NL-20-0553, Withdrawal of Proposed Inservice Inspection Alternative FNP-ISI-ALT-05-06. Version 1.0

From kanterella
Jump to navigation Jump to search

Withdrawal of Proposed Inservice Inspection Alternative FNP-ISI-ALT-05-06. Version 1.0
ML20143A171
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 05/22/2020
From: Gayheart C
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
FNP-ISI-ALT-05-06, NL-20-0553
Download: ML20143A171 (1)


Text

~ Southern Nuclear May 22, 2020 Cheryl A. Gayheart Regulatory Affairs Director 3535 Colonnade Parkway Birmingham, AL 35243 205 992 5316 cagayhea@southemco.com Docket No.:

50-364 NL-20-0553 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Joseph M. Farley Nuclear Plant, Unit 2 Withdrawal of Proposed lnservice Inspection Alternative FNP-ISI-AL T-05-06. Version 1.0 Ladies and Gentlemen:

By letter dated February 24, 2020, Southern Nuclear Operating Company (SNC) submitted proposed Alternative FNP-ISI-AL T-05-06, Version 1.0 (ADAMS accession number ML20055F672) to allow ASME Code Case N-729-4, Inspection Item B4.40 for Reactor Vessel Closure Head (RVCH) nozzle and partial penetration welds of Primary Water Stress Corrosion Cracking (PWSCC)-resistant materials to be re-examined once every 20 years for Farley Nuclear Plant (FNP) Unit 2 in lieu of the current approved interval of 15 years as documented in the associated NRC safety evaluation (ADAMS accession number ML15104A192). Code Case N-729-6 was recently approved by reference in 10 CFR 50.55a for unconditional use and also allows Inspection Item B4.40 for Reactor Vessel Closure Head (RVCH) nozzle and partial penetration welds of Primary Water Stress Corrosion Cracking (PWSCC)-resistant materials to be re-examined once every 20 years. This negates the need for SNC's proposed Alternative. Based on this, SNC hereby withdraws Alternative FNP-ISI-AL T-05-06, Version 1.0.

This letter contains no NRC commitments. If you have any questions, please contact Jamie Coleman at 205.992.6611.

Cheryl A. Gay eart Regulatory Affairs Director CAG/dsp/scm cc:

Regional Administrator, Region II NRR Project Manager-Farley Nuclear Plant Senior Resident Inspector-Farley Nuclear Plant RTYPE: CFA04.054