2023 INPO Executive Meeting August 02, 2023
Admiral Willard President and Chief Executive Officer Institute of Nuclear Power Operations Opening Comments 2
Opening Comments 3
Daniel Dorman Executive Director for Operations US Nuclear Regulatory Commission
Opening Comments 4
Scott Morris Deputy Executive Director Reactor and Preparedness Programs Mike King Deputy Director Office of Nuclear Reactor Regulation
Inspection Findings Trend 5
- Clear downward trend in number of green ROP inspection findings began in 2015 through 2020, but has increased each of the past two years
- The average number of findings per site decreased by approximately 1.5 findings per site each year from 2015 through 2020
comparable to the number of green findings issued in 2019 0
50 100 150 200 250 300 Green ROP Inspection Findings 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr
Greater than Green ROP Findings Trend 6
- Noticeable increase in greater-than-Green ROP findings in 2022 compared to the previous few years
- Looking a few years further back though, this appears to be in line with previous levels of performance
- Going back further yet shows a clear decreasing trend over a 15-year time frame 12 10 8
6 4
2 0
2018 2019 2020 2021 2022*
Greater-than-Green Findings 0
6 4
2 12 10 8
2015 2016 2017 2018 2019 2020 2021 2022*
30 25 20 15 10 5
0
Focusing on risk significant issues and continuing to enhance the ROP 7
8 Vogtle Unit 3 Commercial Operations / Vogtle Unit 4 10 CFR 52.103(g)
Preparing for the Future of the Operating Fleet 9
Reactor Decommissioning Subsequent License Renewal By 2030-2050, nearly all U.S.
operating power reactors will need to pursue subsequent license renewal in order to operate past 60 years.
Twenty-five power reactors are currently in decommissioning.
More may announce plans to shutdown in the coming years.
Light Water Reactor Sustainability Program
Priorities Moving Forward 11
- Nuclear Safety Issues
- Vogtle 3&4
- Advanced Reactor Preparation and Licensing, including 10 CFR Part 53 Rulemaking
- Digital I&C
- Reactor Oversight
- NRR Risk Activities
- Hiring/Staffing
12