| ML25268A141 | 26 September 2025 | 99900003 | Public - Final Safety Evaluation for GE-Hitachi Licensing Topical Report NEDC-33926P, Revision 3 BWRX-300 Steel-Plate Composite Containment Vessel and Reactor Building Structural Design |
| IR 05000456/2025010 | 4 September 2025 | Braidwood | Comprehensive Engineering Team Inspection (Ceti) Report 05000456/2025010 and 05000457/2025010 |
| ML25261A269 | 3 September 2025 | | Transcript of the Advisory Committee on Reactor Safeguards 728th Full Committee Meeting, September 3, 2025 Pages 1-157 (Open) |
| IR 05000498/2025011 | 29 August 2025 | South Texas | NRC Comprehensive Engineering Team Inspection Report 050004982025011 and 050004992025011 |
| IR 05000244/2025002 | 24 July 2025 | Ginna | Integrated Inspection Report 05000244/2025002 |
| IR 05000413/2025010 | 27 June 2025 | Catawba | Comprehensive Engineering Team Inspection Report 05000413/2025010 and 05000414/2025010 |
| IR 05000335/2025010 | 14 May 2025 | Saint Lucie 05000398 | Comprehensive Engineering Team Inspection Report 05000335/2025010 and 05000389/2025010 |
| IR 05000333/2025001 | 13 May 2025 | FitzPatrick | Integrated Inspection Report 05000333/2025001 |
| IR 05000327/2025010 | 26 March 2025 | Sequoyah | Design Basis Assurance Inspection (Teams) Inspection Report 05000327/2025010 and 05000328/2025010 |
| IR 05000338/2024004 | 12 February 2025 | North Anna | Integrated Inspection Report 05000338/2024004 and 05000339/2024004 |