ND-22-0571, ITAAC Closure Notification on Completion of 3.2.00.02 (Index Number 745)
| ML22203A148 | |
| Person / Time | |
|---|---|
| Site: | Vogtle |
| Issue date: | 07/22/2022 |
| From: | Coleman J Southern Nuclear Operating Co |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| ND-22-0571 | |
| Download: ML22203A148 (6) | |
Text
A Southern Nuclear JUL 2 2 2022 Docket No.:
52-026 U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Jamie M. Coleman Regulatory Affairs Director Vogtle 3 & 4 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 4 7825 River Road Waynesboro, GA 30830 706-848-6926 tel ND-22-0571 10 CFR 52.99(c)(1)
ITAAC Closure Notification on Completion of 3.2.00.02 [Index Number 745)
Ladies and Gentlemen:
In accordance with 1 O CFR 52.99(c)(1 ), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) of the completion of Vogtle Electric Generating Plant (VEGP) Unit 4 Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 3.2.00.02 [Index Number 745]. This ITAAC confirms the main control room contains operator and supervisor workstations and safety-related displays and controls. The closure process for this ITAAC is based on the guidance described in Nuclear Energy Institute (NEI) 08-01, "Industry Guideline for the ITAAC Closure Process under 1 O CFR Part 52," which was endorsed by the NRC in Regulatory Guide 1.215.
This letter contains no new NRG regulatory commitments. Southern Nuclear Operating Company (SNC) requests NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 1 O CFR 52.99.
If there are any questions, please contact Kelli Roberts at 706-848-6991.
Respectfully submitted, Jamie M. Coleman Regulatory Affairs Director Vogtle 3 & 4
Enclosure:
JMC/GES/sfr Vogtle Electric Generating Plant (VEGP) Unit 4 Completion of 3.2.00.02 [Index Number 745)
U.S. Nuclear Regulatory Commission ND-22-0571 Page 2 of 3 To:
Southern Nuclear Operating Company/ Georgia Power Company Mr. Peter P. Sena Ill Mr. D. L. McKinney Mr. H. Nieh Mr. G. Chick Mr. S. Stimac Mr. P. Martino Mr. D. Pitts Mr. J.B. Williams Mr. A. S. Parton Ms. K. A. Roberts Ms. J.M. Coleman Mr. C. T. Defnall Mr. C. E. Morrow Mr. K. J. Drudy Mr. J. M. Fisher Mr. R. L. Beilke Mr. S. Leighty Ms. A. C. Chamberlain Mr. J.C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 Nuclear Regulatory Commission Mr. M. King Mr. G. Bowman Ms. A. Veil Mr. C. P. Patel Mr. G. J. Khouri Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. J. Gaslevic Mr. 0. Lopez-Santiago Mr. G. Armstrong Mr. M. Webb Mr. T. Fredette Mr. C. Santos Mr. B. Davis Mr. J. Vasquez Mr. J. Eargle Ms. K. Mccurry Mr. J. Parent Mr. B. Griman Mr. V. Hall
U.S. Nuclear Regulatory Commission ND-22-0571 Page 3 of 3 Oglethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Dalton Utilities Mr. T. Bundros Westinghouse Electric Company, LLC Dr. L. Oriani Mr. D. C. Durham Mr. M. M. Corletti Mr. Z. S. Harper Ms. S.L. Zwack Other Mr. S. W. Kline, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.
Dr. W. R. Jacobs, Jr., Ph.D., GOS Associates, Inc.
Mr. S. Roetger, Georgia Public Service Commission Mr. R. L. Trokey, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. S. Blanton, Balch Bingham
U.S. Nuclear Regulatory Commission ND-22-0571 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-22-0571 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 4 Completion of 3.2.00.02 [Index Number 745]
U.S. Nuclear Regulatory Commission ND-22-0571 Enclosure Page 2 of 3 ITAAC Statement Design Commitment
- 2. The MCR includes reactor operator workstations, supervisor workstation(s), safety-related displays, and safety-related controls.
Inspections/Tests/ Analyses An inspection of the MCR workstations and control panels will be performed.
Acceptance Criteria The MCR includes reactor operator workstations, supervisor workstation(s), safety-related displays, and safety-related controls.
ITAAC Determination Basis An inspection of the Main Control Room (MCR) workstations and control panels was performed to verify that the MCR includes reactor operator workstations, supervisor workstation(s), safety-related displays, and safety-related controls.
The visual inspection utilized approved construction drawings and control room panel design specifications to perform inspections of the Unit 3 MCR. The inspections compared the as-built workstations, displays, and controls with design documents (References 1 through 12) to confirm that the MCR includes reactor operator workstations, supervisor workstation(s), safety-related displays, and safety-related controls.
The inspection results are documented in SV4-OCS-ITR-800745 (Reference 13), which serves as the Principal Closure Document and confirms that the MCR includes reactor operator workstations, supervisor workstation(s), safety-related displays, and safety-related controls.
Principal Closure Document SV4-OCS-ITR-800745 is available for NRC inspection as part of the Unit 4 ITAAC 3.2.00.02 Completion Package (Reference 14).
ITAAC Finding Review In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company (SNC) performed a review of findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC. The ITAAC completion review is documented in the ITAAC Completion Package for ITAAC 3.2.00.02 (Reference 14) and available for NRG review.
IT AAC Completion Statement Based on the above information, SNC hereby notifies the NRG that ITAAC 3.2.00.02 was performed for VEGP Unit 4 and that the prescribed acceptance criteria are met.
U.S. Nuclear Regulatory Commission ND-22-0571 Enclosure Page 3 of 3 Systems, structures, and components verified as part of this ITAAC are being maintained in their as-designed, ITAAC compliant condition in accordance with approved plant programs and procedures.
References (available for NRC inspection)
- 1. SV4-JC01-Z0-001, Rev. 2, "AP1000 Design Specification for Control Room Consoles and Panels"
- 2. SV4-JC01-V1-001, Rev. 3, "AP1000 Main Control Area Layout Top View"
- 3. SV4-1242-P3-001, Rev. 1, "Auxiliary Building Equipment Location Plan Index EL 117' - 6" Area 2 Main Control Room"
- 4. SV4-1242-P3X-001 Rev. 1, "Auxiliary Building Equipment Location Index EL 117' - 6" Area 2 Main Control Room"
- 5. SV4-JC01-V1-002, Rev. 2, "AP1000 Main Control Room Layout Side View"
- 6. SV4-JC01-V1-250 Rev. 1, "AP1000 Reactor Operator Console A Outline"
- 7. SV4-JC01-V8-001, Rev. 3, "AP1000 Main Control Area OCS Installation Consoles and Panels"
- 8. SV4-JC01-V8-002, Rev. 2, "AP1000 Main Control Area OCS Installation Consoles and Panels"
- 9. SV4-JC01-V8-005, Rev. 1, "AP1000 Main Control Area OCS Installation Consoles and Panels"
- 10. SV4-JC01-V8-006, Rev. 0. "AP1000 Main Control Area OCS Installation Consoles and Panels"
- 11. SV4-JC01-V8-007, Rev. 1. "AP1000 Main Control Area OCS Installation Consoles and Panels"
- 12. SV4-G1-V8-001, Rev. 0, "AP1000 Electrical Installation Specification"
- 13. SV4-OCS-ITR-800745, Rev. 0, "Unit 4: Inspection of MCR Workstations and Control Panels"
- 14. 3.2.00.02-U4-CP-Rev 0, ITAAC Completion Package