Extends Completion Date for Item 3.21 Re Safe Shutdown Analysis from 791001 to 1115
ML19254D071
Person / Time
Site: Pilgrim
Issue date: 10/16/1979
From: Andognini G
BOSTON EDISON CO.
To: Ippolito T
Office of Nuclear Reactor Regulation
References
NUDOCS 7910220319
Download: ML19254D071 (1)


Text

BOSTON EDISON Ch 0 M PANY GENERAL OFFICES SCO BOYLSTON STREET BOSTON MAEBACNUSETTs o2199 G. CamL ANDOGNW8 su E = TENoENT October 16, 1979 NWCLEAm OPERATIONg DEPARTMENT BECo Ltr. #79-203 Mr. Thomas A.

Ippolito, Chief Operating Reactor Branch #3 Division of Operacia3 Reactors Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.

20555 License No. DPR-35 Docket No. 50-293 Safe Shutdown Analysis for Nine Critical Areas

References:

(a) NRC Letter (T. A. Ippolito to Boston Edison Company (G. C. Andognini) dated December 21, 1978, titled,

" Amendment No. 35 to Facility Operating License No. DPR-35."

(b) BECo Letter (G. C. Andognini) to NRC (T. A. Ippolito) dated October 5,1979, titled "Information on Alter-nate Shutdown Capability per Fire Protection Amendment No. 35."

Dear Sir:

We wish to inform you that the completion date for Item 3.2.1, " Safe Shutdown Analysis" which was previously due on October 1, 1979, has slipped to November 15, 1979, as a result of our desire to complete all engineering activities associated with the initiation of fire protection measures for Item 3.1.6 (coating of PVC cable) and Item 3.1.14 (exposed steel).

In our engineering judgement, the importance of these items in effecting a safe shutdown of the plant warranted assigning a higher priority.

Consequently, Items 3.1.6 and 3.1.14 will be completed far in advance of the current completion dates of March 1, 1980, and July 1, 1980, respectively.

The safe shutdown analysis for the cable Spreading Room was submitted via Reference (b); the analyses for each of the other eight areas will be sub-mitted as soon as each is completed. We anticipate that all analyses will be submitted prior to the date stipulated above.

We trust this schedule revision meets with your approval.

If you have any questions, do not hesitate to call.

Very truly yours,

)

(4 7910220)/7

'