Transmittal Letter to GEH - SE for LTR #1, Reactor Pressure Vessel Isolation and Overpressure Protection
ML20176A448
Person / Time
Site: 99900003
Issue date: 06/26/2020
From: Rani Franovich
NRC/NRR/DNRL/NRLB
To: Michelle Catts
GE Hitachi Nuclear Energy
Franovich R, Cranston G
Shared Package
ML20176A446 List:
References
NEDC-33910P
Download: ML20176A448 (3)


Text

June 26, 2020 Ms. Michelle Catts Senior Vice President, Regulatory Affairs GE-Hitachi Nuclear Energy Americas, LLC.

SUBJECT:

SAFETY EVALUATION FOR GE-HITACHI LICENSING TOPICAL REPORT NEDC-33910P, REVISION 0, SUPPLEMENT 2, BWRX-300 REACTOR PRESSURE VESSEL ISOLATION AND OVERPRESSURE PROTECTION (DOCKET N0. 99900003)

Dear Ms. Catts:

By letter dated December 30, 2019, GE-Hitachi Nuclear Energy Americas, LLC (GEH) submitted Licensing Topical Report (TR) NEDC-33910P, Revision 0, BWRX-300 Reactor Pressure Vessel Isolation and Overpressure Protection (Agencywide Documents Access and Management System Accession No. ML19364A209), to the U.S. Nuclear Regulatory Commission (NRC) staff for review. In that letter, GEH requested the NRC staff to review and approve the design requirements, acceptance criteria, and regulatory basis for the BWRX-300 reactor pressure vessel isolation and overpressure protection design functions. GEH further requested that the NRC staff review this information, determine its acceptability for use, and issue a final Safety Evaluation (SE) no later than June 26, 2020.

It is the NRC staffs understanding that NEDC-33910P will be referenced in a future application for a construction permit for the BWRX-300 small modular reactor (SMR), an evolutionary boiling water reactor based on GEHs Economic Simplified Boiling Water Reactor (ESBWR) design previously licensed by the NRC staff.

The NRC staff informed GEH that it had accepted NEDC-33910P for review in a letter dated February 27, 2020 (ADAMS Accession No. ML20055E325). By letter dated June 4, 2020 (ADAMS Accession No. ML20156A270), GEH submitted Revision 0, Supplement 1, of this TR for NRC staff review and approval. A public version of Revision 0 Supplement 1 of this TR can be found under ADAMS Accession No. ML20156A273. By letter dated June 22, 2020 (ADAMS Accession No. ML20174A574), GEH submitted Revision 0, Supplement 2, of this TR for the NRC staffs review and approval. A public version of Revision 0, Supplement 2, of this TR can be found under ADAMS Accession No. ML20174A577.

The NRC staffs safety evaluation (SE) for NEDC-33910P, Revision 0, Supplement 2, is available in ADAMS under Accession No. ML20176A446 (Package).

M. Catts If you have any questions or comments concerning this matter, I can be reached at (301) 415-7334 or via e-mail address at Rani.Franovich@nrc.gov.

Sincerely,

/RA/

Rani Franovich, Project Manager New Reactor Licensing Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation Docket No.: 99900003 cc: GEH BWRX-300 NEDC-33910P ListServ

PKG: ML20176A446 Letter: ML20176A448 SER: ML20176A449 (PUBLIC)

SER: ML20176A450 (PROP) *via email NRR-106 OFFICE NRR/DNRL/NRLB: PM NRR/DNRL/NRLB: LA QTE NAME RFranovich CSmith* JDougherty*

DATE 06/23/2020 06/25/2020 06/08/2020 OFFICE NRR/DNRL/NRLB: BC OGC NRR/DNRL: D NAME MDudek* MWright* ABradford*

DATE 06/12/2020 06/24/2020 06/26/2020