SBK-L-06044, Notification of Deviation from MRP-139 Inspection Requirement

From kanterella
Jump to navigation Jump to search
Notification of Deviation from MRP-139 Inspection Requirement
ML060740666
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 03/06/2006
From: St.Pierre G
Florida Power & Light Energy Seabrook
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
BL-04-001, SBK-L-06044
Download: ML060740666 (2)


Text

FPL Energy Seabrook Station IFPL Energy P.O. Box 300 Seabrook, NH 03874 Seabrook Station (603) 773-7000 March 6, 2006 Docket No. 50-443 SBK-L-06044 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001

References:

1. FPL Letter L2004-160, "NRC Bulletin 2004-01, Inspection of Alloy 82/182/600 Materials Used in the Fabrication of Pressurizer Penetrations and Steam Space Piping Connections at Pressurized Water Reactors," July 27, 2004.
2. FPL Letter L2005-1 1, "Request for Additional Information, Inspection of Alloy 82/182/600 Materials Used in the Fabrication of Pressurizer Penetrations and Steam Space Piping Connections at Pressurized Water Reactors," January 18, 2005.

Seabrook Station Notification of Deviation from MRP-139 Inspection Requirement FPL Energy Seabrook, LLC (FPL Energy Seabrook) is providing notification of a deviation from EPRI Materials Reliability Program (MRP) - 139 recommendations. In accordance with the guidance of NEI 03-08, Guideline for the Management of Materials Issues, Addendum D, Materials Guidelines Implementation Protocol, FPL Energy Seabrook has performed the required steps in the NEI Implementation Protocol to deviate from an Industry Materials Issue Program (IP).

In the referenced letters, FPL Energy Seabrook committed that it "will perform a BMV of the pressurizer welds at each RFO until further butt weld inspection guidance is issued by EPRI MRP, the ASME Code, or regulatory action. At that time FPL will follow the published guidance." With the issuance of MRP-139 in July of 2005, the industry has provided additional guidance. FPL Energy Seabrook is postponing the implementation of the recommended guidance issued in MRP-139 to perform UT inspections of the six (6) pressurizer butt welds from December 31, 2007 to the start of the Seabrook refueling outage on or about April 1, 2008.

an FPL Group company

Nuclear Regulatory Commission SBK-L-06044/Page 2 NEI 03-08, Addendum D, dictates how' a utility may deviate from a "mandatory" recommendation from an issues program. In accordance with this guidance, FPL Energy Seabrook prepared the required technical justification that determined the proposed deviation meets the same objective and intent, or level of conservatism exhibited by the original work package and clearly states how long the deviation will be in effect. The justification for deviation was processed as follows:

1) The deviation and basis is documented in the Corrective Action Program
2) A knowledgeable materials expert independent of FPL Energy Seabrook concurs with the deviation.
3) The FPL Chief Nuclear Officer concurs with the deviation.
4) Notification/justification of the deviation has been provided to the EPRI MRP (issuing program), which has the responsibility to inform the other MRP members and the NEI Materials Technical Advisory Group (MTAG).

Should you require further information regarding this matter, please contact Mr. Michael Ossing, Engineering Support Manager, at (603) 773-7512.

Very truly yours, FPL Energy Seabrook, LLC Gene F. St. Pierre Site Vice President cc: S. J. Collins, NRC Region I Administrator G.E. Miller, NRC Project Manager, Project Directorate I-2 G.T. Dentel, NRC Senior Resident Inspector

Text

FPL Energy Seabrook Station IFPL Energy P.O. Box 300 Seabrook, NH 03874 Seabrook Station (603) 773-7000 March 6, 2006 Docket No. 50-443 SBK-L-06044 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001

References:

1. FPL Letter L2004-160, "NRC Bulletin 2004-01, Inspection of Alloy 82/182/600 Materials Used in the Fabrication of Pressurizer Penetrations and Steam Space Piping Connections at Pressurized Water Reactors," July 27, 2004.
2. FPL Letter L2005-1 1, "Request for Additional Information, Inspection of Alloy 82/182/600 Materials Used in the Fabrication of Pressurizer Penetrations and Steam Space Piping Connections at Pressurized Water Reactors," January 18, 2005.

Seabrook Station Notification of Deviation from MRP-139 Inspection Requirement FPL Energy Seabrook, LLC (FPL Energy Seabrook) is providing notification of a deviation from EPRI Materials Reliability Program (MRP) - 139 recommendations. In accordance with the guidance of NEI 03-08, Guideline for the Management of Materials Issues, Addendum D, Materials Guidelines Implementation Protocol, FPL Energy Seabrook has performed the required steps in the NEI Implementation Protocol to deviate from an Industry Materials Issue Program (IP).

In the referenced letters, FPL Energy Seabrook committed that it "will perform a BMV of the pressurizer welds at each RFO until further butt weld inspection guidance is issued by EPRI MRP, the ASME Code, or regulatory action. At that time FPL will follow the published guidance." With the issuance of MRP-139 in July of 2005, the industry has provided additional guidance. FPL Energy Seabrook is postponing the implementation of the recommended guidance issued in MRP-139 to perform UT inspections of the six (6) pressurizer butt welds from December 31, 2007 to the start of the Seabrook refueling outage on or about April 1, 2008.

an FPL Group company

Nuclear Regulatory Commission SBK-L-06044/Page 2 NEI 03-08, Addendum D, dictates how' a utility may deviate from a "mandatory" recommendation from an issues program. In accordance with this guidance, FPL Energy Seabrook prepared the required technical justification that determined the proposed deviation meets the same objective and intent, or level of conservatism exhibited by the original work package and clearly states how long the deviation will be in effect. The justification for deviation was processed as follows:

1) The deviation and basis is documented in the Corrective Action Program
2) A knowledgeable materials expert independent of FPL Energy Seabrook concurs with the deviation.
3) The FPL Chief Nuclear Officer concurs with the deviation.
4) Notification/justification of the deviation has been provided to the EPRI MRP (issuing program), which has the responsibility to inform the other MRP members and the NEI Materials Technical Advisory Group (MTAG).

Should you require further information regarding this matter, please contact Mr. Michael Ossing, Engineering Support Manager, at (603) 773-7512.

Very truly yours, FPL Energy Seabrook, LLC Gene F. St. Pierre Site Vice President cc: S. J. Collins, NRC Region I Administrator G.E. Miller, NRC Project Manager, Project Directorate I-2 G.T. Dentel, NRC Senior Resident Inspector