Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2024006)
ML25064A440
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 03/11/2025
From: Sanchez E
NRC/RGN-III/DORS/RPB2
To: Peter Dietrich
DTE Electric Company
Shared Package
ML24353A192 List:
References
IR 2024006
Download: ML25064A440 (1)


Text

March 11, 2025

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR FERMI POWER PLANT, UNIT 2 (REPORT 05000341/2024006)

Dear Peter Dietrich:

The NRC has completed its end-of-cycle performance assessment of Fermi Power Plant, Unit 2, reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2024, through December 31, 2024. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety. The baseline inspection program was completed at your facility as defined in Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program - Operations Phase.

The NRC determined the performance at Fermi Power Plant, Unit 2, during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green).

Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through December 31, 2026.

The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This letter and its enclosure will be made available for public inspection and copying at ADAMS Public Documents l NRC.gov and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Please contact me at 630-829-9520 with any questions you have regarding this letter.

Sincerely, Elba Sanchez Santiago, Chief Reactor Projects Branch 2 Division of Operating Reactor Safety Docket No. 05000341 License No. NPF-43 Enclosure:

Inspection Plan cc: Distribution via LISTSERV Signed by Sanchez Santiago, Elba on 03/05/25

ML25064A440

SUNSI Review

Non-Sensitive

Sensitive

Publicly Available

Non-Publicly Available OFFICE RIII NAME ESanchezSantiago:gmp DATE 03/05/2025

Site Inspection Activity Plan Fermi 01/01/2025 - 12/31/2026 Unit Start End Activity CAC Title Staff Count Radiation Protection Baseline Inspection

2 5/5/2025 5/9/2025 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation

5/5/2025 5/9/2025 IP 71124.04 000728 Occupational Dose Assessment

5/5/2025 5/9/2025 IP 71151 000746 Performance Indicator Verification Force-On-Force Planning and Exercise Weeks - FER

2 7/14/2025 7/18/2025 IP 71130.03 000735 Contingency Response - Force-On-Force Testing

8/11/2025 8/15/2025 IP 71130.03 000735 Contingency Response - Force-On-Force Testing Biennial Problem Identification and Resolution

2 7/21/2025 8/8/2025 IP 71152B 000747 Problem Identification and Resolution Security Baseline Inspection

2 8/4/2025 8/8/2025 IP 71130.02 000734 Access Control

8/4/2025 8/29/2025 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance

8/4/2025 8/8/2025 IP 71151 001338 Performance Indicator Verification

8/25/2025 8/29/2025 IP 71130.07 000739 Security Training

8/25/2025 8/29/2025 IP 71130.09 001656 Security Plan Changes Emergency Preparedness Program Inspection / Performance Indicator Review

2 8/25/2025 8/29/2025 IP 71114.02 000717 Alert and Notification System Testing

8/25/2025 8/29/2025 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System

8/25/2025 8/29/2025 IP 71114.05 000720 Maintenance of Emergency Preparedness

8/25/2025 8/29/2025 IP 71151 001397 Performance Indicator Verification Radiation Protection Baseline Inspection

2 9/8/2025 9/12/2025 IP 71124.05 000729 Radiation Monitoring Instrumentation

9/8/2025 9/12/2025 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation Fermi 2025 Biennial Licensed Operator Requalification Inspection

2 9/14/2025 9/20/2025 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance Cyber Security Inspection

2 10/27/2025 10/31/2025 IP 71130.10 000741 Cybersecurity Eplan and EAL Changes Review

2 11/1/2025 12/31/2025 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes Fermi February 2026 Initial License Examination

2 1/11/2026 1/17/2026 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)

2/8/2026 2/21/2026 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)

Prepared on 2/28/2025 11:01:40 AM 1 of 2

Site Inspection Activity Plan Security Baseline Inspection

2 2/9/2026 2/13/2026 IP 71130.08 000740 Fitness-For-Duty Program Inservice Inspection

2 3/23/2026 4/3/2026 IP 71111.08G 000701 Inservice Inspection Activities (BWR)

Radiation Protection Baseline Inspection

2 4/6/2026 4/10/2026 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls

4/6/2026 4/10/2026 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation

4/6/2026 4/10/2026 IP 71124.04 000728 Occupational Dose Assessment Security Baseline Inspection

2 4/20/2026 4/24/2026 IP 71130.05 000737 Protective Strategy Evaluation Functional Engineering Inspection - Age Related Degradation of Structures, Systems and Components

2 5/18/2026 6/5/2026 IP 71111.21N.04 001832 Age-Related Degradation Security Baseline Inspection

2 6/22/2026 6/26/2026 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance Comprehensive Engineering Team Inspection

2 8/17/2026 9/4/2026 IP 71111.21M 000713 Comprehensive Engineering Team Inspection Emergency Preparedness Exercise Inspection (HAB)/ Performance Indicator Verification

2 7/27/2026 9/4/2026 IP 71114.08 000723 Exercise Evaluation - Scenario Review

8/31/2026 9/4/2026 IP 71114.07 000722 Exercise Evaluation - Hostile Action (HA) Event

8/31/2026 9/4/2026 IP 71151 001397 Performance Indicator Verification Security Baseline Inspection

2 9/14/2026 9/18/2026 IP 71130.02 000734 Access Control

9/14/2026 9/18/2026 IP 71130.09 001656 Security Plan Changes

9/14/2026 9/18/2026 IP 71151 001338 Performance Indicator Verification EAL & EPlan Changes Review

2 11/1/2026 12/31/2026 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes Prepared on 2/28/2025 11:01:40 AM 2 of 2