IR 05000237/2008406: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
Line 1: Line 1:
{{Adams|number = ML081270591}}
{{Adams
| number = ML081270591
| issue date = 05/06/2008
| title = IR 05000237-08-406(DRS); IR 05000249-08-406(DRS); on 04/02/2008, Exelon Nuclear Corporate; 04/15/2008 - 04/16/2008; Dresden Nuclear Power Station, Units 2 and 3; Temporary Instruction 2201/002 Inspection - Cover Letter
| author name = Duncan E R
| author affiliation = NRC/RGN-III/DRS/PSB
| addressee name = Pardee C G
| addressee affiliation = Exelon Generation Co, LLC
| docket = 05000237, 05000249
| license number = DPR-019, DPR-025
| contact person =
| document report number = IR-08-406
| document type = Inspection Report, Letter
| page count = 4
}}


{{IR-Nav| site = 05000237 | year = 2008 | report number = 406 }}
{{IR-Nav| site = 05000237 | year = 2008 | report number = 406 }}
Line 12: Line 26:


==Dear Mr. Pardee:==
==Dear Mr. Pardee:==
On April 16, 2008, the U. S. Nuclear Regulatory Commission (NRC) completed a temporary instruction inspection at your Dresden Nuclear Power Station. The inspection covered the transition from a contract to a proprietary security force. The enclosed inspection report documents the inspection results, which were discussed on April 16, 2008, with Mr. D. Wozniak and other members of your staff. The inspection examined activities conducted under your license as they relate to security and compliance with the Commission's rules and regulations and with the conditions of your license.
On April 16, 2008, the U. S. Nuclear Regulatory Commission (NRC) completed a temporary instruction inspection at your Dresden Nuclear Power Station. The inspection covered the transition from a contract to a proprietary security force. The enclosed inspection report documents the inspection results, which were discussed on April 16, 2008, with Mr. D. Wozniak and other members of your staff.


The inspector reviewed selected procedures and records, observed activities, and interviewed personnel. No findings of significance were identified.
The inspection examined activities conducted under your license as they relate to security and compliance with the Commission's rules and regulations and with the conditions of your license.


In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site atEnclosure transmitted herewith contains Sensitive Unclassified Non-Safeguards Information. When separated from enclosure, this transmittal document is decontrolled. http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection. Should you have any questions concerning this inspection, we will be pleased to discuss them with you.
The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.


Sincerely,/RA by D. Funk acting for/ Eric Duncan, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 50-237; 50-249 License Nos. DPR-19; DPR-25 Nonpublic  
No findings of significance were identified.
 
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site atEnclosure transmitted herewith contains Sensitive Unclassified Non-Safeguards Information. When separated from enclosure, this transmittal document is decontrolled. http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection.
 
Should you have any questions concerning this inspection, we will be pleased to discuss them with you.
 
Sincerely,/RA by D. Funk acting for/
Eric Duncan, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 50-237; 50-249 License Nos. DPR-19; DPR-25 Nonpublic  


===Enclosure:===
===Enclosure:===
Line 24: Line 45:


===w/Attachment:===
===w/Attachment:===
Supplemental Information cc w/encl: D. Riffle, NSIR/DSO/DDSO C. Symonds, Dresden Site Security Manager J. Klinger, State Liaison Officer, State of Illinois cc w/o encl: Site Vice President - Dresden Nuclear Power Station Plant Manager - Dresden Nuclear Power Station Regulatory Assurance Manager - Dresden Nuclear Power Station Chief Operating Officer and Senior Vice President Senior Vice President - Midwest Operations Senior Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director - Licensing and Regulatory Affairs Manager Licensing - Clinton, Dresden, and Quad Cities Associate General Counsel Document Control Desk - Licensing Assistant Attorney General Illinois Emergency Management Agency Chairman, Illinois Commerce Commission
Supplemental Information cc w/encl: D. Riffle, NSIR/DSO/DDSO C. Symonds, Dresden Site Security Manager J. Klinger, State Liaison Officer, State of Illinois  
 
cc w/o encl: Site Vice President - Dresden Nuclear Power Station Plant Manager - Dresden Nuclear Power Station Regulatory Assurance Manager - Dresden Nuclear Power Station Chief Operating Officer and Senior Vice President Senior Vice President - Midwest Operations Senior Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director - Licensing and Regulatory Affairs Manager Licensing - Clinton, Dresden, and Quad Cities Associate General Counsel Document Control Desk - Licensing Assistant Attorney General Illinois Emergency Management Agency Chairman, Illinois Commerce Commission
}}
}}

Revision as of 00:50, 30 August 2018

IR 05000237-08-406(DRS); IR 05000249-08-406(DRS); on 04/02/2008, Exelon Nuclear Corporate; 04/15/2008 - 04/16/2008; Dresden Nuclear Power Station, Units 2 and 3; Temporary Instruction 2201/002 Inspection - Cover Letter
ML081270591
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 05/06/2008
From: Duncan E R
Plant Support Branch II
To: Pardee C G
Exelon Generation Co
References
IR-08-406
Download: ML081270591 (4)


Text

May 6, 2008

Mr. Charles Chief Nuclear Officer and Senior Vice President Exelon Generation Company, LLC 4300 Winfield Road Warrenville IL 60555

SUBJECT: DRESDEN NUCLEAR POWER STATION NRC SECURITY TEMPORARY INSTRUCTION 2201/002 INSPECTION REPORT 05000237/2008406(DRS); 05000249/2008406(DRS)

Dear Mr. Pardee:

On April 16, 2008, the U. S. Nuclear Regulatory Commission (NRC) completed a temporary instruction inspection at your Dresden Nuclear Power Station. The inspection covered the transition from a contract to a proprietary security force. The enclosed inspection report documents the inspection results, which were discussed on April 16, 2008, with Mr. D. Wozniak and other members of your staff.

The inspection examined activities conducted under your license as they relate to security and compliance with the Commission's rules and regulations and with the conditions of your license.

The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.

No findings of significance were identified.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site atEnclosure transmitted herewith contains Sensitive Unclassified Non-Safeguards Information. When separated from enclosure, this transmittal document is decontrolled. http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection.

Should you have any questions concerning this inspection, we will be pleased to discuss them with you.

Sincerely,/RA by D. Funk acting for/

Eric Duncan, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 50-237; 50-249 License Nos. DPR-19; DPR-25 Nonpublic

Enclosure:

Inspection Report 05000237/2008406(DRS); 05000249/2008406(DRS)

w/Attachment:

Supplemental Information cc w/encl: D. Riffle, NSIR/DSO/DDSO C. Symonds, Dresden Site Security Manager J. Klinger, State Liaison Officer, State of Illinois

cc w/o encl: Site Vice President - Dresden Nuclear Power Station Plant Manager - Dresden Nuclear Power Station Regulatory Assurance Manager - Dresden Nuclear Power Station Chief Operating Officer and Senior Vice President Senior Vice President - Midwest Operations Senior Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director - Licensing and Regulatory Affairs Manager Licensing - Clinton, Dresden, and Quad Cities Associate General Counsel Document Control Desk - Licensing Assistant Attorney General Illinois Emergency Management Agency Chairman, Illinois Commerce Commission