JOSEPH M. FARLEY NUCLEAR PLANT UNITS 1 AND 2 EDWIN I. HATCH NUCLEAR PLANT UNITS 1 AND 2 2019 Annual Assessment Reactor Oversight Process Nuclear Regulatory Commission - Region II ML20101K658

Meetings Purpose

Public forum to address Joseph M. Farley Nuclear Plants & Edwin I.

Hatch Nuclear Plants Units 1 and 2 performance in 2019

Provide an overview on NRC inspection activities

NRC Resident Inspectors and Representatives are available for individual discussion; questions and answers

Agenda

Introduction

Review of Reactor Oversight Process

Discussion of Plant Performance Results

NRC Response to COVID-19

NRC Closing Remarks

NRC available to address public questions

NRC Mission Statement

The NRC licenses and regulates the Nation's civilian use of radioactive materials to provide reasonable assurance of adequate protection of public health and safety and to promote the common defense and security and to protect the environment.

STRATEGIC GOALS SAFETY STRATEGIC GOAL: Ensure the Safe Use of Radioactive Materials SECURITY STRATEGIC GOAL: Ensure the Secure Use of Radioactive Materials

Resident Inspector Program Inspectors live in the community and work at the Nuclear Plants Provide daily coverage and oversight of plant activity

Resident Inspector Program Daily visits to control room and meetings with plant managers Prioritize inspections based on important plant activity

Resident Inspector Program Observe emergency exercises and provide support for any real emergencies or urgent issues

Resident Inspector Program Support NRC allegation process for plant employees and the public Routinely discuss safety concerns with plant management and operators

Action Matrix Columns Licensee

Response

Regulatory

Response

Degraded Performance Multiple/ Repetitive Degraded Cornerstone Unacceptable Performance Farley and Hatch - Licensee Response Column (Column 1 of IMC 305) of the NRCs ROP Action Matrix for 2019

Farley Nuclear Plant Findings and Performance Indicators

All PIs were Green (no performance thresholds exceeded)

4 Green non-cited violations

Order for protection of safeguards

Hatch Nuclear Plant Findings and Performance Indicators

4 - Green non-cited violations identified in 2019

All PIs were Green (no performance thresholds exceeded)

SLIII violation, IR 2019003, Enforcement Action EA-19-062: Improper SRO License Reactivation. This violation received enforcement discretion due to the conflict between the NUREG 1021 and 10 CFR 55.53(f)(2) 1

Slide 11 1

Consider keeping this slide if White/Yellow/Red findings are identified. Otherwise, this slide probably is not necessary.

Nick Hobbs, 1/11/2018

NRC Response to COVID-19 Mission Critical Functions Monitoring plant activities through inspections and oversight Maintaining emergency response capabilities with Regional IRCs and HQ Risk-informing "eyes on" inspections through residents and regional inspections

NRC Response to COVID-19 Additional Actions Expanded use of telework where appropriate.

Dedicated Continuity of Operations Plan.

Coordinating actions with industry on best practices to minimize impacts.

NRC Social Media Channels

Blog:

http://public-blog.nrc-gateway.gov/

Facebook:

https://www.facebook.com/nrcgov/

Flickr:

http://www.flickr.com/photos/nrcgov/

Twitter:

https://twitter.com/#!/nrcgov

Youtube:

http://www.youtube.com/user/NRCgov

RSS:

http://www.nrc.gov/public-involve/listserver.html#rss

Contacting the NRC

Report an emergency

(301) 816-5100 (call collect)

Report a safety concern

(800) 695-7403

Allegation@nrc.gov

General information or questions

www.nrc.gov

Contact Farley Nuclear Plant Resident Inspectors

Phone (404) 997-5140

Contact Hatch Nuclear Plant Resident Inspectors

Phone (404) 997-5160

End of Presentation Nuclear Regulatory Commission Region II April 21, 2020