ML20076M960
| ML20076M960 | |
| Person / Time | |
|---|---|
| Site: | Shoreham File:Long Island Lighting Company icon.png |
| Issue date: | 07/18/1983 |
| From: | Christman W HUNTON & WILLIAMS, LONG ISLAND LIGHTING CO. |
| To: | Atomic Safety and Licensing Board Panel |
| References | |
| ISSUANCES-OL, NUDOCS 8307210164 | |
| Download: ML20076M960 (23) | |
Text
LILCO, July 18, 1983
/
/d b\\
{7
\\ p.;M Y:.
G,62
[f 3
'9 UNITED STATES OF AMERICA r
NUCLEAR REGULATORY COMMISSION j??,\\, h '..tf*.lkl"o
.l
- c. 's,
j yj Before the Atomic Safety and Licensing Board /)),
Vhb,f(-
\\'" / 72;IfU ' '
In the Matter of
)
)
LONG ISLAND LIGHTING COMPANY
)
Docket No. 50-322 (OL)
)
(Shoreham Nuclear Power Station, )
Unit 1)
)
LILCO'S REPLY TO THE ANSWER AND OPPOSITION OF SUFFOLK COUNTY TO LILCO'S MOTION FOR A LOW-POWER OPERATING LICENSE On June 8, 1983, Long Island Lighting Company (LILCO),
pursuant to 10 C.F.R.
S SO.57(c), filed a motion for an operating license authorizing low-power testing and further operations at power levels not to exceed five cercent of full po,wer.
LILCO asked that this Board consider and rule on the motion, recognizing that the Board's decision required a con-sideration of (1) onsite emergency preparedness, (2) a partial initial decision on the contested health and safety issues,1/
i and, perhaps, (3) reasonable assurance that offsite emergency preparedness would eventually exist.
i 1/
The Board has indicated that its partial initial decision will not be issued this month.
Memorandum and Order Regarding Schedule (July 7, 1983).
P
/ D' B307210164 830718
)
DR ADOCK 0500032
As the Motion pointed out, the first element, onsite preparedness, was resolved in LILCO'.s favor by the intervenors' default in " Phase I" of the emergency planning litigation.
Since the Motion was filed, the third element of offsite pre-paredness was removed by the Commission's'decf.sion of June 30, 1983.
Long Island Lighting Co. (Shareham Nuclear Power Sta-tion, Unit 1), CLI-83-17, 17 NRC (June 30, 1983).
The second element, consisting of all the other contest-ed health and safety issues, awaits onl'y a partial initial de-cision by the Board and a resolution of the diesel generator cracking issue.2/
Suffolk County opposes the issuance of a low-power operating license in its " Answer and Opposition to LILCO's Mo-tion for a Low Power Operating License," dated June 27, 1983.
9 The County claims that there are four reasons for denying LILCO's motion for a low-power license:
(1) a low-power license should not be granted in circumstances which raise preliminary doubts that emergency preparedness requirements for full power operation can and will be met l
in the future; 2/
LILCO's motion for a low-power license was conditionally supported by the NRC Staff in its " Response to Applicant's Mo-tion for Low-Power Operating License" of June 29, 1983.
The i
Staff's support is conditioned on an initial decision on the health and safety issues favorable to the Applicant and a fa-vorable resolution of the diesel generator contention concern-ing cracking..
=
(2) the motion is premature under
$ 50.57(c) because the County's con-tentions on diesel generators and po-tential contentions on the Teledyne Report have not been resolved; (3) LILCO fails to meet the requirements of 10 C.F.R. $$ 50.57(c) and 50.47(d) with respect to the offsite elements of onsite emergency preparedness; and (4) necessary environmental analyses, which should consider the cost and benefits of low-power operation followed by the abandonment of Shoreham, have not been performed.
Except for the diesel generator contentions (discussed below), none of these four reasons is sufficient to delay a low-power license.
Indeed, the County's opposition is essen-tially an attempt, in the manner of four variations on a theme, to reopen questions which have been resolved by this Board or 1
by the Commission.
I.
Reasonable Assurance of the Applicant's Ability to Meet Offsite Emergency Pre-paredness Requirements Is Not Required for a Low-Power License Suffolk County cleims that a low-power operating license cannot be granted to LILCO without reasonable assurance of LILCO's ability to meet offsite eme gency preparedness require-ments.
This claim has now been uneqtivocally rejected by the Commission.
a, _. - ~ ~. -.
In its order of June 30, 1983, the Commission stated j
that "present uncertainty about whether the agency's offsite emergency preparedness requirements can be met for full-power operation would not, in and of itself, bar the grant of a-li-i cense for low-power operation under 10 C.F~.R. 5 50.57(c)."
Long Island Lighting Co. (Shoreham Nuclear Power Station, Unit 1), CLI-83-17, 17 NRC slip op. at 1 (June 30, 1983)
(" Order").
As the Commission noted, 5 50.47(d) is unqualified in its authorization of licensing boards to issue low-power li-censes in the absence of NRC or FEMA approval of an offsite emergency plan provided that other prerequisites of 5 50.47(d) are met.
Order at 3.
Thus, contrary to the County's asser-tion, the regulations as interpreted by the Commission require "no predictive finding of ' reasonable assurance' with regard to offsite emergency planning prior to low-power operation."
i Order at 3.
II.
LILCO's Motion for a Low-Power License Is Not Premature Suffolk County incorrectly asserts that LILCO's motion l
is premature because the requirements of 5 50.57(c) cannot be
(
met now or in the immediate future.
The County bases its argu-ment of prematurity on its speculation that the Board is,_ _
unlikely to issue its initial decision in the immediate future because it may reopen the record to litigate two additional matters, namely (1) the Final Report of the Independent Design Review for Shoreham conducted by Teledyne Engineering Services and (2) the newly admitted emergency diesel generator conten-tions.
In addition, the County claims that the Director cf Nu-clear Reactor Regulation has not made the findings specified in S 50.57(a) and, citing the Teledyne Report and the diesel gen-erator contentions, suggests that the Director may not be in a position to make such findings for some time.
The County's speculation that the Board will not issue its decision on the contested health and safety issues in the near future is without merit.
The record has been reopened for the issue of diesel generator cracking, but LILCO has moved for summary disposition and, if summary disposition is not granted, a hearing will begin promptly.
As far as the Teledyne Report goes, the record has not been reopened, and preliminary indica-tions are that a reopening will not be warranted.
A.
Teledyne Report Rather than raise issues appropriate for resolution through litigation, the Executive Summary of the Final Teledyne i
Report confirms that the LILCO Quality Assurance Program meets :
NRC requirements.
The Executive Summary was issued on June 30, 1983, and submitted to this Board on July 5, 1983.
In the con-i clusions of the report, Teledyne states:
In the area of Quality Assurance the TES Reviewers in their summary Trip Report indicate that the LILCO QA Program as ap-plied to construction activity on the LPCS System at Shoreham demonstrates:
management awareness and participation, a
high level of proficiency and efficiency in the Quality Assurance organization, and exceeds the minimum in application and performance of the Quality Assurance Program requirements.
Based on the results of our Indepen-dent Design Review it is TES' opinion that the commitments of the FSAR with re-spect to Design and Quality Assurance have been complied with by LILCO and SWEC for the Shoreham Nuclear Power Station.
Teledyne Executive Summary at 27-28.
Given this favorable con-clusion, it does not appear likely that the full report will raise significant controverted issues that would prompt the Board to reopen the record.
See Vermont Yankee Nuclear Power Corp. (Vermont Yankee Nuclear Power Station), ALAB-138, 6 AEC l
520, 523 (1973).
B.
Diesel Generators l
l l
The County also asserts that the recently admitted die-sel generator contentions on vibration and cracking of the cyl-inder heads must be resolved before a low-power license can be _ _ _ _ _
issued.
The Board did, in its " Memorandum and Order Ruling on Suffolk County's Motion to Admit New Contentions," dated June 22, 1983, state that the cylinder head cracking issue might delay issuance of a low-power license, but only if LILCO could not establish the lack of significance of the cylinder head cracking issue by means of summary procedures.
The Board did not require resolution of the vibration issue prior to fuel load and low power testimony.
LILCO filed a " Motion for Partial Summary Disposition of j
SC's Diesel Generator Contention" on July 7, 1983.
In that Mo-tion LILCO demonstrates, through its statement of material facts and affidavits attached to the motion, as well as the af-fidavit attached to "LILCO's opposition to Suffolk County's Mo-tion to Add an Emergency Diesel Generator Contention" (May 16, 1983) and the all-day on-the-record conference of the parties (June 10, 1983, Tr. 21,179-438), that there is no issue of ma-terial fact to be heard and that summary disposition should be granted under 10 C.F.R. 5 2.749.
Briefly, LILCO's Motion for Summary Disposition shows that there is adequate assurance that the diesel generators will perform their intended functions safely and reliably prior to the replacement of the original diesel generator heads and that the improved cylinder heads will not crack.
Accordingly, -_.
the new diesel generator contention does not appear to present a bar to a low-power license.
If a hearing is necessary on low-power testing aspects of the cracking issue, it is to com-mence the week of August 22, 1983.3/ There is every reason to expect a prompt resolution of the issue.
In short, LILCO's motion for a low-power license is not premature.
The facts that have been contested at length in this proceeding are ripe for resolution, the generator conten-tions are scheduled for prompt resolution one way or another, and there is no reason to expect that the Teledyne Report will provide a cause for reopening the record.
1 III.
LILCO Has Met the Requirements of 10 C.F.R.
SS 50.57(c) and 50.47(d) with Respect to Onsite Emergency Preparedness The County points to its "Suffolk County Motion for Leave to File Contentions Regarding Onsite Emergency Prepared-ness" as a bar to the grant of a low-power testing license to Shoreham.
As discussed in "LILCO's Answer Opposing the Suffolk County Motion for Leave to File Contentions Regarding Onsite Emergency Preparedness" (July 8, 1983),4/ which is attached to 3/
Memorandum and Order Regarding Schedule at 2 (July 7, 1983).
4/
At the prehearing conference of July 13, 1983, the emer-gency planning Board gave Suffolk County leave to reply to LILCO's July 8 Answer..
this Reply, there are five reasons why the County's new onsite contentions should not be admitted and, therefore, five reasons why the County's proposed onsite contentions are not an obsta-cle to the issuance of a low-power testing license:
(1) The new contentions all concern the state of offsite preparedness, not onsite, and the Commission has ruled that a finding on offsite prepared-ness is not necessary to the grant of a low-power license.
(2) The County has been prohibited from litigating onsite preparedness issues as a sanction for improper behavior.
(3) The new contentions are untimely by several months.
(4) The reason for the new onsite conten-tions, namely the County's categori-cal refusal to participate in emer-gency planning, is a challenge to the NRC regulations, because the County has decided to oppose emergency plan-ning no matter whether NRC regula-tions can be met or not.
(5) Individually most of the new onsite l
contentions are inadmissible because they lack specificity or basis.
Some of them could have been litigated in Phase I or are the subject of Phase I settlement agreements.
l Of particular significance to the question of the issu-ance of a low-power testing license is the fact that the Coun-ty's new onsite contentions do not really concern LILCO's onsite plan at all; rather they call for findings on the state of offsite emergency preparedness.5/
As the Commission has 5/
In Diablo Canyon the Appeal Board pointed out that its re-view for purposes of low-power testing was based solely on an l
(footnote continued) l l
i
I ruled, 10 C.F.R. S 50.47(d) " requires no predictive finding of i
' reasonable assurance' with regard to offsite emergency plan-ning prior to low-power operation and none was intended by im-plication or otherwise."
Long Island Lighting Co. (Shoreham Nuclear Power Station, Unit 1), CLI-83-17, 17 NRC slip op.
at 3 (June 30, 1983).
Thus, when they are viewed in their true light as offsite contentions, and for all the other reasons in LILCO's July 8 Answer, the County's. proposed contentions are not an obstacle to the grant of a low-power license.
IV.
The Environmental Analyses Prercquisite to the Issuance of a Low-Power License Have Already Been Performed The County makes two attempts to raise, as a bar to the issuance of a low-power license, the NRC's requirement for an environmental impact assessment of a power reactor.
First, the County claims that NRC regulations require that a separate en-vironmental impact statement (EIS) or environmental impact ap-praisal (EIA) be prepared prior to the issuance of a low-power (footnote continued) assessment of the applicant's emergency plan against the pertinent standards of 10 C.F.R.
S 50.47(b) and 10 C.F.R. Part 50, Appendix E.
Pacific Gas & Electric Co. (Diablo Canyon Nu-clear Power Plant, Units 1 and 2), ALAB-728, 17 NRC slip op. at 15-16 (May 18, 1983).
i. _ _.
license.
The County argues that the Appeal Board's decision in Pacific Gas & Electric Co. (Diablo Canyon Nuclear Power Plant, Units 1 and 2), ALAB-728, 17 NRC (May 18, 1983), which held that a separate EIS or EIA was not required by NRC regulations
~
for the issuance of a low-power license, is distinguishable.
In the alternative, the County suggests that the issuance of a low-power license for Shoreham presents significant new circum-stances which require a supplemental EIS.
The County's theories are not supported by the statutes, regulations or case law.
A.
Diablo Canyon The Appeal Board's decision in Diablo Canyon is control-ling here.
In Diablo Canyon, as here, low-power testing was planned "under the authorization of a separate fuel loading and low-power testing license,"
Diablo Canyon, ALAB-728, slip op.
at 23, and under the cloud of a contested offsite emergency planning issue.
The Diablo Canyon intervenors claimed, as Suffolk County does, that NRC regulations require an EIS or an EIA prior to issuance of a low-power license and further claimed that such an environmental analysis was " crucial be-cause the existing EIS for Diablo Canyon does not address the costs and benefits of low power testing."
Diablo Canyon, slip,
r-
op. at 22.
The Appeal Board rejected both of these arguments and expressly stated that "the existence of a final EIS for Diablo Canyon presents circumstances that obviate the need for the agency's preparation of either an EIS or an EIA aimed at low power testing."
Diablo Canyon, ALAB-728, slip op. at 23.
The Appeal Board noted that:
Low power testing is a normal, necessary and expected step in the life of every nuclear plant.
This is true whether such testing is planned under the authorization of a separate fuel loading and low power testing license, as in the case of Diablo Canyon, or scheduled as the first step toward operation under the au-thority of a full power license.
Low power testing, unlike full power operation, is not intended to produce electrical power, and it is not an alternative to full power operation.
The brief period of low power testing does not involve any environmental impacts different from those already evaluated in the EIS for full term, full power operation.
Diablo Canyon, ALAB-728, slip op. at 23-24.
Clearly the Appeal Board in Diablo Canyon considered 4
precisely the issues raised by Suffolk County here:
the costs and benefits of low-power testing and whether NRC regulations require an EIS or EIA prior to the issuance of a low-power li-cense.
The Appeal Board concluded that a separate EIS for low-power is not required, because the environmental impacts arising from a low-power license are not different from those addressed in the EIS for full-term, full-power operation.
Contrary to the County's claim, the Diablo Canyon deci-sion is not distinguishable from the Shoreham case.
All that Suffolk County says to support its claim ie that Shoreham pres-ents a special circumstance in which it is " highly questionable that a full power operating license ever can issue."
County's opposition at 27.
This argument is only one more at-tempt to assert that the County's refusal to do emergency plan-ning must call a halt to this proceeding.
This argument has been made before,p/ and rejected, and now it comes again dressed in the mantle of NEPA.
It comes under a new legal the-ory, but the basic claim is identical to what the County has argued unsuccessfully before.
In fact, the County's noncooperation does not materially distinguish this case from Diablo Canyon.
As the Commission i
p/
The County has argued repeatedly that the NRC emergency planning regulations cannot be met without its cooperation.
It argued this first in its Motion to Terminate of February 23, 1983.
It argued it again in its Motion for Commission Ruling
(
on LILCO's " Utility Plan" for Emergency Preparedness of June 7 and its Motion for Immediate Commission Decision Rejecting LILCO " Transition Plan" of June 13.
It argued it in its Motion to Defer Commission Action and For Commission to Hear Views of the Parties before Deciding Certified Question Regarding Low Power License for Shoreham on June 29.
It argued it in its Suffolk County Motion for Leave to File Contentions Regarding Onsite Emergency Preparedness of June 27.
It argued it again in the draft contentions it submitted to the Board on July 7, many of which merely assert that the County will stand in the doorway and refuse assistance to anyone attempting emergency planning.
noted in its Order of June 30, in any low-power proceeding it is always possible that the applicant will not ultimately re-ceive an operating license.
But the Commission stated that the emergency planning issues in this case, while difficult, do not appear to be categorically unresolvable.
Order at 4-5.
In short, the fact that Suffolk County is better able than most intervenors to place obstacles in the way of the ap-plicant's cause does not suspend NRC case law for this particu-lar proceeding.
The likelihood of success on the merits 2/ is simply not relevant to the NEPA analysis.
B.
Economic Imoacts Instead of Environmental Ones In its opposition to LILCO's Motion for a Low-Power Li-cense, Suffolk County attempts to delay consideration of LILCO's motion by arguing that, even if an FEIS for full-power operation is generally sufficient for low-power operation, "significant new information regarding the balance of environ-mental costs and benefits requires issuance of a supplemental 2/
It is telling that Suffolk County does not base its claim of ultimate success in blocking Shoreham's operation on evi-dence; the County has 1.ot yet presented its case on emergency planning or submitted its witnesses for cross-examination.
All it has done is refuse to cooperate with emergency planning and then assert that this noncooperation, plus a limited number of j
alleged " local conditions," raises serious legal and practical obstacles.
\\.- -
EIS."
Opposition at 25 (emphasis added).
There are two reasons why this "new information" does not require a new NEPA analysis.
The first is that it has to do with purely economic impacts, not environmental ones.
The second is that it is speculation; all the County is saying is that it has altered the likelihood of something that was always possible -- the de-nial of a full-power license.g/
The County's "significant new information" does not re-late to environmental harm, but to economic harm.
The County argues that, because it has elected to oppose the operating li-cense, and because the emergency planning regulations give it an unique opportunity to do so, the economic benefits of full-power operation are unlikely to materialize.
This economic information cannot serve as the basis for requiring a supplemental EIS.
The National Environmental Poli-cy Act was designed to inject environmental considerations into agencies' decisionmaking processes.
As the Supreme Court noted g/
The County has also failed to articulate a coherent theory as to why NEPA requires an analysis of a federal agency's po-tential decision not to do what it originally proposed.
There is certainly no federal proposal to issue a low-power license and then shut the reactor down.
So the County has suggested that low-power operation followed by shutdown needs to be ana-lyzed as an " alternative" to full-power operation.
See Coun-ty's Opposition at 28.
But the Appeal Board in Diablo Canyon said unequivocally that a low-power license is not an alterna-tive to a full-power license.
ALAB-728, slip op. at 24.
in its recent decision in Baltimore Gas & Electric Co. v. NRDC, U.S.
51 U.S.L.W.
4678 (June 6, 1983), NEPA has two purposes.
First, it obliges an. agency to consider the signifi-cant environmental impacts of its proposed action.
Second, it ensures "that the agency will inform the public that it has in-deed considered environmental concerns in its decisionmaking process."
51 U.S.L.W.
at 4680 (emphasis added).
In another decision in its just completed term, the Court elaborated on the considerations NEPA requires.
In Metropolitan Edison Co. v.
People Against Nuclear Energy, U.S.
51 U.S.L.W.
4371 (April 19, 1983), the Court stated:
4 The theme of S 102 [of NEPA) is sounded by the adjective " environmental":
NEPA does not re-quire the agency to assess every impact or ef-fect of its proposed action, but only the im-pact or effect on the environment.
i 51 U.S.L.W.
at 4373 (emphasis in original).
Thus, the Court has made clear that it is the environmental consequences of an action that are of concern under NEPA.9/
9/
Cf. the Memorandum and Order of January 27, 1978, in this proceeding, in which the Board refused to admit a NEPA conten-tion that LILCO's failure to project accurately the cost of Shoreham would unduly increase electric rates, violating NEPA 5 101, 42 U.S.C.A.
S 4331(b)(5).
Memorandum and Order at 20-21 (January 27, 1978).
The Board pointed out that it had no ju-risdiction over LILCO's rates and that the contention's concern with " undue increases in consumer electricity rates" was not appropriately raised in this proceeding.
Id. 21. - -
In this proceeding, the environmental consequences of the Shoreham facility have been exhaustively studied and de-tailed in the FEIS.
The FEIS considers environmental effects related to construction activities as well as full-power operation.
Since low-power testing involves the same environ-mental impacts as full-power operation, only to a lesser de-gree, the NEPA requirements of consideration and disclosure have been fulfilled.
Diablo Canyon, ALAB-728, slip op. at 23-24.
An EIS dealing with the environmental consequences of low-power testing would lead only to needless duplication.
Suffolk County has not disputed that the environmental consequences of low-power operation have been considered.
Rather, Suffolk County argues that the economic benefits of the project may no longer be present, since the possibility exists that a full-power operating license will not be issued.10/
Thus, Suffolk County has attempted to convert the National Environmental Policy Act into the National Economic Policy Act.11/
10/
Suffolk County's reliance on 40 C.F.R.
$ 1502.9(c)(1)(ii) j of the CEQ guidelines is without merit, since that subsection specifically refers to new circumstances or information rele-vant to " environmental" concerns.
As is discussed above, the County has alleged no changes in environmental conditions.
11/
See Sierra Club v.
Sigler, 532 F. Supp. 1222, 1238 (S.D.
Tex. 1982), in which the court noted that non-environmental economic benefits are tangential to the concerns expressed in l
(footnote continued) l !
Suffolk County's argument, if accepted, would lead to endless reassessments of a project, whenever the cost projec-tions changed, under the guise of amending an existing EIS.
It fs not difficult to imagine a myriad of changing factors; including plant costs, need for power, e t'c., that could be trooped out to show that the benefit side of an EIS analysis was overstated.
This expansion of a judicially created cost-benefit requirement (see Calvert Cliffs' Coordinating Committee
- v. AEC, 449 F.2d 1109 (1971)) was never contemplated by Con-gress when it enacted NEPA and should not be grafted onto the Act now.
In addition, the County's suggested cost-benefit analy-sis is more complex than the County recognizes in its opposi-tion.
First, the County suggests that a decision declining to (footnote continued)
NEPA.
Suffolk County's reliance on Essex County Preservation Ass'n v. Campbell, 536 F.2d 956 (1st Cir. 1976) and Warm Springs Dam Task Force v. Gribble, 621 F.2d 1017 (9th Cir.
i 1980), to support its contention that a supplemental EIS is required is misplaced.
Both cases involved potential changes in encironmental effects.
In Essex County the moratorium on the expansion of I-95 south of Route 128 could have affected the alternatives to expanding the highway segment in question, perhaps requiring a smaller expansion with corresponding lower environmental effects.
In Wapm Springs, the changed circum-stances involved discovery of a potentially more severe fault line near a dam.
After revieving the facts, the court conclud-ed that a supplemental EIS wan not required.
n !
)
grant a low-power license is without cost even if full-power operation is eventually achieved.
That suggestion is plainly false.
In fact, deferral of fuel load and testing until the grant of a full-power license would result in substantial ~ costs associated with the delay in the commencement of commercial operation.
Second, the County asserts that, if the plant is abandoned after low-power operation, the loss of the benefit derived from power generation heavily tips the balance of the cost-benefit scales.
The County fails to recognize that the environmental costs on the other side of the balance -- the costs of decommissioning and disposing of irradiated fuel --
are also substantially less with low-power testing.
The bal-ance of the benefit of low-power testing, even without eventual power generation, and the environmental costs of low-power operation is more equally weighted than the County suggests.
The cost-benefit balance of a low-power operating license does not create significant new circumstances which would require a NEPA analysis.
Diablo Canyon, ALAB-728, slip op. at 22-24.
Moreover, the economic circumstances raised by the Coun-ty are tenuous at best.
The sole foundation of the County's l
argument is a possibility that a full-power operating license will not be granted and that power will not be generated.
As is true in every low-power license proceeding, there is the i I i
possibility that a full-power license may not issue; here the County believes it is in a unique position to bring that result about.
But again, the Commission does not agree that an ac-ceptable utility plan is an impossibility, Long Island Lighting Co. (Shoreham Nuclear Power Station, Unit 1), CLI-83-13, 17 NRC (May 12, 1983), and it has said that the difficult emergen-cy planning issues here do not appear to be categorically unresolvable.
Long Island Lighting Co. (Shoreham Nuclear Power Station, Unit 1), CLI-83-17, 17 NRC slip op. at 4 (June i
30, 1983).
The County's assertion that it will succeed in blocking an operating license does not therefore rise to the level of a new circumstance calling for a whole new NEPA analy-sis.
V.
Conclusion Suffolk County argues once again that its own commitment to prevent radiological emergency preparedness for Long Island, and thus to prevent the operation of Shoreham, changes the cal-culus of this operating license proceeding in such a way as to preclude the issuance of a license -- this time a low-power li-cense.
For the reasons stated above, this argument is wrong.
1 The fact is that the record has closed on all the issues that l
need to be resolved under NRC regulations before a low-power i
l i
' l l
license is issued, or soon will be closed, and nothing Suffolk County says changes that.
Respectfully submitted, l
LONG ISLAND LIGHTING COMPANY By z Vf Taylor Reveley, III ames N. Christman Jessine A. Monaghan Hunton & Williams P.O.
Box 1535 707 East Main Street Richmond, VA 23212 DATED:
July 18, 1983 l
i i
i e
4 LILCO, July 18, 1983 CERTIFICATE OF SERVICE In the Matter of LONG ISLAND LIGHTING COMPANY (Shoreham Nuclear Power Station, Unit 1)
Docket No. 50-322 (OL)
I hereby certify that copies of LILCO's Reply to the An-swer and Opposition of Suffolk County to LILCO's Motion For a Low-Power Operating License were served this date upon the fol-lowing by first-class mail, postage prepaid, or (as indicated by one asterisk) by hand' or (as indicated by two asterisks) by Federal Express.
Lawrence Brenner, Esq.*
Secretary of the Commission Administrative Judge U.S.
Nuclear Regulatory Atomic Safety and Licensing Commission Board Washington, D.C.
20555 U.S. Nuclear Regulatory Commission Atomic Safety and Licensing Fourth Floor Appeal Board Panel East-West Towers (North Tower)
U.S.
Nuclear Regulatory 4350 East-West Highway Commission Bethesda, MD 20814 Washington, D.C.
20555 Dr. James H.
Carpenter
- Atomic Safety and Licensing Administrative Judge Board Panel Atomic Safety and Licensing U.S.
Nuclear Regulatory Board Commiasion U.S. Nuclear Regulatory Washington, D.C.
20555 Commission Fourth Floor Bernard M. Bordenick, Esq.*
East-West Tower, (North Tower)
David A.
Repka, Esq.
4350 East-West Highway Edwin J.
Reis, Esq.
Bethesda, MD 20814 U.S.
Nuclear Regulatory Commission Dr. Peter A.
Morris
- 7735 Old Georgetown Road Administrative Judge (to mailroom)
Atomic Safety and Licensing Bethesda, MD 20814 Board U.S.
Nuclear Regulatory Commission Fourth Floor East-West Tower, (North Tower) 4350 East-West Highway Bethesda, MD 20814
, Herbert H. Brown, Esq.*
James B. Dougherty, Esq.*
Lawrence Coe Lanpher, Esq.
3045 Forter Street Christopher McMurray, Esq.
Washington, D.C.
20008 Kirkpatrick, Lockhart, Hill, Christopher & Phillips Stephen B.
- Latham, Esq.**
8th Floor, 1900 M Street, N.W.
Twomey, Latham & Shea Washington, D.C.
20036 33 West Second Street P.O.
Box 398 David J. Gilmartin, Esq.
Riverhead, New York 11901 Attn:
Patricia A. Dempsey, Esq.
County Attorney Stewart M.
Glass, Esq.
Suffolk County Department of Regional Counsel Law Federal Emergency Management Veterans Memorial Highway Agency Hauppauge, New York 11787 26 Federal Plaza, Room 1349 New York, New York 10278 Mr. Marc W. Goldsmith Energy Research Group Ralph Shapiro, Esq.**
4001 Totten Pond Road Cammer and Shapiro, P.C.
Waltham, Massachusetts 02154 9 East 40th Street New York, New York 11901 Mr. Jay Dunkleberger New York State Energy Office Howard L.
Blau Agency Building 2 217 Newbridge Road Empire State Plaza Hicksville, New York 11801 Albany, New York 12223 Jonathan D.
Feinberg, Esq.
MHB Technical Associates New York State 1723 Hamilton Avenue Department of Public Service Suite K Three Empire State Plaza San Jose, California 95125 Albany, New York 12223 Daniel F.
Brown, Esq.
Ms. Nora Bredes Attorney Executive Coordinator Atomic Safety and Licensing Shoreham Opponents' Coalition Board Panel 195 East Main Street U.S.
Nuclear Regulatory Smithtown, New York 11787 Commission Washington, D.C.
20555
[' fames N.
Christman l
Hunton & Williams P.O.
Box 1535 707 East Main Street Richmond, Virginia 23212 DATED:
July 18, 1983
ATTACHMEET
'v LILCO, July 8, 1982
(
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of
)
)
LONG ISLAND LIGHTING COMPANY
)
Docket No. 50-322 (OL)
)
Emergency Planning (Shoreham Nuclear Power Station, )
Unit 1)
)
LILCO'S ANSWER OPPOSING THE SUFFOLK COUNTY MOTION FOR LEAVE TO FILE CONTENTIONS REGARDING ONSITE EMERGENCY PREPAREDNESS On June 27, 1983, intervenor Suffolk County filed a set of contentions on (allegedly) onsite emergency preparedness, along with a "Suffolk County Motion for Leave to File Conten-tions Regarding Onsite Emergency Preparedness" (hereinafter
" County Motion.").
The purpose of the motion is to place an additional obstacle in the way of a low-power testing license for the Shoreham Station.1/
A motion was necessary to submit these new onsite con-tentions because the County voluntarily gave up its right to 1/
LILCO applied for a low-power license on June 8, 1983.
The NRC has said that before it issues a low-power license, it will review certain "offsite elements of the applicant's emer-gency plan."
47 Fed. Reg. 30,233, 30,234 col. 1 (July 13, 1982).
The County therefore characterizes its contentions as involving "offsite elements" of LILCO's onsite radiological emergency plan for Shoreham.
County Motion 1.
s c;= -
t' e
- (
litigate onsite preparedness issues when it refused to go forward with litigation of such issues last November.
Accord-ingly, t'he Licensing Board dismissed with prejudice the Coun-ty's " Phase I" emergency planning contentions.
Transcript of.
Hearing in Hauppauge, New York, Nov. 23, 1982, Tr. 14,747-48; Memorandum and Order Confirming Ruling on Sanctions for Inter-venors' Refusal to Comply with Order to Participate in Prehearing Examinations (Dec. 22, 1982).
The County's rationale for reopening the onsite pre-paredness record at this late stage is (though not in these words) a plea of " changed circumstances" or "new information."
The County argues that the Phase I litigation in 1982 was based upon the " erroneous fundamental assumption" that Suffolk County would adopt and implement an offsite emergency plan.
County Motion 3.
The County says that "[i]t was not until February 17, 1983, after public hearings held in January, that the Coun-ty Legislature adopted Resolution No. 111-1983 which disap-proved the draft County offsite plan and determined that Suffolk County would not adopt or implement any offsite emer-gency plan."
County Motion 4.
Thus, "only in February 1983 did it become clear that one of the fundamental assumptions of the Phase I litigation -- that the County would participate in overall emergency preparedness for the Shoreham plant -- was no longer valid."
County Motion 4-5.
$r Notwithstanding this explanation, there are five good reasons why the County's new onsite contentions should not be admitted:
I.
The new contentions are about offsite preparedness, not onsite.
Consequently they do not have to be resolved prior to issuance of a low-power license but in-stead can be litigated (if they have the requisite basis, specificity, etc. and could not have been raised in Phase I) along with the County's other Phase II contentions.
II.
The County treats its request to file new contentions as merely a motion to reopen the record because of new information (namely the County's decision to resist emergency preparedness).
This approach ignores the fact that the County has been prohibited from litigating onsite issues as a sanction for improper behavior.
III. Even if this were just an ordinary motion to reopen the record, it would fail be-cause it is untimely.
The "new informa-tion" was in the County's sole control, and it was known to the County no later than February.
The County's request to submit contentions could have been filed in February or April but was in fact not filed until it appeared in June that some new tactic would be required to delay the issuance of a low-power license.
IV.
The new circumstances relied on by the County, namely its categorical refusal to participate in emergency planning, is nothing less than a challenge to NRC reg-ulations.
V.
Individually most of the new onsite con-tentions are inadmissible anyway because of technical deficiencies such as lack of specificity or basis.
Some of them could I
have been litigated in Phase I.
Some of them are covered by settlement agreements signed by the County itself.
'c
- For all these reasons, the Board should deny the County Motion.
We will elaborate below.
I.
The new onsite contentions call for find-ings on the state of offsite emergency preparedness, not on "offsite elements" of the applicant's onsite plan The first objection to the County's new onsite conten-tions is that they are not really about LILCO's onsite plan at all.
This is not so much an objection to their admissibility (since they may still be admissible as Phase II contentions) as an objection to their being treated as "offsite elements of the applicant's emergency plan" -- that is, as low-power issues.
The Federal Register preamble to the lcw-power emergency j(f planning regulation, 10 C.F.R. 5 50.47(d), nays that before issuing a low-power license the NRC will review the offsite el-ements of the applicant's emergency plan cc.eered by 10 C.F.R. 5 50.47(b)(3), (5), (6), (8), (9), (12), :.nd (15).
The key to the phrase "offsite elements of the applicant's emergency plan" is the word " applicant's":
only a review of the applicant's onsite plan is contemplated.
This is consistent with the regu-lation itself, which says that "no NR. or FEMA review, find-ings, or determinations concerning ti-; state of offsite emer-gency preparedness or the adequacy r>J and capability to imple-ment State and local offsite en.ergency plans are required prior to issuance" of a low-power lice:me;.2/
10 C.F.R. 5 50.47(d) 2/
A week ago the NRC ruled that the regulation means just what it says.
Long Island I,.tghting Co. (Shoreham Nuclear Power Station, Unit 1), CLI-83-17, 17 NRC (June 30, 1983).
fe
. (1983), 47 Fed. Reg. 30,236 col. 1 (July 13, 1982).
What this means, generally speaking, is that the licens-ee must have its own onsite arrangements complete and also have in place the communication links between the power plant and the outside world.
As the San Onofre low-power decision 3/ put it, "[t]he most appropriate criteria for testing the adequacy of emergency planning for low-power operations is whether the on-site plan meets relevant full-power requirements (forgiving any deficiencies that are insignificant to low power), plus the ability to communicate with off-site authorities."
Southern California Edison Co. (San Onofre Nuclear Generating Station, Units 2 and 3), LBP-82-3, 15 NRC 61, 196 (Jan. 11, 1982).
All of the County's new onsite contentions share the deficiency that they are not really about elements of LILCO's onsite plan at all,4/ and for this reason alone the County Motion should be denied.
Denying the County Motion would not by itself prevent the County from litigating its new onsite contentions.
All it l
would do would be to prevent the County from interposing them 3/
The decision predated the final regulation, but the San onofre Board said the approach taken in the then-proposed regu-l lation, 46 Fed. Reg. 61,132 (Dec. 10, 1981), was consistent with the approach the Board would have adopted in any case.
Southern California Edison Co. (San Onofre Nuclear Generating Station, Units 2 and 3), LBP-82-3, 15 NRC 61, 194-95 (1982).
4/
This deficiency is indicated, in the detailed objections attached to this answer, by the phrase "not a low-power issue."
l l
l
- e
. as an obstacle to a low-power, as opposed to a full-power, license.
This is as it should be.
Only last week the Commis-sion ru ed that 10 C.F.R.
$ 50.47(d) " requires no predictive finding of ' reasonable assurance' with regard to offsite emer-gency planning prior to low-power operation and none was in-tended by implication or otherwise."
Long Island Lighting Co.
(Shoreham Nuclear Power Station, Unit 1), CLI-83-17, 17 NRC slip op. 3 (June 30, 1983).
The Commission observed:
We believe the better procedure is to re-serve full-power issues, like offsite emergency planning, for the full-power authorization decision.
Id.,
slip op. 4.
As the attachment to this answer shows, the County's new onsite contentions are full-power issues, and they should not be treated otherwise.
II.
The real issue is not whether the new on-site contentions could have been raised last November, but whether a party that has defied a Board order should be able to es-cape the sanctions imposed on it by creat-ing changed circumstances The second objection to the County Motion is that it does not address the sanctions that were imposed against the County last November.
The County treats its motion to file new contentions as an ordinary request to reopen the record because of newly discovered evidence.
(The newly discovered -- that is, newly created -- evidence is simply the County's own refus-al to participate in emergency planning.)
But the issue is
',e
. (
not, as the County would have it, whether the new contentions 4
could have been raised earlier (if it were, the County Motion would still fail, as shown in part III below); it is rather whether this particular party should be allowed to raise them at all.
In fact this is not the usual request to reopen the i
record.
It is rather a request to revoke sanctions imposed on the County for defiance of a Licersing Board order.
The County gave up its right to litigate contentions about LILCO's onsite plan by refusing to comply with the Licensing Board's choice of procedure.
Accordingly, the issue here is not principally one of the untimeliness of the County's new contentions, but wheth-er it should be allowed to use " changed circumstances" created by itself to evade sanctions that were imposed upon it lawfully and for good reason.
A brief review of why the sanctions were imposed in the first place will show why those sanctions should be made to stick.
The Licensing Board ordered evidence on onsite emergen-cy preparedness to be taken in the first instance by deposi-tions.
Full cross-examination was to take place, just as in a public hearing, and the public was free to attend, just as in a public hearing.
The only difference was that the Board was to read the transcripts of the depositions rather than be present at them.
The Board then planned to hold a conventional public hearing to explore parts of the deposition record that still i
l,
. seemed to need more elaboration.
At this hearing the parties were again to cross-examine witnesses, to the extent they had not been'able to do so during the depositions, and the Board would have been present to ask questions itself and observe witnesses' demeanor.
See Memorandum and Order Ruling on Li-censing Board Authority to Direct that Initial Examination of the Pre-Filed Testimony be Conducted by Means of Prehearing Ex-aminations (Nov. 19, 1982).
The judges' remarks about the proposed procedure are illuminating:
JUDGE CARPENTER:
I would just like to make a couple of remarks to provide some perspective on what the Board's hopes are.
If we look at the administra-tive proceedings like this, one would
(
like to see the record which will un-doubtedly be reviewed be both comprehen-sive and incisive, and I think you might tend to agree with me that those are ba-sically incompatible in a simple way, so that it is a difficult thing to produce such a record which is both comprehensive and incisive.
And the reason the Board feels this initial examination to develop a compre-hensive record is very useful and there is unavoidably much detail that must be presented.
Then the Board needs to look at the detail, look at the comprehensive record, and then try to bring to focus all parties on the critical elements that have come from that detailed examination.
So we can proceed to examine with per-spective that has been developed from the detail.
So all we were suggesting is a recog-nition of the need to do two different kinds of things -- to get a comprehensive i
9 record with all of the technical facts 4
put on the table, and then to examine those facts in an incisive way.
And I am trying to be responsive, Mr. Brown, to your request to understand the Board's thinking, and I am trying to express it just as simply as I can.
1 Tr. 14,721-22.
JUDGE MORRIS:
I would just like to add one comment.
The Board recognizes that the subject I
of emergency planning is of great inter-est up here in Suffolk County on Long Is-land, and we want to be sure that we have time to reflect on the details that are developed in the proceeding, and that 4
means hearing the parties, having time to examine the evidence, at least, prior to conducting the final hearing process in public to ask our questions, and to allow for further questioning by the parties.
Tr. 14,722.
The County and other intervenors categorically refused to participate in this procedure, calling it " unlawful."
Tr.
14,725, 14,726.
The Board offered to facilitate appellate re-view of its proposed procedure:
JUDGE BRENNER:
Did you see our re-marks on the transcript of Friday as to the appellate procedures that might be invoked if we advocate that position, that that te a normal course of appel-late procedure when a trial court rules one way and a party rules another, you j
sometimes have to wait until the end of the proceeding for review.
However, in this instance, we would be willing to assist the County in facilitating a rapid review, so long as i
it wasn't otherwise in default of its obligations before us while seeking that s_
I 1
. review.
However, we have never gotten any indication from the County as to any proper appellate procedures that it wished to follow.
Tr. 14,726-27.
We believe we have the authority to implement this quite clearly.
- However, trial boards have been wrong before and j
we would invite that kind of accelerated procedure to assure that the proceeding isn't diverted on the side trail that detracts from the substance, the very antithesis of the comprehensiveness and incisiveness that we are seeking, as Judge Carpenter just said.
Tr. 14,728-29.
Four things about this incident are worth noting here:
l.
The procedure ordered by the Board was so eminently reasonable it is hard to imag-ine why anyone would object.
It is
{(g designed to focus the Board's attention on the significant issues and to give the parties two chances, rather than the usual one, to cross-examine the witness-es.
Since LILCO had the burden of proof, two chances to challenge its witnesses should have been a great benefit to the intervenors, especially since they presented no written testimony of their j
own on some of the Phase I issues, i
2.
The County never explained why it thought the Board's procedure was unlawful.5/
5/
The County did file a paper addressing the issue, but it contained "no supporting analysis and almost no explication."
Memorandum and Order Ruling on Licensing Board Authority to Di-rect that Initial Examination of the Pre-Filed Testimony be Conducted by Means of Prehearing Examinations 5 (Nov. 19, 1982); see also Memorandum and Order Confirming Ruling on Sanc-tions for Intervenors' Refusal to Comply with Order to Partici-pate in Prehearing Examinations 5 n.1 (Dec. 22, 1982).
. 3.
The County never explained why it thought it would be harmed by the Board's proce-dure.
4.
The County never asked the Commission to review the Board's procedure, despite the Board's invitation to do so.
The County, along with the other intervenors, was there-fore prohibited from contesting Phase I issues, since it had refused to do so except on its own terms.
The sanction was im-posed for the County's breach of a fundamental principle --
that litigants obey the orders of judicial bodies even if they disagree with them.p/
The same policy that justified the sanctions in the first place now just as surely justifies denying the County's g
request to ignore the sanctions:
I(
To allow intervenors to decline to follow our order, solely because they disagree with it, would be a particularly egregious abdication of our duty under 10 C.F.R. 5 2.718 to regulate the course of this proceeding.
Not only would permit-ting such actions be contrary to Commis-sion precedent, but it would also likely be repeated were sanctions not imposed for this breach so as to induce future compliance with Board orderr,.
Memorandum and Order Confirming Ruling on Sanctions for Inter-venors' Refusal to Comply with Order to Participate in Prehearing Examinations 13 (Dec. 22, 1982).
p/
See Memorandum and Order Confirming Ruling on Sanctions for Intervenors' Refusal to Comply with Order to Participate in Prehearing Examinations 13 n.5 (Dec. 22, 1982).
1
. The new onsite contentions raise issues about the feasi-bility of emergency preparedness when the County government o
will not cooperate, and there are serious issues involved.
Or-dinarily the NRC recoils at the prospect of denying any party the rignt to litigate serious issues.
But denying admissions of the County's new onsite contentions would not leave the is-sues unexamined, for two reasons.
First, upon the County's de-fault the onsite issues did not disappear; they simply fell to the NRC Staff for review.
Tr. 14,748; Memorandum and Order Confirming Ruling on Sanctions for Intervenors' Refusal to Com-ply with Order to Participate in Prehearing Examinations 18 (Dec. 22, 1982).
Second, as noted in Part I above, the issues raised in the new onsite contentions are in truth offsite is-I(
k sues, and they will be fully litigated before this Board, if they meet the usual requirements for admissible contentions and 4
could not have been raised in Phase I.
1 III.
The County's new onsite contentions are untimely l
The third objection to the new contentions is that they are untimely.
The County could have protected itself in sever-al ways from being precluded from litigating the contentions it now seeks to litigate:
1.
It could have gone forward with the Phase j
I litigation in the first place.
(It never articulated a legal basis for refusing to go forward.)
L
.. 2.
It could have appealed the Licensing Board's action immediately to the Commis-sion; the Board not only invited the County to do so several times, but offered to expedite the appeal.
3.
It could have raised new onsite conten-tions in February, when it created the
" erroneous fundamental assumption."
4.
It could have raised new contentions in April, when the Licensing Board excluded "any contention addressed to Phase I emergency planning matters."7/
The last two of these go to the timeliness of the Coun-ty's current effort to reopen the record.
Obviously Suffolk County could have moved to submit new onsite contentions in February of this year, when the County Legislature decided to oppose emergency planning.3/
Or it could have raised new l((
7/
Memorandum and Order Denying Suffolk County's Motion to Terminate the Shoreham Operating License Proceeding, LBP-83-22, 17 NRC slip op. 63 (Apr. 20, 1983).
The County alleges that its motion at this late date is prompted by the Board's
" Order Scheduling Prehearing Conference," dated June 10, 1983, in which the Board stated that it expected the parties to com-ply with limitations on the scope of contentions prescribed by LBP-83-22.
County Motion 1.
Also, there may be the implication in the County Motion that a recent revision to LILCO's onsite plan prompted the new contentions.
This could not possibly be the case, however, be-cause the revisions were minor ones designed to correct deficiencies found by NRC inspectors.
The County has made no attempt to tie its new onsite contentions to recent revisions in the onsite plan.
g/
Perhaps even earlier.
The County has said that "it is clear from the record that the County had grave concerns about the feasibility of planning for an emergency at Shoreham well in advance of 1982 and that LILCO was on notice of those con-cerns as early as 1977."
Suffolk County's Reply to LILCO's and the NRC Staff's Briefs in Opposition to Suffolk County's Motion
(
(footnote continued)
?.
. contentions in April, when the Licensing Board ruled that Phase I issues would not be permitted in Phase II of the litigation.
fnstead, the County waited two more months until June 27 to submit the new contentions, giving as a justification for this delay only that the County Motion "is prompted by the Board's ' Order Scheduling Prehearing Conference,' dated June 10, 1983, in which the Board stated that it expected the par-ties to comply" with the April 20 order mentioned above.
Coun-ty Motion 1.
It is hard to understand why a June 10 order merely reaffirming an earlier order would have prompted the County to act, especially when an order of May 12 had already said that previous orders " remain in full force and effect."
Order Directing Change of Service on Emergency Planning Submis-lg-(
sions, ASLBP No. 83-488-03-OL (May 12, 1983).
Evidently what really prompted the County's effort to reopen the onsite emergency planning record was LILCO's filing of a low-power license application on June 8.
The County's June 27 onsite contentions were part of a coordinated attack on the low-power license application, consisting of the conten-tions, a formal " Answer and Opposition" to the low-power li-cense application (also dated June 27), and a flurry of (footnote continued) to Terminate the Shoreham Operating License Proceeding and the l
County's Motion for Certification" 23 (Mar. 29, 1983).
l l
I l
._. =.
1
{((
pleadings and correspondence to the Commission on June 29 and 30 on the low-power issue resolved in CLI-83-17.
IheCountycannotclaimitwastakenbysurprisebythe low-power license application, because it was made clear to the j
County long ago that the Phase I record might become the basis i
for a finding authorizing a temporary or low-power license.9/
As the Board said at the April 14, 1982 prehearing conference:
We may be called upon to make partial findings under the proposed legislation in both authorization bills issued by Congress and also under the proposed reg-ulation of the NRC.
And unless and for that reason,* partial findings could well l
be material to some of the issues in the proceeding, and I say that in contradic-tion of the point raised by some of the findings, I believe primarily SOC's that no useful purpose would be served by lg-litigating part of the issues because
(
nothing could happen in any event until all of the issues were litigated.
That may not be the case, depending
~
on the proposed regulation and the legis-j.
lation and depending upon our findings on l
the issues.
If the gap had only been a short period of time, then from a prag-i matic, not a legal, point of view, it may l
have been useful to wait and try j
everything together.
I 9/
The Board did not decide whether the resolution of the Phase I issues would support the legal requirements for a low-power license.
Prehearing Conference Order (Phase I -- Emer-gency Planning) 2 n.1 (July 27, 1982).
It is clear, neverthe-less, that the Phase I issues were defined broadly enough to i
encompass low-power concerns.
For example, Phase I Contention EP 11 on " Communications / telephones" was to focus on "LILCO's communications with the first line of authorities, not to the general public, and on the forms of backup communications available."
Prehearing' Conference Order (Phase I -- Emergency Planning) 11 (July 27, 1982).
m t
u.
. [(
Essentially it is our view, and we also indicated this in our order, that LILCO's actions, the applicant's actions under the plan could be litigated.
That was not restricted to their actions on site.
One of the filings, and we haven't had much time to look at it, underlined the word " site."
We did not describe it that way, I don't believe.
It is licens-ee's actions under their emerge'ncy plan.
There is a distinction between some of the areas, because their actions take place offsite although they depend whol-ly, or at least primarily, upon the ap-plicant's actions; for example, the operations facility, dose monitering (sic] teams, and so on.
Tr. 745-46.
COUNSEL FOR SOC:
I would like to ask the Board, when you say you have a re-sponsibility to make these partial find-ings, are you talking about under this legislation that is being developed?
JUDGE BRENNER:
Yes.
Also under the proposed Regulations and also in terms of litigating that which can be litigated as opposed to taking hiatus for almost a year and then coming back.
Tr. 800.
The Board repeated this point at the July 20, 1982 conference:
l COUNSEL FOR SUFFOLK COUNTY:
If I may, Judge Brenner, I'm just a little mystified.
I don't believe there's any -- and maybe Mr. Black has addressed this, but I don't see a motion that is before the Board for a low-power license.
As far as we are concerned, we are not litigating that question here, un.'?ss there is one that I don't know about.
We haven't been advised of it, so I don't know why the Staff would want to pursue some hypothetical event.
t
. [(
JUDGE BRENNER:
Well, I guess I. don't know why you are mystified.
Back at the first conference of the parties, I believe, or certainly during one of the prehearing conference stages, we talked about going ahead with issues we could go ahead on, with that possibility in mind so as not to preclude by inertia the failure to make those findings.if and when such a motion is made.
Tr. 7264-65 (emphasis added).
Thus, the parties were well aware that if they wanted to raise low-power issues they should do it, to the extent possible,10/ in Phase I, and in many cases we shall find that the County's new oncite contentions could have been litigated during Phase I.
At this late stage of the proceeding, therefore, the County's having waited four and a half months to raise its own refusal to do emergency planning as an onsite issue is intoler-able.
The Shoreham plant will be physically ready to load fuel next month.
The only real issue left before the Licensing Board is whether Suffolk County's efforts to block offsite emergency preparedness make it impossible to accomplish ade-quate offsite preparedness.
All the rest is merely detail.
The County will get a full chance to be heard on both the "im-l possibility" issue and on its detailed criticisms of LILCO's l
l 10/
In response to the intervenors' complaints about dividing emergency planning into two phases, the Board invited them to specify in their contentions where necessary information was lacking because an offsite plan had not yet been developed.
Tr. 802.
i
. l(
offsite plans when it litigates its offsite contentions.
But
(
to allow it in addition to use these offsite issues to delay the low-power license would be to throw away any notion that the parties to NRC proceedings have an obligation not to delay the proceedings unduly.
IV.
The new circumstances relied on by the County are nothing less than its own challenge to NRC regulations It would be particularly inappropriate to allow the County to plead new circumstances to avoid the Board's sanc-tions discussed in Part II above when the new circumstances are nothing but the County's owa out-of-court behavior.
For equi-table reasons, if no others, a litigant should not be permitted to create out-of-court obstacles to another litigant's cause and then plead those very obstacles as reasons for regaining procedural rights he earlier abandoned.ll/
Indeed, the Licensing Board indicated, in its April 20 order, that contentions alleging the County's own refusal to participate would not be entertained:
[I]f the County seeks to have its find-ings adopted, it must litigate before us the facts which it believes support its view that it is not feasible to implement emergency preparedness actions which 11/
"He who prevents a thing from being done may not avail himself of the nonperformance which he himself has occasioned R.
H.
Stearns Co. v. United States, 291 U.S.
54, 61 (1934).
O, l
. C would meet NRC regulatory requirements in the event of a radiological emergency at the Shoreham Nuclear Power Plant.
The right of the County to litigate whether necessary emergency actions can be taken may be distinguishable from the circum-stance of a governmental litigant before us which simply refuses to take otherwise feasible actions.
LBP-83-22, 17 NRC slip op. 59 (April 20, 1982).
For example, we will not entertain con-tentions premised solely on the absence of a Suffolk County approved plan.
Id.,
slip op. 62.12/
These admonitions about what types of contentions will and will not be heard are perfectly justifiable, particularly because the County's contentions about its own refusal to par-f ticipate in emergency planning amount to nothing less than a k
challenge to the NRC's regulations.
The challenge is twofold.
First, in deciding that adequate emergency preparedness is im-possible, the County did not attempt to apply the federal stan-dards 10 C.F.R.
S 50.47 and NUREG-0654; it ignored them, apply-ing criteria of its own that have never been articulated.
So l
the County rejected either the applicability or the adequacy of the NRC regulations.
Second, the County has decided, in j
l 1
1 l
12/
In a sense, of course, all the new onsite contentions are about the County's refusal to do emergency planning; that re-fusal is, after all, the circumstance that the County says justifies its late request.
But in the detailed objections at-
{
tached to this answer we have made the " County's own doing" ob-jection only where the contention is a particularly bald state-ment of the County's unwillingness and nothing more.
l l
O.
20-essence, that a nuclear plant should not be sited on Long Island.
This is a challenge to the NRC siting regulations.13/
-i V.
The new onsite contentions are individually inadmissible for a variety of reasons Finally, apart from the reasons set out in parts I through IV above, many of the proposed new onsite contentions are inadmissible for such traditional technical reasons as lack of specificity or basis or because they could as well have been raised in Phase II.
A list of these objections is attached to this pleading.
Several of the objections are unique to the pe-culiar circumstances of this proceeding and therefore deserve some discussion here.
I 13/ Arguably the County has also challenged the NRC process for assessing emergency plans.
First, it refused to partici-pate in the Phase I hearings before the Board.
Then it held its own hearings apart from the NRC process, made its own find-ing that existing emergency plans were inadequate, and passed a resolution decreeing that no offsite plan would be implemented.
This action was based squarely on the County's own views of radiological health and safety.
Now the County attempts to raise its own Resolution No. 111-1983 and its own refusal to help with emergency planning as a reason why the NRC should deny a license.
Since the County would not be refusing to do emergency planning if it had submitted to the NRC process for l
deciding if emergency preparedness is adequate, the County's position is tantamount to refusing to recognize NRC authority over licensing decisions.
The County is participating in the NRC process, it is true, but it has announced that it will re-sort to the courts if the NRC reaches a decision not to its l
liking, and it is clear that the County is using the NRC pro-cess only as an attempt to impose its own views of emergency l
planning and radiological health and safety.
l t
O,
_21 A.
Lack of basis and specificity
.The objection that some of the new onsite contentions have "no basis" or are "not specific" are familiar ones, but a word about LILCO's view of what these requirements mean in this case may be helpful.
In particular, LILCO believes that in the circumstances of this case Suffolk County should bear an unusu-ally high burden of being specific.
1.
Basis In LILCO's view, the requirement that a contention have a " basis" is that there is a reason to believe the contention may be true.
This is a very light burden; it does not, for ex-f I
ample, require the sponsor of the contention "to detail the ev-k idence which will be offered in support of each contention."
Mississippi Powe' and Light Co. (Grand Gulf Nuclear Station, Units 1 and 2), ALAB-130, 6 AEC 423, 426 (June 19, 1983).
But it does require that the sponsor give a " reasonable explanation or plausible authority" for factual assertions.
Cleveland Electric Illuminating Co. (Perry Nuclear Power Plant, Units 1 and 2), LBP-81-24, 14 NRC 175, 184 (1961).
The sponsor needs l
to " assign reasons for his belief."
See Houston Lighting and Power Co. (Allen's Creek Nuclear Generating Station, Unit 1),
ALAB-590, 11 NRC 542, 548 (1980).
t
- /
4
. 2.
Specificity With regard to the specificity of the contentions LILCO submits that Suffolk County should have an unusually heavy bur-den.14/ The, County is the party that ought to be doing offsite emergency planning, not LILCO.
The County has argued vigor-ously that it and only it has the duty and responsibility of offsite emergency planning.
It has cited its $600,000 study of emergency planning, its public hearings on the subject, and the qualifications of its experts.
It has alleged, in short, that it has done an exhaustive study of emergency planning on Long Island.
Therefore the County ought to be in a position to be very specific about what its objections to emergency planning I
l are.
L In particular, the County should specify in every case which " evaluation criterion" of NUREG-0654 it thinks is not met.15/ Also, it is not enough for the County to merely con-tend that a particular feature of LILCO's emergency plan is not l
" adequate" or even to explain why it is not adequate; the 14/
In Phase I the Board was insistent that the County's con-tentions be " particularized."
- See, e.g.,
Prehearing Conference Order (Phase I - Emergency Planning) 16, 17 (July 27, 1982);
Supplemental Prehearing Conference Order (Phase I - Emergency Planning) 15 (Sept. 7, 1982).
15/ NUREG-0654 is universally used as guidance for assessing emergency plans, and the County should be quite familiar with l
it.
The draft emergency plan prepared by the County's consul-tants was organized along the lines set up by NUREG-0654.
L
. County should also specify in eve ry case exactly what LILCO should do to correct the problem the County sees.
And if the County 5hinksthereisnosolution, it should say so.
Among other things, this would have the beneficial effect of separating out those contentions T. hat the County thinks make emergency planning impossible, and those contentions which the County thinks merely raise problen;s that can be solved.
Requiring the County to specify what measures it thinks would be adequate would also facilitate settlement, because if the County will just say what it wants, LILCO may be able to pro-vide it.
B.
" Phase I issue"
(
Besides the objections regarding basis and specificity, a recurring objection is that the new onsite contentions could have been raised in Phase I.
Some of them actually were Phase I issues.
Some of them are covered by Phase I settlement l
agreements signed by the County itself.
The Board has made clear that these Phase I issues may no longer be litigated:
Accordingly, we will not consider any contention addressing LILCO's onsite plan l
or other matters which either were the j
subject of a previously admitted Phase I l
emergency planning contention or clearly were within the permissible scope of the Phase I emergency planning litigation.
Memorandum and Order Denying Suffolk County's Motion to 1
e* Terminate the Shoreham Operating License Proceeding, LBP-92-22, 17 NRC slip op. 64 (Apr. 20, 1983).
This is because the parties were being bound by any stipulation regarding Phase I contentions which was approved by the Board, see Stipulations ff. Tr. 14,719, as well as by our order dismissing the remaining Phase I contentions "with prej-udice" due to intervenors' intentional default in refusing to proceed with the examinations before hearing is ordered by the Board.
Id. 64-65.
The meaning of " Phase I" was explicated many times:
Therefore, Phase I emergency planning was defined to include not only onsite mat-ters, but also matters such as gaps in 1
siren coverage within 10 miles of the Shoreham plant, notification of and com-munications with offsite response organi-(
zations, arrangements and training for offsite assistance resources needed on site (e.g.,
medical and fire services),
and assessment and monitoring by LILCO of actual or potential onsite and offsite radiological releases in doses.
LBP-83-22, slip op. at 64.
The Phase I issues were those "within LILCO's responsibility to perform whether it be onsite or offsite."
Prehearing Conference of April 14, 1982, Tr. 796; see also Tr. 797-802.
They were the issues " currently capable of final resolution" even without an offsite plan.
Prehearing Conference Order (Phase I - Emergency Planning) 2 (July 27, 1982);
see also Prehearing Conference Order 7 (April 20, 1982).
+
1
- {f In particular, the Phase I issues were to cover the
(
"first channel of communication, if you will, from the utility to the governmental authorities."
Tr. 7225-26 (July 20, 1982).16/ They were to focus on LILCO's communications with the "first line" of authorities and on the forms of backup com-munications available.
Prehearing Conference Order (Phase I -
Emergency Planning) 11 (July 27, 1982).
We would like the parties to jointly examine contentions, those subject areas and determine whether they fall within the category that I am about to describe now, that is, actions by LILCO, whether it be onsite or offsite but actions by LILCO.
That would be the broad defini-tion.
This would include communications between LILCO and offsite response agen-cies, particularly the initial notification from LILCO in the event of I(
an emergency.
k.
Tr. 747 (Apr. 14, 1982) (emphasis added).
As is made clear in the detailed objections attached to this answer, many of the County's new onsite contentions could have been raised in Phase I and so are not litigable now.
VI.
Conclusion The County's new onsite contentions should not be admit-ted.
Most or all of the issues they raise are being addressed 16/ The scope of the Phase I issues encompassed the low-power issues (that is, onsite preparedness plus the offsite elements of the applicant's plan referred to at 47 Fed. Reg. 30,234 col. 1 (July 13, 1983)) plus some full-power issues such as the coverage of the sirens.
. in the Phase II litigation, and there is no reason, except to delay a low-power license, to treat them as onsite (that is, low-power) issues.
Respectfully submitted, LONG ISLAND LIGHTING COMPANY By mes N. Christman Hunton & Williams 707 East Main Street P.O. Box 1535 Richmond, VA 23212 DATED:
July 8, 1983 l
l l
l l
l l
l
4 Attechmant SPECIFIC OBJECTIONS TO INDIVIDUAL NEW ONSITE CONTENTIONS Below are set out the specific technical objections that LILCO has to Suffolk County's new onsite emergency plan-ning contentions (Appendix A to the "Suffolk County Motion for Leave to File Contentions Regarding Onsite Emergency Prepared-ness," filed June 27, 1983).
A.
A generic problem:
cumbersomeness In the first place, LILCO has the fundamental objec-tion, that the new onsite contentions are cumbersome (overlong and wordy).
Typically the County's contentions consist of a fluffy cloud of words surrounding a hard kernel of contention.
One can usually find a sentence or two that state the County's concern in a reasonably concise manner; the surrounding words tend to be background, statement of basis, and argument.
This cumbersomeness, or lack of conciseness, stems from the following problems:
1.
The contentions contain lengthy explanations In an attempt to provide proof against objections for lack of basis and specificity, the County has included a great l
deal of unnecessary information that lengthens the contentions without helping the reader.
Often this excess baggage consists L
- of quoting, rather than merely citing, the regulations the County thinks relevant.
LILCO has no objection to the County's explaining its contentions, but the explanations should be in a separate " statement of basis" or the like so as to avoid freighting the contention itself with too many words.
Asking that the contentions be kept concise is not a frivolous request.
The contentions must be referred to and cited hundreds of times over the next several months.
The me-chanics of preparing documents are made much more difficult by prolix contentions.
More important, it is hard to keep the issue in mind when it is stated in three pages rather than three sentences.
This is a very real difficulty and tends to g
make the litigation more confusing and difficult to manage.
lt 2.
The contentions are repetitive The new onsite contentions are repetitive and contain frequent cross-references to other of the new onsite conten-tions.
The redundancies could be eliminated by a thoughtful consolidation.1/
The repetitiveness apparently results from organizing the contentions along the lines of certain documents (the 1/
In Phase I, the Board in a number of instances directed the parties to consolidate and simplify their contetions.
- See, e.g.,
Prehearing Conference Order (Phase I -- Emergency Plan-ning) 9, 11, 14, 15 (July 27, 1982).
Some contentions were ruled " redundant and inadmissible."
See Supplemental Prehearing Conference Order (Phase I -- Emergency Planning) 14, 27 (September 7, 1982).
. regulations or the emergency plan) rather than along the lines of the facts that will have to be litigated.
For example, in-stead of' writing a contention about command and control and al-leging that the people doing that function will have " role con-flict" and then writing another contention.about ambulance drivers and claiming that they will suffer role conflict, when the same witnesses will testify about role conflict in all of the emergency personnel, there should simply be a contention about role conflict that has as its subparts the different per-sonnel who will allegedly experience role conflict.
3.
The contentions are not self-contained; they cannot be under-stood without resort to the off-site contentions The new onsite contentions contain numerous references to the County's offsite contentions.
Thus one cannot under-stand the new contentions, or decide whether they have the req-uisite basis and specificity, without flipping back and forth from one document to another.2/
l 2/
For example, new onsite contention A.4.a mentions "limita-l tions of the LILCO Customer Service Office resources," refer-l ring the reader to offsite contention 8.A.1 (later renumbered SC 78) for specifics, and then mentions " inadequacies of the LILCO paging systam," referring to offsite contention 8.A.3 (later SC 80).
Contention 8.A.3 in turn references offsite contention 8.A.2 for the reasons why activating pagers by com-mercial telephone is unacceptable.
l Returning to onsite contention A.4.a, the reader next finds a statement that because of the 8.A.1 and 8.A.3 reasons referenced above, there is no assurance that the Director of
(
Local Response can be notified and the EOC activated fast gw (footnote continued)
4 4.
The numbering scheme is over-complicated
'he County identifics its contentions with letters and T
numbers in numerous subparts.
This is largely a result of the County's organizing the contentions according to documents, noted above.
For example, the contentions on pages 4 and 5 of the new draft onsite contentions are somewhat awkwardly desig-nated A.4.a, A.4.b, and so on.
The contentions should instead be numbered sequentially (1, 2, and so forth), with fewer subparts and sub-subparts.
The Board ordered or suggested this type of numbering in Phase I.
Prehearing Conference Order (Phase I - Emergency Planning) 3, 14 (July 27, 1982); see also Tr. 803 (Apr. 14, 1982).
B.
The types of specific objection The observations above suggest that the new onsite con-tentions could profit from a serious rewriting.
In addition, the contentions are subject to seven types of objection:
(footnote continued) enough.
This is followed by a "See Contention D below."
Con-tention D of the new onsite contentions says that (1) Suffolk County will not allow LILCO to use the Suffolk County Probation Building as the EOC and that LILCO's substitute EOC at Brentwood has "not yet been established."
The reader is refer-enced to offsite contention 5 for details about how the Brentwood EOC has not been established.
(The cross-reference does not help since all contention 5 says is that the Brentwood EOC has not been established.)
.- C 1.
Not a low-power issue - A pure offsite issue that is not an "offsite element of the applicant's emergency plan" within the meaning of 47 Fed. Reg. 30,234 col, 1 (July 13, 1982).
2.
Not specific (vague, unparticularized) the contention is not sufficiently pre-cise about what it really means, particu-larly when one asks what type of evidence would have to be presented to either sup-port or refute the contention.
In part vagueness is caused by the use of highly abstract words (such as the contention that " adequate" " medical services" are not provided for).
3.
No basis -- there is no reason to believe that the contention is true, no " reason-able explanation or plausible authority."
In particular, some of the new onsite contentions fail to specify evaluation criteria of NUREG-0654 that are not al-legedly met.
Since what the County is
[(
alleging to raise are offsite elements of the applicant's plan, it must specify a NUREG-0654 criterion, and one with an "X" in the " Licensee" column of the criteri-on.
4.
Phase I issue -- these contentions could have been raised in Phase I.
5.
County's own doing -- this is a shorthand for those contentions that amount simply to the proposition that the County re-i fuses to give its consent.
The basis for this objection is the Board's April 20 order, which indicated that the County must litigate the feasibility of offsite emergency planning and not artificial ob-stacles like the County's own refusal to cooperate.
6.
Repetitive --
Repeats the substance of another new onsite contention.
7.
Already settled --
The onsite security issue was resolved by a settlement agree-ment and is not now litigable.
l
. C.
The contentions
,The contentions below have been rewritten by paring away excess words, but the words that remain are almost entire-ly the County's own.
The numbering scheme too is the County's.
Regulatory requirements and guidelines that are allegedly not met are in parentheses at the end of the contentions.
In some cases the new onsite contentions refer to certain of the Coun-ty's offsite contentions in the draft of June 23, 1982.
In the objections below we have changed those references to conform to the more recent draft of July 7, 1983.
A.1 Authority to make decisions.
LILCO does not have the authority under New York State law to make and imple-ment decisions about public health and safety during a radiological emergency.
(10 C.F.R. 5 50.47(b)(5); 10
{g C.F.R. Part 50 Appendix E $ IV.D.3; NUREG-0654 II.E.6.)
k LILCO's Objections:
1.
Not a low-power issue.
Issues about offsite decisionmaking are not about an "offsite element of the appli-cant's emergency plan" within the l
meaning of 47 Fed. Reg. 30,234 (July 13, 1982).
The fact that the onsite plan states that offsite organiza-tions will notify the public does not l
make such notification an element of the onsite plan for low-power purpos-es.
Likewise, the fact that NUREG-0654 II.E.6 says it is the ap-l plicant's responsibility to demon-f strate that means of notification exist does not mean that such means are elements of the applicant's onsite plan.
Obviously the conten-tion calls for a " finding con-cerning the state of offsite emer-l gency preparedness."
See 10 C.F.R.
I S 50.47(d) (1983).
i 1
- C 2.
Not specific.
Does not specify what state law, if any, is violated.3/
The term " implement decisions" is i
vague and does not specify any act that is prohibited by law (see the
" Repetitive" objection below).
3.
County's own doing.
The issue is created entirely by the County's re-fusal to cooperate.
4.
Repetitive.
People can make any kind of " decision" they want without violating the law; only if they take some action, and a law says they may not, do they run afoul of the law.
The County really means that LILCO lacks legal authority, not to "make decisions," but to " implement" deci-sions by doing such things as activating the sirens and advising people to leave their homes.
These functions are covered by c;ontentions A.2 and A.3, and so A.1 is repeti-tive.
(
A.2 Authority to activate sirens.
LILCO does not have the legal authority to activate the Prompt Notification System sirens.
LILCO's Objections:
1.
Not a low-power issue.
It would be hard to think of a more purely "offsite" issue than siren activation.
NUREG-0654 II.E.6 recog-nizes the sirens as an offsite plan matter, for it says that State and local governments are responsible for activating them.
In Diablo Canyon, which predated the low-power emergen-cy planning regulation 5 50.47(d),
the Board authorized a 5% power li-cense even though the sirens had not yet been installed.
Pacific Gas &
Electric Co. (Diablo Canyon Nuclear 3/
The reference to the FEMA findings does not help, because FEMA's own term "necessary police powers" is too vague to make
(
an admissible contention.
(
Plant,- Units 1 and 2), LBP-81-21, 14 NRC 107, 131 (July 17, 1981), made effective with respect to Unit 1, i
CLI-81-22, 14 NRC 598 (Sept. 21, 1981).
Obviously this contention calls for a " finding.
concerning the state of offsite emergency pre-paredness."
2.
Not specific.
Does not specify any law that prohibits LILCO from activating the sirens.
(However, offsite contention SC 1.F suggests that the County would cite N.Y. Penal Law 55 190.25(3), 195.05 (McKinney) to correct this deficiency.)
3.
No basis.
Generally speaking, people in this country can do what they wish unless a law prohib ' ;s it.
LILCO paid for and installed the sirens, and without more specificity (see above), there is no reason to believe there is any legal reason why LILCO may not sound the sirens in an emer-gency.
4.
County's own doing.
Since the County could give LILCO permission to acti-vate the sirens, this contention is merely another way of saying the County refuses to cooperate.
If Suffolk County were still not cooperating in emergency planning when an accident occurred, LILCO would request the County's permission to activate the sirens, and it is in-conceivable that the County would re-fuse.
So the contention is a sham issue.
A.3 Authority to use EBS.
LILCO lacks authority to acti-vate the emergency broadcast system (EBS).
LILCO's Objections 1.
Not a low-power issue.
Activating l
the radio warning system to alert the l
public is not an element of the ap-plicant's (onsite) plan within the meaning of 47 Fed. Reg. 30,234 col. 1 (July 13, 1982).
r l
4 C 2.
Not specific.
Does not specify any law that prohibits LILCO from using the EBS. (Judging from offsite con-tention SC 1.F, the County would cite N.Y. Penal Law $$ 190.25(3), 195.05 (McKinney) to correct this deficiency in the contention.)
Does not specify any criterion of NUREG-0654, Planning Standard E, that is not met.
3.
No basis.
No reason to believe that lack of authority would hinder emer-gency response in a real emergency.
4.
County's own doing.
A.4.a Too slow notification from Customer Service Office.
Due to the " limitations of the LILCO Customer Service Office resources" (offsite contention SC 78) and the
" inadequacies of the LILCO paging system" (offsite con-tention SC 80), the Director of Local Response can not be notified and the EOC activated in a timely manner.
The time needed to notify and mobilize the LERO person-(
nel necessary to make the decision to activate the si-rens will prohibit [ sic] their timely activation.
According to offsite contention SC 78, the limitations on the Customer Service Office at Hicksville are Too few staff (two operators on midnight shift, no back-up for on-duty dis-patcher (s))
Inadequate training Inadequate equipment to permit timely notification Accordi'4 s offsite contention SC 80, the inadequacies l
of tF9 SIL'O paging system are
- c g.<>Jtes over too short a distance t
(
Batteries must be charged or replaced and tested periodically 1
People with pagers may be ill or away on travel m
i I
t
.. C The pagers are activated by commercial telephones (refer to offsite contention SC 79) i No means exist for determining whether the paged notification is received LILCO's Objections:
1.
Not a low-power issue.
The conten-tion says that once the offsite con-l tact point (the Hicksville Customer Service Office) is contacted it will not in turn be able to contact all the offsite personnel who will be needed fast enough.
But the "offsite element" reviewed for low-power pur-poses is communication to the first line of offsite authorities.
This contention, on the other hand, is an issue about mobilizing emergency per-sonnel after the initial communica-tion from the plant.
It is thus not one of the "offsite elements of the applicant's plan" referred to at 47
(
Fed. Reg. 30,234 col. 1 (July 13, 1982).
(Note that Evaluation Criteria 3 and 4 of Planning Standard E in NUREG-0654 speak of messages "from the plant" and "from the facil-l ity.")
Part of the rationale for limiting the low-power findings to the onsite plan is that there is a j
long time to put together an offsite response if necessary, so a conten-l tion that all the offsite personnel I
cannot be mobilized quickly enough rather clearly falls outside the low-power issues.
2.
No basis for the.part about notifying the Director.
No reasvu to believe that the Director cannot be notified or in a timely manner.
There is sim-ply no reason to believe that it would take longer for LILCO to reach the designated LILCO Director, over whom LILCO has some control, than to notify Suffolk County personnel, over whom LILCO has no control.
That is, I
the County claims that this conten-tion is justified by the fact that
O
- (
the County is no longer participating in emergency planning.
But whatever could be done to notify the County could also be done to mobilize the LERO Director.
A.4.b Backup for sirens.
If the sirens fail, LERO/LILCO per-sonnel will be unable to provide backup notification in a timely manner.
LILCO's Objections:
1.
Not a low-power issue.
Means of no-tifying the public in case the sirens fail is clearly not an element of the applicant's plan.
2.
Not specific.
What is "a timely man-ner" for backup notification?
What type of backup notification would the County think adequate?
3.
No basis.
No reason to believe that backup notification could not be pro-vided in a timely manner.
4.
Phase I contention.
The County raised the issue of backup power to the sirens in Phase I.
See Phase I Contention 2.B (Aug. 20, 1982),
renumbered EP 1.B by the Board in the October 4, 1982 Appendix to the September 7, 1982 Supplemental Prehearing Conference Order.
A.4.c Sirens ineffective for transients and hearing impaired.
The notification system does not provide adequate noti-fication of an emergency to transients moving from out-side to inside the EPZ or to people with impaired hear-ing.
I LILCO's Objections:
1.
Not a low-power issue.
Whether the sirens are adequate for the hearing-impaired and for transients is not an element of the applicant's plan.
Notifying the hearing-impaired was an issue put into Phase II by the Board.
Prehearing Conference Order of July 27, 1982, at 8; see Tr. 7304.
Obviously the contention calls for a
. C
" finding
. concerning the state of offsite emergency preparedness."
See 10 C.F.R. $ 50.47(d) (1983).
2.
Not specific.
What does the County think would provide adequate notifi-cation?
The contention refers to an offsite contention, but that only confuses matters.4/ A different offsite contention (4.C-4(d)) in the June 23 draft questions LILCO's plan for registering the handicapped, but it is not cross-referenced in A.4.c.
Absent a specific complaint about the registration plan, a contention that hearing-impaired people cannot hear sirens is immaterial.
3.
No basis for the part about tran-sients.
No reason to believe that transients would not hear the sirens (though the contention may mean that transients will hear but not under-stand).
(
A.4.d Coast Guard.
There is no assurance that the Coast Guard will receive timely notification of an emergency since LILCO relies on commercial telephone for such communications; moreover, the mobilization time required by the Coast Guard will prevent their timely notification of the public.
LILCO's Objections:
1.
Not a low-power issue.
The 4/
This is an example of a case where the multiple cross-references make the contentions almost impossible to deal with.
The onsite contention A.4.c refers to offsite contention 9.C.1 i
in the June 23 draft but really means 8.C.1.
It is difficult to trace 8.C.1 from the June 23 draft into the July 7 draft, though the first pmrt of it has become SC 92.
(SC 92 in turn references deficiencies noted in SC 78-82.)
Finding the rest of the old 8.C.1 is difficult; SC 93 refers to persons with impaired hearing and people outside the EPZ, but it addresses radio broadcasts, not sirens.
SOC 4 addresses alternate means of notifying the hearing-impaired.
Given all this, it is impossible to know what point the County is trying to make in new onsite contention A.4.c.
l l
t
.=
1 l
. C mobilization time of the Coast Guard is clearly not an element of the ap-plicant's plan.
Obviously the con-
,i tention calls for a finding concern-ing the state of offsite emergency preparedness.
2.
Not specific.
What mobilization time does the County think would be ade-quate?
(Judging from SC 96.B, the County would say less than 15 minutes.)
3.
No basis for the mobilization time part.
4.
Phase I issue.
The part about LILCO's communications with the Coast Guard has not been changed by the County's nonparticipation.
Phase I contention EP 15 (renumbered 11),
sponsored by NSC but supported by SOC and Suffolk County, raised numerous issues about " communication with off-site national, state, and local re-(
sponse organizations."
Contention EP 15.D (Aug. 20, 1982), renumbered EP 11.C in the Board's October 4, 1982 Appendix B, specifically chal-lenged commercial telephones as the primary communications link to the Coast Guard.
Also, Suffolk County signed a settlement agreement resolving Phase I issue EP 3 (ff. Tr.
14,719) by which LILCO agreed to add to its plan a paragraph about calling i
the Coast Guard.
Among other things, the paragraph says this:
Assistance (from the Coast Guard) is available twenty-four (24) hours a day by calling the con-i tact phone number listed in the Emergency Plan Im-plementing Procedures.
It is anticipated that the U.S.
Coast Guard's maximum response time will be four (4) hours.
(t l
<. C Finally, Phase I issue EP 3 in the Board's October 4 Appendix B alleged LILCO's failure to incorporate Feder-i al response capabilities into the onsite emergency plan.
A.4.e LILCO's credibility.
LILCO will not be considered by the public to be a credible source of information and therefore notification or EBS information may be disre-garded.
LILCO's Objection:
1.
Not a low-power issue.
Whether the public will believe the sirens and radio warnings is not an element of the applicant's plan under 47 Fed.
Reg. 30,234 col. 1 (July 13, 1982).
The contention refers to communica-tions by the onsite response organi-zation to the public, not to elements of LILCO's onsite plan.5/
A.4.f Brochures not read.
The LILCO information brochures will not be read or understood by the public.
(
LILCO's Objections:
1.
Not a low-power issue.
The conten-tion calls for a finding on the state of offsite preparedness.
In the San Onofre case the adequacy of the pub-lic brochure was apparently not de-cided as a low-power issue.
Cf. 15 NRC 61 with 15 NRC 1163, 1204.
2.
No basis.
What reason is there to believe that the brochures will not be read or understood by the public?
B.
No County facilities or personnel.
Suffolk County will not permit LILCO to communicate through the Suffolk County emergency operations center in Yaphank and will not allow the County Department of Emergency Prepared-ness to implement the procedures of the various local agencies.
(10 C.F.R. S 50.47(b)(5) and (6).)
5/
The issue of whether Long Island residents would obey in-structions was raised by the County in Phase I contention EP 1.1(v) (Aug. 20, 1982).
The contention was not admitted, the Board deeming it more appropriate for Phase I.T if anywhere.
e
. LILCO's Objections:
1.
Not a low-power issue.
The communi-cations link to the County is the same as it has always been.
If the County's contention is that it will not pick up the receiver, then it is not an onsite plan issue as contem-plated by 47 Fed. Reg. 30,234 col. 1 (July 13, 1982).
The contention does not question the communications from the plant to the first-line authori-ties, only those authorities' will-ingness to help.
A finding on the state of offsite preparedness is called for.
2.
Phase I issue.
The dedicated phone system to the County's Yaphank center is the same as the one to the Hicksville LILCO office.
If the County thought this system inade-quate, it should have litigated it in Phase I.
[
2.
County's own doing.
This is simply
(,
the contention that the County will not cooperate.
The contention ig-nores the LILCO Transition Plan, which substitutes LILCO personnel and facilities for those of Suffolk Coun-ty.
If the County resources mentioned in the contention were needed, LILCO would ask the County to use them, and it is inconceivable that the County would refuse if there were a real radiological emergency.
C.
Training.
Suffolk County Police Department personnel expected by LILCO to respond onsite to a security inci-dent have not received radiological emergency response training.
($ 50.47(b)(15); NUREG-0654 SS II.O.l.b, II.O.3.d [ sics /])
LILCO's Objections:
1.
Not a low-power issue.
The first s/
The County cites 3.d but may mean 4.d of Planning Standard O.
. (
NUREG-0654 criterion cited by the County, II.1.b (apparently this re-fers to section 1.b of Planning Stan-i dard O), does not have an "X" in the
" Licensee" column.
The training of police is obviously a matter for a finding on the state of offsite pre-paredness.
2.
Phase I issue.
The training of po-lice expected to respond onsite, as the new onsite contention puts it, was ripe for adjudication in Phase I.
(By comparison, the County both put forth contentions and submitted tes-timony about traffic conditions mak-ing it difficult for emergency per-sonnel to respond to the site.
See Direct Testimony of Andrew C.
Kanen (Oct. 12, 1982); see also Suffolk County's Response to LILCO's Motion for Summary Disposition of EPs 2B, 5B and 7B (Nov. 19, 1982).
LILCO's written testimony and its Motion for Summary Disposition of November 9,
(
1982, addressed police reporting to the site, even though Suffolk County chose to concentrate on fire trucks and ambulances.
The settlement agreement for Phase I issue EP 6 (ff. Tr. 14,719),
signed by the County, addressed training of offsite agencies, namely fire and ambulance personnel.
3.
County's own doing.
This is simply the contention that the County will not cooperate.
LILCO is ready to provide any necessary training to the police, and if police lack training, it is because the County wants them to lack training.
4.
Already settled.
Training of police in radiological emergency response is a matter covered by the security set-tlement agreement.
Further, contrary l
to the contention, police department personnel have already undergone radiological emergency response training.
l l
l
1
- C D.
Emergency Operations Center.
Suffolk County will not allow the Suffolk County Probation Building in Yaphank to be used as the Emergency Operations Center; LILCO's Alternate EOC in Brentwood has not yet been established.
In the absence of an operational EOC,
'ILCO is unable to:
Notify local response organizations and emergency personnel.
2.
Notify and instruct the populace.
3.
Communicate among principal response organizations to emergency personnel to the public.
4.
Disseminate coordinated information to the public.
($ 50.47(a)(8); see NUREG-0654 II.H.3.)
LILCO's Objections:
1.
Not a low-power issue.
The relevant evacuation criterion in NUREG-0654, II.H.3, has no "X"
in the " Licensee" column.
Therefore this contention does not involve an "offsite element of the applicant's emergency plan" within the meaning of 47 Fed. Reg.
30,234 col. 1 (July 13, 1982).
Obvi-ously a finding on the state of offsite preparedness is being called for.
2.
No basis.
No specific shortcoming in the Brentwood EOC is stated.
That I
the substitute LILCO EOC at Brentwood is not now operational is immaterial, so long as it is operational by the time it may be needed.
An analogous Phase I contention asserting that LILCO's Technical Sup-port Center would not be completed by fuel load (EP 24) was ruled inadmis-sible for lack of basis.
Supplemen-tal Prehearing Conference Order (Phase I - Emergency Planning) 63-64 l
(Sept.
7, 1982).
3.
County's own doing.
The first part of the contention is merely the as-(
sertion that the County will not allow its facility to be used as the g
EOC.
l l
.. (
E.
Communications.
Suffolk County will not allow LILCO to use the communications systems of the Suffolk County Police Department, the Department of Fire Safety, and ithe Department of Emergency Preparedness.
LILCO's al-ternative communication system is inadequate because
($ 50.47(b)(6)):
LILCO's Objections:
1.
Not a low-power issue.
2.
County's own doing.
E.1.
Customer Service Office.
The LILCO Customer Service Office does not have adequate resources to notify nec-essary personnel in a timely manner.
LILCO's Objections:
1.
Repetitive.
As a general matter, contention E appears to be repetitive of B and D.
New onsite contention A.4.a covers the " limitations" of the LILCO Customer Service Office "re-sources."
If the " inadequate" "re-(
sources" cited in E.1 are different from the " limitations" in " resources" cited in A.4.a, the difference is not r
apparent; both A.4.a and E.1 cross-reference offsite contention SC 78.
2.
Same objection as to A.4.a:
Not a low-power issue.
E.2.
LILCO communications system.
The LILCO communications system does not assure prompt notification of key LILCO/LERO personnel.
LILCO's Objections:
1.
Repetitive.
Appears to refer to the same alleged inadequacies of the paging system as A.4.a; both A.4.a and E.2 refer to offsite contention SC 80.
2.
Same objection as to A.4.a:
Not a low-power issue, t
-4.-
,.e.
m-,
.r
.-my. _ _, _, -, _... - _ -,. -. -
.---w,
-,,--.--_..-,..._,,r,
e
. j(F E.3.
Commercial phone lines.
Notification of emergency per-sonnel by a commercial nondedicated phone line will not be feasible during an emergency.
LILCO's Objections:
1.
Not a low-power issue.
As the refer-ence to offsite contention SC 81 makes clear, this contention addresses communications to emergency personnel after the initial offsite communication has been made.
It ob-viotysly calls for a finding on the state of offsite preparedness.
2.
Phase I issue.
The inadequacies of commercial phone lines in an emer-gency were raised during Phase I.
Indeed, the Board admitted EP 15.A and 15.D (renumbered 11.A and 11.C),
which dealt with alleged inadequacies of commercial phones.
Order of Sept.
7, 1982 at 49, 50.
A settlement agreement for Phase I J(g-issue EP 11(E) (ff. Tr. 14,719) addresses the contention that person-nel alerted by pagers would not be able to call in because commercial phone linas would be overloaded.
The agreement was that these personnel would be trained to report to their emergency posts if they found the phone lines overloaded.
E.4.
Training and number of communicators and communications repairmen.
There is no assurance that personnel will be adequately trained or that there will be nn adequate number of communicators and repair technicians to en-able the proposed communications system to operate.
LILCO's Objections:
1.
Not a low-power issue.
Judging from the cross-reference to offsite con-tentions SC 84 and SC 85, this con-tention appears to say that offsite l
communications, following initial notification from the plant, will be inadequate.
The contention thus does l
[
not address elements of the appli-l
(
cant's plan as contemplated by 47 l
s.
l
.. C Fed. Reg. 30,234 col. 1 (July 13, 1982), but rather calls for a finding on the state of offsite preparedness.
2.
Phase I issue.
Most issues about LILCO communications and repairmen could have been raised in Phase I.
For example, a settlement agreement for Phase I issue EP 12(A) (ff. Tr.
14,719) agreed to provide seven com-municators in the Emergency Operations Facility instead of only three.
E.5.
Back-up frequencies and compatibility of LILCO's radio system.
There are no backup frequencies for LILCO's Emergency Radio System; moreover, LILCO's Emergency Radio System will not be compatible with the radio com-munications equipment used by hospitals and ambulance, fire and rescue vehicles, also relied upon by LILCO for assistance in an emergency.
LILCO's Objections:
1.
Not a low-power issue.
If the con-C tention refers to communications from offsite facilities to hospitals etc.,
it is not an element of the applicant's plan as contemplated by 47 Fed. Reg. 30,234 col. 1 (July 13, 1982), and it does call for a finding on the state of offsite preparedness.
2.
Phase I issue.
If the contention addresses communications from Shoreham to ambulances etc. re-sponding to the site, it clearly could have been raised during Phase I.
Of the Phase I contentions, EP 2.B and 5.B addressed whether am-
[
bulances and other emergency person-l nel would be able to make it through l
congested traffic.
LILCO's pleadings and testimony addressed radio commu-nications with ambulances.
See Tes-timony of Nicholas J. DiMascio.
l on.
EP2(B) at 8 (Oct. 12, 1982);
LILCO's Motion for Summary Disposi-tion of the Traffic Congestion Issues (Nov.
9, 1982).
Contention 15.G in the Phase I contentions of August 20, l
k 1982, which was not admitted for lack
. C of basis, addressed coverage and load capacity of UHF and VHF radio-based stations, and EP 15 (subsequently renumbered EP 11) covered other is-sues about communications with offsite organizations.
E.6.
Transfer points.
LILCO's proposal to relay command and control communications to field personnel through transfer points will not work.
LILCO's Objection:
1.
Not a low-power issue.
The conten-tion addresses communications between the offsite field personnel and the offsite EOC.
It thus clearly does not address an element of the appli-cant's plan as contemplated by 47 Fed. Reg. 30,234 col. 1 (July 13, 1982), and it does call for a finding on the state of offsite preparedness.
E.7.
Communications equipment for LILCO field personnel.
(
Many LILCO field personnel will not be equipped with necessary communications equipment.
LILCO's Objections:
1.
Not a low-power issue.
This conten-tion addresses communications between offsite " field personnel" and the offsite EOC.
It is not an element of the applicant's plan as contemplated by 47 Fed. Reg. 30,234 col. 1 (July 13, 1982).
2.
Not specific.
What "LILCO field per-sonnel"?
Are these different field personnel from the ones that would be in the field if the County were participating?
3.
Phase I issue.
If the " field person-nel" are the ones called for in the onsite plan, then this could have been litigated in Phase I.
For exam-ple, the County raised and settled a Phase I issue, EP 10.A, about the I
number of field monitoring teams.
l l
. C E (con-The absence of an EOC exacerbates the tinued) communications deficiencies.
LILCO's Objection:
1.
Repetitive.
This is redundant of contention D.
F.
Identification of offsite response organizations.
Suffolk County will not implement an offsite plan or agree to allow the basement of the Suffolk County Pro-bation Building to be used as the EOC; LILCO does not have the authority to perform many of the functions es-sential to an effective and implementable offsite re-sponse.
(S 50.47(b)(3)7/.)
LILCO's Objections:
1.
Not a low-power issue.
The conten-tion that the offsite organization lacks legal authority is not an "offsite element of the applicant's plan" as contemplated by 47 Fed. Reg.
30,234 col. 1 (July 13, 1982).
The contention calls for a finding on the C
state of offsite preparedness.
2.
County's_own doing.
The contention amounts to nothing more than the as-sertion that Suffolk County refuses to participate.
3.
Repetitive.
The contention has two parts.
The first part says that Suffolk County will not participate.
The second part says LILCO lacks au-I thority to substitute for Suffolk County.
The first of these parts is repetitive of new onsite contentions
^
B, D, E,
and F, plus several offsite contentions.
The second part about LILCO's authority is repetitive of new onsite contentions A.1 through A.3, B, D, and E, plus several offsite contentions.
Indeed, the 7/
The County also cites 10 C.F.R.
$ 50.47(b)(1), but this is not one of the "offsite elements" reviewed before a low-power license is issued.
See 47 Fed. Reg. 30,234 col. 1 (July 13, 1982).
NUREG-0654 II.A.1.a, b, and c, cited "see also" by the County, elaborate on 5 50.47(b)(1).
l
. C.
contention references all the other new onsite contentions (A through E).
4.
Not specific.
Probably because the contention is so repetitive, the County does not bother to specify what " essential functions" cannot be performed, unless one counts the ref-erence to all the other new onsite contentions.
Nor does the contention cite any NUREG-0654 Planning Standard C evaluation criterion that is alleg-edly not r et.
(\\b t
O LILCO, July 8, 1983
{f CERTIFICATE OF SERVICE
(
In the Matter of LONG ISLAND LIGHTING COMPANY (Shoreham Nuclear Power Station, Unit 1)
Docket No. 50-322 (OL)
I hereby certify that copies of LILCO's Answer Opposing the Suffolk County Motion for Leave to File Contentions Regarding Onsite Emergency Preparedness were served this date upon the following by first-class mail, postage prepaid, or (as indicated by one asterisk) by hand, or (as indicated by two as-terisks) by Federal Express.
James A.
Laurenson,*
Lawrence J.
Brenner, Esq.*
Chairman Administrative Judge gr Atomic Safety and Licensing Atomic Safety and Licensing j
Board Board
(,
U.S. Nuclear Regulatory U.S. Nuclear Regulatory Commission Commission East-West Tower, Room 402A Washington, D.C.
20555 4350 East-West Highway Bethesda, MD 20814 Dr. James L. Carpenter
- Administrative Judge Dr. Jerry R.
Kline*
Atomic Safety and Licensing Atomic Safety and Licensing Board Board U.S. Nuclear Regulatory U.S. Nuclear Regulatory Commission Commission Washington, D.C.
20555 East-West Tower, Room 427 4350 East-West Highway Dr. Peter A. Morris
- Bethesda, MD 20814 Administrative Judge Atomic Safety and Licensing l
Dr. M.
Stanley Livingston**
Board 1005 Calle Largo U.S. Nuclear Regulatory Sante Fe, New Mexico 87501 Commission Washington, D.C.
20555 I
e
, i(F Secretary of the Commission David J. Gilmartin, Esq.
U.S. Nuclear. Regulatory Attn:
Patricia A. Dempsey, Esq.
Commiasion County Attorney Washington, D.C.
20555 Suffolk County Department of Law Atomic Safety and Licensing Veterans Memorial Highway Appeal Board Panel Hauppauge, New York 11787 U.S. Nuclear Regulatory 4
Commission Herbert H. Brown, Esq.*
Washington, D.C.
20555 Lawrence Coe Lanpher, Esq.
Christopher McMurray, Esq.
Atomic Safety and Licensing Kirkpatrick, Lockhart, Hill, Board Panel Christopher & Phillips U.S. Nuclear Regulatory 8th Floor Commission 1900 M Street, N.W.
Washington, D.C.
20555 Washington, D.C.
20036 j
Bernard M. Bordenick, Esq.*
Mr. Marc W. Goldsmith David A. Repka, Esq.
Energy Research Group Edwin J. Reis, Esq.
4001 Totten Pond Road
(
U.S. Nuclear Regulatory Waltham, Massachusetts 02154 Commission j
7735 Old Georgetown Road MHB Technical Associates j
(to mailroom) 1723 Hamilton Avenue Bethesda, MD 20814 Suite K San Jose, California 95125 Daniel F. Brown, Esq.*
Atomic Safety and Licensing Mr. Jay Dunkleberger Board Panel New York State Energy Office U.S. Nuclear Regulatory Agency Building 2 Commission Empire State Plaza Washington, D.C.
20555 Albany, New York 12223
(
Eleanor L. Frucci, Esq.*
Stewart M. Glass, Esq.
Attorney Regional Counsel Atomic Safety and Licensing Federal Emergency Management Board Panel Agency U.S. Nuclear Regulatory 26 Federal Plaza, Room 1349
(
Commission New York, New York 10278 l
East-West Tower, North Towbr Stephen B. Latham, Esq.**
4350 East-West Highway 7'
Twomey, Latham & Shea Bethesda, MD 20814 33 West Second Street P.O.
Box 398 Riverhead, New York 11901 i
! (
\\
s.
. C Ralph Shapiro, Esq.**
Jonathan D.
Feinberg, Esq.
Oak Street New York State Wading River, New York 11792 Department of Public Service Three Empire State Plaza James B. Dougherty, Esq.*
Albany, New York 12223 3045 Porter Street Washington, D.C.
20008 Spence W. Perry, Esq.
Associate General Counsel Howard L. Blau Federal Emergency Management 217 Newbridge Road Agency Hicksville, New York 11801 500 C Street, S.W.
Room 840 Washington, D.C.
20472 97').
mes N. Christ. man Hunton & Williams P.O. Box 1535 707 East Main Street Richmond, Virginia 23212 DATED:
July 8, 1983
\\
s
_ _ _. _ _ _ _ _ _ _ _ _ _ _ _ _ _ _... _