ML081280003: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
| Line 2: | Line 2: | ||
| number = ML081280003 | | number = ML081280003 | ||
| issue date = 05/09/2008 | | issue date = 05/09/2008 | ||
| title = | | title = Review of the 180-Day Steam Generator Tube Inspection Report for the 14th Refueling Outage | ||
| author name = Kalyanam N | | author name = Kalyanam N | ||
| author affiliation = NRC/NRR/ADRO/DORL/LPLIV | | author affiliation = NRC/NRR/ADRO/DORL/LPLIV | ||
Revision as of 02:18, 10 February 2019
| ML081280003 | |
| Person / Time | |
|---|---|
| Site: | Waterford |
| Issue date: | 05/09/2008 |
| From: | Kalyanam N NRC/NRR/ADRO/DORL/LPLIV |
| To: | Entergy Operations |
| Kalyanam N, NRR/DORL/LPL4, 415-1480 | |
| References | |
| TAC MD5950 | |
| Download: ML081280003 (3) | |
Text
May 9, 2008
Vice President, Operations Entergy Operations, Inc.
Waterford Steam Electric Station, Unit 3 17265 River Road Killona, LA 70057-3093
SUBJECT:
WATERFORD STEAM ELECTRIC STATION, UNIT 3 - REVIEW OF THE 180-DAY STEAM GENERATOR TUBE INSPECTION REPORT FOR THE 14TH REFUELING OUTAGE - (TAC NO. MD5950)
Dear Sir or Madam:
By letter dated June 21, 2007 ((Agencywide Documents Access and Management System (ADAMS) Accession No. ML071730476), Entergy Operations, Inc. (the licensee) submitted information, pursuant to Technical Specification (TS) 6.9.1.5, summarizing the scope, methods, and results of the Fall 2006 steam generator (SG) tube inspections (during Refueling Outage 14) at Waterford Steam Electric Station, Unit 3 (Waterford 3). Additional details of these inspections are documented in a conference call summary dated February 7, 2007 (ADAMS Accession No. ML070520209).
The U.S. Nuclear Regulatory Commission (NRC) staff reviewed the licensee's June 21, 2007 report and concludes that the licensee provided the information required by their TS. The NRC staff review of this report did not identify any new technical issues that warrant follow-up action. The NRC staff will continue to monitor the licensee's efforts to manage the damaged batwing supports and to ensure that no significant consequential damage of the SG tubing is occurring. The licensee met with the NRC staff on February 12, 2008 (ADAMS Accession No. ML080510251) to discuss the status of its batwing management program and their plans for inspecting the batwings and tubes during the spring 2008 refueling outage. In addition, the licensee will brief the NRC staff by phone on the inspection results when the results become available.
Sincerely,
/RA/
N. Kalyanam, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Docket No. 50-382
cc w/encl: See next page
The U.S. Nuclear Regulatory Commission (NRC) staff reviewed the licensee's June 21, 2007 report and concludes that the licensee provided the information required by their TS. The NRC staff review of this report did not identify any new technical issues that warrant follow-up action. The NRC staff will continue to monitor the licensee's efforts to manage the damaged batwing supports and to ensure that no significant consequential damage of the SG tubing is occurring. The licensee met with the NRC staff on February 12, 2008 (ADAMS Accession No. ML080510251) to discuss the status of its batwing management program and their plans for inspecting the batwings and tubes during the spring 2008 refueling outage. In addition, the licensee will brief the NRC staff by phone on the inspection results when the results become available. Sincerely,
/RA/
N. Kalyanam, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Docket No. 50-382
cc w/encl: See next page
DISTRIBUTION
- PUBLIC LPLIV Reading RidsNrrDorlDpr RidsNrrDorlLpl4 RidsNrrPMNKalyanam RidsNrrLAGLappert RidsOgcRp RidsRgn4MailCenter RidsNrrDciCsgb JAdams, EDO RIV RidsAcrsAcnwMailCenter
ADAMS Accession No. ML081280003 *Concurrence via memorandum OFFICE NRR/LPL4/PM NRR/LPL4/LA NRR/DCI/CSGB NRR/LPL4/BC NAME NKalyanam GLappert AHiser* THiltz DATE 5/7/08 5/7/08 5/5/08 5/9/08 Waterford Steam Electric Station, Unit 3 (2/25/08)
cc:
Senior Vice President Entergy Nuclear Operations P.O. Box 31995 Jackson, MS 39286-1995
Vice President, Oversight Entergy Nuclear Operations P.O. Box 31995 Jackson, MS 39286-1995
Senior Manager, Nuclear Safety
& Licensing Entergy Nuclear Operations P.O. Box 31995 Jackson, MS 39286-1995
Senior Vice President
& Chief Operating Officer Entergy Operations, Inc.
P.O. Box 31995 Jackson, MS 39286-1995
Associate General Counsel Entergy Nuclear Operations P.O. Box 31995 Jackson, MS 39286-1995
Manager, Licensing Entergy Operations, Inc.
Waterford Steam Electric Station, Unit 3 17265 River Road Killona, LA 70057-3093
Mr. Timothy Pflieger Environmental Scientist - Supervisor REP&R-CAP-SPOC Louisiana Department of Environmental Quality P.O. Box 4312 Baton Rouge, LA 70821-4312
Parish President Council St. Charles Parish P.O. Box 302 Hahnville, LA 70057
Chairman Louisiana Public Services Commission P.O. Box 91154 Baton Rouge, LA 70825-1697
Mr. Richard Penrod, Senior Environmental Scientist/State Liaison Officer Office of Environmental Services Northwestern State University Russell Hall, Room 201 Natchitoches, LA 71497
Resident Inspector Waterford NPS P.O. Box 822 Killona, LA 70057-0751
Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011