MONTHYEARRS-20-139, Response to Request for Additional Information Regarding License Amendment Requests to Adopt TSTF-505, Revision 2, and 10 CFR 50.692020-11-24024 November 2020 Response to Request for Additional Information Regarding License Amendment Requests to Adopt TSTF-505, Revision 2, and 10 CFR 50.69 Project stage: Response to RAI JAFP-21-0032, Response to Request for Additional Information - Proposed Alternative Concerning ASME Section XI Repair/Replacement Documentation for Replacement of Pressure Retaining Bolting2021-04-20020 April 2021 Response to Request for Additional Information - Proposed Alternative Concerning ASME Section XI Repair/Replacement Documentation for Replacement of Pressure Retaining Bolting Project stage: Response to RAI JAFP-21-0064, Supplemental Information - Proposed Alternative Concerning ASME Section XI Repair/Replacement Documentation for Replacement of Pressure Retaining Bolting2021-07-0707 July 2021 Supplemental Information - Proposed Alternative Concerning ASME Section XI Repair/Replacement Documentation for Replacement of Pressure Retaining Bolting Project stage: Request JAFP-21-0069, Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2021-07-30030 July 2021 Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Project stage: Request JAFP-21-0070, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk- Informed Extended Completion Times - RITSTF Initiative 4b2021-07-30030 July 2021 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk- Informed Extended Completion Times - RITSTF Initiative 4b Project stage: Request ML21246A2072021-09-0303 September 2021 Acceptance of Requested Licensing Action License Amendment Request to Adopt 10 CFR 50.69 Project stage: Acceptance Review ML21246A2112021-09-0303 September 2021 Acceptance of Requested Licensing Action License Amendment Request to Adopt TSTF-505 Project stage: Acceptance Review 05000333/LER-2021-001, Inadequate Protection Devices for DC Motor Field Shunt Cables Through Separate Fire Areas2021-10-22022 October 2021 Inadequate Protection Devices for DC Motor Field Shunt Cables Through Separate Fire Areas Project stage: Request ML21285A1492021-10-22022 October 2021 Audit Plan in Support of Review of License Amendment Requests Regarding 50.69/TSFT-505 Project stage: Other JAFP-22-2020, Supplemental Information No. 1 for James A. FitzPatrick Nuclear Power Plant to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b. and 10CFR 50.69, Risk-Info2022-03-0404 March 2022 Supplemental Information No. 1 for James A. FitzPatrick Nuclear Power Plant to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b. and 10CFR 50.69, Risk-Informed Project stage: Supplement ML22124A2672022-05-0404 May 2022 Request for Additional Information for James A. FitzPatrick Nuclear Power Plant TSTF-505 Project stage: RAI JAFP-22-0032, Response to Request for Additional Information for James A. FitzPatrick Nuclear Power Plant to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b..2022-06-16016 June 2022 Response to Request for Additional Information for James A. FitzPatrick Nuclear Power Plant to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b.. Project stage: Response to RAI ML22196A0612022-08-23023 August 2022 Issuance of Amendment No. 352 Adoption of 10 CFR 50.69 Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Project stage: Approval ML22238A1202022-08-31031 August 2022 Regulatory Audit Summary Regarding License Amendment Requests to Adopt 10 CFR 50.69 and to Permit the Use of Risk-Informed Completion Times in Accordance with TSTF-505, Rev. 2 (EPIDs L-2021-LLA 0142 and L-2021-LLA-0143) Project stage: Other ML22223A1412022-09-0101 September 2022 Issuance of Amendment No. 353 Adoption of TSTF - 505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4B Project stage: Approval 2021-09-03
[Table View] |
Text
From:
Poole, Justin To:
Williams, Christian D:(Exelon Nuclear)
Cc:
Danna, James
Subject:
JAMES A. FITZPATRICK NUCLEAR POWER PLANT - ACCEPTANCE OF REQUESTED LICENSING ACTION RE:
LICENSE AMENDMENT REQUEST TO ADOPT TSTF-505 (EPID L-2021-LLA-0143)
Date:
Friday, September 03, 2021 11:29:00 AM
SUBJECT:
JAMES A. FITZPATRICK NUCLEAR POWER PLANT - ACCEPTANCE OF REQUESTED LICENSING ACTION RE: LICENSE AMENDMENT REQUEST TO ADOPT TSTF-505 (EPID L-2021-LLA-0143)
By letter dated July 30, 2021, (Agencywide Documents Access and Management System (ADAMS) Accession No. ML21211A053) Exelon Generation Company, LLC submitted a license amendment request for James A. FitzPatrick Nuclear Power Plant (FitzPatrick).
The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an application for an amendment to a license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.
Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 2100 hours0.0243 days <br />0.583 hours <br />0.00347 weeks <br />7.9905e-4 months <br /> to complete. The NRC staff expects to complete this review by September 3, 2022. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.
These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or
hearing-related activities. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.
If you have any questions, please contact me.
Justin C. Poole Project Manager NRR/DORL/LPL I U.S. Nuclear Regulatory Commission (301)415-2048