ML20154C279

From kanterella
Jump to navigation Jump to search
Integrated Assessment Team Insp Rept 50-293/88-21 on 880808- -24.No Violations Noted.Major Areas Inspected:Degree of Readiness of Licensee Mgt Controls,Programs & Personnel to Support Safe Restart & Plant Operation
ML20154C279
Person / Time
Site: Pilgrim
Issue date: 09/07/1988
From: Blough A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20154C278 List:
References
50-293-88-21, NUDOCS 8809140304
Download: ML20154C279 (161)


See also: IR 05000293/1988021

Text

.

.

U.S. NUCLEAR REGULATORY COMMISSION

REGION I

Docket No.:

50-293

Report No.:

50-293/88-21

Licensee:

Boston Edison Company

Pilgrim Nuclear Power Station

RF0 #1, Rocky Hill Road

Plymouth, Massachusetts 02360

Facility:

Pilgrim Nuclear Power Station

Location:

Plymouth, Massachusetts

Dates of Inspection:

August 8-24, 1988

Inspectors:

(See Attachment E)

_ _ ' 7/89

i whc e T.

Approved By:

'

nn

Dw

-

A. Rt.ndy Blough, Ch'ief

~f

Dath

Reactor Projects Section No. 3B

Division of Reactor Projects

Inspection Summary:

Areas Inspected:

Integrated Assessment Team In:,pection to assess the degree

of readiness of licensee management controls, programs, and personnel to sup-

port safe restart and operation of the plant.

The scope of the inspection is

further detailed in Section 2.2.

Results:

The team concluded that licensee management controls, programs, and personnel

are generally ready and performing at a level to support safe startup and

operation of the facility.

Results are further summarized in Sections 1.0

(Executive Summary) and 2.3 (Summary of Findings).

.

l

O

'

O

l

t

.

l

.

e

l

4

1

)

l

TABLE OF CONTENTS

Page

ACR0NYMS.......................................................

iv

1.0 EXECUTIVE SUMMARY.........................................

1

2.0

INTRODUCTION..............................................

2

2.1

Background...........................................

2

2.2 Scope of Inspection..................................

3

2.3 S u mm a ry o f I AT I R e s u l t s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

4

2.3.1

Overall

Summary............................

A

2.3.2

Summary of Results by Functional Areas.....

5

2.4 Licensee Commitments.................................

9

2.4.1

Procedure Validation and Training..........

9

2.4.2

Identifying Procedure Changes Requiring

Training.................................

9

2.4.3

Temporary Modifications....................

9

2.4.4

Operations Review Committee................

10

2.4.5

Maintenin

10

e.

.........................

2.4.6

Survei,ionce..

10

.

.....................

2.4.7

Formalizing Personnel Qualification

Reviews..................................

11

2.4.8

Mission, Organization and Policy Manual....

11

2.4.9

Familiarizing Workers with t'xpected

Radiological

Conditions..................

11

2.4.10

Control Room Human

Factors.................

11

3.0 DE TAI LS O F I N S P EC T ION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

12

3.1 Management 0versight.................................

12

3.1.1

Scope of Review............................

42

3.1.2

Organization...............................

12

3.1.3

Staffing...................................

15

3.1.4

Qualifications..... . .....................

16

3.1.5

Administrative Policy and Procedures.......

18

3.1.6

Communications and Observations............

19

3.1.7

Conclusions.......................

.

20

......

i

. _______

.

e

Table of Contents (Continued)

Page

3.2

Operations...........................................

21

3.2.1

Scope of Review............................

21

3.2.2

Conduct of Operations......................

21

3.2.3

Shift Staffing and Overtime Controls.......

23

3.2.4

Procedure Va11dation.......................

24

3.2 5

Temporary Modification Controls............

25

3.2.6

Required Reading Books.....................

28

3.2.7

Logs.......................................

29

3.2.8

Timely Update of Lif ted Lead / Jumper Log. . . .

29

3.2.9

Tagouts and Operator Aids..................

31

3.2.10

Plant Tours and System Walkdowns...........

31

3.2.11

Conclusions................................

34

3.3

Maintenance..........................................

36

3.3.1

Scope of Review............................

36

3.3.2

Observations and Findings..................

36

3.3.3

Conclusions................................

50

'

3.4 Surveillance Testing and Calibration Control.........

52

3.4.1

Scope of

Review.........................

52

..

3.4.2

Observations and Findings..................

52

3.4.3

Conclusions................................

61

3.5 Radiation

Protection.................................

63

3.5.1

Scope of Review............................

63

3.5.2

Observations and Findings..................

63

3.5.3

Conclusions................................

73

3.6 Security and Safeguards...... .......................

75

3.6.1

Scope of Review............................

/%

3.6.2

Observations and Findings..................

75

3.6.3

Conclusions................................

82

11

_

O.

6

Table of Contents (Continued)

Page

3.7

Training.............................................

83

3.7.1

Scope of Review............................

8'.

3.7.2

Observations and Findings..................

83

3.7.3

Conclusions................................

88

3.8 Fire Protection......................................

89

3.8.1

Scope of Review............................

89

3.8.2

Observations and

Findings..................

89

3.8.3

Conclusions................................

90

3.9 Engineering Support..................................

91

3.9.1

Scope of Review............................

91

3.9.2

Observations and Findings..................

91

3.9.3

Conclusions................................

93

3.10 Safety Assessment / Quality Verification...............

94

3.10.1

Scope of Review............................

94

3.10.2

Nuclear Safety Review and Audit Committee..

94

3.10.3

Operations Review Committee................

97

3.10.4

Quality Assurance Audit and Surveillance

Programs.................................

102

3.10.5

Corrective Action Process and Programs.....

104

3.10.6

Conclusions................................

115

4.0 UNRESOLVED ITEMS..........................................

117

5.0 MANAGEMENT MEETINGS.......................................

118

Appendix A - Entrance Interview Attendees......................

A-1

Appendix B - Exit Interview

Attendees..........................

B-1

Appendix C - Persons Contacted.................................

C-1

Appendix 0 - Documents Reviewed................................

D-1

Appendix E - IATI Composition and Structure................

E-1

...

.

Appendix F - Resumes...........................................

F-1

Appendix G - September 1, 1988 Letter from NRC to Commonwealth

of Massachusetts................................

G-1

Appendix H - September 6, 1988 Letter from Commonwealth of

Massachusetts to NRC...........................

.

H-1

111

. _ _ _ _

.

.

ACRONYMS

ALARA

As Low As Reasonably Achievable

-

ANSI

American National Standards Institute

-

ASME

American Society for Mechanical Engineers

-

BECo

Boston Edison Company

-

BEQAM

Boston Edison Quality Assurance Manual

-

CAS

Central Alarm Station

-

CQI

Commercial Quality Item

-

Core Spray (System)

CS

-

CST

Condensate Storage Tank

-

DC

Direct Current

-

i.

Detaiied Control Room Design Review

DCRDR

-

DG

Diesel Generator

-

DR

Deficiency Reports

-

E0P

Emergency Operating Procedures

-

E0

Equipment Operator

-

EPRI

Electric Power Research Institute

-

EQ

Environmental Qualification

-

ESF

Engineered Safety Feature

-

r

Engineering Service Roquest

-

'

Failure and Malfunction Reports

F6MR

-

For Your Information

FYI

-

General Employee Training

GET

-

iv

Y'

.

.

Acronyms

HP

Health Physics

-

HPES

Human Performance Evaluation System

-

HSA

Housekeeping Service Assistance

-

IATI

Integrated Assessment Team Inspection

-

I&C

Instrumentation and Control

-

ICA

Immediate Corrective Actions

-

INPO

Institute of Nuclear Power Operations

-

IST

In-Service Testing

-

LCO

Limiting Condition for Operations

-

LL/J

Lifted Lead / Jumper

-

LSFT

Logic System Functional Test

-

M&TE

Measuring and Test Equipment

-

MCAR

Management Cnrrective Action Requests

-

MCIAP

Material Condition Improvement Action Plan

-

MO&AT

Management Oversight and Assessment Team

-

MOP

Mission, Organization and Policy Manual

-

MPC

Maximum Permitted Concentration

-

MR

Maintenance Request

-

MSC

Maintenance Summary and Control

-

MSTP

Master Surveillance Tracking Program

-

MWP

Maintenance Work Plan

-

NCR

Nonconformance Report

-

NED

Nuclear Engineering Department

-

h0P

Nuclear Organization Procedures

-

y

.

.

Acronyms

NRC

Nuclear Regulatory Commission

-

NRR

Office of Nuclear Reactor Regulation

-

NSRAC

Nuclear Safety Review and Audit Committee

-

NWE

Nuclear Watch Engineer

-

OMG

Outage Management Group

-

ORC

Operations Review Committee

-

P&ID

Piping and Instrument Diagram

-

PCAQ

Potential Condition Adverse to quality

-

PDC

Plant Design Change

-

PI

Pressere Indicator

-

PM

Preventive Maintenance

-

PNPS

Pilgrim Nuclear Power Station

-

PCIS

Primary Containment Isolation System

-

Quality Assurance Department

QAD

-

RCIC

-

Reactor Core Isolation Cooling

RETS

Radiological Environmental Technical Specifications

-

RHR

Residual Heat Removal (System)

-

RO

Reactor Operator

-

ROR

Radiological Occurrence Report

-

RP

Radiation Protection

-

'

RWP

Radiation Work Permits

-

SAA

Simulated Automatic Actuation

-

SAS

Secondary Alarm Station

-

vi

.

.

Acronyms

SBLC

Standby Liquid Control (System)

-

SDR

Security Deficiency Reports

-

SE

Safety Evaluations

-

SEG

Systems Engineering Group

-

SES

Senior Executive Service

-

SFR

Supplier Finder Reports

-

SGI

Safeguards Information

-

SI

Station Instruction

-

SRO

Senior Reactor Operator

-

STA

Shift Technical Advisor

-

SVP-N

Senior Vice President - Nuclear

-

TM

Temporary Modification

-

TS

Technical Specifications

-

VP-NE

Vice president - Nuclear Engineering

-

WIP

Workforce Information Program

-

WPRT

Work Prioritization Review Team

-

vii

.

.

.

1.0 EXECUTIVE SUMMARY

In response to NRC concerns ever longstanding issues regarding the manage-

ment effectiveness of the Boston Edison Company (BECo) in the operation of

the Pilgrim facility, the licensee agreed to maintain the plant in a

shutdown

condition

following

operational

events which occurred on

April 11-12, 1986.

The NRC conf trmed the licensee's agreement in Con-

firmatory Action Letter (CAL) 86 10.

The CAL, as supplemented in an

August 27, 1986 letter, also confirmed that the licensee would develop a

comprehensive plan to address those concerns and perfonn an in-depth self-

assessment of the effectiveness of that Plan.

On June 25, 1988, the

licensee reported it had completed these activities to the extent that an

NRC review was appropriate. In order to assess the status and results of

BECo's corrective actions, the NRC performed an independent review of the

effectiveness of the licensee's management controls, programs and person-

nel during an Integrated Assessment Team Inspection (IATI) conducted

August 8-24, 1988.

The Team consisted of an SES-level manager, a Team leader, and members of

the NRC Region I

and Headquarters staff.

The inspection team also

included two obseners representing and appointed by the Commonwealth of

i;assachusetts.

These observers had access and input to all aspects of the

inspection as provided by the established protocol.

The areas reviewed

during the

inspection included operations, maintenance, surveillance,

radiation protection, security, training, fire protection and assurance of

quality.

The Team reported directly to the Regional Administrator of

Region I.

Overall, the Team concluded with high confidence that BECo management

controls, programs, and personnel were generally ready and performing at a

level to support safe startup and operation of the Pilgrim Nuclear Power

Station.

Further,

although the Team identified certain items which

require licensee actions or evaluations, there were no fundamental flaws

found in the licensee's management structure, management performance,

programs, or program lmplementation that would inhibit its ability to

assure reactor or public safety during plant operation.

__

_ _ _ _ _ _ _ _ _ _ _

.

o ,

2

.

2.0 INTRODUCTION

This report details the findings, conclusions and observations of NRC's

Integrated Assessment Team Inspection conducted at the Pilgrim Nuclear

Power Station (PNPS) on August 8-24, 1988. The results of this inspection

are to be considered during NRC staff's deliberations as it reaches its

decisior. regarding a restart recommendation to the NRC Commissioners.

2.1 Background

The NRC's 1985 Systematic Assessment of Licensee Performance (SALP)

found programmatic weaknesses in several functional areas at the

Pilgrim Nuclear Power Station and noted that, historically, the

licensee could not sustain performance improvements once achieved. A

'

special NRC Region I diagnostic team inspection was subsequently per-

formed in February and March 1986 to evaluate facility performance.

This inspection, which included monitoring plant activities on a

24-hour basis, confirmed the 1985 SALP and concluded that poor

management control and incomplete staffing contributed to the poor

performance.

Following several operational events, Boston Edison Company (BECo)

shutdown PNPS on April 11-12, 1986.

The NRC subsequently issued a

Confirmatory Action Letter (CAL) on April 12, 1986, and a supplement

on August 27, 1986, maintaining the ple.nt shutdown and requiring that

the licensee obtain NRC approval prior to restert.

The central

issues in the CAL, as supplemented, involved the effectiveness of

licensee management of the facility and technical concerns.

SALP evaluations continued during the shutdown, and improvements were

noted during the 1986 SALP period, although the rate of change was

slow.

Several factors inhibited progress, including continued man-

agement changes and prolonged staf fing vacancies.

Good performance

was noted in four areas:

emergency planning, outage management,

corporate engineering support and licensed operator training.

The

success in these areas reflected a high level of corporate management

attention and substantial resource commitments.

The licensee also

had made signi'icant plant hardware improvements, including Mark I

Containment performance enhancements.

,

!

Consistent with the CAL and its supplement, BECo has addressed the

specific technical

issues, developed and submitted the Pilgrim

Nuclear Power Station Restart Plan and performed a detailed self-

assessment of readiness for restart.

The NRC staff reviews of these

items are complete.

The licensee has also submitted a Power Ascen-

sion Test Program, for which the staff review is ongoing.

.

- -

- _

_

. _ _

___- - -

. _ _ _ . _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

__ ___

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

O

3

NRC subsequently completed a SALP evaluation for Pilgrim covering the

period February 1,1987 to May 15,1988.

It concluded that licensee

managenient initiatives are generally successful in correcting staff-

ing, organization, and material deficiencies. Programmatic perform-

ance improvements were evident in areas previously identified as

having significant weakness and in areas that the licensee's self-

assessment process

identified

as

warranting

further management

attention.

The NRC Confirmatory Action Letter (CAL) of April 1986 required the

NRC to perform a review to assess BECo's corrective actions. In con-

junction with an augmented inspection program and as part of a con-

tinuing effort to monitor BECo's program improvements, the NRC

planned this IATI to independently measure the effectiveness and

readinass of the licensee's management controls, programs and per-

sonnel to support safe restart of the facility. A Restart Readiness

Assessment Report that includes staff assessment results will be

prepared by the NRC in conjunction with development of an NRC staff

recommendation regarding plant restart.

2.2 Scope of Inspection

The IAT inspection was performed to provide an indepenuent, in-depth

assessment of the degree of readiness of licensee management con-

trols, programs, and personnel to support safe restart and operation

of the Pilgrim Nuclear Power Station (PNPS).

The inspection covered

a variety of functional areas, including operations, maintenance,

surveillance, radiation protection, security, training, fire protec-

tion, and assurance of quality.

Particular emphasis was placed on

management ef fectiveness and on the status of the licensee's recent

program improvements in maintenance.

The inspection consisted of

interviews with licensee personnel, plant tours, observations of

plart activities, and selective examinations of procedures, records,

and documents.

The Team also directly observed ongoing

plant

activities on ali shifts from August 10-13, 1988.

The 15-member Team consisted of a senior manager, inspection team

leader, five shift inspectors, and several specialist inspectors from

both NRC Region I and the NRC Of fice of Nuclear Reactor Regulation

(NRR).

Two representatives from the Commonwealth of Massachusetts

were also on the Team as observers throughout the inspection.

The

team roster and member resumes are attached as Appendices E and F to

this report.

Onsite IATI preparation, which included site familiarization and

plant tours, was conducted during the week of July 18, 1988. The Team

was onsite full-time from August 8 through 19, 1938. Some IATI mem-

bers were on site during the documentation period of August 20-24,

1988.

Attendees at the entrance and exit interviess are listed in

Appendices A and 8, respectively. Senior licensee managers contacted

during the course of the inspection are listed in Appendix C.

Many

other persons at all levels of the organization were also contacted

or interviewed.

.

.

4

The licensee was not p/esented with any written material by the NRC

during this inspection. The licensee indicated that no proprietary

material was presented for review during this inspection.

2.3 Summary of IATI Results

2.3.1

Overall Summary

The T2am concluded, with high confidence, that licensee

management controls, programs, and personnel are generally

ready and performing at a level to support safe startup and

operation of the facility. Technical items requiring reso-

lution or completion prior to restart are being addressed

and tracked by the licensee.

The Team identified a rela-

tively small number of additional items for which licensee

actions or evaluations appear appropriate; during the

inspection, the licensee made acceptable commitments in

these areas.

There are currently no fundamental flaws in

the licensee's management structure, management perform-

ance, programs,

or program

implementation

that would

inhibit its ability to assure reactor or public safety dur-

ing plant operation.

The inspection generally confirmed the results of the SALP

report for February 1,1987 through May 15, 1988, as well

as validating the general SALP conclusion that performance

was improving at the end of the SALP period.

Further,

licensee performance appeared to be consistent or improving

in all functional areas examined during the IATI, with the

current level of achievement for overall safety performance

equal to or better than that described in the SALP.

For

maintenance and radiation protection, the performance is

noticeably improved.

The inspection generally confirmed the effectiveness of

various licensee self-improvement programs and of the

licensee's self-assessment process.

The Team identified

relatively few issues that had not been previously identi-

fied by the licensee.

In the interest of continually

improving its self-assessment process, the licensee should

evaluate those cases where NRC either identified new issues

or assigned a higher sense of prior;ty than identified by

the licensee.

The inspection confirmed that important organization and

attitudinal changes had occurred since 1986. Of particular

concern to NRC during the diagnostic inspection in 1986

were several f actors inhibiting progress.

These included:

_

O

5

1)

Incomplete staffing, especially of operators and key

mid-level supervisory personnel;

2)

The prevailing licensee view that improvements to date

had corrected the problems identified;

3)

Reluctance by Itcensee management to acknowledge some

problems identified by NRC; and

4)

Dependence on third parties to identify problems

rather than implementing an offective licensee program

to identify weaknesses.

The Team found these inhibitors to be substantially re-

moved, and noted that a significantly improved nuclear

safety ethic exists at management levels and is developing

successfully at the worker level.

Based on a review of the management structure, staffing,

goals, policies and administrative controls, the Team con-

cluded that the licensee has an acceptable organization and

administrative process, with adequate management and tech-

nical resources to assure that the plant can be operated in

a safe and reliable manner during normal and abnormal con-

ditions.

Further, this performance-based inspection pro-

vided an integrated look at overall management effective-

ness in ensuring high

' andards of nuclear safety.

The

overall conclusions o#

is inspection confirm facility

management effectivene

especially its ability to perform

self-assessment functh

to improve performance, and to

3,

raise nuclear safety awareness and attitudes throughout the

organization.

2.3.2

Summary of Results by Functional Area

Within each functional

area,

conclusions were reached

including the identification of various strengths and weak-

nesses. Those are summarized below.

The basis for these

items, as well as the many significant observations made by

the Team, are explained in Section 3 of this report.

2.3.2.1

Operations

Strengths

Experienced and knowledgeable senior licen-

--

sed operators

,

O

e

6

Effective shift turnover

--

Excellent plant housekeeping

--

Weakness

Lauk of thoroughness and attention to detail

--

in validation and training of Emergency

Operating satellite procedures

2.3.2.2

Fire Protection

Strengths

Effective program staffing and supervision

--

Effective

prioritization,

control,

and

--

tracking

of

fire

protection

equipment

maintenance

Weaknesses

None

2.3.2.3

Maintenance

Strengths

Good organization and structure

--

Thorough program procedures

--

Clear maintenance section internal communi-

--

cations and interactions

Good control and support of field activities

--

Weaknesses

Examples of poor implementation of planning

--

.

for post-work testing

Poorly controlled storage of Q-listed items

--

at

two

locations

outside

the warehouse

_ _ _ _ _ _

.

.

7

2.3.2.4

Radiological Controls

Strengths

Effective

use

of

a

maintenance

health

--

physics (HP) advisor

A well-organized training program

--

Weaknesses

Examples of a lack of continuity and pro-

--

ficiency in certain highly specialized jobs

because

of

frequent

technician

rotation

Indications of weak vertical communications

--

within the HP group

2.3.2.5

Surveillance

Strength

_

Management commitment to improve an already

--

satisfactory program

Weakness

Incomplete resolution of proper frequency

--

and scheduling of once per-refueling outage

tests 2.3.2.6

Security

Strength

Overall management attention

--

Weaknesses

None

.

2.3.2.7

Training

.

Strengths

Excellent management support for operator

--

training programs

-

,-

.

.

8

Strong relations between the plant opera-

--

tions and training departments

Weakness

Lack of a defined process to assure timely

--

identification and implementation of train-

ing needs resulting from newly approved or

revised procedures

2.3.2.8

Engineering Support

Not directly reviewed. No specific strengths

--

or weaknesses identified

2.3.2.9

Safety Assessment / Quality Verification

Strengths

Nuclear Safety Review and Audit Committee

--

(NSRAC) composition,

plant tour program,

frequency and location of meetings, open

forum, and focus of reviews

Attitude and performance toward identifying

--

problems

Effective, meaningful communications between

--

the Quality Assurance and plant Operations

departments

Weaknesses

Operations Review Committee does not perform

--

an effective independent group review of

operations

and

Technical

Specification

violations

Multiplicity of corrective action programs

--

without centralized tracking

Poor tracking of Potential Condition Adverse

--

to Quality (pCAQ) reports

_ _ _ _ _ _ _ _

,

.

9

2.3.2.10 Management Oversight

Strengths

Well-defined

organization,

incorporating

--

appropriate span-of-control

and including

highly qualifted, experienced managers in

key positions

Well-defined and well-conceived corporate

--

goals

Weaknesses

None

2.4 Licensee Commitments

During the IAT inspection, the licensee made certain commitments to

the inspection feam. These commitments relate to licensee corrective

or enhancer.ent actions planned in response to Team findtegs or con-

cerns.

These commitments, summarized below, are discussed in more

detail in subsequent sections of this report, shown in parentheses.

Commitments were confirmed during the exit interview. The status of

these issues will be reviewed by the NRC prior to any restart of the

plant (83-21-01).

2.4.1

Procedure Validation and Training (Section 3.2.4)

isy restart, the licensee will confirm effective implementa-

tion of all of f-normal and E0P satellite procedures that

have been substantively revised during this outage.

2.4.2

Identifying Procedure Changes Requiring Training (Section

3.7.2.1)

Before restart, the licensee will implement a process to

l

allow more timely identification of new procedures and

l

procedure changes which require training.

.

2.4.3

Temporary Modifications (Section 3.2.5)

By restart, the licensee will either prepare a justifica-

tion for operation for each active temporary modification

or apply the temporary modification extension request

process to all temporary modifications, including those

with outstanding engineering seevice requests.

O

8

10

2.4.4

Operations Review Committee (ORC) (Section 3.10.3)

Prior to restart, in order to strengthen its operational

focus, the ORC will begin to:

(1) review plant incident

critiquas; (2) review licensee event reports before their

issuance to NRC; (3) review failure and malfunction reports

on a regular basis; and, (4) provide for a monthly presen-

tation and discussion of plant operations as a specific

agenda item.

2.4.5

Maintenance

Before restart, the licensee will re-evaluate all

--

priority 3 maintenance requests to ensure that they

have

been

properly

scheduled.

(Section

3.3.2.4)

The licensee will complete training addressing the

--

revised post-work testing program by September 9, 1988.

'

(Section 3.3.2.6)

The licensee will resolve the inability to align

--

valves in the Torus Water Makeup Line in accordance

with current operating procedures and drawings prior

to restart.

(Section 3.3.2.4)

The licensee will issue a procedure to provide appro-

--

priate controls for the

"Q"

oil storage facility by

September 7, 1988, and perform an evaluation of the

possible addition of "non-Q" oil to

"Q" equipment and

its potential effect.

(Section 3.3.2.3)

The licensee will complete, before restart, the dis-

--

position of a Potential Condition Adverse to Quality

(PCAQ) identifying the need for a review of Commercial

Quality Item procurement documents for consistency

with approved engineering specific 3tions.

(Section

3.3.2.3)

2.4.6

Surveillance

.

Before restart, the licensee will review and evaluate

--

the once per-refueling-outage surveillance tests to

determine if they should be repeated to enhance the

assurance of system operability and document the basis

for its decision.

(Section 3.4.2.1)

Before restart, the licensee will provide the tech-

--

nical basis for the current test frequency of the

Reactor Core Isolation Cooling (RCIC) System logic

System Functional Test (LSFT) on the initiation logic.

(Section 3.4.2.2)

. _ _ _ _ _ _ _ _ _ .

e

0

11

2.4.7

Formalizing Personnel Qualification Reviews

The licensee will verify before restart the qualifications

of all personnel within the organization required to meet

ANSI 18.1-1971; and, prior to completion of the power

,

ascension program, will have a formalized process in place

to ensure future auditability.

(Section 3.1.4)

2.4.8

Mission, Organization and Policy (MOP) Manual

The licensee will issue MOP policy instructions prior to

restart and the organizational position descriptiens prior

to completion of power ascension.

(Section 3.1.5)

,

2.4.9

Familiarizing Workers with Expected Radiological Conditions

Before restart, the licensee will provide training and

briefings to the appropriate plant staff regarding expected

radiological conditions resulting from plant operation and

hydrogen addition.

(Section 3.5.2.14)

2.4.10

Control Room Human Factors

The licensee will evaluate control room human factors dur-

ing the power ascension program and include an update

regarding the schedule and scope of "Paint, Label and Tape"

items in their report to the NRC at the completion of the

l

Power Ascension Program.

(Section 3.9.2)

1

i

i

,

1

!

.

-.-

_ _ - _ _ _ _ _ - _ _ _ _ _ _ _ - _ _ _

. _ _ _ _

.

.

12

-

3.0 DETAIL 3 0F INSPECTION

The following sections contain the scope of inspection, the detailed

i

findings, and the conclusions for each functional area the Team assessed.

3.1 Management Oversight

3.1.1

Scope of Review

The IATI assessed the organizational structure currently in

place at the Pilgrim Nuclear Power Station (PNPS).

The

assessment also included the administrative processes in

place to control and coordinate the activities and actions

'

affecting safe and reliable operation of the PNPS. Other

areas inspected included the adequacy of staffing, qualifi-

cations of personnel, and mechanisms to enhance and promote

stability in the organization's technical and managerial

staff.

Several management meettags were observed by Team members

to assess the interactions of managers and the effective-

ness of the policies and procedures being implemented.

Continual observations were made and shared by Team members

to augment findings and conclusions in the effectiveness of

.

the organization, management controls, and communications

I

throughout the functional areas.

The Team members inter-

'

viewed a cross-section of personnel at all levels of the

'

organization to determine if the overall attitude towerd

performance of safety-related activities has

improved.

These obrervations and interviews also provided the Team

with insight into the worker perception of management

policies,

involvement, effectiveness and its resulting

impact on safety,

j

i

3.1.2

Organization

The NRC staff noted in the most recent SALP report No.

,

50-293/87-99

for February 1, 1987 through May 15, 1983,

'

that an organizational transition had taken place.

The

report also noted tnat several temporary changes, including

i

.

numerous changes in personnel, had been made to strengthen

planning, control and performance at PNpS. Many of these

'

temporary changes were incorporated into a permanent reor-

ganization in February 1988. The licensee continued to re-

fine the new organziation and control

process through

!

t

,

, , _ _ - , . . - - - - _ . _ - - - . ,

- .

- . - - ,

n-

, - - , ,

.

_ _ ____________ -.

_ _ _ _ _ _

,

.

,

,

13

.

July 1988, notified NRC of the reorganization, and subse-

quently requested an amendment in August 1988 to the admin-

istrative section of its Technical Specifications (TS) to

reflect the new organization. The notification and request

were

in accordance with the PNPS TS, Section 6.2.C.

"Changes to the Organization," which allows organizational

a

changes to be implemented without prior NRC approval, pro-

"

vided notification is made and a subsequent license amend-

ment request is submitted for NRC review and approval.

I

he organization assessed during this inspection is the

j

subject

of

the

licensee's

amendment

request

dated

August 1, 1988, and approved by the Senior Vice President -

s

Nuclear (SVP-N) on August 4, 1988.

The discussion that

follows does not describe in complete detail the entire

,

i

organization, focusing instead on that portion that affects

j

the functional areas being evaluated during this inspection

(See Figure 1).

The results of this inspection will be

,

considered in NRC's review of the licensee's amendment

'

request.

4

I

The Team noted that the licensee has incorporated a balance

]

between the number of management levels from the first-line

supervisors to the SVP-N and the span of control for each

,

i

functional unit. The SVP-N has the Station Director, Vice

l

President

Nuclear Engineering (VP-NE), Emergency Pre-

-

paredness Department manager and Quality Assurance Depart-

t

}

mert manager reporting directly to him. The two department

managers report directly to the SVP-N to assure that inde-

pendence and appropriate management attention are provided

based on their functional requirements and responsibilities.

The committee charged with offsite satety, the Nuclear

i

Safety Review and Audit Committee (NSRAC), reports directly

}

to the SVP-N. The committee for onsite safety review, the

!

Operations Review Committee (ORC), reports directly to the

Station Director.

The reporting of the of fsite committee

!

to the SVP-N and the onsite committee to the Station

Director are appropriate based on their responsibilities.

'

Details on these standirg committees, their functional

requirements, responsibilities and accountabilities, are

contained in Section 3.10 of this report.

,

!

!.

The VP-NE has two department-level managers reporting

Jirectly to him.

These departments are the Nuclear Engi-

i

neering Department av the Manatement Services Department

i

both of which are located offsite.

The Station Director

1

has four department-level managers reporting directly to

l

him:

the Plant Support Department, Plant Manager (Opera-

tions), Planning and Outage Department, and the Nuclear

1

!

Training Department.

1

.,

,.

- , _ . - - , - -

r

_ - _ . . _ _

_.

__

_

_ _ _ _

_ _ _ _

.-

_.

.

q

.

.

I

<

-l

Chairsdn, Board of Directcr5

and CEO

Senior Vice President -

Nuclear

1

Director - Spec 141 Projects

14uclear Safety Review and Audit Coasnittee

I

i

W

4

l

Wice President -

Quality Assurance

Erergency Planning

Station Direc ar

rauclear Engineering

Department flanager

Departinent m nager

i

I

1

,

l

Nuclear Engineering

14uclear Management

Operations fteview

Plant Department

Plannirs &

Department stanager

Services Department

Consmittee

(Plant N nager)

Outage

Department

,

'

Manager

.

tianager

I

,

l

'

Plant Support

Wuclear Training

,

i

J Department

-l

Departs,aent

-

"*"*9'#

.

9"

Manager

Plant Operations

l

'

1

Sc tion Manager

Figure 1.

BOST0i1 E0150ri C0ftPAf4Y - PILGRIF. ORGAf41ZAT104

'

l-

- - _ ~ , . - -

.

.-.

,.

-

.-

-

.- -

_

, -

_.

,

n

15

The senior manager of the functional areas is at the

department level, which is then subdivided into section

levels and division levels. The first-line supervisors, in

some cases senior supervisors, report to the division

managers.

The station organization, now under a Station Director who

has no direct corporate (i.e., off-site) responsibilities,

represents a substantial change frcm previous organiza-

tions.

The current structure was instituted to strengthen

management attention to plant activities. The narrowing of

the span of direct control and responsibility of the Plant

Manager allows a more focused management and control of

operational activities, which should result in the enhance-

ment of safe and reliable operation.

The

martments

reportir.g to the VP-NE have been restructured r ., 1 more

even distribution of responsibilities.

The Team concluded that the current organizational struc-

ture provides for an appropriate distribution (span) of

responsibilities and accountabilities for the activities

being performed by the functional units within it.

The

depth (number) of managers in the functional areas should

contribute

to

improved performance and organizational

stability by providing managers with increased opportun-

ities to participate in professio.tal technical and manage-

ment development programs and by increasing the framework

for career growth.

The Team also concluded that the redistribution of func-

tional responsibilities and increased depth in management

provides the framework necessary to enhance stability and

support safe and reliable operation at PNPS.

The evidence

for these changes thus far has been management's effective-

ness in creating a much-improved nuclear safety ethic and

in improving the functional areas described in the subse-

quent sections of this report.

3.1.3

Staffing

The most recent SALP Report (No. 50-293/87-99) indicated

that the allocated staffing levels were significantly

higher than in the past.

The Nuclear Organization is cur-

,'

rently authorized a staffing level of 985. Approximately

90'. of the autho-ized positions are filled, of which 86*4

are licensee personnel; the remaining 4*4 cc.mprise contract

,

personnel. Licensee personnel fill all Key positions from

'

Section Managers and above, with less than

15*. of the

remaining managers and first-line supervisor positions

filled by contractors or licensee personnel in acting

,

capacities.

I

_ - -__ - - -- -_.

_ _ _ _ _ _ _ _ _ _ _ _ _ _____

_ _ _ _ _ _ _ _ _ _ _ _

______ _

,

16

Increased staffing in all levels of the Radiologica', and

Maintenance Sections are examples of how the licensee has

provided the necessary management attention and resources

to areas that need them.

The increased staffing, specif-

ically at the craf t and technician level, appears f.uffic-

ient to allow for a planned and controlled preventiv, main-

tenance program that should result in overall saf2ty en-

hancement.

The increased staffing levels also allow for

training on a routine schedule.

The Team concluded that the authorized staffing has been

filled to a level acceptable for the licensee to perform

all the necessary functions for all

plant canditions,

including operations.

This finding is reinforced by the

evidence of improvements in the functional areas, described

in the subsequent portions of this report.

3.1.4

Qualifications

The PNPS TS, Sectirn 6.4, "Facility Staff Qualifications,"

requires that PNPS personnel meet tSe requirements of the

American National Standards Institute (ANSI) N18.1-1971,

"Selection and Training of Personiel for Nuclear Power

Plants."

The TS also requires that the Radiation Protec-

tion Manager shall meet or exceed the qualifications of

Regulatory Guide 1.8,

"Quali fica tion and Training for

Personnel at Nuclear Power P1'.nts," September 1975.

The Team audited resumes and position descriptions of key

managers and other selec.ed pe c.onnel throughout the organ-

ization. Their educational ana experience backgrounds were

compared with the requiremerts delineated in ANSI N18.1-

1971Property "ANSI code" (as page type) with input value "ANSI N18.1-</br></br>1971" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process., with special attention on t.he management experience

of key personnel. No deficiencief, were identified relating

to the qualification requirements of the ANSI standard.

More significantly, the Team noted the staffing of key

management positions with persornel having extensive and

successful management experience.

During its review, the Team fouid that some resumes needed

updating, and that no formal, detailed instructions or

guidance in establishing qualifications were available. The

Team reviewed a Quality Assurance Department (QAD) audit

report of the organization's administrative controls which

was conducted June 22 througn July 22, 1988 and which

resulted in similar findings.

The report, Audit Report

8S-25, "Administrative Controls," dated August 18, 1938,

,

e

.

17

indicated that personnel qualifications were audited by the

QA0 to determine compliance with the ANSI N18.1 require-

ments for the organizational positions held.

No defici-

encies were identified as the result of the QA0 audit.

The

report did, howeser, provide a recommendation consistent

with the NRC inspector's finding. Specifically, Reccmmen-

dation No. 88-25-03, notes the need to update resumes,

develop guidelines and procedures for documenting qualifi-

.

cation status, and maintain retrievable files.

The licensee has committed to the Team to reverify the

qualifications of all personnel within the. organization to

.

confirm they comply with ANSI N18.1-1971 prior to restart

and to have a process in place prior to completion of the

Power Ascension Program to ensure future auditability of

personnel qualifications.

Within the scope of the NRC review, the Team deter-

mined that the licensee's personnel are generally well

qualified for the positions hsid within the organization.

The licansee's commitment to reverification of all per-

tonnel qualifications prio: to restart will provide addi-

tional assurance of full compliance relating to personnel

qualifications.

The results of the IATI effort in assessing the adequacy of

the staffing and qualifications of the PNPS organization is

consistent with the overall facility evaluation in the most

recent SALP report (No. 50-293/87-99).

It noted the addi"

tion of management personnel who lack extensive commercial

nuclear power plant operating experience.

However, as

acted above, recent changes have resulted in the addition

of personnel in key management positions with extensive and

successful management experience, much of which is in

nuclear areas.

Also, many mid-level management positions

are held by individuals who have extensive Pilgrim NPS (or

other boiling water reactor) experience.

The Team con-

cluded that the combination of commercial nuclear power

plant operating experience in the organization with the

increased management capebility provides the qualifications

necessary to support safe and reliable operation at PNPS.

In the event of a restart authorization, licensee safety

performance will be closely monitored by the NRC during the

Power Ascension Program.

_ _ _ _ _ _ _ _ _ - __ _ _ _ _

. _ _ _ _

,

,

18

3.1.5

Administrative Policy and Procedures

The licensee has a variety of procedures to provide policy,

control and coordination of organization activities. Cor-

porate policy is provided in the form of company Bulletins

maintained

in

a

Boston

Edison

Company Organizational

Manual. The manual includes information about the corpor-

ate organization, its policy statements, corporate instruc-

tions, and committees which affect the entire company,

including the Nuclear Organization.

The corporate level

policy specifically affecting the Nuclear Organization is

contained in a Mission, Organization and Policy (MOP)

manual.

The Nuclear Organization Procedures (NOPs) provide guidance

for the control and coordination of the Nuclear Organiza-

tion. They include administrative pro edures affecting the

entire organization, as well as proceduret affecting func-

tional portions of the organization.

Each department also

has procedures in place specifier 11y for its functional

areas.

The Team reviewed several :0Ps to assure that the

guidance provided was current, reflected the organization

in place, and addressed coordinating activities within the

organization.

The Team also reviewed department-level

procedures to assure they included the current organiza-

tion, toals, department function, position descriptions,

qualti, cations required, responsibilities, and accounta-

bilities.

The Team concluded that the proceoures are, for the most

part, current.

They adequately identify corporate policy,

organization,

coordination,

functional

requirements,

i

responsibilities,

accountabilities,

and

qualifications

nacessary for the control and coordination of actions

within the organization.

The Mission, Organization and Policy Manual (MOP) is not

fully up to date; however, and is currently being revised

to accurately reflect current policy and to include all the

-

position descriptions within the organization.

The licen-

see has identified additional refin1ments in the organi a-

t

tional position descriptions to assure consistancy and to

provide accurate definitions of responsibilitias necessary

to assure accountability.

The licensee was previously

aware of this and has been working to finalize the updates.

The licensee committed to issue the revised MOP which

L

v

a

e

h

F

19

includes updated policy prior to restart and to complete

the organizational position description refinements before

,

the end of the Power Ascension Program. This commitment is

acceptable, based on the status of the other procedures

previously discussed which assure adequate administrative

controls.

3.1.6

Communications and Observations

Corporate policy for the Nuclear Organization 1.4 the MOP

manual includes, among its goals, the nced to strive to

raise standards of performance, for dedication to protec-

ting the environment and public, and for rigorous adherence

to procedures.

The Team, through its observations and

interviews, noted a positive change in the attitude toward

nuclear safety throughout PNPS.

This change is evident in

improved performance of safety-related activities.

These

improvements are indicated in the most recent SALP Report

(No. 50-293/87-99), and progress in the other functional

areas is addressed in this inspection report.

The Team

also noted during interviews that the corporate goal of

adherence to procedures has been conveyed to all levels of

the organization.

These c'sservations attest to manage-

ment's ef fectiveness in communicating corporate goals and

management's oversight in assuring that the goals are being

pursued.

The Team noted that the licensee established several mech-

anisms to assure adequate communications within the organ-

ization.

Meetings at all levels of the organization are

held on a routine basis.

Plant meetings are held every

morning to discuss plant status and to coordinate daily

,

activities. Several of tiase meetings were observed by the

4

Team to assess the interaction of the managers and the

resulting effectiveness. The Team concluded that the meet-

ings were effective and that safety-related activities are

being planned, scheduled, and prioritized in accordance

'

with their safety significance and plant status. These and

other observations by the Team indicate that teamwork at

the site is evident.

There are programs in place, such as

the Workforce Information Program (WIP), For Your Informa-

tion (FYI), and Management Oversight and Assessment Team

(MO&AT) to enhance management involvement, overall communi-

cations, and management visibility in the plant.

!

l

t

f

I

___ _ _ _ _ _

_

__

_ _ _ _ _ _

0

20

The licensee has also established a set of performance

indicators to track performance issues, restart issues,

plant condition reports, and activity status.

These per-

formance indicators are used as a management tool

to

measure

the

effectiveness

and

results

of established

programs.

The Team concluded, based on its evaluation of programs

in place, that communications throughout the organization

have improved, that teamwork is evident, and that corporate

goals are being conveyed to all levels of the organization.

3.1.7

Conclusions

The Team concluded that the licensee has an acceptable or-

ganization and administrative process in place with ade-

quate management and technical resources to assure that

pNPS can operate in a safo and reliable manner during

normal and abnormal conditions.

This conclusion is based

on the details discussed above,

th'e performance-based

inspection in the functional areas covered by the IATI, the

overall consistency in the findings of this inspection with

the most recent SALP (No. 50-293/87-99), and the plan for a

structured and controlled power ascension program prior to

operation.

This performance-bc

-d inspection of a wide range of func-

tional areas provic.c an integrated look at overall manage-

.

ment effectiveness in ensuring high standards of nuclear

safety. The overall conclusions of this inspection confirm

f acility management ef fectiveness, especially with respect

to management's ability to perform self-assessment func-

tions,

to make performance improvements, and to raise

nuclear

safety

awareness

and

attitudes

within

the

organization.

- _ _ _ __

.. .

_ _ _ _ _ _

__

_ _ _ _ _ _ _ _ _ _ _ _ _

- - - _ _ _ _ _ _ _ _ _ _ _

.____________

__

.

.

21

3.2 Operations

3.2.1

Scope of Reviev

i

The Team evaluated operations by observing how supervisors,

operators and staff performed in the control room and

throughout the plant.

The Team observed plant operations

during backshifts from August 10 through August 13, 1988,

and reviewed staffing levels to determine if they were

sufficient to support restart with minimal reliance on

overtime.

The ability to implement recently written E0P

satellite procedures and the quality of thesce procedures

were evaluated through a field walkdown of a procedure.

The implementation of administrative controls for opera-

tions was evaluated through inspections of overtime con-

trols, temporary modification controls, operator-required

reading, logkeeping, tagouts, and operator aids. The line-

up of two safety systems was independently verified by the

.

!

inspectors.

Housekeeping was observed during frequent

plant tours.

{

3.2.2

Conduct of Operations

The Team observed control reor,. operations en all shifts.

They were conducted in a formal manner, with effective

l

,

communications between

the operators

and

supervisors,

including repeat backs for certain functions. There was no

'

unnecessary traffic in the control

room.

Supervisors

briefed shift personnel on significant functions before

they occurred.

prior to energizing the recirculating pump

heaters, which could have produced smoke in the drywell,

'

the watch engineer thoroughly briefed to the reactor oper-

,

ator, equipment operator, and fire brigade leader,

t

The watch engineers, shif t supervisors, and reactor opera-

tors were knowledgeable about plant conditions and ongoing

work in the plant.

Shif t turnover briefings were thorough

i

and were followed by control room panel walkdowns. Attend-

i

ance at these briefings was inconsistent in that not all

wa:ch enginaars include other shift personnel, och as

health phytics shift workers in the pre-shift briefing.

The Teata observed that the health physics shift workers

receive separate briefings.

.ae Team discussed this prac-

t

tice with plant management, which stated that it was their

[

intent to include non-operations shif t workers in the pre-

!

t

!

shift briefing and that they would review its implementa-

t i o r, .

l

J

t

l

I

'

,

<

- - _ . _ - - _ _ .

--,

- _ -

__ _

_

.-

_

_ _ _ _ _ _ _ _ _ _

.

.

22

Control room operators received good support from the shift

technical advisors (STA), administrative assistants, and

other departments. The STA's were used in developing fail-

ure and malfunction reports (F&MR), and in the initial

followup of an EOD satellite procedure issue.

The admin-

istrative assistants do much of the administrative paper-

work and help to lessen traffic in the control room. There

was very good support of operations from other departments

in understanding and deciding che proper course of action

in response to F&MR events.

The Team accompanied several non-licensed equipment oper-

ators (E0's) on their tours.

The E0's performed their

plant tours in accordance with Procedure 2.1.16, "Nuclear

Power Operator Tour." Readings were taken and recorded, as

required. The operators also checked for abnormal condi-

tions,

such as vibrations, noise, leakage, odors, and

inadequate ventilation.

The E0's commented that they now

have more time to check general piant conditions on their

rounds beer.use the rounds are assigned to two E0's per

shift.

Previously, only one E0 made the plant tour.

The

E0's showed good regard for radiological protection and

ALARA practices. The operators were very familiar with the

plant, systems, and components, and were knowledgeable

about their duties and responsibilities.

The performance

by these operators demonstrated the effectiveness of the

non-licensed training program.

Watch engineers or operating supervisors accompany E0's on

plant tours at least once per week. Operations management,

including the chief ope atug engincar and operations

manager, were observed totring the control room frequently

and discussing plant status and evolutions with the watch

engineer.

i

The Team discussed the licentee's use of NRC's NUREG-1275,

"Operati.ig Ex9erience Feedback Report-New Plants" and ver-

iftad that licensee managemett had reviewed NUREG-1275

recommendations for applicabili'y,

BECo had independently

Initiated a number of improvemeats related to NUREG-1275

.

recommendations before they reviewed the ruort.

This

action was considered by the Team as a positiva example of

the quality of BEco self-improvement ef forts.

Some self-

identified improvement items include operator communica-

tions training, seminars to improve attention to detail,

splitting tours and revising tour sheets to improve equip-

ment operator performarce, and doing dry run training on

.

_ _ . _ _ _ _ _ _ _ _ _ _ _ . _ _ _ . _ _ _ _ _ _ .

_ _ _ _ _ _ _ _

_ _ _ _ _ _

._.

._ __ __ _

. - _________.-____ _-_______-____

. _ _ _

O

O

23

the pcwer ascension and alternate safe shutdown evolutions.

Some improvement items resulting from the NUREG review

include seeking a more positive method of performing on-

shift instructions, repeating all logic system functional

tests, and performing a comprehensive review of inadvertent

emergency safety feature (ESF) actuations.

The ESF actua-

tion review has resulted in several corrective actions.

In summary, the licensee conducted operations in a profess-

ional manner.

Operators are knowledgeable about

their

duties and plant conditions and management keeps an active

and effective oversight of operations.

3.2.3

Shift Staffing and Overtime Controls

The licensee's Ser.ior Reactor Operators (SRO) are ver/

experienced and strengthen the operations organization.

To take advantage of this experience, an extra SRO will be

t

assigned to each shift during the Power Ascension Test

Program. Only 8 Reactor Operators (RO) have unrestricted

licenses because the 14 newly licensed RO's are limited

pending on-watch training and reactivity manipulations dur-

'

ing the Power Ascension Program.

Therefore, the licensee

will initially staff a four-shift rotation during plant

restart. At an appropriate point after restart, the licen-

see will go to a six-shif t rotation of two SRO's and two

RO'S per shift.

There are also sufficient non-licensed

equipment operators to staff six shifts. STA's will work a

five-shift rotation for at least the not year.

These

staffing levels are considered adequate.

It should not be necessary to work ope ators in excess of

the overtime guidelines of NRC Generic Letter 82-12. Senior

i

plant management has been active in restricting overtime.

Procedure 1.3.6.7, "Use and Control of Overtime at PNPS,"

adopts NRC guidelines, provides procedural controls for

overtime hours, and requires advance approval of overtime.

The

inspector reviewed Operations Department overtime

records for the period of July 6,1988 to August 16, 1988.

l

During this period, there were only three occasions when

!

.

staff worked greater than 56 hours6.481481e-4 days <br />0.0156 hours <br />9.259259e-5 weeks <br />2.1308e-5 months <br /> in a 7-day period. Dur-

ing this period, there was one instance of overtime in

,

excess of NRC guidelines.

This occurred August 1 and 2

when a radwaste worker worked 28 hours3.240741e-4 days <br />0.00778 hours <br />4.62963e-5 weeks <br />1.0654e-5 months <br /> in a 48-hour period.

This worker had approval to work up to 60 hours6.944444e-4 days <br />0.0167 hours <br />9.920635e-5 weeks <br />2.283e-5 months <br /> that week

but did not have approval to exceed the 48-hour guideline.

This worker is not a licensed operator and was not doing

'

safety-related work. The licensee identitied this incident

and counseled the individual on overtime requirements.

_ _ _ _ _

o

24

l

3.2.4

Procedure Validation

The Team walked down Procedure 5.3.26, "Reactor Pressure

Vessel Injection During Emergencies," with a non-licensed

equipment operator who had been trained in the procedure,

i

The procedure involved connecting a fire water crosstie to

the residual heat ro;noval (RHR) system.

Minor procedure

(

errors were found. A drain valve labeled 1-DR-122 in the

l

field is referred to as 1-DR-121 and the fire water storage

'

tank low level alarm is referred to as annunciator B-7,

whereas it is actually 0-3.

Also, the procedure instructs

the operator to "connect the locel flow meter" without

specifying

the

instrument

number.

The

procedure was

actually referring to a st ra t r.e r differential pressure

indicator, instrument number 33-PID-4610. The operator did

not simulate connecting this instrument and when questioned

by the Team, he stated that the step referred to flow n)eter

FI 4609 which was already connected. Of more significance

was confusion caused by step IV.B.2.b, which instructs the

operator to install jumpers to defeat LPCI initiation and

PCIS isolation signals and operate LPCI injection valves 28

and 29. The equipment operator requested the assistance of

the watch engineer and the STA.

These watchstanders

initially felt the jumper was not needed,

iha jumper is

not directly ' elated to LPCI valves 28 and 29, but is

needed to provide a flow path for a fire pump and to pre-

pare for contingencies in the E0Ps.

Procedure 5.3.26 was one of eight new procedures written by

contractors and validated by contractors.

All eight of

these procedures are therefore suspect and will be revali-

dated by licensee operations staff before restart.

All

other E0P satellite procedures and other abnormal operating

procedures substantially changed daring this outage will

also be revalidated before restart.

The licensee did not perform any QA audits or surveillances

on the writing of procedures by contractors. However, the

licensee has performed surveillances of the procedure

validation process used on procedures other than the E0P

satellite procedures.

Surve111ances #87-9.3-9 and #88-1.

1-56 found that half of the procedures being revised and

implemented in April and May 1988 were not being validated.

As a result of this finding, procedure 1.3.4-4, "Procedure

Validation," was issued August 15, 1983.

- _ _____

__

_ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

. _ _ . _

_ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _

___ _______ _ __.

.

.

25

There were also somt, training aspects to this procedure

issue.

The equipment operator was trained on Rev. O of

5.3.26 which did not include the instruction to connect the

local flow meter, whereas the inspector used Rev. 1. Licen-

,

sed operators were trained on the control room portion of

the E0P satellite procedures and equipment operators were

trained in the procedural steps outside the control room.

The problem with the jumpers occurred at the interface

between these operators.

Following the procedures revali-

dation discussed above, the licensee will provide addt-

tional training as needed.

During a NSRAC meeting conducted ' on August 2,1988, the

committee discussed an open concern on the validation and

upgrade of plant procedures.

NSRAC concluded that they

were concerned that all of tne routine operating procedures

had not been validated by one o' the validation processes.

Following the meeting, the committee forwarded a concern to

the SVP-N concerning the operating procedures necessary for

long-term operation of the plant.

The plant staff is

scheduled to respond to NSRAC on September 14, 1988.

The

NRC will review this response during a subsequent inspec-

tion.

3.2.5

Temporary Modification Controls

The Team observed that current logs show that about 15 tem-

porary modifications (TMs) are in effect, some of which

date back to 1983. Fif teen is not an unusual or unmanage-

able number of TM's, and represents a significant reduction

from previous conditions.

The Team reviewed nine TM's initiated 1987 and prior years

and noted (1) only three of the nine modifications affected

safety-related systems; (2) licensee safety evaluations

(SE) were filed in the TM package, which demonstrated the

interio

configurations

created

were

acceptable;

and,

(3) licensee actions to address the TM's by conversion to

permanent modifications were apparently based on engineer-

ing service requests and plant design changes referenced in

.

the TM packages.

Team review of the SE's on a sampling

basis did not identify any inadequacies. Further, the Team

noted that reduction of the TM backlog has been a licensee

priority.

I

t

!

L

~

.

_ _ _

_

_ __

_

26

Plant Procedure 1.5.9,

"Temporary Modi fications," allows

temporary modifications to be open for six months and pro-

vides a mechanism for active TM's to be extended. However,

this mechanism is typically not used. Procedure 1.5.9 does

not require a review of the TM for extension of the expira-

tion date if an engineering service request (ESR) for a

permanent design change is in effect for the TM. Of seven

TM's reviewed, six had ESR's and therefore did not have a

current approved extension date.

The inspector indicated

that good engineering practice would dictate continuance of

the periodic reviews for all TM's, and licensee management

agreed. The licensee committed to either prepare a justi-

fication for operation for every TM that is still open

prior to startup or to revise the procedure to apply the TM

extension request process to all TM's, including those with

outstanding ESR's.

TM 84-77 was selected for detailed followup review to

assess the technical adequacy of the change on a temporary

basis and to evaluate the extent and timeliness of licensee

followup actions to either remove the temporary modifica-

tion or convert it to a permanent change to the facility.

The modification involved the replacement of an FCR-type

relay in cubical 72-754 of the DC motor control center for

the RCIC 1301-22 valve.

The valve is in the suction path

from the condensate storage tank (CST), is normally open

for RCIC standby and initial operation, and will cycle

closed on low level in the CST.

After failure of the

existing TCR relay (an open circuit coil), an HFA-type

relay was installed on December 17, 1934 and made elec-

trically equivalent to the original circuit.

An HFA was

used because an FCR relay was not available onsite.

The

change did not affect the normal function of the valve.

Engineering

Service

Request

(ESR)85-368,

dated

July 22, 1985, requested engineering to convert the change

to a permanent modification, with a completion date of

November 22, 1985.

ESR response memorandum NED 86-1275,

dated December 31, 1986, rejected the ESR request to make

the change permanent because of two concerns involving the

need to keep the wiring in the 72-754 cubical consistent

with other DC motor control centers (MCC) and the assumed

differences in the inrush and coil holding currents between

the two types of relays.

In rejecting the request, engi-

neering found that the change was acceptable on a temporJry

basis, but recom. mended restoration of the original design.

.

.

27

A Potential Condition Adverse to Quality (PCAQ) Report (No.

NED 86-110) was issued to assess the deviations.

Further

l

engineering evaluation was requested by ESR 88-080, dated

January 27, 1988, with action requested by May 1, 1988.

Further engineering review determined that the change would

be acceptable as a permanent modification, which was made

by FRN 87-80-52 to PDC 87-80 dated June 14, 1988.

The plant design change (PDC) modified the drawing to per-

manently document the change and addressed the scismic ade-

quacy of the HFA relay installation. The HFA relay was not

certified to be environmentally qualified since the 1301-22

valve is not nn the EQ master list and environmental qual-

ification (EQ) is not required. The PDC also addressed the

adequacy of the inrush and holding current characteristics

of the HFA reley.

The second engineering review found the

HFA current characteristics to be better than those of the

FCR relay.

The Team discussed the bases for the original and final

engineering determinations via telephone on August 17, 1988

with engineering (NED)

The Team noted that engineering

.

initially rejected the proposed design change based on

l

!

information indicating larger power consumption by the HFA

relays, and based on a concern that, if replacement of the

FCRs with HFAs became a general practice, a problem could

result in the increase in DC loads.

Those concerns were

.

not realized since the FCR failure was a random one, and

l

the operating current characteristics of the HFAs are

l

better than initially assumed.

Based on the above, the Team identified no technical con-

cerns with the licensee's dispositioning of the adequacy of

>

the modification.

The Team noted that licensee action on the original 1985

ESR was not timely in either the preparation of the

original ESR or the followup actions by NED in response to

the site request. However, the actions to respond to ESR

88-80 and disposition the issue in 1988 were greatly

improved.

The Team audited the six tag outs for TM 84-22 and found

that MCC R25 was missing two TM tags. Since this is a non

safety-related modification which is about to be withdrawn,

this was not considered by the Team to be of safety signif-

icance.

It does indicate; however, the need to period-

ically recheck TM tagouts.

._ _____ _ _ _ _ _ _ _ _ _

.

.

28

An additional concern is that in the following example the

licensee performed a TM without implementing the formal

review and approval process. During a tour of the reactor

building on August 8,1988, the Team noted that reactor

'

pressure boundary leak detection system monitors C-19A and

C-19B had their doors propped open, and each monitor had a

large fan tied to the opening.

Investigation identified

that no temporary modification had been processed to

evaluate and authorize this alteration.

The

licensee

stated that elevated temperatures in the cabinets result in

failure of the monitor electronics and have been a long-

standing

problem.

Engineering response to Engineering

Service Request (ESR)85-462 implemented a reduction in

system heat-tracing temperature.

This alteration did not

resolve the problem, and on August 6,1988, the licensee

initiated ESR 88-558 requesting further engineering review,

Monitors C-19A and C-19B are required to be operable by

Technical Specifications during power operations so that

some short-term action and long-term resolution are needed.

Since the monitors are not currently required to be oper-

able, the licensee has de-energized them and removed the

fans pending evaluation.

In sumary, even though the licensee has been aggressive in

4

reducing the number of TM's, there have been some lapses in

their control of temporary modifications. This indicates a

need for continued licensee management attention to this

area,

3.2.6

Required Reading Books

The Team reviewed the "Required Reading" books in the con-

trol room.

The books consist of three large binders that

contain procedure changes.

They provide a method for

promptly updating operators on plant and procedure changes.

Each piece of information in the book had a sign-off sheet

to ensure that all operations personnel read the material.

The Team noted that information in the books dated back to

April 1983 and many of the procedure changes had not been

signed of f as read by all personnel. This appears to indi-

cate that the program is not being monitored routinely by

operations management. Material remaining in the book for

long periods defeats the purpose of providing timely infor-

mation on changes to the operators.

Conversely, if the

changes are not important to operations personnel, it may

not be necessary to put them in the books.

The Team discussed these observations with the Plant Opera-

tions Section Manager.

Some improvement was noted later

during the IAT inspection, as a result,

,

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _

.

.

29

3.2.7

Logs

The Team reviewed the implementation of the Technical Spec-

ification Limiting Condition for Operations (LCO) log, the

Otsabled Annunciator Alarm Log, and the operations super-

visor

log

procedures.

The

LCO

log was

implemented

August 18, 1988,

by

Procedure

SI-OP.0008,

"Limiting

Conditions for Operations Log," dated July 25,1988, and

was

being

used

on

a

trial

basis

from August 8

to

August 18, 1988.

The only LCO entered after the log was

implemented, LC0 A-88-002, was properly entered, tracked,

and cleared.

Procedure SI-OP.008 is being revised to

incorporate lessons learned in its initial implementation.

The Disabled Annunciators Alarm Log is controlled by Pro-

cedure 2.3.1, General Action Alarm Procedures, Item VII.

The inspector observed eight disabled annunciator tags on

control room annunciators. All eight were properly logged.

However, only two of the eight annunciators had a mainten-

ance request (MR) issued.

The shift supervisor informed

the Team that disabled annunciators without MRs occurred

due to plant conditions and will be returned to service

before startup.

The licensee aud'ts disabled annunciators

monthly under preventive maintenance (FM) Procedure S. A.24

"Audit of Control Room Annunciators and Instruments," which

should assure that these annunciators are returned to ser-

vice before startup.

There was little activity in the control room during this

inspection, but the Team did observe the following items

properly logged in the operations supervisor's log: LCO's,

Failure and Malfunction Reports, a fire drill, and spent

fuel pool temperatures while the fuel pool pumps were

out of service for maintenance.

However, as discussed in

Section 3.I .8 below, changes in jumpers or lif ted leads

were not logp i in the operations supervisor's log.

The Team concluded that log keeping practices are generally

adequate.

3.2.8

Timely Update of Lif ted Lead / Jumper Log

During a review of the Lif ted Lead / Jumper (LL/J) procedure

and program implementation on August 16, 1988, the Team

identified that the log was not being n;aintained comoletely

up-to-date. Eight entries in the LL/J log involved lif ted

leads or jumpers installed on July 14, 1988, to perform

main station battery werk anc testing per Maintenance Work

Plan (MdP) S7-46-173.

All eight requests were associated

with the same M4P. All log entries showed the LL/J request

_ _ _ _ _ _ .

._.

_ _______ -_ ___ - _ _ _ _ _ _ _ _ _

_ _ - _ _ _

.

.

30

was still active on August 16, 1988. The Team found that

,

the batteries had been returned to normal and LL/J request

was closed out on July 29,1988, and that Maintenance

Request 87-46-173 was completed on August 1,1988, inclu-

sive of the post-work testing.

Step 5.3.1.5 of Station

Procedure 1.5.9.1, "Lif ted Leads and Jumpers," states that

the person performing the LL/J request is to notify the

Watch Engineer when the system is returned to normal by

removing the jumpers or landing the lif ted leads.. The

Watch Engineer is responsible for updatino the LL/J log.

The findings were referred to operations personnel on

August 16, 1988 for followup.

Licensee followup review confirmed that the work had been

completed and the log should have been updated.

The log

was updated to show the correct status on August 16, 1988.

In response to the inspector's findings, the licensee co..-

ducted an audit of the log.

The licensee's audit identi-

fied (1) two instances where the log had not been updated,

and (2) that operations personnel were not making entries

in the Operation's Supervisor log when LL/J log entries

were made.

These matters were referred to the Operations

!

Section for followup and corrective action.

QA followup

and trending will be covered by QA Surveillance Report

,

88-94-61.

4

The licensee reported that the cause of the discrepancy was

the failure of m61ntenance personnel to inform operations

j

that the jumpers and lif ted leads were cleared when the

i

systems were returned tb normal. Inspector interviews with

j.

the Maintenance Supervisor responsible for MR 87-46-173

noted that he failed to discuss the closecut action on the

4

LL/J request as a result of a misunderstanding on the

status of the work package closeout during shift turnover

with another maintenance supervisor.

Team review concluded the inaccurate LL/J log had minimal

significance and no impact on safe plant eperations for

these cases.

There was no loss of control of the physical

plant configuration.

Plant operators would have reviewed

the LL/J log as a prerequisite to plant restoration and

startup.

This review would have identified the open log

entries and

the completed closecut actions.

Further,

licensee followup to the discrepancies identified by the

Teara were prompt and appropriate.

Based on the above, and

in recognition that the jumper and lifted lead log is a new

tracking system, no further NRC action is warranted at this

time.

This

area will

receive

further

review during

subsequent routine NRC inspections.

_ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - -

.

.

31

3.2.9

Tagouts and Operator Aids

The Team reviewed the licensee's administrative controls

for use of protective tagging at PNPS.

The Team reviewed

Procedure No.1.4.5, "PNPS Tagging Procedure," Revision 23,

which is to be implemented September 1,1938, and noted

that this procedure was revised to address concerns with

tag controls identified during the licensee's self-assess-

L

ment.

Specifically, the procedure limits the use of Nu-

clear Watch Engineer (NWE) tags; prohibits the use of dan-

ger (red) tags for identification purposes on lifted leads;

and requires documented monthly reviews, including field

verification, of NWE, Caution and Master Danger tags and

tagout sheets.

The Team reviewed the NWE and caution tag

logs and independently verified that several NWE, caution,

danger, and master danger tags were properly filled out,

properly hung, and positioned as required on the compon-

ents.

No discrepancies were identified.

Based on this

review, the Team concluded that the licensce's control of

protective tagging was adequate and properly implemented.

The Team also reviewed the licensee's control of operator

1

aids as established by Procedure No. 1.3.34, "Conduct of

Operations." An operator aid is information in the form of

sketches, notes, graphs, instructions, or drawings used by

personnel authorized to operate plant equipment. The Team

reviewed the operations and chemistry operator aid log and

determined that it was maintained in accordance with the

i

procedure. The Team noted that periodic licensee reviews

1

and verification of the need for and placement of operator

aids were documented.

The Team independently verified

proper posting of selected operator aids, and no unauthor-

ized aids were identified during the Team's plant tours.

Based on this review, the Team concluded that the licen-

-

see's control of operator aids was adequate.

3.2.10

Plant Tours and System Walkdowns

3.2.10.1 Miscellaneous Tour Observations

!

The IATI Team made frequent plant tours.

The

overall material condition of rooms and equip.

I

ment was excellent.

Particularly notable was

cleanliness, fresh paint, and obvious decontam-

,

ination efforts to make major portions of plant

and equipment accessible. Comnonent labeling and

tagging was very good,

j

i

l

l

l

l

[

l

_ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

O

8

32

The Team observed activities in progress.

Per-

sons interviewed on tour (HP, security, opera-

tions

contractor)

had

experience

in

their

positions and were knowledgeable about their work

and duties.

HPs were cognizant of work activ-

ities in progress.

Housekeeping controls were

being maintained during work in progress.

The Team reviewed the status of indicators and

controls on selected local panels.

Controls and

indications were operable and no deficiencies

were noted. Operating procedures required to be

posted at the local panels were available and

adequate, based on Team review.

The Team observed loose cable tray covers includ-

ing one that was laying on top of an in place

cover.

The licensee reviewed this finding and

documented the review and corrective actions in

an engineering "white paper." This review deter-

mined that loose covers do not compromise the

design but that covers laying on top of in place

cable tray covers could be a seismic concern.

The misplaced cover found by the Team was deter-

mined to not be needed.

The licensee surveyed

cable trays throughout the process buildings and

found additional loose covers but no more that

were completely unfastened and laying on top of

other covers.

Corrective actions completed in-

clude refastening the loose covers, removing the

misplaced cover, revising procedure SI-SG.1010

"Systems Group System Walkdown Inspection Guide-

line," to use periodic walkdowns by the system

engineering division to identify seismic con-

cerns, such as misplaced tray covers, and prepar-

ing F&MR No.88-200, which will be used to deter-

mine how to keep future maintenance and modifica-

tion work

from creating

loose

or misplaced

covers.

The Team concluded that the licensee's

response to this issue was thorough and adequate.

The Team considers this issue resolved.

3.2.10.2 Diesel Generator Walkdown

A walkdown of the 'A' diesel generator (DG) was

completed on August 15, 1988, to verify opera-

bility and standby readiness of the emergency

power supply, and to observe the general condi-

tions in the 03 area.

The valve checkof f lists

of Procedure

2.2.8,

"Standby AC power System

(Diesel Generators) " were used as acceptable

criteria to establish the proper system valve

- _ _ _ _

.

s

33

positions.

The procedure checklists were also

reviewed for adequacy agatast Drawings M219 and

M224, and by comparison with the physical plant

during a walkdown of the diesel skid and room.

Proper valve lineup was verified for the DG fuel

oil and air start systems. This review confirmed

that the 'A' DG was operable in the standoy modo.

Cleanliness and the general condition of equip-

ment and components in the diesel rooms were

excellent.

Valve and component identification

(tags) and labeling were very good and showed

significant improvement in performance in com-

parison to past reviews. Several minor discrep-

ancies were noted, as follows:

(1)identifica-

tion tags were missing on valves 104C and 118,

and the tag was loose on valve 105C; (2) valve

118 was required to be locked in the closed

position and a chain and padlock were provided

for this purpose; however, the chain was suffic-

iently loose that the Team would have been able

to defeat the lock and thereby move the valve;

(3) the inner fire door granting access to the

'A'

DG skid had worn and damaged gaskets along

the closing surface and the door latching mech-

anisms (dogs) were misaligned with the position

indicators; (4) no permanent lighting was instal-

led in the ' A' and 'B'

diesel day tank rooms --

lighting, if installed, would aid operator re-

views during plant tours; and, (5) two isolation

valves for pressure switches 4555A and 4556A were

not labeled with an 10 tag in the plant and were

not identified on system drawings or procedures.

The valves were properly positioned.

Addition-

ally,

proper

valve

position

is demonstrated

indirectly during the monthly functional test of

the diesel air start system.

These discrepancies were noted by the Nuclear

Plant Operator accompanying the Team and were

discussed with the duty Watch Engineer. Actions

were taben to document and correct the discrep-

ancies, inclucing the issuance of Maintenance

Request 88-61-83 for the fire door.

Inspector

followup review on August 16, 1988 confirmed that

actions were in progress and had been completed

to correct the tag on valve 105C and to properly

lock valve 118.

Licensee response to the Team's

findings was appropriate and timely.

No other

inadequacies were noted.

__-______ __ ___

.

.

34

3.2.10.3 Standby liquid Control System Walkdown

'

The Team walked down the standby liquid control

(SBLC) system using the valve checklist in Pro-

cedure No. 2.2.?4, "Valve Lineup for Standby

Liquid Control System," and piping and instrument

diagram (P&ID) M-249. This review was performed

to verify the adequacy of the procedure checklist

and P&ID, evaluate the valve labeling, evaluate

the control of locked valves, verify the opera-

bility of instrument and support systems, and

assess the overall material Condition of the sys-

tem and general cleanliness of the area.

The

Team noted that the checklist control of vent and

drain capped connections differed from other

safety system procedures, such as those for the

residual heat removal (RHR) and core spray (CS)

systems. For example, an outboard vent valve on

the CS checklist would be "locked, closed and

espped." The SBLC procedure only checks "locked,

closed." No deficiencies with capped connections

were noted, however.

The Team also noted that

the vent valve for pressure indicator (PI) 1159

was not on the valve checklist.

The licensee

agreed to review these observations to determine

if the procedure needed to be revised.

No other

deficiencies or concerns were noted.

Overall, the Team found the valve labeling, mate-

rial condition, and general cleanliness to be

excellent.

3.2.11

Conclusions

The operations staff conducted their activities in a pro-

fessional manner. Operators were knowledgeable about their

duties and about plant status. The depth of experience and

knowledge of senior licensed operators is a strength and

will be a major asset du ri r.3 restart.

Shift turnover

.

briefings by individual operators and for the shift are

thorough; however, non-operations shift workers do not

routinely attend these briefings. Site management involve-

ment in operations was evident by their frequent presence

in the control room.

Shift staffing levels are adequate

and plant housekeeping was excellent

O

O

35

1

!

.

A weakness was noted in the validation and/or training of

E0P satellite procedures.

The licensee's commitment to

confirm effective implementation of E0P satellite and off-

normal procedures before restart is responsive to NRC con-

cerns.

Administrative controls and log-keeping practices

,

i

l

are generally adequate, although required reading materials

'

!

are not being reviewed by all personnel on a timely basis.

l

There are lapses in the licensee's control of temporary

4

modifications, particularly the absence of periodic reviews

and scheduled completion dates for temporary modifications

covered by an engineering services request,

i

!

l

l

l

I

I

i

r

l

L __

_ _ _ _ _ _ _ _ _ __ - _________ ____-__ _

..

__

_ _ _

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

_

_ _ _ _

_ _ _ _ _ _ _ _ _ _ _

.

.

36

3.3 Maintenance

3.3.1

Scope of Review

The licensee's maintenance program has undergone signifi-

cant change during the past several months. Weaknesses had

been identified during the SALP period ending May 15, 1988,

,

,

and by Special NRC Maintenance Team Inspection 50-293/

~

88-17.

During the present inspection, the licensee's main-

'

tenance policies and program procedures were reviewed.

Maintenance activities were evaluated during the planning,

implementation, post work testing and closecut

stages.

Emphasis was placed on direct observation of ongoing werk

in the field.

Interviews were conducted with personnel at

each level within the maintenance department to determine

their depth of understanding of program goals.

The Team

'

,

also assessed the size and significance of the licensee's

l

maintenan'.e backlog, and reviewed established licensee

performance indicators.

1

3.3.2

Observations and Findings

3.3.2.1

Management Policies and Goals

'

The Team reviewed the licensee's Mission Organ -

tration and Policy Manual, Nuclear Operations

Procedures

Manual,

and

Maintenance

Section

Manual.

These documents describe the licensee's

'

policy and performance goals for the maintenance

l

l

program. The licensee has also established the

,

Material

Condition

Improvement

Action

Plan

!

,

(MCIAP).

The MCIAP, which is described in the

,

i

licensee's Restart Plan, is designed to achieve

!

long-term improvement in the maintenance program.

>

In addition, maintenance performance indicators

r

are being used by the licensee to evaluate the

success of recent program changes and the allo-

cated maintenance staff has been increased sig-

'

'

nificantly.

Interviews with maintenance person-

nel at various levels within the department indi-

, .

cate

that

the

organization

and

management

,

policies are generally well understood.

,

1

,

i

$

l

i

I

!

,

(

l

,

<

6

,

'

.

,

.

,

37

i

3.3.2.2

Organization and Staffing

The maintenance organization and staffing levels

were reviewed.

Interviews were conducted with

division

supervisors

and

staff personnel

to

determine whether organizational

relationships

were well

understood.

The

current

staffing

status was evaluated, particularly in the super-

visor, maintenance engineer, and planning post-

tions, to determine whether staffing levels were

adequate, responsibilities clearly defined, and

resources effectively used.

The maintenance section consists of three pro-

duction divisions (electrical,

instrumentation

and control and mechanical), plus a planning

,

division and an engineering group. All division

manager positions and all first-line supervisor

i

positions in the production divisions are filled

,

with licensee employees, except for two positions

in the equipment tool room, which are presently

filled by contractors.

Increased stiffing at the

craft level in the production divisions has been

i

authorized.

Instrumentation and Control (I&C)

will increase from 22 to 30 positions; Electrical

'

Maintenance will increase from 14 to 18 post-

tions; and Mechanical Maintenance will increase

from 27 to 33 positions.

Staffing of the plan-

ning division has not baen completed.

Twelve

contractor personnel are presently being used to

perform the planning function, with assistance

from the licensee's outage management group.

This arrangement is performing acceptably, as

described in Section 3.3.2.4

Team

interviews

with

supervisors

and

craft

'

empicyees showed that personnel clearly under-

stand the new program and their area of respon-

sibility. The interviews covered personnel with

a wide range of experience in their positions,

including those newly assigned.

The Team noted;

however, that the recently revised job descrip-

)

tions for the section have not been disseminated

to the staff.

The Maintenance Manager stated

that they would be issued in the near future.

!

!

!

. _ _ - - . __

e

O

38

Two positions in the new maintenance section

organization, the Deputy Manager and the Radio-

logical Advisor, are effectively being used. The

Radiological Advisor is a permanent staff post-

tion and provides a focus for interface with the

Radiological Protection Group. Team observations

indicated that the Deputy Manager was effective

in scheduling and coordinating activities through

his interface with other sections,

j

The Team's review indicated that licensee staff-

ing is ample to meet targeted production goals

without reliance on the use of excessive over-

time. While some variations occur, the percent

of overtime worked has been at or slightly above

the operatirg goal of 20*4, which equals a 48-hour

work week.

Work schedules for craf t and super-

.

visory personnel provide I day off in a 7-day

!

period.

The maintenance staff is working pri-

marily on the day shif t, with night shif t cover-

age provided for certain critical jobs in pro-

gress.

The licensee plans to provide around-

the-clock 8-hour shifts that will match the

Operations

Section

rotating

shift

schedule,

beginning with plant startup. Maintenance shift

coverage will continue through the power escala-

tion sequence and on a redaced scale afterwards.

Licensee staffing is sufficient to staff the

shift schedule without reliance on excessive

overtime.

New personnel assigned to the division manager

and production supervisor positions have adequate

prior experience in related assignments.

The

Team's observations of the first- and second-line

supervisors in conducting their daily activities

showed that the supervisory, oversight, and con-

trol functions were effectively performed. Based

on these observations, the Team concluded that

the newly hired supervisory staff does not have a

negttive impact on the quality of control over

maintenance activities.

. _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

,

.

39

In summary, identified strengths in the present

maintenance section organization include the use

of the Deputy Manager and

the

Radiological

Advisor.

The increase in supervisory positions

in the production divisions has been effective in

increasing oversight and control of work activ-

j

ities. While temporary staffing of the planning

division with contractors is sufficient and pro-

vides for an effective planning function (as

measured by the quantity and quality of mainten-

ance packages produced), plans to staff these

'

positions with permanent licensee employees by

October 1988 should remain a management priority

to assure timely integration of the planning and

i

scheduling functions. Management has controlled

overtime for the craf t and supervisory positions.

Plans to provide for maintenance staffing during

and after restart on an 8-hour rotating shift

basis should provide continued ef fective over-

time control.

3.3.2,3

Communications and Interfaces

Communication between the maintenance department

l

and other portions of the organization, particu-

[

larly operations and radiation protection, had

previously been a weakness.

The licensee has

,

taken successful steps towards improving communt-

cation, both internal to the maintenance depart-

,

ment and with other station groups.

The

Team attended a

variety of maintenance

department status and turnover meetings.

Based

,

on observation of the:S meetings and interviews

with maintenance personnel at each level of the

i

organization, the Team concluded that communica-

tions internal to the maintenance staff are ef-

[

fective.

Maintenance department managers vare

cognizant of the status of activities and of

f

emerging problems.

J

l

The

licensee

has

initiated

several

programs

directly

addressing

the

past

weaknesses

in

j

.

interdepartment communications.

In an effort to

,

l

improve the interface with radiation protection

!

and to raise worker sensitivity to health physics

,

issues, the licensee created and staffed the

!

l

nsintenance Radiological Advisor position. Inter-

l

views with a spectrum of individuals indicated

l

'

that this &ffort has had a positive impact on

f

.

h

.

.

.

. . .

.

.

. - __ _ _--

! .

.

,

6

!

l

40

day-to-day working relationships and performance.

The licensee also formed the Vork Prioritization

Review Team (WPRT), composed of representatives

,

l

of various station departments.

The WPRT pro-

I

vides a forum for discussion of the relative

I

importance of each maintenance item as it arises.

The WPRT has been effective in improving opera-

tion's departtent involvement with the mainten-

ance process. The maintenance department is also

involved in daily and weekly meetings intended to

l

ensure coordination between station groups. !!eet-

ings

attended

by

the

Team were

generally

effective.

l

The need for continued efforts to improve commur +

!

Ications and interfaces were noted in some arers.

The licensee's Stores Department practices .re

not alway: < >lly supportive of specific mainten-

ance department needs.

For example, lubricating

,

l

oil can only be withdrawn in bulk quantities,

l

such as a 55 gailon drum.

Typical maintenance

I

activities require use of only a fraction of this

amount.

Similar restrictions apply to materials

routinely used by the 1&C, electrical, and mech-

anical maintenance divisicns. This policy places

the burden for control and storage of unused

material on the individual requesting the with-

l

drawal. The Team noted that maintenance person-

'

nel were routinely using a cabinet in the main-

tenance shop to store uoused "Q" materials. No

prccedure existed to specify the appropriate con-

trols for the storage area.

The need for estab-

lishment of the storage cabinet had been dis-

cust.ed previously between the Quality Assurance

Department (QAD) and matntenar.ce.

QA0 believed

that the cabinet was nc,t currently in use, while

maintenance personnel believed that Q).O had con-

curred in its creation, demonstrating a lapse in

interdepartment

communications.

The

licensee

subsequently per ormed an inventory of the mate-

,

rials in the cal:1nct, and removed all non-Q ar.d

suspect materials.

Procedure 3.M 1-32, "Contrcl

of

  • Q*

Hold A. ea ," wa s subsequently issued to

provide appropriate controls and surveillance of

the cabinet.

_____

_ _ _ _ .

____

- _ _ _

.

.

41

The Team also noted that partially used drums of

both Q and non-Q lubricatinq oil and grease were

being kept in a storage shed outside the process

building.

Several of the drums were not properly

sealed.

No procedure addressing this storage

arca existed.

Discussions with operations per-

sonnel indicated that the difference between Q

'

and non-Q drums of material was not clearly

understood. Routine withdrawals and their equip-

Mnt application were not A ecorded. In response,

a ..e

licensee removed all non-Q reaterials and

comitted to issue e procedu.*e to establish

aopropriate controls by Septecer 7,1988, in-

cluding provisions to ensure that, the lubricants

<

are traceable to their application in the field.

In addition, the liceasee committed to evaluate

the possible addition of non-Q oil to Q equipment

and its potential significance.

During followup to this issue, the Team reviewed

Engineering Specification M-547, which decuments

the procurement and receipt inspection re?vire-

ments for the purchase of lubricants as a Commer-

cial Quality Item (CQI).

The Team 70tsd that

l

M-547 requires sampling and testing of each b4tch

of material purcFased as a CQI.

At the Yeam%

request, the licensee reviewed records and iden-

I

tified two cases in which a CQI procurement order

had been issued which did not invoke thia samp-

!

ling

require. tent.

The

licensee

subsequently

issued a Potential Condition Adverse to Quality

(PCAQ) to initi.te a review of CQIs issuod for

i

consistency wit.h approved engireering specifica-

l

tions.

The licenste committed to disposition

!

this PCAQ prior to restart.

,

L

Overall ce:nunications between the maintenance

i

department and other groups within the organira-

l

tion are effective. However, the interface prob-

!

lems dis. usseo &bove, among the Stores Ospart-

'

,

men ,1AC, and the Maintenance Department. $ndi-

r

.

catt . hat continued at'.ention is needed.

T

,

i

l

i

P

i

i

f

-

-

'

'

.

.-

42

,

3.3.2.4

Maintunence Planning and Prioritization

' ensee has established a Mainte,a ce Plan-

r. . .

Ji . stor within the Maintenance Department.

The

!-

af the Planning Division is clearly

deline

in approved maintenance procedures and

the

.see's Maintensnce Section Manual .

The

. Planning

Division Manager position

has been

filled and the licensee is actively pursuing

candidates for the eight allccated staff post-

tions.

When staffing efforts are corolete, the

division will corsist of a work package planning

group and a scheduling group.

In the interim,

the licensee is utilizing twelve contractor per-

sonnel to perform the package planning function.

The licensee's Outage Management Group (OMG) is

currently providing scheduling guidance.

The

licensee expects to complete the staffing effort

by October 1988,

Team reviews indicate that the

present staff of contractors, in conjunction with

OMG assistance. is functioning well.

-

Implementation of the revised maintenance work

'.

process, particularly the need to generate de-

tailed job-specific maintenance work plans (K4P)

for each maintenance request (MR), has resulted

in a heavy emphasis on the planning function.

The Team reviewed a large sample of completed

KdP's, and KdP's in the field.

Interviews with

craf t personnel and first-line supervisors indi-

1

'

cated that these individuals were knowled;eable

about the new maintenance process requirements

and considered KdP's issued by Planning to be of

generally good quality.

One weakness was noted

i

in the area of post-work testing specification,

'

as discussed in Section 3.3.2.6.

The lum not"d that the completion of job plan-

ning,

ano approval of the F#P are typically

restraints to commencement of the activity.

This

results in the need to expedite the review pro-

cess, making scheduling difficult.

It appears

1

that this is primarily attributable to the new-

ness of both the program and the Planning staff.

Other factors also contribute.

For example, the

licensee's procedures currently do not provide a

simplified process for non-intert changes to the

M

e

-

m

o

-

43

MWP after issuance. MWP's require a complete re-

review to incorporate minor changes.

The licen-

see rtated that a revision to the program to

include provisions for non-intent changes

is

planned for the future. The licensee's engineer-

ing department is presently reviewing each MR/fiWP

and approving the use of any replacement mate-

rials.

This practice provides positive control

of all materials, but delays issuance of ;.he MWP

and

is

a

significant

drain

on

engineering

resources. While these factors inhibit efficient

planning, no instance of inadequate planning was

identified.

The licensee has created a WPRT to assist in the

assignment of the proper priority to each MR.

The WPRT meets daily and is composed of represen-

tatives of various station groups,

including

maintenance, operations, outage management, con-

struction management, and fire protection.

It

performs a multi-disciplined review of new main-

tenance items to identify potential plant impact.

The IATI Team attended a WPRT meetir.g and ob-

served that discussions were properly focused and

priorities weie assigned appro,-iately.

The Team also independertly reviewed outstanding

maintenance requests for the RHR system and the

electrical

distribution

system.

This

review

focused on MR's not designated for completion

before restart. The Team noted that MR 88-10-105

documented electrical ground and potential cable

insulation damage in the circuit for pressure

switch PS-1001-93A.

This switch is environmen-

tally qualified (EQ) and provides a

safety-

related interlock function for the automatic

depressurization system.

The MR had been sched-

uled for work af ter restart, leaving the switch

,

EQ in an indeterminate state. In response t

the

l

Team's question, the licensee rescheduled tne MR

for completion r~ior to restart.

!

l

,

i

l

_

.

-

~ -.

-

y

.-

-,

,

.

4

8

44

,

Tne -Team also noted that MR 88-10-26 documents

i

'

that valve A0-8901 is currently open and cannot

be closed using the ~ hand switch.

A0-8001 is

-

installed in series with a check. valve in the

tor'us fill line. The check valve satisfies the

,

primary containment isolation function for the

line. While A0-8001 is not rewired for contain-

ment isolation operability, h does serve as a

redundant isolation valve immediately adjacent to

the check valve. A0-8001 was originally designed

.

,

to receive an automatic open signal on sensed low-

t

torus level.

Because normal torus level is now

maintained below the instrument low level. set-

point, the valve continuously receives an open

signal, thus preventing manual closure.

This

condition has existed for at least several years.

The licensee has relied on closure of a maqual

block valve located in the turbine building to

compensate for the problem.

The Team expressed

concern that. the distance between the containment

!

isolation check valve and the redundant isolation

U

valve have been unnecessarily extended outside

the reactor building. In addition, a lineup that

'

is inconsistent with the design drawings and

operating procedures resulted.

The WPRT had

designated this MR as post-restart.

In response

to the Team's concerns, the licensee initiated an

Engineerirg Service Request (ESR) to identify an

acceptablo repair.

The licensee committed to

'

resolve tTis item prior to restart.

l

These tw o examples of misscheduled MR's were

discussed by licensee management with the WPRT.

In addition, the licensee committed to re-evalu-

i

i

ate all priority 3 MR's before restart.

The

licenser's process for review and prior tization

'

!

of MR's is thorough, and with the exuption of

the twc instances described above, appears well

l

implemented. The vffectiveness of the licensee's

plannirg and prioritization program is demon-

'

strated by the overall decrease in the number of

outsta1 ding maintenance tasks, their average age,

i

and their significance.

l

3

L

i

i

I

4

i

<

- .

- . -

- . . - .

- -

- - - . -

- -

- _ . _ _ - . . . -

.

~

-

.

>

45

The licensee tracks several maintenance perform-

ance indicators which are indicative of backlog

status.

Those performance indicators generally

display a favorable trend. The Performance Indi-

cator Report for August 9,1988, shows a total

backlog of 2177 open MR's, of which 746 are in a

test / turnover status.

Of these, 220 cannot be

tested until the plant system becomes operable

during startup. Of the 1431 remaining open MR's,

the

licensee has identified 652 required for

restart.

The physical work had yet to be done

for 145 of these 652 MR's.

Based on tho above,

and an average closeout rate of about 25 packages

per week, elimination of the restart backlog

with)n 6 to 7 weeks appears to be manageable

effort.

The licensee's goal, i r,

addition to

addressing the restart MR's, is to reduce the

total number of open MR's from 1431 to less than

1000 Dy plant restart.

The Team noted that this

would constitute an acceptable open MR backlog

for an opersting plant, and that the licen>ee's

goal was reasonable.

3.3.2.5

Control and Performance of Maintenance

Inspection in this area was performed to deter-

mine whether maintenance activities are being

properly controlled through

-tablished proced-

ures, and the use of approve

2chnical manuals,

drawings and job-specific instructions. Mainten-

ance activities were observed to determine how

well

the new prog am was being implemented.

The new maintenance program is nrimarily defined

in Procedures 1.5.3, "Maintenance Requests," and

1.5.3.1,

"Maintenance Work Plan," which were

implemented

on June 20, 1988.

The procedures

were reviewed and found to provide strong con-

trols for identification, planning, performance,

and closecut of maintenance tasks.

Issuance and

control of materials used for replacement / repair

assure that requisite quality requirements are

' maintained.

Super /isory oversight of work in

progress and the final review of work packages

for completeness is a strength.

Based on its

review of the above procedures and observations

of work in progress, the Tear concluded that the

r,swly defined program provides excellent control

and docu entation of activities.

.

,w

. .

n.

. -

..

..

.

.e-

0

4

46

,

!

'

.The new program and proced',ies formalize controls-

i

.

that were previously in place, but inconsistently.

t

applied and not . recognized by ' procedures.

The

procedures now require better documentation of

the initial

problem description,

the rcpairs

made, and the post-work test requirements. They

'

require detailed work instructions, which should

provide for consistent high quality in mainten-

ance work packages. An. additional improvement in

the maintenance procedures is that the mainton-

[

ance work plan now provides for detailed documen-

I

tation of installation and removal of lifted

I

leads and jumpers (LL/J).

This documentation

i

assures proper performance of the . task and is

i

supplemented by the tracking;provided in the LL/J

!

l

Log initiated by the Operations Department per

Procedure 1.5.9.1.

'

I

To eliminate a previously identified weakness,

.

the

licensee

has

stopped

using

Procedure

3.M.1-11, "Routine Maintenance," which was found

+

,

to be too general to adequately control work

i

activities.

Instead, detailed work instructions

are provided by the work plans prepared in ac-

l

cordance with Procedure 1.5.3.1.

Further, the

licensee has stopped using the Maintenance Sum a

i

i'

mary and Control (MSC) form.

The documentation

provided by the form has been replaced by the

detailed

work

plans,

maintenance

logs,

and

'

'

special process control sheets now required by

'

'

procedure. 1.5.3 and 1.5.3.1.

1

The maintenance activities and packages listed in

[

'

Appendix 0 of this report were reviewed to verify

,

proper implementation of program requirements.

'

t

The Team found that detailed work packages were

prepared and in use in the field with adequate

,

'

job specific instructions to accomplish the as-

!

scope were observed.

Pre-job briefings were

'

signed tasks.

No ad-hoc changes of the work

.

conducted and were appropriate to outline the

activities planned.

Coordination and in-process

!

communications with operations personnel were

[

proper

and

assured

good

control

of

plant

i

equipment.

I

f

t

i

,

.

h

?

-.- - - - -.-. -

_ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

. .

. .

47

Maintenance

personnel,

including

contractors,

have been trained in and were knowledgeable about

the new program and procedure requirements. Al-

though the new controls were deemed cumbersome by

'

some, overall worker attitudes about the new

procedures were positive.

There is a general

acceptance of the present progra:n and a desire to

"do the work right."

Personnel performing the

work wrre qualified, as verified by the training

and qualification status board maintained in the

maf-*.enance shop.

The licensee has made progress in filling vacan-

cies in the. first-line supervisor positions.with

personnel having the requisite experience and

expertise in the associated disciplines.

The

present supervisory staffing is adequate to cover

work production schedules and provides adeouate

oversight.

In an addition 21 program improvement,

supervisor review of work packages is now re-

quired by procedure to assure management review

of packages for completeness.

First-line super-

visors were ruutinely observed in the field di-

recting work in progress.

Supervisory involve-

')

ment was effective to assure completion of work

correctly, to help resolve technical problems,

and to coordinate engineering support, as re-

quired. The oversight function has been enhanced

by the larger number of first-line supervisors

who have been relieved of the excessive adminis-

trative burden associated with planning and pack-

age prepar' tion.

The effectiver.ess of maintenance staff engineers

and system engineers in supporting field activ-

ities was particularly noted in the repairs for

the fuel pool cooling pump and the repair of RHR

discharge valve 288. The engineers are also used

in the root cause analysis of component failures.

The repair of valves 28A and B involved the

.

fabrication of new valvo yokes, which resulted in

a large and complicated work control process that

was appropriately broken down into several work

packages.

Oversight and control of these jobs,

which spanned several weeks, were notable. The

quality of the final product was evident, as was

the welding of the yoke subparts. Good inprocess

t

. _ .

-,

-

i

. , -

,

t

,

48

,

controls resulted in an acceptable root weld on

the first attempt for valve 288.

Although a

'

problem was encountered in the fabrication of the

yokes (short by 3/8 inches), . this item, consid-

ered minor, was properly dispositioned by the

licensee

through Nonconformance

Report (NCR)

88-99.

3.'3.2.6

Post-Maintenance Testing Program

The licensee's program for identification and

implementation of post-maintenance testing was

considered weak during

previous

inspections.

During the current period, the Team revieweo the

licensee's post-maintenance testing program pro-

cedures and other approved test technical guid-

ance. A sample of maintenance tasks was reviewed

to determine if planned testing adequately demon-

strated correction of the cited deficiency. Test-

ing was observed in the field, and completed test

documentation was

reviewed

for

thoroughness.

The licensee recently implemented a major revis-

ion to Procedure

3.M.1-30,

"Post-Work Testing

Guidance."

The current revision establishes a

conservative philosophy designed to ensure that

prescribed testing verifies correction of the

original deficiency, as well as potential prob-

lems which could have resulted from performance

of

the

task.

Organizational

and

individual

responsibilities are clearly defined.

Procedure

3.M.1-30

incorporates

by

reference

Station

Instruction SI-MT.0501, "~os t-Work Test Matrices

and Guidelines."

SI-MT 0301 serves to further

define the method by which post work testing is

to be specified and documented.

It includes an

individual matrix for each type of component

describing the possible maintenance tasks and the

corresponding post-work test requirement.

Each

matrix references an appropriate data sheet which

,

provides more dctailed testing guidance. Proced-

ure 3.M.1-30, in conjunction with SI-MT 0501, is

to be used by the Maintenance Planning Division,

with needed technical input from other mainten-

ance department and systems engineering depart-

ment personnel, to establish comprehensive test-

ing requirements for each maintenance request.

The testing program as described in these docu-

ments is well conceived and is considered a

strength,

i

i

I

,

,

a.

_

49

c

The. Team reviewed a sample of ongoing maintenance

tasks and evaluated the technical adequacy of

prescribed testing. In three of the examples re-

viewed, the planned testing was not adequate to

ensure proper performance of the task. and com-

plete correction of the problem:

(1) Testing identified for the replacement of

i

the fuel pool cooling pump _ and _ motor under

MR 86-109, included only motor current and

vibration monitoring.

No pump head / flow

test was specified.

(2) The package for replacement of a safety 4

related 4160-VAC bus leekout relay under

MR-88-110

initiall/

contained

only

the

general guidance which should have been used

for development of detailed testing. Subse-

quently, suggested testing verified only a

portion

of the lockout relay functions.

(3) Post-maintenance testing following repair of

a motor operated valve limit switch under MR

88-10-179 was also not adequate to ensure

that

the

prcblem

had

been

completely

corrected.

In response to the Team's f_indings, the licensee

Maintenance Section Manager audited task-ready MR

packages and identified one additional case of

inadequately specified testing.

In each of the

above instances, the licensee subsequently de-

veloped and performed adequate post-work tests.

Discussion with the personnel involved and main-

tenance department management revealed that no

training on the newly developed post-work testing

procedures and guidance had been corducted. The

licensee immediately briefed appropriate super-

visors and workers on the program, and committed

to complete formal training in this area by

September 9, 1988.

A second potential contrib-

utor to the problem in planning post-work tests

is the press of business, particularly in the

planning area, in that the planners are currently

just able to keep pace with the schedule for

field activities.

Liensee management appeared

to be sensitive to this issue. The Team reviewed

an additional sample of in process and completed

MR's and did not identify any further problems.

_

__

_ _ _ _

' "

n

'-

50

Overall, the Team concluded that the licensee has

established a . thorough post-work testing program

demonstrating a sound safety perspective.

Al-

though sne program is generally well implen;ented,

some problems were noted.

The newness of the

program, the current press of business, and some

weakncss in personnel training appear to be af-

t

fecting its implementation. Therefore, this area

requires continued licensee attention.

3.3.3

Cor.clusions

1

The licensee has established a viable maintenance organiza-

tion.

Allocated staffing levels have been substantially

increased and are sufficient to support routine maintenance

,

activities. Of particular significance is the addition of

i

first-line supervisory positions, and the creation of an

'

expanded maintenance planning and scheduling division. The

licensee has been largely successful in filling previously

,

vacant positicas.

One exception is the staffing of the

l

maintenance planning division. While none of the permanent

staff in this area is in place, the licensee is effectively

i

utilizing contractors to perform tae function. Full staff-

,

ing and training of the planning division is important to

improving its overall ef fectiveness. Aggregate management

and supervisory qualifications were also found to be

,

adequate.

!

'

Newly revised maintenance and post - ek testing program

procedures provide significantly impre..d control and dccu-

mentation of field activities.

They also result in an

increased emphasis on detailed job planning. Observations

by the Team indicate that implementation of the program is

j

generally effective.

Some

implementation problems are

.

evident; however, the problems affect production and not

i

the ov.'ity of completed work.

Additional attention to

post-w rk test program applicrtion by the licensee

is

needed.

'

t

The licenseo appears to have identified and properly pri-

oritized outstandino maintenance tasks, with only minor

,

F

'

exceptions noted.

A process to ensure continued proper

[

prioritization has been established.

Both licensee senior

r

L

management and maintenance section management are using a

set of indicators to monitor performance.

i

!

,

!

L

t

!

..

.

51

In summary, the licensee's current maintenance staff and

program are adequate to suppo-t plant operations.

Con-

tinued close licensee management monitoring of the newly

implemented program will be required until

additional

experience is gained. The long-term supaort programs, such

as preventive maintenance, will requir : licensee enhance-

ment to further strengthen performance.

l

l

I

l

)-

1

.

o

a

52

3.4 Surveillance Testing and Calibration Control

3.4.1

Scope of Review

The Team reviewed the licensee's administrative controls

and implementation of the surveillance testing and cali-

bration control program to assess its adequacy. As part of

this review, the Team examined the licensee's corrective

action to address past problems which included:

ef fec tive-

ness of test scheduling; the technical adequacy of proced-

ures; and lack of centralized control of the program.

The

inspection consisted of a review of various procedures,

drawings, and records; observations of testing in progress;

and personnel interviews.

3.4.2

Observations and Findings

3.4.2.1

Master Surveillar

Tracking Program

i

The Team reviewed the licensee's program for the

control and evaluation of surveillance testing

and calibration required by the Technical Specif-

ications (TS), inservice testing (IST) of pumps

and valves required by 10 CFR 50.55.a(g), ans

calibration of other safety related instrumenta-

tion not specified in TS.

The program is pre-

scribed by Procedure No.

1.8,

"Master Surveil-

lance Tracking Program." The Systems Engineering

Division Manager has overall adminsitrative re-

sponsibility for the Master Surveillance Tracking

Program (MSTP). A plant Surveillance Coordinator

has been assigned within the Systems Engineering

Division to implement the program, which includes

reviewing and approving the various lists, sched-

ules, and reports generated by the MSTP, and

maintaining the MSTP data base.

Each division

has appointed a Division Surveillance Coordinator

to interface with the plant Surveillarice Coor-

dinator.

The

plant

Surveillance

Coordinator

meets weekly with the Plar t Manager to review the

.

status of the surveillance program.

The purpose of the MSTP is to ensure the timely

perfnrmance of all surveillance testing.

The

MSTP data base contains information such as:

commitment reference (TS, preventive maintenance,

regulatory commitment,

etc.);

the

applicable

procedure number and title; scheduler interval

and basis; the group responsible for performing

_

-

,-

,

53

the test / calibration; and the date last performed,

the next due date, and the last date by which the

surveillance test must be completed (plus 25%

date). Completed tests are rescheduled to ensure

the combined grace period for any three consecu-

tive tests does not exceed 3.25 times the spec-

ified surveillance interval'

The accuracy of the

data base was verified by a contractor during the

current outage. Procedure No. 1.8 contains spec-

ific controls on changing any of the data fields

in the MSTP data base to maintain its accuracy.

,

In addition, a second contractor verification of

the MSTP data base is scheduled to be performed

in the near future.

The Team selected several

TS-required surveillance tests to ensure that

they are in the MSTP data base, that' approved

procedures existed, and that the test frequency

was proper.

No discrepancies were identified

with the data base during the Team's review; how-

ever, the Team was concerned with a potential

problem involving the schedulir;g of once per-

operating-cycle versus once per-refueling-outage

tests, as discussed below.

As part of its review, the Team examined the pro-

cess established by Procedure No. 1.8 to deter-

mine its adequacy in ensuring that surveillance

tests were properly scheduled and performed with-

in the required time period.

A "Division List"

is issued to each division and to the Control

Room Annex each Friday which provides a schedule

of tests due for performance the following week.

A "Monthly Forecast" is also issued weekly to

assist the Section Managers in planning and

scheduling resources. When a surveillance test

is satisfactorily completed, the Control Room

Annex copy of the Division List is signed off.

Daily,

the

Planning and Scheduling Division

transcribes the completion dates and updates the

MSTP data base. A "Surveillance Day File Report"

is issued daily to identify all changes made to

the MSTP data base since the last time the report

was issued. This report is reviewed by the Plant

Surveillance Coordinator and used to verify pro-

per transcription and data entry.

"Variance

Reports" are issued weekly to Section Managers to

_

E.

.

x

a

54

identify those

surveillance

tests

that' were-

scheduled, but not performed. A written explana-

tion as to why the tests were not performed with-

~

in the required time and why it's act.eptable not

to perform the test is sent to the surveillance

coordinator within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of receipt of the

Variance Report.

A "Priority Notice" is issued

for any surveillance test that has reached its

deadline date (plus 25% date) and that has not

been performed by that date to assist in the pre-

vention of TS violations.

Failure to perform a

TS-required surveillance test on the deadline

date requires submission of a Failure and Mal-

function Report.. The Team reviewed samples of

each of the above reports, and their responses,

and concluded that the program was adequate and

contained sufficient checks to ensure that sur-

veillance

tests

were

completed

within

the

required time.

Although the Team found the administrative con-

trol and implementation of the MSTP to be ade-

quate, it noted a commitment by licensee manage-

ment to improve the program.

These improvements

include:

replacing the Division Lists with task

cards to reduce the potential for transcription

errors; adding an alert notice when a scheduled

test is not performed; improving the scheduling

of conditional surveillances; planning for the

addition of a full-time surveillance engineer;

and instituting an equipment history computer

program capable of trending surveillance /calibra-

tion results on individual components.

The Team identified one concern during its review

related to the scheduling of once per-operating-

cycle versus once per-refueling-outage surveil-

lance tests.

The Pilgrim Technical Specifica-

tinns define an operating cycle as the interval

between the end of one refueling outage and the

,

end of the next subsequent refueling outage.

A

refueling outage is the period of time between

the shutdown of the unit prior to refueling and

the startup of the plant after that refueling.

The TS contains some surveillance requirements

that are specified to be performed once per oper-

ating cycle, while there are others, such as

testing the drywell-to-suppression-chamber vacuum

breakers, which are to be performed during each

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ - _ _ _ _ _

,

.o

r

'55

refueling outage.

Also, all the safety-related

instruments not specified in the TS are cali-

brated once per refueling outage. As part of a

previously identified issue, the licensee has

defined once per-operating-cycle to be 18 months;

i

however, no clarification has been provided for

once per-refueling-outage.

As a result, there

are

several

once per-refueling-outage

tests /

l

calibrations which were performed in 1986 and

1987 which are currently scheduled on the MSTP

for

the

"next

refueling

outage," which

is.

projected for some time in 1991.

i

Therefore, by strictly interpreting the defini-

tions, the interval for some of the once per-

t

refueling outage surveillance tests could be as

long as four or five-years. The Team pointed out

that this appears to be beyond the intent of the

TS.

The Team also noted that a licensee task

force established to determine system operability

prior to restart had also identified this issue

and recommended that evaluations be performed on

the once per-refueling-outage surveillance tests

to determine if and when they should be reper-

formed.

The * 'censee committed to evaluate the

status

of

the

once-per-refueling-surveillance

tests and provide justification for those tests

not rescheduled, prior to restart.

3.4.2.2

Logic System Functional Test and Simulated

Automatic Actuation Procedures

The

Team reviewed

the

procedures

listed in

Appendix 0 of this report to determine the ade-

quacy of the licensee's performance of logic

system functional

tests (LSFT) and simulated

,

automatic actuations (SAA). The review consisted

of the indicated channel / train of the primary

containment

isolation

system (PCIS)

and

the

reactor core isolation cooling (RCIC) system LSFT

and SAA, and the diesel generator (DG) initiation

LSFT.

The procedures were reviewed against the

'

system drawings to ensure that they were tech-

!

nically adequate, that all relays and contacts

were tested, that the procedures were properly

,

approved, and that the tests were performed at

,

the required frequency.

The licensee uses a

series of overlapping tests to satisfy the LSFT

.

, -

c.

c

s

G

56

1

?

and SAA. The Team noted that the licensee had a

"

,

contractor review the adequacy of the LSFT and

SAA tests during this outage.

The contractor

identified several deficiencies, which were cor-

i

rected.

The Team found that each procedure re-

viewed was technically adequate and that the

testing sequence satisfied the Technical Specifi--

cation LSFT and SAA frequency and scope require-

ments.

The Team also noted that the format of

the procedures was adequate and included:

en-

vironmental' qualification quality control (QC)

witness

points

on

transmitter

calibrations;

i

<

double verification on lifting and landing leads;

!

fuse holder fit checks; and I&C management review

upon test completion prior to the NWE review.

i

Ouring the review of the RCIC isolation subsystem

LSFT, the Team questioned why there was no LSFT

on initiation logic. The Team acknowledged that

it was not required by TS Table 4.2.B

nor was

credit taken for it in the FSAR.

However, TS 3.5.0.1 re.Jires RCIC be operable (with reactor

pressure greater than 150 psig and coolant tem-

perature greater than 365 degrees F) and the TS

definition of system operability requires that

all subsystems also be operable.

This would

include the RCIC initiation logic.

Also, the~

guidance provided by the Standard Technical Spec-

ifications indicates that an LSFT on the RCIC

initiation logic should be performed every six

l

months. The Team noted that Procedure No. 8.M.2-

2.6.7,

"RCIC

Simulated Automatic

Actuation,"

actually performs an initiation logic LFST; how-

ever, it is scheduled at a once per-18-month fre-

!

quency, while TS-required LSFT's have a frequency

l

of once per 6 months.

This item is unresolved

,

i

pending a licensee evaluation of the adequacy of

i

the RCIC initiation logic LSFT frequency (88-21-

i

02).

The licensee committed to pcovide, before

i

restart, the technical basis for the surveillance

[

frequency.

3.4.2.3

Calibration Procedures

7

!

The Team noted that the licensee established a

!

series of procedures, known as the 6.E series, to

calibrate the safety-related instrumentation not

p

,

specified in the Technical Specifications.

This

,

_ _ _ _ _ _ _ _ - _

__ .

.

.

57

instrumentation is normally used to record data

necessary to complete TS required surveillance

i

tests or inservice testing of pumps and valves.

The 8.E procedures are scheduled on a once per-

refueling-outage interval.

The Team performed a detailed review of Proced-

ures No. 8.E.11, "Standby Liquid Control System

Instrument Calibration," and 8.E.13, "RCIC System

Instrument Calibration." Overall, the Tecm found

i

the technical content and format to be adequate;

'

however, two discrapancies were identified.

Pro-

cedure No. 8.E.11 does not calibrate pressure

indicator (PI) 1159.

This PI was installed dur-

.'

ing the current outage and is used in the per-

formance of Procedure No. 8.4.1, "Stendby Liquid

'

Control Pump Operability and Flow Rate Test."

The Team also noted that Procedure No. 8.E.13

does not calibrate PI 1340-2. This PI is used in

the performance' of Procedure No. 8.5.5.1, "RCIC

,

Pump Operability Flow Rate and Valve Test 9 1,000

psig."

PI 1340-2 was installed and last cali-

brated during the 1984 outage when pressure

i

transmitter 1360-19 was replaced with a Rosemount

Transmitter.

The licensee indicated that the

i

procedures .sould be

revised to correct the

l

deficiencies.

1

3.4.2.4

Survefilance Test Observations

'

,

.

On August 16, 1988, the Team observed a portion

'

of the performance of Procedure No. 8.M.2-2.10.

1-5,

"Core Spray System

'B'

Logic Functional

!

!

Test," Revision 13.

The test was performed as

!

j

part of the restoration of the

"B" Core Spray

l

j

System and as post work testing of relay 14A-

K208.

The test was observed to ensure it was

'

performed in accordance with a properly approved

'

and adequate procedure.

During the test, the

i

Team noted that the technicians' performance was

t

,

.

adequate. They conducted the test in a slow and

deliberate manner and stopped when questions

,

arose concerning mislabelled nameplates and the

'

identification of some relay coil leads.

In both

i

cases, the questions were resolved before they

proceeded.

The Team noted that the I&C first-

line supervisor monitored portions of the test.

.

The test was also monitored by QA personnel as

part of the surveillance monitoring program. QA

i

personnel indicated that they observe approxi-

j

mately one surveillance test a week.

~

'

.

.\\

l

t

l

1

. - - _ , - _ - - , - , -

. . , , , , , , . _ - , . - . _ , - _ , , , , . - . - , _ _ . , , , _ . - . , , _ , . ,_,

- . , _ ,

, . . , ,

. - - ,

--

..,,,e

. --

.

.

_

_

_

~4 f:

9

~

,

-58

i

The test was stopped at Step 25 when the test

results did not agree with the expected results

delineated in the procedure.

The step was sup-

posed to verify the instantaneous pickup of the

-

core spray pump start relay 14A-K128. Subsequent

,

licensee investigation revealed that the instan-

taneous pickup was removed as part c,f the de-

graded grid voltage modification (Plant Design

Change (PDC) 88-07).

The Team noted that PDC

.

88-07 had not yet been closed; however, an impact

!

review performed prior to installing the modifi-

cation failed to identify Procedure 8.M.2-2.10.

1-5 as being affected by the PDC.

The Team noted that one of the licensee's self-

assessment action items was to review the impact

of PDC's

(installed

since October

1987) on

"

L5FT's.

The

licensee's

review

began

on

October 1987 because this was the completion date

,

of the contractor review noted above which ver-

ified the adequacy of LSFT/SAA tests.

The Team

3'

noted that the contractor review produced an

i

LSFT/SAA data base which cross references the

'

safety-related components tested to the appli-

cable LSFT/SAA test.

This data was being used

during the licensee's review.

Four of the five

PDC's involved in the licensee's review of impact

on LSFT's have been completed. The remaining PDC

(88-07) was under review when the problem with

the core spray LSFT was noted.

Twenty-one pro-

i

cedures have been identified as possibly being

'

affected by the PDC and are currently under

review.

The CS functional te3t appears to be the

only affected test run prior to completion of the

!

PDC procedure review,

t

The licensee indicated that a possible future

'

improvement will be to use the LSFT/SAA data base

e

l

to determine the impact of a PDC on procedures

before implementing the modification.

j

.

3.4.2.5

Measuring and Test Equipment

The Tea;n reviewed records, interviewed personnel,

and toured storage areas to determine the ade-

quacy of the licensee's program for control of

measuring and test equipment (M&TE). Administra-

'

tive control of the program is established by

,

l

Procedure No.

1.3.36,

"Measurement

and Test

'

Equipment."

i

. - - _ _ _ _ - _ _ _ _ _-.

- _ - _ _ _

,

-.

59

,

!

,

The licensee has implemented a computerized sys-

.

tem to issue and track M&lE.

This system will

only allow issuance equipment to authorized per-

-

sonnel, will limit the checkout period to only 24

!

hours, and will not issue M&TE if the sticker

r

calibration date does not match the calibration

date in the computer. The system also issues a

PATE traveler form to the user to identify usage

on each plant device tested and each M&TE range

used.

This data is later entered into.the com-

-

puter to assist in evaluations if and when a

l

piece of M&TE is found to be out of calibration.

The Team reviewed two cases where M&TE was out of

calibratinn and noted that the evaluations per-

formed were documented in accordance with proced-

ures

and appeared thorough.

Thus far, only

electrical I&C and electrical PATE are on the new

computerized system; however, similar controls

are being manually implemented for mechanical

equipment until it is incorporated into the new

system.

,

The licensee currently has two storage areas for

l

M&TE:

ene for electrical /I&C and one for mech-

,

anical equipment.

The Team toured each area and

a

noted that the equipment was identified by a

unique number and indicated calibration status.

,

The Team found that the equipment was properly

stored and that P4TE out-of-calibration, on hold

i

for repairs, or new equipment not yet in the sys-

tem, were properly identified and segregated.

i

The licensee indicated plans to go to only one

storage arer and to increase the number of staff

!

issuing and controlling the P4TE.

'

i

!

The Team also reviewed the system for recalling

)

equipment for calibration.

The recall tracking

!

is performed in accordance with Procedure No,

t

1.8.2, "PM Tracking Program." The Team reviewed

l

,

severa' equipment calibration stickers during its

,

tour of the storage areas and during observations

I

of ongoing surveillance and maintenance activ-

t

ities.

No equipment past its calibration due

date was identified.

'

1

The Team found the licensee's control of measur-

ing and test equipment to be adequate.

L

{

r

!

l

L

!

I

1

.

.

.

. -

_ _ _ _ _ _ _ _ .

__

_ _ _ _ .

_____ ___

,

a

60

3.4.2.6

Inservice Testing of Pumps and Valves

The Team reviewed the status of the licensee's

program for inservice testing of pumps and valves

in accordance with the ASME Boiler and Pressure

Vessel Code,Section XI.

The licensee submitted Revision 1A to the inser-

vice test (IST) program on October 24, 1985.

A

meeting was held between BECo and the NRC on

January 14, 1988, to discuss the licensee's pro-

posed Revision 2 to the IST program. To minimize

impact on the NRC review cycle, the licensee sub-

niitted an interim IST program, Revision 18, on

March 14, 1988, to address concerns identified by

the NRC during review of Revision 1A. The licen-

see plans to subm!t Revision 2 af ter the Safety

Eva'.uation Report on Revision IB is issued. Pe-

vision 2 is to maintain the upgrades made to the

program in Revision 18 and increase the program

scope by adding more components

(e.g.,

relief

valves).

Control of the IST Program is established by Pro-

cedure No.

8.I.1,

"Administration of Inservice

Pump and Valve Testing."

The Team reviewed the

procedure and noted that while it defines the

,

methodology for compliance to the IST program for

pumps and valves, including analysis of test

data, direction on corrective action, and estab-

l

lishment of reference values (additional guidance

is contained in Procedure No. 8. I .3, "Inservice

Test Analysis and Documentation Methods"), the

organizational

responsibilities and referenced

IST program revision need to be updated.

For

example, the pump and valve testing is now sched-

uled through the MSTP instead

f.,f

the compliance

group, and a Senior ASME Test Engineer has been

hired to implement the program.

The licensee

acknowledged the Team's comments and showed it a

.

draf t revision to Procedure 8.I, which is sched-

uled to be implemented when Revision 2 is submit-

ted.

The Team reviewed the draf t procedure and

noted that

it provided additicnal detail on:

_ _ - _ _ _ _ - _ _ _ _ _ .. _ __-

,

.

61

responsibilities, definitions, test requirements,

compliance requirements, evaluation, disposition,

post-maintenance testing, and administration and

records maintenance.

The draft procedure also

provides a listing of the pumps and valves cur-

rently within the testing program and includes a

cross-reference for individual test requirements

to the approved PNPS procedure.

The Team noted that other improvements (planned

or in progress) to the IST program include revis-

ing all the implementing procedures to upgrade

them to Revision 2 and creating a position for a

second ASME test engineer.

The Team reviewed several pump and valve test

results for the standby liguid control, core

spray, salt service water and low pressure cool-

ant injection systems to verify that the accept-

ance criteria were met, that the results were

properly evaluated and trended, and that the fre-

quency of testing was increased when required.

The Team noted that Procedure No. 8.I contains

controls to change the MSTP data base test fre-

quency when the deviations fall within the alert

range. The Team reviewed changes to various pump

reference values to ensure that they were justi-

fied and documented.

The Team also checked the

reactor buildirg closed cooling water, salt ser-

vice water, and standby liquid control system

pumps to ensure that the IST vibration data point

was properly marud.

No deficiencies were iden-

tified during this review.

3.4.3

Conclusions

Based on observations, personnel intervieus, and the review

of procedures and records noted above, the Team concluded

that:

,

1.

The licensee has established and is implementing an

adequate and effective program to control all surveil-

lance activities at PNPS.

2.

Responsibility for implementing the MSTP has been

p! aced

in

a

centralized,

strong,

forward-looking

division.

_-

q

O

O

62

3.

The licensee was adequately implementing the IST pro-

gram for pumps and valves.

The Team noted that there

are several

planned

improvements

to

the

program

involving administrative and implementing procedures

and staffing to upgrade the IST program.

4.

Licensee management is committed to improve the sur-

veillance program,

as

evidenced by

the upgrades

planned or in progress in each area examined.

These

include:

contractor data base reviews; increasing the

scope of the IST program, increasing staffing; im-

proved control over issuing and tracking M&TE; estab-

lishing an equipment history computer program; replac-

ing the MSTP division lists with task i:ards; and

improving conditional test scheduling.

S.

With the exception of the few deficiencies noted

above,

the

procedures were

technically

adequate.

6.

The one concern identified was the licensee's need to

resolve

the

once per-refueling-outage

scheduling

deficiency.

i

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _

D

O

63

3.5 Radiation Protection (RP)

3.5.1

Scope of Review

The Team reviewed various aspects of the radiation protec-

tion program during the inspection, with emphasis on the

licensee's ability to safely support plant startup.

Per-

formance was determined from:

observation of work in

progress; periodic tours of plant areas; interviews with

managers,

supervisors,

and technicians; and review of

selected documents.

The areas reviewed are as follows:

1) Organization and staffing;

2) Training, qualification and continuing education of RP

technicians;

3) General employee training;

4) ALARA programs;

5) Control and oversight of work in radiological areas;

6) Control of locked high radiation areas;

7) Acequacy of laboratory (count room) equipment;

8) Availability and

adequacy of portable

RP survey

equipment;

9) Adequacy of gaseous and liquid release monitoring

systems;

'

10) Clarity and consistency of RP policies and procedures;

11) Audits.

3.5.2

Observations and Findings

'

3.5.2.1

Organization and Staffing

i

.

The organization of the radiation protection (RP)

department has remained stable since the signifi-

cant changes which were made early in 1983. The

i

staffing level has remained constant and is ade-

quate to support plant operations.

The RP soc-

tion

marager

described

various

enhancements

_ _ - _ _ - _ _ _ _ _ .

p

a

64

planned for the supervisory staff.

An outline

for qualification as Radiation Protection Man-

ager, per Regulatory Guide 1.8,

has been ap-

proved. One or two division managers within the

RP section will be expected to qualify as Radia-

tion Protection Manager to provide depth in the

organization.

Incentives have been approved for

achieving this qualification.

In addition, the

three division managers will rotate assignments

for cross-training purposes, and all will be

encouraged to pursue advanced scholastic degrees.

These efforts are expected to begin in the near

future.

The Team observed some indications of isolated

morale problems at the technician and first-line

supervisor level which were attributed to several

causes.

Contributors include personnel and as-

signment changes within the organization result-

ing from rotation of radiation protection shif t

supervisors, an influx of new technicians, im-

pending implementation of a new rotating work

.

schedule, and a perceived lack of management

presence in the field.

In addition, weaknesses

may exist in communications within the RP organ-

ization as evidenced by technician perceptions of

a lack of technician input or review during the

development or revision nf RP policies and pro-

cedures.

In summary, and in spite of these dif-

.

ficulties, the Team observed that the technicians

and supervisors were generally enthusiastic and

competent.

Another potential weakness results from the prac-

tice of rotating technicians through job assign-

ments each three to six months.

Although this

practice may have merit for familiarization and

job exposure purposes it may prevent or signifi-

cantly delay the development of a high profici-

ency

level

in certain

specialized

technical

areas, a concern particularly evident in the

instrument repair and calibration facility. Here

the RP technician is assigned to repair and cali-

brate a wide range of instrumentation, including

gas flow detector cells, sophisticated computer-

controlled automatic friskers, air pumps, and all

alpha, beta, gamma and neutron survey meters.

The area supervisor stated that he was attempting

to resolve this problem by requesting an exten-

sion of the rotation cycle.

1

i

--

, , _ _

__

__._._.--,_.c

.-_

- _ _ - _ _

__

i

d

.

65

~.

The RP section has 42 technicians, of whom 36 are

ANSI 18.1 qualified.

Only 21 have commercial

experience. The section manager provided a shift

staffing schedule for power ascension testing

that will ensure that the experience will be

adequately distributed among the individual shift

Crews.

3.5.2.2

RP Technician Training

The RP technician training and qualification pro-

gram is certified by the Institute of Nuclear

Plant Operations (INPO), uses INPO guidelines for

development of instructional material, and uses

the INPO exam question bank.

The training is

conducted in three phases over a period of two

years or less, depending on experience.

Upon

completion of Phase 2,

the technician .is con-

sidered to be ANSI qualified and can issue radia-

tion work permits.

The third phase includes

specialty tasks such as operation of the whole

body counter and respirator fit testing.

Classroom training is provided at the offsite

facility. The training facilities were adequate,

well lighted, comfortable and equipped with prac-

tice equipment.

The Team observed that most of

the basic survey instruments were available, but

laboratory-type gamma spectroscopy equipment, as

well as ALARA mock-ups, were not available. This

is typical of a single unit station.

Most pre-

sentations appeared to rely on lectures with

minimal use of audio-visual equipment. A review

of selected lesson plans showed adequate tech-

nical content.

Classroom training is followed by an in plant

phase where the technician receives on-the-job

training and demonstrates proficiency at various

tasks.

This is documented in a qualification

.

folder.

Qualified technicians will be provided

with ongoing training on a six-week schedule.

This will be contingent on implementation of a

new six-section rotating work schedule.

The

,

,

66

training department has begun drafting lesson

plans which will cover a broad range of topics,

including interpersonal

skills training.

The

instructors must also complete formal qualifica-

tions.

They were recently required to begin

spending a certain number of hours in plant be-

tween training cycles.

This keeps them abreast

of changes occurring in the plant.

The Team concluded that this program is well-

controlled and documented and is aided by a dy-

namic first-line supervisor.

The implementation

and effectiveness of cycle training will be eval-

uated in the future.

The licensee's current ef-

forts are directed at completing initial qual-

ification for the entire staff.

3.5.2.3

General Employee Training (GET)

All general employee training and in processing

is conducted at the on-site training center over

a three-day period.

Classrooms were spacious,

comfortable, and well equipped.

Ample training

aids, as well as audio-visual equipment, were in

evidence.

A comprehensive student manual

is

given to each trainee along with copies of appro-

priate regulations and regulatory guides.

Basic

training involves 20 contact hours, while radia-

tion workers receive an additional 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />.

Res-

pirator fit testing is also provided.

The two instructors associated with GET had com-

pleted the formal

Staff Development

program.

Both have extensive experience and are well qual-

ified. Although their teaching techniques could

not be observed since no classes were in session

during the week of this review, the Team con-

cluded that the training content provided ade-

quate direction to attendees.

Both instructors

spend time in the plant weekly to assess staff

training needs.

The GET training is INPO certified. In addition,

the training center offers five courses to all

new supervisors. A new industrial safety train-

ing program is under development. An instructor

has been hired and will begin providing training

in occupational safcty during the first quarter

of 1989.

- - .

.

.

67

The Team concluded that management support of GET

training was good, that the training was effec-

tively conducted, and that it made a positive

contribution to safety.

3.5.2.4

ALARA Programs

ALARA performance at this station had been a

persistent weakness over several past SALP report

periods.

The Team noted recent apparent improvement in

upper management support for ALARA programs.

Examples of this support are reflected in the

re-evaluatien of the 1988 ALARA goal from 600 to

390 manrem and formulation of 'iveral plans to

reduce exposures. Also, the licensee is assign-

ing an experienced manager to survey INPO, Elec-

tric Power Research Institute (EPRI), and several

other nuclear stations to make a list of cost-

effective exposure source term reduction tech-

niques.

The Station Director will then formulate

a long-term program based on the findings of this

survey.

Another plan is to begin removal of

abandoned in place systems in 1989 which should

remove unnecessary sources of exposure. A th'rd

project is underway to identify hot spotr in

plant piping and determine which of these could

[

be reduced by flushing.

The ALARA staff also has plans to attend a train-

ing course and visit other stations to observe

effective techniques.

This staff

i s in

the

process of filling its final vacancy.

,

'

,

ALARA performance at the working level remains

mixed. Licensing personnel developed a technique

for conducting remote inspections of fire barrier

penetrations using a flashlight mounted on a

telescope.

This concept may ta appiled in num-

,'

erous situations and has the potential for sig-

nificant dose savings.

On the other hand, in-

stances of f ailure to effectively use low-dose

waiting areas were observed during work.

The

ALARA divisicn manager is working to increase the

.

sensitivity of all workers and technicians to

l

ALARA practices.

(

!

!

l

,

l

..g

- _ _ - , - - -

gm

_ _ _ _ _ _ _ _

._ __

,

.

63

The Team concluded that licensee attention to

ALARA programs has significantly improved in

recent months.

The effectiveness and implemen-

tation of AL\\RA plans will be assessed in future

NRC inspections.

3.5.2.5

Control of Work

During closure of a Confirmatory Order in the

fall of D87, NRC noted some improvement in the

r91ations between the RP section and the other

sections performing work. However, poor planning

and lack of work control continued to be ob-

served.

During this assessment, further improve-

ment in resolving these weaknesses was observed.

One indicator of poor planning is the number of

radiation work permits (RWP) issued but not used.

A review found that only a small fraction of

RWP's issued are now unusad.

In addition, the

use of "A" priority maintenance work requests by

the Operations Department to expedite work has

decreased significantly.

The use of a Radiation Protection Advisor as-

signed to the Maintenance department continues to

be effective. This position was recently assumed

by an experienced RP technician.

He has intro-

duced innovations, including frequent work group

training sessions and installation of permanently

situated boxes in the plant for ccntaminated

tools.

The Planning Division is developing improved pro-

cedures for planning work.

This section is re-

sponsible for coordinating with the RP and ALARA

groups during the early phases of work planning.

This allows adequats time for RWP preparation and

ALARA

re*

isponsible

section managers

stated tt

'N

arly maintenance-HP contact

,

will be pr.u

s' ted ir. September 1988.

The Team observed that on-the-job cooperation

between workers and RP technicians was good.

A

minor problem ,vas noted in that RP technicians in

the controlled area appeared unprepared to deal

with a minor first-aid injury.

Technicians were

___

.-_

_ _ _ _ _ _ - . .

.

>

69

uncertain in dealing with a worker with abrasions

to his nose that caused bleeding.

This was at-

tributed by the Team to a lack of training snd

clear policies.

On the other hand, technicians

appeared well prepared to handle more serious

emergencies,

i

3.5.2.6

Control of Locked High Radia_ ion Areas

The

licensee has previously incurred several

violations for failure to properly control locked

high

radiation

areas.

This

issue has

been

tracked as a NRC outstanding item (87-57-01).

The licensee organized a task force to determine

which lasting corrective actions would prevent a

i

recurrence of these problems. Based on the find-

ings of th- task force, the control procedures

were revised to placa basic responsibility on the

RP technician who signs out the door key.

Fur-

i

ther controls are provided by shift tours of all

locked areas and by upgrading locking devices.

Gased on these actions, the Team concluded the

licensee had appropriately addressed concerns ir.

this area.

3.5.2.7

Laboratory Equipment

The adequacy and availability of RP laboratory

-

equipment to support plant startup was reviewed.

The

licensee

has

available

two multichannel

analyzers

(Nuclear Data

6700),

several

beta

counters (BC4), and several alpha counters (SAC

<

t

4).

The radiochemistry laboratory has redundant

,

equipment for backup. This equipment is required

to perform isotopic analysis of air samples for

maximum permitted concentration (MPC) calcula-

'

tions, detection of degraded fuel conditions, and

to support radwaste analysis. Procedures for the

use of the

equipment are available

in

the

laboratory.

The Team noted that, at the time of the inspec-

tion, several pieces of laboratory equipment wert

awaiting repair or calibration.

Only ;ne BC-4

i

and one SAC-4 were operational in the lab.

Both

nultichannel

analyzers

were

awaiting

repair

parts.

The supe tisor in charge attributed this

to the lack of proficiency of the technicians due

to the rotating work assignment policy.

This

issue was discussed in Section 3.5.2.1.

-

.

.

70

3.5.2.8

Survey Equipment

The svailability of properly calibrated survey

equipment was reviewed. Survey equipment is used

by RP techniciant, to measure dose rates, and sur-

face and airborne contamination levels.

Included

in the review were the automatic personnel con-

tamination detectors.

All equipment is calibrated and repaired in a

facility on site, eFCept for neutron survey

meters.

RP technicians are trained to perform

all

functions in the facility.

The facility

appeared to be adequately equipped to perforhi its

task,

s

Stocks of equipment ready for issuance appeared

ample and the calibration / repair backlog was

minimal.

This readiness may have been aided

somewhat by reduced outage activity.

The Team

noted an improvement in that the new manager of

the g"oup has recently implemented a computer

program that shows the status of each piece of

equi pme ri t , the data base for which is updated

each time an instrument is issued.

Information

that is captured includes users of the meter,

calibration due date, and failure mode if placed

out of service.

The Team concluded that an adequate supply of

calibrated instruments is on hand te <;pport

routine

operation.:

and

abnormal

c cm. '.i o n s .

3.5.2.9

Monitoring Environmental Releases

The operability of the environmental

release

monitors was verified.

The two paths for a gas-

eous release are the main stack and the reactor

butiding vent.

The monitors were fouiid to be

operational

and

properly

calibrated,

with

approvea procedures available. The eculpment is

ile the cal-

maintained by the Chemistry Group

'

culations of offsite doses require

oy the re-

<ised Radio

ical Environmental Technical Spec-

ifications

StTS)

are

performed

by

the

RP

seation.

- .

-

-

_

x,

e

O

71

The s'ngle liquid release path monitor was oper-

ational.

Due to elevated background radiation

levels at the sodium iodida e.anitor, a new system

has been installed parallel to the old system.

The new system will offer increased sensitivity

and will be tnught on line in the near future.

3.5.2.10 Policies and Procedures-

-

A sampling of RP procedures indicates that they

ara generally clear.

The number of procedures

controlling

the RP department

activities

is

extensive. However, the format varies from step-

by-step instructions to a more general format.

The RWP procedure is currently being revised to

make the process less cumbersome and more useful.

In general, the RP technicians Md not feel ade-

quately consulted during the revi.ston of proced-

ures.

This

issue was discussed

in

Section

3.5.2.1.

The Team concluded that ;,he RP procedures were

adequate to support startup.

3.5.2.11 Audits

Previous inspections found the licensee's inter-

nal audits and asssessments of the RP program

-

were primarily compliance-oriented.

Currently,

these audits are completed in several ways. Sev-

eral peer evaluators were trained to make on the-

job observations.

A Radiological Assessor is

permanently assigned to the staff reporting to

the Senior Vice President.

The Management Over-

sight and Assessment Team (MO&AT) does monthly

plant tours.

Also, the QA Dr,artment recently

transferred in two expertene.

etP personnel.

In

addition to the above audits and reviews, the

Radiological Occurrence Report (ROR) system pro-

vides a method to capture input from workers and

RP technicians.

A review of these efforts shows that a moderate

level of success has been achieved in finding

program weaknesses.

However, the results i. ave

not been commensurate with the ef' ort involved.

The RP section manager stated that an ef fort is

. .

_ _ _ - _ _ _ _ _ _ _

,

72

,

underway to shift the emphasis of these audits to

performance rather than compliance.

The audit

performed by QA in November 1987 is being used

as a model.

Licensee efforts in this regard are

expected to be long term and are adaquate at this

time to support plant startup.

3.5.2.12 Control of Radiological Shielding

The Tear reviewed the licensee's program for the

,

installation, control, and removal uf radiation

'

shielding. This review concluded that the licen-

see's program for control of radiation shielding

is well documented and that implementation is

good.

The prograr.; guidelines are contained in PNPS Pro-

cedure 6.10-008, "Installation and Removal of

Shielding." Responsibility for implementation of

the procedural requirements fall under the aus-

pices

of

the

Radiological

Technical

Support

'

Division.

The procedural requirements for con-

'

trolling this process appear well defined and

comprehensive.

Licensee personnel

responsible

for implementation of the procedure were well

versed on procedural requirements and current

field installations.

l.icensee records of field

it.stallations were current, had been reviewed at

the required intervals, and were accurate.

3.5.2.13 Health Physics Training

The Team observed licensee personnel during a

i

contamination control

training exercise.

The

'

exercise simulated a spill of highly radioacLive

(3 Rem on contact) resin during transfer opera-

l

tions.

The scenerio document was well defined

-

and included detailed timelines and instructions

to the exercise controllers. The entire exercise

i

was videotaped and replayed during the debriefing

[

.

of participants.

The exercise was well control-

led and interviews with participants indicated

i

that the individuals involved considered it to be

'

an effective training device.

Lessons learned

and feedback frnm participants appeared to be

well disseminated.

,

,

4

i

t

._

-..

.

. . -

_ _ . _ - . _ , _

._

_

. _ .

_ _ _ _

,

.

73

l

3.5.2.14 Hydregen Water Chemistry System

The licensee has installed a system to inject

hydrogen gas into the fcedwater to reduce the

potential for corrosion of ieactor internal pip-

ing.

This process will result in increased radi-

ation levels onsite from increased radioactive

nitrogen isotope levels in the system. A review

of the impact analysis showed that a comprehen-

i

sive plan to control exposures has been developed.

A test run i.1935 resulted in the installation

of a 16-foot high 20-inch thick concrete shield

around the turbine.

Moreover, special controls

are programmed into the computer that controls

the hydrogen injection.

The cognizant engineer

stated that tFese controls are designed to pre-

vent increased exposure either onsite or of fsite.

Team review of these calculations showed that

J

doses may in fact be lowered.

The Training Department is developing a training

program for the RP technicians to review the

l

change in '.adiation levels that occur with opera-

tions. This program was developed to refresh the

RP technicians because of the extended shutdown

1

and the increased levels of radiation in the

shielded areas resulting from the addition of

'

hydrogen.

The RP section manager stated that a

condensed revision of these presentations will

also be given to all maintenance and operations

personnel prior to startup.

3.5.3

Conclusions

The Team determined that progress has been made, that ade-

quate staff and management oversight is in place to achieve

further progress, and that performance is adequate to sup'

port plant startup.

ticenset

strengthr. include a well-controlled and well-

,

organized training program for general employees and RP

technicians.

The use of an RP Advisor in the Maintenance

Section, which had been effective in improving working

relationships, has led to further initiatives in training

and control of :ontaminated tools.

The addition of this

ocsition has also resulted in improved nianning and control

of work.

-

-

-

-

.

.

_ , _ _

- - -

.

.

74

Notable progress was observed regarding upper management

support and emphasis on ALARA.

This attention is expected

to result in improving levels of performance over the next

few years.

Staff development programs for all levels of

personnel, from technicians through managers, should con-

siderably improve their level of performance.

Control of

technical problems, such as the radiological impact of

hydrogen water chemistry and calibration status of survey

meters, has improved.

A weakness was observed as a result of the rotational as-

signment of RP technicians that may affect eheir profic-

1ency in performing certain highly specialized jobs.

An

additional weakness concerns the perception of poor ver-

tical communications between management and RP technicians

and workers. Although this issue has led to some incom-

plete understanding of policies and some morale problems,

it has not significantly affected safety

performance.

Additionally, vertical communications within the RP organ-

ization appeared somewhat weak.

The Team detected a per-

ception on the part of technicians that they have not been

adequately involved in the changes being made in the RP

Department policies and procedures.

This perception ap-

parently has resulted f rom RP management not effectively

communicating the b.ses for these changes to the staf f.

There is also a perception that RP management is remote and

not easily accessible. However, the Team determined that,

despite this weakness, the attitude and safety approach of

the RP Departmeat staff has significantly improved and is

adequate to support plant operations.

The licensee advised that a training program is being

developed to refresh RP technicians concerning the change

in radiological conditions on plant startup and the unique

conditions to be created by the addition of hydrogen. A

condensed version of this training will be provided to

other radiation workers. Cempletion of this effort will be

reviewed in a future NRC inspection.

.

O

..

.

- _ _ _ _ _ _ _ _ _ _ _

,

.

75

3.6 Security and Sateguards

3.6.1

Scope of Review

Prior to the plant shutdown in Anril 1986, NRC had identi-

fled serious concerns regarding the implementation and

management support of the security program at Pilgrim.

The

licensee has been aggressively pursuing a comprehensive

course of action to ider.tify and correct the root causes of

the programmatic weaknesses in physical security. The most

recent SALP (50-293/87-99) covering the period February 1,

1987 to May 15, 1988, determined that the licensee has

demonstrated a commitment to implement an effective secur-

ity program. The licensee's security organization has been

expanded with the addition of experienced personnel in key

positions, significant capital resources have been expend.:1

to upgrade security hardware, and equipment and progr m

plans base been improved.

During the IAT inspection, all phases of the security pro-

gram, including management support, staffing, organization,

and hardware maintenance, have been reviewed to assess the

eff ectiveness of the program implementation.

The results

of the review are described below in general terms to

exclude any safeguards infor.sation.

3.6.2

Observations and Findings

3.6.2.1

Review of Security Program Upgrades

The Team reviewed the progress made to date on

the security program improvements committed to by

the licensee as a result of previous NRC enforce-

ment action.

The Itcensee was advised by the

Team that progress on these improvements will

continue

to be monitored during

future NRC

inspections.

Those commitments and their status

are as follows.

.'roject

Status

.

Protected Area

The upgrades of tne perimeter

Perimeter

barrier, intrusion detection

system,

and assessment aid

system are complete.

- _ .

_

-

_ _ _ - _ _ _ _ _ _ _ . - . .-. _

__. _ . _. _ _ .

_ _

___

_ _ _ _ _ _ _

_ . _ _ _ .

.

.

76

Project

Status

Protected Area and Installation of upgraded

Perimeter Lighting

lighting is approximately 95%

complete.

Four light stan-

chions remain to be instal-

led.

The lighting system as

i

installed

meets

regulatory

requirements.

Main and Alternate The

designs

for

the

new

i.

Access Control

(upgraded)

access

control

Points

points are complete and new

package search equipment is

on site. Installation of new

package and personnel search

equipment

and

full

length

turnstiles is scheduled for

completion on

September 28,

1988, in the site's main ac-

cess point.

Installation of

new package search equipment

in the site's alternate et e-

cess point is also scheduled

for September 28, 1988.

Vital Area

The vital area analysis,

Analysis

including walkdown

of

all

vital areas to verify barrier

integrity,

and issuance of

.

'

the

report,

is

complete.

New Security

The selection of the new

Computer

computer has been made and a

purchase order for the com-

puter has been issued.

The

'

licensee is currently working

with the vendor on software

,

options.

The delivery of the

!

new computer is scheduled for

the first quarter of 1989,

l

with installation to follow.

,

,

I

L

_ _ _ _ _ _ _ _ _ -

.

.

77

3.6.2.2

Followup on Previously Unresolved Item

(Closed)

Unresolved

Item

(50-293/87-44-01):

Neighborhood checks for licensee employees being

assigned to the site were not being consistently

conducted as part of the access control program.

The neighborhood checks were not a regulatory

-

requirement

and

it

is

a

licensee-identified

issue. During this inspection, the Team verified

that the licensee has conducted a review and

identified all site personnel who had not been

subjected to neighborhood checks.

For those

employees with less than three years of service

with the licensee, neighborhood checks were s';b-

sequently conducted.

For employees with more

than three years with the company, a review of

the personnel file was conducted and a memorandum

was put into the file to indicate that the review

was being made in lieu of the netchborhood check.

The acceptability of this alternative to the

neighborhood checks was reviewed by NRC prior to

its implementation and was found satisfactory.

3.6.2.3

Security Plan and Implementing Procedures

The Team met with licensee representatives and

discussed the NRC-approved Security Plan (the

Plan).

As a result of these discussions, and a

review of the Plan and its implementing proced-

ures, the Team found that the implementing pro-

cedures adequately addressed the Plan's commit-

ments.

In addition,

all

security personnel

interviewed demonstrated familiarity with the

L

Plan, implementing procedures, an- NRC's security

program performance objectives.

1

3.6.2.4

Management Effectiveness - Security Programs

'

An in-depth review of the licensees management

ef fectiveness was conducted by NRC in April and

May 1988 and documented in Inspection Report No.

1

50-293/88-18.

During that inspection, the Team

concluded that the licensee has continued with

its initiatives at' taken significant actions to

further improve the effectiveness

1 security

organization.

It was also cor.

that the

i

existing organization should provive the capa-

bility to monitor the program properly.

<

t

P

-

.

.

.

_ _ _ _ _ _ _ _ _ _ _ _. _.

._

.

o

78

During its inspection, the Team independently

concluded that there is a strong management team

in place based on the experience of the expanded

proprietary security organization, the effective

interaction both between members of the security

organization and with other departments, and the

effective oversight of the contract security

organization.

3.6.2.5

Seci~ity Organization

On

ugust 16,1988, at 10:00 p.m.,

the security

con ractor

for PNPS was

changed

from Globe

Security Systems to the Wackenhut Corporation.

The Team reviewed the licensee's and the contrac-

tor's transition plans, and interviewed numerous

management and union security personnel prior to

the transition. Also, the Team was onsite during

the

transition for direct observations.

The

transition was somewhat simplified by the fact

that all Globe employees that applied for posi-

tions were retcined by Wackenhut.

The

Team

determined that, because of comprehensive transi-

tion planning, the change in the contract secur-

ity force was accomplished without any compromise

of security and with minimal disruption to secur-

ity operations.

!

3.6.2.6

Security Program Audit

The Team reviewed the monthly corporate audit

reports. These c

it reports were of gotd qual-

ity and were generated as a result of corporate

oversight of the site security program.

The

i

findings in these reports were minor and not

indicative of any major programmatic problems.

The corrective actions were appropriate for the

findings.

3.6.2.7

Records and Reports

.

The Team reviewed various :ecurity records, logs,

,

and reports, including patrol logs, central alarm

l

station (CAS) logs, visitor control logs, and

testing and maintenance records.

All records,

legs, and reports reviewed were complete and

maintained as committed to in the Plan.

!

l

l

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

o

79

3.6.2.8

Testing and Maintenance

The Team reviewed the testing and maintenance

records and procedures.

The review disclosed

that the preventive maintenance procedures were

comprehensive and that the licensee now has in-

place a program that provides for prioritization

of security maintenance by the security depart-

ment.

The maintenance support to the security

department has improved as a result of the secur-

ity department assigning priority to the mainten-

ance work.

The use of compensatory measures for

inoperative equipment is minimal.

3.6.2.9

Locks, Xeys and Combinations

The Team reviewed the installation, storage, ro-

ta ' ion and related records for all locks, keys

ano combinations and determined that the licensee

was meeting the commitments in the Plan and its

implementing procedures.

3.6.2.10 Physical Barriers - Protected Areas

The Team physically inspected the protected area

l

barriers. It was determined by observations that

the barriers were installed and maintained as

described in the Plan. Progress on upgrading the

barriers is addressed in Section 3.6.2.1 of this

section.

3.6.2.11 Physical Barriers - Vital Areas

The Team physically inspected the vital area bar-

riers and determined that the barriers were

installed and maintained as described in the

Plan.

3.6.2.12 Security System Power Supply

The Team reviewed the security system power sup-

,

ply system and determined that it was in accord-

t

ance with Plan requirements. The Team noted that

as a result of the approval of a recant Plan

!

revision, improvements for protecting the secur-

ity power supply are wnderway, with wo-k expected

i

to be completed by September 28, 1933.

!

I

>

f

i

. _ _ _ _ _

- . _ _ _ _ _ - _ _ _ - _ _ _ - _ _ _ _ _ _

_ _ _ _ _ _ _ -__

._ _

_ _ _ _ _ _ _ _ _ _ _ _ - _ _ - - - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _

,

.

80

3.6.2.13 Lighting

The Team observed lighting within the protected

area. All areas were lighted in accordance with

commitments in the Plan.

Progress on upgrading

the lighting is addressed in Section

3.6.2.1.

3.6.2.14 Compensatory Measures

,

The Team reviewed the licensee's compensatory

measures and determined that their use to be con-

i

sistent with the commitments in the Plan. As a

result of the security program upgrades addressed

in Section

3.6.2.1,

the need for compensatory

measures for degraded security equipment has been

dramatically reduced.

Further reductions in the

7

use of coripeasato 'v measures will occur as pro-

ject upgrades are t spleted.

!

3.6.2.15 Aasessment Aids

The Team reviewed the licensee's use of assess-

l

t

ment aids and Jetermined by observation that the

I

assessment aids are installed, functioning and

i

maintained as committed to in the Plan.

Progress

on upgrading the assessment aids is addressed in

Section 3.6.2.1.

3.6.2.16 Access Control - Personnel and Packages

The Team reviewed the access control procedures

for personnel and packages and determinti that

they are corisistent with commitments in the Plan.

This determination was made by observing person-

,

nel

access

processing

during

shift

changes,

visitor access processing, and by interviewing

l

security personnel about package access proced-

!

ures.

The status of upgrades in the access con-

(

trol points is addressed in Section

3.6.2.1.

'

[

'

.

3.6.2.17 Access Control - Vehicles

Tna Team reviewed vehicle access control proced-

ures and observed vehicle searches at the Main

i

Vehicle Gate.

It was d;t.>rmined that vehicle

[

searches were being conducted consistent with

i

commitments in the Plan.

I

i

I

I

i

i

!

t

-

-

-

- -

- - -

-

-

.

-

-

.

- -

-

-

-

-

-

,

.

81

3.6.2.18 Detection Aids - Protected Area

The Team observed penetration tests of approxi-

mately 25% of the licensee's intrusion detection

system on August 17, 1983. The remaining 75% was

not tested during this inspection; however, pre-

vious test records were reviewed and the records

indicated that the system was operating as de-

scribed in the Plan and implementing procedures.

3.6.2.19 Detection Aids - Vital Area

The Team observed the testing of intrusion detec-

tion aids in selected vital areas and determined

that they wer? installed and functioning as

committed to in the Plan.

3.6.2.20 Alarm Stations

The Team observed the operation of both the Cen-

l

tral Alarm Station (CAS) and the Secondary Alarm

l

Station (SAS) and found them to be in accordance

c

i

with Plan

commitments.

During

the

previous

inspection (50-293/88-16), a concern was identi-

fied that the licensee was diverting an alarm

station monitor f rom security duty to respond to

t

i

fire protection system and health physics alarms.

'

During

the

IAT

inspection,

the Team noted

improvements in that there is a marked decrease

in the number of nuisance alarms, as a result of

the removal of the fire door and health physics

doors from the security alarm system.

L

3.6.2.21 Communications

I

The Team observed tests of all communication

capabilities in both the CAS and the SAS.

The

Team also reviewed testing records for the vari-

ous means of communications available to security

force members and found them to be as committed

,

to in the Plan.

I

3.6.2 ;2 Training and Qualification - General Requirements

The Team reviewed the licensee's Training and

Qualification Plan and teplementing procedures

and determined that they we re be'.ng implemented

i

as committed to in the Plan,

t

t

,

_ _ _ _ _ _ _ - _ _ _ _ _ _ _

_.

.

o

82

3.6.2.23 Safeguards Contingency Plan Implementation Review

The Team reviewed the licensee's Contingency Plan

and implementing procedures and determined that

all exercises were being performed by the secur-

ity organization as committed to in the Plan.

3.6.2.24 Protection of Safeguards Information

The Team reviewed the protection and handling

procedures for Safeguards Information (SGI) and

determined that the licensee had completed an

inspection of each office onsite that handled and

stored SGI.

The inspection result, indicated

that the SGI assigned to each of fice was accoun-

ted for and was being stored in accordance with

established licensee procedures.

3.6.3

Conclusions

A comprehensive review of the licensee's security program

determined that the licensee has established and is imple-

menting a significantly improved seeJrity program over that

which existed when the station was shutdown in April 1986.

Upgrades to the security program include a greatly expanded

proprietary security organization, major installation of

state-of-the-art equipment, improved security maintenance

support, and upgrades to plans and procedures,

i

l

i

. _ _ _ _ _ _ _ _

- . _ _ _ _ _ _ _ _ _ _

__

_ _ _ _

.

.

83

3.7 Training

3.7.1

Scope of Review

The Team assessed the scope, quality, and effectiveness of

the licensee's training programs.

Included in this review

were the licensed and non-licensed operator training pro-

grams and the programs for technical and general training

of the plant staff.

3.7.2

Observations and Findings

3.7.2.1

Operations Training

Operations Training Programs are outlined in PNPS

Nuclear Training Manual, T-001, Part 3, and have

received

INPO

accreditation.

The Operations

Training Programs include initial and requalifi-

cation training for licensed operators, initial

and continuing training for non-licensed opera-

tors, Shif t Technical Advisor (STA) training, and

SRO certification training.

The Team reviewed

these programs and discussed various aspects of

the programs with members of the licensee's

training and operation's staff.

The Team re-

viewed eight Operator and Senior Reactor Operator

training records to verify compliance with Sec-

tion 3.5.5 of the Training Manual.

To evaluate

l

the effectiveness of the training programs, the

l

Team observed classroom and simulator training;

interviewed licensed operators and senior opera-

tors, non-licensed operators and STAS; reviewed

several training evaluation and feedback forms

from classroom and simulator training conducted

during the current requalification cycle; and

observed ongoing operations in the plant.

Overall, the Team determined that the Operations

Training Programs are adequate and effective.

Classroom and simulator training observed ap-

.

peared to be effective.

Instructor preparation

was good and the lesson plan content was com-

plete.

During cbservations of classroom training

for PDC 88-07 involving the degraded voltage

modification, the Team noted that the depth of

knowledge being presented was adeqaste and stu-

dant participation was encouraged. After obser-

ving the conduct of the annual simulator opera-

t.ng exam, the Team noted improved coraunications

_-

_ _ _ _ _ _

._

_

_ _ _ _

__

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ - _ _ _ _ _ _ _ _ _ _ _ _

_ _ _ _ - _

_ _ _ .

.

.

84

s

between meners d the operating crew.

In addi-

tion, the Hm noted the simulator examination

was also bei. , observed by licensee upper manage-

ment.

Discussions with training and operations

personnel confirmed that strong upper tranagement

attention and support for all aspects of the

Itcensed training programs is evident.

Inter-

views with licensed operators indicated that

overall they a re very satisfied thi t training

programs are well-suited to their needs, and that

the programs are responsive to their feedback.

Operators indicated that the training program has

greatly improved over the past year with the

incorporation of simulator training

into the

requalification program.

Discussions with Operations Training staff 4.a-

cated sufficient staffing to conduct training

programs.

Thirteen instructors are

currently

receiving Senior Reactor Operator (SRO) certif t-

cation training and are expected to be fully cer-

tified by the end of 1988

The use of experi-

enced PNPS instructors instead of contractors for

the operations training programs should enhance

the quality of the licensee's programs as well as

contribute to the depth of in-house operational

expertise.

Recent additions to the licensed requalification

program include the incorporation of Emergency

Operating Procedure (EOP) proficiency training.

This includes at least 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> devoted to E0P

review ir, the classroom and/or simulator during

each 32-hour segment of the program. (Each oper-

ator normally receives one segment of requalifi-

cation training every five weeks. )

Also, the

exam structure at the end of each session has

been nodified to include written and simulator

operating exams, which will aid the training

staff in determining the effectiveness of the

programs on a more frequent basis.

In addition,

the training staf f appears to carefully track

attendance in req;alification training to assure

that everyone required to attend is trained in

each module

of

the

requalification

program.

,.

- _ - _ _ _ _ _

_.

,

e

85

4

The operation's training staff appears to have a

very effective working relationship with the

operations department.

They meet to discuss

training needs on a frequent caris.

Through

these meetings, the training department anpears

able to sufficiently track and schedule the

licensed training either required or requested to

be completed prior to restart.

In addition, the

operation's department often provided support

l

during simulator examinations.

'

The Team reviewed the licensee's special training

,

program for the sixteen licensed operators (14

RO's and 2 SRO's) who currently hold NRC licenses

which are limited pending on-watch training dur-

ing the Power Ascension Program. The Team dis-

cussed various aspects of the program with mem-

,

bees of the licensee's training and rperations

'

staff.

The Team noted that the licensee has

established a structured and supervised program

to assure completion of NRC requirements to allow

removal of the individuals' license limitations.

.

Following a discussion with the Team regarding

plans for ensuring that each operator performs a

sufficient number of reactivity manipulations,

the licensee representative stated that en at-

tachment to the special program would be added to

further clarify what constitutes an acceptable

manipulation.

The Team observed

the

operations department

staff on four days of consecutive shift rotation.

These observations verified the overall effec-

'

tiveness

of training.

For example, on-shift

.

'

communications, an area of emphasis in simulator

training, was formal and effective.

However,

during a walk-through with an equipment operator

(non-licensed) of E0P Satellite Procedure 5.3.26,

t

the Team noted several discrepancies in the pro-

,

cedurt.

It also noted that the E0 and an SRO

-

misunderstood a step in the procedure.

Upon

l

investigation of these problems, the licensee

determined that a decision to train only the E0's

and not the licensed operators on the field por-

tion of the ratellite procedures contributed to

the misunderstanding. These issues are discussed

in detail in Section 3.2.4

!

!

!

t

,

!

I

.

.

--

-

-

i

w

.

t

1

86

,

Additional Team followup of the problems found

during the above-mentioned procedure walk-through

identified a weakness in the licensee's method of

determining the need far additional training on

new procedures and procedure changes. The licen-

see's current method incorporates review of ORC

meeting minutes to determine newly approved pro-

cedures or procedure changes requiring training.

However, a delay of 30 to 45 days is not unusual

between the meeting and the distribution of for-

[

mal minutu.

Tor example, Procedure 5.3.26 had

been revised since equipment operator training

was conducted in March and April 1988. The ORC

meeting minutes which addressed this procedure

change had not been received by the training

department as of August M. 1938, 42 days af ter

the ORC meeting on July 6,1988.

The Team discussed the issue with a licensee

training department representative who stated

that the department recognized this concern and

was preparing to implement, in October 1988, a

more timely method for cetermining the needed

training.

During the inspection, the licensee committed to

accelerate implementation cf certain features of

the improved program, such that the training

,

department will become aware of procedure changes

l

within soproximately one day following the ORC

l

meeting.

This will allow the training staff the

opportunity to review the precedure changes end

determine the need for training prior to issuance

of the approved procedure.

If the

training

i

]

department determines that training is required

prior to issuance of the procedure, the depart-

i

ment will have the ability to delay the proced-

i

ure issuance. The licensee representative stated

that .o inta.ed as k iri.tiwtion detailing this

,

process was being written and would be approved

'

by ORC within about a week.

In additica, the

l

training staff will revis, their backlog of ORC

i

recting minutes to determ ne which procedure

,

changes have not been addressed and will take

j

appropriate action. These actions planned by the

'

licensee appeared very responsive to the Team's

concerns.

I

.

l

,

l

i

.

.

.

. .

.

. .

. .

.

.

. -

.

.

.

. .

.

1,

87

3.7.2.2

Technical and General Training

Nuclear Training Manual, T-001, Parts 4 and 5,

outline the licensee's technical and general

training programs.

Included are training 3ro-

grams in maintenance, health physics, chemistry,

fire brigade, emergency plan, supervision, and

technical training for staf f and managers,

ihe

Team reviewed these programs and discussed var-

ious aspects of them with members of the licen-

see's training, technical, and supervisory staff.

To evaluate the ef fectiveness of the training

1

programs, the Team observed classroom instruc-

tion;

interviewed

radiological

controls

and

radiological chemistry (radchem) technicians, QA

engineers and first-line supervision; reviewed

classroom training evaluation and feedback forms;

and observed ongoing work ir. the plant.

Overall, the licensee's training programs were

found to be adequate.

Classroom training ob-

served appeared to be effective and student

participation was strongly encouraged.

In-house

staffing for those training programs appeared

more than sufficient.

The following relatively

new training programs are indicative of licensee

!

initiatives to develop employee skills:

apprentice programs for maintenance, health

--

physics,

and rad chem technicians;

and,

technical

training

for

newly

assigned

--

supervisors.

Additional

training

programs

currently being

developed in industrial safety and safety aware-

ness, along with the licensee's CPR program, show

the licensee's positive attitude in those areas.

The Team's observations of work in the plant dur-

.

ing this inspection verified the averall training

effectiveness. However, inadequacies in mainten-

ance post-work testing appeared to be the result

of lack of training for the maintenance planning

group and first-line supervisors on the post-work

testing portion of the new maintenance program

(See Section 3.3.2.6).

i

. , _

s e

_

.

.

83

3.7.3

Conclusions

The 11:ensee's training programs appear to be very good.

Team findings in all functional areas indicated overall

'

effectiveness of the training implemented.

Examples of

areas where training may have needed to be conducted sooner

include E0P satellite procedures and the post-work testing

program.

A weakness was identified in the licensee's

method of determining training needed for new procedures

and procedure changes.

The licensee appears to have made a strong commitment in

the area of licensed operator training, as exemplified by

increased staffing, simulator use in requalification train-

ing, strong interface between training and operations man-

agement, and increased attention and support from upper

management.

In addition, the creation of new programs for

supervisors and apprentices reflects an effort by the

licensee

to effectively

promote

employee development.

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ .

.

.

89

3.8 Fire Protection

3.8.1

Scope of Review

The Team's evaluation of the fire protection program

focused on the maintenance of fire protection equipment,

the reliance on compensatory measures for degraded equip-

ment, and the performance of personnel on the fire brigade

and standing fire watches.

3.8.2

Observations and Findings

.

Licensee senior management established a station goal of

reducing the number of open fire protection corrective

maintenance requests (MR's) to 40 from a high of 300. This

,.

goal was reached in June 1988.

This reduction is indica-

tive of the overall improvement of the material condition

of fire protection equipment and systems.

The number of

MR's began climbing two weeks before the IAT inspection,

and reached 63 during the second week of this inspection.

The increase was mainly for low priority MR's.

l

Fire protection MR's are tracked as a stction performance

r

indicator and this increasing trend received prompt senior

i

management attention.

Tha licensee is currently contract-

ing to bring in additional fire protection maintenance sup-

port by the end of August 1933.

The fire protectinn man-

ager meets daily with operations, maintenance and planning

,

sections to schedule MR's and develop the station's work

,

plan.

The Team concluded that the licensee is giving

proper management Attention to itre protection MR's.

l

There are over 5,000 fire barrier penetration seals at

PNPS.

The licensee's tagging system has been effective in

identifying these penetrations, with no untagged penetra-

i

tions or degraded penetration seals observed by the Team.

The number of fire watch postings has been reduced from 145

a year ago to 45 prior to this inspection.

Fifteen of

these remaining postings will be eliminated by changes to

the fire protection program which are currently being

i

reviewed by NRC.

Another twelve will be eliminated when

the licensee completes Engineering Services Request (ESR)

'88-339, "Alarm delays on non-vital CAS alarms."

This ESR

will provide a means to electronically monitor fire doors

,

without undue distractian of security personnel from their

'

'

primary function. The remaining 18 fire watch postings are

due to degraded (quipment for which repairs are currently

l

!

being planned.

I

l

l

l

_ _ _ _ _ _ _ _ _ _ _ _

__

_

.

.

t.

90

Because TS's allow one individual to rove and cover more

than one fire watch posting, the number of people on shif t

committed to fire watch activities is substantially lower

than 45.

Two personnel per shift are assigned to cover

these fire watchos. In discussions with the Team, the fire

watches appeared knowledgeable about their duties.

The

Team reviewed several fire watch postings in the plant and

identified no concerns.

All fire watch rounds were com-

pleted on schedule.

The Team observed the on-shif t fire brigade respond to an

unannounced fire drill. The drill scenario was a simulated

main transformer fire with a concurrent failure of the

deluge system.

The brigade leader developed a successful

fire fighting strategy.

The brigade members responded

promptly in full fire fighting gear.

Communications be-

,

tween the brigade and the control room appeared to be ade-

q t.a t e . The fire brigade's first-line supervisors observed

the deill on their own initiative.

The fire protection

training instructor was also found to be knowledgeable and

ent.husiastic about the training program.

"

3.8.3

Conclusions

Effective management by the fire protection manager and

support by senior management are shown by the attention

given to the material condition of fire protection equip-

ment and reduced reliance on compensatory measures for

degraded equipment. Completion of licensing actions and an

ESR will further reduce the number of fire watch postings.

There is good identification and control of fire barriers.

Personnel assigned fire watch and fire brigade duties are

knowledgeable about their duties and perform them properly.

The

f' re protection division is well

staffed to meet

program needs.

,

i

i

)

-

_ _ _ _ _ _ _ _ _

r

,

.

91

3.9 Engineering Support

3.9.1

Scope of Review

NRC found licensee engineering support to be strong in the

past two SALP reports.

Because of this history of good

i

performance, engineering support was not selected as a

specific area of focus for this inspection.

Instead,

observations relative to engineering support were made by

the Team while it inspected the other functional areas.

3.9.2

Observations and Findings

The Team found that engineering support to the facility is

generally very effective.

In particular,

the

Systems

Engineering Division functions well to meet plant needs.

Also, engineering support to maintenance has improved and

is eahanced by the improved maintenance work process and

the effective performance of the maintenance engineers.

The Team noted that a number of technical issues, including

some NRC open items, as well as licensee-identified items,

require NED resolution before plant restart.

They are

being tracked and pursued for resolution by NED.

During tours of the control room, the Team noted the mini-

mal use of certain human engineering features, such as

color-codes, meter "banding"

(e.g.,

marking of normal,

alert, and fail positions on meter and gauge faces), and

system lineup memory aids.

Based on discussions with NED

personnel, the Team determined that the licensee performed

a detailed control room design review (DCRDR) and received

comments on it from the NRC Office of Nuclear Reactor

Regulation.

A

supplemental

licensee D0RDR

report

is

required four months af ter the end of the current outage.

Currently, the licensee's DCRDR project has identified

about 140 proposed human engineering improvements which are

being evaluated and prioritized.

A few were incorporated

into design changes this outage.

The Team noted that some

,

of the remaining improvements were relatively simple, from

an engineering perspective, but could significantly enhance

control room human factors.

The Team asked whether'imple-

mentation of some of these items could be accelerated rela-

tive to the other, more complex items which may require

more detailed engineering and a plant outage to install.

.

l

-

-

.

___

_--

a

. _ _ _ _ _ _ _ _ _ . _ _ _ - _

.

o

92

The

licensee fndicated that these simple improvements,

categorized by the licensee as "Paint-Label-Tape," are

included in the current 1989 budget.

The licensee also

committed to evaluate control room human factors during the

Power Ascension Program and to include an update regarding

the schedule and scope of these "Paint-Label-Tape" items in

their report to NRC at the completion of the Power Ascen-

sfon Program.

The licensee was very responsive on this

issue.

The Team noted that (1) licensee personnel have

performed well in the simulator under NRC observation, and

(2) there has not been any pattern of performance problems

traceable to control room human factors.

Thus, the T:am

cancluded that the licensee's approach to this issue is

acceptable.

The Team reviewed the licensee's program for the control of

transient materials.

This review included the licensee's

methods for identifying, tracking and removing non perman-

ent equipment such as tools, gas bottles, and scaffolding

located in plant treas where safety-related equipment is

housed. The licensee currently assigns responsibility in

this area to the Systems Engineering Group (SEG). Station

Instruction SI-SG.1010 "Systems Group Systems Walkdown and

Area Inspection Guidelines," details the licensee's program

for controlling transient materials. Materials so identi-

fied during weekly walkdowns by system engineers are docu-

mented and are either removed or their presence justified

in writing.

If the material is allowed to remain in the

process building, a seismic missile hazard analysis is per-

formed under Station Instruction SI-SG.1015

"Dotential

Seismic Missile Hazard," and appropriate measures are

implemented to ensure that the materials are properly

secured.

The licensee is compiling a data base which

identifies transient eaterials which must be removed prior

to startup.

The program appears to be comprehensive and

,

adequate.

l

During plant tours, the Team questioned the licensee con-

cerning the installation of splash shields and personnel

barriers in the areas of safety-related instrumentation.

.

Specifically, the Team questioned the seismic response nf

ti,e structures and the effect they may have on safety-

related structures.

l

l

l

I

_.

-..

- --

--__,, -

-

_ _-_

- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

.

93

The fire water spray shield was installed during the cur-

rent outage.

This plant design change was processed under

current

licensee

procedures

which

require

a

seismic

response analysis prior to modification approval.

P9rson-

nel barriers installed during the mid-1970's recently had

seismic analyses performed on their current configurations.

These analyses found them satisfactory.

Based on this information and on a review of licensee docu-

reentation, the Team had no further questions.

3.9.3

Conclusions

'the Team concluded that engineering support continues to be

effective and identified no weaknesses.

The Itcensee has

committed to evaluate potential near-term improverrents in

control

room human engineering during power ascension

testing.

l

l

i

h

4

- - , --

-

, . , , - _ , - , - . , , _ , . _ _ , , _ , _ _ . , _ . - _ - . , , _

,,..,,._,------_,-,,_n

e-

.,

, -- ,

y

g. :,g

, _ _ _ - - - - - - - _ - - _ - -

_

--

. - - - - - - - - -

-- _ ---- ------- --- -- - - . _ -

- - - _ - - _ --

- - - ---- --- ------

o

.

94

3.10 Safety AssessmentfQuality Verj,fication

3.10.1

Scope of Review

The objective of this irspection was to evaluate the ef fec-

i

tivenass of the licensee's t

assessment programs.

The

inspection focused on determining whether these programs

contribute to the prevention of problems by stonitoring and

evaluating plant performance, providing assessments and

findings, and communicating and following up en corrective

action recommendations.

The inspection consisted of a

documentation review, personnel interviews, and observa-

tions of meeting and work.

3.10.2

Nuclear Salety Review and Audit Committee

The Nuclear Safety Review and Audit Committee (NSRAC) is an

independent body responsible for performing senior-manage-

ment-directed

reviews

of activities

affecting

nuclear

safety. The NSRAC reports to the Senior Vfce President

-

Nu: lear (SVP-N).

Membership on the committee is composed

of senior

licensee management

personnel

augmented by

consultants.

The Team reviewed the NSRAC procedures manual, Technical Specification 6.5.B

meeting minutes, audit reports, and

associated NSRAC reports and correspondence. The Team also

attended

a

full

NSRAC

trueting

at

the

station

on

August 2, 1988.

A review of the committee meeting minutes for the period

between January 1987 and June 1988 verified that Technical

Specification requirements have been met with respect to

the composition, duties, meeting frequencies, and responsi-

bilities of the committee.

The composition and charter of

the committee was significantly revised in February 1938.

The selection process for members was designed to assure a

broad-based, independent review of facility activities and

to minimize the potential for cost and schedule pressures

to influence the committee's reviews and findings.

The

current committee is made up of ten eenbers appointed by

the SVP-N

Of the ten members, five are consultants, in-

cluding the Committee Chairman.

Only two members of the

committee hold line responsibility for operation of the

plant. Only one member, also a consultant, belonged a year

ago. To enhance the perspective of the new members, the

licensee implemented an annual training program. The Team

was provided with a t strix indicating the ev.cerience of

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

_ _ _ _ .

O'

0

,

,

95

i

current committce members relative to Technical Specifica-

tion requirements and verified the committee collectively

possesses a broad based level of experience and competence.

The committee charter, as detailed in NSRAC Procedure

101-1, also does not. allow the use of alternate members,

although these are allowed by the Technical Specifications.

Af ter a review of recent membership changes, and discuss-

ions with the NSRAC Ceordinator, the Team r ified that the

collective competence of the committee monborship has been

maintained as changes were made.

NSRAC currently conducts meetings approximately once a

~

month.

Since the beginning of 1988, seven meetings have

been conducted, six of which were held at the site.

This

is significantly more than the once per-six-months minimum

required by the Technical Specifications. Three additional

meetings are scheduled for 1988.

In addition, individual

subcommittees may hold additional meetings at the site.

NSRAC also intends to meet at the site in September with

several key members of station management to review restart

preparations and plans to provide its own independent

recommendations for restart readiness.

NSRAC uses subcommittees ef fectively to review specific

areas of interest. Currently, six subcommittees are estab-

lished:

(1) safety evaluations;

(2) operations /mainten-

ance; (3) training / security / fire protection; (4) radiation

control / chemistry / emergency preparedness; (5) quality over-

view; and, (6) engineering / technical. Each subcommittee is

chaired by a NSRAC member, and is composed of additional

personnel appointed by the committee.

The subcommittees

provide reports to the full committee during their ;ched-

uled meetings.

The subcommittees are especially usef ul in

performing documentation review to allow more time for open

discussions at the meetings.

A stronger NSRAC involvement in station accivities is evi-

dent not only in the recent site meetings and effective use

of subcommittees, but also in scheduled site tours and

audit participation.

The NSRAC has established a schedule

for individual committee members to perform station tours

and report the results to the full committee.

NSRAC has

also designated

individual

members

to participate in

selected QA audits throughout the year.

The Team reviewed selected audits conducted under the

cognizance of NSRAC, which are required by Technical

Specifications. The audits reviemed were thorough, timely,

and the noted deficiencies have been corrected or are being

tracked. The audit reports reviewed included a third party

assessment of the adequacy of the QA program, and QA audits

.

o

o

i

96

of

Technical

Specifications,

administrative

controls,

operations, chemistry, radiation protection, and inservice

testing.

In addition, special audits were recently con-

ducted concerning shutdown from outside the control room,

the salt service water system, and NSRAC activities.

The current committee has an effective formal tracking

system for all "concerns" forwarded to management and com-

'

mittee

followup

items.

The

"concerns"

reviewed were

clearly transmitted to the SVP-N.

However, review of

,

recent meeting minutes by NRC revealed that a number of

"recommendations" had been forwarded to the SVP-N, but a

formal response had not been received.

The committee also

di.d not formally track resolution of these recommendations.

Further investigation by the NSRAC Coordinator determined

that although the items had not been tracked, the specific

recommendations had been implemented, or were incorporated

into another corrective action process.

,

Ouring NSRAC Meeting 88-04, conducted on May 24, 1983, the

Operations and Maintenance Subcommittee presented a report

on the conduct of the Operations Review Committee (ORC).

,

NSRAC raised concerns over whether the ORC was fully meet-

'

ing the intent of its duties required in the Technical

Specifications. The report identified four specific find-

ings of deficiency. They included:

'

Inadequate method of reviewing changes to safety-

'

-

related procedures;

i

Lack of ORC prepared reports resulting from ORC inves-

-

tigation of a Technical Specifications violations;

,

Lack of specific review and reports of facility oper-

I

-

ations by ORC; and,

!

Lack of formality in the conduct of ORC meetings.

-

Af ter the discussion, NSRAC concurred that the ORC perform-

ance issues should be formally raised as a concern to the

,

SVP-N. Tha NSRAC concern (88-04-01) was transmitted to the

SVP-N on May 27,1938.

The concern stated that NSRAC's

'

.

overall assessment was that ORC's conduct and administra-

tion needed substantial improvement.

Specifically, the

!

concern stated that the established process did not appear

j

to foster adequate depth and discipline for substantive

indepandent reviews. In addition, NSRAC noted that of the

[

40 meetings cenducted in 1933 prior to the review, neither

l

the Station Director nor the Plant Manager had attended,

l

based on its review of the meeting minutes.

'

I

!

I

!

(

- -

- -

_ - _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _

,

97

The NSRAC concern was responded to on June 22, 1988.

In

response, the Station Director initiated revisions to the

ORC Charter and Procedure 1.3.4, "Procedures," to accur-

ately describe the specific methods by which ORC met the

procedure and operations review requirements.

In addition,

the

Station

Director

attended

an

ORC

meeting

on

June 22, 1988, and is considering additional initiatives to

improve the conduct and administration of ORC activities.

N5RAC closed the concern at the August 2, 1988 meeting, but

initiated a followup item to continue to monitor ORC per-

formance.

In addition, NSRAC members were encouraged to

attend ORC meetings as observers. NRC's review of ORC per-

formance 'Jentified similar deficiencies and concluded that

additior.1 actions to strengthen some ORC functions were

warranted (See Section 3.10.3).

Based on meeting attendance and review of recent meeting

minutes, the Team noted that the NSRAC reviews have been

thorough and focused on improving performance in areas

important to safety. During the August 2, 1988 NSRAC meet-

ing, the Team noted that the discussions were frank and

open, with the reviews concentrated on recurring and emerg-

ing issues.

The areas of emphasis have included 50.59

reviews, ORC performance, corrective action programs, pro-

cedure adequacy, and management depth.

Due to the limited number of "concerns" issued by NSRAC

since revision of the committee in February 1988, the Team

could not reach a conclusion on the responsiveness of the

station organization to NSRAC.

It appears at least in one

case pertaining to ORC performance, that the response was

not comprehensive.

However, all other "concerns" reviewed

were responded to adequately.

3.10.3

Operations Review Committee

The function, composition, and responsibilities of the

i

Operations Review Committee (ORC) are described in PNPS

L

Technical Specification 6.5.A.

In addition, PNPS Procedure

1.2.1, "Operations Review Committee," describes in greater

detail the authority and responsibility of the ORC at the

Pilgrim Station.

For this inspection, the Team reviewed

the

minutes

of

ORC

meetir,g s

88-40

through

88-63

(April 1,1988 through July 5,1988) and observed the con-

duct of three regularly scheduled and two special ORC meet-

ings (ORC Meetings 80-80, 81, 82, 83 and 86). In addi+1on,

the Team interviewed various ORC members and alternates.

_ _ _ _ _ _ _ _ _ _ _ _ _

. _ _ _ _ _ _ _

a

.

93

The inspection focused on whether ORC operations satisfied

current Technical Specification requirenents; whether the

ORC was meeting its responsibilities identified in PNPS

Procedure

1.2.1,

and whether the CRC was responsive to

recommendations for improvements icentified during NSRAC

and QA audits of its operations.

3.10.3.1 Compliance with Technical Specifications and

Procedures

'

By reviewing existing documentation, and through

direct observation of ORC meetings, the Team has

determined

that

the

Technical

Specification

requirements for the ORC composition, quorum,

meeting frequency, authority, and records are

being satisfied. During the period reviewed, the

Team noted that the ORC reviewed plant proced-

ure changes, plant design changes (PDCs), Field

Revision Notices

(FRNs),

and

Licensea

Event

Reports (LERs), as well as proposed revisions to

the security plan, to the inservice inspection

program, to the emergency plan and to fire pro-

tection program implementing procedures. The ORC

members and alternates are appointed by memur-

andum from the Station Director and cannot serve

on the committee until they have successfully

completed the station ORC training course.

There

is also a required reading review program used by

the Training Department as a retraining program

for ORC members and alternates.

The Team re-

viewed the training course material and deter-

mined that it bad an appropriate emphasis on

assuring safe operation as well as on regulatory

requirements.

The ORC at Pilgrim Station has been reeting

regularly every Wednesday and has a scheduled

"special" meeting every Friday on an as-needed

basis.

The ORC met an average of about twice a

week, which is well above Technical Specification

,

requirements.

While there was evidence in the minutes of dis-

cussions about LERs, PDCs or FRNs, the prepond-

'

erence of the ninutes described changes to pro-

cedures.

The Team saw no reference of ORC

reviews of Failure and Malfunction Reports.

The

ORC has a system for following issues identified

during

discussions

which

requires

a

formal

response to the ORC and a review of the response

by ihe ORC to assure that the response resolved

'

the initial concerns.

-_.

O

99

The Team reviewed the closeout process for ORC

followup items and determined that, in one case,

an item (88-58-01) may have been clo'.ed prema-

turely. During a discussien among the Team, the

ORC Chairman, the Design Section Manager, and the

Construction Division Manager, the ORC Chairman

agreed that the item should be reopened for addi-

tional review.

During ORC Meeting 88-82, the

item was reopened.

By observing the ORC, the Team concluded that the

committee members and alternates are concerned

with assuring the safe operation of the facility.

Discussions focused on the impact of items on

safety systems, as well as whether the items

being discussed met regulatory requirements or

constituted unreviewed safety questions.

The

Station Director also attended one of the regu-

larly scheduled ORC meetings during the inspec-

tion period.

During its review, the Team identified two weak-

.

nesses in the operation of the ORC. They are the

Technical Specification (TS) review of plant

operations (T.S. 6.5 A.6.e) and the TS require-

ment to investigate violations and prepare i

report covering the evaluation and recommenda-

tions to prevent a recurrence (T.S. 6.5.A.6.1).

TS 6.5. A.6 e states that the ORC ds responsible

for the review of facility operations to detect

po te;.',i a l

safety hazards while

TS 6.5.A.6.1

states that the ORC is responsible for investiga-

ting all TS violations and for preparing a report

covering the evaluation and recommendations to

prevent a recurrence.

The Team noted that ORC routinely uses the review

of LERs and Failure and Malfunction Reports

(F&MRs) to satisfy the TS required review of

plant operations and TS violations.

The Team

also noted that the ORC has appointed the Compli-

ance Division as a subcommittee to the ORC and

assigned it the responsibility et presenting

selected Failure and Malfunction Reports as weil

as the preparation of all LERs, including any

, _ _ _ _ _

O

O

l

100

involving TS violations. Copies of all LERs are

provided to the ORC as a means of satisfying

the TS requirements.

Further, PNPS Procedure

1.2.1 permits the ORC Chairman to set the time-

liness of subcommittee reports to the full ORC.

While the use of subcommittees te support ORC

!

activities is acceptable, the Team believes that

the method used by ORC in fulfilling its respon-

sib 111 ties as defined by TS 6.5.A.6.e and i needs

improvement.

In

particular,

the

Compliance

-

Division has been issuing all LERs, including

those discussing TS violations, prior to any ORC

review of the product prepared. A review of 10

LERs disclosed that ORC review of the LER occurs

usually a week to two weeks after the LER was

formally sent to the NRC. While this may satisfy

'

the timeliness requirements of PNPS Procedure

i

1. 2.1, i t does not appear that the corrective

l

actions proposed to prevent recurrence receives

the full benefit of a timely multi-disciplinary

review, as is intended by the composition and

responsibilities of the ORC.

The formal release

!

of the LER involving a TS violation by the ORC

'

subcommittee without a formal review by the com-

'

plete ORC is a weakness in meeting the require-

!

ments of TS 6.5.A.6.1.

j

'

During a review of F&MRs, which had not yet been

reviewed by ORC, the Team noted that F&MR 86-266,

'

which discussed a TS violation, had not yet been

reviewed by ORC.

f

In this case, the violation was against an admin-

istrative requirement in TS Section 6.8, and was

I

not reportable as an LER.

Therefore, the F&MR

did not result in an LER or a special report.

I

The event occurred in September 1986, and no

reports have yet been

submitted

to ORC as

required by the TS. The licensee stated that the

F&MR was still open punding completion of the

remaining corrective action, and that then a

report would be issued.

Both of these findings indicate that the ORC is

not actively participating in the timely review

of plant orerations and does not appear to pro-

vide reaningful input into the process.

____

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ -

.

O

O

101

3.10.3.2 Responsiveness to /udit Recommendations

The Team reviewed both quality assurance (QA)

audit

findings

and HSRAC

recommendations

to

determine ORC responsiveness to recommendations

for improvements to its operations.

In QA Audit

Report

87-37,

QA

listed

two

recommendations

accepted by the ORC.

PNPS Procedure 1.2.1 was

reviewed and the Team determined that PNPS Pro-

cedure

1.2.1,

Revision 21, contained the QA

recommendations.

The ORC was also audited by QA

i rem May 22 through June 22, 1988.

The audit

generated

one

recommendation

concerning

the

cross-referencing of ORC meetings with document

references.

Based upon discussions between the

QA auditor and the Team, ORC has also accepted

this recommendation.

In May 1988, the ORC received a list of four

concerns from NSRAC based upon an audit review of

the ORC.

While the nature of the specific con-

cerns are discussed in detail in Section 3.10.3

above, they are summarized here.

Specifically,

the NSRAC expressed concerns about the following

areas:

(1) the ORC review of changes to safety-

related procedures, (2) ORC investigation of TS

violations, (3) ORC review of facility opera-

tfons, and (4) conduct of ORC meetings.

The concerns related to the ORC's investigation

of TS violations and its review of plant opera-

tions are paralleled by the Team's findings dis-

cussed in Section 3.10.3.1 above.

The NSRAC concern with ORC procedure reviews is

being evaluated for long-term improvements but no

definitive action is currently planned by the

licensee. As for NSRAC concern #4, the meetings

observed by the Team, were conducted in a manner

permitting formal and informal discussions of

specific issues.

A meeting agenda for regular

ORC meetings was prepared and followed. The Team

concluded

that

the

meetings

were

conducted

acceptably.

Based on the above, the Team has determined that,

in general, the ORC has been receptive to recom-

nendations for improvement.

However, the fact

that the NSRAC concerns remain unresolved sug-

gests that the ORC may have difficulty addressing

more complex recomendations.

_ __

O

O

,

102

The Team also observed that the quality of the

'

>

meeting minutes could be improved by providing

more discussion of the issues by the various ORC

members as opposed to providing abstracts of the

documents discussed.

Based upon a review of the ORC activities, the

,

Team determined that there are weaknesses in the

implementation of responsibilities assigned to

the DRC. In particular, the Team determined that

weaknesses exist in the review of plant opera-

tions and tne investigation of TS violations.

The Team has concluded that improvements in these

two specific areas would result in a more effec-

tive ORC.

In response to the Team's concerns,

the licensee agreed to take certain actions prior

to restart to strengthen the operational focus of

ORC.

These actions are:

(1) to review plant

,

incident critiques; (2) to review LER's prior to

[

their submittal to NRC; (3) to review F&MR's on a

-

regular basis; and, (4) to provide for a monthly

l

presentation and discussion of plant operations

'

as a specific agenda item. The Team found these

licensee commitments responsive to its concerns.

,

I

3.10.4

Quality Assurance Audit and Surveillance Programs

!

1

The Team reviewed selected QA audit and surveillance

i

reports, selecting specific findings, discrepancies, and

i

observations for followup of the licensee's corrective

t

action process. QA personnel, including the QA Department

!

(QAD) manager, and other station nanagers and engineers,

'

were interviewed regarding the audit and surveillance pro-

!

gram objectives and overall conclusions which can be drawn

l

f rom the audit and surveillance findings.

The Team also

i

reviewed the quarterly QA0 Trend Analysis report, and at-

tended several QA interface meetings.

Portions of the

Boston Edison Company Quality Assurance Manual (BEQAM) and

applicable station procedures were also reviewed.

4-

,

The technical content and quality of the issues raised in

'

the selected audit reports were excellent.

The conduct of

.

a performance-based radiological controls audit by outside

i

consultants was noteworthy.

Specificolly, the Team re-

-

viewed audits required under the cognizance of NSRAC, i r.

accordance with the TS, and found that they are being per-

formed as required.

The Team determined that all defici-

i

encies identified in the audits were either closed or ade-

quately tracked by a for al system,

j

t

I

n,-.-.

. - - -

. - - - - _ - _ . - - - - - - - , . - -


-

.- . _ .

,

.-

o

l

l

!

103

During the conduct of audits and surveillances, deficiency

'

reports (OR) are issued by QA for conditions contrary to

management policies and procedures, regJlatory require-

ments, or licensee commitments.

A DR which reports a

,

deficiency identified during a QA audi+, is issued at the

,

time of the audit exit interview.

The licensee has an

t

effective system of re, quiring a written response to the OR

within a specified period, dependent on its significance,

and for subsequent followup of corrective action. A system

also edists for granting extensions through an escalation

process to upper management.

QA prepares a monthly status report, including OR status,

which is forwarded to senior management for appropriate

,

actions.

Review of the most recent QA trend report indi-

cated a decline in the OR backlog, an increase in the num-

ber of OR's completed on time, and few extensions needed

.

L

for OR closeout. The number of deficiencies reported by QA

!

remained fairly constant.

These are all indicators that

,

licensee management attention to the corrective action

l

process has had a positive impact.

'

The licensee also effectively trends Immediate Corrective

'

Actiens (ICA), which are identified in audit and surveil-

,

lance reports. These report conditions which could lead to

a DR, but which are corrected prior to the end of the audit

,

or surveillance.

They also are tracked along with the

,

OR's.

The Team also found the tracking of recommendations

.

from the audits and surveillances to be effective.

l

Approximately 45 QA surveillance reports concerning obser-

i

vations of surveillance testing were reviewed. The reports

I

were well planned, well documented, and thorough.

Again,

,

the tracking and followup of identified deficiencies were

l

adequate. A minor concern of the Team involved QA followup

to identified procedural inadequacies during surveillances,

i

In ten of the surveillance activites reviewed by NRC,

!

technical piocedure deficiencies were identified by QA, but

I

since the technicians being observed halted the test and

(

pursued a procedure change, no deficiency reports were

l

issued. Furt.her review ' snd that the majority of the pro-

!

cedure deficiencies were identified prior to implementation

,

of new procedure validation program, and that QAD has an

i

open DR on the procedure validation process.

QA0 is con-

l

tinuing to monitor the process.

The Team had no further

cor.ce rn s .

l

!

I

,

b

,

-

r .- -

_ _ _ _ _ _

-

__

_____ _

, ,,

,

104

Two QA Interface meetings were attended during the inspec-

tion. The mee*.ing attendees include representatives from

QA, plant staff, and engineering.

They meet weekly to

review the status of various corrective action items,

including OR's,

Management Corrective Action

Requests

(MCARs) and Potenti:1 Conditions Adverse to Quality Reprts

(PCAQ's).

The meetings have improved communications among

the organizations and have contributed to the more timely

resolution of corrective action items.

3.10.5

Corrective Action Process and Programa

The Team reviewed the licensee's programs curr6ntly in

place to identify, follow, and correct safety-related prob-

lems. A newly formulated Corrective Action Program "Clear-

inghouse," and proposed revisions to corrective action pro-

cess procedures were also evaluated with respect to the

current objectives and planned initiatives to improve cor-

rective action program effectiveness.

Samples were chosen

from each of the programmatic areas where problem identift-

cation is routine and implementation of corrective measures

is required.

Each of these programs is discussed below.

The Tean interviewed licensee personnel responsible for

individual program management and implementation, as well

as the technical personnel accountable for problem dis-

position and corrective action adequacy.

For all of the areas evaluated, the Team sought to deter-

mine the effectiveness of the licensee's process for root

cause analysis of problems, investigation of problems and

causes for their generic applicability, and trending of

findings to prevent their recurrence. Selectad issues were

analyzed % understand the technical problems, check how

they were

programmatically hsndled,

and

to determine

whether the corrective measures were appropriate to the

specific cases.

The examples are cited in the following

subparagraphs not only to illustrate the scope of licensee

activities inspected, but also to support the conclusions

reached

regarding

the

corrective

action

program

effectiveness.

3.10.5.1

Failure and Malfunction Reports

The Failure and Malfunction Report (F&MR) is a

process by which failures, malfunctions, and

abnormal operating events are reported, evaluated

and corrected to preclude repetition.

The pro-

cess

is

described

in:

Nuclear

Organization

-

_. ___ __ __ ______

.

.

105

Procedure (NOP) 8305, the "Failure and Malfunc-

tion

Report Process;"

PNPS Procedure Number

i

1.3.24, "Failure and Malfunction Reports;" and

PNPS Work Instruction NS-3.2.12

"F&MR Trend

Analytis."

Team review of licensee precedures verified that

responsibilities are established for the F&MR

process; reports are prioritized by safety sig-

nificance; underlyin

root causes are evaluated;

reports are tracked for completion of corrective

,

action; and, trending for repctitive proble.ns is

performed.

A report may be initiated by any

licensee staff member for failures, malfunctions,

and abnormal operating events identified during

station operation.

The Nuclear Watch Engineer

ensures that adequate compensatoi,, measures are

implemented and the required notifications are

!

performed.

The Compliance Division Manager then

>

recomnends a lead group to perform the investiga-

'

'

tion and performs a reportability review.

The

appropriate department manager is responsible to

ensure that the identified deviations are prc-

perly resolved and that corrective actions are

planned and effectively iniplemented in a timely

manner. The department manager is a'.so responsi-

'

ble for the revi- and approval of the reporta-

bility, root caase analysis, corrective action

!

a

plans, disposition, and final closeout.

A root

cause analysis is performed for those F&MR's

i

determined to be significant. The term "signifi-

'

cant" applies to a condition adverse to quality

which merits further evaluation for cause and

>

requires management attention to preclude recur-

I

!

rence.

The nonsignificant deviations are evalu-

l

ated in a periodic trend analysis.

l

[

The Team identified several discrepancies in the

}

,

3

ddministration of the F&MR process.

Procedure

,

1.3.24

states

that

the

Complianc

Division

'

.

Manager is responsi51e to present F&MR's that are

!

designated significant or important to ORC. As

'

.

discussed in Section 3.10.2, the Team noted that

'

the ORC meeting minutes for the previous six

months did not record the review of any F&MR's.

.

Further Team review found that a backlog of over

j

'

,

t

,

i:

l

l

- - - - - - - - -

1

a

,

106

eristed, and that no F&MRs had been submitted to

ORC since February 3, 1988, except for those

associated with an LER.

Some of the F&MR's

involved events which occurred in 1986.

The

,

licensee stated this was caused by personnel

'

resource constraints.

The Team also found two

i

closed F&MR's which appeared to meet the criteria

established in Proendure 1.3.24 for being submit-

ted to ORC, but which had not been submitted

prior to closure.

F&MR's88-127 and 88-76 were

!

cot reviewed by ORC, but invefived recurring con-

ditions, which is a criterion for ORC review.

Ir. addition, many of the closed safety-related

!

F&MRs were denoted not safety-related by the

,

Watch Engineer during the initial review process.

'

This .nts-clat *fication; however, did not affect

,

the processing and evaluation of the associated

events for those F&MR's inspected.

The Team reviewed a listing of open and closed

F&MR's and evaluated a sampling of closed reports

to determine the completeness and effectiveness

r

of the corrective actions.

The total number of

F&MR's initiated has been increasing over the

!

last few years. The licensee has attributed this

increase to a heightened sensitivity of personnel

i

to critical self-assessment and to the identif f-

l

cation of potentially reportable or significant

events to management.

The total number of open

F&MR's has significantly decreased over the last

year.

l

The root cause analyses performed for the F&MR's

i

'

reviewed were found to be of excellent quality.

l

!

Each analysis included an event description,

probable cause, actions completed, recommended

actions, and safety significance.

The Systems

!

Engineering Group's impact on this important

process has been positive.

1

I

.

The Team revf ewed the latest F&MR Trend Analysis

e

Report, which covered the period July through

December 1987, anti the applicable procedures.

The Team noted that the station's Technical Sec-

l

tions did not specifically assign responsibility

for the report's proposed recommendations.

Fur-

i

ther review found that this program deficiency

i

had been previously identified by the licensee

!

and the NRC and that the licensee had initiated

j

corrective action. Specifically, a review of all

previous trend report rec w endations was per-

forced by the licensee to determine their status.

l

>

_ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

__ _

_

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

__________

- __

_

_

.

o

107

The review was completed in July 1983, and 74% of

the recommendations were corrected.

The remain-

ing items are currently being dispositioned by

the licensee to ensure effective long-term cor-

rective action.

In addition, the licensee has

revised the F&MR procedures to include use of the

Management Corrective Action Report (MCAR) as a

vehicle for the Technical Section to report and

correct negative trends identified in the re-

ports. The most recent trend report resulted in

the issuance of two MCAR's, which the Team

reviewed.

The Team also noted that the trend report focused

its discussions primarily on individual problems

rather than trend patterns and recurring fail-

ures. The Team observed that the Technical Sec-

tion would be more effective if it thoroughly

evaluated trends and patterns, since the indi-

vidual F&MR itself is adequate to evaluate iso-

lated problems.

In addition, the report did not

provide any detailed discussion of personnel

errors or procedural failures, although there

were a large number in the report.

3.10.5.2 Potential Conditions Adverse to Quality

As described by PNPS Nuclear Organization Proced-

ure (NOP) 83A9, "Management Corrective Action

Process," the potential conditions adverse to

-

quality (PCAQ) report can be used by any licensee

member tc document and report any actual or sus-

pected conditions adverse to quality not reported

by other report forms such as NCRs, ors, and

F&MRs.

In short, it is a process for anyone to

elevate a concern to management to assure that

the concern will be evaluated and

resolved.

As

implemented.

PCAQs

are written

from one

'

department to another or from one section to

another within a department.

For example, Oper-

ations (N00) could send a FCAQ to Engineering

(NED) asking for an evaluation of a specific

plant condition.

In each case, the originating

department is responsible for tracking each item

to resolution. According to NOP 83A9, a PCAQ is

not formally closed until the originating depart-

eent is satisfied with the proposed corrective

action

and

the

corrective

action

has

been

implemented.

<

O

103

The Team reviewed a listing of open and closed

PCAQ's and also reviewed a sampling of individual

PCAQ's to determine the completeness and effec-

tiveness

of

corrective

actions.

As

of

August 19, 1988,

there were about

250 PCAQs

awaiting resolution.

There is currently no cen-

tral tracking system for all PCAQs, although

licensee management has begun initiatives in that

area. In June 1988, the licensee began an effort

to reduce the number of open PCAQ's and to estab-

lish a central tracking system for PCAQ's with

the QAO. As part of this effort, each department

is reviewing unresolved PCAQ's to evaluate each

one's significance and its potential impact on

restart.

Based on discussions with respons!ble

managers, the Team learned that QA0 has completed

its review and concluded that r.one of the unre-

solved

PCAQ's

concern

equipment

operability

issues or are of a significance level that re-

quires action before restart.

N00 has not com-

pleted its evaluation but expects to be finished

within two weeks.

NED has been implementing a

routine review of each unresolved PCAQ and has

been maintaining a list of PCAQ's needed to be

resolved prior to restart.

The review of out-

standing PCAQ's is an iten on the restart check-

list maintained by the plai t.

Subsequent check-

list review by ORC also provides a decision point

in the process to assure that all necessary

evaluations have been completed.

Based on the above, the Team has concluded that

the licensee is assuring that each PCAQ is being

evaluated for its nuclear safety and equipment

operability

impact

relative

to

the

planned

restart of the plant and that all PCAQ'; noeded

for resolution before restart will be identified.

The ORC review of the PCAQ's on the restart

checklist will provide another check to assure

)

that resolution n' PCAQ's needed for restart has

I

occurred.

_ _ - - _ _ - _

.

.

109

i

The Team selected several closed PCAQ's to deter-

mine whether the proposed corrective action had

satisfied the originating department's concerns

and whether the corrective action was completed

as required by station procedures.

In general,

all identified corrective actions described on

the PCAQ's were completed; however, the docume -

tation of the completed activity was, in many

cases, limited and specific references were not

provided.

The Team stated that additional guid-

ance on the level of documentation to be provided

on the closecut portion of the PCAQ form could

enhance clarity and auditability of the closure

process. The Team also noted that the PCAQ sys-

J

tem can allow ambiguity of PCAQ status in cases

where a proposed action has been rejected by the

-

originating office.

For example, NED rejected

'

)

the response prepared by N00 to PCAQ NED-SS-087.

A review of the N00 log showed the issue resolved

(July 22, 1933), but further investigation with

parsens af fected indicated that the response was

being rewritten and further corrective action was

to be performed. The fornal closecut process and

I

status tracking for the PCAQ's needs improvement,

i

This finding parallels a similar finding of the

!

QA Department contained in QA0 88-609, dated

May 23, 1988.

l

3.10.5.3 Managenent Corrective Action Request

The GEQAM and NOP 83A9, "Management Corrective

Action Process," describe the purpose of the

Management Corrective Action Request (MCAR).

The

MCAR is a two part corrective action document

]

used to:

(1) perform a root cause analysis of

significant conditions adverse to quality and

'

develop preventive action plans; and (2) request

management to implement selected action plans to

prevent recurrence of a problem.

In lieu of a

,

Deficiency Report, an MCAR may be used to report

,.

and resolve deficiencies involving process or

i

1

policy issues which af fect more than one depart-

'

ment and for which management attention and

direction is required. An MCAR eay also be used

for tracking long-term corrective actions related

i

to nonconformance reports (NCRs) and PCAQ's nr

for identification of adverse trends identified

'

i

threugh trend analysis programs.

i

!

!

_.

_ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _

.

.

110

l

QA0 is assigned adiinistrative control for the

MCAR process.

QAD logs the status, distributes

copies, reports on delinquent MCAR's, and per-

forms the closecut. QAD also reviews each MCAR

where the responsible department is different

j

from the issu.ing department to verify that the

assignment of

the

responsible department

is

-

appropriate.

The Team reviewed the current status of open

l

MCAR's and the administrative controls in place

to track and promptly resolve MCAR's. The latest

monthly status report, issued to the SVP-N on

August 1,1988, from the QA0 Manager listed 30

l

'

open MCAR's. This list included two 1985 MCAR's

and eight 1936 MCAR's. Approximately 40% of the

MCAR's initiated since 1984 remain open,

i

The licensee has previously observed that in-

l

creased management attention is required to close

!

cut MCAR's in a timely manner.

For example, the

I

most recent QAD trend analysis report, issued on

May 23, 1988, recommended that the SVP-N initi-

ate action to closecut MCAR's QA0 85-2 and QA0

87-2, which address the large number of quality

problem reports issued for "f ailure to follow

procedures" and "inadequate procedures."

Team attendance at several QA Interface meetings

also noted

that

there

is

clearly

increased

management attention being directed to c'ostout

the longstanding MCAR's.

The Team reviewed two open M;AR's to evaluate the

effectiveness of the process. MCAR 86-06, issued

in November 1936, involved recurring failures of

the salt service water (SSW) pumps. The MCAR was

issued as a result of an F&MR trend repert find-

ing.

The MCAR resulted in a detailed root cause

.

analysis by a consultant and the development of a

l

long-term corrective action plan, which is not

yet complete.

MCAR 8S-02, issued in June 1938,

concerned programmatic inefficiencies in the PCAQ

process.

The licensee is actively working on

developing an integrated list of the approxi-

mately 250 open PCAQ's with a curre it status (see

Section 3.10.4.2).

This list is to be utilized

to increase emphasis on closecuts.

Review of

these M;AR's did not identify any discrepancies

in the process.

_ . _ _ _ _ _ _ . . _ _ _ _ _ . __

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

-

_ _ _ _ _ _ - _ _ .

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ -

__

D

,

'

111

,

3.10.5.4 Clearinghouse Process

I

The current procedure describing the corrective

i

action process is NOP 83A9, "Management Correc-

[

tive Action Process."

This prccedure discusses

l

the responsibilities of the station depart-cents

t

t

in resolving identified deficiencies and report-

ing the trends observed

The procedure also

describes the various types of reports or docu*

t

ments available to station personnel and specifi-

cally defines their use.

r

As a result of the self-assessment evaluations

and performance improvement plans, the licensee

determined that the existing corrective action

t

processes were

very compliccted and

that a

i

streamlined process was needed that would provide

I

,

an easy means of raising any concerns to manage-

,

'

ment for resolution. A need was also identified

!

for a specific entity which could monitor the

performance of the station organization in imple-

,

menting self-improvement recommendations, as well

!

as provide the focal point for identified issues

to be placed into the appropriate plant correc-

,

tive actin 6 process,

j

.

P

In June 1933, the "Clearinghouse" was established

l

3

to serve a number of needs.

It was developed to

l

'

assure that the licensee's restart assessment

(

team observations had been entered into the

!

,

regular corrective

action

process

and,

when

j

necessary, that all necessary .Nperwork. was pre-

-

pared for the resolution of any outstanding

[

ttems.

As of this inspection, 69 assessment

items remain unresolved but have schedules iden-

e

tified

for

their completion.

Responses

for

!

approximately 69 additional items have not been

!

received

from the station organization.

The

balance of the original 449 items have been

f

listed as closed. The Team cid not evaluate the

l

.

closecut process for any completed or closed

j

,

items.

j

j

A second responsibility of the Clearinghouse was

!

,

to streamline the corrective action process. As

{

of this inspection period, revisions to the sta-

i

i

tion procedures for improvements in corrective

!

!

action processes have not been made. The current

,

i

estirate for cenpletion of the necessary proced-

l

l

ure revist" s was the end of Augus..

j

i

.

,

i

!

4

_.

-

.

.

_ _ _ _ _

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

. _ _ _ _ _

O

4

i

112

While subject to revision during the required

station procedure review process, the following

i

is a discussion of the current licensee philos-

ophy concerning potential modification of the

I

corrective action processes.

The Team did not

evaluate the effectiveness of these proposed

changes

in

the

overall

corrective

action

,

programs.

!

The Clea ringhoui,e is currently revising three

i

existing NOPs, creating a new NOP, and revisirg

l

the BEQAM. The new NOP would define the role and

responsibilities of the Clearinghouse, establish

a new form for identifying real or potential

'

plant

problems,

as

well

as

for

reporting

employee-identified concerns or self-assessment

!

recommendations for plant improvements. The new

,

form would provide a uimple method for raising

issues, concerns, or recommendations to station

,

,

'

management.

Upon receipt of this form,

the

'

Clearinghouse would review the issue described

i

t

and integrate the issue into the regular plant

j

corrective

action

proc 2sses

for

resolution.

l

Another proposed change is a categorization of

l

all

the existing corrective action processes

'

.

identified in NOP B3A9 into three groups.

One

i

group, identified as corrective action processes.

l

would include deficiency reports (OR), non-con-

,

,

formance reports (NCR), management corrective

}

action requests (MCAR), failure and malfunction

!

reports (F&MR), radiological eccurrence reports

,

(ROR), security deficiency reports (50R), and

l

supplier finder reports (SFR).

These processes

i

are used to identify and document plant deficia

'

encies and to provide a neans of tracking the

e

resolution of identified problems.

(

t

j

A second group of controls would be categorized

as normal work control processes.

This group

would potentially include maintenance requests

!

(MR),

housekeeping services assistance (H5A),

!

procedure change notices (PC), and engineering

i

I

services requests (ESR).

t

i

,

!

I

1

i

j

i

-

- -

_ _ _ - _ _ _

.

o

,

f

113

The last group currently being proposed includes

all recommendations or findings from the existing

self-assessment programs.

The information to be

'

,

tracked in this group are recommendations for

improving performance and would not be used to

identify programatic deficiencies.

Any identi-

1

fication of deficiencies would be tracked using

'

I

one of the processes described in the first group

above.

Examples of the types of recommendations

1

to be tracked would be quality assurance audit

findings and peer evaluator reports,

j

Changes would also be required for NOP 84E1,

!

"Engineering Service Request (ESR) Proe-ss," and

NOP 84A7, "Drawing Control," as well as the

'

quality assurance manual,

in order to fully

implement the revised program,

j

The

licensee anticipates

that all

necessary

I

changes to station procedures would be completed

l

by the end of August, with formal implementation

of the program changes within an additional 30

days.

t

3.10.5.5 Management 0.ersight and Assessment Team (MO&AT)

In addition to the plant operations oversight

i

provided by the ORC, the MC&AT also provides an

!

oversight review of plant operations by the

nature of its responsibilities for overview of

restart activities.

The MO&AT is corrposed of

eight sentor managers, which includes the Station

Director. Director of Special Projects and Vice

i

President Nuclear Engineering. The SVP-N acts as

the Chairman of the team.

Further, three M01AT

,

merbers had been licensee managers prior to the

I

arrival of the SVP-N, while the remaining ran-

(

agers joined the licensee subsequent to February

l

1987.

l

The M01AT maintains its oversight of restart-

related activities and associated plant opera-

'

I

tio'is through several self-assessment programs.

These programs include but are not limited to the

,

peer evaluator and management ronttoring pro-

l

grams.

The Team noted that these programs were

ef'ective in evaluating plant activities.

l

l

(

i

!

!

,

I

!

,

- ---

. - - -

- - - _ _ _ - _ _ _ . - _ . - -

- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

'

O

114

The Team determined that, in some ways, the

responsibilities of the MO&AT parallels some of

the responsibilities to review plant operations

assigned to the ORC.

In addition,

the Team

determined that the curreret role of the MO&AT is

not credited by the ORC as a means of fulfilling

its responsibilities to review plant operations,

but it does provide a second, independent look

at plant operations.

3.10.5.6 Engineering Service Requests (ESR's)

ESRs are tracking forms used by any licensee

department to request engireering assistance from

the Nuclear Engineering Department (NED). Stand-

ard practice within NEO is to attach an ESR to

all requests for assistance which may be already

tracked under another corrective action tracking

system, such as DR's, PCAQ's, etc. This is done

to provide a means for the NED to track and

monitor the progress of its work. When ai ESR is

opened or received. NED is to review the concern,

determir.e a plan for resolution of the item,

which wculd include an evaluation relative to

plans for plant restart. Unless the issue can be

resolved within 30 days, a response to the origi-

nating department is to be provided within 30

days which describes the above.

In discussions

'

l

with the Team, a management representative of NED

l

indicated that this practice has not always

worked as planned and that additional emphasis is

being placed on assuring that the 30-day re-

sponses are being sent in a timely fashion.

NED tracks all existing E5R's, determines what

actions are required prior to restart, and rou-

tinely evaluates the potential impacts of out-

standing ESR's on the plansed restart of the

plant.

In each case where NED determines that

resolution of an ESR is not required to support

restart. NED prepares docu entation to support

that

position.

This

documentation

undergoes

several levels of review, including the Section

Manager, Department Manager and the Vice Presi-

dent - Nuclear Engineering.

Any open ESR asso-

ciated with unresolved pCAQ's or MCAR's is also

revie=ed by the CRC as part of its assigned

restart checklist revie.'.

____-_ __-____-_

.

,

!

i

l

'

i

115

!

i

Based upon discussions with NED personnel, the

I

Team concluded that ESR's are adequa0ely tracked

j

and that upper management is routinely informed

!

of potential problems in a timely fashion.

}

i

3.10.5.7 Human Performance Evaluation System

'

The Team inquired as to the licensee's intentions

!

in participating in the Institute for Nuclear

Power Operations (!NPO) Human Performance Evalua-

tion Systvm (HPES) program.

The program

is

r

intended to assist licensees in the reduction of

[

human error by encouraging pe*sonnel to report

!

actual or potential situations which keep a per-

t

son from outstanding performance.

The licensee

I

has designated an HPES coordinator, who is in the

!

Training Department.

The coordinator has been

i

I

trained by INPO and is currently preparing to

implement

the

program.

The

coordinator

has

!

'

already become involved in the Incident Investi-

l

gation and Critique process, and has reviewed the

i

recent findings frc:n the licensee's ESF Actuation

.

!

Task Fo

i report,

This p rog ra.. . ence fully

implete'.' o l,

should provide additional valuable

input int- the corrective action process.

f

3.10.6

Conclusions

Overall, the Team determined the licensee's programs for

!

safety assessment / quality verification to be adequate and

I

improving.

Based upon the areas inspected and examples

'

L

raised, the Team concluded that'

t

1.

The Nuclear Safety Review and Audit Committee is

actively involved in ;.he oversight of facility opera-

'

tions.

The con:11ttee is composed of experienced man-

agers with diverse experience and provides clear and

valid input to the SVP-N on safety-related activities.

2.

Plant problems and deficiencies are being ident'f ted

f

and entered into the appropriate corrective action

system,

t

-- - ---

o

.

.

.

116

3.

There are effective, meaningful communications between

the QA and plant operations departments, as well as

good systems engineering involvement in evaluation and

resolution of problems.

4.

The weekly QA interface meeting has enhanced communt-

cations at the station and improved the process of

resolving open issues.

5.

The Operations Review Committee (ORC) has not been

reviewing plant operat'.ons ef fectively so that mean-

ingful input to Itcensee manag cent is being consist-

ently provided,

Recently, heavy emphasis has been

placed on administrative reviews of procedure changes

and modifications, rather than reviewing plant opera-

tions. Also, ORC review of plant failure and malfunc-

cion reports has neither been timely nor included all

appropriate reports.

6.

Multiple corrective action processes and multiple

tracking systems detract from efficient functioning of

the system. This has been identified by the licensee

and programs ar

being established to correct the

known deficiencie;.

7.

The tracking and ;1osecut of PCAQ's and MCAR's have

not been effective in the pest.

Also, a relatively

large number of open PCAQ's exists.

The licensee is

taking action to resolve these problem.

. . _ .

_ _ _ _ _ _ _ _

,

'

117

4.0 UNRESOLVED ITEMS

An unresolved item is an item for which additional information is required

in order to determine whether the item is acceptable, a violation, or a

deviation.

An unresolved item is discussed in section 3.4.2.2 of this

report.

I

o

i

118

!

5.0 MANAGEMENT MEETINGS

l

At periodic intervals during the inspection period, the Team Leader held

[

meetings with senior facility management tu discuss the inspection scope

and preliminary findings.

A final exit interview vas conducted on

l

August 24, 1938.

Attendees are listed in Appendix 8.

At the exit meet-

i

ing, the Team Leader described the preliminary insoection findings,

!

including both the preliminary overall conclusions and the preliminary

findings and observations in each functional area.

The Team Leader also

!

confirmed licensee comm.itments at the exit meeting, Then the Team Manager

I-

discussed how the Team findings will be used in NRC Restart Assessment

Panel activities. Also, the Regional Administrator outlined the remaining

.

step in the NRC staff process of evaluating Pilgrim restart readiness and

[

developing staff recommendation.

l

l

l

[

t

I

'

i

L

i

i

!

.

I

i

!

!

I

I

.

I

!

--

_ _ _ _ _ _

_ - _ _ . -

l

,

APPEN0!X A

Entrance Interview Attende_es

August 8, 1988

Boston Edison Company

J. Alexander, Plant Operations $ection Hanager

R. Anderson, Plant Manager

H. Balfour, Iraining Section Manager

R. Bird, 5entor Vice President - Nuclear

F. Famulari, Quality Assurance Department Manager

0. Gillispie, Nuclear Training Department Manager

R. Grazio, Regulatory Section Manager

P. Hamilton, Compitance Division Manager

K. Highfill, Station Director

J. Jens, Radiological Section Manager

E. Kraft, Plant Support Department Manager

R, ledgett, Otrector Special Projects

0. Long, Security Section Manager

A. Morist, Planning tad Outage Department Manager

E. Robinson, Corporate Comunication Information Division Head

L. Schmeling, Program V.anager

J. Seery. Technical Section Manager

R. Sherry, Plant Maintehance Section Manager

R. Swanson, Nuclear Engineering Department Manager

E. Wagner, Asr*stant to Senior Vice President - Nuclear

F. Wozniak, Fire Protection Olvision Manager

l

United States Nuclear Regulatory _Comission

l

F. Alstulewicz, Senter Technical Assistant, Policy Development and

!

Technical Support Branch, Office of Nuclear React,or Regulation (NRR)

,

R. Blough, Chief, Reactor Projects Section No. 3B, Otvision of Reactor

l

Projects (DRP), Region 1 (RI)

S. Collins Deputy Director, ORP, RI

L. Doerflein, Project Engineer, ORP, R!

T. Cragoun, Senior Radiation Specialist, Division of Radiation $afety

and Safeguards (CRSS)

M. Evans, Operations Engineer, Olvision of React,or Safety (ORS), R!

J. tyash, Resident Inspector, Ptigrim Nuclear Power Statten, ORP, R1

0. Mcdonald, Project Manager, Project Directorate 1 3, NRR

L. Pitsco, 5tntor Operations Engineer, Otvision of License Performance

and Quality Evaluatien, NRR

W. Raymond, Senior Resident Inspector, Mi11 store Point, ORP, RI

L. Rossbach, Senior Resident Inspector, Indian Point Unit 2, CRP, RI

G. $sith, Safeguards $recia115t, OR55. RI

C. Warren, Senior Resident Inspector, Pilgrim huclear Fe.er Station, ORP, RI

%

_ _ _ _ _ _ _

- _ _ _ _ _ _

_ _

_ _

.

I

I

Appendix A - Entrance Interview

A-2

'

Attendees

r

!

Com.monwealth of_ Massachusetts

l

i

'

P. Agnes, Assistant Secretary of Department of Public Safety

i

P. Chan, Observer

S. Sho11y (MHS Technical Associates, Inc.), observer

i

t

i

I

t

\\

!

!

t

!

l

.

I

!

l

'

l'

i

.

1

4

a

'

1

I

.

s

i

!

,

.I

t

l

.

t

J

f

i

!

'

!

l

i

1

i

1

P

I

'

'

l

,

e

-

- - .

-

- --- --

- ~ ~ ~ ~ - - * - ' ' ^ - ~ '

_ _____________ _ ___ _ _

_ _ _ _ _

,

j

.

e

'

1

!

1

-

l

I

1

'

APPENDIX B

i

Exit Interview Attenden

August _24.193,]

[

j

Boston Edtson Company

>

!

J. Alexander, Plant Operations Section Manager

R. Bird, Senior Vice President - Nuclear

F. Famulari Quality Assurance Department Manager

,

l

0. G1111spie, Nuclear Training Department Manager

i

-

R. Gramont, Deputy Maintenance Section Manager

R. Grazio, Regulatory Section Manager

i

P. Hamtiton, Compliance Divtston Manager

l

K, Highfill, $tation Ofrector

l

J. Jens, Radiological Section Manager

!

E. Kraft, Plant support Department Manager

R. Ledjett, Director $pecial Projects

l

0. Long, Security Section Manager

!

l

E Robinson, Corporate Comunication Irformation Disiston Head

L. Schmeling, Program Manager

J. Seery, Technical Secsion Manager

i

R. Sherry, Plant Maintenance Section Manager

j

R. Swanson, Nuclear Engineering Department Manager

5. Sweeney, Chief Executivc Officer ard Chairman ef the e n d

i

E. Wagner, Assistant to Senior Vice President - Nuclear

,

,

l

F. Wozniak, Fire Protection Otvisten Manager

,

United States Nuclear Regulatory Cemmisslo)

f

f

F. Akstulewicz, Senior Technical Assistant, Policy Development and

T*,:hnical support Branch, Off.ce of Nuclear Raactor Regulation (NRR)

-

R. Blough, Chief, Reactor Projects Section No. 3B, Olvision of Reactor

!

Projects (ORP), Region I (RI)

t

B. Boger, Assistant Director for Region ! Reactors, NRR

l

5. Collins, Deputy Otrector, ORP, R!

l

L. Doerfietn, Project Engineer, DRP. RI

j

W. Little Office of Special Projects, R!!

i

J. Lyash, Resident Inspector, Pileetm Nuclear Power Station, CRP, R!

!

0. Mcdonald, Project Manager, Prc et Directort te (PD) !-3, 'lRR

l

W. Naymond, Senior Resident Inspector, Pills +.ane Point, ORP, RI

L. Rossbach, Senior Resident Inspector, Indian Point Unit 2. ORP, R!

V. Russell, Regional Maintstrator, R!

C. Warren, Senior Resident Inspector, Ptigrim Nucicar Power Station. ORF, RI

R. Vesssan, Director, PO I-3, NRR

i

,

-

,

.

Appendix B - Exit Interview

B-2

Attendees

Commonwealth of Massachusetts

P. Agnes, Assistant Secretary of Department of Public Safety

P. Chan, Observer

G. Minor (MHB Technical Associates, Inc.), Observer

!

I

i

-

__

_

'

.0

APPENDIX C

Persons Contacted

R. Anderson, Plant Manager

R. Bird, Senior Vice President - Nuclear

F. Famulari, Quality Assurance Department Manager

K. Pi-hfill, Station Director

E. ! ,tard, Vice President - Nuclear Engineering

E. Kraft, Plant Support Services Manager

A. Morisi, Planning and Outage Manager

R. Swanson, Nuclear Engineering Department Manager

S. Sweeney, Chairman of the Board and Chief Executive Officer

In addition, the Team interviewed a large number of managers (including

virtually all section and division managers), engineers, supervisors, and

craft personnel in each inspection area.

.

9

O

O

APPENDIX 0

Documents Reviewed

PNPS, Nuclear Training Manual, T-001, Parts 3, 4 and 5

PNPS,

Special

Post-Startup Training Program, Approved August 9, 1988

PNPS Technical Specifications

Boston Edison Company Nuclear Mission, Organization and Policy Manual

Nuclear Organization Procedures

Material Condition Improvement Action Plan

Boston Edison Quality Assurance Manual

Audit Reports -- Sampling review it.cluding the following:

87-40, 88-02,

87-63, 88-10, 88-20, 87-37, 87-49, 8b-04, and 88-11

Potential Conditions Adverse to Quality (PCAQ) Reports -- Sampling review

including N00 87-88, NED 86-71, GE0 87-255, S0 88-57, SO 88-58, 50 88-48,

N00 87-02, N00 87-28, NED 88-087,

50 88-59,

SO 88-12, N00 88-120,

NED 88-90, 50 88-55, and S0 88-22

Management Corrective Action Requests (MCAR's) -- Sampling review includ-

a

ing QA0 85-2, QA0 87-2, 86-06, and 88-02

Licensee Event Reports (LER's) -- Sampling review including 87-21,88-008

thru 88-014,88-016, and 88-017

Maintenance Requests (MR's) -- Sarrpling review including 88-11-6,88-110,

88-10-179, 88-46-300, 88-14-16, 88-45-183, 88-45-181, 88-46-194, 88-10-26,

88-10-105,

88-10-69,

88-10-71,

88-1C-80,

88-10-141,

87-10-282,

and

87-10-283

Maintenance Activities / Packages

Sampl i r.g review including 88-3-26,

--

63-19-109, 88-46-213, 88-10-86, 87-46-173, 88-13-20, 88-46-438, 88-2-12,

86-20-47, 88-45-157, 88-45-176, 88-3-62, 88-63-276, 88-45-190, 88-1-31,

88-14-16, 88-46-194, and 88-10-114

Meeting Minutes for ORC Meetings 88-40 through 88-63

Failure and Malfunction Report 86-266

NEO Procedure 16.03, "Corrective Action Program"

_.

.

.

Appendix 0 - Documents Revir.wed

0-2

QAD Trend Analysis Report for the First Quarter of 1988 - QAD 88-609

PNPS Work Instruction NS-3.2.12, F&MR Trend Analysis

Memo from J. Seery to R. Grazio, Appointment of Compliince Division as ORC

Subcommittee, June 23, 1988

Memo from R. G. Bird to K. L. Highfill, NSRAC Concern from May 24, 1988

NSRAC Meeting - May 27, 1988

Memo from

K. L. Highfill to R. G. Bird, Response to NSRAC Action Item

88-04-01 - June 22, 1988

Memo from J. A. Seery to

R. Flannery, OkC Mee*.ing Minutes Distrioution

List

dated May 6, 1988

Procedure 1.2.1, Operation Review Committee

Procedure 1.3.24, Failure and Malfunction Reports

Procedure 1.3.2.6, Response to Deficiency Reports

Procedure 1.3.4, Procedures

Procedure 1.3.33, Operating Experience Review

Procedure 1.3.37, Post Trip Reviews

Procedure 1.3.33, Plant Performance Monitoring Program

Procedure 1.3.63, Conduct of Critique 5 and Incident Investigations

Procedure NOP 83A9, Management Corre

ive Action Process

Procedure NOP 83A13, Deficiency Repo.t Process

Procedure NOP 83A14, Nonconformance Report Process

Procedure NOP 84A1, Surveillance Monitoring Program

I

Procedure NOP 84A11, Annual Independent Review of BECo's Quality Assurance

Program

Procedure N0P 85A1, Nuclear Organization Performance Monitoring and

Management Information Program

Procedure NOP 88A1, Performance Standards and Evaluation Guidelines for

.

Pilgrim Station

i

a

.

Appendix 0 - Docurents Reviewed

0-3

Procedure NOP 8305, The Failure and Malfunction Report Process

Procedure NOP 8401, Operating Experience Review Program

Procedure 1.4.5, PNPS Tagging

Procedure 1.5.3, Maintenance Requests

Procedure 1.5,3.1, Maintenance Work Plan

Procedure 1.5.7, Energency Maintenance

Procedure 3.M.1-30, Post-Work Testing Guidance

Procedure SI-MT.1000, Maintenance Section Manual

Procedure SI-MT.0501, Post-Work Test Matrices and Guidelines

Procedura 3.M.1-11.1, E0 Maintenance Process:

Repair / Replacement

Procedure 3.M.3-1, A5/A6 Buses 4KV Protective Relay Calibration / Functional

Test and Annunciator Verification

Procedure 3.M.3-8, Inspection / Troubleshooting Electrical Circuits

Procedure TP 88-40, 480 VAC Contactor Testing

Procedure TP 88-22, Pre-Operational Test of the New Degraded Voltage

Relays and Motilfied Load Shedding Logic

Procedure PW TMI-1, Post Work Test Matrix and Guidelines, Revision A

Procedure

3.M.4-14,

Rotating Equipment inspection, Asambly and Dis-

j

assembly, Revision 6, dated April 4, 1988

i

l

Procedure 8.Q.3.4, 125/250V DC Motor Control Center Testing and Mainten-

ance

Procedure 2.2.85, Fuel Pool Cooling System

Procedure 3.M.1-15, Vibration Monitoring for Preventive Maintenance and

.

Balancing, Revision 5, dated June 12, 1938

Procedure 2.2.8, standby AC Power System (Diesel Generators), Revision 20,

,

l

dated January 13, 1988

Procedure ARP, Panel C39, Fuel Pool Cooling System, Revision 0, dated

l

January 30, 1988

l

!

Procedure 2.2.83, Reactor Cleanup System, Revision 22, dated June 20, 1988

l

l

-

-

.

Appendix 0 - Documents Reviewed

D-4

Fire Watch Computer Listing, dated August 4, 1988

Fire Protection Maintenance Request Computer Listing, dated August 9, 1988

Pilgrim

Station

Performance

Indicators,

dated

August 10, 1988

and

August 17, 1988

Procedure 8.8.29, "Inspection of Fire Barriers," Revision 1

Temporary Modification Log

Temporary Modification Status Report to R. Anderson f rom P. Mastrangelo,

dated August 4, 1988

Procedure 1.5.9, "Temporary Modifications," Revi' ion 12

Procedure 1.5.9.1, "Lif ted Leads and Jumpers," Revision 0

Procedure 1.3.34, "Conduct of Operations"

Procedure 2.1.16, "Nuclear Power Plant Operator Tour," Revision 54

Overtime Book

Procedure 1.3.67, "Use and Control of Overtime at PNPS"

Advance Overtime Requests for Week Ending August 6,1988

PNPS 1-ERHS-VIII.8-4-0, Turbine Building Shield Wall Design

Confidential

Memo

  1. 13,

to

J. P. Jens

from

K. L. Highfill,

dated

July 19, 1938, "Training Program for Radiation Protection Manager"

Procedure 6.1-209, "Radiological Occurrence Reports"

Radiological Work Plan for A and B Recirculation Pump Seal Welds

Procedure 6.1-012, "Access Control to High Radiation Areas"

Selected RP Techrician Training and Qualification Folders, lesson Plan,

Quizzes and Training Guides

Selected Radiation Work Pernits from March 1988 to August 19S8

Maintendnce Request 87-20-84

_ _ _ _ _ _ _ _ _ _ _ _ _ _

_

.

Appendix 0 - Documents Reviewed

0-5

Procedure 8.M.2-1.5.3.4, "Primary Containment Isolation Logic Channel Test

- Channel 82," Revision 8, dated September 24, 1987

Procedure 8.M.2-1.5.7, "Group I Primary Containment Isolation Valve Test-

ing," Revision 5, dated November 7, 1987

Procedure 8.M.2-8.2, "Calibration of ATS Transmitters Rack C2206," Revis-

ion 2, dated June 30, 1988

Procedure 8.M.1-32.4, "Analog Trip System - frip Unit Calibration - Cabi-

net C2229-82," Revision 5, dated April 4, 1938

Procedure 8.M.2-2.10.8.5, "Diesel Generator 'A'

Initiation By Loss of Off-

Site Power Logic," Revision 8, dated November 6, 1987

Procedure 8 M.2-2.10.8. 3,

"Diesel Generator 'A'

Initiation By Core Spray

logic," Revision 12, dated April 9, 1988

Procedure

3.M.3-1,

"AUA6

Buses 4KV Protective

Relay Calibration /

Functional

Test

and

Annunciator

Verification,"

Revision 23,

dated

August 13, 1988

Procedure 8.M.2-2.6.7, "RCIC Simulated Automatic Actuation," Revision 6,

dated February 5, 1988

Procedure 8.5.5.1,

"RCIC Pump Operability and Flow Rate Test at 1000

psig," Revision 24, dated June 4, 1988

Procedure 8.M.2-2.10.7, "RCIC Automatic Isolation System Logic," Revi s-

ion 11, dated November 7, 1987

Procedure

8.M.2-2.6.1,

"RCIC Steam Line Hi Flow," Revision 13, dated

June 9, 1988

Procedure

8.M.2-2.6.3,

"RCIC Steam Line Hi Temperature," Revision 12,

dated July 17, 1987

Procedure 8.M.2-2.64, "RCIC Steam Line Low Pressure," Revision 16 dated

June 20, 1988

Procedure 8.M.1-32.5, "Analog Trip System - Trip Unit Calibration Cabinet

C2233A, Section A," Revision 2, dated December 7, 1987

Procedure 8.E.11. "Standby Liquid Control System Instrument Calibration,"

Revision 9, dated September 2, 1987

Procedure 8.E.13, "RCIC System Instrument Calibration," Revision 14, dated

June 26, 1988

_ _ _ _ _ _ _ _ _ _ _

.

Appendix 0 - Documents Reviewed

0-6

l

Procedure 8.4.1,

"Standby Liquid Control Pump Operability and Flow Rate

Test," Revision 19, dated April 9, 1988

Procedure 1.8, "Master Surveillance Tracking Program," Revision 9, dated

August 15, 1988

Procedure

1.3.36, "Measurement and Test Equipment," Revision

4,

dated

March S',

1988

Procedure 8.I.1,

"Administration of Inservice Pump and Valve Testing,"

Revision 4, dated August 15, 1986

Procedure

8.I.3,

"Inservice Test Analysis and Documentatics Methods,"

Revision 6, dated May 11, 1988

Orawings

PNPS Elementary Diagram MIN 34-9 (Revision E1):

Primary Containment

Isolation System

PNPS Elementary Diagram MIN 28-12 (Revision E14):

Primary Containment

Isolation System

,NPS Elementary Diagram MIN 36-7 (Sh. 10, Revision E7): Primary Contain-

t

ment Isolation System

PNPS Elementary Diagram MIN 36-7 (Sh.11, Revision ES): Primary Contain-

ment Isolation System

PNPS Elementary Diagram MIN 41-10 (Revision E2):

Primary Containment

Isolation System

PNPS Elementary Diagram MIN 38-11 (Revision E2):

P rima ry Containment

Isolation Sy', tem

PNPS Elementary Otagram MIN 35-7 (Revision E4):

Primary Containment

Isolation System

PNPS Elementary Diagram mig 11-11 (Revision Ell):

RCIC System

PNPS Elementary Diagram MIG 12-12 (Revision ES):

RCIC System

PNPS Elementary Diagram mig 14-9 (Revision ES):

RCIC System

PNPS Elementary Diagram MIG 15-9 (Revision E8):

RCIC System

PNPS Elementary Diagram MIG 16-7 (Revision ES):

RCIC System

PNPS Elementary Diagram MIK 4-11 (Revision E10):

Core Spray

- - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

__ j

.

Appendix 0 - Dncuments Reviewed

D-7

PNPS Schematic Diagram E-548 (Revision E0): Containment Atmosphere Isola-

tion Control

PNPS Schematic Diagram E-38 (Revision E6):

4160V System Breakers 152-504

and 152-604

PNPS Schematic Diagram E-35 (Revision E3):

4160V Auxiliary Relays and

Miscellaneous Schemes

PNPS Schematic Diagram E-27 (Revision E7):

Diesel Generator

PNPS Schematic Diagram E-17 (Revision E7):

Schematic Meter and Relay

Diagram 4160 Volt System

PNPS Schematic Diagram M6-22-14 (Sh. 1, Revision Ell):

Diesc1 Generator

"A" X107A Engine Control

PNPS Relay Setting Drawing E5-200 (Sh. 1, Revision E3): 4160 Volt Switch-

gear Relay Settings

PNPS Relay Setting Drawing E5-200 (Sh. 3, Revision E2): 4160 Volt Switch-

gear Relay Settings

PNPS P&ID M245 (Revision E13):

RCIC System, Sh. 1

PNPS P&ID M246 (Revision E10):

RCIC System, Sh. 2

PNPS P&ID M249 (Revision E12):

Standby Liquid Control System

.

O

r

APPENDIX E

IATI Composition and Structure

Team Manager

Samuel J. Collins

Team Leader

A. Randy Blough

l

Technical Assistant

Clay C. Warren

Administrative Assistant

Mary Jo DiDonato

Jperations

Lawrence W. Rossbach (Lead)

Shift Inspectors

Lawrence W. Rossbach

William J. Raymond

Loren R. Plisco

Lawrence T. Doerflein

F,ancis M. Akstulewicz

I

Radiological Controls

Thomas F. Dragoun

Maintenance

Jeffrey J. Lyash

William J. Raymond

e

Surveillance

Lawrence T. Doerflein

Security

Gregory C. Smith

Fire Protection

Lawrence W. Roseh..n

Assurance of Quality

Loren R. P11sco

Francis M. Akstulewicz

Training and Management

Daniel G. Mcdonald

Effectiveness

Michele G. Evans

Report Coordinator

Tae K. Kim

Commonwealth of

Steven C. Sholly

Massachusetts (Observers)

Pamela M. Chan

- - _ _ - _ _ - _ _ - _ _ _ _ _ _

_ _ _ _ _ _ _ _ _ _ _ .

.

APPENDIX F

NRC Integraced Assessment Team Inspection (IATI)

Members Resumes

This appendix shows IATI summary resumes of the team members and Common-

wealth of Massachusetts observers.

The resumes outline the nuclear

experience of team members.

.

9

.

.

Appendix F

F-2

NAME:

FPANCIS M. AKSTULEWICZ

ORGANIZATION:

United States Nuclear Regulatory Commission

Office of Nuclear Reactor Regulation

Policy Development and Technical Support Branch

TITLE:

Senior Technical Assistant

EDUCATION:

B.S., Nuclear Engineering

EXPERIENCE:

Fourteen Years of Nuclear Experience as Follows:

Two and Goe-Half Years - Shielding Engineer - Bechtel Power

Corporation

One Year - Technical Analyst - Office of Material Safety

and Safeguards (f.'RC)

Eight Years - Nuclear Engineer - Office of Nuclear Reactor

Regulation (NRC)

Two Years - Project Manager - Haddam Neck Plant, Office of

Nuclear Reactor Reg Jlation (NRC)

One-Half Year - Present Position

SPECIAL

QUALIFICATIONS:

Completion of NRC Fundamental and Advanced BWR Systems

Training Course and BWR Simulator Course

SPECIAL

ASSIGNMENTS:

Member of Fire Protection, Health Physics and Diagnostic

Team Inspection at Haddam Neck

I

!

l

r

I

(

L

o

.

Appendix F

F-3

NAME:

A. RANDOLPH BLOUGH

ORGANIZATION:

United States Nuclear Regulatory Commission, Region I

Division of Reactor Projects

TITLE:

Chief, Reactor Projects Section No. 3B

EDUCATION:

B.S.,

U.S.

Naval Academy, 1973 (Graduated with Honors)

Navy Nuclear Engineer Officer Course, 1977

NRC I,3pector Technical Training Program, 1980

Various technical and management courses in USN and USNRC,

such as QA, Reactor Engineering, Reactor Safety, Supervis-

ing Human Resources, EEO, Management Workshops

EXPERIENCE:

Fifteen Years Nuclear Experience as Follows:

1985-Present

United States Nuclear Regulatory Commission (USNRC)

--

Reactor Projects Section Chief.

Manage s <fety inspection

programs for three commercial reactor fac)'ities.

Super-

vise nine nuclear engineers. Provide formal assessments of

utility management effectiveness and safety performance.

1982-1985

USNRC -- Senior Resident Inspector at operations phase and

preoperational phase nuclear power plants. Planned, super-

vised, and performed inspections of management controls and

activities

important

to

nuclear

safety.

Coordinated

specialist inspector efforts.

Formally reported findings

and recommended appropriate enforcement.

1972-1982

USNRC -- Resident Inspector. Planned, performed, and docu-

mented inspections of all functional areas at a dual-unit

operating reactor site.

1973-1979

U.

S. Navy Nuclear Power Program.

Duties included super-

visory positions in nuclear plant operations, maintenance

and training. Performed audits and coordinated plant self-

assessment.

Was

responsible

for a

complex,

in-plant

nuclear training program for up to 300 students. Shipboard

duties included Main Propulsion Assistant: responsible for

all reactor and main propulsion systems, all radiological

controls and plant chemistry.

Collateral duties included

9A Of ficer, and Nuclear Weapons Safety / Security Officer.

SPECIAL

QUALIFICATIONS:

Qualified BWR Inspector, NRC Region I,1980

Qualified Nuclear Engineer Officer, Naval Reactors, 1977

SPECIAL

ASSIGNMENTS:

Team Lesder, NRC Integrated Performance Assessnment Team

Inspection, Oyster Creek, 1987

Team Leader, NRC Team Inspection of Oyster Creek Contain-

ment Vacuum Breakers Event, 1987

Participated in various other plant readiness inspections,

1984-1985

. - _

-_

{

.

Appendix F

F-4

NAME:

PAMELA M. CHAN

ORGANIZATION:

Massachusetts Energy Facilities Siting Council (Since 12/87)

TITLE:

Engineer / Utility Analyst

EDUCATION:

B.S. M.E. Pennsylvania State University

EXPERIENCE:

Five Years Nuclear Experience as Follows:

1987

United States Nuclear Regulatory Commission, Region III,

Reactor Inspector

1985-1987

Nuclear Power Services - Construction

1984-1985

Combustion Engineering

Nuclear Systems Services; Field

-

Service Engineer

1982-1984

Stone & Webster Engineering Corporation - Power Division

System Engineer - Turbine Plant Systems

SPECIAL

QUALIFICATIONS:

Background in Maintenance and Quality Assurance

SPECIAL

ASSIGNMENTS:

Participated in several team inspections while at NRC

Region III

l

1

.

.

Appendix F

F-5

NAME:

SAMUEL J. COLLINS

ORGANIZATION:

United States Nuclear Regulatory Commission Region I

bivision of Reactor Projects

TITLE:

Deputy Director

EDUCATION:

Bachelor of Science, Maine Maritime Academy

Business Program, Southern Vermont College

EXPERIENCE:

Seventeen Years Nuclear Experience in Design, Construction,

Operations, Inspection and Management as Follows:

1987 - Present

Deputy Director:

Division of Reactor Projects, USNRC,

Region I

1986 - 1987

Deputy Director (Detail):

Division of Reactor Projects,

USNRC, Region I

As a member of the Senior Executive Service, responsible

for division management; the conduct of inspections and

evaluations of assigned NRC programs for all power and

non power reactors within Region I.

1985 - 1986

Branch Chief:

Ret.ctor Projects Branch No. 2. USNRC,

Region I

Responsible for project management, staffing and budget

considerations, including irspectionr, implementation of

SAlp, resident inspection and enforcement for eleven

assigned power reactor sites in operation and under

construction.

1984 - 1985

Section Chief:

Reactor Projects Section No. 2C, USNRC,

Region I

Responsible for implementation of the routine and reactive

inspection program at six assigned power reactors during

new cunstruction, testing and cperation.

1983 - 1934

Senior Resident Inspector: Operations, Yankee Nuclear

Power Station, ORP, USNRC, Region I

Supervised; inspection and event response program at opera-

ting Wastinghouse PWR power reactor facility.

1930 -1933

Pesident Reactor Inspector: Operations, Vereont Yankee

Nuclear Power Station, DRP, USNRC, Region :.

Field

inspector at oper. ting Geners' Electric BWR power reactor

,

facility.

.

Appendix F - Samuel J. Collins

F-6

,

Private Industry:

1971 - 1980

Tenneco Corporation, Newport News Shipbuilding.

Various

positions as contractor to U.S. Navy Nuclear Program

including:

Project Manager - S5W Steam Generator Chemical Cleaning

Project

Chief Test Engineer - Chairman and NNS representative to

Joint Test Group for 55W overhaul and construction

Shif t Test Engineer - Shif t supervisor for reactor overhaul

and refueling

Shift Test Engineer - Shift supervisor for reactor new

construction

Mechanica

Test Engineer - Shift mechanical test for reac-

tor new construction

Reactor Design Engineer - Design support for reactor new

construction

SPECIAL

QUALIFICATIONS:

Senior Executive Service Candidate Development Program,

USNRC, 1986 - 1987

Qualified SWR Resident Inspector

Qualified PWR Resident Inspector

Qualified 55W Shif t Test tingineer

Third Engineer License, USCG

SPECIAL

ASSIGNMENTS:

1988 - Team Manager, Pilgrim Integrated Assessment Restart

Team Inspection

1987 - 1988 - Chairman, Pilgrim Restart Assessment Panel

1987 - 1988 - Region I Representative, NRC Training Ad-

visory Group

1937 - Chairman, Differing Professional Opinion Peer Review

Group

1987 - Chairman, Comanche Peak Task Force Review Group

1986 - Team Leader, Nine Mile Point 1 and 2 Diagnostic Team

Inspection

1985 - Team Leader, Pes:h Bottom 2 and ? 11 agnostic Team

Inspection

- _ - _ _ _ _ _ _ _ _ _

e

Appendix F

F-7

NAME:

LAWRENCE T. DOERFLEIN

ORGANIZATION:

United !tates Nuclear Regulatory Commission, Region I

Division of Reactor Projects

TITLE:

Project Engineer

EDUCATION:

BS Electrical Engineering

US Naval Academy, 1973

EXPERIENCE:

Fifteen Years Nuclear Experience as Follows:

Aug. 1985-Present

Project Engineer

Oct. 1993-July 1935 Senior Resident Inspector, FitzPatrick huclear Power Plant

Nov. 1980-0ct. 1980 Resident Inspector, FitzPatrick Nuclear Power Plant

June 1973-Oct. 1980 US Navy

SPECIAL

QUALIFICATIONS:

Certified NRC SWR Inspector

Qualified Chief Naval Nuclear Engineer

SPECIAL

ASSIGNMENTS:

Limerick Readiness Assessment Team

Pilgrim Augmented Inspection Team

I

t

-

.

l

l

I

I

__ .

. _ __

_

- _ _ _ _ _ _ _

_

._ _____ _ __ .

..

_

.

Appendix F

F-8

NAME:

THOMAS F. DRAGOUN

ORGANIZATION:

United States Nuclear Regulatory Commission, Region I

Division of Radiation Safety and Safeguards

TITLE:

Senior Radiation Specialist

EDUCATION:

Rensselaer Polytechnic Institute, and Union College

000 Staf f College, Battle Creek, Michigan

EXPERIENCE:

Twenty-Three Years of Nuclear Experience as Follows:

1983-Present

NRC - Senior Radiation Specialist

1983-1969

General Electric Company, which included the following:

Qualified as Operations Engineer and E00W at Navy

-

Prototype (3 Years)

Senior Engineer on Trident Prototype Construction

-

Project (0 Years)

Health Physicist responsible for service work, both

-

domestic and foreign by Large Steam Turbine Division

(6 Years)

1955-1969

Cornell University - Taught Radiation Protection Subjects

i

4

_ _.

o

.

Appendix F

F-9

NAME:

MICHELE G. EVANS

ORGANIZAfl0'd:

United Sta#ies H<i.itar Regulatory Commission, Region I

Division of Reactor Safety

TITLE:

Operations Enciseor

EDUCATION:

B.S., Cr/mi as Eno'lecring, University Jf Pennsylvania

EXPERIENCE:

Four Years of Nuslear ;perieace as

r llows:

o

Aug 1987-Present

Operations Enginter, Eoiling Water Rasctor Section - Con-

duct review and inspection o# Power Ascension Programs at

Pilgrim and Nine Mile Point 2.

Currently in training tn

qualify as BWR Operator Licensing Examiner

July 1934-Aug 1937 Reactor Engineer, Test Programs Section - Conducted review

and ii:spection of preoperational test programs at Hope

Cre2k ar.d Nine Mile Point 2, and Startup Testing Programs

at Limerick 1, Shoreham, Pope Creek and Nine Mile Point 2.

SPECIAL

QUALIFICATICNS:

USNRC Certified BWR Inspector

Engineer in Training (State of Pennsylvania)

SPECIAL

ASSIGNMENTS:

Currently participating in the Women's Executive Leadership

Program for Management Development

,

. _ _ _ _ _ _ _ _ _ _ _ - _ _ _ - _

.

Appendix F

F-10

NAME:

JEFFREY J. LYASH

ORGANIZATION:

United States Nuclear Regulatory Commission, Region I

Division of Reactor Projects

TITLE:

Resident Inspector - Pilgrim Nuclear Power Station

EDUCATION:

B.S. , Mechanical Engineering, Orexel University

EXPERIENCE:

Six Years Nuclear Experience as Follows:

Two and One-Half Years - NRC Resident Inspector - Pilgrim

Nuclear Power Station

One Year - NRC Resident Inspector - Hope Creek Generating

Station

One Year - NRC Reactor Engineer - Region I

One and One-Half Years - Pennsylvania Power and Light

Company - Test Engineer - Susquehanna Steam Electric

Station

SPECIAL

QUALIFICATIONS:

Meritorious Service Award as NRC Resident Inspector of the

Year 1987-1988

.

,

Appendix F

F-11

NAME:

DANIEL G. M 00NALD, JR.

ORGANIZATION:

United States Nuclear Regulatory Commission (USNRC)

Office of Nuclear Reactor Regulation

TITLE:

Senior Project Manager

EDUCATION:

B.S., Management, Shenandoah College

A.A., Engineering, Solano College

EXPERIENCE:

Thirty-One Years Nuclear Experience as Follows:

1982-Present

Senior Project Manager - Manage and coordinite all NRC

licensing functions on assigned operating reactor facil-

ities which have difficulties or complexities with manage-

ment and operation.

(NRC)

1982 (3 Months)

Reactor Engineer (Instrumentation) - Technical evaluations

of instrumentation and control systems or licensee appli-

cations and operating reactor modifications. Assist in

developing regulatory requirements and establishing staff

policy.

(NRC)

1980-1932

Staff Member - Conduct, direct and coordinate assessments

of critical technologies in the context of national secur-

ity.

Provide technical support to the Nuclear Regulatory

Commission.

(Los Alamos National Laboratory)

1979-1980

Reactor Inspector (Electrical) - Inspects reactors under

construction and in operation.

(NRC)

1978-1979

Senior Electrical Engineer - Technical evaluations of

electrical, instrumentation and control systems. Assist in

developing staff policy.

(NRC)

1973-1978

Reactor Engineer (Instrumentation) - Technical evaluation

for license applications and operating reactors.

(NRC)

1966-1973

Senior Technical Associate - Field engineer in nuclear

weapons test programs.

(Lawrence Livermore Laboratory

(LLL))

>

1964-1966

Senior Electronic Engineering Coordinator - Design of con-

trol, interlock and instrumentation systems for critical

assembly machines, test reactors and containment vaults.

(LLL)

1960-1964

Electronics Designer - Design of cormunication, personnel

warning, closed circu t TV and radiation monitoring

i

systems.

(LLL)

.

,

Appendix F - Daniel G. McDona'.d Jr.

F-12

1957-1960

Senior Electronic Technician - Fabricated and assisted in

the design and development of prototype electrical and

electronics equipment.

(LLL)

1953-1957

Electrical Specialist - Four year apprenticeship with

Department of Navy.

(Mare Island Shipyard)

1

l

1

. .

.

.

_ ______

_ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ .

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

s

.

Appendix F

F 13

NAME:

LOREN R. PLISCO

ORGANIZATION:

United States Nuclear Regulatory Commission

Office of Nuclear Reactor Regulation

Division of Licensee Performance and Quality Evaluation

TITLE:

Senior Operations Engineer

EDUCATION:

B.S., Systems Engineering, U.S. Naval Academy

EXPERIENCE:

Eleven Years Nuclear Experience as Follows:

1937-1988

Senior Operations Engineer, NRC:NRR

1936-1987

Senior Resident Inspector - Susq;ehanna Steam Electric

Station

-

1983-1986

Resident Inspector - Susquehanna Steam Electric Station

1932-1983

Reactor Engineer, Region I

197/-1982

'.'S Navy Nuclear Power Program

SPECIAL

QUALIFICATIONS:

Certified NRC BWR Inspector

'

Qualified Naval Nuclear Engineer Officer

SPECIAL

ASSIGNMENTS:

Susquehanna 2 - Operational Readiness Assessment Team

Inspection

Limerick 1 - Operational Readiness Asssessment Team Inspec-

tion

i

Hope Creek - Operational Readiness Assessment Team Inspec-

tion

i

1

Salt.m - ATWS Inspection

THI-1 - Management Integrity Inspection

i

I

{

I

,

1

i

l

l

1

i

i

!

(

!

l

,

4

. . .

- .

r -

,

Appendix F

F-14

NAME:

WILLIAM J. RAYMOND

ORGANIZATION:

United States Nuclear Regulatory Commission, Region I

Division of Reactor Projects

TITLE:

Senior Resident Inspector - Millstone Nuclear Power Station

EDUCATION:

B.S. Physics

M.S. Nuclear Science and Engineering

EXPERIENCE:

Eighteen Years Nuclear Experience as Follows:

1975-1988

NRC Reactor Operations Inspector

SU&T, Core Physics, Refueling, Pre & SU&T for BV, CC1,

-

IP3, MP2

Project Inspector - Beaver Valley, Ginna and Susque-

-

hanna

TMI Recovery Team - Accident Response and Containment

-

Entry

Senior Resident Inspector - Vermont Yankee and Mill-

-

stone

1972-1975

Startup Engineer, Babcock & Wilcox, Oconee 1 and 2 and

Three Mile Island, Unit 1

1970-1972

Reactor Operator, VP1 Research Reactor

SPECIAL

QUALIFICATIONS:

VPI Reactor Operator License

Certified NRC Licensed Operator Examiner - 1986

SPECIAL

ASSIGNMENTS:

IAEA Assist Visit to Brazil CNEN - 1981

Team Leadar Salem ATWS Event - NRC Fact Finding - 1983

Salem ATWS Generic Issue Review Team - 1983

NRC Response to Crystal River Event - 1981

Assist Visit to Region V - WNP2 Startup Readiness - 1982

Tean Inspections - Shoreham 1932 and Pilgrim 1986

Operator Briefings of TMI Event - 1979

-

_ _ _ _ _ _ _ _ _ _ _ _ _

o

,

t

Appendix F

F-15

NAME:

LAWRENCE ROSSBACH

ORGANIZATION:

United States Nuclear Reguletory Commission, Region I

Division of Reactor Projects

TITLE:

Senior Resident Inspector - Indian Point Unit 2

EDUCATION:

8.S., Nuclear Engineering

EXPERIENCE:

Sixteen Years of Nuclear Experience as Follows:

Six 7 ears, NRC Resident Inspector and Senior Resident

Inspector

Two and One-Half Years, Program Manager for NRC's prepara-

tion to review a high level waste repository li:ense

application

Two and One-Half Years, NRC Project Manager and Reviewer

for Uranium Mills

Five Years, Systems Design Engineer at Architectural

Engineering (AE) Company

l

I

I

i

l

l

l

l

!

.

j

.

App;ndix F

F-16

NAME:

STEVEN C. SHOLLY

ORGANIZATION:

MHB Technical Associates (Observer for the Commonwealth of

Massachusetts

TITLE:

Associate Consultant

EDUCATION:

B.S. in Education (1975) Graduate Course Work in Geo-

environmental Studies (1976-1977)

EXPERIENCE:

Seven and One-Half Years Nuclear Experience as Follows:

1985-Present

MHB Technical Associates, San Jose, CA - Work in Risk

Assessment, Quality Assurance, Optrating Events Analysis,

and Design and Construction Assessment

1981-1935

Union of Concerned Scientists, Washington, D.C. - Work in

generic safety issues, risk assessment and emergency

planning

SPECIAL

ASSIGNMENTS:

Member of NRC Peer Review Group, NUREG-1050 (1984)

-

Participated in NRC Containment Performance Design

-

Objective Workshop (1986)

Participated in NRC/LLNL Workthop on Safety Goals

-

Implementation, Presentation on Seismic Risk

Assessment (1987)

l

.

r -

,

Appendix F

F-17

,

NAME:

GREGORY C. SMITH

ORGANIZATION:

United States Nuclear Regulatory Commission, Region I

Division of Radiation Safety and Safeguards

l

TITLE:

Safeguards Specialist

'

EDUCATION:

B.S. Education, California State College

Various additional courses including:

Technical

-

Writing, Quality Assurance Auditing, Statistics,

'

Reactor Design and Layout, Radiological Accident

Assessment, Rrdiological Emergency Response, BWR

Technology, Transportation of Radioactive Materials,

Advanced Neutron Nuclear Materials Assay, Safeguards

Chemical Analysis of Nuclear Materials, Nondestructive

Assay of Nuclear Materials, Nondestructive Assay of

Fissionable Material, Accident / Incident Investigation

and Intrusion Detection Systems

EXPERIENCE:

Twenty-Two Years Nuclear Incestry Experience as Follows:

1977-Present

Safeguards Specialist, Physical Protection Inspector and

Safeguards Auditor (USNRC)

1966-1977

Westinghouse Electric Corperation, Bettis Atomic Power

Laboratory - Production Engineer, Nuclear !'aterials Aud-

.

itor, Nuclear Materials Analyst, Reactor Development

l

Technician

!

f

1

1

!

!

!

,

!

!

t

,

.

- - -

~

,

o

.

Appendix F

F-18

4

NAME:

CLAY C. WARREN

ORGANIZATION:

United States Nuclear Regulatory Commission, Region I

Division of Reactor Projects

TITLE:

Senior Resident Inspector - Pilgrim Nuclear Power Station

EDUCATION:

B.S., Natural Sciences, Louisianna State University

Industrial:

1986 - USNRC Inspector Qualification Program

1985 - Training Program on the General Electric BWR-6 oro-

.

duct ifne and received NRC Senior Reactor Operator License

1982 - GE Boiling Water Reactor (BWR) Senior Reactor Oper-

stor Certification training at the General Electric BWR

l

. raining Center

1980 - Shif+ Test !

'neer training program at General

Dynamics Corporation, Electric Boat Division.

Successfully

completeo the Naval Engineering Officer exam administered

by Naval Reactors.

Military:

Navy Nuclear Prototype Training

Navy Nuclear Power School

Electronics Technicians School

EXPERIENCE:

Fif teen Years Nuclear Experience as Follows:

Jan 1987-Present

United States Nuclear Regulatory Commission, Senior

Resident Inspector

Jan 1986-Jan 1987

Resident Inspector

June 1934-Jan 1936 Shift Supervisor, Gulf States Utilities Company, River Bend

Nuclear Station

Jan 1931-June 1934 Control Operating Foreman, Gulf States Utilities Company,

River Bend Nuclear Station

June 1979-Dec l'J30 Shift Test Engineer, General Dynamics Corporation, Electric

Boat Olvisien

.

Jan 1971-June 1979 Electronics Technician - Reactor Operate., United States

Navy

SPECIAL

QUALIFICATIONS:

USNRC Senior Reactor Operators License

.

-

_

f

Appendix F - Clay C. Warren

F-19

SPECIAL

ASSIGNMDO S;

Nine Mile Point 2 Operational Readiness Assessment Team

Inspection

Peach Bottom - Special Team Inspection March 1986

1

- - -

-.

. - - - - _

_ _ _ _ _ ,

__

. _ _ _ _ _ _ _ _ _ _ _ _ _ _

_____

_ _ _ _ _ _ _ _ _ _ -

e

  • "%

UNITED STATES

k

f

NUCLEAR REGULATCRY COMMi^^15N

I

.

REGION 1

,

475 ALLINoALE ROAD

KING oF PRUe41 A. PENNSYLVANIA 19406

.....

01 SEF 1988

The Commonwealth of Massachusetts

Executive Office of Public Safety

ATTN: Mr. Charles V. Barry

One Ashburton Place

Boston, Massachusetts 02108

Dear Mr. Barry:

This refers to our letter of July 13, 1988, regarding the Commonwealth of

Massachusetts' participation in the Integrated Assessment Team Inspection

(IATI) conducted at the Pilgrim Huclear Power Station.

As the NRC Senior Manager responsible for the inspection, I would like to ac-

knowledge the conduct of the designated state representatives Ms. Pamela J. Chen

and Mr. Steven C. Sho11y as being professional and contributing to the perfor-

mance of the inspection.

The established protocol (enclosed) provided to you on June 1,1988, clarified

by our letter of July 13, 1988, and discussed directly by myself with

Mr. Peter Agnes of your staff on August 9,1988, provides for collection and

coordination of the concerns from the various interests within the Commonwealth.

As stated in our July 13, 1988 letter, the NRC placed the burden on the Common-

wealth's representative to present the many views, be they from the local

governments or from the State's Attorney General's office, to the NRC for

consideration during development of tne inspection scope.

In this regard, we

understand that Mr. Agnes conducted a public meeting on August 4, 19:3, with a

designated state representative to the IATI present.

On August 9, 1988, having received no issues from the Commonwealth as an

additional input to the existing inspection plan, I contacted the Assistant

Secretary of Public Safety directly and was assured that: no formal input to

the IATI inspection plan would be submitted by the Commonwealth, the

Commonwealth would work through the designated representatives for any issues

and that issues brought to the Commonwealth's attention were no different than

those previously noted. Also, the team leader has not.ified me that at no time

during the inspection did he receive immediate notification of any different

state observation or conclusion as would be called for under Protocol

Guideline 3 if any such dif ferences were identified during the inspection.

Since the IATI exit meeting conducted on August 24, 1988 which was attended by

Mr. Agnes and Ms. Chen, the Commonwealth has expressed on several occasions

both to the tredia and #t public meetings that technical issues and management

concerns continue to exist. These statements appear inconsistent with the

Commonwealth's response to repeated NRC requests for IATI inspection scope

input and moreover inconsistent with the Comonwealth views expressed at the

IATI exit meeting.

In order to better understand and address the areas of concern, the NRC

requests that in accordance with the protocol agreement accepted by the

Comrinwealth, as provided f( ? by Guideline 3, that the Commonwealth make

available in writing those conclusions or observations that are substantially

,

different fro'n those of the NRC inspectors in order that the NRC can take the

necessary actions to meet its regulatory responsibilities.

? 0 T O ? ?!C-5

.?g

l_

- - - - - - - _ - - .

_-

.

.

G-2

-

Mr. Charles V. Barry

2

01 SF.F 1988

It is necessary that the Commonwealth's response be provided to the NRC Region

I by September 6, 1988, to be considered in conjunction with the documentation

of the results of the recently completed IATI.

This request was discussed

with Mr. P. Agnes of your staff on August 26 and August 31, 1988.

If you have any questions regarding the above matters, please contact me at

(215) 337-5126 or the State Liaison Officer for Region I, Ms. Marie Miller at

(215) 337-5246.

Sincerely,

we

o

ns, leputy Director

.

Division of Reactor Projects

Enclosure: As Stated

cc w/ enc 1:

'

R. Bird, Senior Vice President - Nuclear

K. Highfill, Station Director

'

R. Anderson, Plant Manager

J. Keyes, Licensing Division Manager

E. Robinson,. Nuclear Information Manager

R. Swanson, Nuclear Engineering Department Manager

The Honorable Edward J. Markey

i

The Honorable Edward P. Kirby

The Honorable Peter V. Forman

!

B. McIntyre, Chairman, Department of Public Utilities

1

Chairman, Plymouth Board of Selectmen

I

Chairman, Duxbury Board of Selectmen

Plymouth Civil Defense Director

P. Agnes, Assistant Secretary of Public Safety, Commonwealth of

Massachusetts

S. Pollard,**sssachusetts Secretary of Energy Resources

,

R. Shieshak, ,s'.SSPIRG

!

Public Documet Room (POR)

Local Public Document Room (LPOR)

Nuclear Safety Information Center (NSIC)

NRC Resident Inspector

CommonwealthofMassachusetts(2)

,

bec w/ enc 1:

!

Region I Docket Room (with concurrences)

l

S. Co11tns, DRP

f

i

'

J. Wiggins, ORP

R. Blough, DRP

L. Doerflein, DRP

R. Bores, DR35

D. Mcdonald, FM, NRR

!

!

f

I

$


.,n------.-m

- - - , - - . --

- - - . - , - -

..-n,,,,--.- - - - _

.

- - - - - - -

. - - - - - - - - - - - - .

_ _ _ _ _

. _ _ - . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

_

__

_ _ _ _ _ _

e

b

G-3

EN,C_LOSURE

Guidelines for Accompaniment on the Integrated Assessment Team Inspection

The following are guidelines for accempaniment during NRC's Pilgrim Integrated

Assessment Team Inspection.

1.

The observer is to make arrangements with the licensee for site access

training and badging.

2.

The observer shall be available throughout the inspection and will accom-

pany NRC inspectors. Communication with the licensee will be through the

appropriate NRC team member, preferably the team leader.

3.

When

the conclusions

or observations made by the Comonwealth of

Massachusetts observer are substantially different from those of the NRC

inspectors, Comonwealth of Massachusetts will make its observations

-

imediately known to the inspection team leader and available in writing

to the NRC and the licensee, in order that NRC can take the necessary

actions to meet its regulatory responsibilities.

These communications

will be publicly available, similar to NRC inspection reports.

4.

NRC inspectors are authorized to refuse to permit continued accompaniment

by the Comonwealth of Massachusetts observer if his conduct interferes

,

l

with a fair and orderly inspection.

S.

The Comonwealth of Massachusetts observer in accompanying NRC inspectors

will not normally be provided access to proprietary information.

No

license material may be removed from the site or licensee possession

without NRC approval.

6.

The Comonwealth of Massachusetts observer in accompanying the NRC

,

inspectors pursuant to these guidelines does so at his (.vn risk. The NRC

i

l

will accept no responsibility for injuries and exposures to harmful

,

substances which may occur to the accompanying individual during the

l

inspection and will assume no liability for any incidents associated with

'

the accompaniment.

L

t

I

_