ML25128A052
| ML25128A052 | |
| Person / Time | |
|---|---|
| Site: | Crane |
| Issue date: | 05/06/2025 |
| From: | Ballard B NRC/NRR/DORL/LPL3 |
| To: | Moore D, Casey Smith Constellation Energy Generation |
| References | |
| EPID L-2025-LLR-0040 | |
| Download: ML25128A052 (1) | |
Text
1 Brent Ballard From:
Brent Ballard Sent:
Tuesday, May 6, 2025 3:55 PM To:
Moore, Dennis M: (Constellation Nuclear); Smith, Craig W: (Constellation Nuclear)
Cc:
Subject:
Acceptance of Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code,Section XI (EPID L-2025-LLR-0040)
Good afternoon, By letter dated March 31, 2025 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML25090A036), Constellation Energy Generation, LLC (the licensee), submitted a request to use specific provisions of a later edition of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel (BPV) Code,Section XI, for Three Mile Island Nuclear Station, Unit 1. Specifically, the licensee proposed to use the 2013 Edition of the ASME BPV Section XI code for performing Non-Destructive Examination and Repair and Replacement activities.
Pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Section 50.55a(g)(4)(iv), Applicable ISI Code: Use of subsequent Code editions and addenda, inservice examination of components and system pressure tests may meet the requirements set forth in subsequent editions and addenda that are incorporated by reference in 10 CFR 50.55a(a),
subject to the conditions listed in 10 CFR 50.55a(b), and subject to Commission approval. Portions of editions or addenda may be used, provided that all related requirements of the respective editions or addenda are met.
The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed request in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staffs detailed technical review by separate correspondence.
Based on the information provided in your submittal, the NRC staff has estimated that this request will take approximately 200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> to complete. The NRC staff expects to complete this review by December 15, 2025. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during routine interactions with the assigned project manager.
These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, and unanticipated addition of scope to the review. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.
If you have any questions, please contact me at 301-415-0680 or by e-mail.
2 Thank you, Brent Brent Ballard Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission 301-415-0680