ML101180318: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
| Line 3: | Line 3: | ||
| issue date = 01/25/2010 | | issue date = 01/25/2010 | ||
| title = E-Mail Form Chou to Franke, Crystal River 3 Concrete Repair Level 2 Schedule | | title = E-Mail Form Chou to Franke, Crystal River 3 Concrete Repair Level 2 Schedule | ||
| author name = Chou R | | author name = Chou R | ||
| author affiliation = NRC/RGN-II/DRS/EB3 | | author affiliation = NRC/RGN-II/DRS/EB3 | ||
| addressee name = Franke M | | addressee name = Franke M | ||
| addressee affiliation = NRC/RGN-II/DRS/EB3 | | addressee affiliation = NRC/RGN-II/DRS/EB3 | ||
| docket = 05000302 | | docket = 05000302 | ||
Revision as of 09:49, 11 July 2019
| ML101180318 | |
| Person / Time | |
|---|---|
| Site: | Crystal River |
| Issue date: | 01/25/2010 |
| From: | Chou R NRC/RGN-II/DRS/EB3 |
| To: | Mark Franke NRC/RGN-II/DRS/EB3 |
| References | |
| FOIA/PA-2010-0116 | |
| Download: ML101180318 (1) | |
Text
Franke, Mark From: Chou, Rich Sent: Monday, January 25, 2010 3:58 PM To: Franke, Mark
Subject:
RE: Crystal River 3 Concrete Repair Level 2 schedule Mark: You are welcome.From: Franke, Mark t"CiSent: Monday, January 25, 2010 1:54 PM To: Chou, Rich
Subject:
Re: Crystal River 3 Concrete Repair Level 2 schedule Thanks Rich This email is being sent from an NRC Blackberry device.From: Chou, Rich To: Franke, Mark Cc: Lake, Louis; Sykes, Marvin; Ninh, Son; Morrissey, Thomas; Reyes, Rogerio; Chou, Rich Sent: Mon Jan 25 13:14:59 2010
Subject:
Crystal River 3 Concrete Repair Level 2 schedule Mark: This morning, Sid Powell of the licensee containment concrete repair coordinator called me to state that President of Progress Energy would meet the Ga Public Service Commission this Thursday or Friday to discuss the CR3 concrete repair schedule.
The currently estimated end schedule is June. However, the licensee does not want to announce the schedule until their President officially discusses it with the Pubic Service Commission.
After that meeting, the licensee will officially announce the repair schedule to the public and gives NRC more accurate repair schedule and details.57