ML20005E895

From kanterella
Jump to navigation Jump to search
Sser Granting one-time Partial Relief from post-maint Test of ASME Code,Section XI,IWV-3200 for Eight Recently Repaired Safety Injection Check Valves as Result of Sys Mods to RHR & Containment Bldg Spray Sys
ML20005E895
Person / Time
Site: Seabrook  NextEra Energy icon.png
Issue date: 01/03/1990
From:
NRC
To:
Shared Package
ML20005E891 List:
References
NUDOCS 9001120040
Download: ML20005E895 (2)


Text

ff

\\

p o;

EHCLOSURE SAFETY EVALVATION REPORT SUPPLEMENT SEABROOK NUCLEAR STATION, UNITS 1 AND 2 DOCKET NOS. 50-443 AND 50-444 i

A.

INTRODUCTION r

By letter dated October 30, 1989, the applicant submitted proposed changes to'the Seabrook inservice testing (IST) program incic< ting a one-time relief request for eight recently repaired safety injection (SI) system check valves. The original IST program was reviewed and approved by the staff in the Seabrook SSER No. 6 dated October 1986.

B.

DISCUSSION 1

The proposed IST program changes and associated additions 1 relief requests are primarily a result of system modifications to the Residual Heat Removal (RHR) and Containment Building Spray (CBS) systems. The staff finds that the RHR/CBS systems modifications, corresponding IST program changes, and associated additional relief reauests are made in accordance with previous staff review results, and therefore are acceptable.

A one-time relief request which was also included in the applicant's October 30, 1989, letter addresses the post-maintenance requirements of ASME Section XI, IWV-3200, for eight recently repaired SI check valves. However, a post-maintenance full stroke test of these valves requires that the reactor vessel head be removed. Since removing the reactor vessel head to perform the test is impractical in its current operation mode, the applicant proposed to postpone the required test

-to the first refueling outage. The staff finds that relief as requested originally from the post-maintenance test of all eight SI check valves cannot be granted since a meaningful partial. flow test can be performed. On the basis of the staff finding, the licensee modified the one-time relief request and proposed by letter dated December. 27, 1989, a partial flow stroke test utilizing an RHR pump and temporary flow paths connected to the SI system.

A review of the proposed partial flow test method and the test set-up indicates that each of.the eight SI check valves will be tested and flow through each valve quantified. The flow resistance of the normal SI flow paths is many times lower than tne flow resistance of the proposed test loop while the SI pump head is many times higher than that of the RHR pumps. Accordingly, in view of the high flow resistance of the test loop and the low RHR pump head, performance of the proposed partial flow through each check valve should provide adequate assurance that the check valves will lift to e position that significantly high flow through the SI system would be delivued by the SI pumps.

9001120040 900103 PDR ADOCK 05000443 P

PDC

y r

(

kJ

?

2 C.

CONCLUSION.

Based on the partial flow test discussed above, the acceptable results from last disassembly and inspection, the acceptable results of the radiography-after reassembly, the lack of reported industry experience of similar check valves not opening when required, the applicant's commitment to perform a full flow stroke test of_these valves during the first scheduled refueling outage but in no case later than June of 1992, and the impracticality of performing the required test.during the' current mode of operation, the staff finds in accordance with 10CFR50.55a(g)(6)(1), that the one-time partial relief from the post-maintenance test of the ASME Code Section XI, lWV-3200, as requested by the applicant's December 27, 1989, letter authorized by law and will not endanger life or property or the common-defense and security and is otherwise in the public interest giving due consideration to the burden upon the licensee that could result if the requirements-of the IST program for these eight check valves were imposed on the facility. Accordingly, the applicant's request of October 30, 1989, as modified by its letter of December 27, 1989, is acceptable and therefore granted.

-- -