ML25045A210

From kanterella
Jump to navigation Jump to search
NRC Inspection Report 05000361/2025001 05000362/2025001 and Notice of Violation
ML25045A210
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 02/26/2025
From: Jeffrey Josey
NRC/RGN-IV/DRSS/DIOR
To: Bailly F
Southern California Edison Co
Evans R
References
IR 2025001
Download: ML25045A210 (1)


See also: IR 05000361/2025001

Text

February 26, 2025

Frederic Bailly, Vice President

and Chief Nuclear Officer

Southern California Edison Company

San Onofre Nuclear Generating Station

P.O. Box 128

San Clemente, CA 92674-0128

SUBJECT:

SAN ONOFRE NUCLEAR GENERATING STATION - NRC INSPECTION

REPORT 050-00361/2025-001; 050-00362/2025-001 AND NOTICE OF

VIOLATION

Dear Frederic Bailly:

This letter refers to the U.S. Nuclear Regulatory Commission (NRC) inspection conducted

onsite from January 27-30, 2025, for San Onofre Nuclear Generating Station, Units 2 and 3.

The inspectors discussed the preliminary inspection results with you and members of your staff

at the end of the onsite inspection on January 30, 2025. The final inspection results were

presented to you via Microsoft Teams meeting on February 11, 2025. The inspection results are

documented in the enclosures to this letter.

This inspection examined activities conducted under your license as they relate to public health

and safety, the common defense and security, and to confirm compliance with the

Commissions rules and regulations and with the conditions of your licenses. Within these

areas, the inspection consisted of selected examination of procedures and representative

records, observation of activities, independent measurement of radiation levels, and interviews

with personnel. Specifically, the inspectors reviewed decommissioning performance; remedial

and final surveys; safety reviews, design changes, and modifications; and solid radioactive

waste management and transportation of radioactive materials.

The enclosed report discusses a Severity Level IV violation related to the licensees failure to

implement the fire protection program as required by 10 CFR 50.48(f)(1). This violation was

evaluated in accordance with the NRC Enforcement Policy, which can be found on the NRC

website at http://www.nrc.gov/aboutnrc/regulatory/enforcement/enforce-pol.html. The violation is

cited in Enclosure 1, Notice of Violation (Notice), and the circumstances surrounding it are

described in detail in the subject inspection report (Enclosure 2). The NRC determined that this

violation did not meet the criteria to be treated as a non-cited violation (NCV) because the issue

was not entered into a credited corrective action program and the corrective actions taken were

not adequate, consistent with Section 2.3.2 of the NRC Enforcement Policy.

F. Bailly

2

You are required to respond to this letter and should follow the instructions specified in the

enclosed Notice when preparing your response. If you have additional information that you

believe the NRC should consider, you may provide it in your response to the Notice. The NRC

review of your response to the Notice will also determine whether further enforcement action is

necessary to ensure compliance with regulatory requirements.

In accordance with 10 CFR 2.390 of the NRCs Agency Rules of Practice and Procedure, a

copy of this letter, its enclosures, and your response will be made available electronically for

public inspection in the NRC Public Document Room or from the NRCs Agencywide

Documents Access and Management System (ADAMS). ADAMS is accessible from the NRCs

Website at http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response

should not include any personal privacy or proprietary information so that it can be made

available to the public without redaction.

If you have any questions regarding this inspection report, please contact Eric McManus at

817-200-1127 or the undersigned at 817-200-1249.

Sincerely,

Jeffrey E. Josey, Chief

Decommissioning, ISFSI, Operating Reactor Branch

Division of Radiological Safety and Security

Docket Nos. 50-361; 50-362

License Nos. NPF-10; NPF-15

Enclosures:

1. Notice of Violation

2. Inspection Report 050-00361/2025-001; 050-00362/2025-001

w/Attachment: Supplemental Inspection Information

Distribution via ListServ

Signed by Josey, Jeffrey

on 02/26/25

F. Bailly

3

SAN ONOFRE NUCLEAR GENERATING STATION - NRC INSPECTION REPORT 050-

00361/2025-001; 050-00362/2025-001 AND NOTICE OF VIOLATION - DATED

FEBRUARY 26, 2025

DISTRIBUTION:

JMonninger, ORA

JLara, ORA

JGroom, DRSS

NOKeefe, DRSS

RAlexander, ORA

DCylkowski, ORA

VDricks, ORA

TSmith, ORA

AAlen-Arias, OEDO/ETA

SAnderson, NMSS/DUWP/RDB

ASnyder, NMSS/DUWP/RDB

LWilkins, OCA

AMoreno, RIV/OCA

R4-DRSS-DIOR-DECOM

DOCUMENT NAME: SAN ONOFRE NUCLEAR GENERATING STATION - NRC INSPECTION REPORT 050-

00361/2025-001; 050-00362/2025-001 AND NOTICE OF VIOLATION

ADAMS Accession Number: ML25045A210

SUNSI Review By:

RJE

ADAMS:

Yes

No

Sensitive

Non-Sensitive

Non-Publicly Available

Publicly Available

Keyword NRC-002

OFFICE

SHP:DIOR:DRSS

HP:DIOR:DRSS

SHP:DIOR:DRSS

C:DIOR:DRSS

NAME

REvans

EMcManus

SAnderson

JJosey

SIGNATURE

/RA/

/RA/

/RA/

/RA/

DATE

02/14/25

02/14/25

02/24/25

02/26/25

OFFICIAL RECORD COPY

Enclosure 1

NOTICE OF VIOLATION

Southern California Edison Company

Docket Nos. 50-361; 50-362

San Onofre Nuclear Generating Station

License Nos. NPF-10; NPF-15

San Clemente, CA

During an NRC inspection conducted on January 27-30, 2025, a violation, with three examples,

of NRC requirements was identified. In accordance with the NRC Enforcement Policy, the

violation is listed below:

Title 10 CFR 50.48(f) states in part that the licensee shall maintain a fire protection

program to address the potential for fires that could cause the release or spread of

radioactive materials.

Licensee fire protection implementing procedure SDS-FP1-PGM-0015, Control of

Ignition Sources, revision 13, states in part:

1.

Section 4.1.7: Licensee must verify all Class A combustibles or Dry Active Waste

bags within 35 feet of hot work have been removed or are shielded with approved

welding curtains, welding blankets or welding pads.

2.

Section 4.1.9: Licensee must relocate combustibles a minimum of 5 feet from the

side opposite work performed on metal walls.

Contrary to the above, the licensee failed to maintain the require standoff distance

between ignition sources and combustible materials, as evidenced by the following three

examples:

1.

On December 4, 2024, the licensee failed to maintain the 5 feet distance when they

were welding a metal shield to a shipping container containing dry active waste

which resulted in the burning of the waste material in the container.

2.

On January 20, 2025, the licensee failed to maintain 5 feet distance when they were

welding a shield to a shipping container containing dry active waste which again

resulted in burning of the waste material in the container.

3.

On February 6, 2025, the licensee failed to verify all combustible material within 35

feet of hot work was removed prior to the start of hot work which resulted in sparks

from cutting contacting flammable material.

This is a Severity Level IV violation (Section 6.3 d.3).

Pursuant to the provisions of 10 CFR 2.201, Southern California Edison Company is hereby

required to submit a written statement or explanation to the U.S. Nuclear Regulatory

Commission, ATTN: Document Control Desk, Washington, DC 20555-0001, with a copy to the

Regional Administrator, Region IV, within 30 days of the date of the letter transmitting this

Notice of Violation. This reply should be clearly marked as a "Reply to a Notice of Violation, and

should include for each violation: (1) The reason for the violation, or, if contested, the basis for

disputing the violation or severity level; (2) The corrective steps that have been taken and the

results achieved; (3) The corrective steps that will be taken; and (4) The date when full

compliance will be achieved. Your response may reference or include previous docketed

2

correspondence, if the correspondence adequately addresses the required response. If an

adequate reply is not received within the time specified in this Notice, an order or a Demand for

Information may be issued requiring information as to why the license should not be modified,

suspended, or revoked, or why such other action as may be proper should not be taken. Where

good cause is shown, consideration will be given to extending the response time.

If you contest this enforcement action, you should also provide a copy of your response, with

the basis for your denial, to the Director, Office of Enforcement, U.S. Nuclear Regulatory

Commission, Washington, DC 20555-0001.

Your response will be made available electronically for public inspection in the NRC Public

Document Room or in the NRCs Agencywide Documents Access and Management System

(ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. To

the extent possible, your response should not include any personal privacy, proprietary, or

safeguards information so that it can be made available to the public without redaction. If

personal privacy or proprietary information is necessary to provide an acceptable response,

then please provide a bracketed copy of your response that identifies the information that

should be protected and a redacted copy of your response that deletes such information. If you

request withholding of such material, you must specifically identify the portions of your response

that you seek to have withheld and provide in detail the bases for your claim of withholding (e.g.,

explain why the disclosure of information will create an unwarranted invasion of personal

privacy or provide the information required by 10 CFR 2.390(b) to support a request for

withholding confidential commercial or financial information). If safeguards information is

necessary to provide an acceptable response, please provide the level of protection described

in 10 CFR 73.21.

Dated this 26TH day of February 2025

Enclosure 2

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket Nos.

050-00361; 050-00362

License Nos.

NPF-10; NPF-15

Report Nos.

050-00361/2025-001; 050-00362/2025-001

Licensee:

Southern California Edison Company

Facility:

San Onofre Nuclear Generating Station, Units 2 and 3

Location:

5000 South Pacific Coast Highway

San Clemente, California

Inspection Dates:

Onsite January 27-30, 2025

Exit Date:

February 11, 2025

Inspectors:

Robert J. Evans, PE, CHP, PhD, Senior Health Physicist

Decommissioning, ISFSI, and Operating Reactor Branch

Division of Radiological Safety and Security

Eric S. McManus, Health Physicist

Decommissioning, ISFSI, and Operating Reactor Branch

Division of Radiological Safety and Security

Accompanied by:

Tiffany N. Rushing, Health Physicist

Decommissioning, ISFSI, and Operating Reactor Branch

Division of Radiological Safety and Security

Approved By:

Jeffrey E. Josey, Chief

Decommissioning, ISFSI, and Operating Reactor Branch

Division of Radiological Safety and Security

Attachment:

Supplemental Inspection Information

2

EXECUTIVE SUMMARY

San Onofre Nuclear Generating Station

NRC Inspection Report 050-00361/2025-001; 050-00362/2025-001

This U.S. Nuclear Regulatory Commission (NRC) inspection was a routine, announced

inspection of decommissioning activities being conducted at the San Onofre Nuclear Generating

Station. In summary, the licensee and its decommissioning general contractor were found to be

conducting activities in accordance with site procedures, license requirements, and applicable

NRC regulations, with one exception as described below.

Decommissioning Performance and Status Reviews at Permanently Shutdown Reactors

The licensee was effectively implementing decommissioning activities at Units 2 and 3 in

accordance with approved procedures and commitments provided in the PSDAR. The

licensee maintained good radiological control over these work activities. (Section 1.2)

Inspection of Remedial and Final Surveys at Permanently Shutdown Reactors

The licensee implemented final status survey isolation and control measures in accordance

with approved procedures. The licensee continued to identify, document, and resolve

problems in the final status survey program area. (Section 2.2)

Safety Reviews, Design Changes, and Modifications at Permanently Shutdown Reactors

The licensee developed and implemented a written program for safety reviews, design

changes, and modifications. The program was being implemented by qualified individuals.

Based on a limited NRC review of recently issued safety reviews, the licensee was noted to

be effectively implementing the program. (Section 3.2)

Solid Radioactive Waste Management and Transportation of Radioactive Materials

The inspectors reviewed selected radioactive waste management and transportation

activities and identified one violation of regulatory requirements. The violation involved the

licensees failure to maintain a fire protection program to address the potential for fires that

could cause the release or spread of radioactive materials. (Section 4.2)

3

Report Details

Summary of Plant Status

Southern California Edison Company (SCE), the licensee, formally notified the NRC in June

2013 that it had permanently ceased power operations at San Onofre Nuclear Generating

Station (SONGS), Units 2 and 3 (Agencywide Documents Access and Management System

[ADAMS] Accession No. ML131640201). The NRC subsequently issued the permanently

defueled technical specifications in July 2015 (ML15139A390), along with revised facility

operating licenses to reflect the permanent cessation of operations at Units 2 and 3.

As required by Title 10 to the Code of Federal Regulations (10 CFR) 50.82(a)(4), the licensee

submitted its Post-Shutdown Decommissioning Activities Report (PSDAR) to the NRC on

September 23, 2014 (ML14269A033). The PSDAR outlined the licensees planned

decommissioning activities. The current version of the PSDAR is dated May 7, 2020

(ML20136A339). As discussed in the revised PSDAR, the licensee chose the decommissioning

alternative DECON. DECON is the removal or decontamination of equipment, structures, or

portions of the facility and site that contain radioactive contaminants to levels that permit

termination of the license.

On December 20, 2016, the licensee announced the selection of AECOM and Energy Solutions

as the decommissioning general contractor. The joint venture between the two companies was

named SONGS Decommissioning Solutions (SDS). The SDS organization manages most of the

decommissioning activities as described in the PSDAR.

During the inspection, the licensee was preparing the rigging equipment for the Unit 3 reactor

vessel lift and subsequent segmentation of the vessel shell. In Unit 2, the licensee removed the

final reactor coolant pump and prepared it for shipment to a disposal site. The material handling

facility was operational for open air demolition of the site radioactive structures.

1

Decommissioning Performance and Status Review at Permanently Shutdown

Reactors (Inspection Procedure [IP] 71801)

1.1

Inspection Scope

The inspectors observed site activities, reviewed documents, and interviewed site

personnel in order to: (1) evaluate the status of decommissioning and verify whether the

licensee was conducting decommissioning and maintenance activities in accordance with

regulatory and license requirements; (2) evaluate the licensee awareness of work activities

to assess their control and conduct of decommissioning; and (3) evaluate the licensees

decommissioning staffing, personnel qualifications, and training requirements, including

that of the contracted workforce, to ensure that license requirements were met, as

applicable to the current decommissioning status.

1.2

Observations and Findings

a.

Status of Decommissioning

At the time of the onsite inspection, the licensee and its decommissioning general

contractor SDS were conducting major decommissioning activities in accordance with

the commitments provided in Section II.B.1 of the PSDAR. The inspectors discussed the

4

current decommissioning schedule with management staff, observed daily planning

meetings, and observed open air demolition work in progress. The status of

decommissioning was noted to be commensurate with the challenges encountered.

During the onsite inspection, the Units 2 and 3 radwaste buildings were being

demolished. The building demolition work was approximately 90-percent complete.

The inspectors attended meetings that included discussion of decommissioning activities

as well as the current plant status for each day. The topics discussed included an As

Low As Is Reasonably Achievable (ALARA) briefing, safety briefing, current work

projects, and near-term work projects. The meeting provided participants with current

information of the work in progress including radiological and industrial safety updates as

needed.

The inspectors performed tours of the Unit 2 and Unit 3 containment buildings, facilities

adjacent to the containment buildings, and the former location of the multipurpose

handling facility in the south yard area. Plant staff appeared to be knowledgeable of site

conditions and based on observations, the inspectors determined that the licensee was

adequately maintaining the material condition of the facilities, as well as the structures,

systems, and components that are necessary for safe decommissioning. The inspectors

identified good housekeeping practices and appropriate radiological postings and

labeling. The inspectors did not identify any radiological areas that were not adequately

identified and posted by the licensee.

The inspectors conducted site tours, in part, to observe open air demolition activities.

The work was being conducted in accordance with the instructions provided in SDS-

RP1-TSD-24-01, Open-Air Demolition Plan for San Onofre, revision 2, The licensee

was demolishing the buildings, sorting the debris, transferring the debris to the adjacent

material handling facility, and loading the debris into railcars for offsite disposal.

The inspectors reviewed the radiological status of the open-air demolition project. The

radiological work control requirements were provided in Radiation Work Permit 25-0-77,

revision 0. The permit included worker requirements for dosimetry, protective clothing,

and respiratory protection. The inspectors reviewed the actual and budgeted dose

estimates for the demolition workers for 2025. At the time of the inspection, the

combined assigned doses to demolition workers were about 38 millirem with an annual

budgeted dose of 495 millirem. In summary, the licensee continued to monitor demolition

workers for exposure to radiation and radioactive material, and actual doses were

consistent with the estimated doses for the project.

The open-air demolition plan also provides instructions for daily environmental air

sampling, workplace air sampling, contamination surveys, and dose rate surveys. The

inspectors reviewed the results for the January 28, 2025, daily sampling, in part, to

determine if contamination was spreading outside of the demolition work area. The daily

results did not identify surface contamination outside of the work area, and relatively low

exposure rate readings were identified inside the work area. The licensee continued to

conduct daily sampling as required by the open-air demolition plan, and the daily results

indicated no release of contamination outside of the work area during the inspection.

5

b.

Observation of Decommissioning Work Activities in Units 2 and 3 Containments

The inspectors toured the Units 2 and 3 containments to observe work in progress and

to independently assess radiological conditions. In Unit 2, the licensee continued to

prepare for future reactor segmentation activities including the cutting of the vessel

nozzles. The licensee completed the cutting and removal of the two steam generators.

The licensee removed the final reactor coolant pump from the containment building

during the inspection. The other three reactor coolant pumps were still onsite, awaiting

packaging and offsite shipment for disposal.

In Unit 3, the major work activities included continued preparation for future cutting of the

reactor vessel shell. The licensee continued to cut and remove the remainder of the

steam generators from the containment building. All four reactor coolant pumps had

been removed from containment and shipped offsite for disposal.

The inspectors observed strong radiation protection support in both containments.

Housekeeping was adequate based on the work in progress. A minor radioactive

labeling issue was identified and reported to the radiation protection staff for resolution.

The inspectors conducted independent radiological surveys during site tours using a

Thermo Scientific Radeye G survey meter (serial number 13420, calibration due date of

7/23/2025, calibrated to cesium-137). Overall, the measured exposure rates were

consistent with existing signs, boundaries, and postings.

The licensee and its decommissioning contractor were conducting decommissioning

activities in accordance with the instructions provided in site procedures and

commitments provided in the PSDAR.

c.

Decommissioning Staffing and Training

As described in Section 3.2 below, the inspectors conducted a review of the training and

qualification program for personnel conducting 10 CFR 50.59 safety reviews, design

changes, and modifications. In summary, the training was conducted in accordance with

procedure requirements, and all reviewers were found to be trained and qualified to

conduct their assigned reviews.

1.3

Conclusions

The licensee was effectively implementing decommissioning activities at Units 2 and 3 in

accordance with approved procedures and commitments provided in the PSDAR. The

licensee maintained good radiological control over these work activities.

2

Inspection of Remedial and Final Surveys at Permanently Shutdown Reactors

(IP 83801)

2.1

Inspection Scope

The inspectors observed site activities, reviewed documents, and interviewed site

personnel to verify that permanently shut down power reactor sites have been

decontaminated to acceptable residual radioactivity levels and to verify that the

licensees procedures, radiological measurements, decommissioning surveys, and

6

documentation of decommissioning surveys were implemented in accordance with NRC

guidance.

2.2

Observations and Findings

a.

Remediation Activities and Final Status Surveys

Section II of the PSDAR states that appropriate radiological and environmental programs

will be maintained throughout the decommissioning process to ensure radiological safety

of the workforce and the public, and environmental compliance is maintained. The

inspectors reviewed selected areas of the licensees final status survey and radiological

assessment programs to ensure that surveys were being conducted in accordance with

procedural requirements. Specifically, the inspectors reviewed the licensees

implementation of its final status survey isolation and control measures.

The isolation and control measures are described in procedure SDS-LT1-PCD-1008,

Final Status Survey Isolation and Control Measures, revision 2, isolation and control

measures are used to limit the potential for cross-contamination from other

decommissioning activities and to maintain the final configuration of the applicable

survey units. These measures are implemented for survey units that are ready for final

status surveys and survey units that have been final status surveyed. The measures

include access control to the survey units, installation of postings and boundaries, and

post-survey surveillances.

At the time of the inspection, the areas that were under isolation and control included the

Unit 3 intake gate No. 1, former makeup demineralizer area, former multipurpose

handling facility area, electrical tunnels, and tendon galleries. Other previously surveyed

areas included the underground intake and discharge tunnels that were previously

backfilled with a flowable fill material and are no longer accessible.

The inspectors conducted site tours, in part, to observe the accessible areas being

managed with isolation and control measures. All areas were properly posted with signs

and boundaries. The inspectors also reviewed the licensees program for managing the

post-turnover surveillances. The licensee had established and implemented a program

consistent with procedure requirements. All surveillances were found to be up-to-date.

No evidence of cross-contamination had been identified by the licensee in any final

status survey unit at the time of the inspection.

b.

Verification and Confirmatory Surveys

The inspectors did not conduct independent confirmatory or verification surveys during

this inspection.

c.

Problem Identification and Resolution

The inspectors reviewed recent corrective action program entries involving final status

surveys. The decommissioning contractor was writing Condition Reports (CR) to

address problems as they were identified. Recent issues that were documented in CRs

included a missed meter response background check and clarification of training

requirements. For all CRs, the licensee developed and implemented corrective actions

to prevent reoccurrence of the identified problems.

7

2.3

Conclusions

The licensee implemented final status survey isolation and control measures in

accordance with approved procedures. The licensee continued to identify, document,

and resolve problems in the final status survey program area.

3

Safety Reviews, Design Changes, and Modifications at Permanently Shutdown

Reactors (IP 37801)

3.1

Inspection Scope

The inspectors reviewed documents and interviewed site personnel to verify that the

licensees safety review process was being implemented in accordance with the

requirements of 10 CFR 50.59, Changes, Tests, and Experiments. The inspectors

reviewed the licensees implementation of its safety review programs, selected design

changes and completed safety reviews, training and qualification of reviewers, and SDS

CRs issued in this program area.

3.2

Observations and Findings

a.

Safety Reviews, Design Changes, and Modifications

The licensees programs are described in procedures ENG-3, 10 CFR 50.59, 72.48,

and 50.82 Program, revision 1, and SDS-RA1-PGM-0002, 10 CFR 50.59 and 72.48

Program, revision 3. The inspectors reviewed recently issued safety reviews, design

changes, and modifications. These reviews included:

Elimination of the exclusion area boundary and clarification of site boundary due to

the absence of off-site design-basis accident consequences

Installation of protective enclosures over the lower beach discharge flap valves to

prevent rocks and cobble from obstructing valve operation during rainstorms

Abandonment of the onsite sewage treatment plant and oily waste holding sumps,

and to remove the components from the defueled safety analysis report

Modify, mobilize, and relocate the liquid radioactive waste system from plant

equipment to a mobile platform to allow for demolition of the radwaste building

Verification of the tornado missile protection requirements for tank T-351 to allow the

tank to be used for temporary storage of radioactive water

The inspectors noted that the reviews were conducted and documented by trained and

qualified individuals. No findings of significance were identified during the NRC review of

these safety reviews.

b.

Training and Qualification Program Review

Procedure ENG-3, 10 CFR 50.59, 72.48, and 50.82 Program, revision 1, Section 5.4

provided the qualification requirements for SCE staff, while procedure SDS-RA1-PGM-

0002, 10 CFR 50.59 and 72.48 Program, revision 3, Section 3.2.2, Attachment 5.1 and

Attachment 5.2 provided the training requirements for SDS staff. The inspectors

reviewed both training programs and discussed the programs with representatives from

8

each organization. Both programs had a sufficient number of qualified individuals to

implement the respective programs, and the qualifications were consistent with

procedure requirements.

c.

Problem Identification and Resolution

There were no recent SCE Action Request (AR) or contractor CRs of significance issued

in this program area.

3.3

Conclusions

The licensee developed and implemented a written program for safety reviews, design

changes, and modifications. The program was being implemented by qualified

individuals. Based on a limited NRC review of recently issued safety reviews, the

licensee was noted to be effectively implementing the program.

4

Solid Radioactive Waste Management and Transportation of Radioactive Materials

(IP 86750)

4.1

Inspection Scope

The inspectors observed site activities, reviewed documents, and interviewed site

personnel to verify the effectiveness of the licensees programs for transportation of

radioactive materials. The focus of the inspection was on recently issued CRs

documented for events related to the preparation and transportation of radioactive

material.

4.2

Observations and Findings

a.

Hot work adjacent to combustibles

The inspectors reviewed two contractor CRs (the contractors corrective action program

is not a credited corrective action program) generated after hot work had caused the

burning of Dry Active Waste (DAW). After the on-site inspection was completed, the

inspectors reviewed one licensee AR generated after it was determined that hot work

was again being performed contrary to procedural requirements. Based on the results of

this review, the NRC inspectors identified one violation, with three examples, of NRC

requirements.

Title 10 CFR 50.48(f) requires the licensee to maintain a fire protection program to

address the potential for fires that could cause the release or spread of radioactive

materials. The licensees fire protection program implementing procedure SDS-FP1-

PGM-0015, Control of Ignition Sources, revision 13, states in part:

1.

Section 4.1.7: Licensee must verify all Class A combustibles or Dry Active Waste

bags within 35 feet of hot work have been removed or are shielded with approved

welding curtains, welding blankets or welding pads.

2.

Section 4.1.9: Licensee must relocate combustibles a minimum of 5 feet from the

side opposite work performed on metal walls.

9

Contrary to the above, the licensee failed to maintain the require standoff distance

between ignition sources and combustible materials, as evidenced by the following three

examples:

1.

Contrary to the section 4.1.9 above, on December 4, 2024, the licensee failed to

maintain a 5-foot distance between hot metal surfaces and combustible materials

which resulted in the burning of combustible materials. Specifically, the licensee

contractors were welding shielding to a shipping container which contained DAW.

Contrary to licensee procedures, the DAW was not located greater than 5 feet from

the hot area of the container. The heat from the welding burned the DAW. There

were no flames observed, and the heat was extinguished immediately by the fire

watch. CR SDS-002042 provided the following corrective actions: (a) examination of

container contents prior to performing welding on containers; and (b) providing

shielding on the interior of a container if the container includes flammable material.

2.

Contrary to the section 4.1.9 above, on January 20, 2025, the licensee failed to

maintain a 5-foot distance between hot metal surfaces and combustible materials

which resulted in the burning of combustible materials. Specifically, the licensee

contractors were welding shielding to a shipping container which contained DAW.

The DAW was located greater than 5 feet from the hot areas of the container,

however, during the welding, the DAW shifted into the hot area and the heat from the

welding burned the DAW. There were no flames observed, and the heat was

extinguished immediately by the fire watch. This event was documented in CR SDS-

002057.

3.

Contrary to section 4.1.7 above, on February 6, 2025, the licensee failed to verify all

Class A combustibles within 35 feet of hot work were removed or shielded with

approved welding curtains, welding blankets or welding pad prior to the start of hot

work. Specifically, combustible material was located approximately 10 feet from

active torch cut work performed by a contractor. This resulted in sparks from the

torch cut contacting the flammable material. An SCE observer identified the

deficiency, and the combustibles were moved to an area greater than 35 feet away

from the hot work. No fire or resulted from this event. This event was documented in

AR 0225-70419.

Based on the continued events, the inspectors determined that the corrective actions

taken were not adequate. On January 30, 2024, SCE issued AR 0125-77465 which

states that the licensee will track action taken by the contractor to improve performance

related to hot work as well as to track corrective action creation and implementation.

After the third hot work procedure violation on February 6, 2025, SCE issued a stop work

order for all hot work activities while the above events and appropriate corrective actions

are evaluated. (VIO 050-00362/2025-01-01; Failure to verify all combustibles had been

removed when performing hot work)

b. Leaking Railcars

The inspectors reviewed CR SDS-002048 generated after two railcars containing

radioactive material were found leaking liquid from the bottom of the container after they

were certified for shipment. Upon identification of the leaks, the containers were not

permitted to leave the site. The containers were loaded with concrete and metal from

building demolition. The licensee conducted radiation and contamination surveys and

10

verified no radioactive material had leaked out of the container. The licensee placed a

hold on shipments, inspected similar railcars on site, and subsequently identified

additional railcars with wet contents.

The inspectors reviews of documentation and interviews with personnel verified all

required actions were performed in accordance licensee emergency procedure SDS-

WM1-PCD-0003, Transportation Incident and Emergency Response Plan, revision 7.

The inspectors also verified the containers used for transport of the demolition debris

were in accordance with Department of Transportation requirements for shipment of

Limited Surface Activity material.

The inspectors observed corrective actions implemented after the leaking containers

were investigated. The corrective actions included changes to the debris collection and

increased oversight during loading to ensure liquid is minimized during loading of

demolition debris. The inspectors observations, interviews, and record reviews validated

the licensees corrective action program effectively identified and bounded the problem.

c.

Imbalanced Railcars

The inspectors reviewed CR SDS-002054 generated after two railcars carrying

radioactive material were stopped during transit by the rail company. The railcars transit

was suspended after a railyard found the railcars had imbalanced loads. The licensees

response was prompt, and they determined there were no radiological problems in

addition to the imbalanced load. During the investigation, the licensee determined the

railcar carrier caused the imbalance for both railcars. The licensee worked with the

appropriate Agreement State and obtained the required mobile license with authorized

personnel to correct the imbalance and allow the railcars to complete the shipment to the

waste disposal site. The inspectors interviews, and record reviews validated the

licensees corrective action program effectively assessed and responded the

transportation event.

4.3

Conclusions

The inspectors reviewed selected radioactive waste management and transportation

activities and identified one violation of regulatory requirements. The violation involved

the licensees failure to maintain a fire protection program to address the potential for

fires that could cause the release or spread of radioactive materials.

5

Exit Meeting Summary

The inspectors presented the preliminary inspection results to Frederic Bailly, Vice

President and Chief Nuclear Officer, and other members of the licensees staff at the

conclusion of the onsite inspection on January 30, 2025. A final exit briefing was

provided to the Vice President and Chief Nuclear Officer on February 11, 2025. The

inspectors asked the licensee whether any materials examined during the inspection

should be considered proprietary. No proprietary information was identified except for

certain SDS procedures and documents which were marked as proprietary.

Attachment

SUPPLEMENTAL INSPECTION INFORMATION

KEY POINTS OF CONTACT

Licensee and Contractor Personnel

N. Alchaar, Manager, Project Management Office

F. Bailly, SCE, Chief Nuclear Officer and Vice President Decommissioning

J. Carey, SCE, Corrective Action Program Manager

C. Cates, SCE, Manager, Prudency, Safety Culture and Employees Concern Program

G. Ferrigno, SDS, Radiation Protection Manager

T. Giard, SDS, D&D Project Director

R. Kalman, SDS, Executive Sponsor

T. Laursen, SDS, Corrective Action Program Manager

J. Madigan, SCE, Manager, Radiation Protection and Waste Oversight; Nuclear Oversight

S. Mannon, SDS, Programs Project Director/Regulatory Manager

A. Martinez, SDS, Performance Improvement Manager

M. Morgan, SCE, Manager, Regulatory Affairs

L. Mosher, SCE, Manager, Communications

J. Peattie, SCE, General Manager, Site Operations

R. Pontes, SCE, General Manager, Site Closure and Environmental Oversight

L. Rafner, SCE, Regulatory Affairs

S. Seward, Audit Services Representative

S. Sewell, SCE, Manager, Radiation Protection and Waste

B. Sholler, SDS, LT/FSS Project Manager

J. Stephenson, SCE, Manager, Engineering

INSPECTION PROCEDURES USED

IP 71801

Decommissioning Performance and Status Reviews at Permanently Shutdown

Reactors

IP 83801

Inspection of Remedial and Final Surveys at Permanently Shutdown Reactors

IP 37801

Safety Reviews, Design Changes, and Modifications at Permanently Shutdown

Reactors

IP 86750

Solid Radioactive Waste Management and Transportation of Radioactive

Materials

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

05000362/2025-01-01

VIO

Failure to verify all combustibles had been

removed when performing hot work

Closed

None

Discussed

None

2

PARTIAL LIST OF DOCUMENTS REVIEWED

Procedures

SDS-FP1-PGM-0015, Control of Ignition Sources, revision 13

SDS-RP1-TSD-24-01, Open-Air Demolition Plan for San Onofre, revision 2

SDS-LT1-PCD-1008, Final Status Survey Isolation and Control Measures, revision 2

ENG-3, 10 CFR 50.59, 72.48, and 50.82 Program, revision 1

SDS-RA1-PGM-0002, 10 CFR 50.59 and 72.48 Program, revision 3

SDS-WM1-PCD-0003, Transportation Incident and Emergency Response Plan, revision 7

SDS-3-M-CO-2212, U3 RV (RLS) Reactor Lifting System Equipment Installation, revision 0

SDS-LT1-PCD-1008, Final Status Survey Isolation and Control Measures, revision 2

SDS-RP1-PGM-3000, Control of Radioactive Material, revision 5

SDS-RP1-PCD-3005, Portable Ventilation and the Use of Vacuum Cleaners, revision 9

SDS-QA1-PGM-0001, SONGS DecommissioningSolutions Quality Assurance Program,

revision 5

Brandenburg MA0879-SONGS, Site-specific Health and Safety Plan, revision 12/30/2020

Condition Reports/Action Requests Reviewed

SDS CR SDS-002042, December 4, 2024, Heat transfer through Conex, from welding, to DAW

bag

SDS CR SDS-002057, January 20, 2025, Transfer of heat from welding to a DAW bag inside

ISO container

SDS CR SDS-002048, December 1, 2025, Two railcars identified to be leaking from the bottom

corners of floor

SDS CR SDS-002054, January 15, 2025, SONGS railcar placed on Bad Order by United

Pacific

Open Air Demo Nightly Report, January 28, 2025

SCE AR 1024-49410, October 10, 2024, Undesirable conditions related to safety signs

SCE AR 0225-70419, February 6, 2025, All combustibles not removed prior to performance of

hot work

Condition Reports/Action Requests Generated from Inspection

SCE AR 0125-77465, January 30, 2025, Track and document actions taken by the contractor to

improve performance specific to Hot Work

SDS CR SDS-002062, January 30, 2025, Evaluate monthly inventory frequency and labeling for

adequacy of in-service vacuums and HEPA ventilation units in accordance with SDS-RP1-PCD-

3005

Licensing Bases Documents

San Onofre Nuclear Generating Station Units 2 & 3 Defueled Safety Analysis Report (DSAR)

November 2024

Post-Shutdown Decommissioning Activities Report and Irradiated Fuel Management Plan dated

May 7, 2022

Miscellaneous

Radiation Work Permit 25-0-777

Signed Shipping Manifest LLRW-25-006, January 8, 2025

Signed Shipping Manifest LLRW-25-002, January 8, 2025

SONGS Hot Work Permit, January 20, 2025

SONGS Pre-Job Checklist/Post Job Brief, January 20, 2025

Calculation of Airborne Radioactivity Resulting from Smoldering Herculite, January 28, 2025

3

Open Air Demo Nightly Report dated January 28, 2025

SDS Daily ALARA Report dated January 29, 2025

Brandenburg Hot Work Permit MA0879, February 6, 2025

Safety Reviews, Design Changes, and Modifications

SCE Applicability Determination, Screens and/or Evaluations for Elimination of Exclusion Area

Boundary and Clarification of Site Boundary, 1220-99225-3, revision 0

SCE Engineering Change Package, NECP Number 1220-99225-4, Elimination of Exclusion

Area Boundary (EAB) and Clarification of Site Boundary, revision 0

SCE Applicability Determination, Screens, and/or Evaluations for Install Protective Enclosures

Over Beach Discharge Flaps, AR 1023-30925-6, revision 0

SCE Engineering Change Package, NECP Number 1023-30925-5, Install Protective Enclosures

Over Beach Discharge Flap Valves, revision 0

SDS Applicability Determination, SDS-50.59-2023-0009, Abandon Sewage Treatment Plant and

East/West Oily Waste Holding Sumps, revision N/A

SDS Design Plan, Sewage Treatment Plant Isolation, revision 0

SDS Applicability Determination, SDS-50.59-2022-0005, LRW Mobile Processing & Discharge,

revision 0

SDS Design Plan, LRW Mobile Processing & Discharge, revision 0

SONGS Calculation Package, SDS-EN1-CAL-0061m T-351 Tornado Missile Standard Review

Plan 3.5 Review, revision 1

LIST OF ACRONYMS

ADAMS

Agencywide Documents Access and Management System

ALARA

As Low As Is Reasonably Achievable

AR

Action Request

CFR

Code of Federal Regulations

CR

Condition Report

DAW

Dry Active Waste

DSAR

Defueled Safety Analysis Report

IP

Inspection Procedure

ISFSI

Independent Spent Fuel Storage Installation

NRC

Nuclear Regulatory Commission

PSDAR

Post-Shutdown Decommissioning Activities Report

SCE

Southern California Edison Company

SDS

SONGS Decommissioning Solutions

SONGS

San Onofre Nuclear Generating Station