Letter Sequence Other |
|---|
EPID:L-2023-CRS-0008, Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point (Open) |
Results
Other: ML24137A014, ML24137A015, ML24170A881, ML24330A080, ML25052A070, ML25097A168, ML25097A169, ML25099A042, ML25183A399, ML25199A095, ML25199A103
|
MONTHYEARML23306A0992023-11-0202 November 2023 And Indian Point Energy Center, Notification of Changes in Schedule in Accordance with 10 CFR 50.82(a)(7) Project stage: Request L-23-012, Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point2023-11-13013 November 2023 Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point Project stage: Request ML23339A1922023-12-0505 December 2023 Petition to Intervene and Request for Adjudicatory Hearing by Beyond Nuclear, Don’T Waste Michigan, and Michigan Safe Energy Future Project stage: Request PMNS20240422, Meeting with the U.S. Nuclear Regulatory Commission Petition Review Board and Beyond Nuclear, Michigan Safe Energy Future, and Dont Waste Michigan Regarding a 2.206 Petition Submitted on December 5, 20232024-03-25025 March 2024 Meeting with the U.S. Nuclear Regulatory Commission Petition Review Board and Beyond Nuclear, Michigan Safe Energy Future, and Dont Waste Michigan Regarding a 2.206 Petition Submitted on December 5, 2023 Project stage: Meeting L-24-007, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI)2024-03-29029 March 2024 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI) Project stage: Request ML24170A8812024-05-15015 May 2024 NRR E-mail Capture - Post Acceptance/Abeyance Process for the 10 CFR 2.206 Petition on Palisades Misuse of Decommissioning Trust Fund Project stage: Other ML24137A0142024-07-0202 July 2024 OEDO-24-00011 - 2.206 Petition for Misuse of Palisades Decommissioning Trust Fund (EPID L-2023-CRS-0008) - Letter Project stage: Other ML24137A0152024-07-0202 July 2024 OEDO-24-00011 - 2.206 Petition for Misuse of Palisades Decommissioning Trust Fund (EPID L-2023-CRS-0008) - FRN Project stage: Other ML24330A0802024-11-25025 November 2024 Decommissioning Trust Fund 2.206 Petition - Notification of Petition Manager Change Project stage: Other ML25052A0702025-02-20020 February 2025 2.206 Petition Regarding Decommissioning Trust Fund Misuse - Petition Review Board Resuming Review Project stage: Other ML25099A0422025-04-0808 April 2025 Routine Update - Email to the Petitioner - Palisades Dtf Misuse 2.206 Petition (EPID L-2023-CRS-0008 Project stage: Other ML25097A1682025-06-18018 June 2025 Petitioner Request for Comment - Proposed Directors Decision Regarding Decommissioning Trust Fund Misuse for Palisades Nuclear Plant Project stage: Other ML25097A1692025-06-18018 June 2025 Licensee Request for Comment - Proposed Directors Decision Regarding Decommissioning Trust Fund Misuse for Palisades Nuclear Plant Project stage: Other ML25097A1672025-06-18018 June 2025 Draft Proposed Directors Decision - Palisades Dtf - OEDO-24-00011 - rev0 Project stage: Draft Other ML25183A3992025-07-0202 July 2025 Comments on Proposed Directors Decision Regarding Decommissioning Trust Fund Misuse at Palisades Nuclear Plant Project stage: Other ML25199A0952025-08-14014 August 2025 OEDO-24-00011 - Directors Decision Regarding Decommissioning Trust Fund Misuse for Palisades Nuclear Plant (EPID L-2023-CRS-0008) - Letter to Petitioners Project stage: Other ML25199A1032025-08-19019 August 2025 OEDO-24-00011 - Directors Decision Regarding Decommissioning Trust Fund Misuse for Palisades Nuclear Plant (EPID L-2023-CRS-0008) - FRN Project stage: Other 2024-05-15
[Table View] |
Text
From:
Zach Turner To:
wtaylorlaw@aol.com; tjlodge50@yahoo.com
Subject:
Palisades 2.206 Petition Regarding Decommissioning Trust Fund Misuse - Petition Review Board Resuming Review Date:
Thursday, February 20, 2025 6:12:38 AM
Dear Wallace Taylor and Terry Lodge:
As described in the July 2, 2024, Acknowledgement Letter (ML24137A014), your petitions concern regarding the Holtec Decommissioning International, LLC (Holtec), 2023 expenditure report (ML24089A117) for Palisades was accepted for further review and has been held in abeyance pending the U.S. Nuclear Regulatory Commission (NRC) completing its review of Holtecs 2023 expenditure report.
This email is to inform you that the NRC staff has completed its review of the 2023 expenditure report (ML24045A147 and ML25041A225) and that the Petition Review Board (PRB) will resume its assessment of the 2.206 petition. Furthermore, the PRB will provide the proposed directors decision to the petitioner for comment in accordance with NRC Management Directive 8.11, Review Process for 10 CFR [Code of Federal Regulations] 2.206 Petitions (ML18296A043),Section IV.B, Schedule, and V.E, Issuing the Proposed Directors Decision for Comment.
If you have any questions regarding this e-mail, please feel free to contact me at Zachary.Turner@nrc.gov.
Very Respectfully,
Zach Turner, Project Manager Nuclear Regulatory Commission Division of Operating Reactor Licensing NRR/DORL/LPL2-1 (301) 415-2258 Office: OWFN-07C12 Mail Stop: O-08 B01A