Letter Sequence Request |
|---|
EPID:L-2023-LLA-0123, ITAAC Closure Verification Evaluation Form (Vef) for ITAAC Number 2.1.02.08e (Index No. 40) for Vogtle Unit 4 Combined License (VOG4) (Open) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, ... further results|Request]]
- Acceptance
|
MONTHYEARND-22-0830, ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.1 0.ii (Index Number 816)2022-10-26026 October 2022 ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.1 0.ii (Index Number 816) Project stage: Request ND-22-0689, ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.i (Index Number 53)2022-11-0303 November 2022 ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.i (Index Number 53) Project stage: Request ND-22-0862, ITAAC Closure Notification on Completion of ITAAC Item C.2.5.04.04a (Index Number 561)2022-11-0808 November 2022 ITAAC Closure Notification on Completion of ITAAC Item C.2.5.04.04a (Index Number 561) Project stage: Request ND-22-0730, ITAAC Closure Notification on Completion of ITAAC 2.3.03.02 (Index Number 319)2022-11-10010 November 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.03.02 (Index Number 319) Project stage: Request ND-22-0657, ITAAC Closure Notification on Completion of ITAAC 2.3.14.04 (Index Number 480)2022-11-17017 November 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.14.04 (Index Number 480) Project stage: Request ND-22-0898, ITAAC Closure Notification on Completion of 3.2.00.04 (Index Number 751)2022-11-18018 November 2022 ITAAC Closure Notification on Completion of 3.2.00.04 (Index Number 751) Project stage: Request ND-22-0714, ITAAC Closure Notification on Completion of ITAAC 2.3.08.02.iii (Index Number 4171)2022-11-22022 November 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.08.02.iii (Index Number 4171) Project stage: Request ND-22-0711, ITAAC Closure Notification on Completion of ITAAC 3.3.00.01 (Index Number 759)2022-11-23023 November 2022 ITAAC Closure Notification on Completion of ITAAC 3.3.00.01 (Index Number 759) Project stage: Request ML22332A5372022-11-28028 November 2022 Draft LAR 23-001 for 12-8-22 Public Meeting ND-22-0821, ITAAC Closure Notification on Completion of ITAAC 3.3.00.13 (Index Number 819)2022-11-29029 November 2022 ITAAC Closure Notification on Completion of ITAAC 3.3.00.13 (Index Number 819) Project stage: Request ML22334A0752022-12-0101 December 2022 Update to Targeted Inspections, Tests, Analysis, and Acceptance Criteria for Vogtle Electric Generating Plant Unit 4 Project stage: Request ND-22-0920, ITAAC Closure Notification on Completion of ITAAC 2.7.01 .02a (Index Number 678)2022-12-0707 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.7.01 .02a (Index Number 678) Project stage: Request ND-22-0899, ITAAC Closure Notification on Completion of ITAAC 2.2.03.12a.i (Index Number 214)2022-12-15015 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.2.03.12a.i (Index Number 214) Project stage: Request ND-22-0656, ITAAC Closure Notification on Completion of ITAAC 2.3.05.03b.iii (Index Number 348)2022-12-15015 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.05.03b.iii (Index Number 348) Project stage: Request ND-22-0600, ITAAC Closure Notification on Completion of ITAAC 2.3.02.05.i (Index Number 291)2022-12-16016 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.02.05.i (Index Number 291) Project stage: Request ND-22-0747, ITAAC Closure Notification on Completion of ITAAC 2.1 .02.08d.ii (Index Number 33)2022-12-21021 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.1 .02.08d.ii (Index Number 33) Project stage: Request ND-22-0967, Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.c (Index Number 802)2022-12-22022 December 2022 Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.c (Index Number 802) Project stage: Request ND-22-0964, Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.a (Index Number 800)2022-12-22022 December 2022 Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.a (Index Number 800) Project stage: Request ND-22-0965, Resubmittal of Notice of Uncompleted IT Aac 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.b (Index Number 801)2022-12-22022 December 2022 Resubmittal of Notice of Uncompleted IT Aac 225-days Prior to Initial Fuel Load Item 3.3.00.07d.ii.b (Index Number 801) Project stage: Request ND-22-0895, ITAAC Closure Notification on Completion of ITAAC 2.2.01.01 (Index Number 90)2022-12-28028 December 2022 ITAAC Closure Notification on Completion of ITAAC 2.2.01.01 (Index Number 90) Project stage: Request ML22349A2142023-01-0303 January 2023 Summary of December 8, 2022, Public Meeting with Southern Nuclear Operating Company Project stage: Request ND-23-1001, ITAAC Closure Notification on Completion of ITAAC 2.7.01.05.i (Index Number 684)2023-01-0505 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.7.01.05.i (Index Number 684) Project stage: Request ND-22-0848, ITAAC Closure Notification on Completion of ITAAC 2.3.02.14 (Index Number 317)2023-01-10010 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.02.14 (Index Number 317) Project stage: Request ND-22-0869, ITAAC Closure Notification on Completion of Item 2.3.13.05.i (Index Number 462)2023-01-12012 January 2023 ITAAC Closure Notification on Completion of Item 2.3.13.05.i (Index Number 462) Project stage: Request ND-23-0030, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.d (Index Number 763)2023-01-13013 January 2023 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.d (Index Number 763) Project stage: Request ND-23-0026, ITAAC Closure Notification on Completion of ITAAC 2.2.03.12a.iv (Index Number 216)2023-01-13013 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.12a.iv (Index Number 216) Project stage: Request ND-23-0029, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.c (Index Number 762)2023-01-13013 January 2023 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.c (Index Number 762) Project stage: Request ND-22-0649, ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.iv (Index Number 56)2023-01-13013 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.iv (Index Number 56) Project stage: Request ND-22-0893, ITAAC Closure Notification on Completion of ITAAC 2.1.02.01 (Index Number 12)2023-01-16016 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.01 (Index Number 12) Project stage: Request ND-22-0700, ITAAC Closure Notification on Completion of Item 2.2.04.12a.i (Index Number 248)2023-01-20020 January 2023 ITAAC Closure Notification on Completion of Item 2.2.04.12a.i (Index Number 248) Project stage: Request ND-22-0521, ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.i.03 (Index Number 179)2023-01-20020 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.i.03 (Index Number 179) Project stage: Request ND-22-0585, ITAAC Closure Notification on Completion of 2.2.02.11a.i (Index Number 154)2023-01-23023 January 2023 ITAAC Closure Notification on Completion of 2.2.02.11a.i (Index Number 154) Project stage: Request ND-23-0041, ITAAC Closure Notification on Completion of ITAAC 2.2.04.01 (Index Number 219)2023-01-26026 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.04.01 (Index Number 219) Project stage: Request ND-23-0078, ITAAC Closure Notification on Completion of ITAAC 2.2.02.06b (Index Number 133)2023-01-27027 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.02.06b (Index Number 133) Project stage: Request ND-22-0739, ITAAC Closure Notification on Completion of ITAAC 2.3.08.02.i (Index Number 415)2023-01-31031 January 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.08.02.i (Index Number 415) Project stage: Request ND-22-0876, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02h 9Index Number 776)2023-01-31031 January 2023 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02h 9Index Number 776) Project stage: Request ND-23-0079, ITAAC Closure Notification on Completion of ITAAC 2.3.02.02a (Index Number 285)2023-02-0202 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.02.02a (Index Number 285) Project stage: Request ND-23-0039, ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.ii (Index Number 181)2023-02-0303 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.ii (Index Number 181) Project stage: Request ND-23-0043, ITAAC Closure Notification on Completion of ITAAC 2.1.02.08d.i (Index Number 32)2023-02-0303 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.1.02.08d.i (Index Number 32) Project stage: Request ND-22-0670, ITAAC Closure Notification on Completion of 2.4.06.02 (Index Number 504)2023-02-0707 February 2023 ITAAC Closure Notification on Completion of 2.4.06.02 (Index Number 504) Project stage: Request ND-22-0733, ITAAC Closure Notification on Completion of ITAAC 2.3.05.03c.ii (Index Number 350)2023-02-10010 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.05.03c.ii (Index Number 350) Project stage: Request ND-23-0130, ITAAC Closure Notification on Completion of ITAAC 2.3.07.07c (Index Number 408)2023-02-10010 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.07.07c (Index Number 408) Project stage: Request ND-22-0737, ITAAC Closure Notification on Completion of ITAAC 2.3.05.03d.ii (Index Number 352)2023-02-10010 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.05.03d.ii (Index Number 352) Project stage: Request ND-23-0124, ITAAC Closure Notification on Completion of ITAAC Item 2.3.10.12 (Index Number 879)2023-02-13013 February 2023 ITAAC Closure Notification on Completion of ITAAC Item 2.3.10.12 (Index Number 879) Project stage: Request ND-23-0153, ITAAC Closure Notification on Completion of ITAAC 2.3.09.02a (Index Number 421)2023-02-16016 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.09.02a (Index Number 421) Project stage: Request ND-23-0141, ITAAC Closure Notification on Completion of ITAAC 2.3.04.05 (Index Number 332)2023-02-16016 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.04.05 (Index Number 332) Project stage: Request ND-23-0071, ITAAC Closure Notification on Completion of Item 2.2.05.05a.i (Index Number 259)2023-02-17017 February 2023 ITAAC Closure Notification on Completion of Item 2.2.05.05a.i (Index Number 259) Project stage: Request ND-23-0118, ITAAC Closure Notification on Completion of ITAAC 2.3.07.05.i (Index Number 396)2023-02-17017 February 2023 ITAAC Closure Notification on Completion of ITAAC 2.3.07.05.i (Index Number 396) Project stage: Request ND-22-0919, ITAAC Closure Notification on Completion of ITAAC 3.3.00.07d.i (Index Number 799)2023-02-24024 February 2023 ITAAC Closure Notification on Completion of ITAAC 3.3.00.07d.i (Index Number 799) Project stage: Request ND-23-0159, ITAAC Closure Notification on Completion of ITAAC 2.6.03.05d.i (Index Number 613)2023-03-0101 March 2023 ITAAC Closure Notification on Completion of ITAAC 2.6.03.05d.i (Index Number 613) Project stage: Request 2023-01-12
[Table View] |
Text
Jamie M. Coleman Regulatory Affairs Director Vogtle 3 & 4 7825 River Road Waynesboro, GA 30830 706-848-6926 tel April 28, 2023 Docket No.:
52-026 ND-23-0350 10 CFR 52.99(c)(1)
U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 4 ITAAC Closure Notification on Completion of ITAAC 2.4.01.02 [Index Number 493]
Ladies and Gentlemen:
In accordance with 10 CFR 52.99(c)(1), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) of the completion of Vogtle Electric Generating Plant (VEGP)
Unit 4 Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 2.4.01.02 [Index Number 493]. This ITAAC requires testing and inspections be performed to verify that the Main and Startup Feedwater System (FWS) provides 260 gpm of startup feedwater flow from the Condensate Storage Tank (CST) to the Steam Generator System (SGS) for Reactor Coolant System (RCS) heat removal. The ITAAC also verifies that controls exist in the Main Control Room (MCR) and operate to cause the components listed in the VEGP Unit 4 Combined Operating License COL Appendix C Table 2.4.1-1 to perform the listed function. Finally, it verifies that the displays of parameters identified in VEGP Unit 4 COL Appendix C Table 2.4.1-1 can be retrieved in the MCR. The closure process for this ITAAC is based on the guidance described in NEI 08-01, Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215.
This letter contains no new NRC regulatory commitments. Southern Nuclear Operating Company (SNC) requests NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 10 CFR 52.99.
If there are any questions, please contact Kelli Roberts at 706-848-6991.
Respectfully submitted, Jamie M. Coleman Regulatory Affairs Director Vogtle 3 & 4
Enclosure:
Vogtle Electric Generating Plant (VEGP) Unit 4 Completion of ITAAC 2.4.01.02 [Index Number 493]
JMC/PCM/sfr
U.S. Nuclear Regulatory Commission ND-23-0350 Page 2 of 2 cc:
Regional Administrator, Region ll Director, Office of Nuclear Reactor Regulation (NRR)
Director, Vogtle Project Office NRR Senior Resident Inspector - Vogtle 3 & 4
U.S. Nuclear Regulatory Commission ND-23-0350 Enclosure Page 1 of 6 Southern Nuclear Operating Company ND-23-0350 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 4 Completion of ITAAC 2.4.01.02 [Index Number 493]
U.S. Nuclear Regulatory Commission ND-23-0350 Enclosure Page 2 of 6 ITAAC Statement Design Commitment
- 2. The FWS provides startup feedwater flow from the CST to the SGS for heat removal from the RCS.
- 3. Controls exist in the MCR to cause the components identified in Table 2.4.1-1 to perform the listed function.
- 4. Displays of the parameters identified in Table 2.4.1-1 can be retrieved in the MCR.
Inspections/Tests/Analyses Testing will be performed to confirm that each of the startup feedwater pumps can provide water from the CST to both steam generators.
Testing will be performed on the components in Table 2.4.1-1 using controls in the MCR.
Inspection will be performed for retrievability of parameters in the MCR.
Acceptance Criteria Each FWS startup feedwater pump provides a flow rate greater than or equal to 260 gpm to each steam generator system at a steam generator secondary side pressure of at least 1106 psia.
Controls in the MCR operate to cause the components listed in Table 2.4.1-1 to perform the listed functions.
The displays identified in Table 2.4.1-1 can be retrieved in the MCR.
ITAAC Determination Basis This ITAAC requires testing and inspections be performed to verify that the Main and Startup Feedwater System (FWS) provides 260 gpm of startup feedwater flow from the Condensate Storage Tank (CST) to the Steam Generator System (SGS) for Reactor Coolant System (RCS) heat removal, that controls exist in the Main Control Room (MCR) and operate to cause the components listed in the VEGP Unit 4 Combined Operating License COL Appendix C Table 2.4.1-1 (Attachment A) to perform the listed function, and that the displays of parameters identified in VEGP Unit 4 COL Appendix C Table 2.4.1-1 (Attachment B) can be retrieved in the MCR.
Each FWS startup feedwater pump provides a flow rate greater than or equal to 260 gpm to each steam generator system at a steam generator secondary side pressure of at least 1106 psia.
Testing was performed and results were documented in accordance with Unit 4 Preoperational Test Procedure 4-FWS-ITPP-502 (Reference 1) and ITAAC Technical Report SV4-FWS-ITR-800493 (Reference 2) to verify that each Startup Feedwater pump can provide greater than or equal to 260 gpm to each steam generator system at a secondary side pressure of at least 1106 psia.
Initial conditions were established with the plant at Normal Operating Pressure (NOP) and Normal Operating Temperature (NOT) utilizing the plant general operating procedure. Steam Generator pressure control was placed into Automatic to maintain secondary pressure at 1110
U.S. Nuclear Regulatory Commission ND-23-0350 Enclosure Page 3 of 6 psia and temporary flow instruments were installed on the startup feedwater lines to each steam generator. Main Feedwater flow was stopped, and Startup Feedwater flow was initiated using the A Startup Feedwater pump. Flow was recorded and verified to be greater than or equal to 260 gpm to each steam generator system. This testing was repeated using the B Startup Feedwater pump.
The results of the testing showed that the Unit 4 A startup feedwater pump provided 313 gpm to the steam generator 1 and 324 gpm to the steam generator 2 and the B startup feedwater pump provided 322 gpm to the steam generator 1 and 314 gpm to the steam generator 2.
This testing confirmed that for Unit 4 each FWS startup feedwater pump provided a flow rate greater than or equal to 260 gpm to each steam generator system at a steam generator secondary side pressure of at least 1106 psia.
Controls in the MCR operate to cause the components listed in Table 2.4.1-1 to perform the listed functions.
Testing was performed as documented in ITAAC Technical Report SV4-FWS-ITR-801493 (Reference 3) to verify that controls exist in the MCR, and the controls operate to cause the components listed in Table 2.4.1-1 (Attachment A) to perform the listed functions.
The component test began with the components in Attachment A in the closed position or shutdown condition. An operator was stationed locally to monitor and verify component actuations. The A startup feedwater pump was started using PLS controls and the pump isolation valve was verified to open. The A startup feedwater pump was stopped, and this testing was repeated for the B startup feedwater pump. The test results confirmed that controls in Unit 4 MCR operated to cause the components listed in Table 2.4.1-1 to perform the listed functions.
The displays identified in Table 2.4.1-1 can be retrieved in the MCR.
The inspection was performed and results were documented in ITAAC Technical Report SV4-FWS-ITR-801493 (Reference 3) to verify that the displays identified in Table 2.4.1-1 (Attachment B) could be retrieved in the MCR.
Testing began at an operator work station in the Unit 4 MCR and verified all the displays identified in Attachment B could be retrieved. This confirmed that the displays identified in Table 2.4.1-1 could be retrieved in the Unit 4 MCR.
The completed test results (References 1 through 3) confirmed that each of the startup feedwater pumps provided the required flow to each steam generator system, that the controls in the MCR operated to cause the components listed in Table 2.4.1-1 to perform the listed functions, and that the displays identified in Table 2.4.1-1 could be retrieved in the MCR.
References 1 through 3 are available for NRC inspection as part of the Unit 4 Completion Package (Reference 4).
ITAAC Finding Review In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company (SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there were no relevant ITAAC findings associated with this ITAAC. The ITAAC completion review is documented in the ITAAC Completion Package for ITAAC 2.4.01.02 (Reference 4) and is available for NRC review.
U.S. Nuclear Regulatory Commission ND-23-0350 Enclosure Page 4 of 6 ITAAC Completion Statement Based on the above information, SNC hereby notifies the NRC that ITAAC 2.4.01.02 was performed for VEGP Unit 4 and that the prescribed acceptance criteria were met.
Systems, structures, and components verified as part of this ITAAC are being maintained in their as-designed, ITAAC compliant condition in accordance with approved plant programs and procedures.
References (available for NRC inspection)
- 1. 4-FWS-ITPP-502, Version 2.0, Main and Startup Feedwater System (FWS) Hot Functional Test Procedure.
- 2. SV4-FWS-ITR-800493, Rev. 0, Unit 4 Recorded Results of Main and Startup Feedwater System (FWS): ITAAC 2.4.01.02 Item 2
- 3. SV4-FWS-ITR-801493, Rev. 0, Unit 4 Recorded Results of Main and Startup Feedwater System (FWS): ITAAC 2.4.01.02 Items 3 and 4
- 4. 2.4.01.02-U4-CP-Rev0, ITAAC Completion Package
U.S. Nuclear Regulatory Commission ND-23-0350 Enclosure Page 5 of 6 Attachment A
- Excerpt from COL Appendix C Table 2.4.1-1 Equipment Name*
Tag No.*
Control Function*
Startup Feedwater Pump A (Motor)
FWS-MP-03A Start Startup Feedwater Pump B (Motor)
FWS-MP-03B Start Startup Feedwater Pump A Isolation Valve FWS-PL-V013A Open Startup Feedwater Pump B Isolation Valve FWS-PL-V013B Open
U.S. Nuclear Regulatory Commission ND-23-0350 Enclosure Page 6 of 6 Attachment B
- Excerpt from COL Appendix C Table 2.4.1-1 Equipment Name*
Tag No.*
Display*
Startup Feedwater Pump A (Motor)
FWS-MP-03A Yes (Run Status)
Startup Feedwater Pump B (Motor)
FWS-MP-03B Yes (Run Status)
Startup Feedwater Pump A Isolation Valve FWS-PL-V013A Yes (Valve Position)
Startup Feedwater Pump B Isolation Valve FWS-PL-V013B Yes (Valve Position)