ML16092A200: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 3: Line 3:
| issue date = 03/29/2016
| issue date = 03/29/2016
| title = Notification of H.B. Robinson Steam Electric Plant - Component Design Bases Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000261/2016008
| title = Notification of H.B. Robinson Steam Electric Plant - Component Design Bases Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000261/2016008
| author name = Bartley J H
| author name = Bartley J
| author affiliation = NRC/RGN-II/DRS/EB1
| author affiliation = NRC/RGN-II/DRS/EB1
| addressee name = Glover R M
| addressee name = Glover R
| addressee affiliation = Duke Energy Corp
| addressee affiliation = Duke Energy Corp
| docket = 05000261
| docket = 05000261
Line 14: Line 14:
| page count = 5
| page count = 5
}}
}}
See also: [[followed by::IR 05000261/2016008]]
See also: [[see also::IR 05000261/2016008]]


=Text=
=Text=

Revision as of 06:32, 20 June 2019

Notification of H.B. Robinson Steam Electric Plant - Component Design Bases Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000261/2016008
ML16092A200
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 03/29/2016
From: Bartley J
NRC/RGN-II/DRS/EB1
To: Glover R
Duke Energy Corp
References
IR 2016008
Download: ML16092A200 (5)


See also: IR 05000261/2016008

Text

UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257

March 29, 2016

Richard Michael Glover Site Vice President H.B. Robinson Steam Electric Plant

Duke Energy

3581 West Entrance Road, RNPA01

Hartsville, SC 29550

SUBJECT: NOTIFICATION OF H.B. ROBINSON STEAM ELECTRIC PLANT - COMPONENT DESIGN BASES INSPECTION - U.S. NUCLEAR REGULATORY COMMISSION

INSPECTION REPORT 05000261/2016008

Dear Mr. Glover:

The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)

Region II staff will conduct a component design bases inspection (CDBI) at your H.B. Robinson Steam Electric Plant during the weeks of July 18 - 22, August 1 - 5, and August 15 - 19, 2016. Geoffrey Ottenberg, a Senior Reactor Inspector from the NRC's Region II Office, will lead the inspection team. This inspection will be conducted in accordance with Inspection Procedure

71111.21, "Component Design Bases Inspection," issued November 29, 2013.

The inspection will evaluate the capability of risk-significant/low-margin components to function as designed and to support proper system operation. The inspection will also include a review of selected operator actions, operating experience, and modifications.

During a telephone conversation on March 22, 2016, the staff confirmed with Mr. J. Wild of your

staff, arrangements for an information-gathering site visit and the three-week onsite inspection. The schedule is as follows:

  • Information-gathering visit: Week of June 27 - July 1, 2016
  • Onsite weeks: July 18 - 22, August 1 - 5, and August 15 - 19, 2016

The purpose of the information-gathering visit is to meet with members of your staff to identify

risk-significant components and operator actions. Information and documentation needed to

support the inspection will also be identified. Mr. Geoffrey Ottenberg, a Senior Reactor

Inspector, will be conducting all preparation activities associated with the inspection. In addition, Mr. George MacDonald, a Region II Senior Reactor Analyst, will support Mr. Ottenberg during the information-gathering visit to review probabilistic risk assessment data and identify

risk-significant components, which will be examined during the inspection.

The Enclosure lists documents that will be needed prior to the information-gathering visit.

Please provide the referenced information to the Region II Office by June 13, 2016.

R. Glover 2

Additional documents may be requested during the information-gathering visit. The inspectors will try to minimize your administrative burden by specifically identifying only those documents

required for inspection preparation. The additional information will need to be available to the team in the Region II office prior to the inspection team's preparation week of July 11, 2016. During the information-gathering trip, Mr. Ottenberg will also discuss the following inspection

support administrative details: (1) availability of knowledgeable plant engineering and licensing personnel to serve as points of contact during the inspection; (2) method of tracking inspector

requests during the inspection; (3) licensee computer access; (4) working space;

(5) arrangements for site access; and (6) other applicable information.

In accordance with Title 10 of the Code of Federal Regulations 2.390 of the NRC's "Rules of Practice," a copy of this letter and its Enclosure will be available electronically for public

inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management Sy

stem (ADAMS). ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Thank you for your cooperation in this matter. If you have any questions, regarding the

information requested or the inspection, please contact Mr. Ottenberg at 404-997-4658 or

contact me at 404-997-4607.

Sincerely,

/RA/ Jonathan H. Bartley, Chief Engineering Branch 1

Division of Reactor Safety

Docket No: 50-261 License No: DPR-23

Enclosure:

Information Request for H.B. Robinson Steam Electric

Plant, Component Design Bases Inspection

cc: Distribution via Listserv

_________________________ SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRS RII:DRS

SIGNATURE JHB1 FOR GKO JHB1 NAME GOTTENBERG JBARTLEY DATE 3/29/2016 3/26/2016 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES

Enclosure INFORMATION REQUEST FOR H.B. ROBINSON STEAM ELECTRIC PLANT COMPONENT DESIGN BASES INSPECTION

Please provide the information electronically in ".pdf" files, Excel, or other searchable format on CDROM (or FTP site, Sharepoint, etc.). The CDROM (or website) should be indexed and

hyperlinked to facilitate ease of use.

1. From your most recent probabilistic safety analysis (PSA)

excluding external events and

fires: a. Two risk rankings of components from your site-specific PSA: one sorted by Risk Achievement Worth (RAW), and the other sorted by Birnbaum Importance

b. A list of the top 500 cutsets

2. From your most recent PSA

including external events and fires:

a. Two risk rankings of components from your site-specific PSA: one sorted by RAW, and the other sorted by Birnbaum Importance

b. A list of the top 500 cutsets

3. Risk ranking of operator actions from your site-specific PSA sorted by RAW. Provide human reliability worksheets for these items.

4. List of time-critical operator actions with a brief description of each action.

5. List of Emergency and Abnormal Operating Procedures revised (significant) since July 1, 2013, with a brief description of each revision.

6. List of components with low-design margins (i.e., pumps closest to the design limit for flow or pressure, diesel generator close to design-required output, heat exchangers close to

rated design heat removal, and motor-operated valve risk-margin rankings, etc.).

7. List of station-operating experience evaluations/reviews performed, and documented in the station's corrective action program, for industry events and safety-related equipment

failures/vulnerabilities (as communicated by NRC Generic Communications, Industry

Communications, 10 CFR Part 21 Notifications, etc.) since July 1, 2013.

8. List and brief description of safety-related structures, systems, or components (SSCs)

design modifications implemented since July 1, 2013.

9. List and brief description of common-cause component failures that have occurred

since July 1, 2013.

10. List of equipment on the site's Station Equipment Reliability Issues List, including a description of the reason(s) why each component is on that list, and summaries (if

available) of your plans to address the issue(s).

2 11. List and brief description of equipment currently in degraded or nonconforming status as described in NRC Inspection Manual Chapter 0326, Operability Determinations and

Functionality Assessments for Conditions Adverse to Quality or Safety, issued

January 31, 2014.

12. List and reason for equipment classified in maintenance rule (a) (1) status from

July 1, 2013, to present.

13. Copy of Updated Final Safety Analysis Report.

14. Copy of Technical Specification(s).

15. Copy of Technical Specifications Bases.

16. Copy of Technical Requirements Manual(s).

17. List and brief description of Root Cause Evaluations performed since July 1, 2013.

18. Corrective Action Program Procedure(s).

19. Copy of Operability Determination procedure(s).

20. one-line diagram of electrical plant. (Electronic and full size - hard copy week

of June 27 - July 1, 2016)

21. Index and legend for electrical plant one-line diagrams.

22. Piping and instrumentation diagrams (P&IDs) for safety-related systems. (Electronic and 11 x 17 size - hard copy week of June 27 - July 1, 2016)

23. Index and Legend for P&IDs.

24. Copies of corrective action documents (i.e. CRs) associated with findings from previous CDBI. (If applicable)

25. Index (procedure number, title, and current revision) of station Emergency Operating Procedures, Abnormal Operating Procedures, and Annunciator Response Procedures.

26. Copies of any self-assessments performed in preparation for this inspection (2016 CDBI) and the self-assessment performed in preparation for the previous CDBI (2013).

27. List of any condition reports generated in preparation for this inspection.

28. Copies of condition reports generated from previous CDBI (2013).

29. Contact information for a person to discuss PSA information prior to and during the information-gathering trip. (Name, title, phone number, and e-mail address)