{{Adams
{{Adams
| number = ML16053A400
| number = ML19067A189
| issue date = 02/22/2016
| issue date = 03/07/2019
| title = Ltr. 02/22/16 Palisades Nuclear Plant Follow-Up to Disputed Violations of NRC Inspection Report 05000255/2015003 (Lnr)
| title = Ltr. 03/07/19 Revised NCV - Palisades Nuclear Plant NRC Integrated IR 05000255/2015003 (NCV 05000255/2015003-01; Failure to Justify Continued Service of Safety-Related Electrolytic Capacitors Installed Beyond Their Service Life (DRS-N.Feliz
| author name = Hills D E
| author name = O'Brien K
| author affiliation = NRC/RGN-III/DRS/EB1
| author affiliation = NRC/RGN-III/DRS
| addressee name = Vitale A
| addressee name = Arnone C
| addressee affiliation = Entergy Nuclear Operations, Inc
| addressee affiliation = Entergy Nuclear Operations, Inc
| docket = 05000255
| docket = 05000255
Line 13: Line 13:
| document report number = IR 2015003
| document report number = IR 2015003
| document type = Letter
| document type = Letter
| page count = 2
| page count = 8
}}
}}


Line 19: Line 19:


=Text=
=Text=
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUIT E 210 LISLE, IL 60532
{{#Wiki_filter:
-4352 February 22, 2016 EA-15-264 Mr. Anthony Vitale Vice President, Operations Entergy Nuclear Operations, Inc.
[[Issue date::March 7, 2019]]


Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043
EA-1 5-264 Mr. Charles Arnone Vice President, Operations Entergy Nuclear Operations, Inc.
-9530


SUBJECT: PALISADES NUCLEAR PLANT FOLLOW-UP TO DISPUTED VIOLATION OF NRC INSPECTION REPORT 05000255/2015003
Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043-9530


==Dear Mr. Vitale:==
SUBJECT: REVISED NON-CITED VIOLATION
This is a follow
-PALISADES NUCLEAR PLANT NRC INTEGRATED INSPECTION REPORT 05000255/2015003 (NCV 05000255/2015003
-up letter to the U.S. Nuclear Regulatory Commission (NRC)
-01; FAILURE TO JUSTIFY CONTINUED SERVICE OF SAFETY-RELATED ELECTROLYTIC CAPACITORS INSTALLED BEYOND THEIR SERVICE LIFE)
acknowledgement of disputed violation of NRC Inspection Report (IR) 05000255/2015003. Specifically, on December 21, 2015, the NRC acknowledged your letter sent to the NRC, dated November 30, 2015, that contested a Non
-Cited Violation (NCV) documented in our IR issued on October 30
, 2015. The contested NCV is "Failure to Justify Continued Service of Safety-Related Electrolytic Capacitors Installed Beyond their Service Life
." The NRC seeks to provide a thorough response to disputed violations within 90 days of receipt of licensee's points of contention, as described in Section 2.2.8 of the NRC Enforcement Manual, Part I. However, the NRC review of this disputed violation is expected to take longer than 90 days as we pursue a generic Agency position for the industry
. In the interim, we understand you have entered the underlying technical issue into your Corrective Action Program, as discussed in I R 05000255/2015003. W e will inform you as soon as we complete our evaluation
. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," of the NRC's "Rules of Practice," a copy


of this letter will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide
==Dear Mr. Arnone:==
On November 30, 2015, Palisades Nuclear Plant (PNP) provided a written response to U.S. Nuclear Regulatory Commission (NRC) Inspection Report 05000255/2015003
, which was issued on October 30, 2015. Specifically, the lette r contested Non
-Cited Violation 05000255/2015003
-01 associated with the failure to justify continued service of safety-related containment floor level indicating transmitter electrolytic capacitors installed beyond their service life. The letter explained PNP agreed a performance deficiency occurred but disagreed the deficiency was associated with a violation of Title 10 of the Code of Federal Regulations
, Part 50, Appendix B, Criterion III, "Design Control," as stated in the inspection report. The letter further stated PNP believed the performance deficiency was associated with 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures, and Drawings."


Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading
The NRC carefully reviewed PNP's reply and determined the Non-Cited Violation should be changed to a violation of Technical Specifications Section 5.4.1, "Procedures
-rm/adams.html (the Public Electronic Reading Room).
," as shown in the enclosed report.


Sincerely,/RA/ David E. Hills, Acting Chief Engineering Branch 2 Division of Reactor Safety Docket No. 50
Technical Specifications Section 5.4.1
-255 License No. DPR
, requires, in part, the establishment, implementation, and maintenance of written procedures recommended in Regulatory Guide 1.33, Revision 2, Appendix A, February 1978. Section 9 of the Regulatory Guide requires the development of preventive maintenance schedules and associated procedure s for the inspection or replacement of parts that have a specific lifetime.
-20 cc: Distribution via LISTSERV


February 22, 2016 EA-15-264 Mr. Anthony Vitale Vice President, Operations Entergy Nuclear Operations, Inc.
The bases for the staff's conclusion are detailed in the enclosed report. This letter, its enclosure, PNP's November 30, 2015, response, and your response (if any)
will be made available for public inspection and copying at http://www.nrc.gov/reading
-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, "Public Inspections, Exemptions, Requests for Withholding."


Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043
Sincerely,/RA/ Kenneth O'Brien, Director Division of Reactor Safety Docket No. 50
-9530
 
SUBJECT: PALISADES NUCLEAR PLANT FOLLOW
-UP TO DISPUTED VIOLATION OF NRC INSPECTION REPORT 05000255/2015003
 
==Dear Mr. Vitale:==
This is a follow
-up letter to the U.S. Nuclear Regulatory Commission (NRC) acknowledgement of disputed violation of NRC Inspection Report (IR) 05000255/2015003. Specifically, on December 21, 2015, the NRC acknowledged your letter sent to the NRC, dated November 30, 2015, that contested a Non
-Cited Violation (NCV) documented in our IR issued on October 30, 2015. The contested NCV is "Failure to Justify Continued Service of Safety-Related Electrolytic Capacitors Installed Beyond their Service Life."
 
The NRC seeks to provide a thorough response to disputed violations within 90 days of receipt of licensee's points of contention, as described in Section 2.2.8 of the NRC Enforcement Manual, Part I. However, the NRC review of this disputed violation is expected to take longer than 90 days as we pursue a generic Agency position for the industry. In the interim, we understand you have entered the underlying technical issue into your Corrective Action Program, as discussed in IR 05000255/2015003. We will inform you as soon as we complete our evaluation.
 
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections , Exemptions, Requests for Withholding," of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading
-rm/adams.html (the Public Electronic Reading Room).
 
Sincerely,/RA/ David E. Hills, Acting Chief
 
Engineering Branch 2 Division of Reactor Safety Docket No. 50
-255 License No. DPR
-255 License No. DPR
-20 cc: Distribution via LISTSERV DISTRIBUTION
-20  
: Janelle Jessie
 
RidsNrrDorlLpl3
-1 Resource RidsNrrPMMonticello RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Richard Skokowski Allan Barker Carole Ariano
 
Linda Linn DRPIII DRSIII Jim Clay Carmen Olteanu


ADAMS Accession Number ML16053A400 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME LRodriguez DHills DATE 0 2/18/16 0 2/22/1 6 OFFICIAL RECORD COPY
===Enclosure:===
NRC Staff Assessment of Disputed NCV 05000255/2015003
-01 cc: Distribution via LISTSERV
}}
}}

Revision as of 19:10, 7 April 2019

Ltr. 03/07/19 Revised NCV - Palisades Nuclear Plant NRC Integrated IR 05000255/2015003 (NCV 05000255/2015003-01; Failure to Justify Continued Service of Safety-Related Electrolytic Capacitors Installed Beyond Their Service Life (DRS-N.Feliz
ML19067A189
Person / Time
Site: Palisades Entergy icon.png
Issue date: 03/07/2019
From: O'Brien K
Division of Reactor Safety III
To: Arnone C
Entergy Nuclear Operations
References
EA-15-264 IR 2015003
Download: ML19067A189 (8)


Text

March 7, 2019

EA-1 5-264 Mr. Charles Arnone Vice President, Operations Entergy Nuclear Operations, Inc.

Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043-9530

SUBJECT: REVISED NON-CITED VIOLATION

-PALISADES NUCLEAR PLANT NRC INTEGRATED INSPECTION REPORT 05000255/2015003 (NCV 05000255/2015003

-01; FAILURE TO JUSTIFY CONTINUED SERVICE OF SAFETY-RELATED ELECTROLYTIC CAPACITORS INSTALLED BEYOND THEIR SERVICE LIFE)

Dear Mr. Arnone:

On November 30, 2015, Palisades Nuclear Plant (PNP) provided a written response to U.S. Nuclear Regulatory Commission (NRC) Inspection Report 05000255/2015003

, which was issued on October 30, 2015. Specifically, the lette r contested Non

-Cited Violation 05000255/2015003

-01 associated with the failure to justify continued service of safety-related containment floor level indicating transmitter electrolytic capacitors installed beyond their service life. The letter explained PNP agreed a performance deficiency occurred but disagreed the deficiency was associated with a violation of Title 10 of the Code of Federal Regulations

, Part 50, Appendix B, Criterion III, "Design Control," as stated in the inspection report. The letter further stated PNP believed the performance deficiency was associated with 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures, and Drawings."

The NRC carefully reviewed PNP's reply and determined the Non-Cited Violation should be changed to a violation of Technical Specifications Section 5.4.1, "Procedures

," as shown in the enclosed report.

Technical Specifications Section 5.4.1

, requires, in part, the establishment, implementation, and maintenance of written procedures recommended in Regulatory Guide 1.33, Revision 2, Appendix A, February 1978. Section 9 of the Regulatory Guide requires the development of preventive maintenance schedules and associated procedure s for the inspection or replacement of parts that have a specific lifetime.

The bases for the staff's conclusion are detailed in the enclosed report. This letter, its enclosure, PNP's November 30, 2015, response, and your response (if any)

will be made available for public inspection and copying at http://www.nrc.gov/reading

-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, "Public Inspections, Exemptions, Requests for Withholding."

Sincerely,/RA/ Kenneth O'Brien, Director Division of Reactor Safety Docket No. 50

-255 License No. DPR

-20

Enclosure:

NRC Staff Assessment of Disputed NCV 05000255/2015003

-01 cc: Distribution via LISTSERV