November 14, 1996
SUBJECT:
REQUEST FOR CLARIFICATION OF EXAMINATION REPORT COMMENTS l
l
Dear Mr. Watzt:
l l
We have reviewed a letter from Mr. M. Wadley dated October 7,1996, requesting clarification of comments in operator licensing examination report OL-96-01 with respect l
to procedural inadequacies; specifically "During the course of the examination, the l
_ examiners observed a number of operations procedures were lacking consistent,
>
!
comprehensive operator actions to ensure continued safe operations during normal and abnormal conditions. These procedure discrepancies will be discussed in Inspection
!
Reports 50-282/96007; 50-306/96007."
'
l l
Inspection Report 96007 identifies two separate proceduralissues. The first was
!
l observed when candidates had difficulty in the simulator responding to a degraded voltage -
'
,
event. The procedure referenced in the annunciator response procedure did not exist and
,
the crew members took actions they deemed necessary without procedural guidance. The
'
second involved a lack of recording "as found" surveillance test data. Although these issues had been identified by you, it still showed a weakness in procedures.
l
,
!
'
.
.
At the time the examination report was issued an additional procedure violation was believed to exist. This item was identified by an examiner and involved a potential l
l violation for an inadequate surveillance procedure. This item in concert with the two
!
examples of procedural problems identified in Inspection Report 96007. formed the basis for the comment in the examination report. ' However, during independent review of the matter before proceeding with a violation, the surveillsnce procedure was determined to be
<
satisfactory and therefore this issue was not discussed in inspection Report 96007.
l Based upon the issues described above, we do not feel you have a significant problem D
with operational procedures; however, some additional attention to procedure details may be warranted.
,
l
,
9611200134 961114 PDR ADOCK 05000282 PDR i
l
.
.-
_
-._ -.
...
-
.
.-.
!T l
,
L i
!
E. Watzi-2-November 14, 1996
>
We will gladly discuss any questions you may have relative to this letter.
l
!
j_
Sincerely,
'
i Original Signed by Brent Clayton (for)
Geoffrey E. Grant, Director Division of Reactor Safety I
i Docket No. 50-282
!
Docket No. 50-306 e
cc:
Plant Manager, Prairie Island John W. Fermar., Ph.D.
Nuclear Engineer, MPCA
-
State Liaison Officer, State of Minnesota l
State Liaison Officer, State t
of Wisconsin Tribal Council, Prairie Island
,
Dakota Community l
Cistribution:
i Docket File Rlli PRR Enf. Coordinator, Rlli
'
PUBLIC lE-42 SRis, Prairie Island, CAA1 (E-mail)
'
OC/LFDCB Montice!!o W. L. Axelson, Rlli j
DRP LPM, NRR A. B. Beach, Rill
'
!
l DOCUMENT NAME: G:DRS\\PRA11d6.DRS
To receive a copy of ibis document, indicate in the box "C" = Copy without attach /enci
"E" = Copy with attach /c9cl "N" = No copy OFFICE Rlli C-Rill C--
Rlll gt C
,,,
NAME MLeach:jp 4Vv4 JJacobsh[ok BClayton/GGrant
/
i DATE 11/4 /96 11//Y/96 11/19/96 OFFICIAL RECORD COPY
-