________________________________ Plant Communicator: __________________  Time of Communication: V.B. ______                           S.O.M. ______                NRC ______      Plant Message Number Calling From:    Control Room        TSC        EOF      Other______ Call Back Telephone Number: _____________________________________________ Current Classification  Unusual Event     Alert      Site Area Emergency      General Emergency      Termination This Classification was declared as of:     Date: Today         Time: Within 15 minutes from start of JPM Reason for Classification  Abnormal Rad Levels / Radiological Effluent  System Malfunctions  Hazards and Other Conditions Affecting  Cold Shutdown / Refueling System Malfunction  Plant Safety    Independent Spent Fuel Storage    Installation Events    Fission Product Barrier Degradation IC Number: CA4.1 Radiological Release in Progress Due to Event   Yes       No Protective Action Recommendations  None Evacuation of Areas(s): 1  2  3  4  5 In-Place Shelter of Area(s)  1  2  3  4 5 PAR based on:           Dose Calculation (Palisades Event Technical Data Sheet required)    Plant Status    Security Event  Other  ___________________________________________________________________________________________________ Meteorological Data Wind Direction (degrees):  From  270    To  90    Wind Speed (MPH):    12  Stability Class:    B           Precipitation:  Yes  No  Emergency Director Approval: ________________________________  Date: _________  Time: ________ ANSWER KEY 1 Proc No EI-3 Attachment 1 Revision 31 Page 1 of 1 JPM SRO ADMIN 4  PALISADES NUCLEAR PLANT Page 8 of 9 SEPTEMBER 2014  SIMULATOR OPERATOR INSTRUCTIONS  No Simulator setup required. Prepare EI-6.7 Attachment 1 with the following data and then sign and date form: o Wind Speed is 12 mph o Wind Direction is from 270 degrees o Stablity Class = B  It is preferred that this JPM be done separately from the simulator. If, by chance, candidate IS in the simulator while doing this JPM, THEN ensure the IC does NOT have a release in progress. ENSURE ALL DATA IS CLEARED FROM EP NOTIFICATION COMPUTER ON BACK-BAR OF CRS ISLAND PRIOR TO NEXT USE OF THIS JPM.
Comments:
JPM SRO ADMIN 4  PALISADES NUCLEAR PLANT Page 9 of 9 SEPTEMBER 2014  CANDIDATE CUE SHEET  (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK) INITIAL CONDITIONS: The Plant is in MODE 6 and fuel shuffles in progress, the following events occur:  All offsite power is lost o Buses 1C and 1D are reenergized by D/G 1-1 and D/G 1-2 respectively  Air to the Steam Generator (S/G) nozzle dams was lost for several minutes and approximately 90 gallons of PCS drained to the Containment floor o Air to S/G nozzle dams has been restored: dams are no longer leaking  Containment closure was established with the exception that the Equipment Hatch was not closed due to the hatch being inadvertently knocked off it's track  Shutdown Cooling restoration is delayed and the PCS has risen to 212°F and PCS boil-off has commenced  Rising counts indicated on RIA-2326 (Normal Range RGEM)  INITIATING CUES: You are the Shift Manager (acting as the Emergency Plant Manager). You are to classify the event given the above information and complete the Event Notification Form. No previous event declaration has been made. This JPM is Time Critical.
Examiner: _______________________________                     Date: ______________
NRC REGION III  INITIAL LICENSE EXAM  JOB PERFORMANCE MEASURE    JPM: RO/SRO-I/SRO-U SYS A  TITLE: GRAVITY FEED BORATION WHILE SHUTDOWN      CANDIDATE:  EXAMINER:
Signature PALISADES NUCLEAR PLANT                   Page 2 of 9                       SEPTEMBER 2014
JPM SYSTEM A  PALISADES NUCLEAR PLANT Page 2 of 10 SEPTEMBER 2014  JOB PERFORMANCE MEASURE  DATA PAGE  Task: Perform gravity feed boration to PCS while shutdown. Alternate Path: YES  Facility JPM #: NEW  K/A: 004A4.07  Importance:  RO:  3.9  SRO: 3.7  K/A Statement: Ability to manually operate and/or monitor in the control room: Boration/dilution. Task Standard: Gravity feed at 33 gpm Charging flow for at least two minutes. Preferred Evaluation Location: Simulator ___X___ In Plant  _____ Preferred Evaluation Method: Perform  ___X___ Simulate _____ 
 
JPM SRO ADMIN 4 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:
SEP SUP 1, Site Emergency Plan Supplement 1 - EAL Wall Charts EI-1, Emergency Classification and Actions Procedure, Attachment 1 EI-3, Communications and Notification Procedure, Attachment 1 Also see Simulator Operator Instructions (later page of this document).
READ TO CANDIDATE DIRECTION TO CANDIDATE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
The Plant is in MODE 6 and fuel shuffles in progress, the following events occur:
All offsite power is lost o Buses 1C and 1D are reenergized by D/G 1-1 and D/G 1-2 respectively Air to the Steam Generator (S/G) nozzle dams was lost for several minutes and approximately 90 gallons of PCS drained to the Containment floor o Air to S/G nozzle dams has been restored: dams are no longer leaking Containment closure was established with the exception that the Equipment Hatch was not closed due to the hatch being inadvertently knocked off it's track Shutdown Cooling restoration is delayed and the PCS has risen to 212°F and PCS boil-off has commenced Rising counts indicated on RIA-2326 (Normal Range RGEM)
INITIATING CUES:
You are the Shift Manager (acting as the Emergency Plant Manager). You are to classify the event given the above information and complete the Event Notification Form. No previous event declaration has been made.
This JPM is Time Critical.
PALISADES NUCLEAR PLANT                     Page 3 of 9                       SEPTEMBER 2014
 
JPM SRO ADMIN 4 EVALUATOR CUE: Candidate may use placard of site emergency plan classifications or provide working copy of EI-1 SEP Supp 1.
Proc.Step                 TASK ELEMENT 1                                         STANDARD                   Grade
: 1. Determine the Category in which the Initiating Conditions/symptoms best fit from the list of Categories below:
A - Abnormal Rad Levels / Radiological Effluent EI-1 C - Cold Shutdown / Refueling System 6.1.b.1                                                        Refers to SEP Supp 1, MODE 5, 6, or DEF Malfunction                                                                                  S U page and determines Category C applies.
SEP E - Independent Spent Fuel Storage SUPP 1 Installation (ISFSI)
F - Fission Product Barrier Degradation H - Hazards S - System Malfunction Comment:
START TIME FOR CLASSIFICATION:_________
Proc.Step                 TASK ELEMENT 2                                           STANDARD                   Grade
___ Refers to CA4
: 2. Use the Category identified above and EI-1                                                         ___ Determines per Table C-3 that with SEP Supplement 1 to determine which 6.1.b.2 Emergency Action Level (EAL) threshold                   CONTAINMENT CLOSURE and PCS integrity not established that an          S U has been exceeded. Move from the highest SEP                                                              UNPLANNED event results in PCS classification (left) to lowest classification SUPP 1                                                              temperature > 200°F for > Table C-3 (right) when determining the classification.
duration Comment:
CRITICAL STEP PALISADES NUCLEAR PLANT                              Page 4 of 9                              SEPTEMBER 2014
 
JPM SRO ADMIN 4 Proc.Step              TASK ELEMENT 3                                       STANDARD                  Grade SEP                                                      Declares an Alert per CA4 based on status of Declares Emergency Classification.                                                            S U SUPP 1                                                    event.
Comment:
END TIME FOR CLASSIFICATION:_________ (START TIME FOR FORM COMPLETION)
CRITICAL STEP - must be performed within 15 minutes of start of JPM.
Proc.Step             TASK ELEMENT 4                                        STANDARD                   Grade EI-1
: b. Using the "Action" column of Attachment Obtains EI-1, Attachment 1 and performs or 6.2.b  1, perform each action as M (Mandatory), S                                                    S U delegates actions.
(Subsequent), or I (If Needed).
Att 1 Comment:
EVALUATOR CUE: Another SRO will perform this task.
PALISADES NUCLEAR PLANT                        Page 5 of 9                            SEPTEMBER 2014
 
JPM SRO ADMIN 4 Proc.Step                 TASK ELEMENT 5                                        STANDARD                   Grade Palisades Event Notification Form completely EI-3      Completes filling out Palisades Event            filled per attached KEY AND form is approved S U Att 1     Notification Form.                               (Candidate signature/initials, date, and time entered at bottom of form)
* Comment:
EVALUATOR CUE (provide when applicable as Candidate fills out form):
Hand Candidate EI-6.7 Attachment 1 (meteorological data)
It is a hot sunny day with no rain in the forecast EVALUATOR NOTE: KEY is attached to this JPM.
EVALUATOR NOTE: EI-3, Attachment 2, "Palisades Event Technical Data Sheet" is NOT required during this JPM.
EVALUATOR NOTE: If JPM is conducted in the Simulator, then Candidate may use computer on Control Room island area to prepare this form.
EVALUATOR NOTE: If JPM is conducted in the Simulator, then Candidate may use computer on back-bar of Control Room island area to complete and print this form.
* The following are the critical parts of this step:
ALERT is checked in "current classification" section Date and time filled in "current classification" section CA4.1 filled in "reason for classification" section OR Cold Shutdown/Refueling System Malfunction checked in "reason for classification" section YES checked in Radiological Release in Progress END TIME FOR FORM COMPLETION:_________
CRITICAL STEP (must be completed within 12 minutes of time listed in Task Element 3)
END OF TASK PALISADES NUCLEAR PLANT                              Page 6 of 9                              SEPTEMBER 2014
 
Proc No EI-3 Attachment 1 PALISADES EVENT NOTIFICATION FORM                                                      Revision 31 Page 1 of 1 Actual Event                                                                Drill Plant Contact Information Nuclear Power Plant: _________________________________________
Plant Communicator: __________________ Time of Communication: V.B. ______                                            1 S.O.M. ______
NRC ______      Plant Message Number Calling From:               Control Room                TSC              EOF          Other______
Call Back Telephone Number: _____________________________________________
Current Classification Unusual Event        Alert          Site Area Emergency                  General Emergency          Termination This Classification was declared as of:       Date: Today              Time: Within 15 minutes from start of JPM Reason for Classification Abnormal Rad Levels / Radiological Effluent                           System Malfunctions Hazards and Other Conditions Affecting                                Cold Shutdown / Refueling System Malfunction Plant Safety Independent Spent Fuel Storage Installation Events Fission Product Barrier Degradation IC Number:    CA4.1 Radiological Release in Progress Due to Event Yes                                  No Protective Action Recommendations None Evacuation of Areas(s):               1          2         3          4          5 In-Place Shelter of Area(s)            1          2        3          4          5 PAR based on:        Dose Calculation (Palisades Event Technical Data Sheet required)  Plant Status  Security Event Other ___________________________________________________________________________________________________
Meteorological Data Wind Direction (degrees): From 270              To 90                        Wind Speed (MPH):      12 Stability ClassB                                          Precipitation:        Yes     No Emergency Director Approval: ________________________________ Date: _________ Time: ________
ANSWER KEY PALISADES NUCLEAR PLANT                                  Page 7 of 9                                    SEPTEMBER 2014
 
JPM SRO ADMIN 4 SIMULATOR OPERATOR INSTRUCTIONS No Simulator setup required.
Prepare EI-6.7 Attachment 1 with the following data and then sign and date form:
o Wind Speed is 12 mph o Wind Direction is from 270 degrees o Stablity Class = B It is preferred that this JPM be done separately from the simulator. If, by chance, candidate IS in the simulator while doing this JPM, THEN ensure the IC does NOT have a release in progress.
ENSURE ALL DATA IS CLEARED FROM EP NOTIFICATION COMPUTER ON BACK-BAR OF CRS ISLAND PRIOR TO NEXT USE OF THIS JPM.
PALISADES NUCLEAR PLANT                  Page 8 of 9                      SEPTEMBER 2014
 
JPM SRO ADMIN 4 CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
The Plant is in MODE 6 and fuel shuffles in progress, the following events occur:
All offsite power is lost o Buses 1C and 1D are reenergized by D/G 1-1 and D/G 1-2 respectively Air to the Steam Generator (S/G) nozzle dams was lost for several minutes and approximately 90 gallons of PCS drained to the Containment floor o Air to S/G nozzle dams has been restored: dams are no longer leaking Containment closure was established with the exception that the Equipment Hatch was not closed due to the hatch being inadvertently knocked off it's track Shutdown Cooling restoration is delayed and the PCS has risen to 212°F and PCS boil-off has commenced Rising counts indicated on RIA-2326 (Normal Range RGEM)
INITIATING CUES:
You are the Shift Manager (acting as the Emergency Plant Manager). You are to classify the event given the above information and complete the Event Notification Form. No previous event declaration has been made.
This JPM is Time Critical.
PALISADES NUCLEAR PLANT                Page 9 of 9                    SEPTEMBER 2014
 
NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I/SRO-U SYS A TITLE: GRAVITY FEED BORATION WHILE SHUTDOWN CANDIDATE:
EXAMINER:
 
JPM SYSTEM A JOB PERFORMANCE MEASURE DATA PAGE Task:    Perform gravity feed boration to PCS while shutdown.
Alternate Path: YES Facility JPM #: NEW K/A:     004A4.07        Importance:      RO:        3.9    SRO:    3.7 K/A Statement: Ability to manually operate and/or monitor in the control room:
Boration/dilution.
Task Standard: Gravity feed at 33 gpm Charging flow for at least two minutes.
Preferred Evaluation Location: Simulator      ___X___    In Plant    _____
Preferred Evaluation Method:     Perform      ___X___    Simulate    _____


==References:==
==References:==
SOP-2AChemical and Volume Control System   Validation Time: 10 minutes Time Critical: NO   Candidate:   Time Start: ________ Time Finish: ________ Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______ Comments:     Examiner: _______________________________ Date: ______________ Signature JPM SYSTEM A  PALISADES NUCLEAR PLANT Page 3 of 10 SEPTEMBER 2014 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:   SOP-2A sections 7.1.1, 7.1.2, and 7.5.3 SOP-   ARP-4System Volume Level Pressure Scheme EK-07 (C- window 27 Also see Simulator Operator Instructions (later page of this document). READ TO CANDIDATE DIRECTION TO CANDIDATE: I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:   Plant is shutdown in MODE 6 with reactor cavity filled All three Charging Pumps are aligned for operation, have been operated within the last 12 hours, and their seal lube systems have been operated and placed in automatic Charging Pump P-55B has been started per SOP- g Gravity Feed Paths have been verified operable by a flow test INITIATING CUES: The CRS directs you to borate the PCS for two minutes using Charging Pump P-55B and the gravity feed method from Boric Acid Storage Tank T-53A per SOP-2A, 7.5.3.
SOP-2A, Chemical and Volume Control System Validation Time:   10 minutes       Time Critical: NO Candidate:
JPM SYSTEM A  PALISADES NUCLEAR PLANT Page 4 of 10 SEPTEMBER 2014 EVALUATOR CUE: Provide candidate with a working copy of SOP-2A front-end up to page 13 AND Section 7.5.3 (2 pages). Proc. Step TASK ELEMENT 1 STANDARD Grade 7.5.3.a ENSURE charging flow greater than 33 gpm as indicated by FIA-0212, Charging Line Flow Indicator Alarm. Candidate determines Charging Pump P-55B is in service and flow is above 33 gpm. S  U Comment:     Proc. Step TASK ELEMENT 2 STANDARD Grade 7.5.3.b OPEN Boric Acid Tank Gravity Feed Isolation Valve for tank(s) to be used: Candidate momentarily places handswitch for MO-2169 to OPEN and eventually observes Red light ON and Green light OFF. S  U Comment:   CRITICAL STEP   Proc. Step TASK ELEMENT 3 STANDARD Grade 7.5.3.c CLOSE CV-2155, Make-Up Stop. Candidate checks handswitch for CV-2155 in CLOSE and observes Red light OFF and Green light ON. S  U Comment:     Proc. Step TASK ELEMENT 4 STANDARD Grade 7.5.3.d CLOSE MO-2087, VCT T-54 Outlet. Candidate holds handswitch for MO-2087 to CLOSE and eventually observes Red light OFF and Green light ON. S  U Comment:   CRITICAL STEP JPM SYSTEM A  PALISADES NUCLEAR PLANT Page 5 of 10 SEPTEMBER 2014 Proc. Step TASK ELEMENT 5 STANDARD Grade -- Acknowledge alarm EK-0727 and EK-0735 and refers to ARP. Candidate acknowledges alarm on Panel C-02 and refers to ARP-4. S  U Comment:   EVALUATOR CUE: When candidate refers to ARP-4, then provide a working copy of ARP-4 Window 27 and Window 35 EVALUATOR NOTE: Alternate Path begins here: covered in task elements 6 and 7. Proc. Step TASK ELEMENT 6 STANDARD Grade -- Determine that Charging Pump P-55B has tripped. Candidate dispatches NPO to report on P-55B pump and breaker status. S  U Comment: EVALUATOR CUE: If candidate asks for direction on which procedure to use or action to take, then inform Candidate that CRS directs you to continue with the task. EVALUATOR CUE: If asked as NPO, report P-55B breaker is open (no overcurrent trips) and pump looks normal (not hot). EVALUATOR NOTE: If candidate does not send NPO to investigate P-55B status, then GO TO Task Element #8. EVALUATOR CUE: If requested, provide candidate with a working copy of SOP-2A section 7.1.1. Proc. Step TASK ELEMENT 7 STANDARD Grade --- Start Charging Pump Candidate places P-55B handswitch to TRIP and then back to START. Candidate observes Red light On and Green light Off for P-55B. S  U Comment:   EVALUATOR NOTE: Candidate may use SOP-2A section 7.1.1 to complete this action (not required to meet Task Standard). If this Task Element was performed, then GO TO Task Element #9. CRITICAL STEP JPM SYSTEM A  PALISADES NUCLEAR PLANT Page 6 of 10 SEPTEMBER 2014 Proc. Step TASK ELEMENT 8 STANDARD Grade --- Start Charging Pump Candidate starts P-55A or P-55C by placing respective handswitch to START. Candidate observes Red light On and Green light Off for Charging Pump that was started. S  U Comment:   EVALUATOR NOTE: Candidate may use SOP-2A section 7.1.1 to complete this action (not required to meet Task Standard). CRITICAL STEP   Proc. Step TASK ELEMENT 9 STANDARD Grade 7.5.3.e ENSURE CLOSED MO-2160, SIRWT T-58 Outlet To Charging Pp P-55A,B,C. Candidate observes MO-2160 Red light OFF and Green light ON. S  U Comment:       Proc. Step TASK ELEMENT 10 STANDARD Grade 7.5.3.f VERIFY charging flow greater the 33 gpm. Candidate observes FI-0212 flow on Panel C-02 above 33 gpm. S  U Comment:
Time Start: ________         Time Finish:     ________
JPM SYSTEM A  PALISADES NUCLEAR PLANT Page 7 of 10 SEPTEMBER 2014 Proc. Step TASK ELEMENT 11 STANDARD Grade 7.5.3.g.1 RESTORE from Gravity Feed Boration as follows: 1. OPEN desired suction source for Charging Pumps: (a) MO-2087, VCT T-54 Outlet After two minutes, candidate momentarily places handswitch for MO-2087 to OPEN and eventually observes Red light ON and Green light OFF. S  U Comment:  EVALUATOR CUE: Desired suction source is the VCT CRITICAL STEP    Proc. Step TASK ELEMENT 12 STANDARD Grade 7.5.3.g.2 ENSURE CLOSED: (a) MO-2169, BAST T-53A Gravity Feed Isolation. (b) MO-2170, BAST T-53B Gravity Feed Isolation Candidate momentarily places handswitch for MO-2169 to CLOSE and eventually observes Red light OFF and Green light ON. S  U Comment:   CRITICAL STEP   Proc. Step TASK ELEMENT 13 STANDARD Grade 7.5.3.g.3 IF continued boration from the SIRWT is desired, THEN FLUSH each Charging Pump from the SIRWT for at least five minutes. Candidate determines step is not applicable. S U Comment:
Performance Time:       ________ minutes Performance Rating:     SAT______       UNSAT ______
JPM SYSTEM A  PALISADES NUCLEAR PLANT Page 8 of 10 SEPTEMBER 2014 Proc. Step TASK ELEMENT 14 STANDARD Grade 7.5.3.g.4 IF continued boration from the VCT is desired, THEN FLUSH each Charging Pump from the VCT for at least five minutes. Candidate continues to operate Charging Pump for flush. S  U Comment:   EVALUATOR CUE: Flush is in progress and JPM is complete. END OF TASK JPM SYSTEM A  PALISADES NUCLEAR PLANT Page 9 of 10 SEPTEMBER 2014 SIMULATOR OPERATOR INSTRUCTIONS   Reset to IC-20 Create Event Trigger 1 to trip Charging Pump: o Event: .not.MO-2087 red light being OFF o Action: IMF CV03Brips P55B Create Event Trigger 2 to clear Charging Pump trip when pump restart is attempted: o Event: ZDI2P(69 is P-55B handswitch taken to TRIP o Action: DMF CV03B deletes P-55B trip malfunction Open Charging Line valves CV-2111, CV-2113, and CV-2115 Ensure open MO-2087, VCT Outlet Start P-55B FREEZE and SNAP into a saved IC JPM SYSTEM A  PALISADES NUCLEAR PLANT Page 10 of 10 SEPTEMBER 2014 CANDIDATE CUE SHEET   (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)   INITIAL CONDITIONS:   Plant is shutdown in MODE 6 with reactor cavity filled All three Charging Pumps are aligned for operation, have been operated within the last 12 hours, and their seal lube systems have been operated and placed in automatic Charging Pump P-55B has been started per SOP- 7.1.1.e.2 and g Gravity Feed Paths have been verified operable by a flow test INITIATING CUES: The CRS directs you to borate the PCS for two minutes using Charging Pump P-55B and the gravity feed method from Boric Acid Storage Tank T-53A per SOP-2A, 7.5.3.
Comments:
REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE     JPM: RO/SRO-I/SRO-U SYS B TITLE: MANUALLY INITIATE CONTAINMENT ISOLATION       CANDIDATE:   EXAMINER:
Examiner: _______________________________               Date:   ______________
JPM SYSTEM B PALISADES NUCLEAR PLANT Page 2 of 7 SEPTEMBER 2014  JOB PERFORMANCE MEASURE DATA PAGE   Task: Perform Containment Isolation initiation Alternate Path: NO Facility JPM #: BANK K/A: 103A2.03   Importance: RO: 3.5   SRO: 3.8 K/A Statement: Ability to (a) predict the impacts of the following malfunctions or operations on the containment system and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Phase A and B isolation Task Standard: Manual Containment Isolation initiated with all pathways having at least one isolation valve closed. Preferred Evaluation Location: Simulator __X__ In Plant _____ Preferred Evaluation Method: Perform __X__ Simulate _____
Signature PALISADES NUCLEAR PLANT                 Page 2 of 10                         SEPTEMBER 2014
 
JPM SYSTEM A EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:
SOP-2A, Chemical and Volume Control System sections 7.1.1, 7.1.2, and 7.5.3 SOP-1C, Primary Coolant System - Heatup section 7.1.1 ARP-4, Primary System Volume Level Pressure Scheme EK-07 (C-12) window 27 Also see Simulator Operator Instructions (later page of this document).
READ TO CANDIDATE DIRECTION TO CANDIDATE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
Plant is shutdown in MODE 6 with reactor cavity filled All three Charging Pumps are aligned for operation, have been operated within the last 12 hours, and their seal lube systems have been operated and placed in automatic Charging Pump P-55B has been started per SOP-1C, Primary Coolant System
        - Heatup steps 7.1.1.e.2 and g Gravity Feed Paths have been verified operable by a flow test INITIATING CUES:
The CRS directs you to borate the PCS for two minutes using Charging Pump P-55B and the gravity feed method from Boric Acid Storage Tank T-53A per SOP-2A, Chemical and Volume Control System, section 7.5.3.
PALISADES NUCLEAR PLANT                   Page 3 of 10                       SEPTEMBER 2014
 
JPM SYSTEM A EVALUATOR CUE: Provide candidate with a working copy of SOP-2A front-end up to page 13 AND Section 7.5.3 (2 pages).
Proc. Step             TASK ELEMENT 1                                       STANDARD                     Grade ENSURE charging flow greater than Candidate determines Charging Pump P-55B is 7.5.3.a  33 gpm as indicated by FIA-0212, Charging                                                       S U in service and flow is above 33 gpm.
Line Flow Indicator Alarm.
Comment:
Proc. Step             TASK ELEMENT 2                                       STANDARD                     Grade Candidate momentarily places handswitch for OPEN Boric Acid Tank Gravity Feed 7.5.3.b                                                 MO-2169 to OPEN and eventually observes Red      S U Isolation Valve for tank(s) to be used:
light ON and Green light OFF.
Comment:
CRITICAL STEP Proc. Step             TASK ELEMENT 3                                       STANDARD                     Grade Candidate checks handswitch for CV-2155 in 7.5.3.c   CLOSE CV-2155, Make-Up Stop.                   CLOSE and observes Red light OFF and Green       S U light ON.
Comment:
Proc. Step             TASK ELEMENT 4                                       STANDARD                     Grade Candidate holds handswitch for MO-2087 to 7.5.3.d   CLOSE MO-2087, VCT T-54 Outlet.               CLOSE and eventually observes Red light OFF     S U and Green light ON.
Comment:
CRITICAL STEP PALISADES NUCLEAR PLANT                         Page 4 of 10                               SEPTEMBER 2014
 
JPM SYSTEM A Proc. Step             TASK ELEMENT 5                                 STANDARD                   Grade Acknowledge alarm EK-0727 and EK-0735     Candidate acknowledges alarm on Panel C-02
    --                                                                                              S U and refers to ARP.                        and refers to ARP-4.
Comment:
EVALUATOR CUE: When candidate refers to ARP-4, then provide a working copy of ARP-4 Window 27 and Window 35 EVALUATOR NOTE: Alternate Path begins here: covered in task elements 6 and 7.
Proc. Step             TASK ELEMENT 6                                 STANDARD                   Grade Determine that Charging Pump P-55B has   Candidate dispatches NPO to report on P-55B
    --                                                                                              S U tripped.                                  pump and breaker status.
Comment:
EVALUATOR CUE: If candidate asks for direction on which procedure to use or action to take, then inform Candidate that CRS directs you to continue with the task.
EVALUATOR CUE: If asked as NPO, report P-55B breaker is open (no overcurrent trips) and pump looks normal (not hot).
EVALUATOR NOTE: If candidate does not send NPO to investigate P-55B status, then GO TO Task Element #8.
EVALUATOR CUE: If requested, provide candidate with a working copy of SOP-2A section 7.1.1.
Proc. Step             TASK ELEMENT 7                                 STANDARD                   Grade Candidate places P-55B handswitch to TRIP and then back to START.
  ---    Start Charging Pump                                                                      S U Candidate observes Red light On and Green light Off for P-55B.
Comment:
EVALUATOR NOTE: Candidate may use SOP-2A section 7.1.1 to complete this action (not required to meet Task Standard). If this Task Element was performed, then GO TO Task Element #9.
CRITICAL STEP PALISADES NUCLEAR PLANT                   Page 5 of 10                           SEPTEMBER 2014
 
JPM SYSTEM A Proc. Step             TASK ELEMENT 8                                     STANDARD                   Grade Candidate starts P-55A or P-55C by placing respective handswitch to START.
  ---    Start Charging Pump                                                                        S U Candidate observes Red light On and Green light Off for Charging Pump that was started.
Comment:
EVALUATOR NOTE: Candidate may use SOP-2A section 7.1.1 to complete this action (not required to meet Task Standard).
CRITICAL STEP Proc. Step             TASK ELEMENT 9                                     STANDARD                   Grade ENSURE CLOSED MO-2160, SIRWT T-58           Candidate observes MO-2160 Red light OFF 7.5.3.e                                                                                              S U Outlet To Charging Pp P-55A,B,C.           and Green light ON.
Comment:
Proc. Step           TASK ELEMENT 10                                     STANDARD                   Grade Candidate observes FI-0212 flow on Panel C-02 7.5.3.f   VERIFY charging flow greater the 33 gpm.                                                   S U above 33 gpm.
Comment:
PALISADES NUCLEAR PLANT                     Page 6 of 10                             SEPTEMBER 2014
 
JPM SYSTEM A Proc. Step           TASK ELEMENT 11                                     STANDARD                     Grade RESTORE from Gravity Feed Boration as follows:                                     After two minutes, candidate momentarily places handswitch for MO-2087 to OPEN and 7.5.3.g.1  1. OPEN desired suction source for                                                            S U eventually observes Red light ON and Green Charging Pumps:
light OFF.
(a) MO-2087, VCT T-54 Outlet Comment:
EVALUATOR CUE: Desired suction source is the VCT CRITICAL STEP Proc. Step            TASK ELEMENT 12                                    STANDARD                      Grade ENSURE CLOSED:
(a) MO-2169, BAST T-53A Gravity Feed         Candidate momentarily places handswitch for 7.5.3.g.2  Isolation.                                  MO-2169 to CLOSE and eventually observes         S U Red light OFF and Green light ON.
(b) MO-2170, BAST T-53B Gravity Feed Isolation Comment:
CRITICAL STEP Proc. Step           TASK ELEMENT 13                                     STANDARD                     Grade IF continued boration from the SIRWT is desired, THEN FLUSH each Charging 7.5.3.g.3                                              Candidate determines step is not applicable. S U Pump from the SIRWT for at least five minutes.
Comment:
PALISADES NUCLEAR PLANT                       Page 7 of 10                             SEPTEMBER 2014
 
JPM SYSTEM A Proc. Step           TASK ELEMENT 14                                     STANDARD                     Grade IF continued boration from the VCT is desired, THEN FLUSH each Charging            Candidate continues to operate Charging Pump 7.5.3.g.4                                                                                              S U Pump from the VCT for at least five           for flush.
minutes.
Comment:
EVALUATOR CUE: Flush is in progress and JPM is complete.
END OF TASK PALISADES NUCLEAR PLANT                       Page 8 of 10                             SEPTEMBER 2014
 
JPM SYSTEM A SIMULATOR OPERATOR INSTRUCTIONS Reset to IC-20 Create Event Trigger 1 to trip Charging Pump:
o Event: .not.ZLO2P(61).this is MO-2087 red light being OFF o Action: IMF CV03B..this trips P55B Create Event Trigger 2 to clear Charging Pump trip when pump restart is attempted:
o Event: ZDI2P(69)this is P-55B handswitch taken to TRIP o Action: DMF CV03B ..deletes P-55B trip malfunction Open Charging Line valves CV-2111, CV-2113, and CV-2115 Ensure open MO-2087, VCT Outlet Start P-55B FREEZE and SNAP into a saved IC PALISADES NUCLEAR PLANT               Page 9 of 10                   SEPTEMBER 2014
 
JPM SYSTEM A CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
Plant is shutdown in MODE 6 with reactor cavity filled All three Charging Pumps are aligned for operation, have been operated within the last 12 hours, and their seal lube systems have been operated and placed in automatic Charging Pump P-55B has been started per SOP-1C, Primary Coolant System
      - Heatup steps 7.1.1.e.2 and g Gravity Feed Paths have been verified operable by a flow test INITIATING CUES:
The CRS directs you to borate the PCS for two minutes using Charging Pump P-55B and the gravity feed method from Boric Acid Storage Tank T-53A per SOP-2A, Chemical and Volume Control System, section 7.5.3.
PALISADES NUCLEAR PLANT                Page 10 of 10                    SEPTEMBER 2014
 
REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I/SRO-U SYS B TITLE: MANUALLY INITIATE CONTAINMENT ISOLATION CANDIDATE:
EXAMINER:
 
JPM SYSTEM B JOB PERFORMANCE MEASURE DATA PAGE Task:   Perform Containment Isolation initiation Alternate Path: NO Facility JPM #: BANK K/A: 103A2.03             Importance:     RO: 3.5         SRO: 3.8 K/A Statement: Ability to (a) predict the impacts of the following malfunctions or operations on the containment system and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Phase A and B isolation Task Standard: Manual Containment Isolation initiated with all pathways having at least one isolation valve closed.
Preferred Evaluation Location: Simulator       __X__     In Plant   _____
Preferred Evaluation Method:       Perform     __X__     Simulate   _____


==References:==
==References:==
EOP-4.0, Loss of Coolant Accident     EOP Supplement 6, Checksheet for Containment Isolation and CCW Restoration Validation Time: 10 minutes Time Critical: NO   Candidate:   Time Start: ________ Time Finish: ________ Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______ Comments:     Examiner: _______________________________ Date: ______________ Signature JPM SYSTEM B PALISADES NUCLEAR PLANT Page 3 of 7 SEPTEMBER 2014 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:   EOP-4.0, LOCA Recovery, step 13   EOP Supplement 6, Checksheet for Containment Isolation and CCW Restoration Also see Simulator Operator Instructions (last page of this document). READ TO CANDIDATE DIRECTION TO CANDIDATE: I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:   A Loss of Coolant Accident has occurred. The Reactor has been tripped and EOP 1.0, "Standard Post Trip Actions" have been performed. Containment radiation is above 10 R/hr. Automatic Containment isolation has not occurred. INITIATING CUES:   During performance of EOP 4.0, "Loss of Coolant Accident Recovery", the Control Room Supervisor directs you to manually initiate Containment isolation, referring to Step 13.
EOP-4.0, Loss of Coolant Accident EOP Supplement 6, Checksheet for Containment Isolation and CCW Restoration Validation Time:     10 minutes       Time Critical: NO Candidate:
JPM SYSTEM B PALISADES NUCLEAR PLANT Page 4 of 7 SEPTEMBER 2014 Evaluator Cue: Provide candidate with a Working Copy of EOP-4.0, step 13. Proc. Step TASK ELEMENT 1 STANDARD Grade EOP-4.0, 13.a IF ANY of the following conditions exit: Containment pressure is greater than or equal to 4.0 psig Any operable Containment Radiation Monitor rises to 1 X 101 R/hr, THEN PERFORM ALL of the following: a. VERIFY (EK-1126) is alarmed -1126) has not alarmed. Either HIGH RADIATION INITIATE pushbuttons on Panel EC-13 pushed:  CHRL-CS  CHRR-CS  S  U Comment: Evaluator Note: Candidate verifies -1126) is in alarm once pushbutton is pushed, it is permissible, but not necessary, to push both pushbuttons. CRITICAL STEP    Proc. Step TASK ELEMENT 2 STANDARD Grade EOP-4.0, 13.b IF ANY of the following conditions exit: Containment pressure is greater than or equal to 4.0 psig Any operable Containment Radiation Monitor rises to 1 X 101 R/hr, THEN PERFORM ALL of the following: b. VERIFY Containment Isolation, Refer to EOP Supplement 6  EOP Supplement 6 obtained. S  U Comment:  Evaluator Note:  Candidate will attempt to use the laminated version of EOP Supplement 6. For exam security purposes, do NOT allow this. Provide candidate with a working copy of EOP Supplement 6.
Time Start: ________         Time Finish:     ________
JPM SYSTEM B PALISADES NUCLEAR PLANT Page 5 of 7 SEPTEMBER 2014 Proc. Step TASK ELEMENT 3 STANDARD Grade Supp.6, 1.0 ENSURE CLOSED all valves unless otherwise specified by the notes. Verifies that all valves closed as required, checking them off on the checklist, except for CWRT Vent Valves, CV-1064 and CV-1065. S  U Comment: Evaluator Note: Determining that the CWRT Vent Valves failed to close is the only action needed to satisfactorily perform this critical step. Evaluator Cue: If asked by candidate what should be done with CV-1064 and CV-1065, RESPONSE: direct candidate to perform EOP Supplement 6. Proc. Step TASK ELEMENT 4 STANDARD Grade Supp.6, 1.0 ENSURE CLOSED all valves unless otherwise specified by the notes. CWRT Vent Valves, CV-1064 and CV-1065 have failed to isolate,   Handswitches for both CV-1064 and CV-1065 are placed to close. CV-1064 is verified closed (green light on), CV-1065 remains open (red light on) S  U Comment: Evaluator Note: CV-1064 closes, CV-1065 remains open. Evaluator Note: Placing the handswitch for CV-1064 to close is the critical component of this step. Evaluator Cue: If asked by candidate, EOP Supplement 6 Step 2.0 is not required. CRITICAL STEP   Proc. Step TASK ELEMENT 5 STANDARD Grade n/a Report status of EOP Supplement 6 for Containment Isolation to the CRS. CRS informed of completion of EOP Supplement 6 and all containment isolation valves are closed, with the exception of CV-1065. S  U Comment:   END OF TASK JPM SYSTEM B PALISADES NUCLEAR PLANT Page 6 of 7 SEPTEMBER 2014 SIMULATOR OPERATOR INSTRUCTIONS (The following is for more than one JPM): Use IC 17 (100% power) Enter malfunction RC04 using Event Trigger 1 Trip Reactor and carry out all EOP 1.0 immediate actions Reduce Final Value of RC04 to 10 after SIAS Trip MFPs after SIAS Verify Containment Radiation is greater than 10R/hr on at least one Containment Area Radiation Monitor Place Letdown Orifice Stop valves to close Allow at least 10% level reduction in each BAST Simulator Setup: Event Number Event Action WORD DESCRIPTION 2 Zdi1p(731) Dmf wp03a Handswitch for CV-1064 in close 3 Zdi1p(696) Dmf ch05b Right channel CHR push button 4 Zdi1p(696) Dmf ch05a Right channel CHR push button 5 Zdi1p(689) Dmf ch05a Left channel CHR push button 6 Zdi1p(689) Dmf ch05b Left channel CHR push button Malfunction: Malfunction Title: Et: Delay: Location: Ramp: Value: RC04 PCS Leak 1 N/A PIDRC01 N/A 100 CH05A Auto Initiate Failure Left N/A N/A PIDCH01 N/A True CH05B Auto Initiate Failure Right N/A N/A PIDCH01 N/A True RC22 Failed Fuel Element 1 N/A PIDRC01 N/S 100 WP03A CV-1064 valve binding N/A N/A PIDWP01 N/A 100 WP03B CV-1065 valve binding N/A N/A PIDWP01 N/A 100 Overrides: Overrides Title:     NONE JPM SYSTEM B PALISADES NUCLEAR PLANT Page 7 of 7 SEPTEMBER 2014 CANDIDATE CUE SHEET   (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)   INITIAL CONDITIONS:   A Loss of Coolant Accident has occurred. The Reactor has been tripped and EOP 1.0, "Standard Post Trip Actions" have been performed. Containment radiation is above 10 R/hr. Automatic Containment isolation has not occurred. INITIATING CUES: During performance of EOP 4.0, "Loss of Coolant Accident Recovery", the Control Room Supervisor directs you to manually initiate Containment isolation, referring to Step 13.
Performance Time:         ________ minutes Performance Rating:       SAT______       UNSAT ______
NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE     JPM: RO/SRO-I SYS C TITLE: PERFORM POST RAS STEP 54 OF EOP-4.0       CANDIDATE:   EXAMINER:
Comments:
JPM SYSTEM C PALISADES NUCLEAR PLANT Page 2 of 9 SEPTEMBER 2014  JOB PERFORMANCE MEASURE DATA PAGE   Task: Perform Post RAS Step 54 of EOP-4.0 Alternate Path: NO Facility JPM #: NEW K/A: 006A4.07   Importance: RO: 4.4   SRO: 4.4 K/A Statement: Ability to manually operate and/or monitor in the control room: ECCS Pumps and valves Task Standard: All Charging Pumps stopped and at least one HPSI Pump remains in operation Preferred Evaluation Location: Simulator __X__ In Plant _____ Preferred Evaluation Method: Perform __X__ Simulate _____
Examiner: _______________________________                 Date:   ______________
Signature PALISADES NUCLEAR PLANT                   Page 2 of 7                     SEPTEMBER 2014
 
JPM SYSTEM B EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:
EOP-4.0, LOCA Recovery, step 13 EOP Supplement 6, Checksheet for Containment Isolation and CCW Restoration Also see Simulator Operator Instructions (last page of this document).
READ TO CANDIDATE DIRECTION TO CANDIDATE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
A Loss of Coolant Accident has occurred.
The Reactor has been tripped and EOP 1.0, "Standard Post Trip Actions" have been performed.
Containment radiation is above 10 R/hr.
Automatic Containment isolation has not occurred.
INITIATING CUES:
During performance of EOP 4.0, "Loss of Coolant Accident Recovery", the Control Room Supervisor directs you to manually initiate Containment isolation, referring to Step 13.
PALISADES NUCLEAR PLANT                     Page 3 of 7                     SEPTEMBER 2014
 
JPM SYSTEM B Evaluator Cue: Provide candidate with a Working Copy of EOP-4.0, step 13.
Proc. Step             TASK ELEMENT 1                                     STANDARD                 Grade IF ANY of the following conditions exit:
Containment pressure is greater         CIS INITIATED (EK-1126) has not alarmed.
than or equal to 4.0 psig Either HIGH RADIATION INITIATE pushbuttons Any operable Containment Radiation 1                on Panel EC-13 pushed:
EOP-          Monitor rises to 1 X 10 R/hr, S U 4.0, 13.a      THEN PERFORM ALL of the                           CHRL-CS following:
CHRR-CS
: a. VERIFY CIS INITIATED (EK-1126) is alarmed Comment:
Evaluator Note: Candidate verifies CIS INITIATED (EK-1126) is in alarm once pushbutton is pushed, it is permissible, but not necessary, to push both pushbuttons.
CRITICAL STEP Proc. Step            TASK ELEMENT 2                                      STANDARD                  Grade IF ANY of the following conditions exit:
Containment pressure is greater than or equal to 4.0 psig EOP Supplement 6 obtained.
Any operable Containment Radiation 1
EOP-           Monitor rises to 1 X 10 R/hr, THEN PERFORM ALL of the                                                                S U 4.0, 13.b following:
: b. VERIFY Containment Isolation, Refer to EOP Supplement 6 Comment:
Evaluator Note: Candidate will attempt to use the laminated version of EOP Supplement 6. For exam security purposes, do NOT allow this. Provide candidate with a working copy of EOP Supplement 6.
PALISADES NUCLEAR PLANT                         Page 4 of 7                           SEPTEMBER 2014
 
JPM SYSTEM B Proc. Step             TASK ELEMENT 3                                       STANDARD                       Grade ENSURE CLOSED all valves unless             Verifies that all valves closed as required, Supp.6,    otherwise specified by the notes.            checking them off on the checklist, except for       S U 1.0 CWRT Vent Valves, CV-1064 and CV-1065.
Comment:
Evaluator Note: Determining that the CWRT Vent Valves failed to close is the only action needed to satisfactorily perform this critical step.
Evaluator Cue: If asked by candidate what should be done with CV-1064 and CV-1065, RESPONSE: direct candidate to perform EOP Supplement 6.
Proc. Step             TASK ELEMENT 4                                       STANDARD                       Grade CWRT Vent Valves, CV-1064 and CV-1065 have ENSURE CLOSED all valves unless              failed to isolate, otherwise specified by the notes.                  Handswitches for both CV-1064 and Supp.6, CV-1065 are placed to close.                 S U 1.0 CV-1064 is verified closed (green light on),
CV-1065 remains open (red light on)
Comment:
Evaluator Note: CV-1064 closes, CV-1065 remains open.
Evaluator Note: Placing the handswitch for CV-1064 to close is the critical component of this step.
Evaluator Cue: If asked by candidate, EOP Supplement 6 Step 2.0 is not required.
CRITICAL STEP Proc. Step             TASK ELEMENT 5                                       STANDARD                       Grade Report status of EOP Supplement 6 for       CRS informed of completion of EOP Supplement n/a    Containment Isolation to the CRS.            6 and all containment isolation valves are closed,   S U with the exception of CV-1065.
Comment:
END OF TASK PALISADES NUCLEAR PLANT                       Page 5 of 7                                 SEPTEMBER 2014
 
JPM SYSTEM B SIMULATOR OPERATOR INSTRUCTIONS (The following is for more than one JPM):
Use IC 17 (100% power)
Enter malfunction RC04 using Event Trigger 1 Trip Reactor and carry out all EOP 1.0 immediate actions Reduce Final Value of RC04 to 10 after SIAS Trip MFPs after SIAS Verify Containment Radiation is greater than 10R/hr on at least one Containment Area Radiation Monitor Place Letdown Orifice Stop valves to close Allow at least 10% level reduction in each BAST Simulator Setup:
Event Number     Event               Action                 WORD DESCRIPTION 2               Zdi1p(731)         Dmf wp03a               Handswitch for CV-1064 in close 3               Zdi1p(696)         Dmf ch05b               Right channel CHR push button 4               Zdi1p(696)         Dmf ch05a               Right channel CHR push button 5               Zdi1p(689)         Dmf ch05a               Left channel CHR push button 6               Zdi1p(689)         Dmf ch05b               Left channel CHR push button Malfunction:     Malfunction Title:             Et: Delay: Location:     Ramp: Value:
RC04             PCS Leak                       1   N/A     PIDRC01       N/A     100 CH05A           Auto Initiate Failure Left     N/A N/A     PIDCH01       N/A     True CH05B           Auto Initiate Failure Right   N/A N/A     PIDCH01       N/A     True RC22             Failed Fuel Element           1   N/A     PIDRC01       N/S     100 WP03A           CV-1064 valve binding         N/A N/A     PIDWP01       N/A     100 WP03B           CV-1065 valve binding         N/A N/A     PIDWP01       N/A     100 Overrides:       Overrides Title:
NONE PALISADES NUCLEAR PLANT                 Page 6 of 7                   SEPTEMBER 2014
 
JPM SYSTEM B CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
A Loss of Coolant Accident has occurred.
The Reactor has been tripped and EOP 1.0, "Standard Post Trip Actions" have been performed.
Containment radiation is above 10 R/hr.
Automatic Containment isolation has not occurred.
INITIATING CUES:
During performance of EOP 4.0, "Loss of Coolant Accident Recovery", the Control Room Supervisor directs you to manually initiate Containment isolation, referring to Step 13.
PALISADES NUCLEAR PLANT              Page 7 of 7                        SEPTEMBER 2014
 
NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I SYS C TITLE: PERFORM POST RAS STEP 54 OF EOP-4.0 CANDIDATE:
EXAMINER:
 
JPM SYSTEM C JOB PERFORMANCE MEASURE DATA PAGE Task:   Perform Post RAS Step 54 of EOP-4.0 Alternate Path: NO Facility JPM #: NEW K/A: 006A4.07           Importance:     RO:       4.4         SRO:     4.4 K/A Statement: Ability to manually operate and/or monitor in the control room: ECCS Pumps and valves Task Standard: All Charging Pumps stopped and at least one HPSI Pump remains in operation Preferred Evaluation Location: Simulator     __X__     In Plant     _____
Preferred Evaluation Method:   Perform       __X__     Simulate     _____


==References:==
==References:==
EOP-4.0, Loss of Coolant Accident Recovery     EOP Supplement 39, Alternate Methods of Reducing PCS Pressure Validation Time: 8 minutes Time Critical: NO   Candidate:   Time Start: ________ Time Finish: ________ Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______ Comments:     Examiner: _______________________________ Date: ______________ Signature JPM SYSTEM C PALISADES NUCLEAR PLANT Page 3 of 9 SEPTEMBER 2014 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:     EOP-54 Also see Simulator Operator Instructions (later page of this document). READ TO CANDIDATE DIRECTION TO CANDIDATE: I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:   A LOCA has occurred The Plant has been tripped and EOP-1.0 have been completed EOP-4.0, Loss of Coolant Accident Recoveryis in progress SIS and CHP have actuated Pre-RAS and Post-RAS actions have been taken per EOP Supplement 42 Auxiliary Spray Valve, CV-2117, is INOPERABLE   INITIATING CUES: During performance of EOP-4.0, the Control Room Supervisor directs you to perform Step 54.
EOP-4.0, Loss of Coolant Accident Recovery EOP Supplement 39, Alternate Methods of Reducing PCS Pressure Validation Time:   8 minutes       Time Critical: NO Candidate:
JPM SYSTEM C PALISADES NUCLEAR PLANT Page 4 of 9 SEPTEMBER 2014 EVALUATOR CUE: Provide candidate a Working Copy of EOP-4.0, Step 54 SIMULATOR OPERATOR: Place simulator to RUN when candidate is ready to perform first task element. Proc. Step TASK ELEMENT 1 STANDARD Grade 54.a IF RAS is initiated, THEN PERFORM the following: a. IF BOTH HPSI Pumps are operating, THEN VERIFY total HPSI Pump flow greater than 100 gpm. Candidate observes the four HPSI flow indicators on Panel C-13 and concludes that less than 100 gpm total HPSI flow exists. S  U Comment:     EVALUATOR CUE: Provide candidate a Working Copy of EOP Supplement 39. Proc. Step TASK ELEMENT 2 STANDARD Grade 54..a.1 a.1 IF total HPSI Pump flow less than 100 gpm, THEN PERFORM ALL of the following: 1) STOP ALL Charging Pumps. Refer to EOP Supplement 39, "Alternate Methods of Reducing PCS Pressure," as needed to control PZR pressure. 2)  Candidate stops Charging Pumps P-55A, P-55B and P-55C. May place auto/manual handswitches on Panel C-12 to MANUAL (not required) o P-55B o P-55C  Trips P-55A, from Panel C-02 Trips P-55B from Panel C-02  Trips P-55C from Panel C-02 S  U Comment:  CRITICAL STEP JPM SYSTEM C PALISADES NUCLEAR PLANT Page 5 of 9 SEPTEMBER 2014 Proc. Step TASK ELEMENT 3 STANDARD Grade 54.a.1 and Supplement 39 a.1 IF total HPSI Pump flow less than 100 gpm, THEN PERFORM ALL of the following: 1) STOP ALL Charging Pumps. Refer to EOP Supplement 39, "Alternate Methods of Reducing PCS Pressure," as needed to control PZR pressure. 2) Candidate refers to EOP Supplement 39  Determines Section 1.0 applies  Verifies SI throttling criteria met for Degraded Containment conditions o PCS greater than the minimum subcooling curve on EOP Supplement 1 for degraded Containment conditions using Qualified CETs o Corrected PZR level is greater than 20% (40% for degraded Containment) and controlled o At least one S/G is available for PCS heat removal with corrected level being maintained or being restored to between 60% and 70% o Operable RVLMS channels indicate PCS level is greater than 102 inches above the bottom of fuel alignment plate (621'8") S  U Comment: EVALUATOR CUE:  Provide candidate a Working Copy of EOP Supplement 39 EVALUATOR CUE: If asked as CRS for preference of throttling HPSI Valves or stopping HPSI Pump, ask candidate for recommendation, then approve their recommendation. EVALUATOR NOTE: If candidate decides to stop a HPSI Pump, then GO TO Task Element #5.
Time Start: ________       Time Finish:     ________
JPM SYSTEM C PALISADES NUCLEAR PLANT Page 6 of 9 SEPTEMBER 2014 Proc. Step TASK ELEMENT 4 STANDARD Grade Supplement 39 a. Operate ANY of the following valves, one train at a time, to obtain the desired PZR level change: -3007 -3009 -3011 -3013 I Train 2 Loop 2B, MO-3062 -3064 -3066 -3068 Candidate closes HPSI Valves one at a time to lower PZR pressure/raise HPSI flow. S  U Comment:  EVALUATOR NOTE: When PCS pressure falls back below 1470 psia, then total HPSI flow will be above 100 gpm: IF SO, Then GO TO Task Element 6. CRITICAL STEP   Proc. Step TASK ELEMENT 5 STANDARD Grade 54.a.2 a.1 IF total HPSI Pump flow less than 100 gpm, THEN PERFORM ALL of the following: 1) 2) IF total HPSI Pump still has flow less than 100 gpm, THEN STOP one HPSI Pump. Candidate stops P-66A HPSI Pump. If HPSI Pump P-66B trip was attempted, candidate informs CRS of failure of P-66B to trip. S  U Comment:  EVALUATOR NOTE: HPSI Pump P-66B will not trip if selected; candidate must use HPSI Pump P-66A. CRITICAL STEP JPM SYSTEM C PALISADES NUCLEAR PLANT Page 7 of 9 SEPTEMBER 2014 Proc. Step TASK ELEMENT 6 STANDARD Grade 54.b IF one HPSI Pump is operating, THEN VERIFY the operating HPSI Pump has flow greater than 50 gpm. Candidate determines that HPSI flow and either: If greater than 50 gpm, then considers task complete OR If less than 50 gpm, then goes to RNO 54.b.1 S  U Comment: EVALUATOR NOTE: If PCS pressure falls back below 1485 psia, then total HPSI flow would be above 50 gpm: IF SO, Then GO TO Task Element 8 CRITICAL STEP(only if one HPSI Pump has already been tripped)   Proc. Step TASK ELEMENT 7 STANDARD Grade 54.b.1 IF the operating HPSI Pump has flow less than 50 gpm, THEN PERFORM ALL of the following: 1) STOP ALL Charging Pumps. Refer to EOP Supplement 39, "Alternate Methods of Reducing PCS Pressure," as needed to control PZR pressure. 2) IF the operating HPSI Pump still has flow less than 50 gpm, THEN STOP the HPSI Pump. 3) CONSULT with the TSC for further guidance. Candidate: determines Step 1) was previously completed Candidate dispatches NPO to manually trip P- Candidate informs CRS of TSC notification. S  U Comment:  EVALUATOR NOTE: If PCS pressure falls back below 1485 psia, then total HPSI flow would be above 50 gpm. (not critical since HPSI flow WILL rise to above 50 gpm) EVALUATOR CUE: If asked as NPO to trip P-66B breaker, acknowledge request   Proc. Step TASK ELEMENT 8 STANDARD Grade n/a NOTIFY the CRS that step 54 actions are completed. CRS NOTIFIED that step 54 contingency actions are completed. S U Comment:   EVALUATOR CUE: Repeat back notification. END OF TASK JPM SYSTEM C PALISADES NUCLEAR PLANT Page 8 of 9 SEPTEMBER 2014   SIMULATOR OPERATOR INSTRUCTIONS SIMULATOR SETUP:   Use IC-17 Enter the following malfunctions and overrides: MF/OR Description Location Event Delay Ramp Final  Value RC04 PCS Leak into Containment PIDRC01 1 0 0 100 ED01 Loss of Offsite Power PIDED03 1 0 0 N/A CV-2117 PZR Auxiliary Spray Valve handswitch PNLC02 none 0 0 OFF P-66B-1 HPSI P-66B Trip PNLC03 none 0 0 OFF               [Deoverride of HPSI Pump P-66B in setup is necessary since this is dominant pump in simulator model] Take simulator out of freeze, reactor should automatically trip: carry out the following actions: NOTE: total time for setup is over an hour. EOP 1.0 Immediate Actions. Perform pre RAS actions in EOP Supplement 42. When RAS occurs, then: o Perform post-RAS actions of EOP Supplement 42 (no major actions needed) o Reduce value for Malfunction RC04 to 7.5 with a 3 minute ramp time o Observe PZR refill towards solid conditions and PZR pressure rising to above 1460 psia: this will results in total HPSI flow approaching less than 100 gpm o Ensure total HPSI Flow indicated on Panel C-13 is less than 100 gpm Freeze simulator and take a snapshot.
Performance Time:       ________ minutes Performance Rating:     SAT______       UNSAT ______
JPM SYSTEM C PALISADES NUCLEAR PLANT Page 9 of 9 SEPTEMBER 2014 CANDIDATE CUE SHEET   (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)   INITIAL CONDITIONS:   A LOCA has occurred The Plant has been tripped and EOP-1.0 have been completed EOP-4.0, Loss of Coolant Accident Recoverygress  SIS and CHP have actuated Pre-RAS and Post-RAS actions have been taken per EOP Supplement 42 Auxiliary Spray Valve, CV-2117, is INOPERABLE   INITIATING CUES: During performance of EOP-4.0, the Control Room Supervisor directs you to perform Step 54.
Comments:
NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE     JPM: RO SYS D TITLE: BYPASS MSIV CLOSURE       CANDIDATE:   EXAMINER:
Examiner: _______________________________               Date:   ______________
JPM SYSTEM D PALISADES NUCLEAR PLANT Page 2 of 9 SEPTEMBER 2014  JOB PERFORMANCE MEASURE DATA PAGE   Task: Bypass MSIV Closure Alternate Path: YES Facility JPM #: 2012 NRC EXAM K/A: 039A4.01 Importance: RO: 2.9 SRO: 2.8 K/A Statement: Ability to manually operate and/or monitor in the control room: Main steam supply valves. Task Standard: Both MSIV Bypass Valves, MO-0501 and MO-0510, opened with S/G pressure less than 500 psia. Preferred Evaluation Location: Simulator ___X___ In Plant  _____ Preferred Evaluation Method: Perform  ___X___ Simulate _____ 
Signature PALISADES NUCLEAR PLANT                 Page 2 of 9                     SEPTEMBER 2014
 
JPM SYSTEM C EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:
EOP Supplement 39, Alternate Methods of Reducing PCS Pressure EOP-4.0, Loss of Coolant Accident Recovery, Step 54 Also see Simulator Operator Instructions (later page of this document).
READ TO CANDIDATE DIRECTION TO CANDIDATE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
A LOCA has occurred The Plant has been tripped and EOP-1.0, Standard Post Trip Actions, have been completed EOP-4.0, Loss of Coolant Accident Recovery, is in progress SIS and CHP have actuated Pre-RAS and Post-RAS actions have been taken per EOP Supplement 42 Auxiliary Spray Valve, CV-2117, is INOPERABLE INITIATING CUES:
During performance of EOP-4.0, the Control Room Supervisor directs you to perform Step 54.
PALISADES NUCLEAR PLANT                     Page 3 of 9                     SEPTEMBER 2014
 
JPM SYSTEM C EVALUATOR CUE: Provide candidate a Working Copy of EOP-4.0, Step 54 SIMULATOR OPERATOR: Place simulator to RUN when candidate is ready to perform first task element.
Proc. Step               TASK ELEMENT 1                                   STANDARD                       Grade IF RAS is initiated, THEN PERFORM the following:                                     Candidate observes the four HPSI flow indicators 54.a        a. IF BOTH HPSI Pumps are operating,       on Panel C-13 and concludes that less than       S U THEN VERIFY total HPSI Pump flow        100 gpm total HPSI flow exists.
greater than 100 gpm.
Comment:
EVALUATOR CUE: Provide candidate a Working Copy of EOP Supplement 39.
Proc. Step               TASK ELEMENT 2                                   STANDARD                       Grade Candidate stops Charging Pumps P-55A, P-55B and P-55C.
a.1 IF total HPSI Pump flow less than               May place auto/manual handswitches 100 gpm, THEN PERFORM ALL of the                     on Panel C-12 to MANUAL (not following:                                           required) 54..a.1      1) STOP ALL Charging Pumps. Refer to                   o  P-55B                              S U EOP Supplement 39, "Alternate Methods of Reducing PCS Pressure,"                   o  P-55C as needed to control PZR pressure.             Trips P-55A, from Panel C-02
: 2) .
Trips P-55B from Panel C-02 Trips P-55C from Panel C-02 Comment:
CRITICAL STEP PALISADES NUCLEAR PLANT                        Page 4 of 9                             SEPTEMBER 2014
 
JPM SYSTEM C Proc. Step             TASK ELEMENT 3                                   STANDARD                       Grade Candidate refers to EOP Supplement 39 Determines Section 1.0 applies Verifies SI throttling criteria met for Degraded Containment conditions o  PCS greater than the minimum subcooling curve on EOP a.1 IF total HPSI Pump flow less than                       Supplement 1 for degraded 100 gpm, THEN PERFORM ALL of the                             Containment conditions using following:                                                   Qualified CETs 54.a.1 and    1) STOP ALL Charging Pumps. Refer                   o  Corrected PZR level is greater Supplement        to EOP Supplement 39, "Alternate                       than 20% (40% for degraded        S U 39          Methods of Reducing PCS                               Containment) and controlled Pressure," as needed to control o  At least one S/G is available for PZR pressure.
PCS heat removal with
: 2)                                                     corrected level being maintained or being restored to between 60% and 70%
o  Operable RVLMS channels indicate PCS level is greater than 102 inches above the bottom of fuel alignment plate (621'8")
Comment:
EVALUATOR CUE: Provide candidate a Working Copy of EOP Supplement 39 EVALUATOR CUE: If asked as CRS for preference of throttling HPSI Valves or stopping HPSI Pump, ask candidate for recommendation, then approve their recommendation.
EVALUATOR NOTE: If candidate decides to stop a HPSI Pump, then GO TO Task Element #5.
PALISADES NUCLEAR PLANT                        Page 5 of 9                              SEPTEMBER 2014
 
JPM SYSTEM C Proc. Step                  TASK ELEMENT 4                                    STANDARD                        Grade
: a. Operate ANY of the following valves, one train at a time, to obtain the desired PZR level change:
* HPSI Train 1 Loop 1A, MO-3007
* HPSI Train 1 Loop 1B, MO-3009 Supplement
* HPSI Train 1 Loop 2A, MO-3011                  Candidate closes HPSI Valves one at a time to S U 39                                                          lower PZR pressure/raise HPSI flow.
* HPSI Train 1 Loop 2B, MO-3013
* HPSI Train 2 Loop 2B, MO-3062
* HPSI Train 2 Loop 2A, MO-3064
* HPSI Train 2 Loop 1B, MO-3066
* HPSI Train 2 Loop 1A, MO-3068 Comment:
EVALUATOR NOTE: When PCS pressure falls back below 1470 psia, then total HPSI flow will be above 100 gpm: IF SO, Then GO TO Task Element 6.
CRITICAL STEP Proc. Step                 TASK ELEMENT 5                                       STANDARD                         Grade a.1 IF total HPSI Pump flow less than 100 gpm, THEN PERFORM ALL of the following:                                       Candidate stops P-66A HPSI Pump.
54.a.2        1)                                           If HPSI Pump P-66B trip was attempted,              S U
: 2) IF total HPSI Pump still has flow less     candidate informs CRS of failure of P-66B to trip.
than 100 gpm, THEN STOP one HPSI Pump.
Comment:
EVALUATOR NOTE: HPSI Pump P-66B will not trip if selected; candidate must use HPSI Pump P-66A.
CRITICAL STEP PALISADES NUCLEAR PLANT                             Page 6 of 9                             SEPTEMBER 2014
 
JPM SYSTEM C Proc. Step             TASK ELEMENT 6                                       STANDARD                     Grade Candidate determines that HPSI flow and either:
IF one HPSI Pump is operating, THEN           If greater than 50 gpm, then considers task 54.b    VERIFY the operating HPSI Pump has flow       complete                                        S U greater than 50 gpm.                           OR If less than 50 gpm, then goes to RNO 54.b.1 Comment:
EVALUATOR NOTE: If PCS pressure falls back below 1485 psia, then total HPSI flow would be above 50 gpm: IF SO, Then GO TO Task Element 8 CRITICAL STEP(only if one HPSI Pump has already been tripped)
Proc. Step             TASK ELEMENT 7                                       STANDARD                     Grade IF the operating HPSI Pump has flow less than 50 gpm, THEN PERFORM ALL of the following:
: 1) STOP ALL Charging Pumps. Refer to           Candidate: determines Step 1) was previously EOP Supplement 39, "Alternate Methods of       completed Reducing PCS Pressure," as needed to 54.b.1                                                  Candidate dispatches NPO to manually trip        S U control PZR pressure.
P-66B at its breaker
: 2) IF the operating HPSI Pump still has flow less than 50 gpm, THEN STOP the HPSI           Candidate informs CRS of TSC notification.
Pump.
: 3) CONSULT with the TSC for further guidance.
Comment:
EVALUATOR NOTE: If PCS pressure falls back below 1485 psia, then total HPSI flow would be above 50 gpm. (not critical since HPSI flow WILL rise to above 50 gpm)
EVALUATOR CUE: If asked as NPO to trip P-66B breaker, acknowledge request Proc. Step             TASK ELEMENT 8                                       STANDARD                     Grade NOTIFY the CRS that step 54 actions are       CRS NOTIFIED that step 54 contingency actions n/a    completed.                                    are completed.
S U Comment:
EVALUATOR CUE: Repeat back notification.
END OF TASK PALISADES NUCLEAR PLANT                         Page 7 of 9                             SEPTEMBER 2014
 
JPM SYSTEM C SIMULATOR OPERATOR INSTRUCTIONS SIMULATOR SETUP:
Use IC-17 Enter the following malfunctions and overrides:
Final MF/OR                       Description                   Location       Event   Delay Ramp Value RC04         PCS Leak into Containment                       PIDRC01         1       0       0   100 ED01         Loss of Offsite Power                           PIDED03         1       0       0   N/A CV-2117       PZR Auxiliary Spray Valve handswitch             PNLC02       none       0       0   OFF P-66B-1       HPSI P-66B Trip                                 PNLC03       none       0       0   OFF
[Developers Note: override of HPSI Pump P-66B in setup is necessary since this is dominant pump in simulator model]
Take simulator out of freeze, reactor should automatically trip: carry out the following actions:
NOTE: total time for setup is over an hour.
EOP 1.0 Immediate Actions.
Perform pre RAS actions in EOP Supplement 42.
When RAS occurs, then:
o   Perform post-RAS actions of EOP Supplement 42 (no major actions needed) o   Reduce value for Malfunction RC04 to 7.5 with a 3 minute ramp time o   Observe PZR refill towards solid conditions and PZR pressure rising to above 1460 psia:
this will results in total HPSI flow approaching less than 100 gpm o   Ensure total HPSI Flow indicated on Panel C-13 is less than 100 gpm Freeze simulator and take a snapshot.
PALISADES NUCLEAR PLANT                         Page 8 of 9                           SEPTEMBER 2014
 
JPM SYSTEM C CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
A LOCA has occurred The Plant has been tripped and EOP-1.0, Standard Post Trip Actions, have been completed EOP-4.0, Loss of Coolant Accident Recovery, is in progress SIS and CHP have actuated Pre-RAS and Post-RAS actions have been taken per EOP Supplement 42 Auxiliary Spray Valve, CV-2117, is INOPERABLE INITIATING CUES:
During performance of EOP-4.0, the Control Room Supervisor directs you to perform Step 54.
PALISADES NUCLEAR PLANT                  Page 9 of 9                    SEPTEMBER 2014
 
NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO SYS D TITLE: BYPASS MSIV CLOSURE CANDIDATE:
EXAMINER:
 
JPM SYSTEM D JOB PERFORMANCE MEASURE DATA PAGE Task:   Bypass MSIV Closure Alternate Path: YES Facility JPM #: 2012 NRC EXAM K/A:     039A4.01       Importance:     RO:       2.9   SRO:     2.8 K/A Statement: Ability to manually operate and/or monitor in the control room: Main steam supply valves.
Task Standard: Both MSIV Bypass Valves, MO-0501 and MO-0510, opened with S/G pressure less than 500 psia.
Preferred Evaluation Location: Simulator      ___X___      In Plant    _____
Preferred Evaluation Method:    Perform      ___X___      Simulate    _____


==References:==
==References:==
GOP-   Validation Time: 25 minutes Time Critical: NO   Candidate:   Time Start: ________ Time Finish: ________ Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______ Comments:     Examiner: _______________________________ Date: ______________ Signature JPM SYSTEM D  PALISADES NUCLEAR PLANT Page 3 of 9 SEPTEMBER 2014 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:   GOP-  with GCL-9 completed through Step 3.6 and Step 2.15 circled but not slashed. ARP-erator and Rod Drives Scheme EK-09 (C- Also see Simulator Operator Instructions (later page of this document). READ TO CANDIDATE DIRECTION TO CANDIDATE: I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:   Plant cooldown via the Turbine Bypass Valve, CV-0511, is in-progress per GOP-9, MODE 3   525°F to MODE 4 or MODE 5. S/G pressures are approximately 560 psia. INITIATING CUES: During performance of GOP-MODE 3   525°F to MODE 4 or MODE 5, the CRS directs you to block open the MSIVs per step 3.7 and verify block is successful as S/G pressure continues to lower.
GOP-9, MODE 3  525°F to MODE 4 or MODE 5 Validation Time:     25 minutes     Time Critical:     NO Candidate:
JPM SYSTEM D  PALISADES NUCLEAR PLANT Page 4 of 9 SEPTEMBER 2014 EVALUATOR CUE: Provide candidate with a working copy of GOP-9 with GCL-9 completed through Step 3.3 and Step 2.14 circled but not slashed. Proc. Step TASK ELEMENT 1 STANDARD Grade 3.7 WHEN 3 of 4 associated Steam Generator pressure sigmas indicate between 510 and 550 psia and the indicator is between alarm flags, THEN DEPRESS the associated pushbutton to bypass MSIV closure:  HS/LPE-50A, BYPASS OF MSIV CLOSURE pushbutton HS/LPE-50A, BYPASS OF MSIV CLOSURE pushbutton depressed S  U Comment:   EVALUATOR NOTE: Alarm EK-0970, Steam Gen Valves Isolation Lockout, will alarm when at least one MSIV auto block signal has been blocked (i.e. blocking second MSIV does not change alarm status or cause it to reflash). EVALUATOR NOTE: Candidate can perform Task Elements 1 and 2 in any order and may perform Task Element 3 as soon as alarm occurs. Proc. Step TASK ELEMENT 2 STANDARD Grade 3.7 WHEN 3 of 4 associated Steam Generator pressure sigmas indicate between 510 and 550 psia and the indicator is between alarm flags, THEN DEPRESS the associated pushbutton to bypass MSIV closure:  HS/LPE-50B, BYPASS OF MSIV CLOSURE pushbutton HS/LPE-50B, BYPASS OF MSIV CLOSURE pushbutton depressed S  U Comment:   EVALUATOR NOTE: Alarm EK-0970, Steam Gen Valves Isolation Lockout, will alarm when at least one MSIV auto block signal has been blocked (i.e. blocking second MSIV does not change alarm status or cause it to reflash).
Time Start: ________         Time Finish:     ________
JPM SYSTEM D  PALISADES NUCLEAR PLANT Page 5 of 9 SEPTEMBER 2014 Proc. Step TASK ELEMENT 3 STANDARD Grade ---- Acknowledge alarm EK-0970 and refer to ARP. Candidate acknowledges alarm on Panel C-02 and refers to ARP-5. S  U Comment:   EVALUATOR CUE: Provide a working copy of ARP-5 Window 70 EVALUATOR NOTE: Alternate Path begins here and is covered in task elements 4 through 6 Proc. Step TASK ELEMENT 4 STANDARD Grade ---- Determine that both MSIVs auto closed when 2/4 S/G pressures on either S/G went below 500 psia. Candidate determines that both MSIVs have closed. S  U Comment: EVALUATOR CUE: If candidate asks for direction on which procedure to use or action to take, then ask Candidate what they would recommend and the basis for this recommendation: Candidate Responses: 1. Continue with cooldown using Turbine Bypass Valve and opening MSIV bypasses (basis= equivalent to previous method in-loose water inventory) OR use Atmospheric Steam Dump Valves (basis = quicker method but loose water inventory and make noise to environment) EVALUATOR Response: Use procedures and continue the plant cooldown using your recommended method (CV-0511, Turbine Bypass Valve via MSIV Bypass Valves OR using Atmospheric Steam Dump Valves EVALUATOR CUE: If candidate asks for Vacuum Pump to be placed in service, acknowledge request and state that this has been completed. EVALUATOR NOTE: GOP-9 Steps 2.13.b thru d are N/A. EVALUATOR NOTE: If Candidate is using Turbine Bypass Valve, then GO TO Task Element #6 JPM SYSTEM D  PALISADES NUCLEAR PLANT Page 6 of 9 SEPTEMBER 2014 Proc. Step TASK ELEMENT 5 STANDARD Grade 2.13.e OPERATE ASDVs as necessary to maintain PCS temperature. Candidate operates ADV Controller HIC-0781A as needed to continue PCS cooldown at rate at or below 60F/Hr S U Comment:   EVALUATOR NOTE: If Candidate attempts to perform GOP-9 step 2.13.f (perform GOP-9.0 section 5.0 actions): inform candidate that another operator will complete this task. EVALUATOR NOTE: If this Task Element is performed, then GO TO Task Element 8. CRITICAL STEP   Proc. Step TASK ELEMENT 6 STANDARD Grade 2.15 ENSURE OPEN both MSIV Bypass Valves: MO-0501, MSIV CV-0501 Bypass MO-0510, MSIV CV-0510 Bypass Candidate opens MSIV Bypass Valve  MO-0501 S  U Comment:   EVALUATOR NOTE: Candidate may close CV-0511 with PIC-0511 prior to opening the MSIV Bypass Valves. EVALUATOR NOTE: Order in which candidate opens MSIV bypass valves is not critical. CRITICAL STEP   Proc. Step TASK ELEMENT 7 STANDARD Grade 2.15 ENSURE OPEN both MSIV Bypass Valves: MO-0501, MSIV CV-0501 Bypass MO-0510, MSIV CV-0510 Bypass Candidate opens MSIV Bypass Valve:  MO-0510 S  U Comment:  EVALUATOR NOTE: Candidate may close CV-0511 with PIC-0511 prior to opening the MSIV Bypass Valves. EVALUATOR NOTE: Order in which candidate opens MSIV bypass valves is not critical. CRITICAL STEP JPM SYSTEM D  PALISADES NUCLEAR PLANT Page 7 of 9 SEPTEMBER 2014   Proc. Step TASK ELEMENT 8 STANDARD Grade N/A Notify CRS that either 1)both MSIV Bypass Valves are open and cooldown is continuing via TBV OR 2) ADVs are being used to continue plant cooldown. CRS notified. S  U Comment:     END OF TASK JPM SYSTEM D  PALISADES NUCLEAR PLANT Page 8 of 9 SEPTEMBER 2014 SIMULATOR OPERATOR INSTRUCTIONS   Reset to IC-11. Insert override for zdi3p(174) to OFF (this is CV-0501-BYP, Bypass of MSIV Closure on -01). Trip the reactor. Fully open both MSIV Bypass Valves and then latch both using remotes MS25 and MS36 on PID MS02. Commence a 60°/hr cooldown using CV-0511, TBV. Close both MSIV Bypass Valves. Annotate/perform other GOP-9 activities up to step 3.7. FREEZE when S/G pressures are approximately 555 psia (on sigmas) or 540 psia (on PPC) and SNAP into a saved IC.
Performance Time:       ________ minutes Performance Rating:     SAT______       UNSAT ______
JPM SYSTEM D  PALISADES NUCLEAR PLANT Page 9 of 9 SEPTEMBER 2014 CANDIDATE CUE SHEET   (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)   INITIAL CONDITIONS:   Plant cooldown via the Turbine Bypass Valve, CV-0511, is in-progress per GOP-9, MODE 3   525°F   S/G pressures are approximately 560 psia. INITIATING CUES: During performance of GOP-MODE 3   525°F to MODE 4 or MODE 5, the CRS directs you to block open the MSIVs per step 3.7 and verify block is successful as S/G pressure continues to lower.
Comments:
NRC REGION III  INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE     JPM: RO/SRO-I/SRO-U SYS E TITLE: ALIGN CONTAINMENT AIR COOLERS       CANDIDATE:   EXAMINER:
Examiner: _______________________________                 Date:   ______________
JPM SYSTEM E PALISADES NUCLEAR PLANT Page 2 of 11 SEPTEMBER 2014  JOB PERFORMANCE MEASURE DATA PAGE Task: Alignment of Containment Air Coolers following fan maintenance Alternate Path: NO Facility JPM #: 2012 NRC EXAM K/A: 022A1.04 Importance: RO: 3.2   SRO: 3.3 K/A Statement: Ability to predict and/or monitor changes in parameters (to prevent exceeding design limits) associated with operating the CCS controls including: Cooling water flow Task Standard: All four Containment Air Cooling System aligned per SOP-5. Third Service Water Pump started. Preferred Evaluation Location: Simulator __X__ In Plant _____ Preferred Evaluation Method: Perform __X__ Simulate _____
Signature PALISADES NUCLEAR PLANT                 Page 2 of 9                           SEPTEMBER 2014
 
JPM SYSTEM D EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:
GOP-9, MODE 3  525°F to MODE 4 or MODE 5 with GCL-9 completed through Step 3.6 and Step 2.15 circled but not slashed.
ARP-5, Primary Coolant Pump Steam Generator and Rod Drives Scheme EK-09 (C-12)
Also see Simulator Operator Instructions (later page of this document).
READ TO CANDIDATE DIRECTION TO CANDIDATE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
Plant cooldown via the Turbine Bypass Valve, CV-0511, is in-progress per GOP-9, MODE 3 525°F to MODE 4 or MODE 5.
S/G pressures are approximately 560 psia.
INITIATING CUES:
During performance of GOP-9, MODE 3 525°F to MODE 4 or MODE 5, the CRS directs you to block open the MSIVs per step 3.7 and verify block is successful as S/G pressure continues to lower.
PALISADES NUCLEAR PLANT                     Page 3 of 9                       SEPTEMBER 2014
 
JPM SYSTEM D EVALUATOR CUE: Provide candidate with a working copy of GOP-9 with GCL-9 completed through Step 3.3 and Step 2.14 circled but not slashed.
Proc. Step             TASK ELEMENT 1                                   STANDARD               Grade WHEN 3 of 4 associated Steam Generator pressure sigmas indicate between 510 and 550 psia and the indicator is between alarm flags, THEN DEPRESS the               HS/LPE-50A, BYPASS OF MSIV CLOSURE 3.7    associated pushbutton to bypass MSIV                                                  S U pushbutton depressed closure:
HS/LPE-50A, BYPASS OF MSIV CLOSURE pushbutton Comment:
EVALUATOR NOTE: Alarm EK-0970, Steam Gen Valves Isolation Lockout, will alarm when at least one MSIV auto block signal has been blocked (i.e. blocking second MSIV does not change alarm status or cause it to reflash).
EVALUATOR NOTE: Candidate can perform Task Elements 1 and 2 in any order and may perform Task Element 3 as soon as alarm occurs.
Proc. Step             TASK ELEMENT 2                                   STANDARD               Grade WHEN 3 of 4 associated Steam Generator pressure sigmas indicate between 510 and 550 psia and the indicator is between alarm flags, THEN DEPRESS the               HS/LPE-50B, BYPASS OF MSIV CLOSURE 3.7    associated pushbutton to bypass MSIV                                                  S U pushbutton depressed closure:
HS/LPE-50B, BYPASS OF MSIV CLOSURE pushbutton Comment:
EVALUATOR NOTE: Alarm EK-0970, Steam Gen Valves Isolation Lockout, will alarm when at least one MSIV auto block signal has been blocked (i.e. blocking second MSIV does not change alarm status or cause it to reflash).
PALISADES NUCLEAR PLANT                       Page 4 of 9                       SEPTEMBER 2014
 
JPM SYSTEM D Proc. Step             TASK ELEMENT 3                                   STANDARD                   Grade Acknowledge alarm EK-0970 and refer to     Candidate acknowledges alarm on Panel C-02
  ----                                                                                              S U ARP.                                      and refers to ARP-5.
Comment:
EVALUATOR CUE: Provide a working copy of ARP-5 Window 70 EVALUATOR NOTE: Alternate Path begins here and is covered in task elements 4 through 6 Proc. Step             TASK ELEMENT 4                                   STANDARD                   Grade Determine that both MSIVs auto closed     Candidate determines that both MSIVs have
  ----      when 2/4 S/G pressures on either S/G       closed.                                      S U went below 500 psia.
Comment:
EVALUATOR CUE: If candidate asks for direction on which procedure to use or action to take, then ask Candidate what they would recommend and the basis for this recommendation:
Candidate Responses: 1. Continue with cooldown using Turbine Bypass Valve and opening MSIV bypasses (basis= equivalent to previous method in-use, wont loose water inventory)
OR use Atmospheric Steam Dump Valves (basis = quicker method but loose water inventory and make noise to environment)
EVALUATOR Response: Use procedures and continue the plant cooldown using your recommended method (CV-0511, Turbine Bypass Valve via MSIV Bypass Valves OR using Atmospheric Steam Dump Valves EVALUATOR CUE: If candidate asks for Vacuum Pump to be placed in service, acknowledge request and state that this has been completed.
EVALUATOR NOTE: GOP-9 Steps 2.13.b thru d are N/A.
EVALUATOR NOTE: If Candidate is using Turbine Bypass Valve, then GO TO Task Element #6 PALISADES NUCLEAR PLANT                       Page 5 of 9                           SEPTEMBER 2014
 
JPM SYSTEM D Proc. Step           TASK ELEMENT 5                               STANDARD                     Grade Candidate operates ADV Controller HIC-0781A OPERATE ASDVs as necessary to 2.13.e                                            as needed to continue PCS cooldown at rate at S U maintain PCS temperature.
or below 60F/Hr Comment:
EVALUATOR NOTE: If Candidate attempts to perform GOP-9 step 2.13.f (perform GOP-9.0 section 5.0 actions): inform candidate that another operator will complete this task.
EVALUATOR NOTE: If this Task Element is performed, then GO TO Task Element 8.
CRITICAL STEP Proc. Step           TASK ELEMENT 6                               STANDARD                     Grade ENSURE OPEN both MSIV Bypass Valves:                                 Candidate opens MSIV Bypass Valve 2.15                                                                                            S U MO-0501, MSIV CV-0501 Bypass           MO-0501 MO-0510, MSIV CV-0510 Bypass Comment:
EVALUATOR NOTE: Candidate may close CV-0511 with PIC-0511 prior to opening the MSIV Bypass Valves.
EVALUATOR NOTE: Order in which candidate opens MSIV bypass valves is not critical.
CRITICAL STEP Proc. Step           TASK ELEMENT 7                               STANDARD                     Grade ENSURE OPEN both MSIV Bypass Valves:                                 Candidate opens MSIV Bypass Valve:
2.15                                                                                            S U MO-0501, MSIV CV-0501 Bypass           MO-0510 MO-0510, MSIV CV-0510 Bypass Comment:
EVALUATOR NOTE: Candidate may close CV-0511 with PIC-0511 prior to opening the MSIV Bypass Valves.
EVALUATOR NOTE: Order in which candidate opens MSIV bypass valves is not critical.
CRITICAL STEP PALISADES NUCLEAR PLANT                   Page 6 of 9                           SEPTEMBER 2014
 
JPM SYSTEM D Proc. Step           TASK ELEMENT 8                               STANDARD               Grade Notify CRS that either 1)both MSIV Bypass Valves are open and N/A    cooldown is continuing via TBV OR         CRS notified.                          S U
: 2) ADVs are being used to continue plant cooldown.
Comment:
END OF TASK PALISADES NUCLEAR PLANT                     Page 7 of 9                     SEPTEMBER 2014
 
JPM SYSTEM D SIMULATOR OPERATOR INSTRUCTIONS Reset to IC-11.
Insert override for zdi3p(174) to OFF (this is CV-0501-BYP, Bypass of MSIV Closure on Low SG Press, SG B Bypass pushbutton on Panel C-01).
Trip the reactor.
Fully open both MSIV Bypass Valves and then latch both MSIVs using remotes MS25 and MS36 on PID MS02.
Commence a 60°/hr cooldown using CV-0511, TBV.
Close both MSIV Bypass Valves.
Annotate/perform other GOP-9 activities up to step 3.7.
FREEZE when S/G pressures are approximately 555 psia (on sigmas) or 540 psia (on PPC) and SNAP into a saved IC.
PALISADES NUCLEAR PLANT                 Page 8 of 9                   SEPTEMBER 2014
 
JPM SYSTEM D CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
Plant cooldown via the Turbine Bypass Valve, CV-0511, is in-progress per GOP-9, MODE 3 525°F to MODE 4 or MODE 5.
S/G pressures are approximately 560 psia.
INITIATING CUES:
During performance of GOP-9, MODE 3 525°F to MODE 4 or MODE 5, the CRS directs you to block open the MSIVs per step 3.7 and verify block is successful as S/G pressure continues to lower.
PALISADES NUCLEAR PLANT                Page 9 of 9                        SEPTEMBER 2014
 
NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I/SRO-U SYS E TITLE: ALIGN CONTAINMENT AIR COOLERS CANDIDATE:
EXAMINER:
 
JPM SYSTEM E JOB PERFORMANCE MEASURE DATA PAGE Task:   Alignment of Containment Air Coolers following fan maintenance Alternate Path: NO Facility JPM #: 2012 NRC EXAM K/A:     022A1.04       Importance:     RO:     3.2       SRO:   3.3 K/A Statement: Ability to predict and/or monitor changes in parameters (to prevent exceeding design limits) associated with operating the CCS controls including: Cooling water flow Task Standard: All four Containment Air Cooling System aligned per SOP-5. Third Service Water Pump started.
Preferred Evaluation Location: Simulator     __X__       In Plant   _____
Preferred Evaluation Method:     Perform     __X__       Simulate   _____


==References:==
==References:==
SOP-5, Containment Air Cooling Validation Time: 10 minutes Time Critical: NO   Candidate:   Time Start: ________ Time Finish: ________ Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______ Comments:     Examiner: _______________________________ Date: ______________ Signature JPM SYSTEM E PALISADES NUCLEAR PLANT Page 3 of 11 SEPTEMBER 2014 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:   SOP-5,   Also see Simulator Operator Instructions (later page of this document). READ TO CANDIDATE DIRECTION TO CANDIDATE: I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:   The plant is operating at steady state 100% power. VHX-1 Cooling Fans V-1A and V-1B are OFF with Service Water isolated. VHX-4 Cooling Fans V-4A and V-4B are OFF with Service Water isolated. All CAC Outlet Bypass Valves are properly aligned per SOP-Cooling, step 7.1.1.b.1 table. INITIATING CUES: The Control Room Supervisor has directed you to align the Containment Air Cooling System to its normal alignment per SOP-5, section 7.1.1 with all fans operating and all inlet and high capacity valves open.
SOP-5, Containment Air Cooling Validation Time:     10 minutes     Time Critical:   NO Candidate:
JPM SYSTEM E PALISADES NUCLEAR PLANT Page 4 of 11 SEPTEMBER 2014 EVALUATOR CUE: Provide candidate with a working copy of SOP-5 (entire procedure) Proc.Step TASK ELEMENT 1 STANDARD Grade 7.1.1.a REFER TO Step 5.2.3 for guidance on Service Water Pump operation. Candidate refers to step 5.2.3 for guidance on SW pump operation. S U Comment: EVALUATOR CUE: If asked whether a third Service Water Pump should be started, state that, "If possible, operate with two Service Water Pumps."   EVALUATOR NOTE: Order of valve alignment and fan starts is not critical. Proc.Step TASK ELEMENT 2 STANDARD Grade 7.1.1 b.1 ENSURE control valves are positioned as follows: For VHX-4, verify open Inlet Valve CV-0869. CV-0869 is verified open. S  U Comment:    EVALUATOR NOTE: Service Water Pump discharge pressure has been setup low and will lower further when CAC high capacity valves are opened. Proc.Step TASK ELEMENT 3 STANDARD Grade 7.1.1 b.1 ENSURE control valves are positioned as follows: For VHX-4, open High Capacity Outlet Valve CV-0867. High Capacity Outlet Valve CV-0867 is opened. S  U Comment:   CRITICAL STEP JPM SYSTEM E PALISADES NUCLEAR PLANT Page 5 of 11 SEPTEMBER 2014 Proc.Step TASK ELEMENT 4 STANDARD Grade 7.1.1 b.1 ENSURE control valves are positioned as follows: For VHX-1 verify Open Inlet Valve CV-0862. Inlet Valve CV-0862 is verified open. S U Comment:  EVALUATOR NOTE: Will receive EDG Trouble Alarms on Panel C-11 after Service Water Pump start. EVALUATOR NOTE: This step may be performed AFTER Service Water Pump start. Proc.Step TASK ELEMENT 5 STANDARD Grade 7.1.1 b.1 ENSURE control valves are positioned as follows: For VHX-1 open High Capacity Outlet Valve CV-0861. High Capacity Outlet Valve CV-0861 is opened. S  U Comment:   EVALUATOR NOTE: This step may be performed AFTER Service Water Pump start. CRITICAL STEP   Proc.Step TASK ELEMENT 6 STANDARD Grade 5.2.3 Monitor Service Water Header pressure and determine that Service Water system pressure is < 50 psig. Determines that the Standby Service Water Pump P-7C needs to be started because system pressure has lowered to < 50 psig. May need to respond to alarms EK-0551 and EK-0557: Has AO investigate D/G local alarm boards. S  U Comment:   EVALUATOR CUE: When asked as AO report that D/G local alarm panels indicate low raw water pressure. Reading is 24 psig if asked.
Time Start: ________         Time Finish:   ________
JPM SYSTEM E PALISADES NUCLEAR PLANT Page 6 of 11 SEPTEMBER 2014 Proc.Step TASK ELEMENT 7 STANDARD Grade n/a Obtain SOP-15, Service Water System procedure, section 7.1.1. Locates SOP-15, Service Water System procedure. S U Comment:   EVALUATOR CUE: Provide candidate with a working copy of SOP-15, section 7.1.1. Proc.Step TASK ELEMENT 8 STANDARD Grade SOP-15 7.1.1.a IF starting the first Service Water Pump, THEN GO TO Section 7.1.5. Candidate determines this step is N/A. S U Comment:       Proc.Step TASK ELEMENT 9 STANDARD Grade SOP-15 7.1.1.b IF starting the third Service Water Pump, THEN NOTIFY Chemistry so that they can recalculate mixing basin discharge flow volume. Notify Chemistry to recalculate Mixing Basin discharge flow volume. S  U Comment:   EVALUATOR CUE: CRS will notify Chemistry of P-7C start so they can recalculate mixing basin discharge flow volume. Proc.Step TASK ELEMENT 10 STANDARD Grade SOP-15 7.1.1.c ENSURE OPEN associated pump discharge valve:  P-7C  MV-SW104 Dispatch AO to check OPEN P-7C discharge valve MV-SW104. S U Comment:   EVALUATOR (or Simulator Operator) CUE: "MV-SW104 is OPEN" JPM SYSTEM E PALISADES NUCLEAR PLANT Page 7 of 11 SEPTEMBER 2014 Proc.Step TASK ELEMENT 11 STANDARD Grade SOP-15 7.1.1.d ENSURE motor oil levels normal. Dispatch AO to check P-7C motor oil levels normal. S U Comment:   EVALUATOR (or Simulator Operator) CUE: "P-7C Motor oil levels normal"   Proc.Step TASK ELEMENT 12 STANDARD Grade SOP-15 7.1.1.e Remove P-7C from standby by placing Control Switch to TRIP. P-7C Control Switch placed momentarily in TRIP until standby light extinguishes. S  U Comment:       Proc.Step TASK ELEMENT 13 STANDARD Grade SOP-15 7.1.1.f START desired pump from Control Room Handswitch (preferred) or using Handswitch on breaker. P-7C control switch placed in START and released to mid-position. S  U Comment:   SIMULATOR OPERATOR: Call in as AO and report that SW Pump P-7C local discharge pressure is 73 psig, and packing leakoff is not excessive. If asked, report that P-7C Basket Strainer DP is 4 psid. EVALUATOR NOTE: EK-1144, P-7C Basket Strainer HI dP may alarm and then clear after pump start: candidate should reference ARP-7, but no actions are required. CRITICAL STEP JPM SYSTEM E PALISADES NUCLEAR PLANT Page 8 of 11 SEPTEMBER 2014 Proc.Step TASK ELEMENT 14 STANDARD Grade --- Verify Service Water Header pressure rises to > 50 psig. Verify Service Water Header pressure rises to > 50 psig. S  U Comment:     EVALUATOR NOTE: Candidate will refer back to SOP-5, 7.1.1.b.2 to complete alignment of Containment Air Coolers. Also, the following four steps may be performed in any order. Proc.Step TASK ELEMENT 15 STANDARD Grade 7.1.1 b.2 ENSURE all available Containment Air Cooler Fans are operating: For VHX-1 start fan V-1A (SOP-5). V-1A is started. S  U Comment:   CRITICAL STEP   Proc.Step TASK ELEMENT 16 STANDARD Grade 7.1.1 b.2 ENSURE all available Containment Air Cooler Fans are operating: For VHX-1 start fan V-1B (SOP-5) V-1B is started. S  U Comment:   CRITICAL STEP   Proc.Step TASK ELEMENT 17 STANDARD Grade 7.1.1 b.2 ENSURE all available Containment Air Cooler Fans are operating: For VHX-4 start fan V-4A (SOP-5) V-4A is started. S  U Comment:  CRITICAL STEP JPM SYSTEM E PALISADES NUCLEAR PLANT Page 9 of 11 SEPTEMBER 2014 Proc.Step TASK ELEMENT 18 STANDARD Grade 7.1.1 b.2 ENSURE all available Containment Air Cooler Fans are operating: For VHX-4 start fan V-4B (SOP-5) V-4B is started. S  U Comment:   CRITICAL STEP   Proc. Step TASK ELEMENT 19 STANDARD Grade N/A Notify CRS that Containment Air Coolers are aligned with all High Capacity outlet valves open and all fans running. CRS notified. S  U Comment:     END OF TASK JPM SYSTEM E PALISADES NUCLEAR PLANT Page 10 of 11 SEPTEMBER 2014 SIMULATOR OPERATOR INSTRUCTIONS Reset to IC-17. Ensure P-7A and P-7B are in service, with P-7C in standby. Stop V-1A, 1B, 4A, and 4B. Close VHX-1 High Capacity Outlet, CV-0861. Close VHX-4 High Capacity Outlet, CV-0867. Insert SW leak: SW09 in at 50% (at setup). Create Event Trigger 2: Event = zlo1p(26).and.zlo1p(32), Action imf sw09 65 {this is for having the red lights on for CVs-0861 and 0867}
Performance Time:       ________ minutes Performance Rating:     SAT______       UNSAT ______
JPM SYSTEM E PALISADES NUCLEAR PLANT Page 11 of 11 SEPTEMBER 2014 CANDIDATE CUE SHEET   (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)   INITIAL CONDITIONS:   The plant is operating at steady state 100% power. VHX-1 Cooling Fans V-1A and V-1B are OFF with Service Water isolated. VHX-4 Cooling Fans V-4A and V-4B are OFF with Service Water isolated. All CAC Outlet Bypass Valves are properly aligned per SOP- 7.1.1.b.1 table. INITIATING CUES: The Control Room Supervisor has directed you to align the Containment Air Cooling System to its normal alignment per SOP-5, section 7.1.1 with all fans operating and all inlet and high capacity valves open.
Comments:
REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE     JPM: RO/SRO-I SYS F TITLE: PERFORM A DIESEL GENERATOR (D/G) VOLTAGE TEST ON 1-1 D/G       CANDIDATE:   EXAMINER:
Examiner: _______________________________               Date:   ______________
JPM: SYSTEM F PALISADES NUCLEAR PLANT Page 2 of 10 SEPTEMBER 2014  JOB PERFORMANCE MEASURE DATA PAGE   Task: Perform Diesel Generator Surveillance MO-7A-1 and MO-7A-2 Alternate Path: NO Facility JPM #: PL-OPS-EDG-005J K/A: 064A4.06 Importance: RO: 3.9   SRO: 3.9 K/A Statement: Manual start, loading, and stopping of the ED/G Task Standard: 1-1 D/G Auto Voltage Regulator High and Low Limits verified. Preferred Evaluation Location: Simulator __X__ In Plant _____ Preferred Evaluation Method: Perform __X__ Simulate _____
Signature PALISADES NUCLEAR PLANT               Page 2 of 11                     SEPTEMBER 2014
 
JPM SYSTEM E EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:
SOP-5, Containment Air Cooling Also see Simulator Operator Instructions (later page of this document).
READ TO CANDIDATE DIRECTION TO CANDIDATE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
The plant is operating at steady state 100% power.
VHX-1 Cooling Fans V-1A and V-1B are OFF with Service Water isolated.
VHX-4 Cooling Fans V-4A and V-4B are OFF with Service Water isolated.
All CAC Outlet Bypass Valves are properly aligned per SOP-5, Containment Air Cooling, step 7.1.1.b.1 table.
INITIATING CUES:
The Control Room Supervisor has directed you to align the Containment Air Cooling System to its normal alignment per SOP-5, section 7.1.1 with all fans operating and all inlet and high capacity valves open.
PALISADES NUCLEAR PLANT                   Page 3 of 11                       SEPTEMBER 2014
 
JPM SYSTEM E EVALUATOR CUE: Provide candidate with a working copy of SOP-5 (entire procedure)
Proc.Step           TASK ELEMENT 1                                       STANDARD                     Grade REFER TO Step 5.2.3 for guidance on           Candidate refers to step 5.2.3 for guidance on 7.1.1.a                                                                                                S U Service Water Pump operation.                  SW pump operation.
Comment:
EVALUATOR CUE: If asked whether a third Service Water Pump should be started, state that, "If possible, operate with two Service Water Pumps."
EVALUATOR NOTE: Order of valve alignment and fan starts is not critical.
Proc.Step           TASK ELEMENT 2                                       STANDARD                     Grade ENSURE control valves are positioned as
 
====7.1.1 follows====
CV-0869 is verified open.                      S U b.1 For VHX-4, verify open Inlet Valve CV-0869.
Comment:
EVALUATOR NOTE: Service Water Pump discharge pressure has been setup low and will lower further when CAC high capacity valves are opened.
Proc.Step           TASK ELEMENT 3                                       STANDARD                     Grade ENSURE control valves are positioned as
 
====7.1.1 follows====
High Capacity Outlet Valve CV-0867 is opened. S U b.1    For VHX-4, open High Capacity Outlet Valve CV-0867.
Comment:
CRITICAL STEP PALISADES NUCLEAR PLANT                       Page 4 of 11                             SEPTEMBER 2014
 
JPM SYSTEM E Proc.Step             TASK ELEMENT 4                                   STANDARD                     Grade ENSURE control valves are positioned as
 
====7.1.1 follows====
Inlet Valve CV-0862 is verified open.         S U b.1 For VHX-1 verify Open Inlet Valve CV-0862.
Comment:
EVALUATOR NOTE: Will receive EDG Trouble Alarms on Panel C-11 after Service Water Pump start.
EVALUATOR NOTE: This step may be performed AFTER Service Water Pump start.
Proc.Step             TASK ELEMENT 5                                   STANDARD                     Grade ENSURE control valves are positioned as
 
====7.1.1 follows====
High Capacity Outlet Valve CV-0861 is opened. S U b.1    For VHX-1 open High Capacity Outlet Valve CV-0861.
Comment:
EVALUATOR NOTE: This step may be performed AFTER Service Water Pump start.
CRITICAL STEP Proc.Step             TASK ELEMENT 6                                   STANDARD                     Grade Determines that the Standby Service Water Pump P-7C needs to be started because Monitor Service Water Header pressure and    system pressure has lowered to < 50 psig.
5.2.3  determine that Service Water system                                                          S U pressure is < 50 psig.                        May need to respond to alarms EK-0551 and EK-0557: Has AO investigate D/G local alarm boards.
Comment:
EVALUATOR CUE: When asked as AO report that D/G local alarm panels indicate low raw water pressure. Reading is 24 psig if asked.
PALISADES NUCLEAR PLANT                     Page 5 of 11                             SEPTEMBER 2014
 
JPM SYSTEM E Proc.Step               TASK ELEMENT 7                                       STANDARD                   Grade Obtain SOP-15, Service Water System             Locates SOP-15, Service Water System n/a                                                                                                  S U procedure, section 7.1.1.                        procedure.
Comment:
EVALUATOR CUE: Provide candidate with a working copy of SOP-15, section 7.1.1.
Proc.Step               TASK ELEMENT 8                                       STANDARD                   Grade SOP-15   IF starting the first Service Water Pump, Candidate determines this step is N/A.       S U 7.1.1.a  THEN GO TO Section 7.1.5.
Comment:
Proc.Step               TASK ELEMENT 9                                       STANDARD                   Grade IF starting the third Service Water Pump, SOP-15    THEN NOTIFY Chemistry so that they can           Notify Chemistry to recalculate Mixing Basin S U 7.1.1.b  recalculate mixing basin discharge flow          discharge flow volume.
volume.
Comment:
EVALUATOR CUE: CRS will notify Chemistry of P-7C start so they can recalculate mixing basin discharge flow volume.
Proc.Step             TASK ELEMENT 10                                       STANDARD                   Grade ENSURE OPEN associated pump SOP-15                                                    Dispatch AO to check OPEN P-7C discharge discharge valve:                                                                              S U 7.1.1.c                                                  valve MV-SW104.
P-7C MV-SW104 Comment:
EVALUATOR (or Simulator Operator) CUE: "MV-SW104 is OPEN" PALISADES NUCLEAR PLANT                         Page 6 of 11                             SEPTEMBER 2014
 
JPM SYSTEM E Proc.Step             TASK ELEMENT 11                                   STANDARD                     Grade SOP-15                                                 Dispatch AO to check P-7C motor oil levels ENSURE motor oil levels normal.                                                             S U 7.1.1.d                                              normal.
Comment:
EVALUATOR (or Simulator Operator) CUE: "P-7C Motor oil levels normal" Proc.Step             TASK ELEMENT 12                                   STANDARD                     Grade SOP-15   Remove P-7C from standby by placing         P-7C Control Switch placed momentarily in S U 7.1.1.e  Control Switch to TRIP.                      TRIP until standby light extinguishes.
Comment:
Proc.Step             TASK ELEMENT 13                                   STANDARD                     Grade SOP-15   START desired pump from Control Room P-7C control switch placed in START and Handswitch (preferred) or using Handswitch                                                  S U 7.1.1.f                                              released to mid-position.
on breaker.
Comment:
SIMULATOR OPERATOR: Call in as AO and report that SW Pump P-7C local discharge pressure is 73 psig, and packing leakoff is not excessive. If asked, report that P-7C Basket Strainer DP is 4 psid.
EVALUATOR NOTE: EK-1144, P-7C Basket Strainer HI dP may alarm and then clear after pump start: candidate should reference ARP-7, but no actions are required.
CRITICAL STEP PALISADES NUCLEAR PLANT                     Page 7 of 11                             SEPTEMBER 2014
 
JPM SYSTEM E Proc.Step             TASK ELEMENT 14                                   STANDARD                 Grade Verify Service Water Header pressure rises   Verify Service Water Header pressure rises
  ---                                                                                            S U to > 50 psig.                               to > 50 psig.
Comment:
EVALUATOR NOTE: Candidate will refer back to SOP-5, 7.1.1.b.2 to complete alignment of Containment Air Coolers. Also, the following four steps may be performed in any order.
Proc.Step             TASK ELEMENT 15                                   STANDARD                 Grade ENSURE all available Containment Air 7.1.1 Cooler Fans are operating:                   V-1A is started.                            S U b.2 For VHX-1 start fan V-1A (SOP-5).
Comment:
CRITICAL STEP Proc.Step             TASK ELEMENT 16                                   STANDARD                 Grade ENSURE all available Containment Air 7.1.1 Cooler Fans are operating:                   V-1B is started.                            S U b.2 For VHX-1 start fan V-1B (SOP-5)
Comment:
CRITICAL STEP Proc.Step             TASK ELEMENT 17                                   STANDARD                 Grade ENSURE all available Containment Air 7.1.1 Cooler Fans are operating:                   V-4A is started.                            S U b.2 For VHX-4 start fan V-4A (SOP-5)
Comment:
CRITICAL STEP PALISADES NUCLEAR PLANT                     Page 8 of 11                           SEPTEMBER 2014
 
JPM SYSTEM E Proc.Step             TASK ELEMENT 18                                     STANDARD               Grade ENSURE all available Containment Air 7.1.1 Cooler Fans are operating:                     V-4B is started.                          S U b.2 For VHX-4 start fan V-4B (SOP-5)
Comment:
CRITICAL STEP Proc. Step           TASK ELEMENT 19                                     STANDARD               Grade Notify CRS that Containment Air Coolers N/A    are aligned with all High Capacity outlet     CRS notified.                              S U valves open and all fans running.
Comment:
END OF TASK PALISADES NUCLEAR PLANT                       Page 9 of 11                         SEPTEMBER 2014
 
JPM SYSTEM E SIMULATOR OPERATOR INSTRUCTIONS Reset to IC-17.
Ensure P-7A and P-7B are in service, with P-7C in standby.
Stop V-1A, 1B, 4A, and 4B.
Close VHX-1 High Capacity Outlet, CV-0861.
Close VHX-4 High Capacity Outlet, CV-0867.
Insert SW leak: SW09 in at 50% (at setup).
Create Event Trigger 2: Event = zlo1p(26).and.zlo1p(32), Action - imf sw09 65
{this is for having the red lights on for CVs-0861 and 0867}
PALISADES NUCLEAR PLANT                   Page 10 of 11                 SEPTEMBER 2014
 
JPM SYSTEM E CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
The plant is operating at steady state 100% power.
VHX-1 Cooling Fans V-1A and V-1B are OFF with Service Water isolated.
VHX-4 Cooling Fans V-4A and V-4B are OFF with Service Water isolated.
All CAC Outlet Bypass Valves are properly aligned per SOP-5, Containment Air Cooling, step 7.1.1.b.1 table.
INITIATING CUES:
The Control Room Supervisor has directed you to align the Containment Air Cooling System to its normal alignment per SOP-5, section 7.1.1 with all fans operating and all inlet and high capacity valves open.
PALISADES NUCLEAR PLANT                Page 11 of 11                    SEPTEMBER 2014
 
REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I SYS F TITLE: PERFORM A DIESEL GENERATOR (D/G) VOLTAGE TEST ON 1-1 D/G CANDIDATE:
EXAMINER:
 
JPM: SYSTEM F JOB PERFORMANCE MEASURE DATA PAGE Task: Perform Diesel Generator Surveillance MO-7A-1 and MO-7A-2 Alternate Path: NO Facility JPM #: PL-OPS-EDG-005J K/A: 064A4.06 Importance:         RO: 3.9           SRO: 3.9 K/A Statement: Manual start, loading, and stopping of the ED/G Task Standard: 1-1 D/G Auto Voltage Regulator High and Low Limits verified.
Preferred Evaluation Location: Simulator       __X__       In Plant   _____
Preferred Evaluation Method:       Perform     __X__       Simulate   _____


==References:==
==References:==
MO-7A-1, Emergency Diesel Generator 1-1 Validation Time: 10 minutes Time Critical: NO   Candidate:   Time Start: ________ Time Finish: ________ Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______ Comments:     Examiner: _______________________________ Date: ______________ Signature JPM: SYSTEM F PALISADES NUCLEAR PLANT Page 3 of 10 SEPTEMBER 2014 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:   MO-7A-1, Emergency Diesel Generator 1-1, Section 5.6 Also see Simulator Operator Instructions (last page of this document). READ TO CANDIDATE DIRECTION TO CANDIDATE: I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS: Diesel Generator 1-1 running unloaded at 60 Hz for fifteen minutes. MO-7A-1, "Emergency Diesel Generator 1-1" is in progress; all steps up to 5.6 are completed. Month is January. Plant is in Mode 1. Auxiliary Operator is stationed at EC-22, Diesel Generator 1-1 Local Panel. INITIATING CUES: During performance of MO-7A-1, the Control Room Supervisor directs you to perform Section 5.6 "Voltage Regulator Test."
MO-7A-1, Emergency Diesel Generator 1-1 Validation Time:   10 minutes         Time Critical:   NO Candidate:
JPM: SYSTEM F PALISADES NUCLEAR PLANT Page 4 of 10 SEPTEMBER 2014 Proc. Step TASK ELEMENT 1 STANDARD Grade n/a Operator obtains a copy of MO-7A-1, Section 5.6  MO-7A-1, Section 5.6 obtained U Comment: Evaluator Cue: Provide a working copy of MO-7A-1, Section 5.6.     Proc. Step TASK ELEMENT 2 STANDARD Grade 5.6.1 DETERMINE the Voltage Regulator Mode Select switch position from the table for the AND PERFORM the following: Voltage Regulator Mode Select Switch  Operator determines that the Voltage Regulator Mode Select switch position is AUTO. S U Comment: Evaluator Note: The Voltage Regulator Mode Select switch position is determined by the Month of the test. Evaluator Cue: If asked as System Engineer what switch position to use, CUE that the procedure, MO-7A-1 is to be followed. Proc. Step TASK ELEMENT 3 STANDARD Grade   5.6.1a IF position is AUTO, THEN ENSURE Voltage Regulator Mode Select switch is in the AUTO position (location C-04 panel). Voltage Regulator Mode Select switch is verified in AUTO position. S  U Comment: Evaluator Cue: If candidate places this switch in MANUAL, then this task element is a failed critical step.
Time Start: ________         Time Finish:     ________
JPM: SYSTEM F PALISADES NUCLEAR PLANT Page 5 of 10 SEPTEMBER 2014 Proc. Step TASK ELEMENT 4 STANDARD Grade 5.6.1b.1 IF position is MANUAL, THEN PERFORM   Operator determines that this step is not applicable. S U Comment:       Proc. Step TASK ELEMENT 5 STANDARD Grade 5.6.1b.2 IF the plant is in Mode 1, 2, 3, or 4, THEN PERFORM off-site source checks. Operator determines that this step is not applicable. S  U Comment:      Proc. Step TASK ELEMENT 6 STANDARD Grade 5.6.2 DETERMINE the switch from the table for PERFORM the Following:  Operator determines that the Field Rheostat switch on C-04 is to be used. S U Comment: Evaluator Note: The Field Rheostat switch on C-04 is determined by the Month of the test. Evaluator Cue: If asked as System Engineer what switch to use, CUE The procedure, MO-7A-1 is to be followed.
Performance Time:       ________ minutes Performance Rating:     SAT______         UNSAT ______
JPM: SYSTEM F PALISADES NUCLEAR PLANT Page 6 of 10 SEPTEMBER 2014 Proc. Step TASK ELEMENT 7 STANDARD Grade 5.6.2a Slowly raise generator voltage to between 2575 VAC and 2625 VAC on EVI-1107L, Local Volt Meter or as directed by the System Engineer. Operator adjusts generator voltage between 2575 VAC and 2625 VAC on EVI-1107L with the Field Rheostat switch on C-04. S  U Comment: Evaluator Cue: If asked as System Engineer what generator voltage limits to use, CUE that the procedure, MO-7A-1 is to be followed. Evaluator Cue: If asked as AO to report local generator voltage, USE voltage indication on C-04 for the local voltage reading. CRITICAL STEP   Proc. Step TASK ELEMENT 8 STANDARD Grade 5.6.2b RECORD generator voltage and field voltage (location EC-22 panel) Local Volt Meter (EVI-1107L) Volts: ____  Field Voltage (EVI-1107DC) Volts: ____ Recorded generator and field voltages (from EC-22 panel: Local Volt Meter (EVI-1107L) Volts: 2575 to 2625 Field Voltage (EVI-1107DC) Volts: __80V_ S  U Comment: Evaluator Cue: If asked as AO to report local generator voltage, USE voltage indication on C-04 for the local voltage reading. Evaluator Cue: If asked as AO to report field voltage, REPORT: field voltage reads 80 V on EVI-1107DC.
Comments:
JPM: SYSTEM F PALISADES NUCLEAR PLANT Page 7 of 10 SEPTEMBER 2014 Proc. Step TASK ELEMENT 9 STANDARD Grade 5.6.2c Slowly lower generator voltage to between 2275 VAC and 2325 VAC on EVI-1107L, Local Volt Meter or as directed by the System Engineer. Operator adjusts generator voltage between 2275 VAC and 2325 VAC on EVI-1107L with the Field Rheostat switch on C-04. S  U Comment: Evaluator Cue: If asked as System Engineer what generator voltage limits to use, CUE that the procedure, MO-7A-1 is to be followed. Evaluator Cue: If asked as AO to report local generator voltage, USE voltage indication on C-04 for the local voltage reading. CRITICAL STEP     Proc. Step TASK ELEMENT 10 STANDARD Grade 5.6.2d RECORD generator voltage and field voltage (location EC-22 panel) Local Volt Meter (EVI-1107L0 Volts: ____  Field Voltage (EVI-1107DC)n Volts: ____  Recorded generator and field voltages (from EC-22 panel: Local Volt Meter (EVI-1107L) Volts: 2275 to 2325 Field Voltage (EVI-1107DC) Volts: __70V_ S  U Comment: Evaluator Cue: If asked as AO to report local generator voltage, USE voltage indication on C-04 for the local voltage reading. Evaluator Cue: If asked as AO to report field voltage, REPORT: field voltage reads 70 V on EVI-1107DC.
Examiner: _______________________________                   Date:   ______________
JPM: SYSTEM F PALISADES NUCLEAR PLANT Page 8 of 10 SEPTEMBER 2014 Proc. Step TASK ELEMENT 11 STANDARD Grade 5.6.2e RAISE generator voltage to 2400 VAC (2390 VAC 2410 VAC) on EVI-1107L, Local Volt Meter. Generator voltage raised to between 2390 VAC and 2410 VAC on EVI-1107L with the Field Rheostat switch on C-04. S U Comment: Evaluator Cue: If asked as AO to report local generator voltage, USE voltage indication on C-04 for the local voltage reading. CRITICAL STEP     Proc. Step TASK ELEMENT 12 STANDARD Grade 5.6.3  ENSURE Voltage Regulator Mode Select switch is in AUTO position (location C-04 panel). Performed By: Signed, Time and Dated Verified By: Signed, Time and Dated Voltage Regulator Mode Select switch verified in the AUTO position Performed By: N/A Verified By: Signed, Time and Dated S  U Comment: Evaluator Cue: Operator will not sign the Performed By line, the Verified By line will be signed (Voltage Selector switch in proper position and not manipulated)     Proc. Step TASK ELEMENT 13 STANDARD Grade n/a Notify CRS that 1-1 D/G Voltage Regulator Test has been completed per Section 5.6 of MO-7A-1, for 1-1 D/G. CRS notified that Section 5.6 of MO-7A-1 for Voltage Regulator Test Complete. S  U Comment:     END OF TASK JPM: SYSTEM F PALISADES NUCLEAR PLANT Page 9 of 10 SEPTEMBER 2014 SIMULATOR OPERATOR INSTRUCTIONS   Any at power IC can be used. Start EDG 1-1 in UNIT. Clear Local Alarm gauge board on PIDED08, using ED27.
Signature PALISADES NUCLEAR PLANT                 Page 2 of 10                     SEPTEMBER 2014
JPM: SYSTEM F PALISADES NUCLEAR PLANT Page 10 of 10 SEPTEMBER 2014 CANDIDATE CUE SHEET   (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)   INITIAL CONDITIONS:   Diesel Generator 1-1 running unloaded at 60 Hz for fifteen minutes. MO-7A-1, "Emergency Diesel Generator 1-1" is in progress; all steps up to 5.6 are completed. Month is January. Plant is in Mode 1. Auxiliary Operator is stationed at EC-22, Diesel Generator 1-1 Local Panel. INITIATING CUES: During performance of MO-7A-1, the Control Room Supervisor directs you to perform Section 5.6 "Voltage Regulator Test."
 
NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE     JPM: RO/SRO-I SYS G TITLE: ADJUST RIA-1049 SETPOINT       CANDIDATE:   EXAMINER:
JPM: SYSTEM F EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:
JPM SYSTEM G PALISADES NUCLEAR PLANT Page 2 of 8 SEPTEMBER 2014  JOB PERFORMANCE MEASURE DATA PAGE   Task: Adjust RIA-1049 Alarm Setpoint Alternate Path: NO Facility JPM #: 2012 NRC EXAM K/A: 073A4.01 Importance: RO: 3.9 SRO: 3.9 K/A Statement: Ability to manually operate and/or monitor in the control room: Effluent release Task Standard: RIA-1049 high alarm set to 1100 cpm. Preferred Evaluation Location: Simulator ___X___ In Plant _____ Preferred Evaluation Method: Perform ___X___ Simulate _____
MO-7A-1, Emergency Diesel Generator 1-1, Section 5.6 Also see Simulator Operator Instructions (last page of this document).
READ TO CANDIDATE DIRECTION TO CANDIDATE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
Diesel Generator 1-1 running unloaded at 60 Hz for fifteen minutes.
MO-7A-1, "Emergency Diesel Generator 1-1" is in progress; all steps up to 5.6 are completed.
Month is January.
Plant is in Mode 1.
Auxiliary Operator is stationed at EC-22, Diesel Generator 1-1 Local Panel.
INITIATING CUES:
During performance of MO-7A-1, the Control Room Supervisor directs you to perform Section 5.6 "Voltage Regulator Test."
PALISADES NUCLEAR PLANT                     Page 3 of 10                     SEPTEMBER 2014
 
JPM: SYSTEM F Proc. Step             TASK ELEMENT 1                                     STANDARD                       Grade Operator obtains a copy of MO-7A-1, MO-7A-1, Section 5.6 obtained n/a    Section 5.6                                                                                      S U Comment:
Evaluator Cue: Provide a working copy of MO-7A-1, Section 5.6.
Proc. Step             TASK ELEMENT 2                                     STANDARD                       Grade DETERMINE the Voltage Regulator Mode Select switch position from the table for the month .. AND PERFORM the following:           Operator determines that the Voltage Regulator 5.6.1                                                  Mode Select switch position is AUTO.           S U Voltage Regulator Mode Select Switch Position is AUTO for month of January Comment:
Evaluator Note: The Voltage Regulator Mode Select switch position is determined by the Month of the test.
Evaluator Cue: If asked as System Engineer what switch position to use, CUE that the procedure, MO-7A-1 is to be followed.
Proc. Step             TASK ELEMENT 3                                     STANDARD                       Grade IF position is AUTO, THEN ENSURE Voltage Regulator Mode Select switch is verified Voltage Regulator Mode Select switch is in 5.6.1a                                                  in AUTO position.                                S U the AUTO position (location C-04 panel).
Comment:
Evaluator Cue: If candidate places this switch in MANUAL, then this task element is a failed critical step.
PALISADES NUCLEAR PLANT                         Page 4 of 10                             SEPTEMBER 2014
 
JPM: SYSTEM F Proc. Step             TASK ELEMENT 4                                         STANDARD                     Grade IF position is MANUAL, THEN PERFORM             Operator determines that this step is not 5.6.1b.1  the following:                                  applicable.                                     S U Comment:
Proc. Step             TASK ELEMENT 5                                         STANDARD                     Grade IF the plant is in Mode 1, 2, 3, or 4, THEN     Operator determines that this step is not 5.6.1b.2  PERFORM off-site source checks.                  applicable.                                      S U Comment:
Proc. Step              TASK ELEMENT 6                                         STANDARD                     Grade DETERMINE the switch from the table for Operator determines that the Field Rheostat the performance month . AND 5.6.2                                                    switch on C-04 is to be used.                   S U PERFORM the Following:
Comment:
Evaluator Note: The Field Rheostat switch on C-04 is determined by the Month of the test.
Evaluator Cue: If asked as System Engineer what switch to use, CUE The procedure, MO-7A-1 is to be followed.
PALISADES NUCLEAR PLANT                           Page 5 of 10                             SEPTEMBER 2014
 
JPM: SYSTEM F Proc. Step             TASK ELEMENT 7                                       STANDARD                   Grade Slowly raise generator voltage to between Operator adjusts generator voltage between 2575 VAC and 2625 VAC on EVI-1107L, 2575 VAC and 2625 VAC on EVI-1107L with the 5.6.2a    Local Volt Meter or as directed by the                                                        S U Field Rheostat switch on C-04.
System Engineer.
Comment:
Evaluator Cue: If asked as System Engineer what generator voltage limits to use, CUE that the procedure, MO-7A-1 is to be followed.
Evaluator Cue: If asked as AO to report local generator voltage, USE voltage indication on C-04 for the local voltage reading.
CRITICAL STEP Proc. Step             TASK ELEMENT 8                                       STANDARD                   Grade Recorded generator and field voltages (from RECORD generator voltage and field EC-22 panel:
voltage (location EC-22 panel)
Local Volt Meter (EVI-1107L) Volts: 2575 to 5.6.2b    Local Volt Meter (EVI-1107L) Volts: ____                                                     S U 2625 Field Voltage (EVI-1107DC) Volts: ____
Field Voltage (EVI-1107DC) Volts: __80V_
Comment:
Evaluator Cue: If asked as AO to report local generator voltage, USE voltage indication on C-04 for the local voltage reading.
Evaluator Cue: If asked as AO to report field voltage, REPORT: field voltage reads 80 V on EVI-1107DC.
PALISADES NUCLEAR PLANT                         Page 6 of 10                             SEPTEMBER 2014
 
JPM: SYSTEM F Proc. Step             TASK ELEMENT 9                                       STANDARD                   Grade Slowly lower generator voltage to between Operator adjusts generator voltage between 2275 VAC and 2325 VAC on EVI-1107L, 2275 VAC and 2325 VAC on EVI-1107L with the 5.6.2c    Local Volt Meter or as directed by the                                                        S U Field Rheostat switch on C-04.
System Engineer.
Comment:
Evaluator Cue: If asked as System Engineer what generator voltage limits to use, CUE that the procedure, MO-7A-1 is to be followed.
Evaluator Cue: If asked as AO to report local generator voltage, USE voltage indication on C-04 for the local voltage reading.
CRITICAL STEP Proc. Step             TASK ELEMENT 10                                       STANDARD                   Grade Recorded generator and field voltages (from RECORD generator voltage and field EC-22 panel:
voltage (location EC-22 panel)
Local Volt Meter (EVI-1107L) Volts: 2275 to 5.6.2d    Local Volt Meter (EVI-1107L0 Volts: ____                                                    S U 2325 Field Voltage (EVI-1107DC)n Volts: ____
Field Voltage (EVI-1107DC) Volts: __70V_
Comment:
Evaluator Cue: If asked as AO to report local generator voltage, USE voltage indication on C-04 for the local voltage reading.
Evaluator Cue: If asked as AO to report field voltage, REPORT: field voltage reads 70 V on EVI-1107DC.
PALISADES NUCLEAR PLANT                         Page 7 of 10                             SEPTEMBER 2014
 
JPM: SYSTEM F Proc. Step             TASK ELEMENT 11                                     STANDARD                     Grade RAISE generator voltage to 2400 VAC          Generator voltage raised to between 2390 VAC (2390 VAC - 2410 VAC) on EVI-1107L,         and 2410 VAC on EVI-1107L with the Field 5.6.2e    Local Volt Meter.                            Rheostat switch on C-04.                         S U Comment:
Evaluator Cue: If asked as AO to report local generator voltage, USE voltage indication on C-04 for the local voltage reading.
CRITICAL STEP Proc. Step             TASK ELEMENT 12                                     STANDARD                     Grade ENSURE Voltage Regulator Mode Select Voltage Regulator Mode Select switch verified in switch is in AUTO position the AUTO position (location C-04 panel).
5.6.3                                                                                                  S U Performed By: N/A Performed By: Signed, Time and Dated Verified By: Signed, Time and Dated Verified By: Signed, Time and Dated Comment:
Evaluator Cue: Operator will not sign the Performed By line, the Verified By line will be signed (Voltage Selector switch in proper position and not manipulated)
Proc. Step             TASK ELEMENT 13                                     STANDARD                     Grade Notify CRS that 1-1 D/G Voltage Regulator CRS notified that Section 5.6 of MO-7A-1 for Test has been completed per Section 5.6 of n/a                                                  Voltage Regulator Test Complete.                  S U MO-7A-1, for 1-1 D/G.
Comment:
END OF TASK PALISADES NUCLEAR PLANT                       Page 8 of 10                             SEPTEMBER 2014
 
JPM: SYSTEM F SIMULATOR OPERATOR INSTRUCTIONS Any at power IC can be used.
Start EDG 1-1 in UNIT.
Clear Local Alarm gauge board on PIDED08, using ED27.
PALISADES NUCLEAR PLANT             Page 9 of 10         SEPTEMBER 2014
 
JPM: SYSTEM F CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
Diesel Generator 1-1 running unloaded at 60 Hz for fifteen minutes.
MO-7A-1, "Emergency Diesel Generator 1-1" is in progress; all steps up to 5.6 are completed.
Month is January.
Plant is in Mode 1.
Auxiliary Operator is stationed at EC-22, Diesel Generator 1-1 Local Panel.
INITIATING CUES:
During performance of MO-7A-1, the Control Room Supervisor directs you to perform Section 5.6 "Voltage Regulator Test."
PALISADES NUCLEAR PLANT                Page 10 of 10                    SEPTEMBER 2014
 
NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I SYS G TITLE: ADJUST RIA-1049 SETPOINT CANDIDATE:
EXAMINER:
 
JPM SYSTEM G JOB PERFORMANCE MEASURE DATA PAGE Task:   Adjust RIA-1049 Alarm Setpoint Alternate Path: NO Facility JPM #: 2012 NRC EXAM K/A:     073A4.01       Importance:   RO:       3.9   SRO:     3.9 K/A Statement: Ability to manually operate and/or monitor in the control room: Effluent release Task Standard: RIA-1049 high alarm set to 1100 cpm.
Preferred Evaluation Location: Simulator     ___X___     In Plant     _____
Preferred Evaluation Method:   Perform     ___X___     Simulate     _____


==References:==
==References:==
SOP-37, Process Liquid Monitor System   Validation Time: 10 minutes Time Critical: NO   Candidate:   Time Start: ________ Time Finish: ________ Performance Time: ________ minutes Performance Rating: SAT ______ UNSAT ______ Comments:     Examiner: _______________________________ Date: ______________ Signature JPM SYSTEM G PALISADES NUCLEAR PLANT Page 3 of 8 SEPTEMBER 2014 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:   SOP-37, Process Liquid Monitor System Also see Simulator Operator Instructions (later page of this document). READ TO CANDIDATE DIRECTION TO CANDIDATE: I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:   Release Order, Form CH 6.21-3 (batch card) has been prepared. The following RE-1049 data has already been entered on this form: o RE-1049 Check Source reading = 6.6 E6 cpm o High alarm setpoint net cpm = 640 o RE-1049 background cpm = 460 o RIA-1049 alarm setpoint cpm = 1100   Breaker 34 on EY-01 is closed. -1049, Digital Rate Meter has been performed. INITIATING CUES: The CRS directs you to set up Radwaste Discharge Monitor, RIA-1049 High Alarm Setpoint using SOP-37 Section 7.3.2 to a setpoint of 1100 cpm (hand candidate prepared Release Order).
SOP-37, Process Liquid Monitor System Validation Time:     10 minutes     Time Critical:   NO Candidate:
JPM SYSTEM G PALISADES NUCLEAR PLANT Page 4 of 8 SEPTEMBER 2014 EVALUATOR CUE: Provide candidate with a working copy of SOP-37, section 7.3.2   Proc. Step TASK ELEMENT 1 STANDARD Grade a PUSH HIGH pushbutton on front of RIA-1049 and read current High Alarm Setpoint. "High Alarm" push button on the front of RIA-1049 pushed and current high alarm setpoint is read as 2.70E3 CPM. S  U Comment:       Proc. Step TASK ELEMENT 2 STANDARD Grade b PULL RIA-1049 out from the panel about six inches (6") to access the control buttons. RIA-1049 pulled out from panel about 6 inches. S U Comment:   CRITICAL STEP   Proc. Step TASK ELEMENT 3 STANDARD Grade c VERIFY seen on right side of switch. Checks right side of Function Switch is set to  S U Comment:       Proc. Step TASK ELEMENT 4 STANDARD Grade d PRESS ENTER button to display High Alarm setpoint. "Enter" button pressed and one digit blinking. S U Comment:   CRITICAL STEP JPM SYSTEM G PALISADES NUCLEAR PLANT Page 5 of 8 SEPTEMBER 2014 Proc. Step TASK ELEMENT 5 STANDARD Grade e SET the High Alarm setpoint by performing the following as necessary:   IF selecting another digit, THEN PRESS the DIGIT pushbutton. IF changing the digit value, THEN PRESS the VALUE pushbutton until value desired for that digit is displayed. Digit and Value pushbuttons manipulated as necessary to set the high alarm setpoint at 1.10E3. S  U Comment:   CRITICAL STEP   Proc. Step TASK ELEMENT 6 STANDARD Grade f WHEN entire display indicates desired trip setpoint, THEN: (a) PRESS ENTER pushbutton. Enter button pressed. S  U Comment:   CRITICAL STEP   Proc. Step TASK ELEMENT 7 STANDARD Grade f WHEN entire display indicates desired trip setpoint, THEN: (b) PUSH monitor back into panel. Monitor pushed back into panel. S  U Comment:       Proc. Step TASK ELEMENT 8 STANDARD Grade g PRESS HIGH pushbutton on front of RIA-1049 to verify high alarm setpoint is correct. High Alarm" push button pressed and 1.10E3 CPM trip setpoint verified. S  U Comment:
Time Start: ________       Time Finish:     ________
JPM SYSTEM G PALISADES NUCLEAR PLANT Page 6 of 8 SEPTEMBER 2014 Proc. Step TASK ELEMENT 9 STANDARD Grade h PRESS ALARM ACK button to clear any high alarms that may have come in. Alarm Ack pushed and Alarms clear. S U Comment:       Proc. Step TASK ELEMENT 10 STANDARD Grade N/A Notify the CRS that RIA-1049 High Alarm Setpoint is 1100 cpm. CRS is notified. S U Comment:   EVALUATOR CUE: As CRS, repeat back the notification. END OF TASK JPM SYSTEM G PALISADES NUCLEAR PLANT Page 7 of 8 SEPTEMBER 2014 SIMULATOR OPERATOR INSTRUCTIONS   Any IC Ensure RIA-1049 high alarm setpoint is set at 2.61E3 cpm PRIOR TO performing this JPM and AFTER it is completed (as appropriate). Fill out Release Order, form CH 6.21-3 (procedure CH 6.21, attachment 3) as follows: CH 6.21, Attachment 3, page 1 of 2. In the first section of the form, fill in the following: Batch = LRW-Today Tank = T-91 % released = 70% Volume released (gal) = 51100 Minimum required Dilution Water Pumps = 1 Minimum required Service Water Pumps = 2 Maximum permitted release rate (gpm) = 250 Authorization Shift Manager = any signature; Date = today In the second section of the form, Control Room Operator pre-release section, fill in the following: Check both DW pumps operating Check P-7A and P-7B SW pumps operating RE-1049 Check Source reading = 6.6 E6 cpm High alarm setpoint net cpm = 640 RE-1049 background cpm = 460 RIA-1049 alarm setpoint cpm = 1100 Control Room Operator = any signature, Date = today JPM SYSTEM G PALISADES NUCLEAR PLANT Page 8 of 8 SEPTEMBER 2014 CANDIDATE CUE SHEET   (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK) INITIAL CONDITIONS:   Release Order, Form CH 6.21-3 (batch card) has been prepared. The following RE-1049 data has already been entered on this form: o RE-1049 Check Source reading = 6.6 E6 cpm o High alarm setpoint net cpm = 640 o RE-1049 background cpm = 460 o RIA-1049 alarm setpoint cpm = 1100   Breaker 34 on EY-01 is closed. -1049, Digital Rate Meter has been performed. INITIATING CUES: The CRS directs you to set up Radwaste Discharge Monitor, RIA-1049 High Alarm Setpoint using SOP-37 Section 7.3.2 to a setpoint of 1100 cpm.
Performance Time:       ________ minutes Performance Rating:     SAT   ______ UNSAT ______
REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE     JPM: RO/SRO-I SYS H TITLE: TRANSFER SHIELD COOLING COILS       CANDIDATE:   EXAMINER:
Comments:
JPM: SYSTEM H PALISADES NUCLEAR PLANT Page 2 of 8 SEPTEMBER 2014  JOB PERFORMANCE MEASURE DATA PAGE   Task: Operate the Shield Cooling System Alternate Path: YES Facility JPM #: BANK K/A: G2.1.30 Importance: RO: 4.4 SRO: 4.0   K/A Statement: Ability to locate and operate components, including local controls Task Standard: Shield Cooling Coil transferred -service and at least one Shield Cooling Pump operating. Preferred Evaluation Location: Simulator _X__ In Plant ______ Preferred Evaluation Method: Perform _X__ Simulate ______
Examiner: _______________________________               Date:   ______________
Signature PALISADES NUCLEAR PLANT               Page 2 of 8                       SEPTEMBER 2014
 
JPM SYSTEM G EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:
SOP-37, Process Liquid Monitor System Also see Simulator Operator Instructions (later page of this document).
READ TO CANDIDATE DIRECTION TO CANDIDATE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
Release Order, Form CH 6.21-3 (batch card) has been prepared. The following RE-1049 data has already been entered on this form:
o RE-1049 Check Source reading = 6.6 E6 cpm o High alarm setpoint net cpm = 640 o RE-1049 background cpm = 460 o RIA-1049 alarm setpoint cpm = 1100 Breaker 34 on EY-01 is closed.
Attachment 3, Checklist 37, Table Digital Rate Meter Instruments for RIA-1049, Digital Rate Meter has been performed.
INITIATING CUES:
The CRS directs you to set up Radwaste Discharge Monitor, RIA-1049 High Alarm Setpoint using SOP-37 Section 7.3.2 to a setpoint of 1100 cpm (hand candidate prepared Release Order).
PALISADES NUCLEAR PLANT                     Page 3 of 8                       SEPTEMBER 2014
 
JPM SYSTEM G EVALUATOR CUE: Provide candidate with a working copy of SOP-37, section 7.3.2 Proc. Step             TASK ELEMENT 1                                       STANDARD                   Grade PUSH HIGH pushbutton on front of               "High Alarm" push button on the front of a      RIA-1049 and read current High Alarm          RIA-1049 pushed and current high alarm         S U Setpoint.                                      setpoint is read as 2.70E3 CPM.
Comment:
Proc. Step             TASK ELEMENT 2                                       STANDARD                   Grade PULL RIA-1049 out from the panel about b      six inches (6") to access the control         RIA-1049 pulled out from panel about 6 inches. S U buttons.
Comment:
CRITICAL STEP Proc. Step             TASK ELEMENT 3                                       STANDARD                   Grade VERIFY Function switch is set to 0 as        Checks right side of Function Switch is set c                                                                                                    S U seen on right side of switch.                  to 0.
Comment:
Proc. Step             TASK ELEMENT 4                                       STANDARD                   Grade PRESS ENTER button to display High d                                                    "Enter" button pressed and one digit blinking. S U Alarm setpoint.
Comment:
CRITICAL STEP PALISADES NUCLEAR PLANT                         Page 4 of 8                             SEPTEMBER 2014
 
JPM SYSTEM G Proc. Step             TASK ELEMENT 5                                       STANDARD                     Grade SET the High Alarm setpoint by performing the following as necessary:
IF selecting another digit, THEN             Digit and Value pushbuttons manipulated as e          PRESS the DIGIT pushbutton.                 necessary to set the high alarm setpoint at    S U IF changing the digit value, THEN           1.10E3.
PRESS the VALUE pushbutton until value desired for that digit is displayed.
Comment:
CRITICAL STEP Proc. Step             TASK ELEMENT 6                                       STANDARD                     Grade WHEN entire display indicates desired trip f      setpoint, THEN:                                 Enter button pressed.                          S U (a) PRESS ENTER pushbutton.
Comment:
CRITICAL STEP Proc. Step             TASK ELEMENT 7                                       STANDARD                     Grade WHEN entire display indicates desired trip f      setpoint, THEN:                                 Monitor pushed back into panel.                S U (b) PUSH monitor back into panel.
Comment:
Proc. Step             TASK ELEMENT 8                                       STANDARD                     Grade PRESS HIGH pushbutton on front of High Alarm" push button pressed and g      RIA-1049 to verify high alarm setpoint is                                                       S U 1.10E3 CPM trip setpoint verified.
correct.
Comment:
PALISADES NUCLEAR PLANT                           Page 5 of 8                             SEPTEMBER 2014
 
JPM SYSTEM G Proc. Step             TASK ELEMENT 9                                 STANDARD                 Grade PRESS ALARM ACK button to clear any h                                                  Alarm Ack pushed and Alarms clear.         S U high alarms that may have come in.
Comment:
Proc. Step             TASK ELEMENT 10                                 STANDARD                 Grade Notify the CRS that RIA-1049 High Alarm N/A                                                CRS is notified.                           S U Setpoint is 1100 cpm.
Comment:
EVALUATOR CUE: As CRS, repeat back the notification.
END OF TASK PALISADES NUCLEAR PLANT                       Page 6 of 8                         SEPTEMBER 2014
 
JPM SYSTEM G SIMULATOR OPERATOR INSTRUCTIONS Any IC Ensure RIA-1049 high alarm setpoint is set at 2.61E3 cpm PRIOR TO performing this JPM and AFTER it is completed (as appropriate).
Fill out Release Order, form CH 6.21-3 (procedure CH 6.21, attachment 3) as follows:
CH 6.21, Attachment 3, page 1 of 2.
In the first section of the form, fill in the following:
Batch = LRW-Today Tank = T-91
                      % released = 70%
Volume released (gal) = 51100 Minimum required Dilution Water Pumps = 1 Minimum required Service Water Pumps = 2 Maximum permitted release rate (gpm) = 250 Authorization Shift Manager = any signature; Date = today In the second section of the form, Control Room Operator pre-release section, fill in the following:
Check both DW pumps operating Check P-7A and P-7B SW pumps operating RE-1049 Check Source reading = 6.6 E6 cpm High alarm setpoint net cpm = 640 RE-1049 background cpm = 460 RIA-1049 alarm setpoint cpm = 1100 Control Room Operator = any signature, Date = today PALISADES NUCLEAR PLANT                     Page 7 of 8                     SEPTEMBER 2014
 
JPM SYSTEM G CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
Release Order, Form CH 6.21-3 (batch card) has been prepared. The following RE-1049 data has already been entered on this form:
o RE-1049 Check Source reading = 6.6 E6 cpm o High alarm setpoint net cpm = 640 o RE-1049 background cpm = 460 o RIA-1049 alarm setpoint cpm = 1100 Breaker 34 on EY-01 is closed.
Attachment 3, Checklist 37, Table Digital Rate Meter Instruments for RIA-1049, Digital Rate Meter has been performed.
INITIATING CUES:
The CRS directs you to set up Radwaste Discharge Monitor, RIA-1049 High Alarm Setpoint using SOP-37 Section 7.3.2 to a setpoint of 1100 cpm.
PALISADES NUCLEAR PLANT                Page 8 of 8                      SEPTEMBER 2014
 
REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I SYS H TITLE: TRANSFER SHIELD COOLING COILS CANDIDATE:
EXAMINER:
 
JPM: SYSTEM H JOB PERFORMANCE MEASURE DATA PAGE Task:   Operate the Shield Cooling System Alternate Path: YES Facility JPM #: BANK K/A:     G2.1.30     Importance:           RO:       4.4   SRO:     4.0 K/A Statement: Ability to locate and operate components, including local controls Task Standard: Shield Cooling Coil transferred to A in-service and at least one Shield Cooling Pump operating.
Preferred Evaluation Location: Simulator         _X__         In Plant     ______
Preferred Evaluation Method:       Perform     _X__         Simulate     ______


==References:==
==References:==
SOP-29, Shield Cooling     ARP--13 (EC-   Validation Time: 10 minutes Time Critical: NO   Candidate:   Time Start: ________ Time Finish: ________ Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______ Comments:     Examiner: _______________________________ Date: ______________ Signature JPM: SYSTEM H PALISADES NUCLEAR PLANT Page 3 of 8 SEPTEMBER 2014 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:   SOP-29 section 7.1.2 ARP-8-13 (EC-windows 1, 2, and 3 Also see Simulator Operator Instructions (last page of this document). READ TO CANDIDATE DIRECTION TO CANDIDATE: I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:   Plant is at full power -29, Shield Cooling System, section 7.1.1. INITIATING CUES: The CRS directs you to transfer Shield Cooling Coils per SOP-29, Shield Cooling System, section 7.1.2.
SOP-29, Shield Cooling System ARP-8, Safeguards Safety Injection and Isolation Scheme EK-13 (EC-13)
JPM: SYSTEM H PALISADES NUCLEAR PLANT Page 4 of 8 SEPTEMBER 2014 Evaluator Cue: Provide a working copy of SOP-29, Section 7.1.2. Proc. Step TASK ELEMENT 1 STANDARD Grade 7.1.2.a CHECK Shield Cooling System in operation (refer to Section 7.1.1). No actions needed since this is status provided in initial conditions. S U Comment:     Proc. Step TASK ELEMENT 2 STANDARD Grade b OPEN Inlet Valve for coil set to be placed in operation: Coil A CV-0932 Coil B CV-0934 Coil A CV-0932 opened using key #141: red light ON, green light OFF S  U Comment: Evaluator Note: EK-1303 may alarm and then clear when this step is performed. Use of ARP not required to complete Critical portion of this step. CRITICAL STEP   Proc. Step TASK ELEMENT 3 STANDARD Grade c CLOSE Inlet Valve for coil set to be removed from operation: Coil A CV-0932 Coil B CV-0934 Coil B CV-0934 closed using key #142: red light OFF, green light ON S  U Comment: Evaluator Cue: If candidate references ARP-8, provide working copy of appropriate alarm windows (1, 2, and or 3). Evaluator Note: When CV-0934 red light goes off, then P-77A will trip. CRITICAL STEP JPM: SYSTEM H PALISADES NUCLEAR PLANT Page 5 of 8 SEPTEMBER 2014 Proc. Step TASK ELEMENT 4 STANDARD Grade d CHECK Annunciator EK-1303, "Reactor Shield Clg Lo Flo" CLEAR. EK-1303 checked and IS alarming. The following alarms are also alarming: EK-1301, Shield CLG Pumps Trip EK-1302, Shield CLG Pumps Disch Low Press S  U Comment: Evaluator Cue: If asked as CRS for direction, respond to follow procedures. EVALUATOR NOTE: Alternate Path begins here: covered in task elements 5 and 6. Proc. Step TASK ELEMENT 5 STANDARD Grade ARP-8 Window EK-1301 actions: ENSURE running standby Shield Cooling Pump P-77A OR P-77B  PLACE control switch for tripped pump to TRIP position P-77B handswitch taken to START and then released: red light ON, green light OFF P-77A handswitch taken to TRIP and released (NOT a critical task element) S  U Comment: CRITICAL STEP   Proc. Step TASK ELEMENT 6 STANDARD Grade ARP-8 Window EK-1302 actions: ENSURE running standby Shield Cooling Pump P-77A OR P-77B CHECK Shield Cooling Surge Tank T-62 level normal Window EK-1303 actions: CHECK running Shield Cooling Pump P-77A OR P-77B T-62 level checked: level is stable. S  U Comment: Evaluator Note: 1st action in each alarm is same action as in Task Element #5     Candidate may check Containment Sump level.
Validation Time:   10 minutes         Time Critical:     NO Candidate:
JPM: SYSTEM H PALISADES NUCLEAR PLANT Page 6 of 8 SEPTEMBER 2014   Proc. Step TASK ELEMENT 7 STANDARD Grade -- Report to CRS status of Shield Cooling System. Reports been removed from service. P-77B was manually started and is in service since P-77A tripped and P-77B did not auto start. S  U Comment:     END OF TASK JPM: SYSTEM H PALISADES NUCLEAR PLANT Page 7 of 8 SEPTEMBER 2014 SIMULATOR OPERATOR INSTRUCTIONS   Reset to any at power IC. Create Event Trigger 1 (red light going off on CV-): Event: .not.zlo1p(113) Action: leave blank   Create Event Trigger 2 (when P-77B HS taken to START position): Event: zdi1p(121) Action: dor P-77B-1   Create Event Trigger 3 (when P-77A HS taken to TRIP position): Event: zdi1p(106) Action: dmf ANN-K-13-01   Insert the following overrides on Panel C-08: P-77B-1, Shield Clg P-77B Standby, final value = OFF Tie the following to Event Trigger #1: o P-77A-2, Shield Clg P-77A Trip, final value = ON o P-77A-4, Shield Clg P-77A NA Close, final value =OFF o ANN-K-13-01, Reactor Shield CLG Pump Trip, final value = ON JPM: SYSTEM H PALISADES NUCLEAR PLANT Page 8 of 8 SEPTEMBER 2014 CANDIDATE CUE SHEET   (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)   INITIAL CONDITIONS:   Plant is at full power -29, Shield Cooling System, section 7.1.1. INITIATING CUES: The CRS directs you to transfer Shield Cooling Coils per SOP-29, Shield Cooling System, section 7.1.2 REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE     JPM: RO/SRO-I/SRO-U SYS I TITLE: ENERGIZE BUS 1C FROM STARTUP TRANSFORMER 1-2 LOCALLY       CANDIDATE:   EXAMINER:
Time Start: ________         Time Finish:       ________
JPM SYSTEM I PALISADES NUCLEAR PLANT Page 2 of 12 SEPTEMBER 2014  JOB PERFORMANCE MEASURE DATA PAGE   Task: Perform Actions Specified In Alternate Safe Shutdown Procedure (AOP-41) Alternate Path: YES Facility JPM #: PL-OPS-ONP-014J K/A: 068AA1.10   Importance: RO: 3.7   SRO: 3.9 K/A Statement: Ability to operate/or monitor the following as they apply to the Control Room Evacuation: Power distribution: ac and dc Task Standard: Bus 1C is energized from Startup Transformer 1-2 Preferred Evaluation Location: Simulator ____ In Plant __X__ Preferred Evaluation Method: Perform ____ Simulate __X__
Performance Time:       ________ minutes Performance Rating:     SAT______         UNSAT ______
Comments:
Examiner: _______________________________                     Date:   ______________
Signature PALISADES NUCLEAR PLANT                   Page 2 of 8                       SEPTEMBER 2014
 
JPM: SYSTEM H EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:
SOP-29, Shield Cooling System, section 7.1.2 ARP-8, Safeguards Safety Injection and Isolation Scheme EK-13 (EC-13),
windows 1, 2, and 3 Also see Simulator Operator Instructions (last page of this document).
READ TO CANDIDATE DIRECTION TO CANDIDATE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
Plant is at full power B Shield Cooling Coil is in service per SOP-29, Shield Cooling System, section 7.1.1.
INITIATING CUES:
The CRS directs you to transfer Shield Cooling Coils per SOP-29, Shield Cooling System, section 7.1.2.
PALISADES NUCLEAR PLANT                     Page 3 of 8                       SEPTEMBER 2014
 
JPM: SYSTEM H Evaluator Cue: Provide a working copy of SOP-29, Section 7.1.2.
Proc. Step             TASK ELEMENT 1                                       STANDARD                               Grade CHECK Shield Cooling System in operation       No actions needed since this is status provided in initial 7.1.2.a                                                  conditions.
S U (refer to Section 7.1.1).
Comment:
Proc. Step             TASK ELEMENT 2                                       STANDARD                               Grade OPEN Inlet Valve for coil set to be placed in operation:
Coil A CV-0932 opened using key #141: red light b                                                                                                                  S U Coil A CV-0932                                  ON, green light OFF Coil B CV-0934 Comment:
Evaluator Note: EK-1303, Reactor Shield Clg Lo Flo, may alarm and then clear when this step is performed. Use of ARP not required to complete Critical portion of this step.
CRITICAL STEP Proc. Step             TASK ELEMENT 3                                       STANDARD                               Grade CLOSE Inlet Valve for coil set to be removed from operation:
Coil B CV-0934 closed using key #142: red light c                                                                                                                  S U Coil A CV-0932                                  OFF, green light ON Coil B CV-0934 Comment:
Evaluator Cue: If candidate references ARP-8, provide working copy of appropriate alarm windows (1, 2, and or 3).
Evaluator Note: When CV-0934 red light goes off, then P-77A will trip.
CRITICAL STEP PALISADES NUCLEAR PLANT                         Page 4 of 8                                 SEPTEMBER 2014
 
JPM: SYSTEM H Proc. Step             TASK ELEMENT 4                                       STANDARD                   Grade EK-1303 checked and IS alarming.
CHECK Annunciator EK-1303, "Reactor           The following alarms are also alarming:
d                                                                                                    S U Shield Clg Lo Flo" CLEAR.                     EK-1301, Shield CLG Pumps Trip EK-1302, Shield CLG Pumps Disch Low Press Comment:
Evaluator Cue: If asked as CRS for direction, respond to follow procedures.
EVALUATOR NOTE: Alternate Path begins here: covered in task elements 5 and 6.
Proc. Step             TASK ELEMENT 5                                       STANDARD                   Grade Window EK-1301 actions:
P-77B handswitch taken to START and then ENSURE running standby Shield              released: red light ON, green light OFF ARP-8        Cooling Pump P-77A OR P-77B                                                                S U P-77A handswitch taken to TRIP and released PLACE control switch for tripped pump (NOT a critical task element) to TRIP position Comment:
CRITICAL STEP Proc. Step             TASK ELEMENT 6                                       STANDARD                   Grade Window EK-1302 actions:
ENSURE running standby Shield Cooling Pump P-77A OR P-77B CHECK Shield Cooling Surge Tank ARP-8        T-62 level normal                         T-62 level checked: level is stable.            S U Window EK-1303 actions:
CHECK running Shield Cooling Pump P-77A OR P-77B Comment:
Evaluator Note: 1st action in each alarm is same action as in Task Element #5 Candidate may check Containment Sump level.
PALISADES NUCLEAR PLANT                         Page 5 of 8                               SEPTEMBER 2014
 
JPM: SYSTEM H Proc. Step           TASK ELEMENT 7                                         STANDARD                     Grade Reports A Coil is in service and B Coil has Report to CRS status of Shield Cooling       been removed from service. P-77B was
    --                                                                                                    S U System.                                      manually started and is in service since P-77A tripped and P-77B did not auto start.
Comment:
END OF TASK PALISADES NUCLEAR PLANT                       Page 6 of 8                               SEPTEMBER 2014
 
JPM: SYSTEM H SIMULATOR OPERATOR INSTRUCTIONS Reset to any at power IC.
Create Event Trigger 1 (red light going off on CV-0934, B Shield Clg Coil Inlet):
Event: .not.zlo1p(113) Action: leave blank Create Event Trigger 2 (when P-77B HS taken to START position):
Event: zdi1p(121) Action: dor P-77B-1 Create Event Trigger 3 (when P-77A HS taken to TRIP position):
Event: zdi1p(106) Action: dmf ANN-K-13-01 Insert the following overrides on Panel C-08:
P-77B-1, Shield Clg P-77B Standby, final value = OFF Tie the following to Event Trigger #1:
o P-77A-2, Shield Clg P-77A Trip, final value = ON o P-77A-4, Shield Clg P-77A NA Close, final value =OFF o ANN-K-13-01, Reactor Shield CLG Pump Trip, final value = ON PALISADES NUCLEAR PLANT                 Page 7 of 8                     SEPTEMBER 2014
 
JPM: SYSTEM H CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
Plant is at full power B Shield Cooling Coil is in service per SOP-29, Shield Cooling System, section 7.1.1.
INITIATING CUES:
The CRS directs you to transfer Shield Cooling Coils per SOP-29, Shield Cooling System, section 7.1.2 PALISADES NUCLEAR PLANT                  Page 8 of 8                    SEPTEMBER 2014
 
REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I/SRO-U SYS I TITLE: ENERGIZE BUS 1C FROM STARTUP TRANSFORMER 1-2 LOCALLY CANDIDATE:
EXAMINER:
 
JPM SYSTEM I JOB PERFORMANCE MEASURE DATA PAGE Task:   Perform Actions Specified In Alternate Safe Shutdown Procedure (AOP-41)
Alternate Path: YES Facility JPM #: PL-OPS-ONP-014J K/A: 068AA1.10           Importance:       RO: 3.7       SRO: 3.9 K/A Statement: Ability to operate/or monitor the following as they apply to the Control Room Evacuation: Power distribution: ac and dc Task Standard: Bus 1C is energized from Startup Transformer 1-2 Preferred Evaluation Location: Simulator       ____       In Plant   __X__
Preferred Evaluation Method:       Perform     ____       Simulate   __X__


==References:==
==References:==
AOP-41, Alternate Safe Shutdown Procedure     EOP Supplement 29, Restore Buses 1C, 1D, 1E From Offsite Power Validation Time: 15 minutes Time Critical: NO   Candidate:   Time Start: ________ Time Finish: ________ Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______ Comments:     Examiner: _______________________________ Date: ______________ Signature JPM SYSTEM I PALISADES NUCLEAR PLANT Page 3 of 12 SEPTEMBER 2014 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:     AOP-41   EOP Supplement 29, Restore Buses 1C, 1D, 1E From Offsite Power,Section 3.0, Locally Energize Bus 1C and 1D From Startup XFRM 1-2 Also see Simulator Operator Instructions (last page of this document). READ TO CANDIDATE DIRECTION TO CANDIDATE: I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:   Control Room is not habitable. Reactor has been tripped and all rods have been inserted into the core. Bus 1C and Bus 1D are de-energized. Startup Power Transformer 1-2 is available. The control power circuit for breaker 152-106 has been damaged. INITIATING CUES: During performance of AOP-41, "Alternate Safe Shutdown Procedure" Step 15.1.a, the CRS directs you to energize Bus 1C from Startup Transformer 1-2 locally using EOP Supplement 29 section 3.0.
AOP-41, Alternate Safe Shutdown Procedure EOP Supplement 29, Restore Buses 1C, 1D, 1E From Offsite Power Validation Time:   15 minutes         Time Critical: NO Candidate:
JPM SYSTEM I PALISADES NUCLEAR PLANT Page 4 of 12 SEPTEMBER 2014 Evaluator Cue: Provide a Working Copy of EOP Supplement 29. Proc. Step TASK ELEMENT 1 STANDARD Grade n/a LOCATE EOP Supplement 29 EOP Supplement 29 LOCATED S U Comment: Evaluator Cue: If asked, provide candidate a Working Copy of AOP-41 step 15.1.a. Proc. Step TASK ELEMENT 2 STANDARD Grade 3.0 1.a IF Bus 1C is NOT ENERGIZED, THEN PERFORM the following: a. ENSURE OPEN Safeguards/Station Power Incoming Breaker to Bus 1C, 152-105 ENSURES OPEN Safeguards/Station Power Incoming Breaker 152-105 is open by VERIFYING Breaker 152-105 position indication inside the breaker cubicle indicates OPEN S  U Comment: Evaluator Note: The breaker status lights for breakers 152-105, 152-106 and 152-107 will not be lit due to breaker 72-307 being tripped Evaluator Cue: If asked about the breaker status lights for breakers 152-105, 152-106 or 152-107, cue that they are not lit. Evaluator Cue: If the position indication inside of 152-105 is checked, cue that breaker 152-105 indicates OPEN     Proc. Step TASK ELEMENT 3 STANDARD Grade 3..0 1.b IF Bus 1C is NOT ENERGIZED, THEN PERFORM the following: b. OBTAIN a Remote-Local-Transfer switch handle from the cubicle above Dilution Water Pump Breaker, 152-102 DESCRIBES/OBTAINS the Remote-Local-Transfer switch handle from cubicle above the Dilution Water Pump Breaker (152-102). S  U Comment:   CRITICAL STEP JPM SYSTEM I PALISADES NUCLEAR PLANT Page 5 of 12 SEPTEMBER 2014 Proc. Step TASK ELEMENT 4 STANDARD Grade 3.0 1.c IF Bus 1C is NOT ENERGIZED, THEN PERFORM the following: c. PLACE Remote-Local-Transfer switch, HS-152-106RLTS, to the LOCAL position to isolate Startup Power Incoming Breaker to Bus 1C, 152-106 Simulates or describes PLACING HS-152-106 RLTS in "LOCAL" position S  U Comment: Evaluator Cue: After simulated operation of the Remote-Local-Transfer switch, the breaker 152-106 status lights on front of breaker door remain NOT lit (i.e. red, white, and green lights are NOT illuminated). CRITICAL STEP EVALUATOR NOTE: Alternate Path begins here: covered in task element 5.
Time Start: ________         Time Finish:     ________
JPM SYSTEM I PALISADES NUCLEAR PLANT Page 6 of 12 SEPTEMBER 2014 Proc. Step TASK ELEMENT 5 STANDARD Grade 3.0 1.d.1) IF Bus 1C is NOT ENERGIZED, THEN PERFORM the following: d. IF breaker status lights do NOT light after operating the Remote-Local-Transfer switch, THEN PERFORM the following: 1) ENSURE CLOSED Control Power Breaker 72-307 on Panel D11A Operator simulates or describes PLACING Breaker 72-  AND  Operator simulates or describes PLACING Breaker 72-n S  U Comment:  Evaluator Note: The breaker status lights for breakers 152-105, 152-106 and 152-107 will be lit when breaker 72-307 is closed. Evaluator Cue: When operator indicates that he would open Panel D11A to check breaker 72-307, cue him that the handle is in between open and closed. Evaluator Cue: If operator contacts CRS to request permission to reset and close breaker 72-307, cue him that he has CRS permission. Evaluator Cue: When operator indicates that breaker 72-307 will be placed to the tripped position and then to close, cue that the breaker is all the way to the right. Evaluator Cue: When operator checks the breaker status lights on the front on 152-106, cue that breaker 152-106 the green and white light status lights are lit. CRITICAL STEP JPM SYSTEM I PALISADES NUCLEAR PLANT Page 7 of 12 SEPTEMBER 2014 Proc. Step TASK ELEMENT 6 STANDARD Grade 3.0 1.d.2) IF Bus 1C is NOT ENERGIZED, THEN PERFORM the following: d. IF breaker status lights do NOT light after operating the Remote-Local-Transfer switch, THEN PERFORM the following: 2) INSPECT the following fuses: 152-106 Charging Motor Circuit FUZ/1106-2 &deg; LOCAL TRANSFER FUSE FUZ/A1106-3 Determines this step not applicable since the breaker status lights came back on. OR  Operator VERIFIES the 152-106 Charging Motor Circuit FZ/1106-2 and LOCAL TRANSFER FUSE FZ/A1106-3 fuses are not damaged S  U Comment:  Evaluator Cue: IF operator simulates opening breaker door, then provide operator with CUE SHEET #2A (provide Sheet #2B if candidate cannot read fuse block). IF operator simulates opening door above breaker cubical, then provide CUE SHEET#2C Evaluator Note: Operator should point to Charging Motor fuses (upper left) and Local Transfer Fuse (above breaker cubical) Evaluator Cue: If fuses checked for damage, cue the operator: uses are not damaged. Actual cue will be dependent on method of checking (e.g. fuse checking flashlight is lit).     Proc. Step TASK ELEMENT 7 STANDARD Grade 3.0 1.e REMOVE the 152-106 CLOSE AND TRIP CIRCUIT FUZ/A1106-1 fuses from Startup Power Incoming Breaker to Bus 1C, 152-106 Simulates or describes REMOVING the "152-106 CLOSE AND TRIP CIRCUIT FUZ/A1106-1" fuses by pulling them from the fuse holder S  U Comment: Evaluator Cue: When operator simulates opening breaker door, then provide operator with CUE SHEET #2A (provide Sheet #2B if candidate cannot read fuse block) (if not provided in Task Element 6). When operator points to Close and Trip fuses (upper right), then cue the operator: "152-106 CLOSE AND TRIP CIRCUIT FUZ/A1106-1 fuses are removed. CRITICAL STEP JPM SYSTEM I PALISADES NUCLEAR PLANT Page 8 of 12 SEPTEMBER 2014   Proc. Step TASK ELEMENT 8 STANDARD Grade 3.0 1.f PLACE the local breaker handswitch for Startup Power Incoming breaker to Bus 1C, 152-106 to the CLOSE position to energize Bus 1C Simulates or describes PLACING the local breaker hand switch for Startup Power Incoming Breaker 152-106 to "CLOSE" position S  U Comment: Evaluator Note/Cue: Candidate shall determine that use of protective clothing is required per EN-IS-123 Attachment 9.3 page 41 table (see below): use follow-up question after JPM is complete if candidate does not note requirements during step simulation. Cue that use of Arc Face Shield and FR clothing is being simulated. Evaluator Cue: Red light on breaker 152-106 is illuminated. Clothing requirements are NOT part of the critical step. CRITICAL STEP     Proc. Step TASK ELEMENT 9 STANDARD Grade n/a NOTIFY the CRS that Bus 1C is energized from Startup Power CRS NOTIFIED that Bus 1C is energized from Startup Power S U Comment:     END OF TASK JPM SYSTEM I PALISADES NUCLEAR PLANT Page 9 of 12 SEPTEMBER 2014 CANDIDATE CUE SHEET #2C   (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)
Performance Time:       ________ minutes Performance Rating:     SAT______         UNSAT ______
JPM SYSTEM I PALISADES NUCLEAR PLANT Page 10 of 12 SEPTEMBER 2014 CANDIDATE CUE SHEET #2B   (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)
Comments:
JPM SYSTEM I PALISADES NUCLEAR PLANT Page 11 of 12 SEPTEMBER 2014 CANDIDATE CUE SHEET #2A   (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)
Examiner: _______________________________                 Date:   ______________
JPM SYSTEM I PALISADES NUCLEAR PLANT Page 12 of 12 SEPTEMBER 2014 CANDIDATE CUE SHEET   (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)   INITIAL CONDITIONS:   Control Room is not habitable. Reactor has been tripped and all rods have been inserted into the core. Bus 1C and Bus 1D are de-energized. Startup Power Transformer 1-2 is available. The control power circuit for breaker 152-106 has been damaged. INITIATING CUES: During performance of AOP-41, "Alternate Safe Shutdown Procedure" Step 15.1.a, the CRS directs you to energize Bus 1C from Startup Transformer 1-2 locally using EOP Supplement 29 section 3.0.
Signature PALISADES NUCLEAR PLANT                 Page 2 of 12                     SEPTEMBER 2014
NRC REGION III  INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE     JPM: RO/SRO-I SYS J TITLE: MANUALLY START FIRE PUMP P-9A     CANDIDATE:   EXAMINER:
 
JPM SYSTEM J PALISADES NUCLEAR PLANT Page 2 of 7 SEPTEMBER 2014  JOB PERFORMANCE MEASURE DATA PAGE   Task:   Manually start P-9A Fire Pump Alternate Path: YES Facility JPM #: ISDB-JPM-01 K/A: 086A3.01 Importance: RO: 2.9 SRO: 3.3 K/A Statement: Ability to monitor automatic operation of the Fire Protection System including starting mechanisms of fire water pumps. Task Standard: P-9A is in service  Preferred Evaluation Location: Simulator ______  In Plant  __X___ Preferred Evaluation Method: Perform  ______  Simulate __X___ 
JPM SYSTEM I EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:
AOP-41, Alternate Safe Shutdown Procedure, Step 15.1.a EOP Supplement 29, Restore Buses 1C, 1D, 1E From Offsite Power, Section 3.0, Locally Energize Bus 1C and 1D From Startup XFRM 1-2 Also see Simulator Operator Instructions (last page of this document).
READ TO CANDIDATE DIRECTION TO CANDIDATE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
Control Room is not habitable.
Reactor has been tripped and all rods have been inserted into the core.
Bus 1C and Bus 1D are de-energized.
Startup Power Transformer 1-2 is available.
The control power circuit for breaker 152-106 has been damaged.
INITIATING CUES:
During performance of AOP-41, "Alternate Safe Shutdown Procedure" Step 15.1.a, the CRS directs you to energize Bus 1C from Startup Transformer 1-2 locally using EOP Supplement 29 section 3.0.
PALISADES NUCLEAR PLANT                     Page 3 of 12                     SEPTEMBER 2014
 
JPM SYSTEM I Evaluator Cue: Provide a Working Copy of EOP Supplement 29.
Proc. Step             TASK ELEMENT 1                                     STANDARD                     Grade n/a     LOCATE EOP Supplement 29                     EOP Supplement 29 LOCATED                       S U Comment:
Evaluator Cue: If asked, provide candidate a Working Copy of AOP-41 step 15.1.a.
Proc. Step             TASK ELEMENT 2                                     STANDARD                     Grade IF Bus 1C is NOT ENERGIZED, THEN PERFORM the following:                       ENSURES OPEN Safeguards/Station Power 3.0                                                  Incoming Breaker 152-105 is open by
: a. ENSURE OPEN Safeguards/Station                                                         S U 1.a                                                  VERIFYING Breaker 152-105 position indication Power Incoming Breaker to Bus 1C,      inside the breaker cubicle indicates OPEN 152-105 Comment:
Evaluator Note: The breaker status lights for breakers 152-105, 152-106 and 152-107 will not be lit due to breaker 72-307 being tripped Evaluator Cue: If asked about the breaker status lights for breakers 152-105, 152-106 or 152-107, cue that they are not lit.
Evaluator Cue: If the position indication inside of 152-105 is checked, cue that breaker 152-105 indicates OPEN Proc. Step             TASK ELEMENT 3                                     STANDARD                     Grade IF Bus 1C is NOT ENERGIZED, THEN PERFORM the following:
3..0                                                  DESCRIBES/OBTAINS the Remote-Local-
: b. OBTAIN a Remote-Local-Transfer        Transfer switch handle from cubicle above the  S U 1.b          switch handle from the cubicle above   Dilution Water Pump Breaker (152-102).
Dilution Water Pump Breaker, 152-102 Comment:
CRITICAL STEP PALISADES NUCLEAR PLANT                       Page 4 of 12                             SEPTEMBER 2014
 
JPM SYSTEM I Proc. Step             TASK ELEMENT 4                                     STANDARD                 Grade IF Bus 1C is NOT ENERGIZED, THEN PERFORM the following:
3.0        c. PLACE Remote-Local-Transfer           Simulates or describes PLACING HS-152-106 switch, HS-152-106RLTS, to the                                                     S U 1.c                                                  RLTS in "LOCAL" position LOCAL position to isolate Startup Power Incoming Breaker to Bus 1C, 152-106 Comment:
Evaluator Cue: After simulated operation of the Remote-Local-Transfer switch, the breaker 152-106 status lights on front of breaker door remain NOT lit (i.e. red, white, and green lights are NOT illuminated).
CRITICAL STEP EVALUATOR NOTE: Alternate Path begins here: covered in task element 5.
PALISADES NUCLEAR PLANT                       Page 5 of 12                         SEPTEMBER 2014
 
JPM SYSTEM I Proc. Step             TASK ELEMENT 5                                     STANDARD                     Grade IF Bus 1C is NOT ENERGIZED, THEN PERFORM the following:                         Operator simulates or describes PLACING Breaker 72-307 to the TRIP position.
: d. IF breaker status lights do NOT light 3.0          after operating the Remote-Local-       AND                                            S U 1.d.1)        Transfer switch, THEN PERFORM the following:
Operator simulates or describes PLACING
: 1) ENSURE CLOSED Control Power           Breaker 72-307 to the CLOSE position Breaker 72-307 on Panel D11A Comment:
Evaluator Note: The breaker status lights for breakers 152-105, 152-106 and 152-107 will be lit when breaker 72-307 is closed.
Evaluator Cue: When operator indicates that he would open Panel D11A to check breaker 72-307, cue him that the handle is in between open and closed.
Evaluator Cue: If operator contacts CRS to request permission to reset and close breaker 72-307, cue him that he has CRS permission.
Evaluator Cue: When operator indicates that breaker 72-307 will be placed to the tripped position and then to close, cue that the breaker is all the way to the right.
Evaluator Cue: When operator checks the breaker status lights on the front on 152-106, cue that breaker 152-106 the green and white light status lights are lit.
CRITICAL STEP PALISADES NUCLEAR PLANT                         Page 6 of 12                           SEPTEMBER 2014
 
JPM SYSTEM I Proc. Step             TASK ELEMENT 6                                       STANDARD                   Grade IF Bus 1C is NOT ENERGIZED, THEN PERFORM the following:
Determines this step not applicable since the
: d. IF breaker status lights do NOT light   breaker status lights came back on.
after operating the Remote-Local-Transfer switch, THEN PERFORM           OR 3.0          the following:
S U 1.d.2)        2) INSPECT the following fuses:         Operator VERIFIES the 152-106 Charging Motor Circuit FZ/1106-2 and LOCAL 152-106 Charging Motor Circuit        TRANSFER FUSE FZ/A1106-3 fuses are not FUZ/1106-2                            damaged
                &deg; LOCAL TRANSFER FUSE FUZ/A1106-3 Comment:
Evaluator Cue: IF operator simulates opening breaker door, then provide operator with CUE SHEET #2A (provide Sheet #2B if candidate cannot read fuse block). IF operator simulates opening door above breaker cubical, then provide CUE SHEET#2C Evaluator Note: Operator should point to Charging Motor fuses (upper left) and Local Transfer Fuse (above breaker cubical)
Evaluator Cue: If fuses checked for damage, cue the operator: Fuses are not damaged.
Actual cue will be dependent on method of checking (e.g. fuse checking flashlight is lit).
Proc. Step             TASK ELEMENT 7                                       STANDARD                   Grade REMOVE the 152-106 CLOSE AND TRIP 3.0                                                    Simulates or describes REMOVING the "152-CIRCUIT FUZ/A1106-1 fuses from Startup 106 CLOSE AND TRIP CIRCUIT FUZ/A1106-1"       S U 1.e    Power Incoming Breaker to Bus 1C, fuses by pulling them from the fuse holder 152-106 Comment:
Evaluator Cue: When operator simulates opening breaker door, then provide operator with CUE SHEET #2A (provide Sheet #2B if candidate cannot read fuse block) (if not provided in Task Element 6). When operator points to Close and Trip fuses (upper right), then cue the operator: "152-106 CLOSE AND TRIP CIRCUIT FUZ/A1106-1 fuses are removed.
CRITICAL STEP PALISADES NUCLEAR PLANT                         Page 7 of 12                             SEPTEMBER 2014
 
JPM SYSTEM I Proc. Step           TASK ELEMENT 8                                     STANDARD                     Grade PLACE the local breaker handswitch for 3.0                                                Simulates or describes PLACING the local Startup Power Incoming breaker to Bus breaker hand switch for Startup Power Incoming  S U 1.f    1C, 152-106 to the CLOSE position to Breaker 152-106 to "CLOSE" position energize Bus 1C Comment:
Evaluator Note/Cue: Candidate shall determine that use of protective clothing is required per EN-IS-123 Attachment 9.3 page 41 table (see below): use follow-up question after JPM is complete if candidate does not note requirements during step simulation. Cue that use of Arc Face Shield and FR clothing is being simulated.
Evaluator Cue: Red light on breaker 152-106 is illuminated. Clothing requirements are NOT part of the critical step.
CRITICAL STEP Proc. Step           TASK ELEMENT 9                                     STANDARD                     Grade NOTIFY the CRS that Bus 1C is energized     CRS NOTIFIED that Bus 1C is energized from n/a    from Startup Power                          Startup Power S U Comment:
END OF TASK PALISADES NUCLEAR PLANT                     Page 8 of 12                           SEPTEMBER 2014
 
JPM SYSTEM I CANDIDATE CUE SHEET #2C (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)
PALISADES NUCLEAR PLANT       Page 9 of 12           SEPTEMBER 2014
 
JPM SYSTEM I CANDIDATE CUE SHEET #2B (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)
PALISADES NUCLEAR PLANT       Page 10 of 12           SEPTEMBER 2014
 
JPM SYSTEM I CANDIDATE CUE SHEET #2A (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)
PALISADES NUCLEAR PLANT       Page 11 of 12           SEPTEMBER 2014
 
JPM SYSTEM I CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
Control Room is not habitable.
Reactor has been tripped and all rods have been inserted into the core.
Bus 1C and Bus 1D are de-energized.
Startup Power Transformer 1-2 is available.
The control power circuit for breaker 152-106 has been damaged.
INITIATING CUES:
During performance of AOP-41, "Alternate Safe Shutdown Procedure" Step 15.1.a, the CRS directs you to energize Bus 1C from Startup Transformer 1-2 locally using EOP Supplement 29 section 3.0.
PALISADES NUCLEAR PLANT                  Page 12 of 12                  SEPTEMBER 2014
 
NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I SYS J TITLE: MANUALLY START FIRE PUMP P-9A CANDIDATE:
EXAMINER:
 
JPM SYSTEM J JOB PERFORMANCE MEASURE DATA PAGE Task:           Manually start P-9A Fire Pump Alternate Path: YES Facility JPM #: ISDB-JPM-01 K/A:     086A3.01   Importance:       RO:           2.9   SRO:     3.3 K/A Statement: Ability to monitor automatic operation of the Fire Protection System including starting mechanisms of fire water pumps.
Task Standard: P-9A is in service Preferred Evaluation Location: Simulator        ______      In Plant    __X___
Preferred Evaluation Method:      Perform      ______      Simulate    __X___


==References:==
==References:==
SOP- Validation Time: 10 minutes Time Critical: NO   Candidate:   Time Start: ________ Time Finish: ________ Performance Time: ________ minutes Performance Rating: SAT ______ UNSAT ______ Comments:         Examiner: _______________________________ Date: ______________ Signature JPM SYSTEM J PALISADES NUCLEAR PLANT Page 3 of 7 SEPTEMBER 2014 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:   SOP-   READ TO CANDIDATE DIRECTION TO CANDIDATE: I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:   The Plant is shutdown for a refueling outage. A fire at the Cooling Towers requires the use of P-9A, Fire Water Pump, which has NOT automatically started. Jockey Pump P-13 is operating and there are NO Service Water Booster Pumps (P-25A/B/C) in service. INITIATING CUES:   The Shift Manager has directed you to manually start Fire Water Pump P-9A per SOP-21.
SOP-21, Fire Protection System Validation Time:   10 minutes         Time Critical:     NO Candidate:
JPM SYSTEM J PALISADES NUCLEAR PLANT Page 4 of 7 SEPTEMBER 2014 Evaluator Cue: Provide candidate a working copy of SOP-21 (entire procedure). Proc. Step TASK ELEMENT 1 STANDARD Grade n/a Locates correct procedure section SOP-21, Section 7.2.1 LOCATED. S U Comment:       Proc. Step TASK ELEMENT 2 STANDARD Grade 7.2.1.a Press START pushbutton on Local Control Panel Operator simulates pressing START push button on local control panel. S U Comment: Evaluator Cue: P-9A is not operating or discharge pressure is zero. EVALUATOR NOTE: Alternate Path begins here: covered in task elements 3 thru 5. Proc. Step TASK ELEMENT 3 STANDARD Grade 7.2.1.b.1 out to start mechanically Operator simulates pulling the manual ohandle all the way out and holding in this position. S U Comment:   CRITICAL STEP JPM SYSTEM J PALISADES NUCLEAR PLANT Page 5 of 7 SEPTEMBER 2014 Proc. Step TASK ELEMENT 4 STANDARD Grade 7.2.1.b.2 ROTATE the MANUAL LATCH handle counter-clockwise in order to latch the MANUAL OPERATOR T HANDLE. Operator simulates rotating the manual latch handle counter-clockwise and releases the manual operator "T" handle. S  U Comment: Evaluator Cue: Manual Latch handle is rotated counter-clockwise. CRITICAL STEP   Proc. Step TASK ELEMENT 5 STANDARD Grade ---- Verify P-9A is operating Operator verifies pump operating. S U Comment: Evaluator Cue: P-9A is operating and discharge pressure is 153 psig. Proc. Step TASK ELEMENT 6 STANDARD Grade 7.2.1.c IF Attachment 2 is in effect, THEN STOP selected Service Water Booster Pump Operator determines that this step is N/A because Fire Jockey Pump, P-13, was in service. S U Comment:     Proc. Step TASK ELEMENT 7 STANDARD Grade n/a Operator notifies the Control Room that P-9A has been manually started. Control Room notified. S U Comment:     END OF TASK JPM SYSTEM J PALISADES NUCLEAR PLANT Page 6 of 7 SEPTEMBER 2014   SIMULATOR OPERATOR INSTRUCTIONS   N/A JPM SYSTEM J PALISADES NUCLEAR PLANT Page 7 of 7 SEPTEMBER 2014 CANDIDATE CUE SHEET   (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK) INITIAL CONDITIONS:   The Plant is shutdown for a refueling outage. A fire at the Cooling Towers requires the use of P-9A, Fire Water Pump, which has NOT automatically started. Jockey Pump P-13 is operating and there are NO Service Water Booster Pumps (P-25A/B/C) in service. INITIATING CUES:   The Shift Manager has directed you to manually start Fire Water Pump P-9A per SOP-21.
Time Start: ________         Time Finish:       ________
REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE     JPM: RO/SRO-I/SRO-U SYS K TITLE: SUPPLY ALTERNATE SUCTION SOURCE TO AFW PUMP P-8C     CANDIDATE:   EXAMINER:
Performance Time:       ________ minutes Performance Rating:     SAT       ______ UNSAT ______
JPM SYS K PALISADES NUCLEAR PLANT Page 2 of 7 SEPTEMBER 2014  JOB PERFORMANCE MEASURE DATA PAGE   Task: Supply AFW Pumps From Alternate Source IAW EOP Supplement 31 Alternate Path: NO Facility JPM #: PL-OPS-EOP-011J   K/A: CE/E06EA1.1   Importance: RO: 4.0 SRO: 3.9 K/A Statement: Ability to operate and/or monitor the following as they apply to loss of the (Loss of Feedwater): Components, and functions of control and safety systems, including instrumentation, signals, interlocks, failure modes, and automatic and manual features. Task Standard: AFW pump, P-8C, has suction from the Service Water system and its low suction pressure trip reset. Preferred Evaluation Location: Simulator ____ In Plant _X__ Preferred Evaluation Method: Perform ____ Simulate _X__
Comments:
Examiner: _______________________________                   Date:   ______________
Signature PALISADES NUCLEAR PLANT                   Page 2 of 7                       SEPTEMBER 2014
 
JPM SYSTEM J EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:
SOP-21, Fire Protection System READ TO CANDIDATE DIRECTION TO CANDIDATE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
The Plant is shutdown for a refueling outage.
A fire at the Cooling Towers requires the use of P-9A, Fire Water Pump, which has NOT automatically started.
Jockey Pump P-13 is operating and there are NO Service Water Booster Pumps (P-25A/B/C) in service.
INITIATING CUES:
The Shift Manager has directed you to manually start Fire Water Pump P-9A per SOP-21.
PALISADES NUCLEAR PLANT                     Page 3 of 7                       SEPTEMBER 2014
 
JPM SYSTEM J Evaluator Cue: Provide candidate a working copy of SOP-21 (entire procedure).
Proc. Step               TASK ELEMENT 1                                             STANDARD                       Grade n/a     Locates correct procedure section                   SOP-21, Section 7.2.1 LOCATED.                       S U Comment:
Proc. Step               TASK ELEMENT 2                                             STANDARD                       Grade Press START pushbutton on Local Control             Operator simulates pressing START push button on 7.2.1.a  Panel                                              local control panel.
S U Comment:
Evaluator Cue: P-9A is not operating or discharge pressure is zero.
EVALUATOR NOTE: Alternate Path begins here: covered in task elements 3 thru 5.
Proc. Step               TASK ELEMENT 3                                             STANDARD                       Grade Pull the Manual Operator T handle all the way    Operator simulates pulling the manual operator T 7.2.1.b.1 out to start mechanically                           handle all the way out and holding in this position.
S U Comment:
CRITICAL STEP PALISADES NUCLEAR PLANT                             Page 4 of 7                                 SEPTEMBER 2014
 
JPM SYSTEM J Proc. Step               TASK ELEMENT 4                                           STANDARD                           Grade ROTATE the MANUAL LATCH handle counter-            Operator simulates rotating the manual latch handle 7.2.1.b.2 clockwise in order to latch the MANUAL             counter-clockwise and releases the manual operator     S U OPERATOR T HANDLE.                                "T" handle.
Comment:
Evaluator Cue: Manual Latch handle is rotated counter-clockwise.
CRITICAL STEP Proc. Step               TASK ELEMENT 5                                           STANDARD                           Grade
  ----   Verify P-9A is operating                           Operator verifies pump operating.                       S U Comment:
Evaluator Cue: P-9A is operating and discharge pressure is 153 psig.
Proc. Step               TASK ELEMENT 6                                           STANDARD                           Grade IF Attachment 2 is in effect, THEN STOP           Operator determines that this step is N/A because Fire 7.2.1.c  selected Service Water Booster Pump                Jockey Pump, P-13, was in service.
S U Comment:
Proc. Step               TASK ELEMENT 7                                           STANDARD                           Grade Operator notifies the Control Room that P-9A n/a    has been manually started.
Control Room notified.                                 S U Comment:
END OF TASK PALISADES NUCLEAR PLANT                             Page 5 of 7                                 SEPTEMBER 2014
 
JPM SYSTEM J SIMULATOR OPERATOR INSTRUCTIONS N/A PALISADES NUCLEAR PLANT         Page 6 of 7         SEPTEMBER 2014
 
JPM SYSTEM J CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
The Plant is shutdown for a refueling outage.
A fire at the Cooling Towers requires the use of P-9A, Fire Water Pump, which has NOT automatically started.
Jockey Pump P-13 is operating and there are NO Service Water Booster Pumps (P-25A/B/C) in service.
INITIATING CUES:
The Shift Manager has directed you to manually start Fire Water Pump P-9A per SOP-21.
PALISADES NUCLEAR PLANT                Page 7 of 7                      SEPTEMBER 2014
 
REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I/SRO-U SYS K TITLE: SUPPLY ALTERNATE SUCTION SOURCE TO AFW PUMP P-8C CANDIDATE:
EXAMINER:
 
JPM SYS K JOB PERFORMANCE MEASURE DATA PAGE Task:   Supply AFW Pumps From Alternate Source IAW EOP Supplement 31 Alternate Path: NO Facility JPM #: PL-OPS-EOP-011J K/A:     CE/E06EA1.1             Importance:         RO:   4.0     SRO:   3.9 K/A Statement: Ability to operate and/or monitor the following as they apply to loss of the (Loss of Feedwater): Components, and functions of control and safety systems, including instrumentation, signals, interlocks, failure modes, and automatic and manual features.
Task Standard: AFW pump, P-8C, has suction from the Service Water system and its low suction pressure trip reset.
Preferred Evaluation Location: Simulator       ____         In Plant   _X__
Preferred Evaluation Method:     Perform       ____         Simulate   _X__


==References:==
==References:==
EOP Supplement 31   Validation Time: 20 minutes Time Critical: NO   Candidate:   Time Start: ________ Time Finish: ________ Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______ Comments:     Examiner: _______________________________ Date: ______________ Signature JPM SYS K PALISADES NUCLEAR PLANT Page 3 of 7 SEPTEMBER 2014 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:   EOP Supplement 31, Supply AFW Pumps from Alternate Sources   READ TO CANDIDATE DIRECTION TO CANDIDATE: I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you. INITIAL CONDITIONS:   A Reactor trip has occurred. Loss of all Feedwater has occurred and Auxiliary Feedwater Pumps, P-8A and P-8B, are not available. Condensate Storage Tank, T-2, has a very large hole at the bottom of the tank and is empty. AFW Pump, P-8C, has tripped on low suction pressure. P-8C Start Select Switch HS-P8C is in the MANUAL position. Chemistry has been notified that Service Water will be supplied to the Steam Generators. INITIATING CUES: The CRS gives you a locked valve key and directs you to complete section 1.0, steps 1 through 7, of EOP Supplement 31, "Supply AFW Pumps from Alternate Sources," to supply Service Water to P-8C.
EOP Supplement 31, Supply AFW Pumps from Alternate Sources Validation Time:     20 minutes       Time Critical:     NO Candidate:
JPM SYS K PALISADES NUCLEAR PLANT Page 4 of 7 SEPTEMBER 2014 Proc. Step TASK ELEMENT 1 STANDARD Grade n/a Locate copy of EOP Supplement 31 and obtain a locked valve key from control room. EOP Supplement 31 is located. S U Comment: Evaluator Cue: Provide the candidate with a working copy of EOP Supplement 31. Evaluator Cue: Inform the candidate that they have a simulated locked valve key. Proc. Step TASK ELEMENT 2 STANDARD Grade 1.0.1 PLACE P-8C Start Select Switch HS-P-8C to MANUAL. Operator determines this step has been completed per initial conditions. S U Comment:       Proc. Step TASK ELEMENT 3 STANDARD Grade 1.0.2 UNLOCK MV-FW750, AFW Pump P-8C Supply from SWS. Operator simulates unlocking MV-FW750 S U Comment: Evaluator Cue: MV-FW750 is unlocked. CRITICAL STEP   Proc. Step TASK ELEMENT 4 STANDARD Grade 1.0.3 THROTTLE OPEN MV-FW750, AFW Pump P-8C Supply from SWS until water issues from Leak-off valve P-8C Supply from SWS Leak Test, MV-FW759. Operator simulates throttling open MV-FW750 and looks for leakage from leak-off valve MV-FW759. S U Comment: Evaluator Cue: MV-FW750 is throttled open and water is issuing from MV-FW759. CRITICAL STEP JPM SYS K PALISADES NUCLEAR PLANT Page 5 of 7 SEPTEMBER 2014 Proc. Step TASK ELEMENT 5 STANDARD Grade 1.0.4 WHEN water issues from P-8C Supply from SWS Leak Test, MV-FW759, THEN CLOSE MV-FW759. Operator simulates closing MV-FW759. S U Comment: Evaluator Cue: When candidate simulates closing MV-FW759, cue that valve will not turn any further to the right and water is not issuing from MV-FW759. CRITICAL STEP   Proc. Step TASK ELEMENT 6 STANDARD Grade 1.0.5 OPEN MV-FW750, AFW Pump P-8C Supply from SWS. Operator simulates fully opening MV-FW750. S U Comment: Evaluator Cue: When candidate simulates MV-FW750 open, then cue that valve will not turn any further to the left. CRITICAL STEP   Proc. Step TASK ELEMENT 7 STANDARD Grade 1.0.6 UNLOCK AND OPEN AFW Pump P-8C Supply from SWS MV-FW750A. ___ Simulates unlocking MV-FW750A ___ Simulates opening MV-FW-750A S  U Comment: Evaluator Cue: MV-FW-750A is unlocked. When candidate simulates MV-FW750A open, then cue that valve will not turn any further to the left. CRITICAL STEP   Proc. Step TASK ELEMENT 8 STANDARD Grade 1.0.7 NOTIFY Control Room Supervisor or Nuclear Control Operator P-8C AFW pump service water supply is aligned. Operator simulates notifying the Control Room Supervisor or Nuclear Control Operator that P-8C, AFW pump, is aligned to service water. S  U Comment:   END OF TASK JPM SYS K PALISADES NUCLEAR PLANT Page 6 of 7 SEPTEMBER 2014 SIMULATOR OPERATOR INSTRUCTIONS   N/A JPM SYS K PALISADES NUCLEAR PLANT Page 7 of 7 SEPTEMBER 2014 CANDIDATE CUE SHEET   (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK) INITIAL CONDITIONS:   A Reactor trip has occurred. Loss of all Feedwater has occurred and Auxiliary Feedwater Pumps, P-8A and P-8B, are not available. Condensate Storage Tank, T-2, has a very large hole at the bottom of the tank and is empty. AFW Pump, P-8C, has tripped on low suction pressure. P-8C Start Select Switch HS-P8C is in the MANUAL position. Chemistry has been notified that Service Water will be supplied to the Steam Generators. INITIATING CUES: The CRS gives you a locked valve key and directs you to complete section 1.0, steps 1 through 7, of EOP Supplement 31, "Supply AFW Pumps from Alternate Sources," to supply Service Water to P-8C.}}
Time Start: ________         Time Finish:       ________
Performance Time:       ________ minutes Performance Rating:     SAT______         UNSAT ______
Comments:
Examiner: _______________________________                   Date:   ______________
Signature PALISADES NUCLEAR PLANT                   Page 2 of 7                       SEPTEMBER 2014
 
JPM SYS K EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:
EOP Supplement 31, Supply AFW Pumps from Alternate Sources READ TO CANDIDATE DIRECTION TO CANDIDATE:
I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.
INITIAL CONDITIONS:
A Reactor trip has occurred.
Loss of all Feedwater has occurred and Auxiliary Feedwater Pumps, P-8A and P-8B, are not available.
Condensate Storage Tank, T-2, has a very large hole at the bottom of the tank and is empty.
AFW Pump, P-8C, has tripped on low suction pressure.
P-8C Start Select Switch HS-P8C is in the MANUAL position.
Chemistry has been notified that Service Water will be supplied to the Steam Generators.
INITIATING CUES:
The CRS gives you a locked valve key and directs you to complete section 1.0, steps 1 through 7, of EOP Supplement 31, "Supply AFW Pumps from Alternate Sources," to supply Service Water to P-8C.
PALISADES NUCLEAR PLANT                     Page 3 of 7                       SEPTEMBER 2014
 
JPM SYS K Proc. Step             TASK ELEMENT 1                                           STANDARD                   Grade Locate copy of EOP Supplement 31 and n/a    obtain a locked valve key from control         EOP Supplement 31 is located.                     S U room.
Comment:
Evaluator Cue: Provide the candidate with a working copy of EOP Supplement 31.
Evaluator Cue: Inform the candidate that they have a simulated locked valve key.
Proc. Step             TASK ELEMENT 2                                           STANDARD                   Grade PLACE P-8C Start Select Switch HS-P-8C to       Operator determines this step has been completed 1.0.1    MANUAL.                                        per initial conditions.
S U Comment:
Proc. Step             TASK ELEMENT 3                                           STANDARD                   Grade UNLOCK MV-FW750, AFW Pump P-8C 1.0.2    Supply from SWS.
Operator simulates unlocking MV-FW750             S U Comment:
Evaluator Cue: MV-FW750 is unlocked.
CRITICAL STEP Proc. Step             TASK ELEMENT 4                                           STANDARD                   Grade THROTTLE OPEN MV-FW750, AFW Pump P-8C Supply from SWS until water issues from   Operator simulates throttling open MV-FW750 and 1.0.3    Leak-off valve P-8C Supply from SWS Leak       looks for leakage from leak-off valve MV-FW759.
S U Test, MV-FW759.
Comment:
Evaluator Cue: MV-FW750 is throttled open and water is issuing from MV-FW759.
CRITICAL STEP PALISADES NUCLEAR PLANT                         Page 4 of 7                                 SEPTEMBER 2014
 
JPM SYS K Proc. Step             TASK ELEMENT 5                                     STANDARD                         Grade WHEN water issues from P-8C Supply from 1.0.4    SWS Leak Test, MV-FW759, THEN CLOSE           Operator simulates closing MV-FW759.                 S U MV-FW759.
Comment:
Evaluator Cue: When candidate simulates closing MV-FW759, cue that valve will not turn any further to the right and water is not issuing from MV-FW759.
CRITICAL STEP Proc. Step             TASK ELEMENT 6                                     STANDARD                         Grade OPEN MV-FW750, AFW Pump P-8C Supply 1.0.5    from SWS.
Operator simulates fully opening MV-FW750.           S U Comment:
Evaluator Cue: When candidate simulates MV-FW750 open, then cue that valve will not turn any further to the left.
CRITICAL STEP Proc. Step             TASK ELEMENT 7                                     STANDARD                         Grade UNLOCK AND OPEN AFW Pump P-8C Supply         ___ Simulates unlocking MV-FW750A 1.0.6    from SWS MV-FW750A.
S U
___ Simulates opening MV-FW-750A Comment:
Evaluator Cue: MV-FW-750A is unlocked. When candidate simulates MV-FW750A open, then cue that valve will not turn any further to the left.
CRITICAL STEP Proc. Step             TASK ELEMENT 8                                     STANDARD                         Grade NOTIFY Control Room Supervisor or Nuclear     Operator simulates notifying the Control Room 1.0.7    Control Operator P-8C AFW pump service       Supervisor or Nuclear Control Operator that P-8C,   S U water supply is aligned.                      AFW pump, is aligned to service water.
Comment:
END OF TASK PALISADES NUCLEAR PLANT                       Page 5 of 7                                 SEPTEMBER 2014
 
JPM SYS K SIMULATOR OPERATOR INSTRUCTIONS N/A PALISADES NUCLEAR PLANT         Page 6 of 7         SEPTEMBER 2014
 
JPM SYS K CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)
INITIAL CONDITIONS:
A Reactor trip has occurred.
Loss of all Feedwater has occurred and Auxiliary Feedwater Pumps, P-8A and P-8B, are not available.
Condensate Storage Tank, T-2, has a very large hole at the bottom of the tank and is empty.
AFW Pump, P-8C, has tripped on low suction pressure.
P-8C Start Select Switch HS-P8C is in the MANUAL position.
Chemistry has been notified that Service Water will be supplied to the Steam Generators.
INITIATING CUES:
The CRS gives you a locked valve key and directs you to complete section 1.0, steps 1 through 7, of EOP Supplement 31, "Supply AFW Pumps from Alternate Sources," to supply Service Water to P-8C.
PALISADES NUCLEAR PLANT                Page 7 of 7                      SEPTEMBER 2014}}

Revision as of 19:51, 31 October 2019

2014 Palisades Nuclear Plant Initial License Examination As-Administered Operating Test JPMs
ML14307B723
Person / Time
Site: Palisades Entergy icon.png
Issue date: 09/15/2014
From:
NRC/RGN-III
To:
Entergy Nuclear Operations
Reeser, D.
Shared Package
ML13093A486 List:
References
Download: ML14307B723 (173)


Text

NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO ADMIN 1a TITLE: DETERMINE QUADRANT POWER TILT PER PO-3 CANDIDATE:

EXAMINER:

JPM RO ADMIN 1a JOB PERFORMANCE MEASURE DATA PAGE Task: Determine Quadrant Power Tilt per PO-3 Alternate Path: N/A Facility JPM #: 2010 NRC EXAM K/A: G2.1.7 Importance: RO: 4.4 SRO: 4.7 K/A Statement: Ability to evaluate plant performance and make operational judgments based on operating characteristics, reactor behavior, and instrument interpretation.

Task Standard: Four NI Power readings recorded within +/- 1% of key and Quadrant Power Tilt calculated correctly per PO-3 Preferred Evaluation Location: Simulator __X__ In Plant _____

Preferred Evaluation Method: Perform __X__ Simulate _____

References:

PO-3, Alternate Incore and Excore Applications Validation Time: 22 minutes Time Critical: NO Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 8 SEPTEMBER 2014

JPM RO ADMIN 1a EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

PO-3, Alternate Incore and Excore Applications Also see Simulator Operator Instructions (last page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Plant was at full power.

Incores #9 and #35 are inoperable.

Control Rod #11 has dropped into the core.

INITIATING CUES:

During performance of PO-3, Alternate Incore and Excore Applications, the Control Room Supervisor directs you to perform Excore Quadrant Power Tilt per section 5.2 of PO-3.

PALISADES NUCLEAR PLANT Page 3 of 8 SEPTEMBER 2014

JPM RO ADMIN 1a EVALUATOR CUE: Provide candidate with a working copy of PO-3 entire procedure with SRO approval indicated in section 3.1.1 Proc. Step TASK ELEMENT 1 STANDARD Grade Lower and upper excore readings from the Obtain lower and upper excore Upper and Lower NI Detector meters on 5.2.1 readings as required. (SAL, SBL, SCL, S U EC-06 are entered on PO-3, Attachment 2 SDL and SAU, SBU, SCU, SDU).

per the answer key.

Comment:

CRITICAL STEP Proc. Step TASK ELEMENT 2 STANDARD Grade Calculate the sum from the Lower +

Upper excore readings (SA, SB, SC, Lower + Upper excore readings (SA, SB, SC, 5.2.1 SD) SD) summed and entered on PO-3, S U Attachment #2, within per the answer key.

Comment:

CRITICAL STEP Proc. Step TASK ELEMENT 3 STANDARD Grade

1. Calculate the sum of all excore Sum of all excores reading divided by 4 readings divided by 4: calculated and entered on PO-3, 5.2.1 Attachment 2. S U (S = all detectors/4).

Comment:

CRITICAL STEP PALISADES NUCLEAR PLANT Page 4 of 8 SEPTEMBER 2014

JPM RO ADMIN 1a Proc. Step TASK ELEMENT 4 STANDARD Grade Using the formula T EX = [(SX - S)/S],

Att 2 calculate the tilt for each Quadrant.

Calculate the Quadrant Tilt. S U Note Comment:

EVALUATOR NOTE: All four Quadrant Tilts should add up to approximately zero (0).

CRITICAL STEP Proc. Step TASK ELEMENT 5 STANDARD Grade Have another qualified individual verify the Have calculations verified.

5.2.1 calculations. S U Comment:

EVALUATOR NOTE: Sign-off as the other qualified individual verifying the calculation.

Proc. Step TASK ELEMENT 6 STANDARD Grade Operator notifies CRS of completion of Notify the CRS that Excore Quadrant PO-3, Attachment 2, Excore Quadrant n/a Power Tilt has been completed per Power Tilt and recognizes Tech Spec limits S U PO-3, Attachment 2.

are exceeded.

Comment:

EVALUATOR CUE: If candidate does NOT indicate values above 0.05 as being out of tolerance readings, then ask the following:

Are any limits being exceeded?

Answer should include that Flux Tilt limit of less than or equal to 0.05 is specified in LCO 3.2.3, Quadrant Power Tilt CRITICAL STEP (recognize Tech Specs are exceeded)

END OF TASK PALISADES NUCLEAR PLANT Page 5 of 8 SEPTEMBER 2014

JPM RO ADMIN 1a SIMULATOR OPERATOR INSTRUCTIONS SIMULATOR SET UP:

Simulator Setup Instructions:

Full power IC Drop Control Rod #11 fully into the core with RD-11 (Final Value = 2) on PIDRD02 When plant has stabilized, freeze the Simulator and SNAP Use PO-3, Attachment 2 and record/calculate from the Upper and Lower NI Detector meters on EC-06 and use as answer key.

PALISADES NUCLEAR PLANT Page 6 of 8 SEPTEMBER 2014

JPM RO ADMIN 1a Excore Lower Reading (%) Upper Reading (%) Lower + Upper S = ( All Detectors)/4 Excore Quadrant Tilt SAL, SBL, SCL, SDL SAU, SBU, SCU, SDU SA, SB, SC, SD = (SA + SB + SC + SD)/4 TEA, TEB, TEC, TED 5 (CH A) SAL = SAU = SA = SAL + SAU TEA = [(SA-S)/S] QUAD 1

[NI-005 Lower (A)] [NI-005 Upper (B)]

51 (50.5-51.5) 50 (49.5-50.5) 101 (100-102) 0.055 (0.034 to 0.076) 6 (CH B) SBL = SBU = SB = SBL + SBU TEB = [(SB-S)/S] QUAD 3 95.75 (94.75-96.75)

[NI-0065 Lower (A)] [NI-006 Upper (B)]

41 (40.5-41.5) 40 (39.5-40.5) 81 (80-82) -0.154 (-0.17 to -0.13) 7 (CH C) SCL = SCU = SC = SCL + SCU TEC = [(SC-S)/S] QUAD 4

[NI-007 Lower (A)] [NI-007 Upper (B)]

50 (49.5-50.5) 50 (49.5-50.5) 100 (99-101) 0.044 (0.023 to 0.066) 8 (CH D) SDL = SDU = SD = SDL + SDU TED = [(SD-S)/S] QUAD 2

[NI-008 Lower (A)] [NI-008 Upper (B)]

52 (51.5-52.5) 49 (48.5-49.5) 101 (100-102) 0.055 (0.034 to 0.076)

NOTE: The four QPTs should sum to approximately zero.

Comments:

Performed By: ____Pat Person_________________________________ Date: _____Today__________ Time: _______Now______

Calculations Verified By: _____________________________________________________ Date: _______________

After calculations are verified, forward to NSSS and Reactor Engineering Supervisor or designee for final review.

Reactor Engineering Supervisor or designee: _______________________________________ Date: _______________

ANSWER KEY ANSWER KEY ANSWER KEY ANSWER KEY ANSWER KEY ANSWER KEY PALISADES NUCLEAR PLANT Page 7 of 8 SEPTEMBER 2014

JPM RO ADMIN 1a CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

Plant was at full power.

Incores #9 and #35 are inoperable.

Control Rod #11 has dropped into the core.

INITIATING CUES:

During performance of PO-3, Alternate Incore and Excore Applications, the Control Room Supervisor directs you to perform Excore Quadrant Power Tilt per section 5.2 of PO-3.

PALISADES NUCLEAR PLANT Page 8 of 8 SEPTEMBER 2014

NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO ADMIN 1b TITLE: ESTIMATION OF RIA-0631, CONDENSER OFF GAS MONITOR COUNT RATE CANDIDATE:

EXAMINER:

JPM RO ADMIN 1b JOB PERFORMANCE MEASURE DATA PAGE Task: Determine RIA-0631 Count Rate per AOP-24 Alternate Path: N/A Facility JPM #: NEW K/A: G2.1.20 Importance: RO: 4.6 SRO: 4.6 K/A Statement: Ability to interpret and execute procedure steps.

Task Standard: RIA-0631 count rate determined for 0.1 gpm leak rate 1.735E4 cpm (1.73E4 to 1.74E4cpm)

Preferred Evaluation Location: ANY __X___

Preferred Evaluation Method: Perform __X__ Simulate _____

References:

AOP-24, Steam Generator Tube Leak Validation Time: 8 minutes Time Critical: NO Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 8 SEPTEMBER 2014

JPM RO ADMIN 1b EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

AOP-24, Steam Generator Tube Leak ESOMS log printout that includes offgas flow reading of 7 scfm Also see Simulator Operator Instructions (last page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Plant was at full power.

A Steam Generator Tube Leak is in progress.

Crew has entered AOP-24, Steam Generator Tube Leak.

Action Level 2 is in effect.

INITIATING CUES:

During performance of AOP-24, Steam Generator Tube Leak, the Control Room Supervisor directs you to estimate the count rate for RIA-0631, Condenser Off Gas Monitor that would require entry into Action Level Three, utilizing Attachment 1 of the procedure.

PALISADES NUCLEAR PLANT Page 3 of 8 SEPTEMBER 2014

JPM RO ADMIN 1b EVALUATOR CUE: Provide candidate with a working copy of AOP-24.

Proc. Step TASK ELEMENT 1 STANDARD Grade Att 1pg 3 DETERMINE maximum Primary to Candidate determines 0.1 gpm to be value Secondary Leakrate (gpm) based on needed based on AOP-24, Attachment 2, S U Step 1 current Action Level. page 6 and initiating cue.

Comment:

EVALUATOR CUE: If asked as CRS, inform candidate that the rate of change in the primary to secondary leakage is stable/unchanged.

CRITICAL STEP Proc. Step TASK ELEMENT 2 STANDARD Grade Att 1 pg OBTAIN Condenser Off Gas Monitor 3 flow rate (preferred) OR USE last Candidate obtains information. S U known reading recorded in ESOMS Step 2 narrative log if taken within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

Comment:

EVALUATOR CUE: When asked as NPO/CRS, provide ESOMS log sheet that includes Offgas flowrate = 7 SCFM (Cue Sheet #2)

CRITICAL STEP Proc. Step TASK ELEMENT 3 STANDARD Grade NOTIFY Chemistry to obtain the following parameters from Nuclear Att 1 pg IQ:

3 Bkg = RIA-0631 background reading, Candidate obtains information. S U Step 3 in cpm Rc = Total response factor RIA-0631, (cpm)

Comment:

EVALUATOR CUE: When asked as Chemistry, provide the following:

Background reading = 20 cpm, Total Response Factor = 9.1E6 cpm.

CRITICAL STEP PALISADES NUCLEAR PLANT Page 4 of 8 SEPTEMBER 2014

JPM RO ADMIN 1b Proc. Step TASK ELEMENT 4 STANDARD Grade Att 1 pg CALCULATE RIA-0631 count rate Calculates 1.735E4 cpm 3 S U using the equation provided (1.73E4 to 1.74E4 cpm)

Step 4 Comment:

EVALUATOR NOTE:

R (cpm) = 20 cpm + (0.1 gpm x 1440 min/day x 9.1E6 cpm) (7 SCFM x 1.08E4)

R = 20cpm + 1310.4E6 7.56E4 = 20 cpm + 173E2 = 1.735E4 cpm CRITICAL STEP Proc. Step TASK ELEMENT 5 STANDARD Grade Notify the CRS that RIA-0631 Count Operator notifies CRS of completion of N/A Rate estimation has been completed S U AOP-24, Attachment 1.

per AOP-24, Attachment 1.

Comment:

END OF TASK PALISADES NUCLEAR PLANT Page 5 of 8 SEPTEMBER 2014

JPM RO ADMIN 1b SIMULATOR OPERATOR INSTRUCTIONS

1. N/A PALISADES NUCLEAR PLANT Page 6 of 8 SEPTEMBER 2014

JPM RO ADMIN 1b CANDIDATE CUE SHEET #2 (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

TODAY Shift 2 has assumed the watch.

06:00:00 SM - Mike Kane, CRS - John Mannikko, SE - Bracy Means.

SM U/I - Paul Rhodes.

NCOs - Aaron Miller and Scott Nichols.

NPOs - Gerry Thompson, Joe Hoerle, Larry King, Ernest Wheeler, Keith Myrick, Joe Ford, and Chris McClure.

Plant is in Mode 1, Reactor Power @ 100.0%, MWe gross @ 835.

RAW = 1.06/Green/Low. Integrated Risk: LOW due to MO-3007, HPSI TO REACTOR COOLANT LOOP 1A TRAIN 1, work and Main Transformer scaffold erection.

No items are on the LCO board. [Mannikko, John M, CRS]

TODAY Secondary NPO reports Condenser Off Gas @ 7.0 scfm. Updated PPC pg 540.

09:04:45 [Nichols, Scott L, NCO-T]

TODAY Secondary area checks completed satisfactorily. Blewdown F-13A/B SEAL 09:32:37 WATER SUPPLY STRAINERS and Instrument air compressor C-2C. [Wheeler IV, Ernest, Secondary - Safe S/D NPO]

TODAY Feedwater area checks completed satisfactorily.

10:00:23 Blew down MV-VA50034A, CONTROL ROOM HVAC CAM TRAIN 'A' DRAIN VLV, MV-VA50034B, CONTROL HVAC CAM TRAIN 'B' DRAIN VALVE.

Manually primed P-210A, DIESEL GENERATOR 1-1 K-6A FUEL OIL PRIMING, and P-210B, DIESEL GENERATOR 1-2 K-6B FUEL OIL PRIMING.

T-939, DEMINERALIZED WATER STORAGE TANK @ 63%. [Ford, Joseph D, Feedwater NPO]

TODAY Authorized MT-10, "CORE MONITORING." No Tech Spec LCO Action entered 10:10:00 during this procedure. WO# 52549760-01. [Mannikko, John M, CRS]

TODAY T/G operated IAW NERC/NPOA per SOP-8 section 4.4. [Nichols, Scott L, NCO-T]

10:15:00 PALISADES NUCLEAR PLANT Page 7 of 8 SEPTEMBER 2014

JPM RO ADMIN 1b CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

Plant was at full power.

A Steam Generator Tube Leak is in progress.

Crew has entered AOP-24, Steam Generator Tube Leak.

Action Level 2 is in effect.

INITIATING CUES:

During performance of AOP-24, Steam Generator Tube Leak, the Control Room Supervisor directs you to estimate the count rate for RIA-0631, Condenser Off Gas Monitor that would require entry into Action Level Three, utilizing Attachment 1 of the procedure.

PALISADES NUCLEAR PLANT Page 8 of 8 SEPTEMBER 2014

REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO ADMIN 2 TITLE: PERFORM TSST MO-8 COMPARISON OF T POWER VS ACTUAL POWER CANDIDATE:

EXAMINER:

JPM RO ADMIN 2 JOB PERFORMANCE MEASURE DATA PAGE Task: Perform TSST MO-8 Section 5.2 Comparison of Delta-T Power vs Actual Power Alternate Path: N/A Facility JPM #: BANK K/A: 2.2.12 Importance: RO: 3.7 SRO: 4.1 K/A Statement: Knowledge of surveillance procedures.

Task Standard: Delta-T power for PIP and SPI obtained and compared to actual power. Determine that acceptance criteria not met.

Preferred Evaluation Location: Simulator __X___ In Plant ______

Preferred Evaluation Method: Perform __X___ Simulate ______

References:

MO-8, Palisades Plant Computer (PPC) - PDIL and PPDIL Check and Control Rod Out-Of-Sequence Alarm.

Technical Data Book Figure 1.9 Validation Time: 10 minutes Time Critical: NO Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT ______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 7 SEPTEMBER 2014

JPM RO ADMIN 2 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

MO-8 Technical Data Book READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

The monthly surveillance for PDIL and PPDIL Checks is due. The plant is operating at approximately 100% power.

INITIATING CUES:

You have been directed to perform Section 5.2, "Comparison of Delta-T Power VS Actual Power," of MO-8, Palisades Plant Computer (PPC) - PDIL and PPDIL Check and Control Rod Out-Of-Sequence Alarm.

PALISADES NUCLEAR PLANT Page 3 of 7 SEPTEMBER 2014

JPM RO ADMIN 2 Proc. Step TASK ELEMENT 1 STANDARD Grade Locate procedure. MO-8 located. S U Comment:

EVALUATOR CUE: Provide candidate with a working copy of MO-8 with sign-offs and placekeeping completed such that section 5.2 is ready to be performed.

Proc. Step TASK ELEMENT 2 STANDARD Grade Obtains POWER_PIP_DELTA_T value from 5.2.1 Obtain T Power for PIP node S U PPC MO-8 Trend Screen and records Comment:

EVALUATOR NOTE: Reading should be 94.25+/-0.1%

CRITICAL STEP Proc. Step TASK ELEMENT 3 STANDARD Grade Obtains POWER_SPI_DELTA_T value from 5.2.1 Obtain T Power for SPI node S U PPC MO-8 Trend Screen and records Comment:

EVALUATOR NOTE: Reading should be 100.98+/-0.1%

CRITICAL STEP PALISADES NUCLEAR PLANT Page 4 of 7 SEPTEMBER 2014

JPM RO ADMIN 2 Proc. Step TASK ELEMENT 4 STANDARD Grade Record Actual Power from the Plant heat Obtains HB_PWR_STEADY value from PPC 5.2.3 S U balance, HB_PWR_STEADY. MO-8 Trend Screen and records Comment:

EVALUATOR NOTE: Reading should be 99.98+/-0.1%

CRITICAL STEP Proc. Step TASK ELEMENT 5 STANDARD Grade Recognizes PIP Node T Power is NOT within 4% of actual power, circles in red and notifies CRS.

VERIFY T Power values in step 5.2.1 are 5.2.4 NOT lower than Actual Power in Step 5.2.3 Verifies SPI Node T Power within 4% of actual S U by greater than 4% for each node. power (not critical)

Does NOT sign step 5.2.4 since step criteria is not met.

Comment:

EVALUATOR CUE: If candidate informs CRS that PIP node is not within limits, acknowledge same.

CRITICAL STEP END OF TASK PALISADES NUCLEAR PLANT Page 5 of 7 SEPTEMBER 2014

JPM RO ADMIN 2 SIMULATOR OPERATOR INSTRUCTIONS Reset to IC-17.

Insert RX22B (PIDRX04) final value = 71.

Check the PPC MO-8 Trend Screen to ensure POWER_PIP-DELTA T is more than 4%

lower than HB_PWR_STEADY: [may also use Trend Group 53 (DJB) Trends Sets 2 and 4 for this info].

PALISADES NUCLEAR PLANT Page 6 of 7 SEPTEMBER 2014

JPM RO ADMIN 2 CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

The monthly surveillance for PDIL and PPDIL Checks is due. The plant is operating at approximately 100% power.

INITIATING CUES:

You have been directed to perform Section 5.2, "Comparison of Delta-T Power VS Actual Power," of MO-8, Palisades Plant Computer (PPC) - PDIL and PPDIL Check and Control Rod Out-Of-Sequence Alarm.

PALISADES NUCLEAR PLANT Page 7 of 7 SEPTEMBER 2014

REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO ADMIN 4 TITLE: OBTAIN METEOROLOGICAL DATA FOR EMERGENCY NOTIFICATION FORM CANDIDATE:

EXAMINER:

JPM RO ADMIN 4 JOB PERFORMANCE MEASURE DATA PAGE Task: Obtain Meteorological Data for Emergency Notification Form Alternate Path: N/A Facility JPM #: BANK K/A: 2.4.39 Importance: RO: 3.9 K/A Statement: Knowledge of RO responsibilities in emergency plan implementation Task Standard: EI-6.8, Attachment 2, completed with correct data obtained within 15 minutes per attached key Preferred Evaluation Location: ANY __X___

Preferred Evaluation Method: Perform __X__ Simulate _____

References:

EI-3.0, Communications and Notifications EI-6.0, Offsite Dose Calculation and Recommendations for Protective Actions EI-6.8, Backup and Supplemental Meteorology Validation Time: 10 minutes Time Critical: YES - 12 Minutes Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 9 SEPTEMBER 2014

JPM RO ADMIN 4 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

EI-6.8 Also see Simulator Operator Instructions (last page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

The Shift Manager, acting as the Site Emergency Director, has declared an Alert condition.

A thunderstorm is in progress and the onsite meteorological data system is out of service due to a lightning strike.

The Shift Manager has printed out data from the WSI Weather System per EI-6.8, Backup and Supplemental Meteorology, steps 5.1.1 through 5.1.6.

Today is May 24th, the current time is 0810.

INITIATING CUES:

The Shift Manager has directed you to complete EI-6.8 step 5.1.10 (i.e. fill out of EI-6.8) by using the WSI data printout and steps 5.1.7 through 5.1.9.

The Shift Manager requires this data to complete EI-3, Attachment 1, Palisades Event Notification Form.

THIS JPM IS TIME CRITICAL PALISADES NUCLEAR PLANT Page 3 of 9 SEPTEMBER 2014

JPM RO ADMIN 4 EVALUATOR CUE: Provide candidate with a Working Copy of EI-6.8, Backup and Supplemental Meteorology and second cue sheet (WSI data printout).

Proc. Step TASK ELEMENT 1 STANDARD Grade Obtain meteorological data from the WSI Printout: Wind for hourly observation in On EI-6.8 Att. 2 data recorded as follows:

5.1.10 Benton Harbor is 1511 which means S U wind direction is from 150 degrees Wind Direction = 150 Comment:

EVALUATOR NOTE: Applicant uses steps 5.1.7 through 5.1.9 to identify data from the WSI printout and then records data using step 5.1.10.

CRITICAL STEP Proc. Step TASK ELEMENT 2 STANDARD Grade Obtain meteorological data from the WSI Printout: Wind for hourly observation in On EI-6.8 Att. 2 data recorded as follows:

5.1.10 Benton Harbor is 1511 which means S U wind speed is 11 mph Wind Speed = 11 mph Comment:

CRITICAL STEP Proc. Step TASK ELEMENT 3 STANDARD Grade Obtain meteorological data from the WSI Printout: PS for hourly observation in On EI-6.8 Att. 2 data recorded as follows:

5.1.10 S U Benton Harbor is D Stability Class = D Comment:

CRITICAL STEP PALISADES NUCLEAR PLANT Page 4 of 9 SEPTEMBER 2014

JPM RO ADMIN 4 Proc. Step TASK ELEMENT 4 STANDARD Grade On EI-6.8 Att. 2 data recorded as follows:

Date: Todays date EI-6.8, Attachment 2 completed:

n/a *Time: Current time -within 12 minutes from S U Date:, Time:, Completed By:

start of JPM Completed By: Operators name Comment:

CRITICAL STEP

  • Time is only portion of critical step Proc. Step TASK ELEMENT 5 STANDARD Grade Notify the CRS that EI-6.8 Attachment 2 Operator notifies CRS of completion of EI-6.8, n/a completed. Attachment 2. S U Comment:

END OF TASK PALISADES NUCLEAR PLANT Page 5 of 9 SEPTEMBER 2014

JPM RO ADMIN 4 SIMULATOR OPERATOR INSTRUCTIONS

1. N/A PALISADES NUCLEAR PLANT Page 6 of 9 SEPTEMBER 2014

Proc No EI-6.8 Attachment 2 Revision 6 Page 1 of 1 BACKUP AND SUPPLEMENTAL METEOROLOGY WORKSHEET ANSWER KEY ANSWER KEY ANSWER KEY ANSWER KEY ANSWER KEY

1. Wind Direction = __150____ Degrees From
2. Wind Speed = ___11_____ mph
3. Stability Class = D Date: __TODAY_____ Time: __NOW___ Completed By: __JOE OPERATOR_______

ANSWER KEY ANSWER KEY ANSWER KEY ANSWER KEY ANSWER KEY PALISADES NUCLEAR PLANT Page 7 of 9 SEPTEMBER 2014

JPM RO ADMIN 4 CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

MOSPAL 00 DATE/GMT 24/18 25/00 25/06 25/12 25/18 26/00 26/06 26/12 DATE/EST 24/13 24/19 25/01 25/07 25/13 25/19 26/01 26/07 WIND-MP 1111 2109 3303 0910 0711 0813 0811 0610 CLDS-1 10 10 10 10 10 10 8 2 HGT-FT 5200 5450 4750 3750 4650 5500 5600 4500 PAS C C C C C D D D

+USINFO BEH, MKG YWZQ OBSERVATIONS FOR 8AM(13Z) 24-MAY-11 STATION NAME WIND PS BENTON HARBOR, MI 1511 D MUSKEGON, MI 1011 D PALISADES NUCLEAR PLANT Page 8 of 9 SEPTEMBER 2014

JPM RO ADMIN 4 CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

The Shift Manager, acting as the Site Emergency Director, has declared an Alert condition.

A thunderstorm is in progress and the onsite meteorological data system is out of service due to a lightning strike.

The Shift Manager has printed out data from the WSI Weather System per EI-6.8, Backup and Supplemental Meteorology.

Today is May 24th, the current time is 0810.

INITIATING CUES:

The Shift Manager has directed you to complete EI-6.8 step 5.1.10 (i.e. fill out of EI-6.8) by using the WSI data printout and steps 5.1.7 through 5.1.9.

The Shift Manager requires this data to complete EI-3, Attachment 1, Palisades Event Notification Form.

THIS JPM IS TIME CRITICAL PALISADES NUCLEAR PLANT Page 9 of 9 SEPTEMBER 2014

NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: SRO ADMIN 1a TITLE: DETERMINE AVERAGE QUALIFIED CET TEMPERATURE AND SUB-COOLING VALUE CANDIDATE:

EXAMINER:

JPM No. SRO ADMIN 1a JOB PERFORMANCE MEASURE DATA PAGE Task: Determine Primary Coolant System sub-cooled margin using all available methods Alternate Path: N/A Facility JPM #: PL-OPS-EOP-024J K/A: 2.1.7 Importance: RO:4.4 SRO: 4.7 K/A Statement: Ability to evaluate plant performance and make operational judgments based on operating characteristics, reactor behavior, and instrument interpretation.

Task Standard: Average CET Temperature correctly calculated and sub-cooling value determined.

Preferred Evaluation Location: Simulator _X_ In Plant ______

Preferred Evaluation Method: Perform _X_ Simulate ______

References:

SOP-34 EOP Supplement 1 Validation Time: 15 minutes Time Critical: NO Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 9 September 2014

JPM No. SRO ADMIN 1a EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

SOP-34, revision 22 EOP Supplement 1, revision 5 Also see Simulator Operator Instructions (last page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

A loss of off-site power has resulted in a Reactor trip from 100% power Buses 1C and 1D are energized from their D/Gs EOP-8.0 is in use The PPC is inoperable INITIATING CUES:

The CRS has directed you to determine PCS sub-cooling value in accordance with SOP-34, Attachment 5, using all available Qualified CET readings.

PALISADES NUCLEAR PLANT Page 3 of 9 September 2014

JPM No. SRO ADMIN 1a EVALUATOR CUE: Provide candidate with a working copy of SOP-34 Attachment 5.

Proc. Step TASK ELEMENT 1 STANDARD Grade Operator records qualified CET temperatures as read from the CET recorders (TR-0101A1. TR-0101A2, TR-0101B1, TR-0101B2) on Panel C-11A Obtain at least 2 Qualified CET readings per 1.a core quadrant from the CET recorders.

and the time. At least two (2) qualified CET readings S U per quadrant required. The readings are recorded in section 2. Per CRS direction in the initiating cue, all 16 readings will be taken.

Comment:

Evaluator Note: Verify data taken by Operator CRITICAL STEP Proc. Step TASK ELEMENT 2 STANDARD Grade Operator sums the CET readings (recorded in CALCULATE the average of the temperature section 2), then divides the sum by the number of 1.b readings used. CETs used (8 minimum) to obtain the average CET S U temperature (recorded in section 2).

Comment:

Evaluator Note: Verify calculation by Operator with attached answer key.

CRITICAL STEP Proc. Step TASK ELEMENT 3 STANDARD Grade If any individual temperature readings is greater that 15°F higher or lower from the rd average, then: CET # 23 (3 quadrant) will be approximately 19°F 1.c Do not utilize that individual higher than the average. The candidate will S U temperature reading. recalculate excluding this reading.

Return to Step 1a.

Comment:

CRITICAL STEP PALISADES NUCLEAR PLANT Page 4 of 9 September 2014

JPM No. SRO ADMIN 1a Proc. Step TASK ELEMENT 4 STANDARD Grade Operator performs the following:

___ Obtains PCS Pressure reading from PI-0104

___ Determines subcooling using one of the following methods:

Use EOP Supplement 1 OR Steam REFER TO EOP Supplement 1, Pressure Tables to determine saturation Temperature Limit Curves, to determine sub-1.d cooling value utilizing the average temperature temperature for 1750 psia (617F) and S U subtract average CET calculated calculated in step 1.b.

(538F) to obtain 79F (+/- 1F)

Use EOP Supplement 1 OR Steam Tables to the 25F subcooled value for 1750 psia (617-25 = 592F) and then subtract average CET calculated (538F) to obtain 79F (+/- 1F)

Comment:

CRITICAL STEP Proc. Step TASK ELEMENT 5 STANDARD Grade Operator informs CRS of Average Qualified CRS informed that subcooling value is approximately n/a CET Temperature and sub-cooling value. 80°F.

S U Comment:

END OF TASK PALISADES NUCLEAR PLANT Page 5 of 9 September 2014

JPM No. SRO ADMIN 1a SIMULATOR OPERATOR INSTRUCTIONS Reset to IC-17.

Enter ED01 (on PIDED03), reactor should auto trip Perform actions of EOP-1.0 through section 5.0 Restore power to Transformer 13, clear D/G trouble alarms and take manual control of ADVs to stabilize temperature Have SSG turn off PPC monitors Insert overrides for Qualified CET values per attached answer key Insert override for PI-0104 to read 1750 psia.

When natural circulation has developed, freeze Simulator Verify qualified CETs data matches answer key Place calculator at operator station Restore power to Transformer 16 Enter Overrides for Qualified CET readings on C-11A (refer to answer key)

PALISADES NUCLEAR PLANT Page 6 of 9 September 2014

JPM No. SRO ADMIN 1a Answer Key QUALIFIED TIME TIME QUADRANT CET # now now 1 2 536 536 9 547 547 ANSWER KEY 2

10 19 5

11 541 535 539 534 541 535 539 534 16 532 532 ANSWER KEY 3

21 23 25 31 532 559 537 534 532


537 534 ANSWER KEY 35 534 534 27 537 537 30 547 547 4

33 540 540 36 548 548 TOTAL 8632 8073 AVERAGE 539.5 538.2 PALISADES NUCLEAR PLANT Page 7 of 9 September 2014

JPM No. SRO ADMIN 1a

~ 80°F PALISADES NUCLEAR PLANT Page 8 of 9 September 2014

JPM No. SRO ADMIN 1a CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

A loss of off-site power has resulted in a Reactor trip from 100% power Buses 1C and 1D are energized from their D/Gs EOP-8.0 is in use The PPC is inoperable INITIATING CUES:

The CRS has directed you to determine PCS sub-cooling value in accordance with SOP-34, Attachment 5, using all available Qualified CET readings.

PALISADES NUCLEAR PLANT Page 9 of 9 September 2014

NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: SRO ADMIN 1b TITLE: MONITOR PCS HEATUP/COOLDOWN WITH THE PPC CANDIDATE:

EXAMINER:

JPM SRO ADMIN 1b JOB PERFORMANCE MEASURE DATA PAGE Task: Operate the Palisades Plant Computer System Alternate Path: N/A Facility JPM #: PPC-JPM-02 K/A: 2.1.19 Importance: RO: 3.9 SRO: 3.8 K/A Statement: Ability to use plant computers to evaluate system or component status.

Task Standard: PPC setup to monitor the PCS heatup rate and candidate determines that LCO action statement 3.4.3.A needs to be entered due to heatup rate being above the limit.

Preferred Evaluation Location: Simulator __X__ In Plant _____

Preferred Evaluation Method: Perform __X__ Simulate _____

References:

GOP-2, MODE 5 To MODE 3 525°F PO-2, PCS Heatup/Cooldown Operations Validation Time: 20 minutes Time Critical: NO Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 8 SEPTEMBER 2014

JPM SRO ADMIN 1b EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

PO-2, PCS Heatup/Cooldown Operations PPC Cyclic Printout Pages 391, 392, 393 for at least one-hour showing a heatup rate that exceeds the 40F/hr Tech Spec limit (see Simulator setup page).

Separate each set of cycle printouts and staple.

Also see Simulator Operator Instructions (later page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

A Plant refueling has just been completed Shutdown Cooling is NOT in service PCS temperature is approximately 190°F GCL-2, MODE 5 to MODE 3 525°F Checklist is in progress Two PCPs are in service Technical Specification Surveillance Procedure PO-2, PCS Heatup/Cooldown Operations, has just been authorized by the CRS No equipment is out of service, all systems are OPERABLE INITIATING CUES:

The Control Room Supervisor directs you to monitor and record PCS parameters during the heatup using the PPC per PO-2, step 5.1.

PALISADES NUCLEAR PLANT Page 3 of 8 SEPTEMBER 2014

JPM SRO ADMIN 1b EVALUATOR CUE: Provide candidate a working copy of PO-2.

Proc. Step TASK ELEMENT 1 STANDARD Grade Candidate performs one of the following:

SELECT the Operator Mode Support screen from the main menu a. Main menu screen SELECTED, then 5.1.1b Operator Mode Support screen SELECTED SELECT any of the following, as applicable, S U 5.1.1c from main menu screen.

to monitor PCS heatup/cooldown rate:

Page 361 PCS 15 Minute Rate Trend b. Page 361 PCS 15 Minute Trend page SELECTED Comment:

EVALUATOR NOTE: Operator may go straight to PPC page 361 (task element 3).

Proc. Step TASK ELEMENT 2 STANDARD Grade START 15 minute automatic reports as 5.1.1.d.1 follows: F7 key HCR Reports DEPRESSED S U

1. DEPRESS F7 key HCR Reports.

Comment:

CRITICAL STEP Proc. Step TASK ELEMENT 3 STANDARD Grade START 15 minute automatic reports as follows:

5.1.1.d.2 Cyclic Printout Enabled SELECTED S U

2. SELECT the Cyclic Printout Enabled response Comment:

CRITICAL STEP PALISADES NUCLEAR PLANT Page 4 of 8 SEPTEMBER 2014

JPM SRO ADMIN 1b Proc. Step TASK ELEMENT 4 STANDARD Grade START 15 minute automatic reports as follows:

Page 361 PCS 15 Minute Trend page 5.1.1.d.3 3. SELECT the HCR Reports page from S U SELECTED any of the selected heatup/cooldown pages (361, 362, 372, AND 373).

Comment:

CRITICAL STEP Proc. Step TASK ELEMENT 5 STANDARD Grade START 15 minute automatic reports as follows:

4. WHEN the HCR Report page is displayed, SELECT the output device at the bottom right corner of the page Candidate determines that this step is N/A since by performing one of the following "PRINTER_1" is already selected in bottom right-depending on the desired print hand corner. Candidate may perform the 5.1.1.d.4 following: S U location:
a. TYPE a one (1) AND DEPRESS the One (1) is TYPED AND Update Hardkey is "UPDATE" Hardkey to start the reports DEPRESSED.

to print to the control room.

b. TYPE a two (2) AND DEPRESS the "UPDATE" Hardkey to start the reports to print to the TSC.

Comment:

NOTE: The Heatup/Cooldown print out is on a 15 minute timer that is always running.

When the printout is enabled, the next print timeout could be anywhere from 1 second to 15 minutes later.

EVALUATOR: When candidate has completed this step, hand them the printouts of PPC pages 391, 392, and 393 for the last hour. Tell the candidate that the SE did not review the sheets for the last hour and you have just relieved him/her. Ensure the candidate understands that one hour has elapsed.

CRITICAL STEP PALISADES NUCLEAR PLANT Page 5 of 8 SEPTEMBER 2014

JPM SRO ADMIN 1b Proc. Step TASK ELEMENT 6 STANDARD Grade Candidate determines that step 5.2 is N/A.

5. DETERMINE PCS parameters are within allowable limits at least once every Candidate refers to step 5.3 and compares 15 minutes during the heatup/cooldown heatup limits in step 6.0 to the heatup rates 5.1.1.d.5 S U AND INITIAL the PPC Data Sheet. Refer determined on the PPC printout.

to Step 5.2 and Step 5.3. Candidate determines that the heatup rate limit of 40°F hour has been exceeded Comment:

CRITICAL STEP (only critical part is determining heatup rate limit has been exceeded.)

Proc. Step TASK ELEMENT 7 STANDARD Grade IF any PCS parameter exceeds its limit or Candidate determines that LCO 3.4.3 condition A the heatup/cooldown rate exceeds the 5.3.1 needs to be entered because the heatup rate limit S U maximum allowable rate, THEN PERFORM has been exceeded.

the following ...

Comment:

EVALUATOR: When candidate determines that LCO 3.4.3 condition A needs to be entered, end the JPM.

CRITICAL STEP END OF TASK PALISADES NUCLEAR PLANT Page 6 of 8 SEPTEMBER 2014

JPM SRO ADMIN 1b SIMULATOR OPERATOR INSTRUCTIONS IC-3, Ready to come off S/D Cooling.

Preparation of PPC Pages for this JPM:

Turn on PPC Cyclic Printout Remove SDC from service per SOP-3 Allow simulator to run for at least one-hour When at least one-hour of Cyclic Printout pages have finished printing, then preparation is complete Prior to adminstering JPM, remove SDC from service per SOP-3.

ENSURE PPC CYCLIC PRINTOUT IS TURNED OFF AFTER EACH JPM.

PALISADES NUCLEAR PLANT Page 7 of 8 SEPTEMBER 2014

JPM SRO ADMIN 1b CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

A Plant refueling has just been completed Shutdown Cooling is NOT in service PCS temperature is approximately 190°F GCL-2, MODE 5 to MODE 3 525°F Checklist is in progress Two PCPs are in service Technical Specification Surveillance Procedure PO-2, PCS Heatup/Cooldown Operations, has just been authorized by the CRS No equipment is out of service, all systems are OPERABLE INITIATING CUES:

The Control Room Supervisor directs you to monitor and record PCS parameters during the heatup using the PPC per PO-2, step 5.1.

PALISADES NUCLEAR PLANT Page 8 of 8 SEPTEMBER 2014

NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: SRO ADMIN 2 TITLE: REVIEW AND APPROVE A COMPLETED TECHNICAL SPECIFICATION SURVEILLANCE TEST CANDIDATE:

EXAMINER:

JPM SRO ADMIN 2 JOB PERFORMANCE MEASURE DATA PAGE Task: Conduct Surveillance Testing Alternate Path: N/A Facility JPM #: 2012 NRC EXAM K/A: 2.2.12 Importance: SRO: 4.1 K/A Statement: Knowledge of Surveillance Procedures Task Standard: Supervisory Review of MO-29 completed in accordance with MO-29, step 5.3 AND LCO 3.6.6.A entered due to left train Containment Spray inoperable.

Preferred Evaluation Location: ANY _X_

Preferred Evaluation Method: Perform _X_ Simulate ______

References:

ADMIN 9.20, Technical Specification Surveillance and Special Test Program MO-29, Engineered Safety System Alignment Validation Time: 20 minutes Time Critical: NO Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 9 SEPTEMBER 2014

JPM SRO ADMIN 2 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

Completed MO-29, Engineered Safety System Alignment, with one data point for Containment Spray Header pressure (PI-3001) below the acceptance range.

Also include a missed signature date.

ADMIN 9.20, Technical Specification Surveillance and Special Test Program Technical Specifications Technical Specifications Bases RED PEN FOR STUDENT USE READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Its Friday night shift, 2130 hours0.0247 days <br />0.592 hours <br />0.00352 weeks <br />8.10465e-4 months <br />.

You are the on-shift Shift Engineer.

MO-29, Engineered Safety System Alignment, was completed at 2115 hours0.0245 days <br />0.588 hours <br />0.0035 weeks <br />8.047575e-4 months <br />.

The plant is in MODE 1.

INITIATING CUES:

The Shift Manager directs you to complete a supervisory review of completed MO-29, Engineered Safety System Alignment, in accordance with step 5.3 of MO-29.

Evaluator Note: Provide candidate with completed MO-29 with the data point for Containment Spray Header 'B' pressure (PI-3001) below the acceptance range at 61.8 psig. Do not circle the reading in red. Also, include a missed signature date for step 3.1 Authorization.

PALISADES NUCLEAR PLANT Page 3 of 9 SEPTEMBER 2014

JPM SRO ADMIN 2 EVALUATOR CUE: Hand candidate a complete MO-29 Surveillance Test with one spray header pressure (PI-3001) indication below the acceptance criteria.

Proc. Step TASK ELEMENT 1 STANDARD Grade All pages present with all blanks filled in or N/A REVIEW MO-29 to ensure all applicable 5.3.1.a except for the date field of step 3.1 S U components have been inspected.

Authorization.

Comment:

EVALUATOR NOTE: The missed signature date is not a critical task Proc. Step TASK ELEMENT 2 STANDARD Grade Operator reviews section 6.0 of MO-29 and verifies the following:

___ Containment Air Cooler 'A' Fans operated for greater than or equal to 15 minutes.

___ *Containment Spray Header pressure ENSURE entries on MO-29 are circled in gauges (PI-3001 and PI-3001) greater than red for any components found in an 5.3.1.b or equal to 62.0 psig. S U incorrect position OR acceptance criteria not met. ___ "As Found" position of applicable fans, valves, breakers, and controls agrees with "Required Position" listed in MO-29 Checklist (Attachment 1).

___ *All out of tolerance data shall be circled in red.

Comment:

EVALUATOR NOTE: The containment spray header pressure reading for PI-3001 is below the acceptance range. The candidate must recognize this.

  • CRITICAL STEP PALISADES NUCLEAR PLANT Page 4 of 9 SEPTEMBER 2014

JPM SRO ADMIN 2 Proc. Step TASK ELEMENT 3 STANDARD Grade INITIATE a Condition Report in accordance with EN-LI-102, Corrective Action Process, for acceptance criteria not met unless at least one of the following conditions exist:

1. Out of tolerance item is controlled by a previously identified LCO.

Operator determines that this step is applicable 5.3.1.c 2. Component is in position resulting S U and recognizes that a CR should be initiated.

from prior Operations review and approval. To allow alternate position of any component, adequate redundancy shall exist to ensure operability of Engineering Safety System Equipment.

Comment:

EVALUATOR CUE: Inform candidate that CR has been initiated Proc. Step TASK ELEMENT 4 STANDARD Grade IF spray header pressures are less than 62.8 psig, THEN NOTIFY System Engineer to determine if Containment Spray Header Fill can wait until the next scheduled performance of MO-29 based on MO-29 5.3.1.d trend data analysis. Operator notifies System Engineer. S U

1. System Engineer: NOTIFY Planning/Scheduling and Operations when to schedule ESSO-1, Containment Spray Header Fill.

Comment:

EVALUATOR CUE: If asked as System Engineer: report that the containment spray header fill can not wait until the next scheduled performance of MO-29 and they will notify Planning/Scheduling.

PALISADES NUCLEAR PLANT Page 5 of 9 SEPTEMBER 2014

JPM SRO ADMIN 2 Proc. Step TASK ELEMENT 5 STANDARD Grade Operator performs the following for the acceptable criteria and operability sheet:

___

  • Answers #1 NO and signs and provides explanation on page 2 (i.e., Spray Header pressure PI-3001 is below acceptance range) (signature is not part of the critical step)

___

  • Answers #2 NO and signs (signature is not part of the critical step)

___ Completes CAP and WR numbers for #3 COMPLETE Acceptance Criteria and ___ Notifies SM/CRS/SE and signs for #4 5.3.1.e S U Operability Sheet. (signature is not part of the critical step)

___

  • Operator reviews LCO 3.6.6A.1 and determines that left train of Containment Cooling system is inoperable and LCO Action A.1 of LCO 3.6.6 has been entered.

The Yes or NO box will be checked for #5 and justification filled out on page 2. This justification should explain that the plant has 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to restore left train of containment cooling system back to operable status or place the plant in a MODE where the LCO is not applicable.

Comment:

EVALUATOR CUE: If asked, supply candidate with the following:

WR#: 02004567 (not required since this is an Operations activity, per ESSO-1, and is not controlled by Work Order process.)

CR#: CR-PLP-2014-99999.

EVALUATOR CUE: Inform candidate that SM/CRS/SE have been notified.

EVALUATOR CUE: If asked, candidate also performs Step 5. System Engineer will perform Step 6, Tech. Rev.

  • CRITICAL STEP PALISADES NUCLEAR PLANT Page 6 of 9 SEPTEMBER 2014

JPM SRO ADMIN 2 Proc. Step TASK ELEMENT 6 STANDARD Grade 5.3.2 On Shift SRO Reviewed Completed by: Operator signs and dates for SRO Review S U Comment:

END OF TASK PALISADES NUCLEAR PLANT Page 7 of 9 SEPTEMBER 2014

JPM SRO ADMIN 2 SIMULATOR OPERATOR INSTRUCTIONS N/A PALISADES NUCLEAR PLANT Page 8 of 9 SEPTEMBER 2014

JPM SRO ADMIN 2 CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

Its Friday night shift, 2130 hours0.0247 days <br />0.592 hours <br />0.00352 weeks <br />8.10465e-4 months <br />.

You are the on-shift Shift Engineer.

MO-29, Engineered Safety System Alignment, was completed at 2115 hours0.0245 days <br />0.588 hours <br />0.0035 weeks <br />8.047575e-4 months <br />.

The plant is in Mode 1.

INITIATING CUES:

The Shift Manager directs you to complete a supervisory review of completed MO-29, Engineered Safety System Alignment, in accordance with step 5.3 of MO-29.

PALISADES NUCLEAR PLANT Page 9 of 9 SEPTEMBER 2014

REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: SRO ADMIN 3 TITLE: DETERMINE WASTE GAS RELEASE HIGH ALARM SETPOINT CANDIDATE:

EXAMINER:

JPM SRO ADMIN 3 JOB PERFORMANCE MEASURE DATA PAGE Task: Determine setpoint changes to process radiation monitors Alternate Path: N/A Facility JPM #: NEW K/A: 2.3.11 Importance: RO: 3.8 SRO: 4.3 K/A Statement: Ability to control radiation releases.

Task Standard: Correct setpoint is calculated for Waste Gas release Preferred Evaluation Location: Simulator _X_ In Plant ______

Preferred Evaluation Method: Perform _X_ Simulate ______

References:

SOP-18A, Radioactive Waste System CH 6.23, Waste Gas Decay Tank Release SOP-38, Gaseous Process Monitoring System Validation Time: 10 minutes Time Critical: NO Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 8 SEPTEMBER 2014

JPM SRO ADMIN 3 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

SOP-18A, Radioactive Waste System, section 7.5 with placekeeping completed through step g.

Partially completed form CH 6.23-3 Calculator Also see Simulator Operator Instructions (later page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

A Containment purge is not in progress.

RIA-1113, Waste Gas Monitor is operable per DWO-1.

T-101C, Waste Gas Decay Tank, has been authorized for release.

INITIATING CUES:

The Shift Manager asks you to determine RIA-1113 HIGH alarm setpoint per SOP-18A steps 7.5.h through 7.5.j.

PALISADES NUCLEAR PLANT Page 3 of 8 SEPTEMBER 2014

JPM SRO ADMIN 3 Evaluator Cue: Provide Operator a working copy of SOP-18A, section 7.5 placekept through step g AND batch release order, Form CH 6.23-3, page 1 only (last page of JPM)

Proc. Step TASK ELEMENT 1 STANDARD Grade

___ Operator depresses HS-2317 for >1 minute and releases

___ Operator reads background cpm 7.5.h Operator reads RIA-1113 background S U

___ RECORD cpm on CH Form 6.23-3, WGDT Release Authorization and checks Purge RIA-1113 Box Comment:

Evaluator Note: Reading should be ~8.3 x 101 to 9.5 x 101 cpm CRITICAL STEP Proc. Step TASK ELEMENT 2 STANDARD Grade

___ DEPRESS and HOLD the Check Source pushbutton on RE-1113

___ Verify the meter indication rises 7.5.i PERFORM a source check of RE-1113 S U

___ RELEASE the Check Source pushbutton

___ RECORD cpm on CH Form 6.23-3, WGDT Release Authorization Comment:

Proc. Step TASK ELEMENT 3 STANDARD Grade

___ Candidate adds RIA-1113 background to the release limit to obtain high alarm DETERMINE Hi Alarm setpoint. (This is the setpoint:

sum of the observed background and the 8.3 x 10 to 9.5 x 10 cpm + 8.5 x 10 1 1 3 7.5.j S U established release limit provided on Form cpm CH 6.23-3.)

___ Determines high alarm setpoint to be 3

8.6 x 10 cpm Comment:

Evaluator Note: (Acceptable range is 8.5 - 8.6 x 103 cpm).

CRITICAL STEP PALISADES NUCLEAR PLANT Page 4 of 8 SEPTEMBER 2014

JPM SRO ADMIN 3 Proc. Step TASK ELEMENT 4 STANDARD Grade Operator returns CH form 6.23-3 to Shift n/a Operator reports task is complete. S U Manager for verification of calculation.

Comment:

Evaluator Note: Role play as SM and inform candidate that you will verify calculation.

END OF TASK PALISADES NUCLEAR PLANT Page 5 of 8 SEPTEMBER 2014

JPM SRO ADMIN 3 SIMULATOR OPERATOR INSTRUCTIONS Reset to any IC Ensure V-6A, Main Exhaust Fan, is in service PALISADES NUCLEAR PLANT Page 6 of 8 SEPTEMBER 2014

JPM SRO ADMIN 3 CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

A Containment purge is not in progress.

RIA-1113, Waste Gas Monitor is operable per DWO-1.

T-101C, Waste Gas Decay Tank, has been authorized for release.

INITIATING CUES:

The Shift Manager asks you to determine RIA-1113 HIGH alarm setpoint per SOP-18A steps 7.5.h through 7.5.j.

PALISADES NUCLEAR PLANT Page 7 of 8 SEPTEMBER 2014

FORM CH 6.23-3 Proc No CH 6.23 Attachment 3 WGDT RELEASE AUTHORIZATION Revision 6 Page 1 of 2 Batch Number WG-TODAY WGDT Number T-101C Release Pressure 93 psig 3

Release Volume 32.5 m Calculated RIA-1113 1

Reading 9.5 x 10 cpm b factor 10 RIA-1113 Alarm 3

Setpoint > Bkg 8.5 x 10 cpm Release Authorization Authorized By Jane Retssup Jane Retssup Today Printed Name and Signature Date Shift Manager/CRS Ralph Manager Ralph Manager Today Printed Name and Signature Date Control Room Operator Main Exhaust Fan in Service V-6A V-6B Ensure at least one exhaust fan is operating prior to releasing a WGDT Purge RIA-1113 Source Check RIA-1113 cpm RIA-1113 Alarm Setpoint > Bkg cpm RIA-1113 Background + cpm RIA-1113 Alarm Setpt = cpm Alarm Set By Alarm Verified By Purge RIA-1113 After Release Reset Alarm to 2500 Alarm Reset By Alarm Reset Verified By Remarks If RIA-1113 is not operational, effluent releases may continue provided that prior to release:

1. At least two independent samples are analyzed; and
2. At least two technically qualified members of the Facility Staff independently verify the release rate calculations and discharge line valving.

Palisades ODCM Appnedix A, Table A-1, Item 1.a, Action 1 PALISADES NUCLEAR PLANT Page 8 of 8 SEPTEMBER 2014

REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: SRO ADMIN 4 TITLE: CLASSIFY EVENT CANDIDATE:

EXAMINER:

JPM SRO ADMIN 4 JOB PERFORMANCE MEASURE DATA PAGE Task: Classify an Event Alternate Path: N/A Facility JPM #: NEW K/A: 2.4.41 Importance: SRO: 4.6 K/A Statement: (2.4.41) Knowledge of the emergency action level thresholds and classifications.

Task Standard: Event classified as an Alert within 15 minutes and completion of Event Notification Form within an additional 12 minutes.

Preferred Evaluation Location: ANY __X__

Preferred Evaluation Method: Perform __X__ Simulate _____

References:

EI-3, Communications and Notification Procedure EI-1, Emergency Classification and Actions Procedure Validation Time: 20 minutes Time Critical: YES Evaluation Location: Simulator __X__ In Plant ______

Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 9 SEPTEMBER 2014

JPM SRO ADMIN 4 EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

SEP SUP 1, Site Emergency Plan Supplement 1 - EAL Wall Charts EI-1, Emergency Classification and Actions Procedure, Attachment 1 EI-3, Communications and Notification Procedure, Attachment 1 Also see Simulator Operator Instructions (later page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

The Plant is in MODE 6 and fuel shuffles in progress, the following events occur:

All offsite power is lost o Buses 1C and 1D are reenergized by D/G 1-1 and D/G 1-2 respectively Air to the Steam Generator (S/G) nozzle dams was lost for several minutes and approximately 90 gallons of PCS drained to the Containment floor o Air to S/G nozzle dams has been restored: dams are no longer leaking Containment closure was established with the exception that the Equipment Hatch was not closed due to the hatch being inadvertently knocked off it's track Shutdown Cooling restoration is delayed and the PCS has risen to 212°F and PCS boil-off has commenced Rising counts indicated on RIA-2326 (Normal Range RGEM)

INITIATING CUES:

You are the Shift Manager (acting as the Emergency Plant Manager). You are to classify the event given the above information and complete the Event Notification Form. No previous event declaration has been made.

This JPM is Time Critical.

PALISADES NUCLEAR PLANT Page 3 of 9 SEPTEMBER 2014

JPM SRO ADMIN 4 EVALUATOR CUE: Candidate may use placard of site emergency plan classifications or provide working copy of EI-1 SEP Supp 1.

Proc.Step TASK ELEMENT 1 STANDARD Grade

1. Determine the Category in which the Initiating Conditions/symptoms best fit from the list of Categories below:

A - Abnormal Rad Levels / Radiological Effluent EI-1 C - Cold Shutdown / Refueling System 6.1.b.1 Refers to SEP Supp 1, MODE 5, 6, or DEF Malfunction S U page and determines Category C applies.

SEP E - Independent Spent Fuel Storage SUPP 1 Installation (ISFSI)

F - Fission Product Barrier Degradation H - Hazards S - System Malfunction Comment:

START TIME FOR CLASSIFICATION:_________

Proc.Step TASK ELEMENT 2 STANDARD Grade

___ Refers to CA4

2. Use the Category identified above and EI-1 ___ Determines per Table C-3 that with SEP Supplement 1 to determine which 6.1.b.2 Emergency Action Level (EAL) threshold CONTAINMENT CLOSURE and PCS integrity not established that an S U has been exceeded. Move from the highest SEP UNPLANNED event results in PCS classification (left) to lowest classification SUPP 1 temperature > 200°F for > Table C-3 (right) when determining the classification.

duration Comment:

CRITICAL STEP PALISADES NUCLEAR PLANT Page 4 of 9 SEPTEMBER 2014

JPM SRO ADMIN 4 Proc.Step TASK ELEMENT 3 STANDARD Grade SEP Declares an Alert per CA4 based on status of Declares Emergency Classification. S U SUPP 1 event.

Comment:

END TIME FOR CLASSIFICATION:_________ (START TIME FOR FORM COMPLETION)

CRITICAL STEP - must be performed within 15 minutes of start of JPM.

Proc.Step TASK ELEMENT 4 STANDARD Grade EI-1

b. Using the "Action" column of Attachment Obtains EI-1, Attachment 1 and performs or 6.2.b 1, perform each action as M (Mandatory), S S U delegates actions.

(Subsequent), or I (If Needed).

Att 1 Comment:

EVALUATOR CUE: Another SRO will perform this task.

PALISADES NUCLEAR PLANT Page 5 of 9 SEPTEMBER 2014

JPM SRO ADMIN 4 Proc.Step TASK ELEMENT 5 STANDARD Grade Palisades Event Notification Form completely EI-3 Completes filling out Palisades Event filled per attached KEY AND form is approved S U Att 1 Notification Form. (Candidate signature/initials, date, and time entered at bottom of form)

  • Comment:

EVALUATOR CUE (provide when applicable as Candidate fills out form):

Hand Candidate EI-6.7 Attachment 1 (meteorological data)

It is a hot sunny day with no rain in the forecast EVALUATOR NOTE: KEY is attached to this JPM.

EVALUATOR NOTE: EI-3, Attachment 2, "Palisades Event Technical Data Sheet" is NOT required during this JPM.

EVALUATOR NOTE: If JPM is conducted in the Simulator, then Candidate may use computer on Control Room island area to prepare this form.

EVALUATOR NOTE: If JPM is conducted in the Simulator, then Candidate may use computer on back-bar of Control Room island area to complete and print this form.

  • The following are the critical parts of this step:

ALERT is checked in "current classification" section Date and time filled in "current classification" section CA4.1 filled in "reason for classification" section OR Cold Shutdown/Refueling System Malfunction checked in "reason for classification" section YES checked in Radiological Release in Progress END TIME FOR FORM COMPLETION:_________

CRITICAL STEP (must be completed within 12 minutes of time listed in Task Element 3)

END OF TASK PALISADES NUCLEAR PLANT Page 6 of 9 SEPTEMBER 2014

Proc No EI-3 Attachment 1 PALISADES EVENT NOTIFICATION FORM Revision 31 Page 1 of 1 Actual Event Drill Plant Contact Information Nuclear Power Plant: _________________________________________

Plant Communicator: __________________ Time of Communication: V.B. ______ 1 S.O.M. ______

NRC ______ Plant Message Number Calling From: Control Room TSC EOF Other______

Call Back Telephone Number: _____________________________________________

Current Classification Unusual Event Alert Site Area Emergency General Emergency Termination This Classification was declared as of: Date: Today Time: Within 15 minutes from start of JPM Reason for Classification Abnormal Rad Levels / Radiological Effluent System Malfunctions Hazards and Other Conditions Affecting Cold Shutdown / Refueling System Malfunction Plant Safety Independent Spent Fuel Storage Installation Events Fission Product Barrier Degradation IC Number: CA4.1 Radiological Release in Progress Due to Event Yes No Protective Action Recommendations None Evacuation of Areas(s): 1 2 3 4 5 In-Place Shelter of Area(s) 1 2 3 4 5 PAR based on: Dose Calculation (Palisades Event Technical Data Sheet required) Plant Status Security Event Other ___________________________________________________________________________________________________

Meteorological Data Wind Direction (degrees): From 270 To 90 Wind Speed (MPH): 12 Stability Class: B Precipitation: Yes No Emergency Director Approval: ________________________________ Date: _________ Time: ________

ANSWER KEY PALISADES NUCLEAR PLANT Page 7 of 9 SEPTEMBER 2014

JPM SRO ADMIN 4 SIMULATOR OPERATOR INSTRUCTIONS No Simulator setup required.

Prepare EI-6.7 Attachment 1 with the following data and then sign and date form:

o Wind Speed is 12 mph o Wind Direction is from 270 degrees o Stablity Class = B It is preferred that this JPM be done separately from the simulator. If, by chance, candidate IS in the simulator while doing this JPM, THEN ensure the IC does NOT have a release in progress.

ENSURE ALL DATA IS CLEARED FROM EP NOTIFICATION COMPUTER ON BACK-BAR OF CRS ISLAND PRIOR TO NEXT USE OF THIS JPM.

PALISADES NUCLEAR PLANT Page 8 of 9 SEPTEMBER 2014

JPM SRO ADMIN 4 CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

The Plant is in MODE 6 and fuel shuffles in progress, the following events occur:

All offsite power is lost o Buses 1C and 1D are reenergized by D/G 1-1 and D/G 1-2 respectively Air to the Steam Generator (S/G) nozzle dams was lost for several minutes and approximately 90 gallons of PCS drained to the Containment floor o Air to S/G nozzle dams has been restored: dams are no longer leaking Containment closure was established with the exception that the Equipment Hatch was not closed due to the hatch being inadvertently knocked off it's track Shutdown Cooling restoration is delayed and the PCS has risen to 212°F and PCS boil-off has commenced Rising counts indicated on RIA-2326 (Normal Range RGEM)

INITIATING CUES:

You are the Shift Manager (acting as the Emergency Plant Manager). You are to classify the event given the above information and complete the Event Notification Form. No previous event declaration has been made.

This JPM is Time Critical.

PALISADES NUCLEAR PLANT Page 9 of 9 SEPTEMBER 2014

NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I/SRO-U SYS A TITLE: GRAVITY FEED BORATION WHILE SHUTDOWN CANDIDATE:

EXAMINER:

JPM SYSTEM A JOB PERFORMANCE MEASURE DATA PAGE Task: Perform gravity feed boration to PCS while shutdown.

Alternate Path: YES Facility JPM #: NEW K/A: 004A4.07 Importance: RO: 3.9 SRO: 3.7 K/A Statement: Ability to manually operate and/or monitor in the control room:

Boration/dilution.

Task Standard: Gravity feed at 33 gpm Charging flow for at least two minutes.

Preferred Evaluation Location: Simulator ___X___ In Plant _____

Preferred Evaluation Method: Perform ___X___ Simulate _____

References:

SOP-2A, Chemical and Volume Control System Validation Time: 10 minutes Time Critical: NO Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 10 SEPTEMBER 2014

JPM SYSTEM A EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

SOP-2A, Chemical and Volume Control System sections 7.1.1, 7.1.2, and 7.5.3 SOP-1C, Primary Coolant System - Heatup section 7.1.1 ARP-4, Primary System Volume Level Pressure Scheme EK-07 (C-12) window 27 Also see Simulator Operator Instructions (later page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Plant is shutdown in MODE 6 with reactor cavity filled All three Charging Pumps are aligned for operation, have been operated within the last 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />, and their seal lube systems have been operated and placed in automatic Charging Pump P-55B has been started per SOP-1C, Primary Coolant System

- Heatup steps 7.1.1.e.2 and g Gravity Feed Paths have been verified operable by a flow test INITIATING CUES:

The CRS directs you to borate the PCS for two minutes using Charging Pump P-55B and the gravity feed method from Boric Acid Storage Tank T-53A per SOP-2A, Chemical and Volume Control System, section 7.5.3.

PALISADES NUCLEAR PLANT Page 3 of 10 SEPTEMBER 2014

JPM SYSTEM A EVALUATOR CUE: Provide candidate with a working copy of SOP-2A front-end up to page 13 AND Section 7.5.3 (2 pages).

Proc. Step TASK ELEMENT 1 STANDARD Grade ENSURE charging flow greater than Candidate determines Charging Pump P-55B is 7.5.3.a 33 gpm as indicated by FIA-0212, Charging S U in service and flow is above 33 gpm.

Line Flow Indicator Alarm.

Comment:

Proc. Step TASK ELEMENT 2 STANDARD Grade Candidate momentarily places handswitch for OPEN Boric Acid Tank Gravity Feed 7.5.3.b MO-2169 to OPEN and eventually observes Red S U Isolation Valve for tank(s) to be used:

light ON and Green light OFF.

Comment:

CRITICAL STEP Proc. Step TASK ELEMENT 3 STANDARD Grade Candidate checks handswitch for CV-2155 in 7.5.3.c CLOSE CV-2155, Make-Up Stop. CLOSE and observes Red light OFF and Green S U light ON.

Comment:

Proc. Step TASK ELEMENT 4 STANDARD Grade Candidate holds handswitch for MO-2087 to 7.5.3.d CLOSE MO-2087, VCT T-54 Outlet. CLOSE and eventually observes Red light OFF S U and Green light ON.

Comment:

CRITICAL STEP PALISADES NUCLEAR PLANT Page 4 of 10 SEPTEMBER 2014

JPM SYSTEM A Proc. Step TASK ELEMENT 5 STANDARD Grade Acknowledge alarm EK-0727 and EK-0735 Candidate acknowledges alarm on Panel C-02

-- S U and refers to ARP. and refers to ARP-4.

Comment:

EVALUATOR CUE: When candidate refers to ARP-4, then provide a working copy of ARP-4 Window 27 and Window 35 EVALUATOR NOTE: Alternate Path begins here: covered in task elements 6 and 7.

Proc. Step TASK ELEMENT 6 STANDARD Grade Determine that Charging Pump P-55B has Candidate dispatches NPO to report on P-55B

-- S U tripped. pump and breaker status.

Comment:

EVALUATOR CUE: If candidate asks for direction on which procedure to use or action to take, then inform Candidate that CRS directs you to continue with the task.

EVALUATOR CUE: If asked as NPO, report P-55B breaker is open (no overcurrent trips) and pump looks normal (not hot).

EVALUATOR NOTE: If candidate does not send NPO to investigate P-55B status, then GO TO Task Element #8.

EVALUATOR CUE: If requested, provide candidate with a working copy of SOP-2A section 7.1.1.

Proc. Step TASK ELEMENT 7 STANDARD Grade Candidate places P-55B handswitch to TRIP and then back to START.

--- Start Charging Pump S U Candidate observes Red light On and Green light Off for P-55B.

Comment:

EVALUATOR NOTE: Candidate may use SOP-2A section 7.1.1 to complete this action (not required to meet Task Standard). If this Task Element was performed, then GO TO Task Element #9.

CRITICAL STEP PALISADES NUCLEAR PLANT Page 5 of 10 SEPTEMBER 2014

JPM SYSTEM A Proc. Step TASK ELEMENT 8 STANDARD Grade Candidate starts P-55A or P-55C by placing respective handswitch to START.

--- Start Charging Pump S U Candidate observes Red light On and Green light Off for Charging Pump that was started.

Comment:

EVALUATOR NOTE: Candidate may use SOP-2A section 7.1.1 to complete this action (not required to meet Task Standard).

CRITICAL STEP Proc. Step TASK ELEMENT 9 STANDARD Grade ENSURE CLOSED MO-2160, SIRWT T-58 Candidate observes MO-2160 Red light OFF 7.5.3.e S U Outlet To Charging Pp P-55A,B,C. and Green light ON.

Comment:

Proc. Step TASK ELEMENT 10 STANDARD Grade Candidate observes FI-0212 flow on Panel C-02 7.5.3.f VERIFY charging flow greater the 33 gpm. S U above 33 gpm.

Comment:

PALISADES NUCLEAR PLANT Page 6 of 10 SEPTEMBER 2014

JPM SYSTEM A Proc. Step TASK ELEMENT 11 STANDARD Grade RESTORE from Gravity Feed Boration as follows: After two minutes, candidate momentarily places handswitch for MO-2087 to OPEN and 7.5.3.g.1 1. OPEN desired suction source for S U eventually observes Red light ON and Green Charging Pumps:

light OFF.

(a) MO-2087, VCT T-54 Outlet Comment:

EVALUATOR CUE: Desired suction source is the VCT CRITICAL STEP Proc. Step TASK ELEMENT 12 STANDARD Grade ENSURE CLOSED:

(a) MO-2169, BAST T-53A Gravity Feed Candidate momentarily places handswitch for 7.5.3.g.2 Isolation. MO-2169 to CLOSE and eventually observes S U Red light OFF and Green light ON.

(b) MO-2170, BAST T-53B Gravity Feed Isolation Comment:

CRITICAL STEP Proc. Step TASK ELEMENT 13 STANDARD Grade IF continued boration from the SIRWT is desired, THEN FLUSH each Charging 7.5.3.g.3 Candidate determines step is not applicable. S U Pump from the SIRWT for at least five minutes.

Comment:

PALISADES NUCLEAR PLANT Page 7 of 10 SEPTEMBER 2014

JPM SYSTEM A Proc. Step TASK ELEMENT 14 STANDARD Grade IF continued boration from the VCT is desired, THEN FLUSH each Charging Candidate continues to operate Charging Pump 7.5.3.g.4 S U Pump from the VCT for at least five for flush.

minutes.

Comment:

EVALUATOR CUE: Flush is in progress and JPM is complete.

END OF TASK PALISADES NUCLEAR PLANT Page 8 of 10 SEPTEMBER 2014

JPM SYSTEM A SIMULATOR OPERATOR INSTRUCTIONS Reset to IC-20 Create Event Trigger 1 to trip Charging Pump:

o Event: .not.ZLO2P(61).this is MO-2087 red light being OFF o Action: IMF CV03B..this trips P55B Create Event Trigger 2 to clear Charging Pump trip when pump restart is attempted:

o Event: ZDI2P(69)this is P-55B handswitch taken to TRIP o Action: DMF CV03B ..deletes P-55B trip malfunction Open Charging Line valves CV-2111, CV-2113, and CV-2115 Ensure open MO-2087, VCT Outlet Start P-55B FREEZE and SNAP into a saved IC PALISADES NUCLEAR PLANT Page 9 of 10 SEPTEMBER 2014

JPM SYSTEM A CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

Plant is shutdown in MODE 6 with reactor cavity filled All three Charging Pumps are aligned for operation, have been operated within the last 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />, and their seal lube systems have been operated and placed in automatic Charging Pump P-55B has been started per SOP-1C, Primary Coolant System

- Heatup steps 7.1.1.e.2 and g Gravity Feed Paths have been verified operable by a flow test INITIATING CUES:

The CRS directs you to borate the PCS for two minutes using Charging Pump P-55B and the gravity feed method from Boric Acid Storage Tank T-53A per SOP-2A, Chemical and Volume Control System, section 7.5.3.

PALISADES NUCLEAR PLANT Page 10 of 10 SEPTEMBER 2014

REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I/SRO-U SYS B TITLE: MANUALLY INITIATE CONTAINMENT ISOLATION CANDIDATE:

EXAMINER:

JPM SYSTEM B JOB PERFORMANCE MEASURE DATA PAGE Task: Perform Containment Isolation initiation Alternate Path: NO Facility JPM #: BANK K/A: 103A2.03 Importance: RO: 3.5 SRO: 3.8 K/A Statement: Ability to (a) predict the impacts of the following malfunctions or operations on the containment system and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of those malfunctions or operations: Phase A and B isolation Task Standard: Manual Containment Isolation initiated with all pathways having at least one isolation valve closed.

Preferred Evaluation Location: Simulator __X__ In Plant _____

Preferred Evaluation Method: Perform __X__ Simulate _____

References:

EOP-4.0, Loss of Coolant Accident EOP Supplement 6, Checksheet for Containment Isolation and CCW Restoration Validation Time: 10 minutes Time Critical: NO Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 7 SEPTEMBER 2014

JPM SYSTEM B EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

EOP-4.0, LOCA Recovery, step 13 EOP Supplement 6, Checksheet for Containment Isolation and CCW Restoration Also see Simulator Operator Instructions (last page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

A Loss of Coolant Accident has occurred.

The Reactor has been tripped and EOP 1.0, "Standard Post Trip Actions" have been performed.

Containment radiation is above 10 R/hr.

Automatic Containment isolation has not occurred.

INITIATING CUES:

During performance of EOP 4.0, "Loss of Coolant Accident Recovery", the Control Room Supervisor directs you to manually initiate Containment isolation, referring to Step 13.

PALISADES NUCLEAR PLANT Page 3 of 7 SEPTEMBER 2014

JPM SYSTEM B Evaluator Cue: Provide candidate with a Working Copy of EOP-4.0, step 13.

Proc. Step TASK ELEMENT 1 STANDARD Grade IF ANY of the following conditions exit:

Containment pressure is greater CIS INITIATED (EK-1126) has not alarmed.

than or equal to 4.0 psig Either HIGH RADIATION INITIATE pushbuttons Any operable Containment Radiation 1 on Panel EC-13 pushed:

EOP- Monitor rises to 1 X 10 R/hr, S U 4.0, 13.a THEN PERFORM ALL of the CHRL-CS following:

CHRR-CS

a. VERIFY CIS INITIATED (EK-1126) is alarmed Comment:

Evaluator Note: Candidate verifies CIS INITIATED (EK-1126) is in alarm once pushbutton is pushed, it is permissible, but not necessary, to push both pushbuttons.

CRITICAL STEP Proc. Step TASK ELEMENT 2 STANDARD Grade IF ANY of the following conditions exit:

Containment pressure is greater than or equal to 4.0 psig EOP Supplement 6 obtained.

Any operable Containment Radiation 1

EOP- Monitor rises to 1 X 10 R/hr, THEN PERFORM ALL of the S U 4.0, 13.b following:

b. VERIFY Containment Isolation, Refer to EOP Supplement 6 Comment:

Evaluator Note: Candidate will attempt to use the laminated version of EOP Supplement 6. For exam security purposes, do NOT allow this. Provide candidate with a working copy of EOP Supplement 6.

PALISADES NUCLEAR PLANT Page 4 of 7 SEPTEMBER 2014

JPM SYSTEM B Proc. Step TASK ELEMENT 3 STANDARD Grade ENSURE CLOSED all valves unless Verifies that all valves closed as required, Supp.6, otherwise specified by the notes. checking them off on the checklist, except for S U 1.0 CWRT Vent Valves, CV-1064 and CV-1065.

Comment:

Evaluator Note: Determining that the CWRT Vent Valves failed to close is the only action needed to satisfactorily perform this critical step.

Evaluator Cue: If asked by candidate what should be done with CV-1064 and CV-1065, RESPONSE: direct candidate to perform EOP Supplement 6.

Proc. Step TASK ELEMENT 4 STANDARD Grade CWRT Vent Valves, CV-1064 and CV-1065 have ENSURE CLOSED all valves unless failed to isolate, otherwise specified by the notes. Handswitches for both CV-1064 and Supp.6, CV-1065 are placed to close. S U 1.0 CV-1064 is verified closed (green light on),

CV-1065 remains open (red light on)

Comment:

Evaluator Note: CV-1064 closes, CV-1065 remains open.

Evaluator Note: Placing the handswitch for CV-1064 to close is the critical component of this step.

Evaluator Cue: If asked by candidate, EOP Supplement 6 Step 2.0 is not required.

CRITICAL STEP Proc. Step TASK ELEMENT 5 STANDARD Grade Report status of EOP Supplement 6 for CRS informed of completion of EOP Supplement n/a Containment Isolation to the CRS. 6 and all containment isolation valves are closed, S U with the exception of CV-1065.

Comment:

END OF TASK PALISADES NUCLEAR PLANT Page 5 of 7 SEPTEMBER 2014

JPM SYSTEM B SIMULATOR OPERATOR INSTRUCTIONS (The following is for more than one JPM):

Use IC 17 (100% power)

Enter malfunction RC04 using Event Trigger 1 Trip Reactor and carry out all EOP 1.0 immediate actions Reduce Final Value of RC04 to 10 after SIAS Trip MFPs after SIAS Verify Containment Radiation is greater than 10R/hr on at least one Containment Area Radiation Monitor Place Letdown Orifice Stop valves to close Allow at least 10% level reduction in each BAST Simulator Setup:

Event Number Event Action WORD DESCRIPTION 2 Zdi1p(731) Dmf wp03a Handswitch for CV-1064 in close 3 Zdi1p(696) Dmf ch05b Right channel CHR push button 4 Zdi1p(696) Dmf ch05a Right channel CHR push button 5 Zdi1p(689) Dmf ch05a Left channel CHR push button 6 Zdi1p(689) Dmf ch05b Left channel CHR push button Malfunction: Malfunction Title: Et: Delay: Location: Ramp: Value:

RC04 PCS Leak 1 N/A PIDRC01 N/A 100 CH05A Auto Initiate Failure Left N/A N/A PIDCH01 N/A True CH05B Auto Initiate Failure Right N/A N/A PIDCH01 N/A True RC22 Failed Fuel Element 1 N/A PIDRC01 N/S 100 WP03A CV-1064 valve binding N/A N/A PIDWP01 N/A 100 WP03B CV-1065 valve binding N/A N/A PIDWP01 N/A 100 Overrides: Overrides Title:

NONE PALISADES NUCLEAR PLANT Page 6 of 7 SEPTEMBER 2014

JPM SYSTEM B CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

A Loss of Coolant Accident has occurred.

The Reactor has been tripped and EOP 1.0, "Standard Post Trip Actions" have been performed.

Containment radiation is above 10 R/hr.

Automatic Containment isolation has not occurred.

INITIATING CUES:

During performance of EOP 4.0, "Loss of Coolant Accident Recovery", the Control Room Supervisor directs you to manually initiate Containment isolation, referring to Step 13.

PALISADES NUCLEAR PLANT Page 7 of 7 SEPTEMBER 2014

NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I SYS C TITLE: PERFORM POST RAS STEP 54 OF EOP-4.0 CANDIDATE:

EXAMINER:

JPM SYSTEM C JOB PERFORMANCE MEASURE DATA PAGE Task: Perform Post RAS Step 54 of EOP-4.0 Alternate Path: NO Facility JPM #: NEW K/A: 006A4.07 Importance: RO: 4.4 SRO: 4.4 K/A Statement: Ability to manually operate and/or monitor in the control room: ECCS Pumps and valves Task Standard: All Charging Pumps stopped and at least one HPSI Pump remains in operation Preferred Evaluation Location: Simulator __X__ In Plant _____

Preferred Evaluation Method: Perform __X__ Simulate _____

References:

EOP-4.0, Loss of Coolant Accident Recovery EOP Supplement 39, Alternate Methods of Reducing PCS Pressure Validation Time: 8 minutes Time Critical: NO Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 9 SEPTEMBER 2014

JPM SYSTEM C EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

EOP Supplement 39, Alternate Methods of Reducing PCS Pressure EOP-4.0, Loss of Coolant Accident Recovery, Step 54 Also see Simulator Operator Instructions (later page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

A LOCA has occurred The Plant has been tripped and EOP-1.0, Standard Post Trip Actions, have been completed EOP-4.0, Loss of Coolant Accident Recovery, is in progress SIS and CHP have actuated Pre-RAS and Post-RAS actions have been taken per EOP Supplement 42 Auxiliary Spray Valve, CV-2117, is INOPERABLE INITIATING CUES:

During performance of EOP-4.0, the Control Room Supervisor directs you to perform Step 54.

PALISADES NUCLEAR PLANT Page 3 of 9 SEPTEMBER 2014

JPM SYSTEM C EVALUATOR CUE: Provide candidate a Working Copy of EOP-4.0, Step 54 SIMULATOR OPERATOR: Place simulator to RUN when candidate is ready to perform first task element.

Proc. Step TASK ELEMENT 1 STANDARD Grade IF RAS is initiated, THEN PERFORM the following: Candidate observes the four HPSI flow indicators 54.a a. IF BOTH HPSI Pumps are operating, on Panel C-13 and concludes that less than S U THEN VERIFY total HPSI Pump flow 100 gpm total HPSI flow exists.

greater than 100 gpm.

Comment:

EVALUATOR CUE: Provide candidate a Working Copy of EOP Supplement 39.

Proc. Step TASK ELEMENT 2 STANDARD Grade Candidate stops Charging Pumps P-55A, P-55B and P-55C.

a.1 IF total HPSI Pump flow less than May place auto/manual handswitches 100 gpm, THEN PERFORM ALL of the on Panel C-12 to MANUAL (not following: required) 54..a.1 1) STOP ALL Charging Pumps. Refer to o P-55B S U EOP Supplement 39, "Alternate Methods of Reducing PCS Pressure," o P-55C as needed to control PZR pressure. Trips P-55A, from Panel C-02

2) .

Trips P-55B from Panel C-02 Trips P-55C from Panel C-02 Comment:

CRITICAL STEP PALISADES NUCLEAR PLANT Page 4 of 9 SEPTEMBER 2014

JPM SYSTEM C Proc. Step TASK ELEMENT 3 STANDARD Grade Candidate refers to EOP Supplement 39 Determines Section 1.0 applies Verifies SI throttling criteria met for Degraded Containment conditions o PCS greater than the minimum subcooling curve on EOP a.1 IF total HPSI Pump flow less than Supplement 1 for degraded 100 gpm, THEN PERFORM ALL of the Containment conditions using following: Qualified CETs 54.a.1 and 1) STOP ALL Charging Pumps. Refer o Corrected PZR level is greater Supplement to EOP Supplement 39, "Alternate than 20% (40% for degraded S U 39 Methods of Reducing PCS Containment) and controlled Pressure," as needed to control o At least one S/G is available for PZR pressure.

PCS heat removal with

2) corrected level being maintained or being restored to between 60% and 70%

o Operable RVLMS channels indicate PCS level is greater than 102 inches above the bottom of fuel alignment plate (621'8")

Comment:

EVALUATOR CUE: Provide candidate a Working Copy of EOP Supplement 39 EVALUATOR CUE: If asked as CRS for preference of throttling HPSI Valves or stopping HPSI Pump, ask candidate for recommendation, then approve their recommendation.

EVALUATOR NOTE: If candidate decides to stop a HPSI Pump, then GO TO Task Element #5.

PALISADES NUCLEAR PLANT Page 5 of 9 SEPTEMBER 2014

JPM SYSTEM C Proc. Step TASK ELEMENT 4 STANDARD Grade

a. Operate ANY of the following valves, one train at a time, to obtain the desired PZR level change:
  • HPSI Train 1 Loop 1A, MO-3007
  • HPSI Train 1 Loop 1B, MO-3009 Supplement
  • HPSI Train 1 Loop 2A, MO-3011 Candidate closes HPSI Valves one at a time to S U 39 lower PZR pressure/raise HPSI flow.
  • HPSI Train 1 Loop 2B, MO-3013
  • HPSI Train 2 Loop 2B, MO-3062
  • HPSI Train 2 Loop 2A, MO-3064
  • HPSI Train 2 Loop 1B, MO-3066
  • HPSI Train 2 Loop 1A, MO-3068 Comment:

EVALUATOR NOTE: When PCS pressure falls back below 1470 psia, then total HPSI flow will be above 100 gpm: IF SO, Then GO TO Task Element 6.

CRITICAL STEP Proc. Step TASK ELEMENT 5 STANDARD Grade a.1 IF total HPSI Pump flow less than 100 gpm, THEN PERFORM ALL of the following: Candidate stops P-66A HPSI Pump.

54.a.2 1) If HPSI Pump P-66B trip was attempted, S U

2) IF total HPSI Pump still has flow less candidate informs CRS of failure of P-66B to trip.

than 100 gpm, THEN STOP one HPSI Pump.

Comment:

EVALUATOR NOTE: HPSI Pump P-66B will not trip if selected; candidate must use HPSI Pump P-66A.

CRITICAL STEP PALISADES NUCLEAR PLANT Page 6 of 9 SEPTEMBER 2014

JPM SYSTEM C Proc. Step TASK ELEMENT 6 STANDARD Grade Candidate determines that HPSI flow and either:

IF one HPSI Pump is operating, THEN If greater than 50 gpm, then considers task 54.b VERIFY the operating HPSI Pump has flow complete S U greater than 50 gpm. OR If less than 50 gpm, then goes to RNO 54.b.1 Comment:

EVALUATOR NOTE: If PCS pressure falls back below 1485 psia, then total HPSI flow would be above 50 gpm: IF SO, Then GO TO Task Element 8 CRITICAL STEP(only if one HPSI Pump has already been tripped)

Proc. Step TASK ELEMENT 7 STANDARD Grade IF the operating HPSI Pump has flow less than 50 gpm, THEN PERFORM ALL of the following:

1) STOP ALL Charging Pumps. Refer to Candidate: determines Step 1) was previously EOP Supplement 39, "Alternate Methods of completed Reducing PCS Pressure," as needed to 54.b.1 Candidate dispatches NPO to manually trip S U control PZR pressure.

P-66B at its breaker

2) IF the operating HPSI Pump still has flow less than 50 gpm, THEN STOP the HPSI Candidate informs CRS of TSC notification.

Pump.

3) CONSULT with the TSC for further guidance.

Comment:

EVALUATOR NOTE: If PCS pressure falls back below 1485 psia, then total HPSI flow would be above 50 gpm. (not critical since HPSI flow WILL rise to above 50 gpm)

EVALUATOR CUE: If asked as NPO to trip P-66B breaker, acknowledge request Proc. Step TASK ELEMENT 8 STANDARD Grade NOTIFY the CRS that step 54 actions are CRS NOTIFIED that step 54 contingency actions n/a completed. are completed.

S U Comment:

EVALUATOR CUE: Repeat back notification.

END OF TASK PALISADES NUCLEAR PLANT Page 7 of 9 SEPTEMBER 2014

JPM SYSTEM C SIMULATOR OPERATOR INSTRUCTIONS SIMULATOR SETUP:

Use IC-17 Enter the following malfunctions and overrides:

Final MF/OR Description Location Event Delay Ramp Value RC04 PCS Leak into Containment PIDRC01 1 0 0 100 ED01 Loss of Offsite Power PIDED03 1 0 0 N/A CV-2117 PZR Auxiliary Spray Valve handswitch PNLC02 none 0 0 OFF P-66B-1 HPSI P-66B Trip PNLC03 none 0 0 OFF

[Developers Note: override of HPSI Pump P-66B in setup is necessary since this is dominant pump in simulator model]

Take simulator out of freeze, reactor should automatically trip: carry out the following actions:

NOTE: total time for setup is over an hour.

EOP 1.0 Immediate Actions.

Perform pre RAS actions in EOP Supplement 42.

When RAS occurs, then:

o Perform post-RAS actions of EOP Supplement 42 (no major actions needed) o Reduce value for Malfunction RC04 to 7.5 with a 3 minute ramp time o Observe PZR refill towards solid conditions and PZR pressure rising to above 1460 psia:

this will results in total HPSI flow approaching less than 100 gpm o Ensure total HPSI Flow indicated on Panel C-13 is less than 100 gpm Freeze simulator and take a snapshot.

PALISADES NUCLEAR PLANT Page 8 of 9 SEPTEMBER 2014

JPM SYSTEM C CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

A LOCA has occurred The Plant has been tripped and EOP-1.0, Standard Post Trip Actions, have been completed EOP-4.0, Loss of Coolant Accident Recovery, is in progress SIS and CHP have actuated Pre-RAS and Post-RAS actions have been taken per EOP Supplement 42 Auxiliary Spray Valve, CV-2117, is INOPERABLE INITIATING CUES:

During performance of EOP-4.0, the Control Room Supervisor directs you to perform Step 54.

PALISADES NUCLEAR PLANT Page 9 of 9 SEPTEMBER 2014

NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO SYS D TITLE: BYPASS MSIV CLOSURE CANDIDATE:

EXAMINER:

JPM SYSTEM D JOB PERFORMANCE MEASURE DATA PAGE Task: Bypass MSIV Closure Alternate Path: YES Facility JPM #: 2012 NRC EXAM K/A: 039A4.01 Importance: RO: 2.9 SRO: 2.8 K/A Statement: Ability to manually operate and/or monitor in the control room: Main steam supply valves.

Task Standard: Both MSIV Bypass Valves, MO-0501 and MO-0510, opened with S/G pressure less than 500 psia.

Preferred Evaluation Location: Simulator ___X___ In Plant _____

Preferred Evaluation Method: Perform ___X___ Simulate _____

References:

GOP-9, MODE 3 525°F to MODE 4 or MODE 5 Validation Time: 25 minutes Time Critical: NO Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 9 SEPTEMBER 2014

JPM SYSTEM D EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

GOP-9, MODE 3 525°F to MODE 4 or MODE 5 with GCL-9 completed through Step 3.6 and Step 2.15 circled but not slashed.

ARP-5, Primary Coolant Pump Steam Generator and Rod Drives Scheme EK-09 (C-12)

Also see Simulator Operator Instructions (later page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Plant cooldown via the Turbine Bypass Valve, CV-0511, is in-progress per GOP-9, MODE 3 525°F to MODE 4 or MODE 5.

S/G pressures are approximately 560 psia.

INITIATING CUES:

During performance of GOP-9, MODE 3 525°F to MODE 4 or MODE 5, the CRS directs you to block open the MSIVs per step 3.7 and verify block is successful as S/G pressure continues to lower.

PALISADES NUCLEAR PLANT Page 3 of 9 SEPTEMBER 2014

JPM SYSTEM D EVALUATOR CUE: Provide candidate with a working copy of GOP-9 with GCL-9 completed through Step 3.3 and Step 2.14 circled but not slashed.

Proc. Step TASK ELEMENT 1 STANDARD Grade WHEN 3 of 4 associated Steam Generator pressure sigmas indicate between 510 and 550 psia and the indicator is between alarm flags, THEN DEPRESS the HS/LPE-50A, BYPASS OF MSIV CLOSURE 3.7 associated pushbutton to bypass MSIV S U pushbutton depressed closure:

HS/LPE-50A, BYPASS OF MSIV CLOSURE pushbutton Comment:

EVALUATOR NOTE: Alarm EK-0970, Steam Gen Valves Isolation Lockout, will alarm when at least one MSIV auto block signal has been blocked (i.e. blocking second MSIV does not change alarm status or cause it to reflash).

EVALUATOR NOTE: Candidate can perform Task Elements 1 and 2 in any order and may perform Task Element 3 as soon as alarm occurs.

Proc. Step TASK ELEMENT 2 STANDARD Grade WHEN 3 of 4 associated Steam Generator pressure sigmas indicate between 510 and 550 psia and the indicator is between alarm flags, THEN DEPRESS the HS/LPE-50B, BYPASS OF MSIV CLOSURE 3.7 associated pushbutton to bypass MSIV S U pushbutton depressed closure:

HS/LPE-50B, BYPASS OF MSIV CLOSURE pushbutton Comment:

EVALUATOR NOTE: Alarm EK-0970, Steam Gen Valves Isolation Lockout, will alarm when at least one MSIV auto block signal has been blocked (i.e. blocking second MSIV does not change alarm status or cause it to reflash).

PALISADES NUCLEAR PLANT Page 4 of 9 SEPTEMBER 2014

JPM SYSTEM D Proc. Step TASK ELEMENT 3 STANDARD Grade Acknowledge alarm EK-0970 and refer to Candidate acknowledges alarm on Panel C-02


S U ARP. and refers to ARP-5.

Comment:

EVALUATOR CUE: Provide a working copy of ARP-5 Window 70 EVALUATOR NOTE: Alternate Path begins here and is covered in task elements 4 through 6 Proc. Step TASK ELEMENT 4 STANDARD Grade Determine that both MSIVs auto closed Candidate determines that both MSIVs have


when 2/4 S/G pressures on either S/G closed. S U went below 500 psia.

Comment:

EVALUATOR CUE: If candidate asks for direction on which procedure to use or action to take, then ask Candidate what they would recommend and the basis for this recommendation:

Candidate Responses: 1. Continue with cooldown using Turbine Bypass Valve and opening MSIV bypasses (basis= equivalent to previous method in-use, wont loose water inventory)

OR use Atmospheric Steam Dump Valves (basis = quicker method but loose water inventory and make noise to environment)

EVALUATOR Response: Use procedures and continue the plant cooldown using your recommended method (CV-0511, Turbine Bypass Valve via MSIV Bypass Valves OR using Atmospheric Steam Dump Valves EVALUATOR CUE: If candidate asks for Vacuum Pump to be placed in service, acknowledge request and state that this has been completed.

EVALUATOR NOTE: GOP-9 Steps 2.13.b thru d are N/A.

EVALUATOR NOTE: If Candidate is using Turbine Bypass Valve, then GO TO Task Element #6 PALISADES NUCLEAR PLANT Page 5 of 9 SEPTEMBER 2014

JPM SYSTEM D Proc. Step TASK ELEMENT 5 STANDARD Grade Candidate operates ADV Controller HIC-0781A OPERATE ASDVs as necessary to 2.13.e as needed to continue PCS cooldown at rate at S U maintain PCS temperature.

or below 60F/Hr Comment:

EVALUATOR NOTE: If Candidate attempts to perform GOP-9 step 2.13.f (perform GOP-9.0 section 5.0 actions): inform candidate that another operator will complete this task.

EVALUATOR NOTE: If this Task Element is performed, then GO TO Task Element 8.

CRITICAL STEP Proc. Step TASK ELEMENT 6 STANDARD Grade ENSURE OPEN both MSIV Bypass Valves: Candidate opens MSIV Bypass Valve 2.15 S U MO-0501, MSIV CV-0501 Bypass MO-0501 MO-0510, MSIV CV-0510 Bypass Comment:

EVALUATOR NOTE: Candidate may close CV-0511 with PIC-0511 prior to opening the MSIV Bypass Valves.

EVALUATOR NOTE: Order in which candidate opens MSIV bypass valves is not critical.

CRITICAL STEP Proc. Step TASK ELEMENT 7 STANDARD Grade ENSURE OPEN both MSIV Bypass Valves: Candidate opens MSIV Bypass Valve:

2.15 S U MO-0501, MSIV CV-0501 Bypass MO-0510 MO-0510, MSIV CV-0510 Bypass Comment:

EVALUATOR NOTE: Candidate may close CV-0511 with PIC-0511 prior to opening the MSIV Bypass Valves.

EVALUATOR NOTE: Order in which candidate opens MSIV bypass valves is not critical.

CRITICAL STEP PALISADES NUCLEAR PLANT Page 6 of 9 SEPTEMBER 2014

JPM SYSTEM D Proc. Step TASK ELEMENT 8 STANDARD Grade Notify CRS that either 1)both MSIV Bypass Valves are open and N/A cooldown is continuing via TBV OR CRS notified. S U

2) ADVs are being used to continue plant cooldown.

Comment:

END OF TASK PALISADES NUCLEAR PLANT Page 7 of 9 SEPTEMBER 2014

JPM SYSTEM D SIMULATOR OPERATOR INSTRUCTIONS Reset to IC-11.

Insert override for zdi3p(174) to OFF (this is CV-0501-BYP, Bypass of MSIV Closure on Low SG Press, SG B Bypass pushbutton on Panel C-01).

Trip the reactor.

Fully open both MSIV Bypass Valves and then latch both MSIVs using remotes MS25 and MS36 on PID MS02.

Commence a 60°/hr cooldown using CV-0511, TBV.

Close both MSIV Bypass Valves.

Annotate/perform other GOP-9 activities up to step 3.7.

FREEZE when S/G pressures are approximately 555 psia (on sigmas) or 540 psia (on PPC) and SNAP into a saved IC.

PALISADES NUCLEAR PLANT Page 8 of 9 SEPTEMBER 2014

JPM SYSTEM D CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

Plant cooldown via the Turbine Bypass Valve, CV-0511, is in-progress per GOP-9, MODE 3 525°F to MODE 4 or MODE 5.

S/G pressures are approximately 560 psia.

INITIATING CUES:

During performance of GOP-9, MODE 3 525°F to MODE 4 or MODE 5, the CRS directs you to block open the MSIVs per step 3.7 and verify block is successful as S/G pressure continues to lower.

PALISADES NUCLEAR PLANT Page 9 of 9 SEPTEMBER 2014

NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I/SRO-U SYS E TITLE: ALIGN CONTAINMENT AIR COOLERS CANDIDATE:

EXAMINER:

JPM SYSTEM E JOB PERFORMANCE MEASURE DATA PAGE Task: Alignment of Containment Air Coolers following fan maintenance Alternate Path: NO Facility JPM #: 2012 NRC EXAM K/A: 022A1.04 Importance: RO: 3.2 SRO: 3.3 K/A Statement: Ability to predict and/or monitor changes in parameters (to prevent exceeding design limits) associated with operating the CCS controls including: Cooling water flow Task Standard: All four Containment Air Cooling System aligned per SOP-5. Third Service Water Pump started.

Preferred Evaluation Location: Simulator __X__ In Plant _____

Preferred Evaluation Method: Perform __X__ Simulate _____

References:

SOP-5, Containment Air Cooling Validation Time: 10 minutes Time Critical: NO Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 11 SEPTEMBER 2014

JPM SYSTEM E EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

SOP-5, Containment Air Cooling Also see Simulator Operator Instructions (later page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

The plant is operating at steady state 100% power.

VHX-1 Cooling Fans V-1A and V-1B are OFF with Service Water isolated.

VHX-4 Cooling Fans V-4A and V-4B are OFF with Service Water isolated.

All CAC Outlet Bypass Valves are properly aligned per SOP-5, Containment Air Cooling, step 7.1.1.b.1 table.

INITIATING CUES:

The Control Room Supervisor has directed you to align the Containment Air Cooling System to its normal alignment per SOP-5, section 7.1.1 with all fans operating and all inlet and high capacity valves open.

PALISADES NUCLEAR PLANT Page 3 of 11 SEPTEMBER 2014

JPM SYSTEM E EVALUATOR CUE: Provide candidate with a working copy of SOP-5 (entire procedure)

Proc.Step TASK ELEMENT 1 STANDARD Grade REFER TO Step 5.2.3 for guidance on Candidate refers to step 5.2.3 for guidance on 7.1.1.a S U Service Water Pump operation. SW pump operation.

Comment:

EVALUATOR CUE: If asked whether a third Service Water Pump should be started, state that, "If possible, operate with two Service Water Pumps."

EVALUATOR NOTE: Order of valve alignment and fan starts is not critical.

Proc.Step TASK ELEMENT 2 STANDARD Grade ENSURE control valves are positioned as

7.1.1 follows

CV-0869 is verified open. S U b.1 For VHX-4, verify open Inlet Valve CV-0869.

Comment:

EVALUATOR NOTE: Service Water Pump discharge pressure has been setup low and will lower further when CAC high capacity valves are opened.

Proc.Step TASK ELEMENT 3 STANDARD Grade ENSURE control valves are positioned as

7.1.1 follows

High Capacity Outlet Valve CV-0867 is opened. S U b.1 For VHX-4, open High Capacity Outlet Valve CV-0867.

Comment:

CRITICAL STEP PALISADES NUCLEAR PLANT Page 4 of 11 SEPTEMBER 2014

JPM SYSTEM E Proc.Step TASK ELEMENT 4 STANDARD Grade ENSURE control valves are positioned as

7.1.1 follows

Inlet Valve CV-0862 is verified open. S U b.1 For VHX-1 verify Open Inlet Valve CV-0862.

Comment:

EVALUATOR NOTE: Will receive EDG Trouble Alarms on Panel C-11 after Service Water Pump start.

EVALUATOR NOTE: This step may be performed AFTER Service Water Pump start.

Proc.Step TASK ELEMENT 5 STANDARD Grade ENSURE control valves are positioned as

7.1.1 follows

High Capacity Outlet Valve CV-0861 is opened. S U b.1 For VHX-1 open High Capacity Outlet Valve CV-0861.

Comment:

EVALUATOR NOTE: This step may be performed AFTER Service Water Pump start.

CRITICAL STEP Proc.Step TASK ELEMENT 6 STANDARD Grade Determines that the Standby Service Water Pump P-7C needs to be started because Monitor Service Water Header pressure and system pressure has lowered to < 50 psig.

5.2.3 determine that Service Water system S U pressure is < 50 psig. May need to respond to alarms EK-0551 and EK-0557: Has AO investigate D/G local alarm boards.

Comment:

EVALUATOR CUE: When asked as AO report that D/G local alarm panels indicate low raw water pressure. Reading is 24 psig if asked.

PALISADES NUCLEAR PLANT Page 5 of 11 SEPTEMBER 2014

JPM SYSTEM E Proc.Step TASK ELEMENT 7 STANDARD Grade Obtain SOP-15, Service Water System Locates SOP-15, Service Water System n/a S U procedure, section 7.1.1. procedure.

Comment:

EVALUATOR CUE: Provide candidate with a working copy of SOP-15, section 7.1.1.

Proc.Step TASK ELEMENT 8 STANDARD Grade SOP-15 IF starting the first Service Water Pump, Candidate determines this step is N/A. S U 7.1.1.a THEN GO TO Section 7.1.5.

Comment:

Proc.Step TASK ELEMENT 9 STANDARD Grade IF starting the third Service Water Pump, SOP-15 THEN NOTIFY Chemistry so that they can Notify Chemistry to recalculate Mixing Basin S U 7.1.1.b recalculate mixing basin discharge flow discharge flow volume.

volume.

Comment:

EVALUATOR CUE: CRS will notify Chemistry of P-7C start so they can recalculate mixing basin discharge flow volume.

Proc.Step TASK ELEMENT 10 STANDARD Grade ENSURE OPEN associated pump SOP-15 Dispatch AO to check OPEN P-7C discharge discharge valve: S U 7.1.1.c valve MV-SW104.

P-7C MV-SW104 Comment:

EVALUATOR (or Simulator Operator) CUE: "MV-SW104 is OPEN" PALISADES NUCLEAR PLANT Page 6 of 11 SEPTEMBER 2014

JPM SYSTEM E Proc.Step TASK ELEMENT 11 STANDARD Grade SOP-15 Dispatch AO to check P-7C motor oil levels ENSURE motor oil levels normal. S U 7.1.1.d normal.

Comment:

EVALUATOR (or Simulator Operator) CUE: "P-7C Motor oil levels normal" Proc.Step TASK ELEMENT 12 STANDARD Grade SOP-15 Remove P-7C from standby by placing P-7C Control Switch placed momentarily in S U 7.1.1.e Control Switch to TRIP. TRIP until standby light extinguishes.

Comment:

Proc.Step TASK ELEMENT 13 STANDARD Grade SOP-15 START desired pump from Control Room P-7C control switch placed in START and Handswitch (preferred) or using Handswitch S U 7.1.1.f released to mid-position.

on breaker.

Comment:

SIMULATOR OPERATOR: Call in as AO and report that SW Pump P-7C local discharge pressure is 73 psig, and packing leakoff is not excessive. If asked, report that P-7C Basket Strainer DP is 4 psid.

EVALUATOR NOTE: EK-1144, P-7C Basket Strainer HI dP may alarm and then clear after pump start: candidate should reference ARP-7, but no actions are required.

CRITICAL STEP PALISADES NUCLEAR PLANT Page 7 of 11 SEPTEMBER 2014

JPM SYSTEM E Proc.Step TASK ELEMENT 14 STANDARD Grade Verify Service Water Header pressure rises Verify Service Water Header pressure rises

--- S U to > 50 psig. to > 50 psig.

Comment:

EVALUATOR NOTE: Candidate will refer back to SOP-5, 7.1.1.b.2 to complete alignment of Containment Air Coolers. Also, the following four steps may be performed in any order.

Proc.Step TASK ELEMENT 15 STANDARD Grade ENSURE all available Containment Air 7.1.1 Cooler Fans are operating: V-1A is started. S U b.2 For VHX-1 start fan V-1A (SOP-5).

Comment:

CRITICAL STEP Proc.Step TASK ELEMENT 16 STANDARD Grade ENSURE all available Containment Air 7.1.1 Cooler Fans are operating: V-1B is started. S U b.2 For VHX-1 start fan V-1B (SOP-5)

Comment:

CRITICAL STEP Proc.Step TASK ELEMENT 17 STANDARD Grade ENSURE all available Containment Air 7.1.1 Cooler Fans are operating: V-4A is started. S U b.2 For VHX-4 start fan V-4A (SOP-5)

Comment:

CRITICAL STEP PALISADES NUCLEAR PLANT Page 8 of 11 SEPTEMBER 2014

JPM SYSTEM E Proc.Step TASK ELEMENT 18 STANDARD Grade ENSURE all available Containment Air 7.1.1 Cooler Fans are operating: V-4B is started. S U b.2 For VHX-4 start fan V-4B (SOP-5)

Comment:

CRITICAL STEP Proc. Step TASK ELEMENT 19 STANDARD Grade Notify CRS that Containment Air Coolers N/A are aligned with all High Capacity outlet CRS notified. S U valves open and all fans running.

Comment:

END OF TASK PALISADES NUCLEAR PLANT Page 9 of 11 SEPTEMBER 2014

JPM SYSTEM E SIMULATOR OPERATOR INSTRUCTIONS Reset to IC-17.

Ensure P-7A and P-7B are in service, with P-7C in standby.

Stop V-1A, 1B, 4A, and 4B.

Close VHX-1 High Capacity Outlet, CV-0861.

Close VHX-4 High Capacity Outlet, CV-0867.

Insert SW leak: SW09 in at 50% (at setup).

Create Event Trigger 2: Event = zlo1p(26).and.zlo1p(32), Action - imf sw09 65

{this is for having the red lights on for CVs-0861 and 0867}

PALISADES NUCLEAR PLANT Page 10 of 11 SEPTEMBER 2014

JPM SYSTEM E CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

The plant is operating at steady state 100% power.

VHX-1 Cooling Fans V-1A and V-1B are OFF with Service Water isolated.

VHX-4 Cooling Fans V-4A and V-4B are OFF with Service Water isolated.

All CAC Outlet Bypass Valves are properly aligned per SOP-5, Containment Air Cooling, step 7.1.1.b.1 table.

INITIATING CUES:

The Control Room Supervisor has directed you to align the Containment Air Cooling System to its normal alignment per SOP-5, section 7.1.1 with all fans operating and all inlet and high capacity valves open.

PALISADES NUCLEAR PLANT Page 11 of 11 SEPTEMBER 2014

REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I SYS F TITLE: PERFORM A DIESEL GENERATOR (D/G) VOLTAGE TEST ON 1-1 D/G CANDIDATE:

EXAMINER:

JPM: SYSTEM F JOB PERFORMANCE MEASURE DATA PAGE Task: Perform Diesel Generator Surveillance MO-7A-1 and MO-7A-2 Alternate Path: NO Facility JPM #: PL-OPS-EDG-005J K/A: 064A4.06 Importance: RO: 3.9 SRO: 3.9 K/A Statement: Manual start, loading, and stopping of the ED/G Task Standard: 1-1 D/G Auto Voltage Regulator High and Low Limits verified.

Preferred Evaluation Location: Simulator __X__ In Plant _____

Preferred Evaluation Method: Perform __X__ Simulate _____

References:

MO-7A-1, Emergency Diesel Generator 1-1 Validation Time: 10 minutes Time Critical: NO Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 10 SEPTEMBER 2014

JPM: SYSTEM F EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

MO-7A-1, Emergency Diesel Generator 1-1, Section 5.6 Also see Simulator Operator Instructions (last page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Diesel Generator 1-1 running unloaded at 60 Hz for fifteen minutes.

MO-7A-1, "Emergency Diesel Generator 1-1" is in progress; all steps up to 5.6 are completed.

Month is January.

Plant is in Mode 1.

Auxiliary Operator is stationed at EC-22, Diesel Generator 1-1 Local Panel.

INITIATING CUES:

During performance of MO-7A-1, the Control Room Supervisor directs you to perform Section 5.6 "Voltage Regulator Test."

PALISADES NUCLEAR PLANT Page 3 of 10 SEPTEMBER 2014

JPM: SYSTEM F Proc. Step TASK ELEMENT 1 STANDARD Grade Operator obtains a copy of MO-7A-1, MO-7A-1, Section 5.6 obtained n/a Section 5.6 S U Comment:

Evaluator Cue: Provide a working copy of MO-7A-1, Section 5.6.

Proc. Step TASK ELEMENT 2 STANDARD Grade DETERMINE the Voltage Regulator Mode Select switch position from the table for the month .. AND PERFORM the following: Operator determines that the Voltage Regulator 5.6.1 Mode Select switch position is AUTO. S U Voltage Regulator Mode Select Switch Position is AUTO for month of January Comment:

Evaluator Note: The Voltage Regulator Mode Select switch position is determined by the Month of the test.

Evaluator Cue: If asked as System Engineer what switch position to use, CUE that the procedure, MO-7A-1 is to be followed.

Proc. Step TASK ELEMENT 3 STANDARD Grade IF position is AUTO, THEN ENSURE Voltage Regulator Mode Select switch is verified Voltage Regulator Mode Select switch is in 5.6.1a in AUTO position. S U the AUTO position (location C-04 panel).

Comment:

Evaluator Cue: If candidate places this switch in MANUAL, then this task element is a failed critical step.

PALISADES NUCLEAR PLANT Page 4 of 10 SEPTEMBER 2014

JPM: SYSTEM F Proc. Step TASK ELEMENT 4 STANDARD Grade IF position is MANUAL, THEN PERFORM Operator determines that this step is not 5.6.1b.1 the following: applicable. S U Comment:

Proc. Step TASK ELEMENT 5 STANDARD Grade IF the plant is in Mode 1, 2, 3, or 4, THEN Operator determines that this step is not 5.6.1b.2 PERFORM off-site source checks. applicable. S U Comment:

Proc. Step TASK ELEMENT 6 STANDARD Grade DETERMINE the switch from the table for Operator determines that the Field Rheostat the performance month . AND 5.6.2 switch on C-04 is to be used. S U PERFORM the Following:

Comment:

Evaluator Note: The Field Rheostat switch on C-04 is determined by the Month of the test.

Evaluator Cue: If asked as System Engineer what switch to use, CUE The procedure, MO-7A-1 is to be followed.

PALISADES NUCLEAR PLANT Page 5 of 10 SEPTEMBER 2014

JPM: SYSTEM F Proc. Step TASK ELEMENT 7 STANDARD Grade Slowly raise generator voltage to between Operator adjusts generator voltage between 2575 VAC and 2625 VAC on EVI-1107L, 2575 VAC and 2625 VAC on EVI-1107L with the 5.6.2a Local Volt Meter or as directed by the S U Field Rheostat switch on C-04.

System Engineer.

Comment:

Evaluator Cue: If asked as System Engineer what generator voltage limits to use, CUE that the procedure, MO-7A-1 is to be followed.

Evaluator Cue: If asked as AO to report local generator voltage, USE voltage indication on C-04 for the local voltage reading.

CRITICAL STEP Proc. Step TASK ELEMENT 8 STANDARD Grade Recorded generator and field voltages (from RECORD generator voltage and field EC-22 panel:

voltage (location EC-22 panel)

Local Volt Meter (EVI-1107L) Volts: 2575 to 5.6.2b Local Volt Meter (EVI-1107L) Volts: ____ S U 2625 Field Voltage (EVI-1107DC) Volts: ____

Field Voltage (EVI-1107DC) Volts: __80V_

Comment:

Evaluator Cue: If asked as AO to report local generator voltage, USE voltage indication on C-04 for the local voltage reading.

Evaluator Cue: If asked as AO to report field voltage, REPORT: field voltage reads 80 V on EVI-1107DC.

PALISADES NUCLEAR PLANT Page 6 of 10 SEPTEMBER 2014

JPM: SYSTEM F Proc. Step TASK ELEMENT 9 STANDARD Grade Slowly lower generator voltage to between Operator adjusts generator voltage between 2275 VAC and 2325 VAC on EVI-1107L, 2275 VAC and 2325 VAC on EVI-1107L with the 5.6.2c Local Volt Meter or as directed by the S U Field Rheostat switch on C-04.

System Engineer.

Comment:

Evaluator Cue: If asked as System Engineer what generator voltage limits to use, CUE that the procedure, MO-7A-1 is to be followed.

Evaluator Cue: If asked as AO to report local generator voltage, USE voltage indication on C-04 for the local voltage reading.

CRITICAL STEP Proc. Step TASK ELEMENT 10 STANDARD Grade Recorded generator and field voltages (from RECORD generator voltage and field EC-22 panel:

voltage (location EC-22 panel)

Local Volt Meter (EVI-1107L) Volts: 2275 to 5.6.2d Local Volt Meter (EVI-1107L0 Volts: ____ S U 2325 Field Voltage (EVI-1107DC)n Volts: ____

Field Voltage (EVI-1107DC) Volts: __70V_

Comment:

Evaluator Cue: If asked as AO to report local generator voltage, USE voltage indication on C-04 for the local voltage reading.

Evaluator Cue: If asked as AO to report field voltage, REPORT: field voltage reads 70 V on EVI-1107DC.

PALISADES NUCLEAR PLANT Page 7 of 10 SEPTEMBER 2014

JPM: SYSTEM F Proc. Step TASK ELEMENT 11 STANDARD Grade RAISE generator voltage to 2400 VAC Generator voltage raised to between 2390 VAC (2390 VAC - 2410 VAC) on EVI-1107L, and 2410 VAC on EVI-1107L with the Field 5.6.2e Local Volt Meter. Rheostat switch on C-04. S U Comment:

Evaluator Cue: If asked as AO to report local generator voltage, USE voltage indication on C-04 for the local voltage reading.

CRITICAL STEP Proc. Step TASK ELEMENT 12 STANDARD Grade ENSURE Voltage Regulator Mode Select Voltage Regulator Mode Select switch verified in switch is in AUTO position the AUTO position (location C-04 panel).

5.6.3 S U Performed By: N/A Performed By: Signed, Time and Dated Verified By: Signed, Time and Dated Verified By: Signed, Time and Dated Comment:

Evaluator Cue: Operator will not sign the Performed By line, the Verified By line will be signed (Voltage Selector switch in proper position and not manipulated)

Proc. Step TASK ELEMENT 13 STANDARD Grade Notify CRS that 1-1 D/G Voltage Regulator CRS notified that Section 5.6 of MO-7A-1 for Test has been completed per Section 5.6 of n/a Voltage Regulator Test Complete. S U MO-7A-1, for 1-1 D/G.

Comment:

END OF TASK PALISADES NUCLEAR PLANT Page 8 of 10 SEPTEMBER 2014

JPM: SYSTEM F SIMULATOR OPERATOR INSTRUCTIONS Any at power IC can be used.

Start EDG 1-1 in UNIT.

Clear Local Alarm gauge board on PIDED08, using ED27.

PALISADES NUCLEAR PLANT Page 9 of 10 SEPTEMBER 2014

JPM: SYSTEM F CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

Diesel Generator 1-1 running unloaded at 60 Hz for fifteen minutes.

MO-7A-1, "Emergency Diesel Generator 1-1" is in progress; all steps up to 5.6 are completed.

Month is January.

Plant is in Mode 1.

Auxiliary Operator is stationed at EC-22, Diesel Generator 1-1 Local Panel.

INITIATING CUES:

During performance of MO-7A-1, the Control Room Supervisor directs you to perform Section 5.6 "Voltage Regulator Test."

PALISADES NUCLEAR PLANT Page 10 of 10 SEPTEMBER 2014

NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I SYS G TITLE: ADJUST RIA-1049 SETPOINT CANDIDATE:

EXAMINER:

JPM SYSTEM G JOB PERFORMANCE MEASURE DATA PAGE Task: Adjust RIA-1049 Alarm Setpoint Alternate Path: NO Facility JPM #: 2012 NRC EXAM K/A: 073A4.01 Importance: RO: 3.9 SRO: 3.9 K/A Statement: Ability to manually operate and/or monitor in the control room: Effluent release Task Standard: RIA-1049 high alarm set to 1100 cpm.

Preferred Evaluation Location: Simulator ___X___ In Plant _____

Preferred Evaluation Method: Perform ___X___ Simulate _____

References:

SOP-37, Process Liquid Monitor System Validation Time: 10 minutes Time Critical: NO Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT ______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 8 SEPTEMBER 2014

JPM SYSTEM G EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

SOP-37, Process Liquid Monitor System Also see Simulator Operator Instructions (later page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Release Order, Form CH 6.21-3 (batch card) has been prepared. The following RE-1049 data has already been entered on this form:

o RE-1049 Check Source reading = 6.6 E6 cpm o High alarm setpoint net cpm = 640 o RE-1049 background cpm = 460 o RIA-1049 alarm setpoint cpm = 1100 Breaker 34 on EY-01 is closed.

Attachment 3, Checklist 37, Table Digital Rate Meter Instruments for RIA-1049, Digital Rate Meter has been performed.

INITIATING CUES:

The CRS directs you to set up Radwaste Discharge Monitor, RIA-1049 High Alarm Setpoint using SOP-37 Section 7.3.2 to a setpoint of 1100 cpm (hand candidate prepared Release Order).

PALISADES NUCLEAR PLANT Page 3 of 8 SEPTEMBER 2014

JPM SYSTEM G EVALUATOR CUE: Provide candidate with a working copy of SOP-37, section 7.3.2 Proc. Step TASK ELEMENT 1 STANDARD Grade PUSH HIGH pushbutton on front of "High Alarm" push button on the front of a RIA-1049 and read current High Alarm RIA-1049 pushed and current high alarm S U Setpoint. setpoint is read as 2.70E3 CPM.

Comment:

Proc. Step TASK ELEMENT 2 STANDARD Grade PULL RIA-1049 out from the panel about b six inches (6") to access the control RIA-1049 pulled out from panel about 6 inches. S U buttons.

Comment:

CRITICAL STEP Proc. Step TASK ELEMENT 3 STANDARD Grade VERIFY Function switch is set to 0 as Checks right side of Function Switch is set c S U seen on right side of switch. to 0.

Comment:

Proc. Step TASK ELEMENT 4 STANDARD Grade PRESS ENTER button to display High d "Enter" button pressed and one digit blinking. S U Alarm setpoint.

Comment:

CRITICAL STEP PALISADES NUCLEAR PLANT Page 4 of 8 SEPTEMBER 2014

JPM SYSTEM G Proc. Step TASK ELEMENT 5 STANDARD Grade SET the High Alarm setpoint by performing the following as necessary:

IF selecting another digit, THEN Digit and Value pushbuttons manipulated as e PRESS the DIGIT pushbutton. necessary to set the high alarm setpoint at S U IF changing the digit value, THEN 1.10E3.

PRESS the VALUE pushbutton until value desired for that digit is displayed.

Comment:

CRITICAL STEP Proc. Step TASK ELEMENT 6 STANDARD Grade WHEN entire display indicates desired trip f setpoint, THEN: Enter button pressed. S U (a) PRESS ENTER pushbutton.

Comment:

CRITICAL STEP Proc. Step TASK ELEMENT 7 STANDARD Grade WHEN entire display indicates desired trip f setpoint, THEN: Monitor pushed back into panel. S U (b) PUSH monitor back into panel.

Comment:

Proc. Step TASK ELEMENT 8 STANDARD Grade PRESS HIGH pushbutton on front of High Alarm" push button pressed and g RIA-1049 to verify high alarm setpoint is S U 1.10E3 CPM trip setpoint verified.

correct.

Comment:

PALISADES NUCLEAR PLANT Page 5 of 8 SEPTEMBER 2014

JPM SYSTEM G Proc. Step TASK ELEMENT 9 STANDARD Grade PRESS ALARM ACK button to clear any h Alarm Ack pushed and Alarms clear. S U high alarms that may have come in.

Comment:

Proc. Step TASK ELEMENT 10 STANDARD Grade Notify the CRS that RIA-1049 High Alarm N/A CRS is notified. S U Setpoint is 1100 cpm.

Comment:

EVALUATOR CUE: As CRS, repeat back the notification.

END OF TASK PALISADES NUCLEAR PLANT Page 6 of 8 SEPTEMBER 2014

JPM SYSTEM G SIMULATOR OPERATOR INSTRUCTIONS Any IC Ensure RIA-1049 high alarm setpoint is set at 2.61E3 cpm PRIOR TO performing this JPM and AFTER it is completed (as appropriate).

Fill out Release Order, form CH 6.21-3 (procedure CH 6.21, attachment 3) as follows:

CH 6.21, Attachment 3, page 1 of 2.

In the first section of the form, fill in the following:

Batch = LRW-Today Tank = T-91

% released = 70%

Volume released (gal) = 51100 Minimum required Dilution Water Pumps = 1 Minimum required Service Water Pumps = 2 Maximum permitted release rate (gpm) = 250 Authorization Shift Manager = any signature; Date = today In the second section of the form, Control Room Operator pre-release section, fill in the following:

Check both DW pumps operating Check P-7A and P-7B SW pumps operating RE-1049 Check Source reading = 6.6 E6 cpm High alarm setpoint net cpm = 640 RE-1049 background cpm = 460 RIA-1049 alarm setpoint cpm = 1100 Control Room Operator = any signature, Date = today PALISADES NUCLEAR PLANT Page 7 of 8 SEPTEMBER 2014

JPM SYSTEM G CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

Release Order, Form CH 6.21-3 (batch card) has been prepared. The following RE-1049 data has already been entered on this form:

o RE-1049 Check Source reading = 6.6 E6 cpm o High alarm setpoint net cpm = 640 o RE-1049 background cpm = 460 o RIA-1049 alarm setpoint cpm = 1100 Breaker 34 on EY-01 is closed.

Attachment 3, Checklist 37, Table Digital Rate Meter Instruments for RIA-1049, Digital Rate Meter has been performed.

INITIATING CUES:

The CRS directs you to set up Radwaste Discharge Monitor, RIA-1049 High Alarm Setpoint using SOP-37 Section 7.3.2 to a setpoint of 1100 cpm.

PALISADES NUCLEAR PLANT Page 8 of 8 SEPTEMBER 2014

REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I SYS H TITLE: TRANSFER SHIELD COOLING COILS CANDIDATE:

EXAMINER:

JPM: SYSTEM H JOB PERFORMANCE MEASURE DATA PAGE Task: Operate the Shield Cooling System Alternate Path: YES Facility JPM #: BANK K/A: G2.1.30 Importance: RO: 4.4 SRO: 4.0 K/A Statement: Ability to locate and operate components, including local controls Task Standard: Shield Cooling Coil transferred to A in-service and at least one Shield Cooling Pump operating.

Preferred Evaluation Location: Simulator _X__ In Plant ______

Preferred Evaluation Method: Perform _X__ Simulate ______

References:

SOP-29, Shield Cooling System ARP-8, Safeguards Safety Injection and Isolation Scheme EK-13 (EC-13)

Validation Time: 10 minutes Time Critical: NO Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 8 SEPTEMBER 2014

JPM: SYSTEM H EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

SOP-29, Shield Cooling System, section 7.1.2 ARP-8, Safeguards Safety Injection and Isolation Scheme EK-13 (EC-13),

windows 1, 2, and 3 Also see Simulator Operator Instructions (last page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Plant is at full power B Shield Cooling Coil is in service per SOP-29, Shield Cooling System, section 7.1.1.

INITIATING CUES:

The CRS directs you to transfer Shield Cooling Coils per SOP-29, Shield Cooling System, section 7.1.2.

PALISADES NUCLEAR PLANT Page 3 of 8 SEPTEMBER 2014

JPM: SYSTEM H Evaluator Cue: Provide a working copy of SOP-29, Section 7.1.2.

Proc. Step TASK ELEMENT 1 STANDARD Grade CHECK Shield Cooling System in operation No actions needed since this is status provided in initial 7.1.2.a conditions.

S U (refer to Section 7.1.1).

Comment:

Proc. Step TASK ELEMENT 2 STANDARD Grade OPEN Inlet Valve for coil set to be placed in operation:

Coil A CV-0932 opened using key #141: red light b S U Coil A CV-0932 ON, green light OFF Coil B CV-0934 Comment:

Evaluator Note: EK-1303, Reactor Shield Clg Lo Flo, may alarm and then clear when this step is performed. Use of ARP not required to complete Critical portion of this step.

CRITICAL STEP Proc. Step TASK ELEMENT 3 STANDARD Grade CLOSE Inlet Valve for coil set to be removed from operation:

Coil B CV-0934 closed using key #142: red light c S U Coil A CV-0932 OFF, green light ON Coil B CV-0934 Comment:

Evaluator Cue: If candidate references ARP-8, provide working copy of appropriate alarm windows (1, 2, and or 3).

Evaluator Note: When CV-0934 red light goes off, then P-77A will trip.

CRITICAL STEP PALISADES NUCLEAR PLANT Page 4 of 8 SEPTEMBER 2014

JPM: SYSTEM H Proc. Step TASK ELEMENT 4 STANDARD Grade EK-1303 checked and IS alarming.

CHECK Annunciator EK-1303, "Reactor The following alarms are also alarming:

d S U Shield Clg Lo Flo" CLEAR. EK-1301, Shield CLG Pumps Trip EK-1302, Shield CLG Pumps Disch Low Press Comment:

Evaluator Cue: If asked as CRS for direction, respond to follow procedures.

EVALUATOR NOTE: Alternate Path begins here: covered in task elements 5 and 6.

Proc. Step TASK ELEMENT 5 STANDARD Grade Window EK-1301 actions:

P-77B handswitch taken to START and then ENSURE running standby Shield released: red light ON, green light OFF ARP-8 Cooling Pump P-77A OR P-77B S U P-77A handswitch taken to TRIP and released PLACE control switch for tripped pump (NOT a critical task element) to TRIP position Comment:

CRITICAL STEP Proc. Step TASK ELEMENT 6 STANDARD Grade Window EK-1302 actions:

ENSURE running standby Shield Cooling Pump P-77A OR P-77B CHECK Shield Cooling Surge Tank ARP-8 T-62 level normal T-62 level checked: level is stable. S U Window EK-1303 actions:

CHECK running Shield Cooling Pump P-77A OR P-77B Comment:

Evaluator Note: 1st action in each alarm is same action as in Task Element #5 Candidate may check Containment Sump level.

PALISADES NUCLEAR PLANT Page 5 of 8 SEPTEMBER 2014

JPM: SYSTEM H Proc. Step TASK ELEMENT 7 STANDARD Grade Reports A Coil is in service and B Coil has Report to CRS status of Shield Cooling been removed from service. P-77B was

-- S U System. manually started and is in service since P-77A tripped and P-77B did not auto start.

Comment:

END OF TASK PALISADES NUCLEAR PLANT Page 6 of 8 SEPTEMBER 2014

JPM: SYSTEM H SIMULATOR OPERATOR INSTRUCTIONS Reset to any at power IC.

Create Event Trigger 1 (red light going off on CV-0934, B Shield Clg Coil Inlet):

Event: .not.zlo1p(113) Action: leave blank Create Event Trigger 2 (when P-77B HS taken to START position):

Event: zdi1p(121) Action: dor P-77B-1 Create Event Trigger 3 (when P-77A HS taken to TRIP position):

Event: zdi1p(106) Action: dmf ANN-K-13-01 Insert the following overrides on Panel C-08:

P-77B-1, Shield Clg P-77B Standby, final value = OFF Tie the following to Event Trigger #1:

o P-77A-2, Shield Clg P-77A Trip, final value = ON o P-77A-4, Shield Clg P-77A NA Close, final value =OFF o ANN-K-13-01, Reactor Shield CLG Pump Trip, final value = ON PALISADES NUCLEAR PLANT Page 7 of 8 SEPTEMBER 2014

JPM: SYSTEM H CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

Plant is at full power B Shield Cooling Coil is in service per SOP-29, Shield Cooling System, section 7.1.1.

INITIATING CUES:

The CRS directs you to transfer Shield Cooling Coils per SOP-29, Shield Cooling System, section 7.1.2 PALISADES NUCLEAR PLANT Page 8 of 8 SEPTEMBER 2014

REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I/SRO-U SYS I TITLE: ENERGIZE BUS 1C FROM STARTUP TRANSFORMER 1-2 LOCALLY CANDIDATE:

EXAMINER:

JPM SYSTEM I JOB PERFORMANCE MEASURE DATA PAGE Task: Perform Actions Specified In Alternate Safe Shutdown Procedure (AOP-41)

Alternate Path: YES Facility JPM #: PL-OPS-ONP-014J K/A: 068AA1.10 Importance: RO: 3.7 SRO: 3.9 K/A Statement: Ability to operate/or monitor the following as they apply to the Control Room Evacuation: Power distribution: ac and dc Task Standard: Bus 1C is energized from Startup Transformer 1-2 Preferred Evaluation Location: Simulator ____ In Plant __X__

Preferred Evaluation Method: Perform ____ Simulate __X__

References:

AOP-41, Alternate Safe Shutdown Procedure EOP Supplement 29, Restore Buses 1C, 1D, 1E From Offsite Power Validation Time: 15 minutes Time Critical: NO Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 12 SEPTEMBER 2014

JPM SYSTEM I EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

AOP-41, Alternate Safe Shutdown Procedure, Step 15.1.a EOP Supplement 29, Restore Buses 1C, 1D, 1E From Offsite Power, Section 3.0, Locally Energize Bus 1C and 1D From Startup XFRM 1-2 Also see Simulator Operator Instructions (last page of this document).

READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

Control Room is not habitable.

Reactor has been tripped and all rods have been inserted into the core.

Bus 1C and Bus 1D are de-energized.

Startup Power Transformer 1-2 is available.

The control power circuit for breaker 152-106 has been damaged.

INITIATING CUES:

During performance of AOP-41, "Alternate Safe Shutdown Procedure" Step 15.1.a, the CRS directs you to energize Bus 1C from Startup Transformer 1-2 locally using EOP Supplement 29 section 3.0.

PALISADES NUCLEAR PLANT Page 3 of 12 SEPTEMBER 2014

JPM SYSTEM I Evaluator Cue: Provide a Working Copy of EOP Supplement 29.

Proc. Step TASK ELEMENT 1 STANDARD Grade n/a LOCATE EOP Supplement 29 EOP Supplement 29 LOCATED S U Comment:

Evaluator Cue: If asked, provide candidate a Working Copy of AOP-41 step 15.1.a.

Proc. Step TASK ELEMENT 2 STANDARD Grade IF Bus 1C is NOT ENERGIZED, THEN PERFORM the following: ENSURES OPEN Safeguards/Station Power 3.0 Incoming Breaker 152-105 is open by

a. ENSURE OPEN Safeguards/Station S U 1.a VERIFYING Breaker 152-105 position indication Power Incoming Breaker to Bus 1C, inside the breaker cubicle indicates OPEN 152-105 Comment:

Evaluator Note: The breaker status lights for breakers 152-105, 152-106 and 152-107 will not be lit due to breaker 72-307 being tripped Evaluator Cue: If asked about the breaker status lights for breakers 152-105, 152-106 or 152-107, cue that they are not lit.

Evaluator Cue: If the position indication inside of 152-105 is checked, cue that breaker 152-105 indicates OPEN Proc. Step TASK ELEMENT 3 STANDARD Grade IF Bus 1C is NOT ENERGIZED, THEN PERFORM the following:

3..0 DESCRIBES/OBTAINS the Remote-Local-

b. OBTAIN a Remote-Local-Transfer Transfer switch handle from cubicle above the S U 1.b switch handle from the cubicle above Dilution Water Pump Breaker (152-102).

Dilution Water Pump Breaker, 152-102 Comment:

CRITICAL STEP PALISADES NUCLEAR PLANT Page 4 of 12 SEPTEMBER 2014

JPM SYSTEM I Proc. Step TASK ELEMENT 4 STANDARD Grade IF Bus 1C is NOT ENERGIZED, THEN PERFORM the following:

3.0 c. PLACE Remote-Local-Transfer Simulates or describes PLACING HS-152-106 switch, HS-152-106RLTS, to the S U 1.c RLTS in "LOCAL" position LOCAL position to isolate Startup Power Incoming Breaker to Bus 1C, 152-106 Comment:

Evaluator Cue: After simulated operation of the Remote-Local-Transfer switch, the breaker 152-106 status lights on front of breaker door remain NOT lit (i.e. red, white, and green lights are NOT illuminated).

CRITICAL STEP EVALUATOR NOTE: Alternate Path begins here: covered in task element 5.

PALISADES NUCLEAR PLANT Page 5 of 12 SEPTEMBER 2014

JPM SYSTEM I Proc. Step TASK ELEMENT 5 STANDARD Grade IF Bus 1C is NOT ENERGIZED, THEN PERFORM the following: Operator simulates or describes PLACING Breaker 72-307 to the TRIP position.

d. IF breaker status lights do NOT light 3.0 after operating the Remote-Local- AND S U 1.d.1) Transfer switch, THEN PERFORM the following:

Operator simulates or describes PLACING

1) ENSURE CLOSED Control Power Breaker 72-307 to the CLOSE position Breaker 72-307 on Panel D11A Comment:

Evaluator Note: The breaker status lights for breakers 152-105, 152-106 and 152-107 will be lit when breaker 72-307 is closed.

Evaluator Cue: When operator indicates that he would open Panel D11A to check breaker 72-307, cue him that the handle is in between open and closed.

Evaluator Cue: If operator contacts CRS to request permission to reset and close breaker 72-307, cue him that he has CRS permission.

Evaluator Cue: When operator indicates that breaker 72-307 will be placed to the tripped position and then to close, cue that the breaker is all the way to the right.

Evaluator Cue: When operator checks the breaker status lights on the front on 152-106, cue that breaker 152-106 the green and white light status lights are lit.

CRITICAL STEP PALISADES NUCLEAR PLANT Page 6 of 12 SEPTEMBER 2014

JPM SYSTEM I Proc. Step TASK ELEMENT 6 STANDARD Grade IF Bus 1C is NOT ENERGIZED, THEN PERFORM the following:

Determines this step not applicable since the

d. IF breaker status lights do NOT light breaker status lights came back on.

after operating the Remote-Local-Transfer switch, THEN PERFORM OR 3.0 the following:

S U 1.d.2) 2) INSPECT the following fuses: Operator VERIFIES the 152-106 Charging Motor Circuit FZ/1106-2 and LOCAL 152-106 Charging Motor Circuit TRANSFER FUSE FZ/A1106-3 fuses are not FUZ/1106-2 damaged

° LOCAL TRANSFER FUSE FUZ/A1106-3 Comment:

Evaluator Cue: IF operator simulates opening breaker door, then provide operator with CUE SHEET #2A (provide Sheet #2B if candidate cannot read fuse block). IF operator simulates opening door above breaker cubical, then provide CUE SHEET#2C Evaluator Note: Operator should point to Charging Motor fuses (upper left) and Local Transfer Fuse (above breaker cubical)

Evaluator Cue: If fuses checked for damage, cue the operator: Fuses are not damaged.

Actual cue will be dependent on method of checking (e.g. fuse checking flashlight is lit).

Proc. Step TASK ELEMENT 7 STANDARD Grade REMOVE the 152-106 CLOSE AND TRIP 3.0 Simulates or describes REMOVING the "152-CIRCUIT FUZ/A1106-1 fuses from Startup 106 CLOSE AND TRIP CIRCUIT FUZ/A1106-1" S U 1.e Power Incoming Breaker to Bus 1C, fuses by pulling them from the fuse holder 152-106 Comment:

Evaluator Cue: When operator simulates opening breaker door, then provide operator with CUE SHEET #2A (provide Sheet #2B if candidate cannot read fuse block) (if not provided in Task Element 6). When operator points to Close and Trip fuses (upper right), then cue the operator: "152-106 CLOSE AND TRIP CIRCUIT FUZ/A1106-1 fuses are removed.

CRITICAL STEP PALISADES NUCLEAR PLANT Page 7 of 12 SEPTEMBER 2014

JPM SYSTEM I Proc. Step TASK ELEMENT 8 STANDARD Grade PLACE the local breaker handswitch for 3.0 Simulates or describes PLACING the local Startup Power Incoming breaker to Bus breaker hand switch for Startup Power Incoming S U 1.f 1C, 152-106 to the CLOSE position to Breaker 152-106 to "CLOSE" position energize Bus 1C Comment:

Evaluator Note/Cue: Candidate shall determine that use of protective clothing is required per EN-IS-123 Attachment 9.3 page 41 table (see below): use follow-up question after JPM is complete if candidate does not note requirements during step simulation. Cue that use of Arc Face Shield and FR clothing is being simulated.

Evaluator Cue: Red light on breaker 152-106 is illuminated. Clothing requirements are NOT part of the critical step.

CRITICAL STEP Proc. Step TASK ELEMENT 9 STANDARD Grade NOTIFY the CRS that Bus 1C is energized CRS NOTIFIED that Bus 1C is energized from n/a from Startup Power Startup Power S U Comment:

END OF TASK PALISADES NUCLEAR PLANT Page 8 of 12 SEPTEMBER 2014

JPM SYSTEM I CANDIDATE CUE SHEET #2C (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

PALISADES NUCLEAR PLANT Page 9 of 12 SEPTEMBER 2014

JPM SYSTEM I CANDIDATE CUE SHEET #2B (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

PALISADES NUCLEAR PLANT Page 10 of 12 SEPTEMBER 2014

JPM SYSTEM I CANDIDATE CUE SHEET #2A (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

PALISADES NUCLEAR PLANT Page 11 of 12 SEPTEMBER 2014

JPM SYSTEM I CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

Control Room is not habitable.

Reactor has been tripped and all rods have been inserted into the core.

Bus 1C and Bus 1D are de-energized.

Startup Power Transformer 1-2 is available.

The control power circuit for breaker 152-106 has been damaged.

INITIATING CUES:

During performance of AOP-41, "Alternate Safe Shutdown Procedure" Step 15.1.a, the CRS directs you to energize Bus 1C from Startup Transformer 1-2 locally using EOP Supplement 29 section 3.0.

PALISADES NUCLEAR PLANT Page 12 of 12 SEPTEMBER 2014

NRC REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I SYS J TITLE: MANUALLY START FIRE PUMP P-9A CANDIDATE:

EXAMINER:

JPM SYSTEM J JOB PERFORMANCE MEASURE DATA PAGE Task: Manually start P-9A Fire Pump Alternate Path: YES Facility JPM #: ISDB-JPM-01 K/A: 086A3.01 Importance: RO: 2.9 SRO: 3.3 K/A Statement: Ability to monitor automatic operation of the Fire Protection System including starting mechanisms of fire water pumps.

Task Standard: P-9A is in service Preferred Evaluation Location: Simulator ______ In Plant __X___

Preferred Evaluation Method: Perform ______ Simulate __X___

References:

SOP-21, Fire Protection System Validation Time: 10 minutes Time Critical: NO Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT ______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 7 SEPTEMBER 2014

JPM SYSTEM J EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

SOP-21, Fire Protection System READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

The Plant is shutdown for a refueling outage.

A fire at the Cooling Towers requires the use of P-9A, Fire Water Pump, which has NOT automatically started.

Jockey Pump P-13 is operating and there are NO Service Water Booster Pumps (P-25A/B/C) in service.

INITIATING CUES:

The Shift Manager has directed you to manually start Fire Water Pump P-9A per SOP-21.

PALISADES NUCLEAR PLANT Page 3 of 7 SEPTEMBER 2014

JPM SYSTEM J Evaluator Cue: Provide candidate a working copy of SOP-21 (entire procedure).

Proc. Step TASK ELEMENT 1 STANDARD Grade n/a Locates correct procedure section SOP-21, Section 7.2.1 LOCATED. S U Comment:

Proc. Step TASK ELEMENT 2 STANDARD Grade Press START pushbutton on Local Control Operator simulates pressing START push button on 7.2.1.a Panel local control panel.

S U Comment:

Evaluator Cue: P-9A is not operating or discharge pressure is zero.

EVALUATOR NOTE: Alternate Path begins here: covered in task elements 3 thru 5.

Proc. Step TASK ELEMENT 3 STANDARD Grade Pull the Manual Operator T handle all the way Operator simulates pulling the manual operator T 7.2.1.b.1 out to start mechanically handle all the way out and holding in this position.

S U Comment:

CRITICAL STEP PALISADES NUCLEAR PLANT Page 4 of 7 SEPTEMBER 2014

JPM SYSTEM J Proc. Step TASK ELEMENT 4 STANDARD Grade ROTATE the MANUAL LATCH handle counter- Operator simulates rotating the manual latch handle 7.2.1.b.2 clockwise in order to latch the MANUAL counter-clockwise and releases the manual operator S U OPERATOR T HANDLE. "T" handle.

Comment:

Evaluator Cue: Manual Latch handle is rotated counter-clockwise.

CRITICAL STEP Proc. Step TASK ELEMENT 5 STANDARD Grade


Verify P-9A is operating Operator verifies pump operating. S U Comment:

Evaluator Cue: P-9A is operating and discharge pressure is 153 psig.

Proc. Step TASK ELEMENT 6 STANDARD Grade IF Attachment 2 is in effect, THEN STOP Operator determines that this step is N/A because Fire 7.2.1.c selected Service Water Booster Pump Jockey Pump, P-13, was in service.

S U Comment:

Proc. Step TASK ELEMENT 7 STANDARD Grade Operator notifies the Control Room that P-9A n/a has been manually started.

Control Room notified. S U Comment:

END OF TASK PALISADES NUCLEAR PLANT Page 5 of 7 SEPTEMBER 2014

JPM SYSTEM J SIMULATOR OPERATOR INSTRUCTIONS N/A PALISADES NUCLEAR PLANT Page 6 of 7 SEPTEMBER 2014

JPM SYSTEM J CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

The Plant is shutdown for a refueling outage.

A fire at the Cooling Towers requires the use of P-9A, Fire Water Pump, which has NOT automatically started.

Jockey Pump P-13 is operating and there are NO Service Water Booster Pumps (P-25A/B/C) in service.

INITIATING CUES:

The Shift Manager has directed you to manually start Fire Water Pump P-9A per SOP-21.

PALISADES NUCLEAR PLANT Page 7 of 7 SEPTEMBER 2014

REGION III INITIAL LICENSE EXAM JOB PERFORMANCE MEASURE JPM: RO/SRO-I/SRO-U SYS K TITLE: SUPPLY ALTERNATE SUCTION SOURCE TO AFW PUMP P-8C CANDIDATE:

EXAMINER:

JPM SYS K JOB PERFORMANCE MEASURE DATA PAGE Task: Supply AFW Pumps From Alternate Source IAW EOP Supplement 31 Alternate Path: NO Facility JPM #: PL-OPS-EOP-011J K/A: CE/E06EA1.1 Importance: RO: 4.0 SRO: 3.9 K/A Statement: Ability to operate and/or monitor the following as they apply to loss of the (Loss of Feedwater): Components, and functions of control and safety systems, including instrumentation, signals, interlocks, failure modes, and automatic and manual features.

Task Standard: AFW pump, P-8C, has suction from the Service Water system and its low suction pressure trip reset.

Preferred Evaluation Location: Simulator ____ In Plant _X__

Preferred Evaluation Method: Perform ____ Simulate _X__

References:

EOP Supplement 31, Supply AFW Pumps from Alternate Sources Validation Time: 20 minutes Time Critical: NO Candidate:

Time Start: ________ Time Finish: ________

Performance Time: ________ minutes Performance Rating: SAT______ UNSAT ______

Comments:

Examiner: _______________________________ Date: ______________

Signature PALISADES NUCLEAR PLANT Page 2 of 7 SEPTEMBER 2014

JPM SYS K EXAMINER COPY ONLY Tools/Equipment/Procedures Needed:

EOP Supplement 31, Supply AFW Pumps from Alternate Sources READ TO CANDIDATE DIRECTION TO CANDIDATE:

I will explain the initial conditions, and state the task to be performed. All control room steps shall be performed for this JPM, including any required communications. I will provide initiating cues and reports on other actions when directed by you. Ensure you indicate to me when you understand your assigned task. To indicate that you have completed your assigned task return the handout sheet I provided you.

INITIAL CONDITIONS:

A Reactor trip has occurred.

Loss of all Feedwater has occurred and Auxiliary Feedwater Pumps, P-8A and P-8B, are not available.

Condensate Storage Tank, T-2, has a very large hole at the bottom of the tank and is empty.

AFW Pump, P-8C, has tripped on low suction pressure.

P-8C Start Select Switch HS-P8C is in the MANUAL position.

Chemistry has been notified that Service Water will be supplied to the Steam Generators.

INITIATING CUES:

The CRS gives you a locked valve key and directs you to complete section 1.0, steps 1 through 7, of EOP Supplement 31, "Supply AFW Pumps from Alternate Sources," to supply Service Water to P-8C.

PALISADES NUCLEAR PLANT Page 3 of 7 SEPTEMBER 2014

JPM SYS K Proc. Step TASK ELEMENT 1 STANDARD Grade Locate copy of EOP Supplement 31 and n/a obtain a locked valve key from control EOP Supplement 31 is located. S U room.

Comment:

Evaluator Cue: Provide the candidate with a working copy of EOP Supplement 31.

Evaluator Cue: Inform the candidate that they have a simulated locked valve key.

Proc. Step TASK ELEMENT 2 STANDARD Grade PLACE P-8C Start Select Switch HS-P-8C to Operator determines this step has been completed 1.0.1 MANUAL. per initial conditions.

S U Comment:

Proc. Step TASK ELEMENT 3 STANDARD Grade UNLOCK MV-FW750, AFW Pump P-8C 1.0.2 Supply from SWS.

Operator simulates unlocking MV-FW750 S U Comment:

Evaluator Cue: MV-FW750 is unlocked.

CRITICAL STEP Proc. Step TASK ELEMENT 4 STANDARD Grade THROTTLE OPEN MV-FW750, AFW Pump P-8C Supply from SWS until water issues from Operator simulates throttling open MV-FW750 and 1.0.3 Leak-off valve P-8C Supply from SWS Leak looks for leakage from leak-off valve MV-FW759.

S U Test, MV-FW759.

Comment:

Evaluator Cue: MV-FW750 is throttled open and water is issuing from MV-FW759.

CRITICAL STEP PALISADES NUCLEAR PLANT Page 4 of 7 SEPTEMBER 2014

JPM SYS K Proc. Step TASK ELEMENT 5 STANDARD Grade WHEN water issues from P-8C Supply from 1.0.4 SWS Leak Test, MV-FW759, THEN CLOSE Operator simulates closing MV-FW759. S U MV-FW759.

Comment:

Evaluator Cue: When candidate simulates closing MV-FW759, cue that valve will not turn any further to the right and water is not issuing from MV-FW759.

CRITICAL STEP Proc. Step TASK ELEMENT 6 STANDARD Grade OPEN MV-FW750, AFW Pump P-8C Supply 1.0.5 from SWS.

Operator simulates fully opening MV-FW750. S U Comment:

Evaluator Cue: When candidate simulates MV-FW750 open, then cue that valve will not turn any further to the left.

CRITICAL STEP Proc. Step TASK ELEMENT 7 STANDARD Grade UNLOCK AND OPEN AFW Pump P-8C Supply ___ Simulates unlocking MV-FW750A 1.0.6 from SWS MV-FW750A.

S U

___ Simulates opening MV-FW-750A Comment:

Evaluator Cue: MV-FW-750A is unlocked. When candidate simulates MV-FW750A open, then cue that valve will not turn any further to the left.

CRITICAL STEP Proc. Step TASK ELEMENT 8 STANDARD Grade NOTIFY Control Room Supervisor or Nuclear Operator simulates notifying the Control Room 1.0.7 Control Operator P-8C AFW pump service Supervisor or Nuclear Control Operator that P-8C, S U water supply is aligned. AFW pump, is aligned to service water.

Comment:

END OF TASK PALISADES NUCLEAR PLANT Page 5 of 7 SEPTEMBER 2014

JPM SYS K SIMULATOR OPERATOR INSTRUCTIONS N/A PALISADES NUCLEAR PLANT Page 6 of 7 SEPTEMBER 2014

JPM SYS K CANDIDATE CUE SHEET (TO BE RETURNED TO EXAMINER TO UPON COMPLETION OF TASK)

INITIAL CONDITIONS:

A Reactor trip has occurred.

Loss of all Feedwater has occurred and Auxiliary Feedwater Pumps, P-8A and P-8B, are not available.

Condensate Storage Tank, T-2, has a very large hole at the bottom of the tank and is empty.

AFW Pump, P-8C, has tripped on low suction pressure.

P-8C Start Select Switch HS-P8C is in the MANUAL position.

Chemistry has been notified that Service Water will be supplied to the Steam Generators.

INITIATING CUES:

The CRS gives you a locked valve key and directs you to complete section 1.0, steps 1 through 7, of EOP Supplement 31, "Supply AFW Pumps from Alternate Sources," to supply Service Water to P-8C.

PALISADES NUCLEAR PLANT Page 7 of 7 SEPTEMBER 2014