ML20079F072

From kanterella
Jump to navigation Jump to search
Confirms 780227 Telcon W/R Robb Re Corrections to Jan 1978 Yellowbook (NUREG-0030).Corrections Listed
ML20079F072
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 02/27/1978
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Lovelace W
NRC
Shared Package
ML20079E953 List:
References
FOIA-83-553, RTR-NUREG-30 NUDOCS 8401180073
Download: ML20079F072 (3)


Text

_

a e

M1h M8D

& CS M k3TW

p. n doV geye. -

H:)E NIX, Am2oN A 85o36 j

7 4g February 27, 1978 ANPP-10411 Mr. W. H. Lovelace Plans Branch U. S. Nuclear Regulatory Commission Maryland National Bank Building Washington, D. C.

20055

Subject:

NRC "Yellowbook" Schedules (NUREG-0030-78 /01)

Dear Mr. Lovelace:

This letter is to confirm the telephone conversation between yourself and our Mr. Roger Robb on February 27, 1978. The subject "yelinwbook" for January,1978 was discussed and marked up for reprinting on March 3, 1978 to show the following corrections:

(1) Page 2 Palo Verde 1 Applicants Current Fuel Loading Date 11/81 Previous 11/81 FLD 0 CP Issuance 11/81 Construction Started 6/76 Construction approximately 22% complete at end of January 1978 The schedule network would have all dates removed except the last two nodes on the right-hand side:

Plant Ready for Fuel Loading 11/81T Estimated Start of Commercial Operation 5/82T Note to be printed across schedule network:

DETAILED NETWORK TO BE ESTABLISHED B401100073 831011 PDR FOIA BERNABE83-553 POR

n e

Mr. W. H. Lovelace USNRC - Plans Branch ANPP-10411 February 27, 1978 Page 2 (2) Page 2 Palo Verde 2 Applicants Current Fuel Loading Date 11/83 Previous "

11/83 FLD 0 CP 1ssuance 11/83 i

Construction Started 6/76 Construction approximately 6% complete at end of January 1978 The schedule network would be treated same as Unit 1 with last two nodes on the right-hand side showing:

Plant Ready for Fuel Loading 11/83T Estimated Start of Commercial Operation 5/84T Note to be printed across schedule:

DETAILED NETWORK TO BE ESTABLISHED (3)

Page 2 Palo Verde 3 Applicants Current Fuel Loading Date 11/85 Previous "

11/85 FLD @ CP Issuance 11/85 Construction less than 1% complete The schedule network would remain as is except dates corrected for last two nodes on the right-hand side as follows:

Plant Ready for Fuel Loading 11/85T Estimated Start of Commercial Operation 5/86T l

l a

i Mr. W.11. Lovelace USNRC - Plans Branch ANPP-10411 February 27, 1978 Page 2 l

i i

With the foregoing corrections made for the February issuance of the

-l report, we would now like to start the procedure described in Sect on i

4 of the "yellowbook." We, therefore, request that we set a meeting date sometime the week of March 13, 1978 (or as soon as possible there-after) here in Arizona to establish a correct network for this project, correct node dates for that network and set-up the reporting routine to be followed for the remainder of the project.

Please advise us as soon as posrible of a convenient date for a meeting.

We appreciate your cooperation in bringing this report up to date for the remainder of the project.

Very truly y,ours, 1

e C C L/

[, T, N CLLL f1 A [.-%

E. E. Van Brunt, Jr.

APS Vice President Construction Projects ANPP Project Director EEVBJr/RLR/mW cc:

T. G. Woods, Jr.

A. C. Gehr R. L. Robb W. Grape i

J l

a

UNITED STATES

,l' *

4 NUCLEAR REGULATORY COMMISSION f,.. '

WASHINGTON. D. C. 20586 y.rgv)/

o MAY 141979 Docket Nos. STN 50-528/529/530 APP'LICANT: Arizona Public Service Company FACILITY:

Palo Verde, Units 1, 2, and 3

SUBJECT:

SlM4ARY OF CASELOAD FORECAST PANEL MEETING AND SITE VISIT A meeting was held on April 25, 26, 1979 in Phoenix, Arizona with the applicant to discuss the status cf construction for the facility. A tour of the site was made on the afternc,on of April 25, 1979 to witness the status of construction. The agenda for the meeting is shown on and the meeting attendees are listed in Enclosure 2.

The meating is summarized as follows.

i Sumary The applicant presented a brief overview of the project history, site layout, organization of utility management, plant operations crew and startup crew. Bechtel, the architect-engineer and constructor, presented a brief sumary of its organization in support of the facility.

The applicant also briefly discussed financial considerations and licensing milestones.

The applicant made a more detailed presentation on the project schedule. For Unit 1, the current status of engineering is that specification awards are about 95 percent complete and drawings are about 92 percent complete.

Procurement status is that 54 percent of both piping and valves for Unit 1 have been deliveed. Overall percent completion of Unit 1 construction is estimated at 37 percot. The critical construction activities are (1) the availability of construction personnel (pipe fitter welders and electricians), (2) receipt of Class 1E electrical components, and (3) receipt of pipe hangers.

The preoperational testing program was also discussed.

Currently a detailcd testing schedule is in preparation and is expected to be ready by August 1979. The first system will be ready to be turned over for testing in November 1980. The testing schedule being developed will be based on a three shift operation in order to meet the applicant's projected fuel load oate of November 1981 for Unit 1.

/

m-~--

r

.~.

l

. ggy 14 jg79 At the exit interview held on April 26, 1979, we presented our current assessment of the fuel load date fer Unit 1.

Based on the status and pace of construction, and comparing these aspects with those of similar facilities which have been or are being constructed, we projected that the most likely date for Unit 1 fuel loading is December 1982.

We informed the applicant that we use our projected fuel load dates to (1) determine future manpower requirements, (2) determine when our review of an OL application should start, and (3) establish schedules and priorities for the review of OL applications.

Our current practice is to start an OL review about 2 to 3 years before our projected fuel load date. Therefore, the applicant's plans for submittal of an OL application about the end of 1979 are compatible with this practice.

We informed the applicant that OL review schedules are not established until after an application has been accepted for review.

In this regard we requested that, at the time the applicant submits its application for an OL, the applicant provide us with updated status information in the areas of procurement, construction and scheduling of preoperational testing. We will use this updated information to reassess our projected fuel load date for Unit 1 and thus assure that the schedule we develop will be compatible with this ~date. The applicant agreed to provide the requested information at that time.

' il J'.c.

/'.7..

a Emanuel Licitra, Project Manager Light Water Reactors Branch No. 3 Division of Project Management

Enclosures:

1.

Meeting Agenda 2.

Meeting Attendees cc w/ enclosures:

See next page

. MAY 14 OIS Mr. E. E. Van Brunt, Jr.

Vice President - Construction Projects Arizona Public Service Company P. O. Box 21666 Phoenix, Arizona 85036 cc: Arthur C. Gehr, Esq.

Snell & Wilmer 1100 Valley Center Phoenix, Arizona 85073 Charles S. Pierson Assistant Attorney General 200 State Capitol 1700 West Washington Phoenix, Arizona 85007 David N. Barry, Esq., Senior Counsel Charles R. Kocher, Esq., Assistant Counsel Southern California Edison Company P. O. Box 800 Rosemead, California 91770 Dr. Stanely L. Dolins Assistant Director Energy Programs (OEPAD)

Office of the Governor 1700 West Washington Executive Tower - Rm. 507 Phoenix, Arizona 85007 l

s D

ENCLt?40RE 1 PVNGS 1, 2, 3, 4 & 5 Caseload Forecast Panel Meeting April 25 & 26, 1979 April 25. 1979, 8:00 a.m. - 11f00 a.m.

l. Introduction Project History Sita Layout
2. Overview of Financial Considerations
3. Utility Management Orgaaization
4. Bechtel Organization
5. Licensing
6. Project Schedule A.

Engineering Status B.

Procurement Status C.

Construction Introduction Concrete Structural Steel Piping / Hangers Cable Trays D. Preoperational Testing Status of Procedure Writing Target Dates for System Turnover to Startup Training and Staffing E. Critical Activities

\\

~..

Craft Availability / Negotiations

- _.=

l

l I

PVNGS 1, 2, 3, 4 & 5 i

Caseload Forecast Panel Meeting - Page 2 l

t 1;15 p.m. - 3:00 p.m.

PVNGS Site Tour d

April 26, 1979 4

9:00 a.m. - 12:00 noon

1. Items Remair.ing from Previous Day
2. Exit Conference 4

)

)

0 1

4 0

I

,-.e-n,.

+ - -.

y

ENCLOSURE 2 MEETING ATTENDEES APRIL 25, 1979 NRC

  • Bill Lovelace
  • Sybil Kari
  • Emanuel Licitra APS
  • Don Karner
  • Rex Kramer Wes Hartley
  • Bill Petro Wes Grape John Kirby
  • Ed Van Brunt BECHTEL Doug Wood SNELL & WILMER
  • Arthur Gehr ENERGY PROGRAMS OFFICE, OFFICE OF GOVERNOR Stan Dolins
  • Also attended exit interview on April 26,1979 1

-9' w-

+

y

- e

LJ) a MEETING SlJMMARY DISTRIBUTION Docket File H. Bassett, MPA NRC PDR S. Kari, MPA Local PDR A. Abell, MPA TIC H. Berkow, DPM NRR Reading G. Mathews, IAE LWR #3 File L. Schaub, CON D. Bunch W. Lovelace, MPA E. Case R. Boyd D. Vassallo W. Gammill J. Stoir R. Baer

0. Parr S. Varga C. Heltemes L. Crocker
0. Crutchfield F. Williams R. J..'iattson R. DeYoung Project Manager ELicitra Attorney. OELD M. Rushbrook IE (1)

NDP DarticjDants!

ACRS (16)

R. Denise

(_B.Lovelaci)

L. Rubenstein a sari 9

BCC: Applicant & Service List W

e il l

4 l

-