1 t
oy
\\
. N Hampshire
,,,,, dent and senior Vece Presi i
CW Operating C$icer NYN.89123 Octob,;r 17, 1989 i
United States Nuclear Regulatory Connaission Washington, D. C.
20555 Attention: Document Control Desk 1
References #
(a) Facility Operating License NPF-67, Docket No. 50 443
)
(b) NUREG-0896, supplement No. 8, ' Safety Evaluation Report Related to the Operation of Seabrook Station Units 1 and l
2', May 1989 l
Subject:
Completion of Plant Hodifications As'sociated with SSER 8 l
Confirmatory Issues $56, 58, 60 l
Gentlemen:
Salaty Evaluation Report, Supplement No. 8 (SSER 8) for Seabrook j
Station, Reference (b), reflected New Hampshire Yankee's (NHY) commitment to coaplete pirot modifications associated with certain Confirmatory Issues by September 30, 1989.
S The plant modifications associated with the following SSER 8 Confirmatory Issues have been installed and tested.
Confirmatory Issue $56 Radiation Data Management System (7.5.2.2) i
Reference:
NHY Design Coordination Report 87-317 Confirmatory Issue $58 Control Room habitability (6.4)
Reference:
NHY Design Coordination Report 86-709 i
Confirmatory Issue $60 Sampling and Analysis of Eff1 tents (11.5) c.,
Reference.: NHY Design Coordination Report 88-60 NOTE:
Mr. Jay Lee of the NRC, reviewed documentation I
associated with this design change on October 12, 1989. Mr.
i Lee requested additional information regarding sample line characteristics referenced in the report prepared for NHY by Science Applications International Corporation.
This information is expected to ba submitted by October 31, 1989.
1 8910250101 891017 PDR ADOCK 05000443 L
p FDC New Hampshire Yankee Division of Public Service Company of New Hampshire l
P.O. Box 300
- Seabrook, NH 03874
- Telephone (603) 474 9521
)g E
o.,,4
..,e United States Nucleat Regulatory Commission October 17, 1989 Attention: Document Coptrol Desk Page 2 Implementation documentation associated with the above plant modifications is available at Seabrook Station for NRC review. NHY requests that the completion of Confirmatcry Issues $56, 58 and 60 be reflected in the next SER supplement.
i.
Should you require additional information regarding these l
confirmatory issues, please contact Mr. John B. Eart at (603) 474-9521, extension 2762.
't Very truly yours, 1
fd C b
Ted C. Feigenbaum cci Mr. William 7. Russell Regional Administrator United States Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, PA 19406 Mr. Victor Neroes. Project Manager Project Directorate I-3 United States Nuclear Regulatory Commission Division of Reactor Projects Washington, DC 20555 Mr. Antone C. Corne NRC Senior Resident Inspector P.O. Box 1149 Seabrook,14H 03874 i