Letter Sequence Acceptance Review |
|---|
|
|
MONTHYEARNMP2L2706, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2019-10-31031 October 2019 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b Project stage: Request ML19339E8542019-12-0505 December 2019 Supplemental Information Needed for Acceptance of Requested Licensing Action Adoption of Risk-Informed Completion Times Project stage: Acceptance Review NMP2L2718, Supplemental Information No.1 for Nine Mile Point Nuclear Station, Unit 2, to Adopt TSTF-505, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, Revision 22019-12-12012 December 2019 Supplemental Information No.1 for Nine Mile Point Nuclear Station, Unit 2, to Adopt TSTF-505, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, Revision 2 Project stage: Supplement ML20023B1622020-01-21021 January 2020 Acceptance of Requested Licensing Action Use of Risk-Informed Completion Times Project stage: Acceptance Review ML20037B6542020-02-0606 February 2020 Audit Plan Regarding License Amendment Request to Implement Risk-Informed Extended Completion Times 50-410 (L-2019-LLA-0234) Project stage: Other ML20094J1562020-04-22022 April 2020 Audit Plan Supplement in Support of Review of License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times Project stage: Other ML20213A9352020-07-30030 July 2020 Request for Additional Information Review of License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times Project stage: RAI NMP2L2739, Request for Additional Information for Nine Mile Point Nuclear Station, Unit 2, to Adopt TSTF-505, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, Revision 22020-08-28028 August 2020 Request for Additional Information for Nine Mile Point Nuclear Station, Unit 2, to Adopt TSTF-505, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, Revision 2 Project stage: Request ML20246G6362020-09-0202 September 2020 Request for Additonal Information to Support Review of License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times Project stage: Approval ML20273A2372020-09-28028 September 2020 Request for Additional Information Review of License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times Project stage: RAI ML20272A2802020-09-28028 September 2020 Withdrawal and Replacement of Request for Additional Information to Support Review of License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times Project stage: RAI ML20248H5192020-09-28028 September 2020 Changes to Draft Request for Additional Information Regarding Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times Project stage: Draft RAI NMP2L2745, Request for Additional Information for Nine Mile Point Nuclear Station, Unit 2, to Adopt TSTF-505, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, Revision 22020-10-0202 October 2020 Request for Additional Information for Nine Mile Point Nuclear Station, Unit 2, to Adopt TSTF-505, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, Revision 2 Project stage: Request NMP2L2746, Supplemental Information for Nine Mile Point Nuclear Station, Unit 2, to Adopt TSTF-505, Provide Risk- Informed Extended Completion Times - RITSTF Initiative 4b, Revision 22020-10-0202 October 2020 Supplemental Information for Nine Mile Point Nuclear Station, Unit 2, to Adopt TSTF-505, Provide Risk- Informed Extended Completion Times - RITSTF Initiative 4b, Revision 2 Project stage: Supplement NMP2L2749, Responses to Request for Additional Information Questions 17 and 26 for Nine Mile Point Nuclear Station, Unit 2, to Adopt TSTF-505, Provide Risk- Informed Extended Completion Times - RITSTF Initiative 4b, Rev. 22020-10-22022 October 2020 Responses to Request for Additional Information Questions 17 and 26 for Nine Mile Point Nuclear Station, Unit 2, to Adopt TSTF-505, Provide Risk- Informed Extended Completion Times - RITSTF Initiative 4b, Rev. 2 Project stage: Response to RAI ML20351A1642020-12-15015 December 2020 Request for Additional Information Review of License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times Project stage: RAI NMP2L2754, Responses to Request for Additional Information Questions 27 and 28 to Adopt TSTF-505, Provide Risk- Informed Extended Completion Times - RITSTF Initiative 4b, Revision 22021-01-0707 January 2021 Responses to Request for Additional Information Questions 27 and 28 to Adopt TSTF-505, Provide Risk- Informed Extended Completion Times - RITSTF Initiative 4b, Revision 2 Project stage: Response to RAI ML21082A2212021-04-29029 April 2021 Issuance of Amendment No. 186, Adoption of TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4B Project stage: Approval 2020-02-06
[Table View] |
Text
From:
Marshall, Michael To:
[Licensee] Ron Reynolds (Exelon)
Cc:
James Danna (James.Danna@nrc.gov)
Subject:
Nine Mile Point Nuclear Station, Unit 2 - Acceptance of Requested Licensing Action Re: Use of Rick-Informed Completion Times (EPID: L-2019-LLA-0234)
Date:
Tuesday, January 21, 2020 9:01:00 AM Hello Ron, By letter dated October 31, 2019 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML19304B653), as supplemented by letter dated December 12, 2019 (ADAMS Accession No. ML19346F427), Exelon Generation Company, LLC submitted a license amendment request for the Nine Mile Point Nuclear Station, Unit 2 (Nine Mile Point 2). The proposed amendment would allow the use of risk-informed completion times in the Nine Mile Point 2 Technical Specifications. The proposed changes are based on Technical Specification Task Force Traveler 505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b (ADAMS Accession No. ML18183A493).
The purpose of this email is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review, as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified, despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.
Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 2100 hours0.0243 days <br />0.583 hours <br />0.00347 weeks <br />7.9905e-4 months <br /> to complete. The NRC staff expects to complete this review by the end of April 2021. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.
These estimates are based on the NRC staffs initial review of the application, and they could change due to several factors, including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities. Additional delay may occur if the submittal is provided to the NRC in advance, or in parallel with, industry program initiatives or pilot applications.
If you have any questions, please contact me at (301) 415-2871 or Michael.Marshall@nrc.gov.
Sincerely, Michael L. Marshall, Jr., Senior Project Manager Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-410