ML093080805: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
| Line 3: | Line 3: | ||
| issue date = 05/26/2009 | | issue date = 05/26/2009 | ||
| title = E-mail from J. White to M. Ferdas and R. Bellamy Re Timeline for Second Excavation | | title = E-mail from J. White to M. Ferdas and R. Bellamy Re Timeline for Second Excavation | ||
| author name = White J | | author name = White J | ||
| author affiliation = NRC/RGN-I/DRS/PSB2 | | author affiliation = NRC/RGN-I/DRS/PSB2 | ||
| addressee name = Bellamy | | addressee name = Bellamy R, Ferdas M | ||
| addressee affiliation = NRC/RGN-I/DNMS/MB, NRC/RGN-I/DRP/PB6 | | addressee affiliation = NRC/RGN-I/DNMS/MB, NRC/RGN-I/DRP/PB6 | ||
| docket = 05000219 | | docket = 05000219 | ||
| Line 19: | Line 19: | ||
==Subject:== | ==Subject:== | ||
FW: Timeline for Second Excavation at Oyster Creek From: James. Barstow@exeloncorp.com | FW: Timeline for Second Excavation at Oyster Creek From: James. Barstow@exeloncorp.com | ||
[mailto:James.Barstow@exeloncorp.com].Sent: Thursday, May 21, 2009 2:04 PM To: John White | [mailto:James.Barstow@exeloncorp.com].Sent: Thursday, May 21, 2009 2:04 PM To: John White | ||
Revision as of 16:19, 11 July 2019
| ML093080805 | |
| Person / Time | |
|---|---|
| Site: | Oyster Creek |
| Issue date: | 05/26/2009 |
| From: | Jason White NRC/RGN-I/DRS/PSB2 |
| To: | Ronald Bellamy, Marc Ferdas NRC/RGN-I/DNMS/MB, NRC/RGN-I/DRP/PB6 |
| References | |
| FOIA/PA-2009-0214 | |
| Download: ML093080805 (2) | |
Text
Bellamy, Ronald From: John White.Sent: Tuesday, May 26, 2009 7:57 AM To: Marc Ferdas; Ronald Bellamy Cc: Ronald Nimitz; Harold Gray
Subject:
FW: Timeline for Second Excavation at Oyster Creek From: James. Barstow@exeloncorp.com
[1].Sent: Thursday, May 21, 2009 2:04 PM To: John White
Subject:
Timeline for Second Excavation at Oyster Creek John, Below is the timeline that Project Management is utilizing for the inspection of the CS-38 line. This is a tentative schedule weather permitting.
Jim* Diving complete:
5/20/09* Area policed in preparation of MUA tour: 5/20/09-5/21/09
- Repair of penetration at Turbine Building:
5/22/09 0 Tour of trenching:
5/22/09* De-mob and clean-up of area: 5/26/09-5/29/09
- Free release of material by R.P. 6/01/09-6/13/09
- Backfill of trench: 6/1/09-6/5/09
- Excavation of C.R.D. min flow line: 6/8/09-6/12/09
- Inspection of pipe:6/15/09
- Remove coating (contingent):
6/16/09* UT inspection (contingent):
6/17/09* Re-coat piping (contingent):
6/18/09-6/19/09
- Backfill second excavation:6/22/09-6/26/09 Jim (Barstow Exelon Corporation TeamOysterCreek Oyster Creek Generating Station Regulatory Assurance Manager Office of the Site Vice President James. Barstow(ýexeloncorp.com Work -609-971-4947 This e-mail and any of its attachments may contain Exelon Corporation proprietary information, which is privileged, confidential, or subject to copyright belonging to the Exelon Corporation family of Companies.
This e-mail is intended solely for the use of the individual or entity to which it is addressed.
If you are not the intended recipient of this e-mail, you are hereby notified that any dissemination, distribution, copying, or actionr taken in relation to the contents of and attachments to this e-mail is strictly prohibited and may be unlawful.
If you have received this e-mail in error, please notify the sender immediately and permanently delete the original and any copy of this e-mail and any printout.
Thank You. *2